You are on page 1of 121

GOVERNMENT OF UGANDA

UGANDA NATIONAL ROADS AUTHORITY

CONSULTANCY SERVICES FOR FEASIBILITY STUDY,


DETAILED ENGINEERING DESIGN, TENDER ASSISTANCE
AND PROJECT MANAGEMENT FOR
UPGRADING OF ROADS TO BITUMINOUS STANDARDS

LOT E

FINAL
DETAILED DESIGN REPORT
PKG 1
ROAD E1.1/E1.2
MUSITA-LUMINO/BUSIA-MAJANJI
AUGUST 2012

IN ASSOCIATION WITH

Project Name:

Feasibility Study, Detailed Design, Tender Assistance and Project Management


for Upgrading of Roads to Bituminous Standards

Project Number:

5116004

Report for:

FINAL DETAILED DESIGN REPORT

PREPARATION, REVIEW AND AUTHORISATION


Revision #

Date

31 Aug
2012

Prepared by

Nuruddin
Wajihi/Michael
Ogola/Edward
Byaruhanga

Reviewed by

Various

Approved for Issue by

Nuruddin Wajihi

ISSUE REGISTER
Distribution List

Date Issued

Number of Copies

UNRA

31-08-2012

SMEC staff: Project Manager

31-08-2012

Client:

Associates: NEWPLAN
Office Library (SMEC office location):
SMEC Project File: Kampala

31-08-2012

SMEC COMPANY DETAILS


SMEC INTERNATIONAL PTY LIMITED
Kipro Centre. 3rd Floor, Sports Road, Westlands, Nairobi
Tel:

+254 20 4441541/2

Fax:

+254 20 441543

Email:

Nuruddin.wajihi@smec.com

www.smec.com
The information within this document is and shall remain the property of SMEC INTERNATIONAL PTY LTD.

Detailed Design Report (FINAL)


for
FEASIBILITY STUDY, DETAILED
ENGINEERING DESIGN, TENDER
ASSISTANCE AND PROJECT
MANAGEMENT FOR UPGRADING
ROADS TO BITUMINOUS STANDARDS
LOT E
PACKAGE 1 : ROAD E1.1/E1.2
MUSITA-LUMINO/BUSIA-MAJANJI ROAD
For:
UGANDA NATIONAL ROADS AUTHORITY
AUGUST 2012

