You are on page 1of 15

Collection Systems 2004:

Innovative Approaches to Collection Systems Management

RISK MANAGEMENT FOR MICROTUNNELED SEWERS


Steven W. Hunt, P.E.
MWH
115 S. 84th Street, Suite 350
Milwaukee, WI 53150
ABSTRACT
An increased desire to specify trenchless construction methods to minimize public and utility impacts
along with more contractor capability and competition have resulted in more use of microtunneling for
new sewer construction. In some localities with favorable ground and site conditions, microtunnel
construction has become fairly routine with few significant problems and claims. However in many
ground conditions, a routine approach to subsurface investigation and preparation of a geotechnical
report and specifications can result in significant risks and costly consequences. Owners and
consultants can significantly reduce the risks and consequences of problems on microtunnel projects by
following a more careful, focused subsurface risk management approach.
KEYWORDS
Risk management, subsurface investigation, geotechnical reports, microtunneling
INTRODUCTION
Managing risk for projects involving microtunneling of sewers has received considerable attention
resulting in many papers and some guidelines. This paper is not a complete overview of risk
management approaches for microtunneling, but instead focuses on several key elements involving
characterization of ground conditions desk studies, phased subsurface investigations and geotechnical
report preparation.
Inherent Ground Risk
All parties to sewer construction by microtunneling, including owners, designers, geotechnical firms,
construction managers, contractors and insurers, should never forget that the ground is inherently
variable, uncertain and thus risky. Natural ground was formed by variable and potentially complicated
processes that may not be easily interpreted. Activities of man tend to further complicate underground
conditions. Ground conditions for microtunneling may vary from reasonably predictable to very
complicated and unpredictable. Legget (1979) in his Terzaghi lecture reminded us that:
There can never be any certainty about geological conditions between adjacent boreholes, even
5 ft apart, until the excavation has actually opened up the ground.

In order to reduce uncertainties, designers and geotechnical firms strive to complete thorough subsurface
investigation programs. Owners are tempted to believe that once they have paid to have a reputable firm
complete a reasonable subsurface investigation program, the risk of encountering differening site
conditions (DSCs) and receiving DSC claims is essentially eliminated. Designers and geotechnical firms
often do not explain that significant risks of encountering DSCs remain even after completing an
appropriate subsurface investigation program. Gould, 1995 in his Terzaghi lecture emphasized that the
risk of encountering a DSC cannot be eliminated:

Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

Surprises are inevitable - there will always be unexpected ground conditions and neither the
owner nor the design team can completely eliminate surprises from complex underground
projects.

Ron Heuer, a well-known tunneling specialist, responded to Goulds Terzaghi lecture with the following
comments (Heuer, 1997):
Next, we must understand that it will never be possible to eliminate all encounters of unexpected
conditions when we make underground excavations. We can send an individual to the moon and
back, but we cannot reliably predict all details of the ground beneath or feet we have never
been able to do so and we never will, since geologic conditions are infinitely variable, with too
many features that are unknowable prior to construction. Engineers must accept this basic truth,
and owners must be made to understand it. Engineers should not suggest otherwise to owners.

Ownership of the Ground


Owners should also recognize that they ultimately own or are responsible for the ground that
microtunnels are constructed in. Attempts to transfer all the risk of unexpected ground conditions to the
contractor have often been unacceptable and not cost effective (USNCTT, 1984; Hafer, 2000).
Managing subsurface uncertainties for microtunneling projects becomes more equitable and less
divisive once owners accept that ground risk mostly belongs to them.
While uncertainty is an unavoidable risk when microtunneling, most subsurface uncertainties and risks
can be assessed and mitigated to minimize potential consequences. A focused, thorough geotechnical
desk study, thorough subsurface investigation program and experienced data interpretation are key
elements of subsurface risk minimization.
Tunnel Project Risk Management
Risk management is very important for controlling risks and maximizing chances for success of
microtunneling projects. Abbott (2004) provides a well-written overview of this topic. Additional
references that discuss risk management for microtunneling and tunneling include: Anderson (1998),
Hinze & McClelland (1997), Richards (1999), Salem & Hegab (2001), Sangster (2003), and Westland et
al (1998). Perhaps the most elaborate guideline on risk management for tunneling projects is a recently
completed British code entitled The Joint Code of Practice for Risk Management of Tunnel Works in the
UK (British Tunnelling Society, 2003). Both the British Tunnelling Society and Association of British
Insurers prepared this guideline. Dix (2004) provides an overview of the code and discusses its
implications. The code is intended to make thorough, comprehensive risk management a requirement
from planning through design and construction in order to control risks and result in more insurable
projects. While this approach has not taken root in the United States yet, elements of it may be coming.
In any case, the code shows what thorough risk management might entail.
PRACTICES AFFECTING SUBSURFACE RISK MANAGEMENT
Many microtunneling problems and claims result from poor desk study, subsurface investigation and
geotechnical report practices during planning and final design. The following paragraphs describe some
poor geotechnical practices and example case history consequences.
Lack of an environmental desk study.
A Phase I Environmental Site Assessment (ESA) should be completed for every tunnel project. A tunnel
Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

