Professional Documents
Culture Documents
Andrew Charleson
First Edition, September 2011
ii
T ABLE OF CONTENTS
Preface................................................................................................................................... v
Acknowledgements ............................................................................................................... v
1. INTRODUCTION .......................................................................................... 1
1.1
1.2
1.3
1.4
1.5
Background .................................................................................................................. 1
Vulnerability of Earthen Houses .................................................................................. 3
Methods of Reinforcing Earthen Houses ..................................................................... 5
Applicability of Tire Strap Reinforcement ................................................................... 8
Longevity of Straps .................................................................................................... 10
Equipment.................................................................................................................. 11
Materials .................................................................................................................... 12
Foundations ............................................................................................................... 13
Walls .......................................................................................................................... 16
6. REFERENCES ........................................................................................... 39
APPENDIX A. SUMMARY OF THE TECHNICAL DEVELOPMENT OF TIRE STRAP
REINFORCEMENT .................................................................. 40
A.1.
A.2.
A.3.
A.4.
iii
Tires............................................................................................................................ 48
Straps ......................................................................................................................... 48
Cutting straps ............................................................................................................. 48
Finishing and storing straps ....................................................................................... 48
iv
Preface
The origins of this document are found in a concern for the poor in developing countries who often
build and inhabit unsafe houses. Earthen houses are notable for their lack of tensile resistance. There
is nothing strong enough to hold wall and roof elements together during a damaging earthquake. They
break apart and fall, causing loss of life and injury.
A search then began for waste material that could be transformed into ropes or straps with reasonable
tension strength. Any material other than waste would most likely be unaffordable. The break-through
occurred when following-up the conviction that useful strength might be obtained from used car tires.
How to avoid burying them in landfills but to recycling them to improve seismic safety? It was then
discovered that if tire treads are spirally cut, like the way orange skins can be peeled into continuous
lengths, usefully long and strong straps are obtained.
The implementation of this technology will require collaboration between the tire industry and NGOs
or government agencies who are concerned about the seismic vulnerability of earthen houses. The
vision is for the tire industry to produce straps from used tires rather than paying for them to be
disposed of, and donating and transporting them free of charge to organizations improving housing
safety in developing countries.
Andrew Charleson
Acknowledgements
Many people have contributed to this project. Matthew Frenchs research for his M. Arch degree
involved developing, testing and refining the technology, while for her Masters degree in
Developmental studies, Marcela Markland explored socio-economic and cultural challenges in the
context of Peru. The project was also a vehicle for two undergraduate studies by Matthew French and
Samuel Gwynn, who also completed the bulk of the diagrams. Nabil Allaf finished off the diagrams
and formatted the manual.
The technical assistance in the workshops at the School of Architecture, Victoria University of
Wellington and the Catholic University of Peru, Lima has been essential in developing the tire strap
reinforcement. Thanks to Marcial Blondet and his academic colleagues for their support in Lima, and
also Johanna Aranda for her dual role as a research assistant and Spanish translator for the adobe tests.
The project could not have been completed without a research grant from Victoria University of
Wellington. The grant covered all the costs associated with the testing program in Lima.
Finally, thanks to reviewers Dominik Lang and Marcial Blondet, and to Marjorie Greene and her
assistants working at EERI for the World Housing Encyclopedia who have applied all the necessary
finishing touches.
1. INTRODUCTION
1.1 Background
Before embarking upon the aims of this
construction guide, its content is summarized
visually in Figure 1. This diagram attempts to
convey how the various materials, especially
Figure 1.3 A length of strap cut from the tread of a steel belted radial tire showing the orientation of the belt wires.
Figure 1.4 Steps in the process of reinforcing an earthen (adobe) house with tire straps. Step (a) is performed in a workshop or factory and
(b) to (d) on site. (Courtesy Matthew French)
Figure 1.5 An elevation of a typical wall showing positions of expected cracks and strap placement that ensures at least one strap crosses
every potential crack.
Figure 1.6 Typical damage and collapse of earthen buildings (from IAEE 2004).
Table 1.1 Advantages and disadvantages of three earthen housing reinforcement systems.
Reinforcement System
Vertical canes and crushed
horizontal canes
Advantages
Low-cost, low-tech
reinforcement.
Prevents collapse.
