You are on page 1of 15

33462 Federal Register / Vol. 72, No.

116 / Monday, June 18, 2007 / Notices

Persons unable to file electronically As a separate action, pursuant to section that the regional Reliability Standard is
should submit an original and 14 copies 215(d)(5) of the FPA, the Commission just, reasonable, not unduly
of the protest or intervention to the directs WECC to develop several discriminatory or preferential, and in
Federal Energy Regulatory Commission, specific modifications to the regional the public interest.10
888 First Street, NE., Washington, DC Reliability Standards when WECC 4. When the ERO submits a proposed
20426. develops, through its Reliability Reliability Standard to the Commission,
This filing is accessible on-line at Standards development process, the ERO must: (1) Describe the basis and
http://www.ferc.gov, using the permanent, replacement Reliability purpose of the Reliability Standard; (2)
‘‘eLibrary’’ link and is available for Standards. summarize the development and review
review in the Commission’s Public proceedings that led to the Reliability
Reference Room in Washington, DC. I. Background Standard; and (3) demonstrate that the
There is an ‘‘eSubscription’’ link on the A. EPAct 2005 and Mandatory Reliability Standard is just, reasonable,
Web site that enables subscribers to Reliability Standards not unduly discriminatory or
receive e-mail notification when a 2. In August 2005, the Electricity preferential, and in the public interest.11
document is added to a subscribed 5. In reviewing the ERO’s submission,
Modernization Act of 2005, which is
docket(s). For assistance with any FERC the Commission will give due weight to
Title XII, Subtitle A, of the Energy
Online service, please e-mail the ERO’s technical expertise, except
Policy Act of 2005 (EPAct 2005), was
FERCOnlineSupport@ferc.gov, or call concerning the effect of a proposed
enacted into law.2 EPAct 2005 adds a
(866) 208–3676 (toll free). For TTY, call Reliability Standard on competition.12
new section 215 to the FPA, which
(202) 502–8659. The Commission will also give due
requires a Commission-certified Electric
weight to the technical expertise of a
Kimberly D. Bose, Reliability Organization (ERO) to
Regional Entity organized on an
Secretary. develop mandatory and enforceable
Interconnection-wide basis with respect
[FR Doc. E7–11653 Filed 6–15–07; 8:45 am] Reliability Standards.3 Before a
to a proposed Reliability Standard to be
Reliability Standard may take effect, the
BILLING CODE 6717–01–P applicable within that
ERO must submit the standard to the
Interconnection.13 Moreover, the
Commission and obtain the
Commission may give ‘‘due deference’’
DEPARTMENT OF ENERGY Commission’s approval.4 Once
to the advice of a Regional Advisory
approved, the Reliability Standard can
Body that is organized on an
Federal Energy Regulatory be enforced by the ERO subject to
Interconnection-wide basis.14
Commission Commission oversight, or the
6. The Commission may approve a
Commission can independently enforce proposed Reliability Standard if the
[Docket No. RR07–11–000]
the Reliability Standard.5 Commission finds it is just, reasonable,
North American Electric Reliability 3. On February 3, 2006, the
not unduly discriminatory or
Corporation; Order Approving Commission issued Order No. 672,
preferential, and in the public interest.15
Regional Reliability Standards for the implementing section 215 of the FPA.6
In addition, the Commission explained
Western Interconnection and Directing Pursuant to Order No. 672, the
in Order No. 672 that ‘‘uniformity of
Modifications Commission certified one organization,
Reliability Standards should be the goal
NERC, as the ERO.7 Reliability
and the practice, the rule rather than the
Issued June 8, 2007. Standards that the ERO proposes to the exception.’’ 16 Yet, the Commission
Before Commissioners: Joseph T. Commission may include Reliability recognized that ‘‘the goal of greater
Kelliher, Chairman; Suedeen G. Kelly, Standards that are proposed to the ERO uniformity does not, however, mean
Marc Spitzer, Philip D. Moeller, and Jon by a Regional Entity.8 A Regional Entity that regional differences cannot exist.17
Wellinghoff. is an entity that has been approved by The Commission then provided the
1. On March 26, 2007, the North the Commission to enforce Reliability following guidance:
American Electric Reliability Standards under delegated authority
Corporation (NERC) submitted for from the ERO.9 When the ERO reviews As a general matter, we will accept the
approval eight proposed regional following two types of regional differences,
a regional Reliability Standard that provided they are otherwise just, reasonable,
Reliability Standards for the Western would be applicable on an not unduly discriminatory or preferential,
Electricity Coordinating Council Interconnnection-wide basis and that and in the public interest, as required by the
(WECC). The proposed regional has been proposed by a Regional Entity statute: (1) A regional difference that is more
Reliability Standards would apply in organized on an Interconnection-wide stringent than the continent-wide Reliability
the Western Interconnection in addition basis, the ERO must rebuttably presume Standard, including a regional difference that
to the 83 mandatory Reliability addresses matters that the continent-wide
Standards developed by NERC that will 2 Energy Policy Act of 2005, Pub. L. No. 109–58, Reliability Standard does not; and (2) a
take effect on a nationwide basis Title XII, Subtitle A, 119 Stat. 594, 941 (2005), to
be codified at 16 U.S.C. 824o. 10 16 U.S.C. 824o(d)(3); 18 CFR 39.5(b).
beginning in June 2007.1 The proposed 3 16 U.S.C. 824o(c)–(e). 11 18 CFR 39.5(a).
regional Reliability Standards would 4 16 U.S.C. 824o(d). 12 16 U.S.C. 824o(d)(2).
allow the continuation of certain 5 16 U.S.C. 824o(e)(3). 13 Id.
reliability practices that are currently in 6 Rules Concerning Certification of the Electric 14 16 U.S.C. 824o(j). A Regional Advisory Body is

effect in the Western Interconnection. Reliability Organization; Procedures for the an entity established upon petition to the
As discussed below, pursuant to section Establishment, Approval and Enforcement of Commission that is organized to advise the ERO, a
Electric Reliability Standards, Order No. 672, FERC Regional Entity or the Commission regarding
215(d)(2) of the Federal Power Act Stats. & Regs. ¶ 31,204 (2006), order on reh’g, Order certain matters including whether a Reliability
(FPA), the Commission approves the No. 672–A, FERC Stats. & Regs. ¶ 31,212 (2006). Standard proposed to apply within the region is
jlentini on PROD1PC65 with NOTICES

proposed regional Reliability Standards. 7 See North American Electric Reliability Corp., just, reasonable, not unduly discriminatory or
116 FERC ¶ 61,062 (ERO Certification Order), order preferential, and in the public interest. 18 CFR
1 See Mandatory Reliability Standards for the on reh’g and compliance, 117 FERC ¶ 61,126 39.13(c) (2006).
Bulk-Power System, Order No. 693, 118 FERC (2006). 15 16 U.S.C. 824o(d)(2).
8 16 U.S.C. 824o(e)(4). 16 Order No. 672 at P 290.
¶ 61,218 (March 16, 2007), 72 FR 16,416 (April 4,
2007), reh’g pending. 9 16 U.S.C. 824o(a)(7) and (e)(4). 17 Id. at 291.

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices 33463

regional Reliability Standard that is WECC–TOP–STD–007–0 (Operating replacement standards.25 WECC’s Board
necessitated by a physical difference in the Transfer Capability) of Directors approved the eight regional
Bulk-Power System.18 WECC–VAR–STD–002a–1 (Automatic Reliability Standards on January 5,
B. WECC Voltage Regulators) 2007.
WECC–VAR–STD–002b–1 (Power
7. WECC is responsible for overseeing System Stabilizers) 13. On December 22, 2006, in
transmission system reliability in the anticipation of approval by its board,
10. In its March 26, 2007 filing (NERC
Western Interconnection since 2002, WECC submitted the proposed regional
Filing), NERC states that the proposed
when WECC was formed from Reliability Standards to NERC. On
regional Reliability Standards are
predecessor reliability organizations. translations of existing reliability January 9, 2007, NERC responded with
The WECC region encompasses nearly criteria under WECC’s RMS program. detailed comments. According to NERC,
1.8 million square miles, including 14 According to NERC, WECC developed its primary concern was that the
western U.S. states, the Canadian most of the criteria in the late 1990s in sanctions in the proposed regional
provinces of Alberta and British response to a series of black-outs in the Reliability Standards were inconsistent
Columbia, and the northern portion of Western Interconnection.22 The with NERC Sanction Guidelines.26
Baja California in Mexico. WECC proposed regional Reliability Standards NERC’s January 9 report also identified
developed a Reliability Management would make eight of those RMS criteria NERC’s preferred nomenclature for
System (RMS) pursuant to which binding on the applicable subset of Reliability Standards, identified NERC’s
transmission operators in the Western users, owners and operators of the Bulk- preferred format for submission, and
Interconnection agreed by contract to be Power System in the United States identified language in the proposed
bound by the WECC reliability criteria portion of the Western Interconnection, regional Reliability Standards that
and sanctions for non-compliance. as identified in each proposed standard. NERC found ambiguous or incorrect.27
According to WECC, the criteria are The regional Reliability Standards By letter dated February 28, 2007,
recognized by all WECC members but would supplement rather than replace WECC responded by committing to
are contractually binding only on the Commission-approved Reliability address the shortcomings that NERC
members that signed an RMS Standards developed by the ERO that had identified when WECC develops
Agreement.19 will take effect in June 2007. permanent, replacement standards.28
8. In an April 19, 2007 order, the 11. In translating WECC’s existing 14. Also in response to WECC’s
Commission accepted delegation practices to proposed regional submission, NERC initiated a 45-day
agreements between NERC and each of Reliability Standards, WECC proceeded
eight Regional Entities.20 In the April 19 comment period. NERC received six sets
as follows.23 In 2006, a WECC task force
Order, the Commission accepted WECC of comments. NERC found that WECC
identified criteria in the RMS
as a Regional Entity organized on an had addressed the commenters’
Agreement that, in the task force’s view,
Interconnection-wide basis. In addition, concerns by committing to correct
should be binding on all users, owners
the Commission accepted WECC’s shortcomings in the proposed regional
and operators of the regional Bulk-
Standards Development Manual which Reliability Standards within one year of
Power System. The task force chose
sets forth WECC’s Reliability Standards Commission approval. NERC generally
eight of the identified criteria that have
development process.21 The the highest priority and that can be applied a rebuttable presumption that
Commission also directed WECC to implemented in the near term. WECC the proposed regional Reliability
make certain clarifications to its then used expedited procedures to Standards meet applicable
Standards Development Manual in a develop the eight regional Reliability requirements. However, because each of
filing to be submitted within 180 days Standards. WECC’s rules provide that, the proposed regional Reliability
of the order. when WECC develops a Reliability Standards contains a sanction table that
Standard under expedited procedures, is inconsistent with the NERC Sanction
C. The Eight Proposed Regional Guidelines, the NERC board concluded
Reliability Standards WECC must later develop a permanent,
replacement standard using more that the rebuttable presumption was
9. NERC has submitted for the extensive procedures. overcome with respect to this one
Commission’s approval the following 12. On October 5, 2006, using its component of the proposed standards.29
eight regional Reliability Standards that expedited procedures, WECC solicited Finally, NERC found that the proposed
were proposed to NERC by WECC to comment on whether the eight regional one-year term was inconsistent with the
apply in the Western Interconnection: Reliability Standards accurately reflect Commission’s prior invalidation of
WECC–BAL–STD–002–0 (Operating practices under the RMS Agreement. automatic expiration dates for
Reserves) Commenters raised concerns that Reliability Standards.30
WECC–IRO–STD–006–0 (Qualified Path sanctions under the eight regional 15. On February 8, 2007, the Western
Unscheduled Flow Relief) Reliability Standards are inconsistent Interconnection Regional Advisory
WECC–PRC–STD–001–1 (Certification with NERC Reliability Standards, do not Body (WIRAB) advised NERC that it
of Protective Relay Applications and provide clear guidance for measuring should approve the proposed regional
Settings) compliance, and might be applied in an Reliability Standards as necessary for
WECC–PRC–STD–003–1 (Protective anti-competitive manner.24 The task Reliable Operation of the Western
Relay and Remedial Action Scheme force responded that the regional Interconnection and as meeting the legal
Misoperation) Reliability Standards would remain in
WECC–PRC–STD–005–1 (Transmission effect for at most one year and that 25 Id., Ex. A at 1 and Ex. C, Attachment 2 at 8.
Maintenance) WECC would consider the commenters’ 26 Id. at 3–4. See also ERO Certification Order at
concerns when developing permanent,
jlentini on PROD1PC65 with NOTICES

P 299.
18 Id. 27 Id., Ex. C, Attachment 3.
19 See WECC April 17, 2007 Comments at 16. 22 NERC Filing at 5–6. 28 Id., Ex. C, Attachment 4.
20 North American Electric Reliability Corp., 119 23 See id., Ex. C (Record of Development, 29 NERC Filing at 9.