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

KUMI
BUKUNGU

PACKAGE 4

PACKAGE 2A

NAMAGUMBA-BUDADIRINALUGUGU

TIRINYI-PALLISA/
PALLISA-KUMI

NALUGUGU

PACKAGE 5

PACKAGE 2B

KAMULI - BUKUNGU
PALLISA

BUDADIRI

PALLISA-KAMONKOLI
NAMAGUMBA
KAMONKOLI

TIRINYI
KAMULI

BUMBOBI

PACKAGE 3
BUMBOBI-BUBULOLWAKHAKHA
BUBULO
LWAKHAKHA

MUSITA

BUSIA

PACKAGE 1
MUSITA-LUMINO/
BUSIA-MAJANJI

LUMINO
MAJANJI

LOCATION OF LOT E ROADS

TABLE OF CONTENTS
EXECUTIVE SUMMARY

ES-1

E1. Introduction

ES-1

E2. Economic Evaluation

ES-2

E3. Topographical Survey

ES-2

E4. Traffic Surveys

ES-3

E5. Traffic Growth and Projected Traffic

ES-3

E6. Axle Load Survey

ES-4

E7. Pavement Design

ES-5

E8. Materials Investigation

ES-6

E9. Hydrology

ES-7

E10. Drainage Design

ES-10

E11. Geometric Design

ES-12

INTRODUCTION

1.1

Background

1.2

Contract Details

1.3

Terms of Reference

1.4

Preliminary Design Report

1.5

Packaging of the Project Roads

1.6

This Report

ENGINEERING STUDIES

2.1

Project Location

2.1.1

Description of Project Road

2.1.2

Topography

2.1.3

Geology

2.1.4

Soils

2.2

Topographical and Aerial Survey

2.2.1

General

2.2.2

References and Datum

2.2.3

Ground Control And GPS Measurements

10

2.2.4

Interim Beacons And Total Station Measurements

10

2.2.5

Aerial Survey

10

2.2.6

Final Products

11

2.3

Traffic Surveys

11

2.3.1

Terms of Reference

11

2.3.2

Existing Traffic

12
i

2.3.3

Traffic Counts

12

2.3.4

Base Traffic

13

2.3.5

Traffic Growth

15

2.3.6

Growth in normal traffic

15

2.3.7

Diverted Traffic

15

2.3.8

Generated traffic

15

2.3.9

Projected Traffic growth

15

2.3.10 Origin/Destination Surveys

16

2.3.11 Axle Load Survey

22

2.3.12 Overloading

23

2.3.13 Cumulative Equivalent Standard Axles (CESA)

24

2.3.14 Summarized Road Usage

25

2.3.15 Sensitivity Analysis

26

2.4

Soils and Materials Investigations

27

2.4.1

General

27

2.4.2

Sub-grade Soil Investigation

27

2.4.3

Gravel and Hardstone Sources

27

2.4.4

Laboratory Testing

28

2.5

Hydrological Studies

29

2.5.1

Objectives

29

2.5.2

General Objective

29

2.53

Specific Objectives

29

2.5.4

Background

29

2.5.5

Hydrological Analysis Criteria and Practices

30

2.5.6

Hydrological Analysis Methodology

30

2.5.7

Data Collection

31

2.5.8

Topography, Catchment Area Delineation and Watershed Parameters

31

2.5.8

Watershed Characteristics

32

2.6

Swamp Investigations

36

2.7

Drainage Investigations

36

2.7.1

Assessment of Existing Drainage Structures

36

2.7.2

Classification of Drainage Structures

36

2.7.3

Side Ditches

37

2.7.4

Pipe Culverts

37

2.7.5

Box Culverts

37

2.7.6

Bridges

37

2.7.7

Existing Bridges

38

ii

2.7.8
2.8

Summary

Environmental and Social Studies

38
38

2.8.1

General

38

2.8.2

Geographical Location

38

2.8.3

Biophysical Environment

39

2.8.4

Socio-economic and Cultural Environment

39

2.8.5

Predicted Environment and Social Impacts

40

DETAILED DESIGN

43

3.1

43

Geometric Design

3.1.1

Introduction

43

3.1.2

Design Standards

43

3.1.3

Design Speed

45

3.1.4

Design Departures

47

3.1.5

Cross-Section

48

3.1.6

Embankment Design

48

3.1.7

Adopted Design Parameters and Standards

49

3.1.7

Summary of Adopted Design Speeds

50

3.1.8

Design Road Alignment

50

3.1.9

Alignment Details

51

3.1.10 Low Lying Area

54

3.1.11 Junctions and Accesses

56

3.1.12 Footpaths, Busbays and Road Furniture

57

3.1.13 Service Roads

57

3.1.14 Climbing Lanes

58

3.2

Pavement Design

61

3.2.1

Introduction

61

3.2.2

Design Period

61

3.2.3

Pavement Design Input Data

62

3.2.3

Subgrade

62

3.2.4

Soft spots and Marshy areas

63

3.2.5

Pavement Materials

63

3.2.6

Pavement Design Catalogue

63

3.2.7

Pavement Structural Design

63

3.2.8

Design Traffic Loading

64

3.2.9

Design Subgrade CBR

64

3.2.10 Design Subgrade Class

66

3.2.11 Proposed Pavement Structure

66
iii

3.3

Drainage Design

67

3.3.1

Design Return Period

67

3.3.2

Frequency Distribution Models

67

3.3.3

Design Flood Estimation

70

3.3.4

Runoff Models

70

3.3.5

Frequency analysis

70

3.3.6

The TRRL East African Flood Model

71

3.1.8

Design Discharges

79

3.4

Structure Selection

80

3.4.1

Design Philosophy

80

3.4.2

Bridges

81

3.4.3

Slab/Box Culverts

84

3.4.4

Pipe Culverts

85

3.4.5

Paved Side Ditches

87

3.5

Hydraulic Design

87

3.5.1

Minor Drainage Structures

87

3.5.2

Major Drainage Structures

88

3.6

Structural Design

90

3.6.1

Minor Drainage Structures

90

3.6.2

Major Drainage Structures

90

Quantity and Cost Estimation

97

3.7

3.7.1

Determination of Quantities

97

3.7.2

Unit Rates

97

3.7.3

Provisions

97

3.7.4

Construction Cost Estimates

98

3.7.5

Road Construction Packages

98

APPENDICES
Appendix 1 Terms of Reference (Detailed Design)
Appendix 2A Survey Location Map
Appendix 2B Daily Count Results
Appendix 2C Estimated AADT
Appendix 2D Derivation of Growth Rates
Appendix 2E Traffic Forecast
Appendix 2F O/D Survey Results
Appendix 2G Sensitivity Analysis Results
Appendix 3 Summaries of Test Results
Appendix 4 Delineated Catchments

iv

Appendix 5A Drainage Inventory


Appendix 5B Photographic Inventory
Appendix 5C - Design Flows and Proposed Structures
Appendix 6 - Structural Design Calculations
Appendix 7 - Geometric Alignment Data

EXECUTIVE SUMMARY
E1. Introduction
The Uganda National Roads Authority (UNRA) became a legal entity in 2006 and began
operations in July 2008 with the following objectives at local level:
1. To improve access to goods/passenger transport services and to reduce transport costs along
the route;
2. To improve access to social and economic development opportunities along the route by
providing high capacity infrastructure;
3. To ensure no roadside communities become worse off as a result of the road upgrading
works
In pursuance of the above objectives, UNRA has embarked on upgrading selected roads in several
districts of Uganda. To this end, in September 2009, UNRA commissioned SMEC International Pty
in association with NEWPLAN Ltd. of Uganda to provide consultancy services for the upgrading
of several roads, referred to as Lot E, in the Eastern districts and comprising the following roads,

Road
Reference
No.

Road Name(s)

E1

Musita-Lumino and Busia-Majanji roads (104 Km)

E2

Tirinyi-Pallisa-Kumi and Pallisa-Mbale roads (114 Km)

E3

Mbale-Bubulo-Lwakhakha road (41 Km)

E4

Namagumba-Budadiri-Nalugugu road (29 Km)

E5

Kamuli-Bukungu road (64 Km)

with the following Terms of Reference:


(i)

Feasibility Study, including consideration of alternative routes and pavement options,


environmental and social impact study, road safety, land acquisition, preliminary
design, economic and financial analysis;

(ii)

Detailed engineering design for the approved road option; including all necessary data
collection, field surveys and analysis to cover all aspects of detailed design;

(iii)

Environmental and Social Impact Assessment (EIA) in accordance with Ugandan


legislation and NEMA guidelines;

(iv)

Preparation of a full Resettlement Action Plan and associated surveys to identify and
value property that will be affected by the road upgrading works and the establishment
of the road reserve;

(v)

Preparation of bidding documents based on the approved detailed designs.