project in the Midwest included a thorough geotechnical subsurface investigation, but no Phase I ESA.
The geotechnical firm did not offer environmental services and had a we dont do it attitude. During
construction, the owner was contacted by the owner of a landfill located near the end of the tunnel
alignment and told that the contractors shaft and tunnel dewatering wells were causing leachate that had
leaked from the landfill to migrate further from the spill zone and towards the tunnel. Tunneling was
promptly stopped and the wells were deactivated. Completion of the tunnel without dewatering required
the use of ground freezing for the remaining shafts and compressed air for the tunnel. The consequences
were over six months in delay and $1 million in additional costs.
Poor communication of desk study findings.
Sometimes valuable information obtained during a planning-preliminary engineering phase desk study
is not properly communicated to the final design team allowing it to fall through the cracks. This
happened on a major sewer project near downtown of an urban area. The preliminary engineering team
completed a thorough desk study that obtained records on previous site use and early 1960s
construction of a 20-story building along the alignment. These records showed that the street was
previously narrower and that the new building was built over a 1930s vintage concrete pile supported
building that had been abandoned except for its basement. The records also showed that a soldier pile
and lagging cofferdam was used to support the 1960s
construction excavation.
Figure 1 H Pile Obstructions
The preliminary engineering firm sent this
information to the finally designer but failed to list the
information in a risk register and warn the final
designer in the preliminary engineering report why
they placed the preliminary sewer alignment on the
other side of the street. The final designer moved the
alignment and neither the preliminary engineering
firm nor owners staff that performed design reviews
recognized this change as a potential problem. During
construction, the microtunneling contractor began
encountering difficult obstructions. The resident
engineering staff investigated and found the
information from preliminary engineering showing
that the obstructions were steel soldier piles and that a
basement was also in the tunnel path. The contractor
was immediately notified and microtunneling was
stopped just 3 m short of mining into the basement
wall of the 1930s vintage building (Fig. 1). The
additional costs for delays, a recovery shaft, a realignment shaft and a different TBM were over
$800,000. The consequences would have been much worse had they mined into the basement of the
occupied building.
Inadequate subsurface investigation scope.
Budget concerns and lack of understanding of subsurface risk sometimes result in a grossly inadequate
subsurface investigation scope.

Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

One example of an inadequate subsurface investigation involved a pipeline project where only two
borings that extended to depths of 6.1 and 9.1 m (20 and 30 feet) for 490m (1600 feet) of pipeline to be
constructed at a depth of 9.1 (30 feet). Neither boring was converted to a piezometer. This pipeline
segment included a pump station, a levee undercrossing and a river intake. The two borings happened
to terminate in clay allowing the tunnel subcontractor to optimistically assume low permeability soil and
minimal shallow dewatering measures would be needed throughout most of the tunnel zone.
During construction, a thick stratum of high permeability sand that was directly connected to the river
was found just below the clay. A major dewatering well operation was needed to control water resulting
in over $500,000 in extra shaft and microtunnel construction costs. Upon questioning the manager of
the geotechnical firm that completed the investigation, he admitted that his firm did not know or ask
specifically why the borings were being drilled to the depths specified. Neither the geotechnical firm,
the construction manger, nor the microtunneling subcontractor had questioned the adequacy of the
subsurface investigation until construction problems developed.
Poor subsurface investigation monitoring.
Even if the subsurface investigation scope and budget are adequate for the phase being completed, poor
monitoring of the work and documentation of conditions observable in the field can result in an
investigation failure. A geotechnical firm that specialized in the competitive local foundation design
marketplace completed the borings for one sewer project. Due to habit and a low price bid for the work,
drillers were assigned to monitor the drilling, prepare field logs and select samples to be retained for
laboratory testing. No desk study or anticipated conditions memorandum was completed the firms
responsible geotechnical engineer to guide the drillers.
The ground at one tunnel shaft location was characterized in the geotechnical report by two nearby
boring logs as being a few feet of clean fill overlying native alluvial and glacial soils. One shallow fill
sample was described as having a slight chemical odor. During construction, the soil at the shaft and
boring location site was found to consist of deep (over 6m [20 feet]), biologically hazardous (anaerobic
preserved meat, bones and hides) and chemically hazardous (heavy metals, oil and solvents) fill
overlying less contaminated native soil. The fill was situated within an abandoned timber pile and
timber sheeted cofferdam that was previously a boat slip as indicated by readily available, but
overlooked, municipal outfall sewer records. A Phase I ESA had not been completed but available
records showed that the surrounding industries included tanneries and metal plating. Sufficient clues
existed to allow discover of the contamination during design had a properly managed and monitored
subsurface investigation been completed. Over
Figure 2 Boulder Obstruction of MTBM
$1 million in extra costs and six months in delay
were incurred to complete the shaft and tunnel
work in the contaminated ground with
abandoned dockwall obstructions.
Lack of geologic interpretation.
Some geotechnical engineers have not had
sufficient training in geology and lack sufficient
underground construction experience to
properly interpret subsurface data and predict
ground conditions such as boulders.

Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

Ground conditions for a sewer project along a ridge adjacent to a river valley within an upper
midwestern city was described as stiff glacial silty clay and dense silty sand and sand outwash. During
design, the geotechnical firm was asked to address the risk of encountering boulders. They responded
that no boulders were encountered during drilling and that the contractor might encounter a scattered
cobble or boulder during microtunneling.
During construction the ground was found to be cobbly and bouldery till, outwash and ice margin
deposits along a glacial end-moraine. The geotechnical firm had not assessed local geologic
publications indicating that cobbles and boulders were common and often large for the geologic units
encountered. The microtunnel boring machine (MTBM) selected by the contractor was not equipped to
handle frequent or large boulders. The cuttingwheel was badly damaged and the MTBM became stuck
twice on large boulders before it was finally removed from the project (Fig. 2). A different TBM and
dewatering method had to be mobilized to finish the project resulting in a delay of nearly 10 months and
over $3 million in additional costs.
Consequences not considered.
Recognizing a risk and determining chances of its occurrence is often not enough. The potential
consequences of the risk occurring should also be carefully considered.
A pipeline project in the Pacific Northwest required a river undercrossing. The location was an
environmentally sensitive area due to its trout and salmon fishery and adjacent eagle nesting. Borings
for the project indicated that cobbles and boulders were present. The geotechnical firm that prepared the
microtunnel specification and geotechnical baseline report expected cobbles and small boulders based
on frequent standard penetration test refusal blow counts and observations of drill rig chatter. However,
they did not think that large boulders were present because none of the borings required rock coring for
advancement.
The firm did not complete a desk study of available geological and tunnel case history papers. Had they
done so, they would have recognized that large boulders were common in similar geologic units in this
region and that a significant risk of encountering large boulders existed.
Furthermore, they did not consider that a recovery shaft would not be permitted if the MTBM became
stuck below the river on a large boulder or nest of
Figure 3 Abandoned MTBM Below River
cobbles and boulders. The specifications did not
require the MTBM to be capable of handling large
boulders nor have face access or other backup
River
systems to help ensure successful completion of
the drive. The MTBM became stuck below the
river (Fig. 3). The environmental permit did not
allow a recovery shaft and the machine was too far
Boulder Obstruction
into the drive for a rescue tunnel. The MTBM and
approximately 150 m (500 feet) of steel casing had
to be abandoned. The alignment was moved to
avoid the abandoned tunnel and a new launch shaft
had to be sunk. The contractor purchased a new,
more rugged MTBM and mobilized it to the site.

Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

The result was a one-year delay and over $3.5 million in additional costs.
Lack of Professional or Qualified Professional Interpretation of Subsurface and Site Data.
A thorough geotechnical subsurface investigation alone may not find readily discoverable ground or
groundwater contamination. A Phase I Environmental Site Assessment (ESA) should be completed for
every tunnel project. Where the Phase I ESA indicates that contaminated ground or groundwater is
likely, a Phase II ESA should be completed and the resulting environmental data should be interpreted
by a tunnel engineer that is experienced with management of hazardous gas and contaminated ground
risks.
A tunnel project in the Midwest included a thorough
Figure 4 Burned TBM Equipment
geotechnical subsurface investigation, but no Phase I ESA.
During tunneling, the construction manager was advised by
an outside party that a convenience store along the
alignment was formerly a gasoline service station that had
leaked. A quick check of regulatory agency records
revealed that it was a leaky underground storage tank
(LUST) site that was only partly remediated and was now
being monitored. The construction manager retained a local
environmental investigation and remediation design firm to
complete a subsurface investigation of the tunnel zone
adjacent to the LUST site before the TBM arrived. The
environmental firm approached the work in the manner they
were accustomed for remediation projects. They completed
six geo-probe borings and only those analytical laboratory
tests for normally needed to characterize carcinogenic
petroleum compound contamination for a remedial work
plan. They did not recognize that analysis of toxic and
explosion hazards for tunneling work required
determination of petroleum compounds present and total
petroleum hydrocarbon concentrations in the tunnel zone.
The contractor was told to expect slight gasoline contamination within approximately 100m of tunnel
zone and that special disposal of the muck and pumped water from this zone would be required. They
indicated that only a slight modification of the health and safety plan to avoid skin contact was required
and did not address the risk of toxic and explosion hazards to the miners.
Upon tunneling into the contamination zone, the miners immediately suffered ill effects of a toxic
atmosphere. Eventually the TBM encountered a granite boulder that created a spark when struck by
drag cutters that set off an explosion that burned four miners (Fig. 4). Completion of the tunnel was
delayed over a year and incurred nearly $5 million in additional costs. In addition, the environmental
firm, designer, owner and contractor were sued for negligence by some of the injured miners.
DESK STUDIES
A thorough geotechnical desk study is one of the most underutilized tools for reducing microtunneling
risks. In many cases a desk study is not completed or is not sufficiently thorough. Desk study costs are
generally very small compared to their potential benefit for reducing risks and construction costs.
Owners should recognize that they have an obligation to not withhold pertinent subsurface information

Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

that may be in their files from previous studies or construction. If discovered after bidding in
conjunction with microtunneling impacts, a contractor may have merit to a claim of undisclosed
superior knowledge (USNCTT, 1984).
Geotechnical desk studies involve a process of collecting and evaluating available previous information
including but not limited to:

Subsurface conditions (ground, groundwater, gas, contamination, utilities, foundations, wells,


abandoned ground support systems, etc).

Sewer facility conditions (structural conditions, sewer leaks, sediment contamination, original
design and construction records).

Site conditions (adjacent structure and building conditions, exposed ground conditions, wetland
constraints, petroleum station locations, site access constraints, overhead interferences, etc).

Previous shaft and tunnel construction experience in the region (methods used, problems
encountered, productivity, cost, adjacent property impacts, etc.)

Desk study information may be found in the archived files, published documents, conference
proceedings and websites of the following organizations:

Owners (geotechnical reports, preliminary reports, basis of design reports, contract documents, and
construction inspection records and claims files from previous projects often contain valuable
information.

Engineers (design, geotechnical and supporting specialty firms often have pertinent information
from projects that may not have involved the owner but that can be shared).

Public agencies (library, city, county, state, federal, and regulatory agency historical information on
previous site use, landform alteration, existing building and foundation design files, utilities,
geotechnical reports, ground and groundwater contamination, water quality and water supply well
records, etc.)

Utilities (abandoned and existing utility locations; types and construction methods used; boring logs
and geotechnical reports)

Adjacent property owners (building and foundation design files, geotechnical reports, construction
reports, building performance problems, vibration and settlement sensitivity, previous site use, etc).

Design, construction and manufacturing organizations (articles, published papers, bulletins,


conference proceedings, manuals, guidelines, etc).

Universities (published research and study results involving ground, groundwater, geology, land use,
facility performance, etc).

SUBSURFACE INVESTIGATION
Subsurface Investigation Cost
Some owners may question the value of money spent on a thorough subsurface investigation if a risk of
differing site condition (DSC) claims remains. Studies have shown that an inadequate subsurface
investigation generally results in a higher risk of microtunneling problems and claims, while an
excessive subsurface investigation may not add much additional value. In order to provide a guideline
on what amount of subsurface investigation should generally be cost effective and beneficial at reducing

Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

risk, a committee of interested parties to the tunneling industry studied over 100 tunnel case histories
(U.S. National Committee on Tunneling Technology, 1984). The Committee recommended that total
expenditure for all phases of subsurface investigation and data reporting for tunneling projects should
generally range from 1 to 3 percent of the estimated construction cost with the lowest expenditures
where the geology is less erratic and complex or where consequences of poor behavior are least. Table
1 summarizes the subsurface expenditure recommendations made by various committees and authors.
Table 1 Subsurface Investigation Cost Guideline
Source / Reference

Recommended Percentage of Total Project


Cost*
Golder Associates & James F. MacLaren, Ltd (1976)
1 to 3% (6% if complex)
West et al. (1981)
0.5 to 3%
USNCTT (1984)
1% min, 3% average
Legget & Hatheway (1988)
0.3 to 2%
Sauer (1997)
3 to 4% normal in Europe
Essex (1993)
3 to 5% (8% if complex)
*Not including cost for tunnel engineering and geotechnical baseline report preparation.
Allocating sufficient funds and retaining a geotechnical firm to a complete subsurface investigation is
not adequate to satisfactory reduce tunneling risks. A geotechnical firm experienced with tunnel design
and construction should be retained to direct and manage the subsurface investigation and then complete
the data analyses and geotechnical report preparation. Unsatisfactory results may occur if a
geotechnical firm that has inadequate tunnel experienced is retained.
Subsurface Investigation Phasing
In general, subsurface investigations for microtunnel projects should be phased rather than completed
under a single investigation. While it may be contractually convenient to have only a single phase, more
valuable information for the expenditure results from a phased approach. Phasing provides better results
for three primary reasons:
1. Some subsurface data should be utilized during planning and alternatives assessments prior to
the final design phase to help ensure that microtunnel constructability assessments, risks and
preliminary cost estimates are based on reliable limited knowledge of ground and groundwater
conditions.
2. Phasing allows each subsequent phase to be focused on reducing remaining uncertainties and
risks from previous phases. With a single phase, boring locations, boring depths, piezometer
locations, field and laboratory testing scope, and need for geophysical or alternative exploration
methods must be made based on many ground, groundwater, sewer diameter, alignment and
grade assumptions which may not be correct.
3. Phasing allows later phase borings to be completed at the most strategic locations after
adjustments in alignment and shaft locations are made.
The initial phase subsurface investigation should not be scoped or initiated until after a geotechnical
desk study has been completed. Once the available subsurface information is collected and evaluated, a
viable prediction of anticipated ground conditions and likely microtunnel risks can be made based on
sound geologic principles. The scope of the initial phase subsurface investigation can then be developed
to verify the anticipated conditions and reduce critical uncertainties. The result should be more valuable
Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