Walls dont require
plastering.
Disadvantages
Summary
Geomesh is relatively
expensive so material costs
are high unless subsidized.
A substantial timber or RC
eaves beam is
recommended.
Difficult to apply to existing
construction. Every wall
surface would require replastering and the
connection between
foundation and geomesh has
yet to be developed.
10
Figure 2.1 Elevation and plan of a simple ratchet device and attachments used to lightly tension straps during installation.
11
2.2 Materials
The following materials are required for strap
installation:
12
Figure 3.3.1 Adobe blocks are placed to mark the locations of the straps.
13
Figure 3.3.2 Plan of a house with walls and rafters shown. Straps need to be positioned under rafters where ever possible, and then off-set
or staggered so they rise vertically up the wall and wrap over the rafters.
Figure 3.3 A plan view of a length of the foundation showing the position of off-set straps under a rafter and how they are set into the
width of the wall.
14
Figure 3.4 A sleeve is constructed from any (recycled) material provided the internal diameter is over 50 mm.
15
Figure 3.6 Adobe blocks protect the small excavations from filling up with debris and are slid back immediately prior to installing the strap
under the wall.
3.2 Walls
The preparation of walls prior to strap
installation involves forming vertical and
horizontal rebates in which the straps are to be
positioned and embedded (Figures 3.7 and
3.8). Vertical rebates are 25 mm deep, while
horizontal rebates need be only 15 mm deep
since they accommodate horizontal straps that
are placed after the vertical straps and are
therefore located closer to the exterior surfaces
of the walls.
16
17
Figure 3.8 (a) Section through new wall construction showing a strap passing under the foundation and the position of the vertical strap in
its rebate.
Figure 3.8 (b) Section through a wall showing a strap passing under the foundation of an existing wall.
18
Figure 3.9 Slot formers reduce the need to drill through walls at the corners of new construction.
Figure 3.10 Horizontal straps wrap around the corner of an internal wall. Note the deepened length of rebate to accommodate the nailed
joint of the strap. The position of the deepening should allow for easy strap tensioning of the joint, avoid clashing with a vertical strap
running at right angles and be on the inside face of a wall to reduce the risk of corrosion.
19
Figure 3.11 A typical vertical rebate on an inside wall surface with a deepened length for the strap joint.
Figure 3.12 Section through a vertical strap showing the two internal painted surfaces to protect the strap from moisture.
20
4. INSTALLATION OF STRAPS
4.1 Vertical Straps
At this stage of construction, rebates have been
completed and painted (if necessary) (Figure
4.1). After choosing a strap of suitable length
to minimize wastage, the first half of the
nailed joint should be completed (Figures 4.2
Figure 4.1 Plan sketch showing idealized locations of vertical rebates and straps. Off-sets (see Figure 3.3) allow for wrapping the straps
over the rafters.
21
Figure 4.2 Joint nailing at one end of a strap to be completed before tensioning the strap. For a high or long wall it may be necessary to
join two straps using this detail before tensioning.
Figure 4.4 A half completed joint showing the all-important bending of nails to prevent them pulling through under high tension forces.
This nail layout and bending pattern must always be implemented as shown.
22
Figure 4.5 A firm support and a steel plate assist the nailing and nail bending process.
23
Figure 4.7 A strap with a length of PVC sheet to provide water protection to the strap below ground level and up to the height where the
strap is protected by mud mortar and painted surfaces.
Figure 4.8 A vertical strap wraps over a rafter. Its location in a shallow notch prevents the rafter falling from the wall. In an existing house
an area of roofing needs to be removed to achieve this detail.
24
Figure 4.9 A strap wraps of the rafter and after tensioning is complete, is nailed to it.
Figure 4.10 A strap wrapping over a rafter. In this trial house the straps were not placed in wall rebates and the rafters were not notched.
25
Figure 4.11 Where straps do not meet rafters they should pass over a short wooden block and be nailed to it after tensioning.
Figure 4.12 After a screw is positioned near each end of the tire strap, the ratchet and chains are attached and tensioning begins. (Strap
and ratchet drawn in horizontal position).
26
Figure 4.13 Strap tension on both sides of the wall is equalized using a steel bar during the tensioning process.
Figure 4.14 The strap length might need reducing during tensioning to allow full tension to be achieved before the ends of the strap meet.