The Feasibility Study and the Preliminary Designs of the five project roads were undertaken
between January 2010 and January 2011 and the Preliminary Reports submitted to UNRA
variously between October 2010 and January 2011.

| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-1

Following consultations with UNRA, the five roads were divided into six (6) packages as follows:

Package 1 : Road E1 :

Musita-Lumino/Busia-Majanji roads

Package 2A : Road E2.1/E2.2 : Tirinyi-Pallisa/Pallisa-Kumi road


Package 2B : Road E2.3 :

Pallisa-Kamonkoli road

Package 3 : Road E3 :

Bumbobi-Busumbu-Lwakhakha

Package 4 : Road E4 :

Namagumba-Budadiri-Nalugugu

Package 5 : Road E5 :

Kamuli-Bukungu road

This Detailed Design report refers to Package 1: Road E1: Musita-Lumino/Busia-Majanji roads.
The Project road starts from Musita trading center along the Jinja-Iganga highway passing through
Mayuge, Nankona, Buyinja and ends at Lumino trading center, another link starts from Busia town
through Lumino ending at Majanji. It acts as a shortcut from Busia town to Jinja and also serves as
a link to a number of landing sites along Lake Victoria including Majanji, Lufudu, Omenya,
Wakawaka and Kigandala.
E2. Economic Evaluation
The economic evaluation of Road E1 indicated the upgrading of these roads to bitumen standards
to be economically viable with the following Economic Internal Rates of Return:
Table 1: Results of the Economic Evaluation (Net Present Value-NPV)
SN

E1

Road name/Road section

Musita-Lumino/Busia/Majanji
1.1-Musita-Lumino
1.2-Busia-Majanji

Type of
HDM 4
analysis
Project
Section
Section

NPV
50.682
28.764
21.918

Table 2: Results of the Economic Evaluation (Internal Rate of Return)


SN

E1

Road name/Road section

Musita-Lumino/Busia/Majanji
1.1-Musita-Lumino
1.2-Busia-Majanji

Type of
HDM 4
analysis
Project
Section
Section

EIRR (%)
19.6
18.0
24.0

E3. Topographical Survey


Aerial photography supplemented by ground control was carried out during the preliminary design
stage and formed the basis of the preliminary and detailed alignment designs.

| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-2

E4. Traffic Surveys


Manual classified counts were carried at seven stations along the route for seven days, from 25th to
31st March 2010. Night counts were carried for one weekday and one weekend day at each station.
The average annual daily traffic (AADT) in the current year (2010) is indicated in the chart below,
with vehicular traffic ranging from 154 to 557 vehicles/day.

2500
2090

AADT

2000
1430

1500
946

1000

1046
829

564
500

154

557
337

272

246

200

0
5km after
Lumino

5km before 5km before 5km from


Busia
Namayingo Mayuge
Sation name
AADT (with Motorcycles)

5km from
Musita

5km before
Lumino

AADT (without motorcycles)

The proportion of motorcycles to the other traffic is high as seen from the chart above.
Origin/Destination (OD) survey was conducted during the month of April 2010 using enumerators
hired and trained from along the project road. Information gathered through road side interviews of
vehicle drivers was analyzed to understand the origin-destination characteristics of traffic plying
the project roads. Since these interviews were conducted on a sample of vehicles, the collected
information was expanded to reflect the total volume of traffic plying on the road on that particular
day. The results are discussed fully in the main text.
E5. Traffic Growth and Projected Traffic
Deriving traffic growth from traffic data involves analysis of the growth of the various traffic
classes over a long period of say 10-20 years. This growth will give a trend in the growth of traffic
over the years. This trend is then used to project the traffic growth in the project period. It was
noted that analysis of historical data was not feasible as there was no adequate historical data.
Traffic growth factors were derived using traffic proxies such as fuel consumption, vehicle
registration trends, GDP growth etc. No data on historical traffic growth was available for this road.
It was assumed that road construction shall commence in the year 2011 and end in 2015.
Projections were made for a design period of 15 years and 20 years. Therefore projections were
made up to the year 2030 and 2035 using the corresponding growth factors.
The following tables gives the forecast growth rates for the varios classes of vehicles for three
scenarios, namely pessimistic (low), realistic (medium) and optimistic (high).

| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-3

Vehicle class
Cars
Pick up and vans (Petrol)
Pick up and vans (Diesel)
Minibuses (Petrol)
Minibuses (Diesel)
Buses & Trucks

Vehicle class
Cars
Pick up and vans (Petrol)
Pick up and vans (Diesel)
Minibuses (Petrol)
Minibuses (Diesel)
Buses & Trucks

Vehicle class
Cars
Pick up and vans (Petrol)
Pick up and vans (Diesel)
Minibuses (Petrol)
Minibuses (Diesel)
Buses & Trucks

Pessimistic normal traffic growth (%)


2024 and
2010-2013 2014-2018
2019-2023
beyond
4.7
5.7
3.7
2.4
4.7
5.7
3.7
2.4
4.7
6.8
4.4
2.9
4.7
5.7
3.4
2.4
4.7
6.8
4.4
2.9
4.7
6.8
4.4
2.9
Realistic normal traffic growth (%)
2024 and
2010-2013 2014-2018
2019-2023
beyond
4.7
7.2
4.7
3.2
4.7
7.2
4.7
3.2
4.7
8.5
5.6
3.8
4.7
7.2
4.7
3.2
4.7
8.5
5.6
3.8
4.7
8.5
5.6
3.8

Optimistic normal traffic growth (%)