FERC ¶ 61,060 at P 432 (2007) (April 19 Order). Comments and Correspondence). 30 Id. at 2–4, 8–9 (citing North American Electric
21 Id. at PP 469–470. 24 Id., Ex. C, Attachment 1. Reliability Corp., 118 FERC 61,030 at P 30 (2007)).

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00019 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
33464 Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices

standard for approval set forth in 1. Comments in Support term limitation, noting that WECC
section 215 of the FPA.31 19. WECC states that the proposed approved the regional Reliability
16. On March 2007, NERC approved regional Reliability Standards, which Standards only as interim standards.
the proposed regional Reliability are exact translations of existing WIRAB suggests that it is unclear that
Standards on the conditions that WECC: regional criteria, either address matters NERC has authority to eliminate the
not addressed in the Commission- one-year term limitation. Finally,
(1) Remove the one-year term limitation;
approved ERO Reliability Standards or WIRAB expresses concern that NERC
(2) address the shortcomings 32 in the
contain more stringent requirements effectively disregarded the statutory
standards within one year of approval
than the ERO standards.34 WECC states rebuttable presumption without
by the Commission, including removing sufficient legal analysis.36
the sanctions table that conflicts with that, with the exception of WECC–IRO–
23. PacifiCorp states that, given the
the NERC Sanction Guidelines; (3) until STD–006–0, the WECC regional
unique nature of the Western
the WECC sanction table is removed, Reliability Standard that implements
transmission system, it supports the
follow the NERC Sanction Guidelines to the West’s unique approach to
eight regional Reliability Standards as
the maximum extent possible within the mitigation of unscheduled flow, which
necessary for addressing reliability
limits of the WECC sanction table; and the Commission approved as superior to
concerns of the Western
(4) monitor and enforce the standards the ERO Reliability Standard,35 none of Interconnection.
under a delegation agreement between the regional Reliability Standards in any
NERC and WECC, once that agreement way displace the ERO requirements 2. Protests
is approved.33 approved by the Commission. Rather, 24. Xcel, PPL and California
users, owners and operators in the Cogeneration filed protests or comments
17. NERC submitted its present Western Interconnection will still be in opposition to one or more of the
request for the Commission’s approval required to comply with all of the proposed regional Reliability Standards.
on March 26, 2007. In April 2007, the requirements of the approved ERO California Cogeneration objects to
Commission approved 83 ERO Reliability Standards. proposed regional Reliability Standard
Reliability Standards that apply nation- 20. WECC contends that the eight WECC–BAL–STD–002–0 (Operating
wide, except for Alaska and Hawaii. regional Reliability Standards satisfy the Reserves), which, in relevant part,
NERC and WECC request that the relevant statutory and regulatory criteria requires balancing authorities to
proposed regional Reliability Standards for approval. It states that only a few maintain operating reserves equal to a
take effect as soon as practical and, if commenters raised substantive concerns stated percentage of ‘‘load
possible, on the same day as the nation- in the WECC standard development responsibility.’’ According to California
wide Reliability Standards. process regarding several potentially Cogeneration, ‘‘load responsibility’’
ambiguous terms such as ‘‘load should not include behind-the-meter
D. Notice of Filing and Responsive
responsibility,’’ ‘‘firm transactions,’’ and load that a cogenerator serves at its
Pleadings
‘‘Receiver;’’ and that WECC has industrial or commercial host. It asserts
18. Notice of the NERC Filing was committed to address these issues in that a balancing authority is not
published in the Federal Register, 72 developing permanent regional obligated to serve that load in the case
Fed. Reg. 17,544 (April 9, 2007), with Reliability Standards. of an outage on the Bulk-Power System
interventions, comments and protests 21. WECC acknowledges that the and therefore should not be required to
due on or before April 17, 2007. sanctions tables in the proposed maintain associated reserves.37
Motions to intervene were filed by regional Reliability Standards differ 25. PPL, which owns and operates
Modesto Irrigation District, New York from the NERC Sanction Guidelines. electrical facilities and markets
Transmission Owners, Southern WECC states that it plans to propose electricity in the Western
California Edison Company, and replacement standards that incorporate Interconnection, objects to WECC–IRO–
the NERC Sanction Guidelines and STD–006–0, addressing the mitigation
Transmission Agency of Northern
address other concerns of NERC and of unscheduled flows. According to
California. Motions to intervene and
stakeholders. WECC also explains that PPL, WECC has not justified the need
comment or protest were filed by
the regional sanctions would apply only for this regional Reliability Standard,
PacifiCorp, WECC, Xcel Energy
when an offense was not covered by a which imposes requirements on
Services, Inc. (Xcel), PPL EnergyPlus, ‘‘receivers’’ that are not identified as an
sanction under the ERO Reliability
LLC and PPL Montana, LLC (PPL), and Standards and that the regional applicable entity, and improperly
Cogeneration Association of California Reliability Standards preclude the imposes mitigation obligations on load-
and Energy Producers and Users possibility of being sanctioned under serving entities (LSEs) and marketers
Coalition (California Cogeneration). both the WECC and ERO Reliability that lack authority or ability to comply
WIRAB submitted timely advice to the Standards for the same non-compliance with those obligations.
Commission regarding the NERC Filing. occurrence. 26. Xcel, which owns generation and
An untimely motion to intervene was 22. WIRAB advises that the proposed transmission facilities and serves
filed by Pacific Gas and Electric regional Reliability Standards are electricity customers in the Western
Company (PG&E). necessary for the Reliable Operation of Interconnection, argues that the
the Western Interconnection and should Commission lacks authority to review
31 Id. at 8–9. In Governors of Arizona, California,
take effect on the effective date of the 83 the proposed regional Reliability
Colorado, Montana, Nevada, New Mexico, Oregon, Standards because WECC was not a
Utah, Washington and Wyoming, 116 FERC
ERO Reliability Standards. WIRAB also
¶ 61,061 at P 27 (2006), the Commission established advises reinstatement of the one-year Regional Entity at the time it submitted
WIRAB as a Regional Reliability body pursuant to the proposed regional Reliability
jlentini on PROD1PC65 with NOTICES

section 215(j) of the FPA. 34 Our discussion below of each regional


32 The shortcomings in the regional Reliability Reliability Standard includes WECC’s explanation 36 WIRAB at 8–9 (citing NERC Request, Appendix

Standards were identified by NERC in a January 9, of how it is more stringent than the relevant ERO B at 4–5).
2007 letter to WECC. See NERC Filing, Ex. C at 128– Reliability Standard. 37 California Cogeneration Comments at 6 (citing
139. 35 WECC Comments at 14 (citing Order No. 693 California Independent System Operator Corp., 96
33 Id. at 8–9. at P 964). FERC ¶ 63,015 (2001)).

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices 33465

Standards to NERC. Xcel asserts that the WECC’s development of the proposed due process of WECC members that
WECC Reliability Standards regional Reliability Standards indicates approved them. Likewise, Xcel remarks
development process used to develop that Xcel had full opportunity to that WECC postponed substantive
these eight regional Reliability participate and raise its concerns in the responses to stakeholders’ comments
Standards would be invalid to the (what is now a Commission-approved) based on the rationale that it was
extent that the Commission directs stakeholders process, as well in the proposing the standards on an interim
changes to that process. Xcel contends NERC posting of the WECC regional basis.
that NERC, in eliminating the one-year Reliability Standards for comment.42 33. We affirm NERC’s decision to
interim status of the regional Reliability Accordingly, we deny Xcel’s protest on eliminate the one-year term limitation.
Standards, has effectively approved the this issue. NERC’s decision is consistent with our
regional Reliability Standards on a precedent. In the ERO Certification
2. Term Limitation Order, the Commission directed NERC
permanent instead of interim basis.
Further, Xcel raises substantive 30. As discussed above, WECC had to establish a process for adopting an
objections that are discussed below in proposed that the regional Reliability interim Reliability Standard on an
the context of the relevant regional Standards would be interim standards expedited basis, where the standard
Reliability Standard. that would remain in effect for a might be adopted later on a permanent
maximum of one year after Commission basis, without any possibility that the
II. Discussion approval. Specifically, each regional interim standard would expire in the
A. Procedural Matters Reliability Standard includes a interim.45 NERC subsequently revised
statement that it will remain in effect its ‘‘urgent action’’ procedures to
27. Pursuant to Rule 214 of the ‘‘for one year from the date of remove the automatic one year
Commission’s Rules of Practice and Commission approval or until a North expiration provision. In accepting this
Procedure, 18 CFR 385.214 (2006), the American Standard or a revised [WECC] revision, the Commission explained that
timely, unopposed motions to intervene Regional Reliability Standard goes into ‘‘It is sufficient * * * to allow the
serve to make the entities that filed place, whichever occurs first.’’ During interim Reliability Standard to remain
them parties to this proceeding. We will the interim, WECC would develop in effect until it is made permanent or
grant PG&E’s late motion to intervene, permanent standards that, upon replaced by a permanent Reliability
given the early stage of this proceeding Commission approval, would replace Standard, or possibly even its
and the absence of undue delay, the interim standards. withdrawal as a Reliability Standard so
prejudice or burden to the parties. 31. NERC, however, accepted the long as it is understood that these
B. General and Procedural Objections to regional Reliability Standards on the actions are all subject to Commission
the Regional Reliability Standards condition that ‘‘the standards shall approval.’’ 46 WECC developed the eight
remain mandatory and enforceable until regional Reliability Standards pursuant
1. WECC Reliability Standards they are revised, replaced or withdrawn to its Expedited Process for Urgent
Development Process in a subsequent standards action, Action Interim Standards (Expedited
28. As discussed above, Xcel argues including approval of the revision, Process).47 Thus, our concerns regarding
that the Commission only has the replacement, or withdrawal by the NERC’s urgent action procedures apply
authority to consider Reliability Commission.’’ 43 NERC explained that it equally to WECC’s Expedited Process.
Standards proposed by the ERO or a imposed this condition to be consistent 34. The commenters, however, are
Regional Entity. On April 19, 2007, with a Commission order which mistaken that the elimination of the
subsequent to Xcel’s protest, the provided that, with regard to a similar one-year expiration date necessarily
Commission accepted the proposed provision in NERC’s standards converts these from interim to
Regional Delegation Agreements, and development procedure, once a permanent regional Reliability
accepted WECC as a Regional Entity Reliability Standard is made effective Standards. WECC is still committed
organized on an Interconnection-wide under section 215 of the FPA, it can pursuant to its Expedited Process to
basis.38 Thus, we consider this objection only be revised, replaced or withdrawn completing the development of
by Xcel to be moot. by a further action that requires permanent replacement standards.48
29. Xcel also contends that ‘‘to the Commission approval. Moreover, as another condition of
extent the Commission directs changes 32. WECC, WIRAB and Xcel object to approval, NERC required WECC to
to WECC’s standards development NERC’s elimination of the one-year ‘‘meet its commitment to address the
process that differ from the process used expiration date. WECC and WIRAB state shortcomings identified in the standards
to develop these WECC Standards, those that the entities that voted in favor of * * * over the course of the next
standards will have been developed the regional Reliability Standards did so year.’’ 49 Thus, we disagree with the
pursuant to processes that were with the understanding that they were commenters that NERC, in eliminating
inconsistent with WECC’s own rules.’’ 39 voting for temporary standards, not the one-year expiration date, has made
The Commission, in the April 19 Order, standards that would continue the regional Reliability Standards
accepted WECC’s Standards indefinitely until replaced.44 WIRAB permanent or thwarted due process.
Development Manual,40 and WECC’s states that, while it agrees with the NERC’s decision will assure that, if
eight proposed regional Reliability policy that urgent action standards WECC is unable to develop permanent,
Standards were developed using the should not have sunset dates, it is replacement regional Reliability
concerned that imposing the rule with
process set forth in this manual. The
respect to the eight WECC regional 45 ERO Certification Order, 116 FERC ¶ 61,062 at
Commission also directed WECC to
Reliability Standards will abridge the P 253.
develop several changes to the 46 North American Electric Reliability Corp., 118
manual.41 However, the record of
jlentini on PROD1PC65 with NOTICES