27
Figure 4.15 Successfully stressed strap awaiting final nailing and removal of tensioning equipment.
28
Figure 4.16 Vertical and horizontal straps have been installed. Note how horizontal straps wrap around walls and pass through walls at
right angles in order to form a continuous band.
Figure 4.17 Plan view of a layer of two horizontal straps at an exterior corner. Note that because horizontal straps are applied after the
vertical straps, their rebate is shallower (15 mm).
29
Figure 4.18 The upper strap is taut but requires shortening using a hacksaw before nailing the joint.
Figure 4.19 Strap is tensioned with the half pre-nailed joint hanging down. The right-hand end of the strap requires shortening.
30
Figure 4.20 Levering the strap at the end of a wall is necessary to achieve equal tension on each side of the wall.
31
Figure 4.21 After using a wooden backing block to drive a nail half-way through, a steel plate helps bend the nail down on the back of a
strap.
Figure 4.22 Two straps around an exterior corner. The upper edge of the top strap is aligned with the horizontal mortar joint. The
horizontal joint between the two straps is therefore approximately mid-height of an adobe block. Note that the hole for the lower strap is
deeper vertically than necessary.
32
Figure 4.23 At a T-junction outer straps pass through the U-straps from the return wall.
33
Figure 4.25 Section through the top of a parapet wall showing a U-strap wrapping around a vertical strap and nailed to a rafter. This detail
prevents the wall moving away from the rafter, causing it to fall.
34
Figure 4.26 A gable and a parapet wall. There is a wall behind the middle of the gable wall. If y is greater than 1000 mm, use two top
horizontal straps side by side along the return wall to tie it to the gable wall.
35
Figure 4.27 Corner horizontal straps are tied together with surface ties.
Figure 4.28 Corner horizontal straps are tied together on each side of the corner. Because the junction of the horizontal and vertical straps
is close to a return wall they are tied together, but not through the walls.
36
Figure 4.29 Horizontal hole and tie wire connecting two junctions of horizontal and vertical straps.
Figure 4.30 A strap junction tied together and through the wall tightly by a pair of tie wires.
37
Figure 4.31 Tying the top course(s) of adobe blocks to the top horizontal strap to prevent blocks being dislodged and falling during an
earthquake.
5. MAINTENANCE
Houses reinforced with tire straps are not
expected
to
require
any
additional
maintenance due to the presence of the straps.
However, maintenance is required wherever
damage to exterior plaster leads to strap
reinforcement being exposed to the elements.
As explained earlier, tire straps deteriorate if
exposed to sunlight or moisture. In a situation
38
6. REFERENCES
Blondet, M., Villa-Garcia, G. V. and Brzev, S., 2003. Earthquake-resistant construction of adobe
buildings: a tutorial, World Housing Encyclopedia, www.world-housing.net.
Charleson, A. and Blondet, M., 2012. Seismic reinforcement for adobe houses with straps from used
car tires, Earthquake Spectra (February 2012 publication date).
Charleson, A. W. and French, M. A., 2008. Used car tires as seismic reinforcement for adobe houses.
Proceedings of the 14th World Conference on Earthquake Engineering, October 12-17, Beijing,
China.
Charleson, A. W. and French, M. A., 2005. Improving seismic safety of adobe construction with used
car-tire straps: preliminary investigations, Proceedings of the Conference of the NZ Society for
Earthquake Engineering, 11-13 March, Paper 32.
Charleson, A. W., 2006. Low-cost tension resistance to improve seismic safety of adobe construction:
strips cut from used car tires, Proceedings of the 8th U.S. National Conference on Earthquake
Engineering, April 18-22, San Francisco. California.
Crocker, E., 2000. Earthen architecture and seismic codes: lessons from the field. Proceedings of the
International Conference on the seismic performance of traditional buildings, Istanbul, Turkey,
November 16-18.
EERI. 2007. The Pisco, Per, Earthquake of August 15, 2007. EERI Special Report.
Kuroiwa, J., 2004. Disaster reduction: living in harmony with nature. Quebecor World Peru, Lima.
Mayorca, P. and Meguro, K., 2008. A step towards the formulation of a simple method to design PPband mesh retrofitting for adobe/masonry houses. Proceedings of the 14th World Conference on
Earthquake Engineering, October 12-17, Beijing, China.