information. Without initially completing a desk study, an excessive amount of the exploration
expenditure may be wasted. Glossop (1968) wisely advised site investigation planners:
If you do not know what you should be looking for in a site investigation, you are not likely to
find much of value.

A desk study, initial phase subsurface investigations and a Phase I ESA should all be completed before
the scope of a final design phase subsurface investigation is developed. Contaminated ground and
groundwater can have a significant impact on tunneling if not found prior to bidding and construction.
The final design phase site investigation should focus on reducing uncertainties and providing
information needed by tunneling contractors to determine means and methods and assess productivity
and costs.
Phasing is a cost-effective method of maximizing the benefit of the exploration program while
simultaneously helping to reduce microtunneling risks. Even after several phases of investigation and
completion of the design, design team engineers should communicate the remaining risks and
uncertainties to the owner and indicate the costs and potential risk mitigation that would likely be
realized if additional focused subsurface investigation work is completed. If necessary, late phase
subsurface information can be added to the contract documents being bid by addendum.
GEOTECHNICAL REPORTS
Owners need to understand that geotechnical reports vary considerably in scope and effectiveness at
explaining and baselining anticipated ground conditions to bidders and contractors. Table 2 lists eight
types of geotechnical reports that may be involved with a microtunneling project. Two categories of
reports are most common: recommendations reports and data-baseline reports.
Geotechnical Recommendations Reports
So-called commodity geotechnical firms are accustomed to completing Geotechnical Recommendations
Reports (GRRs). GRRs are typically prepared early during final design as a result of a single phase
subsurface investigation based on a competitive proposal. The final pipeline design is often incomplete
or unknown by the geotechnical firm. Budgets for these subsurface investigations are often lean.
Commodity geotechnical firm experience with shaft and microtunnel construction is generally limited.
As a result, the GRR is written as a recommendations report filled with uncertainties about the actual
design and specified work. GRRs typically have the following shortcomings:

A comprehensive summary of desk study and previous phase subsurface investigation results is
generally missing. GRRs often do not show the locations of available previous borings by others
and seldom include the boring logs and pertinent field and laboratory testing results.

Geology is often ignored. The geologic setting is not given or is inadequately explained. Layers
and deposits indicated on boring logs are generally not characterized as geologic units or formations.

No interpretive ground and groundwater conditions profile along the microtunnel alignment is
provided. Providing a profile is often considered too risky by these firms.

Groundwater data often only consists of drillers observations in boreholes during or immediately
after drilling. Piezometers are not installed or rare. Piezometer permeability or pump tests are even
more rare. Water level readings generally do not extend throughout the design period. Fluctuations
from seasonal and weather events are seldom measured.

Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

Ground and groundwater properties and anticipated ground behavior during shaft and tunnel work
are not baselined. If quantities are provided, wide ranges are given without consideration of how the
low bidder is entitled to interpret the statements. Tunnelmans ground classifications are not
explained or provided.

Numerous disclaimers are provided indicating that at best, the only ground conditions that can be
relied upon are the specific locations of the borings. Some disclaimers suggest that
recommendations are only valid if the firm is retained to monitor construction.

Numerous specification-like and additional work recommendations are provided that may not have
been included in the actual specifications or completed during design. As a result, significant
inconsistencies with the contract documents often exist.

GRRs are commonly completed and often lead to claims. Tarkoy (2004) opined that 95 percent of all
tunneling problems associated with geotechnical conditions are not from inadequate expenditure on
subsurface exploration, but instead from:

A lack of professional interpretation,

Non-existent critical thinking, and

Monumental lapses in common sense.

He considered commodity geotechnical approaches to the work such as overuse of inexperienced junior
engineers for interpretation of data as a serious problem and concluded:

Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

Table 2 Geotechnical Report Types


Type of Geotechnical
Report
GOR
Geotechnical
Overview Report

When Completed
Typically completed
during planning or
pre-design and kept
internal
Typically completed
during planning or
pre-design and kept
internal.
Typically completed
during preliminary,
intermediate and/or
final phases of design.

Report Usage

Typical Report Scope

Generally written for use by


owners, planners and
preliminary design engineers.

Results of a desk study of available geologic papers, subsurface data,


geotechnical reports and underground construction case histories.