42 See, e.g., Ex. C at Attachment 2 at 5, FERC ¶ 61,030 at P 30 (2007).


Attachment 4 at 23–27. 47 WECC Comments at 5.
38 April 19 Order at P 432. 43 NERC Filing at 10–11. See also id. at Ex. B at 48 Id. WECC represents that it expects to complete
39 Xcel Comments at 8. 6–7 (March 12, 2007, NERC Board of Trustees permanent, replacement standards within one year
40 April 19 Order at P 469. Decision on WECC Reliability Standards). for most of the interim standards. See id. at 7.
41 Id. at P 470. 44 See WECC Comments at 7. 49 NERC Filing, Ex. B at 7.

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00021 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
33466 Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices

Standards within one year, the interim understanding, supported by NERC’s are currently legally binding only on
standards that WECC represents are filing, is that NERC determined that the signatories to the RMS Agreement.
crucial for reliability within the Western rebuttable presumption was overcome WECC and NERC explain that
Interconnection will not automatically ‘‘with respect to this component of the Commission approval would extend the
expire. proposed standards,’’ i.e., the sanctions compliance obligations of the regional
table.54 NERC supported this Reliability Standards beyond the RMS
3. NERC’s Application of the Rebuttable
determination by explaining that NERC signatories to all applicable users,
Presumption
staff and industry stakeholders owners and operators in the Western
35. Section 215(d)(3) of the FPA identified a number of shortcomings, Interconnection. According to NERC,
provides that, when a Reliability the most significant of which is the having the regional Reliability
Standard is submitted to the ERO by an sanction table that is inconsistent with Standards approved as mandatory under
Interconnection-wide Regional Entity, the NERC Sanction Guidelines.55 section 215 of the FPA provides
the ERO must rebuttably presume that Although NERC’s explanation is significant additional authority for
the standard meets statutory criteria for succinct, the Commission concludes compliance and enforcement.
approval.50 In Order No. 672, the that NERC has articulated a sufficient 42. Xcel, on the other hand, asserts
Commission explained that the rationale for finding that the rebuttable that the proposed standards are
rebuttable presumption refers to the presumption with regard to this one unnecessary, reasoning that the RMS
burden of proof before the ERO.51 Thus, component was overcome. In general, Agreement will remain in effect and is
a party that objects to a proposed however, NERC should provide a robust sufficient to protect reliability.
Reliability Standard before the ERO discussion of its reasoning for finding 43. We agree with WECC, WIRAB and
must demonstrate that it does not meet that the rebuttable presumption has NERC that approval of the proposed
criteria for approval. If the ERO finds been overcome. regional Reliability Standards under
that the presumption is not adequately section 215 would enhance reliability in
rebutted, it must accept the proposed 4. Potential for Dual Penalties the Western Interconnection by making
Reliability Standard from a Regional 39. Xcel protests that the proposed WECC’s current practices binding on all
Entity organized on an Interconnection- WECC regional Reliability Standards relevant entities in the region and by
wide basis.52 impose an unfair burden because, strengthening WECC’s compliance and
36. Here, NERC correctly applied the according to Xcel, the proposed enforcement authority. WECC’s current
rebuttable presumption to WECC as a standards are duplicative of practices were developed in response to
Regional Entity organized on an Commission-approved NERC Reliability concrete and significant reliability
Interconnection-wide basis. However, Standards. Thus, Xcel contends that the problems in the Western
the NERC Board found that ‘‘[b]ecause regional Reliability Standards present Interconnection in the mid-1990s.
each of the proposed standards contains the risk of dual penalties for the same According to WECC, reliability in the
a sanctions table that is inconsistent offense. region has improved since the practices
with the NERC Sanctions Guidelines, 40. We reject Xcel’s protest on this have been in effect. When we first
the proposed standards have lost the issue. Each of the proposed regional approved the practices in 1999, we
rebuttable presumption that such Reliability Standards provides that ‘‘[a]t lacked full jurisdiction over reliability
standards would otherwise have.’’ 53 no time shall this regional Standard be and therefore could not impose the
NERC then approved the proposed enforced in addition to a similar North practices on a mandatory basis. While
regional Reliability Standards with the American Standard.’’ 56 WECC, in its we laud WECC members for their
condition that WECC conform the comments, makes clear that the intent of voluntary compliance by contract, we
sanctions table to NERC’s Sanction this language is to ensure that there believe that statutorily-based and
Guidelines and that, in the interim, would not be dual sanctions for the mandatory Reliability Standards will
WECC follow the NERC guidelines to same offense.57 Thus, we conclude that better ensure the reliability of the Bulk-
the maximum extent possible. the regional Reliability Standards will Power System.
37. WIRAB disagrees with the manner not result in duplicative penalties
in which NERC dismissed the statutory resulting from the same non-compliance C. Discussion of WECC’s Regional
presumption. It asserts that NERC failed event. Reliability Standards
to provide an adequate analysis 1. WECC–BAL–STD–002–0 (Operating
regarding the reasonableness, potential 5. Need for the Proposed Standards
Reserves)
discriminatory impacts, or the broader 41. In reviewing a proposed
public interest at stake to support a 44. Regional Reliability Standard
Reliability Standard, we consider, in
finding that rebuts the presumption. WECC–BAL–STD–002–0 requires that
relevant part, whether it would address
38. In the first instance, WIRAB’s adequate generating capacity be
a reliability goal.58 Here, WECC, WIRAB
concern is only hypothetical since available at all times to maintain
and NERC each represent that the
NERC, after determining that the scheduled frequency and avoid loss of
proposed regional Reliability Standards
rebuttable presumption should not firm load following transmission or
would enhance regional reliability by
apply, determined that the regional generation contingencies. The regional
making binding, throughout the United
Reliability Standards met the statutory Reliability Standard applies to
States portion of the Western
criteria for approval. Moreover, it balancing authorities and reserve
Interconnection, reliability practices
appears that WIRAB interprets NERC as sharing groups (RSGs) with provision
that are currently implemented in the
having completely disregarded the for agents to provide administrative
Western Interconnection on a voluntary
rebuttable presumption. The duties. A balancing authority or reserve
basis. As noted above, those practices
Commission believes that the better sharing group must maintain minimum
jlentini on PROD1PC65 with NOTICES

54 Id.at 9.
operating reserves, defined as the sum
50 16 U.S.C. 842o(d)(3); 18 CFR 39.5(b). 55 Id.at 10. of: (1) Regulating reserves; (2)
51 Order No. 672 at P 301. 56 See, e.g., WECC–BAL–STD–002–0 § A5. contingency reserves; (3) additional
52 Id. 57 See WECC Comments at 2, n.1. reserve for interruptible imports; and (4)
53 NERC Filing, Ex. B at 4–5. 58 Order No. 672 at P 324. additional reserve for on-demand

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00022 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices 33467