Ottazzi, G., Yep, J., Blondet, M., Villa-Garcia, G. and Ginocchio, J., 1989. Ensayos de simulation
sismica de viviendas de adobe, Publicacion DI-89-01, Pontifica Universidad Catolica del Per
Departamento de Ingenieria, Lima.
Taucer, F., Alarcon, J. and So, E., 2008. 2007 August 15 Magnitude 7.9 Earthquake near the Coast of
Central Per. Earthquake Field Investigation Team (EEFIT) Field Mission, 5-12 September 2007 /
Final Report, JRC Scientific and Technical Reports, European Commission (EUR 23359 EN 2008).
Tolles, E. L., Kimbro, E. E. and Ginell, W. S. 2002. Planning and engineering guidelines for the
seismic retrofitting of historic adobe structures. The Getty Conservation Institute, Los Angeles.
Turer, A., Korkmaz, S. Z. and Korkmaz, H. H., 2007. Performance improvement studies of masonry
houses using elastic post-tensioning straps. Earthquake Engineering and Structural Dynamics,
36:683-705.
Villa-Garcia, G. V. et al 2009. Basic report INF LE 302.08, Laboratorio de Estructuras PUCP,
Lima.
Villa-Garcia, G. V. 2009. Basic Report: adobe tests and results, December 2008, Civil Engineering
Laboratory, PUCP, Lima (Unpublished).
Vargas-Neumann, J., Torrealva, D., Blondet, M., 2007, Constructin de casas saludables y
sismorresistentes de adobe reforzado con geomallas. Fondo editorial PUCP, Lima.
39
41
Figure A.2 An out-of-plane test with the wall pushed towards the supports
Figure A.4 Walls 1 (left) and 2 at a similar stage of their cyclic loading sequence.
42
(Ottazzi et al 1989).
Figure A.5 The module being lowered onto the shaking table.
43
44
Figure A.6 Damage to the rear wall after the Phase 3 (maximum shaking) (left) and the most heavily damaged pier.
45
sliding
shear
and
diagonal
tension
displacements. The main unknowns for adobe
construction were whether sliding shear would
be as prominent, and what were the maximum
shear strength values.
46
Figure A.7 Horizontal load is applied to the top of a vertical steel post pin-jointed at its base which then transfers loads to the wall in
compression, via wooden blocks, and tension, via horizontal straps. The 1.2 m long wall (left) is being pulled to the left and is rocking at its
base while the 2.4 m long wall (right) has undergone five cycles of loading.
47
B.2. Straps
40 mm width 3 mm.
Ends of cut steel fibers to be visible along
each strap face. This means the outer edge
of the initial length of a usable strap is
approximately 20 mm from the edge of the
tire tread, where belt wires commence.
Tensile strength of strap to be greater or
equal to 10 kN (1 Tonne).
Quality control test one specimen from
each of three tires before starting mass
production of the straps and thereafter one
specimen per 100 tires. If any specimen
does not achieve the required strength
discard similar tires of that brand or source
unless further testing shows they meet the
required standard.
48
Material
Quantity
Cost
NZ$1
Cost
US$
Tire straps
90
Nails
1000
20
14
Screws
10
Plastic
adhesive tape
50 m
PVC sheet
7m2
14
10
Tie wire
100 m
Paint
5 liters
87
61
350
245
Mud mortar/
Miscellaneous:
60
40
542
378
Ratchets,
gloves, chains,
costs
of
making good
Total
Comments
49
Figure C.1 Plan of house at level of windows used to calculate quantities of materials.
50
Steps
Construction activities
Worker days
Mark the position of horizontal straps and vertical straps using chalk.
0.5
2.0
1.52
Remove areas of roof and ceiling to pass vertical straps over rafters.
1.51
Place, cut, tighten, connect vertical and horizontal straps (requires two
workers). Apply corrosion protection to vertical straps where they pass
under the foundations.
Drill 5 10 mm dia holes through walls, tie straps together and provide ties 1.5
to top course of adobe blocks.
Plaster over straps with mud mortar. After mortar is dry, paint over the 1.5
straps with water-resistant paint.
Miscellaneous
1.0
Total
20.5
51