Generally written for use by


owners, planners and
preliminary design engineers.

Results of a site visit(s) by a geologist or geotechnical engineer to


observe and map geologic features at sites or along a pipeline
alignment.

Generally written for use by


owners, planners and
preliminary design engineers,
design engineers, regulatory
agencies and contractors.
Generally written for use by an
owner and designer and not by
the contractor.
Generally written for use by
owners, planners, preliminary
design engineers and final
design engineers.

A factual report summarizing a phase of subsurface investigation


work and presenting field and laboratory results without ground
behavior or constructability interpretations.

GFRR

Geotechnical Field
Reconnaissance
Report

GDR

Geotechnical Data
Report

GRR

Geotechnical
Recommendations
Report
Geotechnical
Interpretive Report

Typically completed
during preliminary or
pre-design phases.
Typically completed
during pre-design as
part of preliminary
engineering report and
final design.

GDSR

Geotechnical
Design Summary
Report

Typically completed
during final design.

Generally included in contract


documents for use by the
bidders and contractor.

GBR

Geotechnical
Baseline Report

Typically completed
during final design

Generally included in contract


documents for use by the
bidders and contractor.

Typically completed
during construction.

Used to evaluate DSCs, modify


designs, and document actual
conditions for reference.

GIR

GCR

Geotechnical
Conditions Report

A report presenting field and laboratory results for a subsurface


investigation program along with recommendations or suggestions
for design and possibly construction methods.
A report summarizing results in the GDR and presenting
interpretations of ground behavior and discussing constructability
issues. The GIR also includes recommendations and parameters for
design. Quantities and ground conditions are not rigorously
baselined. The GIR is essentially a preliminary GBR with design
recommendations.
A report summarizing results in the GDR and presenting
interpretations of ground behavior and discussing constructability
issues. Quantities and ground conditions are not rigorously
baselined.
A report summarizing results in the GDR and presenting
interpretations of ground behavior and discussing constructability
issues. Quantities and ground conditions are rigorously baselined
and the bases for quantities are explained.
Results of a site visit(s) by a geologist or geotechnical engineer of
observed or mapped geologic features at sites or along a pipeline
alignment.

Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

We have found it notable that some of the most prominent geotechnical firms consistently
commit the same mistakes, repeatedly while relying on a dearth of disclaimers.

Baker et al (2004), authors from a law firm that represents contractors in support of differing site
condition claims, explain in their paper how poorly written geotechnical reports and specifications can
readily be shown to be defective contract documents and used to win claims. To avoid claim problems
they cite many of the recommendations contained in the 1984 report by the U.S. National Committee on
Tunneling Technology (USNCTT, 1984). They conclude:
If only these guidelines were followed! What appear to be simple concepts brevity, clarity,
specificity, and no discrepancies between documents somehow rarely seem to make it into
practice. Therefore, contractors should evaluate any contracts involving underground work in
light of these standards. Where an owners specification [or geotechnical report] deviates from
the standards, it may indicate some lack of information or research. In any event, such deviation
should raise the proverbial red flag for the contractor.

In summary, owners who desire to minimize claims and risks should avoid the use of GRRs as either
reference documents or as part of the contract documents. In most cases the disclaimers contained in
these reports will be found to be invalid (USNCTT, 1984; Parvin, 1994; Baker, 2004). The vagueness,
inconsistency with final design and recommendations style of these reports will tend to increase claims
rather than minimize them.
GDRs and GBRs
During the last 10 years, the tunneling industry has adopted geotechnical data reports (GDRs) and
geotechnical baseline reports (GBRs) as better approach to communication of anticipated ground
conditions and expected ground behavior for minimizing risks and excessive DSC claims. While no
approach is without some problems and potential for DSC claims, this approach has generally been
more successful at managing subsurface risks than other approaches. The GDR-GBR approach is
explained in detail within an ASCE publication entitled Geotechnical Baseline Reports for Underground
Construction Guidelines and Practices (Technical Committee on Geotechnical Reports of the
Underground Technology Research Council, 1997). Clarifications and recommended improvements on
preparation of GBRs were subsequently made by several authors including: Edgerton (1998), Samuels
(1998), Essex & Klein (2000), Hafer (2000) and Tarkoy (2004).
GBRs are difficult for commodity geotechnical firms and inexperienced geotechnical engineers to write.
A good understanding of tunneling, ground behavior and ground conditions are essential in making
good judgments on what to baseline, quantities to baseline and what associated work to cover with a
separate pay item or include as incidental.
One of the most difficult parameters to baseline is boulders or boulder obstructions. Most commodity
geotechnical firms will not attempt to baseline boulders due to concerns of being wrong. While risks
and uncertainties of boulder baselining are significant, reasonable boulder baselining is needed for
microtunneling and can be successfully completed (Hunt & Angulo, 1999; Hunt, 2000; Hunt & Mazhar,
2004).
Reluctant and inexperienced geotechnical firms and engineers need to learn that baselines are not
necessarily predictions of actual conditions to be encountered, but are instead a contractual mechanism
for obtaining reasonable allowances and compensation methods for select anticipated conditions. GBR
writers and owners should recognize that risk management is more about equitable allocation of risk and

Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

fair compensation than about preparation of contract documents that attempt to eliminate DSCs. In fact,
experienced tunnel engineers believe DSCs should be expected as part of the risk sharing process.
Heuer (1997) expressed this concept:
We must constantly strive to improve our knowledge of the underground and our ability to
predict it. But we will never be 100% successful. This means that evitable encounters of
unexpected conditions are not automatically a reflection of the engineers professional
competence Rather, such encounters are a basic fact of life that we must learn to deal with. We
should accept that a DSC is not a four letter word; it is not unethical or an inherently evil thing
The contact DSC serves a useful and necessary function.

If owners truly desire to manage microtunneling risks by adopting an risk sharing approach through the
use of a DSC clause and by GDRs and GBRs that represent anticipated ground conditions and behavior,
then care must be taken to ensure that retained GBR writers understand the purpose of baselines, have
significant baselining experience and understand microtunneling as a result of involvement on many
projects from design through construction.
CONCLUSIONS
Risk management is an important part of achieving a successful microtunneling project. Proper
completion of desk studies, subsurface investigations and geotechnical reports are key elements of risk
management for microtunneling.
Desk studies should be completed to help cost-effectively utilize available subsurface and tunneling
information during planning and initial phase subsurface investigations.
Subsurface investigations should follow a desk study and then be phased to progressively reduce
uncertainties and improve the geologic model or profile depiction of subsurface conditions.
Experienced tunnel engineering firms should be retained to complete the scope of work and oversight of
subsurface investigations for microtunneling. An experienced tunnel engineer or firm should guide
geotechnical firms that that are retained for subsurface investigation and geotechnical data report work,
but lack credible tunnel engineering experience.
Geotechnical data interpretation and preparation of geotechnical baseline reports should be completed
by or under the close guidance of an experienced tunnel engineer. Geotechnical firms that lack tunnel
design and construction management experience are unlikely to prepare proper geotechnical baseline
reports. Such firms generally produce geotechnical recommendations reports that are filled with widely
ranging values for parameters and numerous disclaimers about the reliability of interpretations.
Geotechnical recommendations reports are not the best choice for management of microtunneling risk.
Owners need to take ownership of the ground and recognize that even thorough subsurface
investigations by experienced geotechnical firms or engineers will not eliminate DSC claims. Some
DSC claims should be expected and resolved with contractors in a cooperative and equitable manner.
While the ground is inherently variable and risky, ground related microtunnel risks can be managed and
controlled by good risk management practices starting with geotechnical desk studies, phased
subsurface investigations and geotechnical baseline reports and specifications prepared by geotechnical
engineers having credible tunnel design and construction experience.

Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

REFERENCES
Abbott, D.G. (2004). Risk Management in Microtunneling A 20 Year Personal and Industry
Perspective. Proceedings: NO-DIG 2004, Paper D-2-01-1, 10p. North American Society for
Trenchless Technology, Arlington, Virginia.
Anderson, J. (1998) Evaluating Risks from Tunnelling, World Tunnelling, August 1998, 315-316.
ASCE, (2001) Standard Construction Guidelines for Microtunneling, CI/ASCE Standard 36-01, 41p.
British Tunnelling Society (2003) The Joint Code of Practice for Risk Management of Tunnel Works in
the UK. British Tunnelling Society c/o Institution of Civil Engineers, London. 19p.
Dix, A. (2004) Implications of the Code of Practice, Tunnels & Tunnelling International, 36 (2)
February 2004, 25-26).
Edgerton, W.B. (1998) Site Investigations: A Guide, Civil Engineering, June 1998, 13A-16A, ASCE.
Essex, R.J., 1993. "Subsurface Exploration Considerations for Microtunneling/Pipe Jacking Projects,"
Proceedings of Trenchless Technology: An Advanced Technical Seminar, Trenchless
Technology Center, Louisiana Tech University, January, pp. 275-288.
Essex, R.J. & Klein, S.J. 2000. Recent developments in the use of Geotechnical Baseline Reports. In
Ozdemer, L. (ed). Proceedings Of The North American Tunneling 2000: 79-84. Rotterdam: Balkema.
Glossop, R. (1968) The rise of geotechnology and its influence on engineering practice, Geotechnique,
18 (2), 107-150.
Golder Associates & James F. MacLaren, Ltd (1976) Site Investigation for Tunnels, Tunneling
Technology An Appraisal of the Sate of the Art for Application to Transit Systems, Ontario
Ministry of Transportation and Communications, 33-36.
Gould, J.P. (1995) Geotechnology in Dispute Resolution. Journal of Geotechnical Engineering.
ASCE. New York. Vol. 121, No. 7. July 1995. pp 523-534.
Hafer, R (2000) Risk management and disputes avoidance in underground construction are owners
satisfied? A view from the trenches, Proceedings of The North American Tunneling 2000: 89-95.
Rotterdam: Balkema.
Hinze, J. & McClelland, T. (1997) Risk Assessment in Underground Construction: Uncertainty is
Certain. No-Dig Engineering, May/June 1997, pp19-22.
Heuer, R.E., (1997). Discussion of Geotechnology in Dispute Resolution. Journal of Geotechnical
and GeoEnvironmental Engineering. ASCE. New York. June 1997, 592.
Hunt, S.W. & Angulo. M. 1999. Identifying and Baselining Boulders for Underground Construction. In
Fernandez, G. & Bauer (eds), Geo-Engineering for Underground Facilities: 255-270. Reston, Virginia:
ASCE.
Hunt, S.W. 2002. Compensation for Boulder Obstructions. In Ozdemer, L. (ed), Proceedings Of The
North American Tunneling 2002: 23-36. Rotterdam: Balkema.
Hunt, S.W. & Mazhar F.M. (2004) MTBM and Small TBM Experience with Boulders, Proceedings of
the North American Tunneling 2004 Conference, April 18-21, 2004 Atlanta Georgia, 47-54,
Rotterdam: Balkema.
Klein S.J., Nagle G.S., Raines, G,L. (1996). Important Geotechnical Considerations in
Microtunneling. No-Dig Engineering. Vol. 3. No. 4. July/August (1996), 9-12.
Legget R.F. (1979). Geology and Geotechnical Engineering. Journal of the Geotechnical Engineering
Division. Vol. 105, No. GT3, March 1979, 342-391. ASCE, New York.
Legget R.F. & Hatheway, A.W. (1988) Geology and Engineering, McGraw-Hill, New York.