obligations. WECC requires balancing provision 61 that is not included in responsibility could be interpreted to
authorities to maintain an amount of NERC’s Reliability Standards template, include gross load in conflict with
contingency reserves: and additional substantive and Opinion No. 464 and, thus, asks the
Sufficient to meet the NERC Disturbance formatting concerns. Commission to remand the regional
Control Standard BAL–002–0, equal to the Reliability Standard so that it can be
Comments
greater of: (a) The loss of generating capacity modified to include a definition of load
due to forced outages of generation or 47. WECC explains that NERC responsibility consistent with Opinion
transmission equipment that would result Reliability Standard BAL–002–0 No. 464.
from the most severe single contingency; or requires an applicable entity to have the 49. Xcel also argues that the term load
(b) The sum of five percent of the load ability to supply reserves equal to the responsibility is overly vague. It quotes
responsibility served by hydro generation most severe single contingency. a WECC document that defines load
and seven percent of the load responsibility According to WECC, while applicable responsibility as ‘‘[a] control area’s firm
served by thermal generation.
users, owners and operators in the load demand plus those firm sales
Further, the contingency reserve must Western Interconnection must comply minus those firm purchases for which
be composed of at least 50 percent with BAL–002–0, the corresponding reserve capacity is provided by the
spinning reserves, which must be regional Reliability Standard goes supplier.’’ 63 According to Xcel, WECC
capable of ramping and being fully further and requires each balancing has not adequately defined the term
deployed within ten minutes. authority in the West to provide a ‘‘firm’’ embedded in its definition of
45. WECC’s regional Reliability minimum reserve of five percent of the load responsibility and, likewise, has
Standard corresponds to NERC’s loads served by hydro generation and not adequately defined the related term
Reliability Standard BAL–002–0 seven percent of the loads served by ‘‘interruptible.’’
(Disturbance Control Performance), thermal generation. WECC states that 50. Xcel notes that WECC–BAL–STD–
which requires a balancing authority this regional minimum reserve 002–0 requires the purchaser of
(either directly or by participating in a requirement was developed to assure interruptible power to carry additional
reserve sharing group) to use its that there would be sufficient generation reserves to replace interruptible
contingency reserves to balance to sustain acceptable power system imports. Xcel posits that, while the
resources and demand and return performance for various contingencies. definition of ‘‘interruptible’’ is unclear,
Interconnection frequency to within Further, WECC explains that WECC– application of a narrow interpretation of
defined limits following a reportable BAL–STD–002–0 is more stringent the term could have adverse impacts on
disturbance. Requirement 3 of NERC’s because NERC’s BAL–002–0 requires competition and reliability. Specifically,
BAL–002–0 requires each balancing contingency reserves to be restored it claims that to avoid application of the
authority or reserve sharing group to within 90 minutes following a ‘‘adder’’ some entities avoid purchasing
‘‘carry at least enough Contingency disturbance while WECC requires ‘‘economy power,’’ or interruptible
Reserve to cover the most severe restoration within 60 minutes. power, thereby impeding competition.
contingency.’’ 48. As noted above, WECC requires Xcel also claims that this practice may
46. As with all eight regional balancing authorities to maintain result in entities utilizing local units
Reliability Standards, NERC approved contingency reserves equal to the greater that are subject to failure or curtailment,
WECC–BAL–STD–002–0 with the of the loss of generating capacity resulting in less reliable operations.
condition that WECC meet its resulting from the most severe single Xcel further argues that certain entities
commitment to address the contingency or the sum of five percent may try to claim that most ‘‘firm’’
shortcomings identified by NERC in a of load responsibility served by hydro transactions, as interpreted by the
January 9, 2007 letter to WECC.59 With generation and seven percent of the load Commission in Order No. 890, are
regard to WECC–BAL–STD–002–0, responsibility served by thermal potentially curtailable and thus
NERC identified various formatting generation. Both Xcel and California ‘‘interruptible’’ under a ‘‘very narrow
concerns including the need to specify Cogeneration protest that the term ‘‘load interpretation.’’ Xcel adds that there is
individual Requirements and responsibility’’ as used by the WECC is no evidence to show that ‘‘economy
corresponding Measures, consistent ambiguous and could lead to transactions’’ are less reliable thus
with the format of the NERC Reliability inconsistent interpretations of the warranting the need for extra reserves.
Standards. NERC also stated that regional Reliability Standard. California 51. Xcel also opposes the 60-minute
WECC’s regional Reliability Standard Cogeneration states that Commission restoration period that would be
defines the terms ‘‘automatic generation Opinion No. 464 determined that a required under BAL–STD–002–0. Xcel
control,’’ ‘‘disturbance,’’ ‘‘frequency qualifying facility’s (QF) net load is the asserts that BAL–STD–002–0 would
bias,’’ and ‘‘non-spinning reserve’’ only relevant load for the purposes of require restoration of contingency
differently from NERC’s Glossary of calculating the operating reserve reserves within 60 minutes rather than
Terms Used in Reliability Standards responsibility of the QF.62 It expresses the 90 minutes permissible under the
(NERC glossary).60 NERC also identifies concern that the term load corresponding NERC standard.
a number of shortcomings that apply According to Xcel, in adopting 60
generally to all of the WECC regional 61 Each proposed regional Reliability Standard minutes of restoration time, WECC and
Reliability Standards including the includes an ‘‘excuse of performance’’ provision NERC disregarded Requirement R6.2 of
stating that ‘‘non-compliance with any of the BAL–002–0 that established a default
sanction tables that conflict with the reliability criteria contained in this Standard shall
NERC Sanction Guidelines, failure to be excused and no sanction applied if such non-
contingency reserve restoration period
include Violation Severity Levels (levels compliance results directly from one or more of the of 90 minutes and allows adjustment of
of non-compliance) and Violation Risk [specified] actions or events,’’ including
governmental order, order of reliability coordinator, 63 Xcel Comments at 12, citing NERC/WECC
jlentini on PROD1PC65 with NOTICES

Factors, an ‘‘excuse of performance’’ protection of facilities and extraordinary Planning Standards and Minimum Operating
contingency (such as act of war, insurrection, flood Reliability Criteria, Definitions, Revised August 9,
59 SeeNERC Filing, Ex. C, Attachment 3 at 5–7. or earthquake). 2002. The California Independent System Operator
60 In
Order No. 693 at P 1893–98, the Commission 62 Citing California Independent System Operator Corporation tariff also uses this definition of load
approved NERC’s glossary and directed certain Corp., Opinion No. 464, 104 FERC ¶ 61,196 at P 40 responsibility. See Opinion No. 464, 96 FERC
modifications. (2003). ¶ 63,015 at 13.

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00023 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
33468 Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices

this period ‘‘to better suit the reliability expects WECC in developing a and who is required to comply.68 Xcel
targets of the Interconnection based on permanent, replacement standard to and California Cogeneration contend
analysis approved by the NERC address these shortcomings as it has that the Commission should remand
Operating Committee.’’ Xcel contends committed to do. For example, for each WECC–BAL–STD–002–0 because of
that WECC failed to obtain approval of of the proposed regional Reliability ambiguities in the terms ‘‘load
the NERC Operating Committee. Xcel Standards, (1) Regional definitions responsibility’’ and ‘‘firm transaction.’’
also claims that WECC’s proposed 60- should conform to the definitions set As discussed above, the Commission
minute restoration period will have a forth in the NERC glossary, unless a believes that the regional Reliability
dampening effect on competition specific deviation has been justified; Standard is sound, as it provides greater
because the shortened restoration period and (2) documents that are referenced in stringency than NERC’s reserve
will provide little time for market the Reliability Standard should be requirements and meets a need of the
participants to procure alternative attached to the Reliability Standard. Western Interconnection. While
resources outside of the host balancing Likewise, with respect to this and each commenters identify potential
authority. of the proposed regional Reliability ambiguities, we do not believe that
52. Further, Xcel argues that WECC Standards, we agree with NERC that these potential uncertainties
has not justified the requirements of the WECC must remove the sanctions table demonstrate a degree of ambiguity
regional Reliability Standard and thus that is inconsistent with NERC’s within the regional Reliability Standard
the technical expertise of WECC should Sanction Guidelines and develop that requires us to remand it.69 Rather,
not be given any weight in the Violation Risk Factors (levels of non- as WECC indicated in its response to
Commission’s evaluation of the regional compliance) and Violation Severity stakeholders in the regional Reliability
Reliability Standard. Levels that conform to corresponding Standards development process, WECC
Commission Determination NERC standards. In approving NERC’s will provide an opportunity to address
Sanction Guidelines, the Commission these concerns when developing a
53. The Commission approves
emphasized the need to achieve permanent, replacement standard. The
regional Reliability Standard WECC–
consistency in the assessment of Commission agrees that this is a
BAL–STD–002–0 as mandatory and
penalties across the regions. Elimination reasonable approach and will expect
enforceable in the Western
of the WECC sanctions table will further WECC’s submission of a replacement
Interconnection. The Commission finds
this goal.66 standard to adequately address these
that the proposed regional Reliability
55. Further, it is important that stakeholder concerns.
Standard is more stringent than the
regional Reliability Standards and NERC 57. California Cogeneration raised
corresponding NERC Reliability
Reliability Standards achieve a concerns that the term load
Standard, BAL–002–0, because WECC
requires a more stringent minimum reasonable level of consistency in the responsibility must be defined
reserve requirement than the nation- structure of a Reliability Standard so consistent with the Commission’s
wide requirement.64 Further, WECC’s that there is a common understanding of Opinion No. 464, which issued in a
requirement to restore contingency the elements. In particular, we agree proceeding under section 205 of the
reserves within 60 minutes is more with NERC that WECC should eliminate FPA that addressed treatment of QFs
stringent than the 90 minute restoration the ‘‘excuse of performance’’ provision under the CAISO open access
period set forth in NERC’s BAL–002–0. of the regional Reliability Standards, transmission tariff. The Commission
While we agree with Xcel that NERC’s which is inconsistent with NERC’s agrees that a QF’s load responsibility
filing did not adequately explain the format. While the factors identified in should be interpreted consistent with
need for WECC–BAL–STD–002–0 or the excuse of performance provision Opinion No. 464, which provided in
why it was more stringent than the may be legitimate mitigating factors for relevant part that:
corresponding NERC Reliability WECC to consider when assessing a We affirm the judge’s finding that the long-
Standards, WECC provides an adequate penalty on a case-by-case basis, the standing practice in the CAISO control area
explanation in its comments for the Commission disagrees that a Reliability of scheduling, metering and procuring
Commission to make a reasoned Standard should contain a blanket reserves on a net load basis should be
determination.65 waiver or excuse for non-compliance.67 permitted to continue, so long as a QF has
We expect WECC, in developing a contracted for standby service with a UDC
54. The Commission agrees with the
permanent, replacement standard, to [Utility Distribution Company], i.e., a
shortcomings identified by NERC contract that provides for the immediate
regarding WECC–BAL–STD–002–0 and address these concerns of both NERC replacement of energy in case of the QF’s
and the Commission. In general, with forced outage. The record indicates * * *
64 While approving the WECC regional Reliability respect to both the eight proposed that by contract with a QF, a UDC will
Standard, the Commission reiterates its directive in Reliability Standards as well as other provide standby service and operating
Order No. 693 that the ERO develop a continent-
wide reserve policy that is ‘‘based on the reliability
standards that are being developed by reserves if there is a forced QF outage.70
risk of not meeting load associated with a particular WECC, it is essential that WECC employ 58. Thus, from an economic
balancing authority’s generation mix and topology.’’ a higher level of precision and perspective under section 205, the UDC
See Order No. 693 at P 340. Our approval of WECC– consistency.
BAL–STD–002–0 does not affect this directive to must pay for the reserves associated
the ERO. 56. In Order No. 672, the Commission, with the backup power provided by the
65 Section 39.5(a) of the Commission’s in discussing the factors it would UDC by contract. While operating
regulations, 18 CFR 39.5(a) (2006), provides that the consider in determining whether a reserves may be required for behind the
ERO’s submission of a new or modified Reliability proposed Reliability Standard met the
Standard must include (1) A concise statement of
the basis and purpose of the proposed Reliability
statutory standard for approval, 68 Order No. 672 at P 325.
Standard, (2) a summary of the Reliability Standard explained that a proposed Reliability 69 The Commission notes that WECC has defined
jlentini on PROD1PC65 with NOTICES

development proceedings, and (3) a demonstration Standard should be clear and the term load responsibility, although not in its
that the proposal is just, reasonable, not unduly unambiguous regarding what is required regional Reliability Standard. The definition can be
discriminatory or preferential, and in the public found at WECC’s Web site at: http://wecc.biz/
interest. Future Reliability Standard filings may be documents/library/procedures/
66 ERO Certification Order at P 254, 350. WECC_Reliability_Criteria_definitions_8-02.pdf.
subject to a deficiency letter if they fail to satisfy
the filing requirements set forth in our regulations. 67 April 19 Order at P 133. 70 Opinion No. 464, 104 FERC ¶ 61,196 at P 40.