2010-2013 2014-2018 2019-2023 2024 and beyond
4.7
8.6
5.7
3.9
4.7
8.6
5.7
3.9
4.7
10
6.8
4.6
4.7
8.6
5.7
3.9
4.7
10
6.8
4.6
4.7
10
6.8
4.6

E6. Axle Load Survey


A three day traffic axle load survey and counts was carried at Nabigingo along the project road
between 6th May and 22nd May 2010.
Weighing was done for both directions simultaneously using a portable weighbridge to Transport
Research Laboratories (TRRL) specifications.
The vehicles weighed were:
- Medium Buses
- Large Buses
- Light Goods Vehicles
- Medium Goods Vehicles
- Heavy Goods Vehicles
- Very Heavy Goods Vehicles
The tables below shows the summary of axle load equivalence factor for each class of the heavy
vehicles.
| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-4

Vehicle category
MB 1.2
LB 1.2
LGV (1.2)
MGV(1.2)
HGV 1.2
VHGV 1.2

Average
gross
weight
4.77
14.68
4.26
4.10
5.38
18.65

Average
equivalence
factor
(80KN)
0.01
1.69
0.07
0.00
0.11
9.61

E7. Pavement Design


The pavement design of the project roads is based on the Ministry of Works, Housing and
Communications Road Design Manual Vol. 3: Pavement Design, Part I: Flexible Pavements (July
2005).
The economical analysis of the project roads is based on a 20 year analysis period. Hence a 20
year pavement design period has been adopted.
Projected traffic loading for low, medium and hight growth scenarios are:
Estimated traffic growth rate (low)
Estimated traffic growth rate (medium)
Estimated traffic growth rate (high)

= 8.7x106
= 8.99x106
= 9.37x106

Estimated traffic growth rate (medium)


pavement structure

= 8.99x106 is adopted for the design of the

Traffic class obtained is:

T6

Subgrade Class: Analysis of soaked CBR test results for the road alignment subgrade soil is
presented in summary form as shown below.

Musita - Lumino
Chainage

Road
Length

Road
From

90th percentile
value

Design
CBR (%)

74.0

S3

26.0

S3

To

(Km)

Musita-Lumino

0+000- 74+000

Busia-Majanji

0+000-26+000

Subgrade
Class

Following the submission of the Preliminary Design Report, UNRA instructed the Consultant to
adopt Chart W2 of the Design Manual for the selection of the pavement structure.

| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-5

On the basis of the projected traffic loading, the following pavement structure has been
recommended:
Pavement layer

Type of material

Layer
thickness

SURFACING
BASE COURSE
SUBBASE
IMPROVED SUBGRADE

AC(Asphalt Concrete)
GB(Granular Base)
CSB(Cemented Subbase)
G15 (Natural Gravel CBR >15%)

50 mm
150 mm
175 mm
125 mm

AC Asphalt Concrete
GB Granular Base (Graded Crushed Stone)
CSB Cement Stabilized Base (Gravel)
G15 Gravel Class 15 (min.CBR=15)
E8. Materials Investigation
The preliminary materials investigations were conducted in accordance with the Terms of
Reference. It consisted of site reconnaissance, field exploration and analysis of the findings of the
field exploration.
Sub-grade Soil Investigation
The sub-grade soil investigation along the existing road alignment comprised sub-grade soil
sampling by means of trail pits, DCP testing and laboratory testing.
Trial Pits
Trial pits were excavated at two (2) kilometre interval on alternate side of the carriageway to
depths of generally 1 m.
The pits were dug to varying depths from the surface to sub-grade level with a total of 34 pits dug
over the total road length of the project road 68 km.
The vertical profile of the pavement in each trial pit was recorded and representative sub-grade
sample taken for laboratory testing.
DCP Investigations
DCP tests were conducted at intervals of 500m as stipulated in the ToR to measure the in-situ
bearing strength (CBR) of the sub-grade.
To avoid weak spots (thin layers) from being overlooked and to identify layer boundaries fairly
accurately, readings were taken at 1-5 blow intervals, depending on the rate of penetration.
Gravel and Hardstone Sources
-

Assessment of the suitability and extent of the material source.

Excavation of trial pits.

Logging of the layers encountered.

Retrieval of samples for laboratory testing.

Backfilling of the trial pits.

| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-6

At each site, trial pits were excavated and depths of overburden and gravel were logged. In some
instances, material was sampled from rock outcrops, talus, or existing quarries, in which cases, test
pit excavation was not required. The volumes of both overburden and gravel were also estimated.

Gravel and Hardstone Sources

A total of 20 existing and potential gravel sources and 3 rock sources were identified and
investigated along the five project roads as listed below:
Laboratory Testing
As a requirement under the Contract, the Consultant fabricated a mobile laboratory in a 40-foot
container at its offices in Kampala. Upon completion of fabrication and fitting out the laboratory
was transported and erected at the compound of UNRAs regional offices in Jinja.