Copyright 2004 Water Environment Federation. All Rights Reserved.

Collection Systems 2004:


Innovative Approaches to Collection Systems Management

Neff. T. (2003) Responsibility, Accountability and the Rule of Parsimony, TBM Tunnel Business
Magazine, Dec. 2003, 8.
Neyer, J.C. (1985) Geotechnical Investigation For Tunnels in Glacial Soils. In Mann, C.D. & Kelly,
M.N. (eds). Proceedings:, 1985 Rapid Excavation and Tunneling Conference. Chapter 1, 3-15.
Littleton CO.: SME.
Osterberg, J.O. (1978). Failures in Exploration Programs. Site Characterization & Exploration.
ASCE. New York, 3-9.
Parvin, C. (1994) Disclaimers no defense v. differing sites, Roads & Bridges, July 1994, 8.
Richards, D.P. (1999) Perspectives on Risk Assessment in Tunneling, In Fernandez, G. & Bauer (eds),
Geo-Engineering for Underground Facilities: 1185-1203. ASCE, Reston, Virginia.
Salem, O. & Hegab, M. (2001). Contractual Risk Identification and Mitigation in Microtunneling and
Trenchless Technology Projects. No-Dig Engineering. Vol. 8. No. 2. 4th Quarter 2001 5-9.
Samuels R. (1998) Geotechnical Baselines Part of the problem or a solution? Proceedings of North
American Tunneling 1998, 29-33, Balkema, Rotterdam.
Sangster, T. (2003) Risk Management in Underground Infrastructure Construction and Rehabilitation,
Proceedings of Pipelines 2003, pp591-598, ASCE.
Sauer, G. (1997). Discussion of Geotechnology in Dispute Resolution. Journal of Geotechnical and
GeoEnvironmental Engineering, June 1997, p598. ASCE. New York.
Tarkoy, P.J. (1999) Microtunneling in Spite of Inherent Risks. TBM: Tunnel Business Magazine.
December 1999. p. 23-24.
Tarkoy, P.J. (2004) Musings Regarding the Mole. TBM: Tunnel Business Magazine. February 2004.
p. 6.
Technical Committee on Geotechnical Reports of the Underground Technology Research Council.
1997. Essex, R.J. (ed). Geotechnical Baseline Reports for Underground Construction
Guidelines and Practices. New York: ASCE. 40p.
U.S. National Committee on Tunneling Technology (USNCTT), (1984). Geotechnical Site
Investigations for Underground Projects. National Academy Press. Washington D.C. Vol. 1,
182p.
West, G., Carter, P.G. Dumbleton, M.J. & Lake, L.M. (1981) Site Investigation for Tunnels,
International Journal of Rock Mechanics and Mining Science, Vol 18. 345-367.
Westland, J,: Busbridge, J.R. & Ball, J.G. (1998) Managing subsurface risk for Torontos Rapid
Expansion Program. Proceedings: North American Tunneling 98. pp37-45, Balkema,
Rotterdam.

Copyright 2004 Water Environment Federation. All Rights Reserved.

You might also like