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices 33469

meter load in a Regional Reliability authorities, and load serving entities Interconnection. WECC notes that, in
Standard for reliability reasons, a QF is within the Western Interconnection. developing the regional Reliability
not required to buy operating reserve for Under WECC’s plan for congestion Standard, stakeholders commented that
the load that has standby service. It management, responsible entities must the term ‘‘receiver’’ as defined in the
remains the responsibility of the host comply with requests from operators of standard should more closely match the
utility that provides the QF’s normal qualified transmission paths to reduce NERC Functional Model and should not
stand-by or back-up power to supply unscheduled flow on the path. The include market entities. WECC states
those reserves. We believe this regional Reliability Standard identifies that it intends to address these issues in
explanation addresses California when an operator shall request developing a permanent, replacement
Cogeneration’s concern. curtailments, states that responsible standard.74
59. In regard to Xcel’s concern about entities shall comply in a timely manner 66. PPL protests the applicability of
the definition of interruptible imports, with a request for curtailments, and WECC–IRO–STD–006–0, noting that
while it is possible that the term may establishes procedures for reducing NERC Reliability Standard IRO–006–3
require refinement by WECC to address flows. In particular, it requires that: applies to reliability coordinators,
specific contexts, the meaning of the transmission operators and balancing
Upon receipt of a curtailment request,
term ‘‘interruptible’’ is generally well Contributing Schedules which are subject to authorities. PPL contends that WECC
understood in the industry, i.e., curtailments will be reduced (or equivalent has, without explanation, significantly
transmission or generation subject to alternative schedule adjustments will be broadened the scope of the regional
interruption at the provider’s discretion. effected) in accordance with the following Reliability Standard by requiring
Xcel’s claims that the provision, under procedures:
compliance by LSEs. According to PPL,
a narrow interpretation, could have (i) Receivers of Contributing Schedules market entities such as LSEs may be
adverse impacts on competition and will initiate the requested schedule
reductions * * *. [72] unable to meet the requirements of
reliability are highly speculative. WECC–IRO–STD–006–0. Second, PPL
60. The Commission rejects Xcel’s 63. NERC’s Reliability Standard IRO– protests that certain requirements apply
protest regarding the 60-minute 006–3 (Transmission Loading Relief), to ‘‘receivers,’’ which are not identified
contingency reserve restoration period. which the Commission approved in in the applicability section of the
This is useful stringency that benefits Order No. 693 subject to certain regional Reliability Standard. PPL
reliability in the Western modifications,73 requires a reliability
Interconnection by shortening the time contends that receivers (1) May lack the
coordinator experiencing potential or authority or ability to comply with a
after a disturbance that the balancing actual System Operating Limit (SOL) or
authority might not have sufficient directive to reduce flows and (2) may
Interconnection Reliability Operating include functional entities beyond LSEs
reserves to meet its reliable obligations Limit (IROL) violations to take
in the Interconnection. Xcel’s concern such as ‘‘purchasing selling entities’’
appropriate actions pursuant to that are not identified in the
that this provision harms competition is established procedures to relieve
speculative. Moreover, the Commission applicability section of the regional
transmission loading. For the Eastern Reliability Standard.
notes that NERC Reliability Standard Interconnection, balancing authorities
EOP–001, Requirement R1 requires 67. PPL recommends that the
must follow the established Commission limit applicability to those
entities to have pre-existing transmission loading relief (TLR)
arrangements. Balancing authorities entities identified in NERC Reliability
procedures to take appropriate actions Standard IRO–006–3 and clarify that the
should not use the reserve restoration pursuant to established procedures to
period to shop for better prices but to be assessment of penalties is limited to the
relieve transmission loading. entities to which the regional Reliability
concerned about restoring the reserves Requirement R2.2 of IRO–006–3
so the Bulk-Power System remains Standard is applicable. PPL asks that, if
identifies ‘‘the equivalent the Commission decides that it is
reliable. Interconnection-wide transmission
61. Finally, while Xcel may be appropriate to include load-serving
loading relief procedure for use in the entities, the applicability should be
technically correct that the current Western Interconnection is the ‘WSCC
NERC BAL–002–2 requires approval of limited to LSEs as defined by NERC 75
Unscheduled Flow Mitigation Plan.’ ’’ and to LSEs that meet NERC’s
the NERC Operating Committee to 64. NERC approved WECC–IRO–STD–
change the restoration period, we do not compliance registry criteria.
006–0 on the condition that WECC meet
believe this is a sufficient reason to its commitment to address specified 68. Xcel protests that no justification
remand WECC’s proposal. First, in shortcomings concerning formatting, has been provided for the WECC
Order No. 693, the Commission directed use of standard terms, and the need for regional Reliability Standard. Xcel
NERC to modify this Requirement to greater specificity in the actions that a recognizes that one benefit of the WECC
replace ‘‘NERC Operating Committee’’ responsible entity must take. In unscheduled flow mitigation procedures
with ‘‘ERO.’’ 71 NERC board approval of addition, NERC noted that the is the coordinated use of phase shifters
WECC–BAL–STD–002–0 suffices. requirements should be part of the to provide some relief on an
Second, WECC did not increase but, regional Reliability Standard rather than overburdened transmission path
rather, decreased the restoration period, being embedded in a filing. without the economic impact of
making the WECC standard include a schedule curtailments. Xcel suggests
more stringent requirement than NERC’s Comments that, as an alternative, the WECC
comparable requirement. 65. According to WECC, WECC-IRO- procedures could be modeled after the
2. WECC–IRO–STD–006–0 (Qualified STD–006–0 is essential because it is the
Path Unscheduled Flow Relief) only source of a mandatory process for 74 See WECC Comments at 10.
75 PPL at 10. See August 2, 2006, NERC Glossary
mitigating overloads due to
jlentini on PROD1PC65 with NOTICES

62. Regional Reliability Standard unscheduled line flows in the Western of Terms Used in Reliability Standards at 10, which
WECC–IRO–STD–006–0 applies to defines load-serving entity as an entity that
‘‘secures energy and transmission service (and
transmission operators, balancing 72 WECC–IRO–STD–006–0, Requirement WR1,
related Interconnected Operations Services) to serve
Plan Attachment 1, Section 9.h. the electric demand and energy requirements of its
71 Order No. 693 at P 356. 73 Order No. 693 at P 960–64. end-use customers.’’

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00025 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
33470 Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices

TLR procedures, while retaining this of the WECC regional Reliability regional Reliability Standard requires,
initial step. Standard beyond the applicability of the in addition, that transmission owners
corresponding NERC Reliability and transmission operators analyze and
Commission Determination
Standard is not in itself problematic, we certify all relay settings and operations
69. We approve WECC–IRO–STD– are concerned regarding PPL’s on specified paths to determine whether
006–0 as mandatory and enforceable for contention that LSEs may not be able to operations were correct, and that
the Western Interconnection. The meet the Requirements of the regional current information on relays is
regional Reliability Standard provides Reliability Standard. While we are provided to the transmission operators.
that practices under WECC’s approving WECC–IRO–STD–006 as WECC explains that these requirements
Unscheduled Flow Mitigation Plan— mandatory and enforceable, we direct were developed to address root causes
including directions thereunder to WECC to address PPL’s concerns in of a July 1996 system disturbance in
reduce flows—are enforceable against developing a permanent, replacement which undesirable relay operations due
all Transmission Operators, Balancing regional Reliability Standard. to incorrect settings and undetected
Authorities and Load-Serving Entities in 72. We also expect that WECC, in relay problems resulted in cascading
the Western Interconnection. In Order developing a permanent, replacement outages in the Western Interconnection.
No. 693, we found that the WECC’s regional Reliability Standard, will 77. Xcel argues that no justification
Unscheduled Flow Mitigation Plan address the shortcomings identified by for WECC’s certification requirement
(which relies on phase angle regulators, NERC. has been provided. According to Xcel,
series capacitors and back-to-back DC regional differences are intended to
lines to mitigate contingencies without 3. WECC–PRC–STD–001–1 (Certification
of Protective Relay Applications and provide reliability protection in
curtailing transactions) is superior to the situations where physical differences in
national Reliability Standard.76 Settings)
the Bulk-Power System justify
Accordingly, the Commission finds that 73. Regional Reliability Standard
additional stringency. It claims that
WECC–IRO–STD–006–0 is adequately WECC–PRC–STD–001–1 applies to
WECC–PRC–STD–001–1 appears to be
justified. In developing a permanent, transmission operators or transmission
driven by a desire for an attestation, not
replacement regional Reliability owners of 40 specified transmission
an actual physical difference in the
Standard, WECC may consider Xcel’s paths.79 The regional Reliability
Western Interconnection and that, to the
suggestion to model the WECC Standard requires these entities to
extent the attestation is needed, it is
procedures after the TLR procedures, certify to WECC that all (1) Protective
appropriate for the NERC Reliability
however, we will not mandate such an relay applications and (2) protective
Standards rather than a regional
approach. relay settings and logic are appropriate
70. The Commission shares PPL’s difference. Xcel further argues that the
for the specified transmission paths. It
concern that, while the applicability of proposed regional Reliability Standard
also requires these entities to certify that
the regional Reliability Standard does not create any additional reliability
‘‘relay operations since the last
identifies LSEs, the requirements refer benefit but, rather, needlessly
certification or during the last three-year
to receivers. As indicated by PPL, the compounds the requirements of the
period have been analyzed for
term ‘‘receiver’’ may refer to LSEs as NERC Reliability Standards.
correctness and appropriate corrective
well as other market participants. While action taken. * * *’’ Commission Determination
WECC states that WECC–IRO–STD–006 74. NERC Reliability Standard PRC–
is an exact translation of existing WECC 78. The Commission approves WECC–
001–1 (System Protection Coordination),
RMS criteria, an entity cannot be subject PRC–STD–001–1 as mandatory and
which addresses protection systems,
to a compliance action if it has not been enforceable in the Western
requires transmission operators and
clearly identified in the applicability Interconnection. The Commission
generator operators to notify appropriate
section of the Reliability Standard.77 expects WECC, in developing
entities of relay or equipment failures
Thus, in approving the regional replacement standards, to address the
and to coordinate when installing new
Reliability Standard, we expect a shortcomings identified by NERC.
or modified protection systems.80
continuation of the existing practices for 75. NERC approved WECC–PRC– 79. The Commission disagrees with
transmission line relief in the Western STD–001–1 with the condition that Xcel’s contentions that the need for the
Interconnection. However, an entity that WECC meet its commitment to address regional Reliability Standard has not
is not clearly identified in the the shortcomings identified by NERC in been justified and that it does not create
applicability provision of a regional a January 9, 2007 letter to WECC, any additional reliability benefits. While
Reliability Standard may not be subject including several formatting concerns. the NERC filing did not elaborate on the
to penalties for non-compliance. reliability benefit of WECC–PRC–STD–
Moreover, pursuant to section 215(d)(5) Comments 001–1, WECC explains that it goes
of the FPA and section 39.5(f) of the 76. WECC states that applicable users, beyond the related NERC Reliability
Commission’s regulations,78 we direct owners and operators in the Western Standard by requiring certification that
that WECC in developing a permanent, Interconnection must comply with the all relay settings and operations on
replacement Reliability Standard, clarify Requirements of the corresponding specified transmission paths are
the term ‘‘receiver’’ and the NERC Reliability Standard. The WECC appropriate for the Bulk-Power System.
applicability of the standard. The certification requirement provides
71. We also share PPL’s concerns 79 Some of the specified transmission paths are an additional level of assurance that
regarding the identification of LSEs as located completely or partially outside the United protection systems will operate as they
States. The Commission addresses the regional should to provide for Bulk-Power
applicable entities. While the expansion Reliability Standard only as it applies to those paths
or portions of paths that are within the United System reliability. It is appropriate to
jlentini on PROD1PC65 with NOTICES

76 See Order No. 693 at P 964. States. give due weight to WECC’s technical
77 See Order No. 693 at P 39 (each Reliability 80 In Order No. 693, at P 1433–49, the expertise in its representation that the
Standard must clearly identify the subset of users, Commission approved NERC Reliability Standard requirements of this regional Reliability
owners and operators of the Bulk-Power System to PRC–001–1 and, as a separate action, directed
which the Reliability Standard applies). NERC to develop certain modifications to the
Standard will address the problems
78 18 CFR 39.5(f) (2006). standard. identified as a root cause of prior