Gravel Samples

Samples of sub-grade material recovered from trial pits and samples from the gravel sources were
transported to the mobile laboratory in Jinja where they were subjected to the following tests:
-

Natural moisture content determination

Particle size analysis

Atterberg limits

Moisture content Dry density relationship (BS 1377 test method)

CBR (4-day soak compacted at 90%, 95% and 98% MDD)

Swell tests

Rock Samples
To confirm the test results obtained on surface samples, during the detailed design stage the
existing operational quarry along Musita-Lumino road was drilled at one location down to 15 m.
Samples of cores were taken to the Ministry of Works central testing laboratory at Kireka where
they were tested for:
- Specific Gravity
- Ten Percent Fines Value (TFV) - dry
- Ten Percent Fines Value (TFV) wet
- Water adsorption
- Sodium Sulphate Soundness
- Bitumen Affinity
The investigations and the test results indicate that there is sufficient gravel and rock meeting the
specifications available for the designed pavement structure.
E9. Hydrology
The objectives of the services as per the terms of reference (TOR) issued to the Consultants are:

| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-7

To undertake hydrological and hydraulic assessment for the project roads under Lot E
To prepare Hydrological Reports as per the Terms of Reference
Specific Objectives are:
Collect and compile hydrological data for the project roads
Carry out hydrological analysis for various drainage basins and channels traversed by the
road,
Computation of design discharges for the existing and proposed drainage structures along
the roads
Preparation of hydrological report for the project
The Road Drainage Design Manual (2005) guidelines require a designer to develop a clear
understanding of the existing drainage conditions for a given assignment before determining the
capacity of the existing cross and lateral drainage structures.
Minor drainage structures e.g. side ditches are to be designed to carry a 10-year flood while major
ones must be evaluated for the 25-100 year storm. The RDDM (Table 3.2) suggests suitable return
periods for various structural categories. Whenever possible, it is required that adequate openings
are provided to limit backwater effects and excessive bed scour.
The TRRL East African Model has been widely applied and found to be more relevant in East
Africa since a number of small catchments were extensively studied prior to establishing the
required parameters for its application.
The watersheds draining to project road have distinct characteristics largely due to their
geographical location, climate and land use characteristics. The relatively common aspect is that
the watersheds are intensively cultivated, human settled and predominantly rolling.
The Musita-Lumino/Busia-Majanji roads are characterized by:
Natural vegetation similar to tropical forest/ grassland.
Low-lying areas
Tropical climate with rainfall having two seasons i.e. from March to June and from
September to November (Bimodal)
Agriculture (sugar canes, maize, cassava, sweet potatoes, millet and sorghum), Cattle
rearing and mining like gold, uranium, iron core, lake sand and oil.

Design Discharges
The tables below gives the design discharges of the project road under the project for the different
return periods.

| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-8

Summary of design floods for different return period Road E1.1- Musita-Lumino
Design flood discharge (m3/s)
Chainage
Catch.
Catch.
from
Northing Easting
area
Ref.
(km2)
Musita
10-yr
25-yr
50-yr
100-yr
283
5+060
546926
55901
1.34
6.28
7.02
7.69
8.75
284
5+440
547329
55567
1.18
5.56
6.22
6.80
7.74
286
7+276
548534
54543
8.62
40.47
45.27
49.56
56.36
287
11+250
551778
51971
0.74
3.66
4.09
4.48
5.09
289
11+660
554420
50807
1.24
3.83
4.28
4.69
5.33
290
15+870
556063
50594
4.78
14.72
16.46
18.02
20.50
292
16+833
558983
50334
1.54
7.86
8.79
9.62
10.94
293
18+800
559865
50573
0.42
1.28
1.44
1.57
1.79
294
19+700
561223
50599
0.21
0.64
0.72
0.78
0.89
295
21+100
562439
50433
0.40
1.24
1.39
1.52
1.73
296
24+000
564029
50880
2.03
6.26
7.00
7.66
8.72
297
25+810
565785
50809
0.29
0.88
0.99
1.08
1.23
298
28+640
568503
50122
0.73
2.24
2.50
2.74
3.11
299
29+465
569306
50281
1.18
5.53
6.18
6.77
7.69
300
30+910
570662
50663
0.71
2.17
2.43
2.66
3.03
31+970
571704
50447
0.44
1.29
1.46
1.59
1.99
34+360
574025
50099
14.32
44.12
49.35
54.03
61.44
301
574151
50076
302
37+960
577490
50202
3.75
11.56
12.93
14.16
16.10
40+240
579850
50501
24.97
88.43
98.91 108.29 123.15
303-306
582090
50406
582238
50370
307
45+990
585222
49136
9.09
42.58
47.63
52.14
59.3
308
50+260
588250
46187
11.47
49.98
55.9
61.2
69.6
309
54+130
591146
41090
13.18
42.82
47.89
52.43
59.63
310
54+870
591696
43504
10.54
32.48
36.33
39.77
45.23
311
58+590
594212
40880
12.42
30.38
33.98
37.2
42.31
312
63+270
597842
38019
1.13
7.01
7.84
8.59
9.76
313
73+330
607154
35225
3.26
17.82
19.93
21.82
24.81
314
76+660
610229
36199
0.97
3.00
3.36
3.67
4.18
Summary of design floods for different return period Road E1.2- Busia-Majanji
Design flood discharge (m3/s)
Chainage
Catch.
Catch. area
from
Northing Easting
(km2)
Ref.
Busia
10-yr 25-yr
50-yr
100-yr
325
1+125
620283
51064
0.19
0.88
0.98
1.07
1.22
324
1+480
619949
50892
0.57
2.87
3.21
3.51
3.99
323
6+970
616014
47143
2.0
10.03
11.22
12.29
13.97
322
10+310
614350
44331
0.88
4.41
4.94
5.4
6.14
0.16
321
10+885
614081
43819
0.81
0.90
0.99
1.12
320
11+860
613606
42931
8.35
24.68
27.61
30.22
34.37
16+310
611423
38133
3.96
17.82
19.94
21.83
24.82
318
17+390
610871
36614
317
21+600
610325
34182
4.96
22.18
24.81
27.16
30.89
| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-9