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices 33471

cascading outages in the Western Regional Entity, must establish 003–1.86 Xcel also contends that WECC
Interconnection.81 procedures for review, analysis, has not explained the physical
80. Further, Xcel incorrectly reporting and mitigation of protection differences in the Western
characterizes the Commission’s system misoperations. WECC–PRC– Interconnection necessitating the
previous statements regarding when a STD–003–1 states that it meets regional difference and, thus, WECC’s
regional difference may be justified. The Requirement 1 of NERC Reliability technical expertise should be given no
Commission has identified two types of Standard PRC–003–1. weight in evaluating the WECC regional
regional differences that it will accept, 83. As with all eight regional Reliability Standard.
provided they otherwise satisfy the Reliability Standards, NERC approved
statutory requirements for approval: (1) Commission Determination
WECC–PRC–STD–003–1 with the
A regional difference that is more condition that WECC meet its 86. The Commission approves WECC–
stringent than the continent-wide commitment to address the PRC–STD–003–1 as mandatory and
Reliability Standard, including a shortcomings identified by NERC in a enforceable in the Western
regional difference that addresses January 9, 2007 letter to WECC. With Interconnection. The Commission
matters that the continent-wide regard to WECC–PRC–STD–003–1, agrees with WECC that the proposed
Reliability Standard does not; and (2) a NERC noted, inter alia, that the WECC regional Reliability Standard goes
regional Reliability Standard that is definition of ‘‘disturbance’’ is not beyond the corresponding NERC
necessitated by a physical difference in identical to the NERC glossary standards because no current NERC
the Bulk-Power System.82 Xcel definition. It also identified a WECC Reliability Standard includes the
incorrectly combines the two Measure that refers to the filing of a equipment removal and repair
appropriate types of regional differences form for reporting misoperations, requirements set forth in this regional
as a single standard category where a without a corresponding requirement. Reliability Standard. Moreover, while
regional difference sets forth a we agree with Xcel that NERC’s filing
stringency needed to address a physical Comments did not adequately explain the need for
difference in the Bulk-Power System. 84. In its comments, WECC explains WECC–PRC–STD–003–1 or why it is
Thus, we reject Xcel’s argument that that the corresponding NERC Reliability more stringent than the corresponding
WECC–PRC–STD–001–1 should not be Standard PRC–003–1 requires the NERC Reliability Standards, WECC has
approved because it is not based on an analysis of misoperations within 90 provided an adequate explanation in its
actual physical difference in the days and the submission of corrective comments, as discussed above.
Western Interconnection. 87. We note that upon failure of
action plans. WECC states that the
protective relays, NERC Reliability
4. WECC–PRC–STD–003–1 (Protective applicable users, owners and operators
Standard PRC–001–1 requires
Relay and Remedial Action Scheme of the Bulk–Power System in the West
transmission operators and generator
Misoperation) must comply with the requirement of
operators to take corrective actions as
81. Regional Reliability Standard NERC’s PRC–003–1. In addition, the
soon as possible (within thirty minutes
WECC–PRC–STD–003–1 has the WECC regional Reliability Standard
as directed by Order No. 693).87 Order
purpose of ensuring that protection goes further and requires the applicable
No. 693 clarifies that ‘‘corrective
system misoperations are analyzed and entities in the West: (1) To remove
actions’’ do not refer to the repair of
mitigated.83 This regional Reliability equipment that has misoperated within
protective relays, but instead to actions
Standard applies to the owners and 22 hours; and (2) to repair or replace
that ensure the reliability of the system,
operators of 40 specific transmission equipment that has misoperated within
such as lowering IROLs and SOLs. The
paths that are identified in Attachment 20 business days for the specific
proposed regional Reliability Standard
A of the standard. The regional transmission paths identified in the
does not relieve compliance with this
Reliability Standard requires the WECC regional Reliability Standard.
requirement but, rather, adds more
removal and repair of protection WECC explains that these requirements
stringency by defining a maximum
systems after a misoperation within were developed as a result of a 345 kV
timeframe for removal and repair of
specified time frames. line relay misoperation in July 1996
protective equipment.
82. The WECC regional Reliability when virtually the same outage 88. The Commission disagrees with
Standard corresponds to NERC’s occurred the next day because the faulty Xcel’s assertion that approval of WECC–
Reliability Standard PRC–003–1, which equipment had not been isolated. PRC–STD–003–1 would sidestep the
also relates to protective system 85. Xcel points out that, in Order No. Commission’s directive that NERC
misoperations.84 Requirement 1 of 693, the Commission stated that it consider whether greater consistency
NERC’s PRC–003–1 provides that each would neither approve nor remand can be achieved as NERC modifies PRC–
regional reliability organization, i.e., NERC Reliability Standard PRC–003–1 003–1. Approval of the WECC regional
until NERC submits additional Reliability Standard does not preclude
81 18 CFR 39.5(c)(2). information regarding regional the development of an appropriate level
82 Order No. 672 at P 291. See also ERO procedures on misoperations.85 The of uniformity on a nationwide basis.
Certification Order, 116 FERC ¶ 61,062 at P 274. Commission also directed NERC to
83 Protection systems are designed to detect and The Commission expects that all of the
isolate faulty elements on a system, thereby limiting
consider whether greater consistency regions, including WECC, will work
the severity and spread of system disturbances, and can be achieved as NERC modifies PRC– together to develop greater uniformity
preventing possible damage to protected elements. 003–1 to provide the missing with regard to reporting procedures for
See Order No. 693 at P 1418. Protection systems information. Xcel asserts that
include protective relays, remedial action schemes misoperation of relays and remedial
(RAS), and special protection schemes.
Commission approval of WECC–PRC– action schemes.
84 In Order No. 693 at P 1460, the Commission STD–003–1 would allow WECC to side- 89. The Commission agrees with the
jlentini on PROD1PC65 with NOTICES

explained that, because NERC’s PRC–003–1 step the process directed by the shortcomings identified by NERC
requires the regions to establish procedures Commission to achieve greater regarding WECC–PRC–STD–003–1 and
regarding misoperations, and those regional uniformity with regard to NERC’s PRC–
procedures had not been submitted, the
86 Id.
Commission neither approved nor remanded the
Reliability Standard. 85 Id. at P 1460–61. 87 See Order No. 693 at P 1443–49.

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
33472 Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices

expects WECC in developing a limited to relays, monitoring equipment, regional Requirement corresponds more
permanent, replacement standard to and special protection systems. WECC closely to NERC Reliability Standard
address these shortcomings as it has explains that relevant users, owners and PRC–017–0 (Special Protection System
committed to do. In particular, we operators must comply with the Maintenance and Testing). It appears
believe that regional definitions should requirements of the NERC Reliability that the NERC Reliability Standard
conform to the definitions set forth in Standard. According to WECC, the includes slightly more specificity in that
the NERC glossary unless a specific proposed regional Reliability Standard it requires a special protection system
deviation has been justified. Likewise, goes further by requiring, for specified maintenance program to include, among
each Requirement should have a transmission paths, a highly detailed other things, batteries and instrument
corresponding Measure and, in this TMIP for all transmission and transformers, which are not specified in
case, vice versa. substation equipment components, WECC–PRC–STD–005–1. Because
including circuit breakers, relays, WECC’s regional Reliability Standards
5. WECC–PRC–STD–005–1
transformers, reactive devices, and are in addition to the NERC Reliability
(Transmission Maintenance)
transmission lines. It also requires Standards, we would expect the
90. Regional Reliability Standard applicable entities to maintain five years maintenance plans of applicable entities
WECC–PRC–STD–005–1 requires each of maintenance records to verify in the West to include these details
transmission owner and transmission compliance. identified in NERC Reliability Standard
operator of specified transmission paths 94. Xcel argues that WECC has failed PRC–017–0.
to perform maintenance and inspection to justify the need for this regional 98. The Commission agrees with
on those paths as described by its Reliability Standard based on physical NERC’s concerns regarding the format
Transmission Maintenance and differences in the bulk power system. and content of WECC–PRC–STD–005–1
Inspection Plan (TMIP). The regional and expects WECC, in developing a
Reliability Standard identifies specific Commission Determination permanent, replacement standard, to
contents that each applicable 95. The Commission approves address these concerns, including but
transmission owner and transmission regional Reliability Standard WECC– not limited to inclusion of all relevant
operator must include in its TMIP. For PRC–STD–005–1 as mandatory and documents.
example, a TMIP must include the enforceable in the Western
scheduled interval for time-based 6. WECC–TOP–STD–007–0 (Operating
Interconnection. As explained by
maintenance, describe maintenance and Transfer Capability)
WECC, the applicable users, owner and
inspection methods, provide relevant operators in the Western 99. Regional Reliability Standard
checklists or forms and provide criteria Interconnection must comply with WECC–TOP–STD–007–0 applies to
for assessing the condition of a facility. NERC’s PRC–003–1 and, in addition, the transmission operators of 40 specified
Each applicable entity must retain all regional Reliability Standard. transmission paths. The goal of this
pertinent maintenance and inspection Accordingly, the Commission finds that regional Reliability Standard is to
records for at least five years. Further, the regional Reliability Standard ensure that the operating transfer
each applicable entity must annually satisfies the statutory standard for capability limits requirements of the
certify to WECC staff that it has approval because it is more stringent Western Interconnection are not
developed, documented and than the corresponding NERC exceeded.89 It includes a Measure that
implemented a TMIP. Reliability Standard by requiring, for provides ‘‘actual power flow on all
91. WECC’s regional Reliability specified transmission paths, a highly transmission paths shall at no time
Standard corresponds to NERC detailed maintenance and inspection exceed the [operating transfer
Reliability Standard PRC–005–1 plan for all transmission and substation capability] for more than 20 minutes for
(Transmission and Generation equipment components. WECC–PRC– paths that are stability limited, or for
Protection System Maintenance and STD–005–1 imposes requirements well more than 30 minutes for paths that are
Testing), which requires transmission beyond the NERC Reliability Standards thermally limited.’’
owners, generator owners and and improves reliability because 100. The corresponding NERC
distribution providers that own disciplined maintenance on equipment Reliability Standard, TOP–007–0,
transmission protection systems to have such as transmission lines, circuit requires that violations of SOL and
a protection system maintenance and breakers, power transformers and IROL be promptly reported to the
testing program for protection systems reliability coordinator so that it can
regulators will help prevent failures
that affect the reliability of the bulk direct corrective action and inform other
during operation.
electric system. 96. Moreover, WECC in its comments affected systems. It also requires a
92. NERC approved WECC–PRC– provided a persuasive need for the transmission operator to mitigate an
STD–005–1 with the condition that regional Reliability Standard as well as IROL violation as soon as possible but
WECC meet its commitment to address a demonstration that the regional no longer than 30 minutes. In Order No.
identified shortcomings. With regard to Reliability Standard is more stringent 693, the Commission approved TOP–
WECC–PRC–STD–005–1, NERC than the corresponding NERC standard. 007–0 as mandatory and enforceable.90
identified various formatting concerns 101. NERC approved WECC–TOP–
Thus, we reject Xcel’s protest on this
including the need to specify individual STD–007–0 with the condition that
issue.
requirements instead of one formal 97. Requirement WR1.b(i)(a)(2) of the
abnormal or predetermined system conditions, and
requirement with multiple subparts regional Reliability Standard requires take corrective actions * * *’’).
(including statements and comments the TMIP to describe the maintenance 89 Requirement WR1 of WECC–TOP–STD–007–0
that do not read as requirements). practices for station equipment defines ‘‘capability limits requirements’’ as the
including remedial action scheme (RAS) maximum amount of actual power that can be
jlentini on PROD1PC65 with NOTICES

Comments transferred over direct or parallel transmission


systems, which are also referred to as elements comprising: An interconnection from one
93. WECC states that the ‘‘special protection systems.’’ 88 This transmission operator area to another, or a
corresponding NERC Reliability transmission path within a transmission operator
Standard, PRC–005–1, requires a 88 See NERC glossary at 16 (defining both terms area.
maintenance and inspection plan as ‘‘an automatic protection system to detect 90 Order No. 693 at P 1674.