316
315

23+180
25+500

610300
610374

32610
30420

0.80
1.38

3.12
5.36

3.49
5.99

3.82
6.56

3.12
7.46

E10. Drainage Design


Assessment of Existing Drainage Structures
A visual assessment of the drainage structures was carried out by the Bridge/Drainage Engineer
and the Hydrologist.
Each minor and major drainage structure was inspected and relevant basic measurements were
taken. Data on hydraulic performance and history of any overtopping and history of rehabilitation
measures undertaken were collected from local residents and branch of the ministry of works.
Moreover, observations were made relating to:

Hydraulic performance
Physical condition
Possible causes of damage
Materials used for construction and their performance
Period of service
Possible reasons for poor performance
Possibility of maintenance or repair
Performance in respect to traffic safety
Replacement options

A detailed photographic inventory and assessment of all the existing drainage structures are
prepared following the field inspection.
Classification of Drainage Structures
For the purpose of this project, all drainage structures are classified in two broad classes namely,
minor and major drainage structures.
Minor Structures
Minor drainage structures are those pipes having single or multiple cell opening either made from
concrete or corrugated metal sheet (Armco) and all the road side drainage facilities.
Major Structures
Structures included in Major Structures category are box culverts, slab culverts and reinforced
concrete /composite/ steel / bridges.
Slab culverts are those with top slab resting on abutments done separately, and box culverts are
those having monolithic top slab, bottom slab and the vertical walls.
Side Ditches
Stone pitched side channels and flow checks are found along a certain sections of the project roads.
Some are recently constructed and are in very good condition. But in general it is observed that due
to lack of regular repair, water flows out of the channel damaged the road pavment and make it
difficult for road users. Please refer to table 1 in Appendix 8.2 for details.
Pipe Culverts
According to the structures inventory data, there are over 300 existing pipe culverts along all the
project routes. The majority of the existing pipe culverts are made from either reinforced concrete
| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-10

with internal diameter ranging from 300mm to 1000mm or Armco sheet ranging from 600mm to
2000mm internal diameter.
During assesmsnt of the drainage structures along the project route, thefollowing major
deficiencies or problems were observed at pipe culverts:
Damaged or missing headwalls
Siltation in pipes due to low invert level
Poor workmanship at the head walls and at pipe joints.
Insufficient length of pipes as compared to the width of the road
Insufficient hydraulic capacity
Lack of regular cleaning
Missing or damaged aprons and energy dissipaters at inlets and outlets
Box Culverts
More than six box/slab culverts are found along the entire project route.
The following major deficiencies or problems were observed at box/slab culverts during the
assessment:
Deteriorated slab concrete
Cracked, damaged abutments and wing walls
Insufficient hydraulic capacity
Eroded bank and scoured bed.
Damaged inlet and outlet aprons (either broken down or dislodged)
Bridges
There are no existing bridges along Musita- Lumino and Busia - Majanji roads.
Recommeded Structures
The list of recommended drainage structures are listed in the Appendix to this report. They
comprise:
Pipe Culverts:
Single 900 mm :
Twin 900 mm :
Single 1050 mm :
Twin 1050 mm :
Single 1200 mm :
Twin 1200 mm :

53 No.
7 No.
7 No.
1 No.
4 No.
4 No.

Box Culverts:
2m x 2m single cell:
3m x 2m single cell:
4m x 2m single cell:
4m x 2m twin cell:
4m x 2.5m single cell:
4m x 2.5m twin cell:

6 No.
3 No.
4 No.
3 No.
3 No.
3 No.

| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-11

E11. Geometric Design


Design Standards
In accordance with the requirements of the TOR, and as confirmed by UNRA, the designs were to
be based on the Ugandan MoWH&C Road Design Manual of July 2005. In order to realize the
most economic design solution this Manual was complimented by recognised design manuals from
neighbouring counties including;
Kenyas Road Design Manual Part 1: Geometric Design Manual
Tanzanias Draft Road Manual
Code of Practice for Geometric Design (SATCC-1998) Trunk Road Design Standards
On the basis of the Ugandan Road Design Manual, the ideal functional classification for the project
road is Class C or a Primary road. These are described as roads linking provincially important
centers to each other or to a higher class roads (urban/rural centers). They provide linkage between
districts, local centers of population and development areas with higher class road. Their major
function is to provide both mobility and access
A paved Class II road standard was adopted for design; the applicable geometric design standards
for which are presented in Figure 4.2a and 4.2b of Section 4 of the Design Manual.
Design Speed
For a Bitumen Class II road traversing a flat terrain (max grades of 5.5%), a design speeds of 90
km/h was recommended. It should however be noted that many sections of the existing road are
long and straight and higher speeds than these will be possible.
Through the more populated centres along the route, a design speed of 50 kph has been set. This
speed applies in sections and locations given in the Table 10.2 in the main report.
The traffic speed in the above locations shall be regulated through the installation of road signage,
speed bumps and rumble strips.
Cross-Section
After consultation with UNRA a cross section comprising 3.5 m lanes and 1.5 m shoulders was
adopted for the project road. In towns/urban areas the shoulder width was increased to 2.0 m.
Summary Of Adopted Design Parameters And Standards
The following parameters and standards have been adopted in the designs:
Design life:

20 years.