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices 33473

WECC meet its commitment to address IRO–005–1 could be interpreted as results in the power system being
identified shortcomings, including allowing a system operator to respect operated one contingency away from a
formatting concerns and inconsistency IROLs in one of two ways: (1) Allowing cascading outage.
between the NERC and WECC definition IROL to be exceeded during normal 108. Thus, it is possible to understand
of the term ‘‘disturbance.’’ operations, i.e., prior to a contingency, the WECC Measure as less stringent
provided that corrective actions are than NERC’s IRO–005–1, if the latter is
Comments interpreted conservatively. While the
taken within 30 minutes; or (2) allowing
102. WECC comments that NERC IROL to be exceeded only after a Commission has stated that a
Reliability Standard TOP–007–0 contingency and subsequently returning Requirement of a Reliability Standard
requires transmission operators to the system to a secure condition as soon sets forth the obligations of the
return the system to within IROL limits as possible, but no longer than 30 applicable users, owners and
for each incident in which an IROL is minutes.92 The Commission explained operators,94 the Commission is
exceeded. While transmission operators that the system could be one concerned regarding the circumstances
in the Western Interconnection must contingency away from potential under which WECC–TOP–STD–007–0
comply with the NERC requirement, cascading failure if operated under the would be implemented and the amount
WECC–TOP–STD–007–0 ‘‘goes further first interpretation and two of time an entity is allowed to be in
in limiting the time period of an contingencies away from cascading violation of an IROL without the
Operational Transfer Capability (which failure under the second interpretation. possibility of being found in non-
is more conservative than an IROL) The Commission directed NERC to compliance. Accordingly, the
exceedance to no more than 20 minutes conduct a survey on IROL practices and Commission directs NERC to submit a
when the limit is based on potential actual operating experiences of filing within 30 days of the date of this
voltage or transient stability.’’ 91 WECC managing within IROL. The survey order explaining whether Requirement
explains that the 20-minute limit was results will provide guidance on the WR1.b is consistent with the second
developed after two major disturbances frequency, duration and magnitude of interpretation of IRO–005–1 (two
in 1996 that caused the system to break IROL violations and whether these IROL contingencies away from cascading
up rapidly. WECC also states that the violations occur during normal or failure).95
regional Reliability Standard applies to contingency conditions. 109. Moreover, Measure WM1 of
40 clearly defined transmission paths, 106. With regard to WECC–TOP– WECC–TOP–STD–007–0, which sets
many of which would not be defined by STD–007–0, Requirement WR1.b. forth the 20 and 30 minutes time limits
NERC as having IROL requirements. provides that ‘‘[t]he interconnected for exceeding operating transfer
103. Xcel protests that no technical capability, states responsibilities of
power system shall remain stable upon
justification has been provided for applicable entities and, thus, is more
loss of any one single element without
WECC–TOP–STD–007–0. appropriately a requirement than a
system cascading that could result in
Commission Determination the successive loss of additional Measure. Accordingly, pursuant to
elements.’’ This Requirement suggests section 215(d)(5) of the FPA and section
104. The Commission approves 39.5(f) of the Commission’s regulations,
WECC–TOP–STD–007–0 as mandatory that WECC expects that IROLs will be
addressed in such a manner that the we direct that WECC in developing a
and enforceable in the Western permanent, replacement regional
Interconnection. WECC has provided an system is two contingencies away from
a cascading failure, which is consistent Reliability Standard: (1) Clarify any
adequate explanation of the need for inconsistency between the Requirement
this regional Reliability Standard and with the more conservative
interpretation of the NERC Reliability WR1.b and corresponding Measure
also adequately explained how the WM1; and (2) ensure that the
Requirements are more stringent than Standard IRO–005–1.93
107. However, Measure WM1 of requirements currently set forth in
the Requirements of the corresponding Measures WM1 are set forth in the
NERC Reliability Standard. In WECC–TOP–STD–007–0 may not be
consistent with Requirement WR1.b Requirements and that corresponding
particular, the imposition of a 20- Measures simply quantify the
minute limit is more restrictive than since it states ‘‘[a]ctual power flow on
all transmission paths shall at no time frequency, duration and magnitude of
NERC’s TOP–007–0 and is a prudent the violations as determined by the
means of limiting the risk of blackouts, exceed the OTC for more than 20
minutes for paths that are stability Requirements.
consistent with sound engineering 110. In addition, we expect that
principles. Thus, we disagree with Xcel limited, or more than 30 minutes for
WECC will address the shortcomings
that WECC–TOP–STD–007–0 has not paths that are thermally limited.’’ This
identified by NERC in developing a
been adequately justified. Measure is more consistent with the
permanent, replacement regional
105. The Commission is concerned first interpretation of NERC Reliability
Reliability Standard.
regarding a possible inconsistency Standard IRO–005–1. Simply put, it
within WECC–TOP–STD–007–0. As could be interpreted that WECC 7. WECC–VAR–STD–002a–1 (Automatic
background, NERC Reliability Standard Requirement WR1.b results in the power Voltage Regulators)
IRO–005–1 (Reliability Coordination— system being operated two 111. Regional Reliability Standard
Current Day Operations) provides, inter contingencies away from a cascading WECC-VAR-STD–002a–1 applies to
alia, that ‘‘if a potential or actual IROL outage while WECC Measure WM1 generator operators of synchronous
violation cannot be avoided through generating units equipped with
92 See Order No. 693 at P 945–51 and n.303.
proactive intervention, the Reliability 93 In
Automatic Voltage Regulators in the
addition to requiring the system to be
Coordinator shall initiate control actions operated to withstand the loss of a single element,
or emergency procedures to relieve the WECC–TOP–STD–007–0 requires operators to take 94 Id.at P 1929.
jlentini on PROD1PC65 with NOTICES

violation without delay, and no longer into consideration single events that might cause 95 IfWECC construes Requirement WR1.b as
than 30 minutes.’’ In Order No. 693, the the loss of multiple elements. See NERC Filing, consistent with the first interpretation of IRO–005–
WECC–TOP–STD–007–0 § B(b). In Order No. 693, 1, we will consider whether modifications are
Commission expressed concern that we addressed element- versus event-based necessary to protect the reliability of the Bulk
contingencies. See Order No. 693 at P 1604, 1715– Power System upon consideration of the survey
91 WECC Comments at 12. 1719. results noted above.

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00029 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
33474 Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices

Western Interconnection.96 The stated 002a–1 as mandatory and enforceable in Commission Determination
purpose of the regional Reliability the Western Interconnection. The 122. The Commission approves
Standard is to ensure that automatic Commission agrees with WECC that this WECC–VAR–STD–002b–1 as mandatory
voltage control equipment on regional Reliability Standard is more and enforceable in the Western
synchronous generators shall be kept in stringent than the related NERC
Interconnection. The regional Reliability
service at all times, except in specified Reliability Standard. WECC–VAR–STD–
Standard is justified as it addresses
circumstances, and that outages of such 002a–1 requires all synchronous
matters that are not addressed by a
equipment must be coordinated. It generators to have their voltage
NERC Reliability Standard. Moreover,
requires that generator operators must regulator in service at all times with
WECC explains that the regional
normally operate automatic voltage only exceptions for specified
Reliability Standard is justified as a
control equipment in voltage control circumstances. The related NERC
means to avoid oscillations that
mode and set to respond effectively to Reliability Standard, VAR–002–1,
contributed to previous disturbances in
voltage deviations. permits a generator to remove its
the Western Interconnection.
112. Related NERC Reliability automatic voltage regulator from service
for additional reasons. The regional 123. We reject Xcel’s protest since the
Standard VAR–002–1 (Generator
standard is appropriate to avoid the root term ‘‘power system stabilizer’’ is
Operation for Maintaining Network
causes of prior disturbances in the generally understood as described
Voltage Schedules) requires generator
Western Interconnection. We reject above, and Xcel has not provided any
operators to operate each generator
Xcel’s protest as WECC has adequately explanation why the regional Reliability
connected to the interconnected
justified the need for this regional Standard is deficient without a formal
transmission grid in the automatic
Reliability Standard. definition. Finally, as with the other
voltage control mode unless the
117. As with the other regional regional standards, we expect WECC to
generator operator has notified the
Reliability Standards, we expect that address the shortcomings identified by
transmission operator.97 Unless
WECC, in developing a permanent, NERC when developing a permanent,
exempted by the transmission operator,
replacement standard, will address the replacement standard.
the generator operator must maintain
voltage or reactive power output as shortcomings identified by NERC D. Effective Date
directed by the transmission operator. regarding WECC–VAR–STD–002a–1.
124. As requested by NERC and
113. NERC approved WECC–VAR– 8. WECC–VAR–STD–002b–1 (Power WECC, the proposed regional Reliability
STD–002a–1 with the condition that System Stabilizers) Standards shall take effect on June 18,
WECC meet its commitment to address
118. Regional Reliability Standard 2007 to coincide with the effective date
identified format-related shortcomings.
WECC–VAR–STD–002b–1 applies to of the Reliability Standards that were
Comments generator operators with generators approved in Order No. 693.
114. WECC comments that, in equipped with power system stabilizers. E. Information Collection Statement
addition to compliance with the related A power system stabilizer is part of the
NERC Reliability Standard, the WECC excitation control system of a generator 125. The Office of Management and
regional Reliability Standard requires used to increase power transfer levels by Budget (OMB) regulations require
automatic voltage regulators to be in improving power system dynamic approval of certain information
service and in voltage control mode performance. It requires that power collection requirements imposed by
with very limited exceptions. WECC system stabilizers on generators must be agency rules.98 Upon approval of a
explains that it instituted this kept in service at all times, except in collection(s) of information, OMB will
requirement after a 1996 disturbance, specified circumstances, and that the assign an OMB control number and an
which was caused by insufficient power system stabilizers must be expiration date. Respondents subject to
supply of reactive power from ‘‘properly tuned’’ in accordance with the filing requirements of an agency rule
generators, including automatic voltage WECC requirements. This standard does will not be penalized for failing to
regulators that were not operating in not have a corresponding NERC respond to these collections of
voltage control mode. As a result of this Reliability Standard. information unless the collections of
experience, WECC determined that 119. NERC approved WECC–VAR– information display a valid OMB
there should be only very limited STD–002b–1 and identified several control number. The Paperwork
circumstances where a generator should format-related shortcomings for WECC Reduction Act (PRA) 99 requires each
remove its unit from AVR operation. to address. federal agency to seek and obtain OMB
115. Xcel asserts that WECC has not approval before undertaking a collection
Comments of information directed to ten or more
provided any technical justification for
the regional Reliability Standard. 120. WECC states that WECC–VAR– persons, or continuing a collection for
STD–002b-1 requires generator which OMB approval and validity of the
Commission Determination operators to always have power system control number are about to expire.100
116. The Commission approves stabilizers in service with very limited 126. This order approves eight
Reliability Standard WECC–VAR–STD– exceptions. It explains that this regional Reliability Standards that were
requirement was developed after the submitted by NERC as the ERO. Section
96 An ‘‘automatic voltage regulator’’ is a device August 1996 disturbance in the Western 215 of the FPA authorizes the ERO to
that continuously monitors the generator terminal Interconnection in which oscillations submit Reliability Standards to provide
voltage and changes the reactive power output as
required to maintain (or regulate) the voltage within
that could possibly have been for the Reliable Operation of the Bulk-
a pre-determined voltage range. For example, if a attenuated by power system stabilizers Power System. Pursuant to the statute,
load increase causes a decline in system voltages were a factor. the ERO must submit each Reliability
jlentini on PROD1PC65 with NOTICES

and thereby the terminal voltage of a generator, the 121. Xcel states the proposed standard Standard that it proposes to be made
automatic voltage regulator will increase the is deficient because it does not define
generator’s reactive output to raise the terminal
voltage. ‘‘power system stabilizers’’ and because 98 5 CFR 1320.8 (2005).
97 In Order No. 693 at P 1884, the Commission WECC has not provided a technical 99 44 U.S.C. 3501–3520.
approved VAR–002–1. justification for the standard. 100 44 U.S.C. 3502(3)(A)(i), 44 U.S.C. 3507(a)(3).