Cross-section:

7.0 m wide carriageway at 2.5% normal camber


1.50 m wide shoulders at 4.0 % normal crossfall (2.0 m in urban
areas)
1.0 m wide side drain.

| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-12

Design Speed Parameters:


Design Speed

90 Km/h

70 Km/h

Min. Horizontal Radius

320 m

185 m
7%

Max. Superelevation
Max Gradient (Absolute)

5.5%

7.5%

0.4-0.6 max

Rate of Change of
Superelevation
Minimum Crest Curve Kmin
(stopping sight distance)

71

31

Minimum Sag Curve Kmin

41

25

Stopping Sight Distance (SSD)

170 m

111 m

Passing sight Distance

750 m

550 m

Selection Of Alignment
The following principles were adopted during selection of an appropriate alignment for the detailed
design:

Conformity to the specified geometric design parameters.


The alignment was designed to conform to or surpass the geometric design parameters as
recommended in the design manual.
Follow the general corridor of the existing road.
The general approach to the route alignment was to use the corridor of the existing road as
much as possible. This was done to retain the present social function with minimum
disruption to existing and long-term residents. Minor realignments were however introduced
to improve the road geometry and remove potentially dangerous curves. This was also done
at locations of new bridges.
Keep the works within the existing right of way.
In most sections, the alignment design was carried out to follow the existing road as much as
possible to enable the use of existing pavement materials to form new a subgrade.
Improve junctions.

| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-13

In order to improve safety at the approach junctions, the project road has been realigned to
approach the main highway at a right angle.

Re-align at trading centres.


There are a number of large trading centers along the project roads with heavy population
and agricultural activities. The possibility of having a bypass at some of these centers was
investigated. Preliminary realignments outside the centers were designed. These were then
presented to the Resettlement and Land Acquisition specialist who also visited the project
road to evaluate the impact of the bypasses against keeping the alignment through the
centers, compensating where necessary and maintaining the current social function of the
road.

| FINAL Detailed Design Report_ Rev.1-AUG 2012 |

ES-14

1 INTRODUCTION
1.1

Background
The Uganda National Roads Authority (UNRA) became a legal entity in 2006 and
began operations in July 2008 with the mission:
to develop and maintain a national road network that is responsive to the
economic development needs of Uganda, to the safety of all road users, and to
the environmental sustainability of the national road corridors.
At local level UNRAs objectives are:
4. To improve access to goods/passenger transport services and to reduce
transport costs along the route;
5. To improve access to social and economic development opportunities
along the route by providing high capacity infrastructure;
6. To ensure no roadside communities become worse off as a result of the
road upgrading works
On This contract was executed on 1st September 2009. Under the agreed terms
and conditions of the contract the effective date of commencement of the services
was set at 27th November 2009.
In pursuance of the above objectives, UNRA has embarked on upgrading selected
roads in several districts of Uganda.
To this end UNRA accepted the proposal of SMEC International Pty in association
with NEWPLAN Ltd. of Uganda to provide consultancy services for the upgrading
of several roads, referred to as Lot E, in the Eastern districts and comprising the
following roads:
Road
Reference No.
E1.1/E1.2

Road Name(s)
Musita-Lumino and Busia-Majanji roads (104 Km)

E2.1/E2.2/E2.3 Tirinyi-Pallisa-Kumi and Pallisa-Mbale roads (114 Km)


E3

Mbale-Bubulo-Lwakhakha road (41 Km)

E4

Namagumba-Budadiri-Nalugugu road (41 Km)

E5

Kamuli-Bukungu road (64 Km)

| FINAL Detailed Design Report _ Rev.1-AUG.2012 |

1.2

Contract Details
This contract was executed on 1st September 2009. Under the agreed terms and
conditions of the contract the effective date of commencement of the services was
set at 27th November 2009.
CLIENT

Uganda National Roads Authority

CONSULTANT

SMEC International Pty Ltd. In association with


NEWPLAN Ltd

CONTRACT PHASES

Phase 1: Feasibility Study and Detailed


Engineering Design
Phase 2: Tender Assistance
Phase 3 : Project Management

CONTRACT TIME

Phase 1 & Phase 2: 10 months


Phase 3 : 48 months

CONTRACT VALUES

Phase 1 : UGX 320,881,504 + USD 3,307,169


Phase 2 : UGX

7,630,560 + USD

122,557

Phase 3 : UGX 609,074,334 + USD 2,116,351


CONTRACT EXECUTION
DATE

1st September 2009

CONTRACT
COMPLETION DATE

Phase 1 + Phase 2 : 30th September 2010

Phases 2 and 3 were subsequently omitted by the Client.

1.3

Terms of Reference
The main objectives of these Consultancy Services are:
(vi)

Feasibility Study, including consideration of alternative routes and


pavement options, environmental and social impact study, road safety, land
acquisition, preliminary design, economic and financial analysis;

(vii)

Detailed engineering design for the approved road option; including all
necessary data collection, field surveys and analysis to cover all aspects of
detailed design;

(viii)

Environmental and Social Impact Assessment (EIA) in accordance with


Ugandan legislation and NEMA guidelines;

(ix)

Preparation of a full Resettlement Action Plan and associated surveys to


identify and value property that will be affected by the road upgrading
works and the establishment of the road reserve;

(x)

Preparation of bidding documents based on the approved detailed designs.

The Terms of Reference relating to the detailed design phase are included in Appendix 1.

| FINAL Detailed Design Report _ Rev.1-AUG.2012 |

1.4

Preliminary Design Report


The Preliminary Design Report was submitted to UNRA in October 2010. The
Report was submitted in two (2) volumes, namely:
Volume 1A:
Volume 1B:
Volume 2.1:
Volume 2.2:
Volume 2.3:
Volume 2.4:
Volume 2.5:

Main Text
Appendices
Book of Drawings Road 1 (Musita-Lumino/Busia-Majanji)
Book of Drawings Road 2 (Tirinyi-Pallisa-Kumi/PallisaKamonkoli)
Book of Drawings Road 3 (Bumbobi-Bubulo-BusumbuLwakhakha)
Book of Drawings Road 4 (Namagumba-Budadiri-Nalugugu)
Book of Drawings Road 5 (Kamuli-Bukungu)

The Consultant received the Clients comments on the Preliminary Design Report
variously in February and July 2011.