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00030 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices 33475

effective to the Commission for retention of maintenance and inspection use of automated information
approval.101 records for five years and retention of techniques.
127. The eight proposed Reliability other data for four years. 130. Our Estimates below are based
Standards do not require responsible 128. We do not believe our approval on the total reporting burdens that arise
entities to file information with the of the WECC Regional Reliability under the approved standards,
Standards will result in a significant including reporting burdens that were
Commission. However, the standards do
increase in reporting burdens as already in place under WECC practices.
require responsible entities to file
compared to current practices in WECC. Thus, the Estimates exceed the
periodic reports with WECC and to
As NERC and WECC explain, the eight incremental burdens that result from
develop and maintain certain
Regional Reliability Standards are our approval of the standards. The
information for a specified period of
translations of existing WECC criteria Estimates are based on the NERC
time, subject to inspection by WECC.
pursuant to its RMS program. The eight compliance registry as of April 2007.
WECC–BAL–STD–002–0 requires
proposed standards: (1) Reflect practices For the Western Interconnection that is
balancing authorities and reserve
that are currently in place on a overseen by WECC, NERC and WECC
sharing groups to submit to WECC
contractual or voluntary basis; (2) have identified approximately 30
quarterly reports on operating reserves represent discrete differences from
as well as reports after any instance of balancing authorities, 146 generator
nation-wide, mandatory Reliability operators, 104 load-serving entities, 41
non-compliance. WECC–IRO–STD–006– Standards that will take effect on June
0 requires transmission operators, transmission operators, and 66
18, 2007; and (3) will be replaced by transmission owners * * * While NERC
balancing authorities and load-serving permanent standards developed by
entities to document and report to has registered 104 load-serving entities
WECC. Moreover, with only limited in the U.S. portion of WECC, we believe
WECC actions taken in response to exceptions, the reporting requirements
direction to mitigate unscheduled flow. that only 50 load-serving entities will be
in the regional Reliability Standards affected by the reporting requirements
The standard also requires transmission apply to large entities that have been
operators to document required actions that apply to load-serving entities
complying with those standards for (under WECC–IRO–STD–006–0)
that are and are not taken by responsible several years. The only possible
entities. WECC–PRC–STD–001 requires because those requirements apply only
exception is WECC–IRO–STD–006–0, in relation to ‘‘qualified transfer paths’’
certain transmission operators to submit which requires applicable entities to
to WECC annual certifications of and because the number of such paths
comply with transmission operators’
protective equipment. WECC–PRC– are limited. Similarly, although NERC
directions to reduce unscheduled flows.
STD–003–1 requires certain has registered 41 transmission operators
Our approval of this regional Reliability
transmission operators to report to and 66 transmission owners in the U.S.
Standard might result in reporting
WECC any misoperation of relays and portion of WECC, we believe only the 14
requirements for load-serving entities
remedial action schemes. WECC–PRC– transmission operators and owners that
that did not previously comply with
STD–005–1 requires certain operate 40 designated paths will be
WECC practices in this regard. We do
transmission operators to maintain, in affected by reporting requirements
not believe that the associated reporting
stated form, maintenance and under this order. We note that some
requirement is significant. Under
inspection records pertaining to their transmission operators operate up to
WECC–IRO–STD–006–0, applicable
transmission facilities. The standard entities must document and report to seven paths. This has been taken into
also requires operators to certify to WECC actions that those entities take in account in our estimate in the line
WECC that the operator is maintaining response to direction to reduce ‘‘Transmission Operators/Owners’’ in
the required records. WECC–TOP–STD– unscheduled flow. We do not expect the table below.
007–0 requires certain transmission that the number of occurrences or 131. NERC’s compliance registry
operators to submit to WECC quarterly nature of the documentation will result indicates that there is a significant
reports on transfer capability data and in significant reporting burdens. amount of overlap among the entities
compliance as well as reports after an 129. The Commission is submitting that perform these functions. In some
instance of non-compliance. WECC– these reporting requirements to OMB for instances, a single entity may be
VAR–STD–002a–1 and WECC–VAR– its review and approval under section registered under all four of these
STD–002b–1 require certain generators 3507(d) of the Paperwork Reduction functions. Thus, the Commission
to submit quarterly reports to WECC on Act. Comments are solicited on the estimates that the total number of
automatic voltage control and power Commission’s need for this information, entities required to comply with the
system stabilizers. All of the foregoing whether the information will have information ‘‘reporting’’ or development
regional Reliability Standards require practical utility, the accuracy of requirements of the proposed Reliability
the reporting entity to retain relevant provided burden estimates, ways to Standards is approximately 180–200
data in electronic form for one year or enhance the quality, utility, and clarity entities.
for a longer period if the data is relevant of the information to be collected, and Burden Estimate: The Public
to a dispute or potential penalty, except any suggested methods for minimizing Reporting burden for the requirements
that WECC–PRC–STD–005–1 requires the respondent’s burden, including the in the present order is as follows:

Number of Number of Hours per Total annual


Data collection respondents responses response hours

FERC–XXX:
Balancing Authorities ................................................................................ 30 1 20 600
Generator Operators ................................................................................ 146 1 10 1460
jlentini on PROD1PC65 with NOTICES

Load-Serving Entities ............................................................................... 50 1 10 500


Transmission Operators/Owners .............................................................. 14 1–7 each (total 40 1600
of 40)

101 See 16 U.S.C. 824(d).

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1
33476 Federal Register / Vol. 72, No. 116 / Monday, June 18, 2007 / Notices

Number of Number of Hours per Total annual


Data collection respondents responses response hours

Recordkeeping:
Balancing Authorities ................................................................................ ........................ ........................ 60 60
Generator Operators ................................................................................ ........................ ........................ 146 146
Load-Serving Entities ............................................................................... ........................ ........................ 50 50
Transmission Operators/Owners .............................................................. ........................ ........................ 160 160

Totals ................................................................................................. ........................ ........................ ........................ 416

(FTE = Full Time Equivalent or 2,080 8415, fax: (202) 273–0873, e-mail: (C) WECC is directed to develop, for
hours) michael.miller@ferc.gov]. Comments on each of its regional Reliability
Total Annual Hours for Collection: the requirements of this order may also Standards, sanctions that follow NERC
4,160 reporting + 416 recordkeeping = be sent to the Office of Information and guidelines as discussed in the body of
4,576 hours. Regulatory Affairs, Office of this order.
Information Collection Costs: The Management and Budget, Washington, (D) WECC is directed to develop
Commission seeks comments on the DC 20503 [Attention: Desk Officer for modifications to regional Reliability
costs to comply with these the Federal Energy Regulatory Standards WECC–IRO–STD–006–0 and
requirements. It has projected the Commission], e-mail: WECC–TOP–STD–007–0 through its
average annualized cost to be $515,840 oira_submission@omb.eop.gov. Reliability Standards development
as shown below: process when developing permanent,
F. Regulatory Flexibility Act
Reporting = 4,160 hours @ $120/hour replacement standards.
Certification
= $499,200. By the Commission.
Recordkeeping = 416 hours @ $40/ 133. The Regulatory Flexibility Act of Kimberly D. Bose,
hour = $16,640. 1980 (RFA) 102 generally requires a
Secretary.
Total Costs = Reporting ($499,200) + description and analysis of rules that
[FR Doc. E7–11685 Filed 6–15–07; 8:45 am]
Recordkeeping ($16,640) = $515,840. will have significant economic impact
BILLING CODE 6717–01–P
Title: FERC–725E Regional Reliability on a substantial number of small
Standards (WECC). entities. As indicated above, based on
Action: Proposed Collection of available information regarding NERC’s
DEPARTMENT OF ENERGY
Information. compliance registry, approximately
OMB Control No.: To be determined. 180–200 entities will be responsible for Federal Energy Regulatory
Respondents: Business or other for compliance with the eight regional Commission
profit, and/or not for profit institutions. Reliability Standards. Most of those
Frequency of Responses: Periodic and entities, i.e., balancing authorities, [Docket No. CP06–89–002]
intermittent. generator operators, transmission
Necessity of the Information: The Northern Natural Gas Company; Notice
owners and operators, do not fall within
eight Reliability Standards would of Compliance Filing
the definition of small entities.103 About
implement the Congressional mandate one-fifth of the approximately 50 load- June 11, 2007.
of the Energy Policy Act of 2005 to serving entities that are subject to the Take notice that on June 1, 2007,
develop mandatory and enforceable approved standards might qualify as Northern Natural Gas Company
Reliability Standards to better ensure small entities. (Northern) tendered for filing in its
the reliability of the nation’s Bulk- 134. Based on this understanding, the FERC Gas Tariff, Fifth Revised Volume
Power System. Commission certifies that the approved No. 1, the following tariff sheets, to be
Internal Review: The Commission has standards will not have a significant effective August 1, 2007:
reviewed the requirements pertaining to economic impact on a substantial
mandatory Reliability Standards for the Tenth Revised Sheet No. 1
number of small entities. Accordingly, 13 Revised Sheet No. 2 75
Bulk-Power System and determined the no regulatory flexibility analysis is Revised Sheet No. 53
proposed requirements are necessary to required. Original Sheet No. 165
meet the statutory provisions of the The Commission orders: Original Sheet No. 166
Energy Policy Act of 2005. These Original Sheet No. 167
(A) The proposed regional Reliability
requirements conform to the Sheet No. 168
Standards are hereby approved, as
Commission’s plan for efficient First Revised Fifth Revised Sheet No. 403
discussed in the body of this order. First Revised Fifth Revised Sheet No. 403A
information collection, communication
and management within the energy (B) NERC is directed to submit a Second Revised Sheet No. 461
industry. The Commission has assured compliance filing within 30 days of this First Revised Sheet No. 462
itself, by means of internal review, that order, as discussed in the body of this Northern states that the above sheets
there is specific, objective support for order. are being filed to comply with
the burden estimates associated with the Commission requirements issued in its
102 5U.S.C. 601–612.
information requirements. 103 The
April 10, 2007 order in Docket Nos.
RFA definition of ‘‘small entity’’ refers to
132. Interested persons may obtain the definition provided in the Small Business Act,
CP06–89 et al. related to the
information on the reporting which defines a ‘‘small business concern’’ as a abandonment by sale of the West
jlentini on PROD1PC65 with NOTICES

requirements by contacting: Federal business that is independently owned and operated Hugoton facilities.
Energy Regulatory Commission, 888 and that is not dominant in its field of operation. Any person desiring to protest this
See 15 U.S.C. 632 (2000). According to the SBA, a
First Street, NE., Washington, DC 20426 small electric utility is defined as one that has a
filing must file in accordance with Rule
[Attention: Michael Miller, Office of the total electric output of less than four million MWh 211 of the Commission’s Rules of
Executive Director, Phone: (202) 502– in the preceding year. Practice and Procedure (18 CFR

VerDate Aug<31>2005 18:19 Jun 15, 2007 Jkt 211001 PO 00000 Frm 00032 Fmt 4703 Sfmt 4703 E:\FR\FM\18JNN1.SGM 18JNN1

You might also like