1.5 Packaging of the Project Roads


Based on the preliminary construction cost estimates, the lengths and geographic
locations of the project roads, the Consultant recommended, and agreed by the
Client, that the project be divided into six (6) distinct packages for the purpose of
bidding as follows:
Package 1 :

1.6

Road E1 :

Musita-Lumino/Busia-Majanji roads

Package 2A : Road E2.1/E2.2 :

Tirinyi-Pallisa/Pallisa-Kumi roads

Package 2B : Road E2.3 :

Pallisa-Kamonkoli road

Package 3 : Road E3 :

Bumbobi-Busumbu-Lwakhakha road

Package 4 : Road E4 :

Namagumba-Budadiri-Nalugugu road

Package 5 : Road E5 :

Kamuli-Bukungu road

This Report
This report relates to the Detailed Design for
Package 1 - Road E1.1/E1.2 : Musita-Lumino/Busia-Majanji roads.

| FINAL Detailed Design Report _ Rev.1-AUG.2012 |

ENGINEERING STUDIES

2.1

Project Location
Lot E roads are located in the Eastern districts of Uganda and cover the five roads
as indicated on the frontispiece.

2.1.1

Description of Project Road


The project road is discussed below. The lengths indicated are based on the final
design chainages.

Road Links
Name
(i) Musita Nankoma
(ii) Nankoma - Buyinja
(iii) Buyinja Lumino
(iv) Busia Majanji
TOTAL

Length
(km)
36
26
15
26
103

| FINAL Detailed Design Report _ Rev.1-AUG.2012 |

MUSITA
BUSIA

LUMINO

MAJANJI

Figure 1 : Location of Musita-Lumino/Busia-Majanji Roads

(a) Alignment
The road traverses the Mayuge, Bugiri and
Busia districts, starting at the Musita trading
centre at its junction with the Jinja - Iganga
road.
The terrain is flat to gently rolling terrain Start at Musita Km
and the horizontal and vertical alignments 0+000
are gentle with good visibility.
The riding surface width is generally 5m
5.5m. The Nankoma-Namayingo link has
recently been subjected to periodic
maintenance
by
UNRA
involving
regravelling

Alignment at Km 27

Alignment at Km 2

Alignment and surface at


Km 30.8

(b) Road condition


The road is a gravel road with generally
good riding surface with a few exceptions
where gullies have developed on the road
surface.
Km 5 Gullies in the
road surface

Stretch along BusiaMajanji road

( c) Land use
Basically subsistence agriculture with
maize, potatoes, cassava and rice. Cash
crop grown along the road is sugarcane.
Rice is grown in the marshy areas.
Km 4.5 Sugarcane
being transported

Km 5.5 Rice paddy


in swamp

(d) Drainage
Minor drainage structures consist of
concrete pipes. There are no major
structures in this section. Pipe culverts are
generally silted up due to invert
Levels being below ground level.
There are stretches where erosion in side Erosion in side drain
drains is evident.

Lined Drain at Km
31.6

Typical Mitre Drain

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

(e) Construction materials


There is an existing rock quarry at Km 2.6
and an existing borrow pit at Km 14. In
addition, potential rock sources exist at Km
2.9, Km 11.8 and Km 18.2.
Existing Rock Quarry
at Km.2.6

(f) Trading Centres

Rock Outcrop at
11.8

Km.

Rock Outcrop at Km Rock Outcrop at Km 31.4


30.6
Km 13 Mayuge Trading
centre

The link passes several trading centres,


namely Buluba at Km 2, Mayuge at Km 13
and Mpungwe at Km 20.7.

Km. 2 Buluba Trading


Centre
-

Namayingo Trading
Centre

2.1.2

Lumino trading centre end


of link
Km 49.3

Topography
The topography of the project area is relatively flat with high ridges and isolated
hills, adulating low lands and perch vents with a few higher residual features.
The hills are linear and of a convex nature scope and almost flat valleys. Some of
the hills include Irimbi, Bululu and Namakoko in Bugiri district.
The lowest point of about 1,200m above sea level is in the south along the Lake
Victoria and the highest 1500m above sea level is found in the north.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

The project area has a long shoreline of Lake Victoria in the south with several
islands. (Statistical
2.1.3

Geology
In terms of geology, the project area is made up Precambrian rocks with bare
granitic rocks at several places heavily eroded. Deposits of eroded soil can be
witnessed in some parts of the low lands on farmers gardens and these tend to
increase towards the lowlands.

2.1.4

Soils
The soils covering most of the project area are mainly loamy and sand loams with
spots of clay at the valley areas. These soils have fine texture with rather loose
structure, which are easily eroded and leached. The soil types can be summarized
as;
Yellow-red sandy, clay loam soils varying from dark grey to dark. These occur
on gently undulating hilly topography.
Brown yellow clay loams with laterite horizon with a variety of dark brown to
dark grayish brown. These occur on flat ridge tops or as of undulating
topography.
Light grey- white mottled loamy soils with laterite horizon ground, structuresless loamy sands. These are acidic-allocative and mainly found on lower and
bottom slopes.
Clay soils are limited to the swamps in the valleys.
(Busia District State of Environment Report, 2005 and Bugiri District
Development Plan 2009/10-2011/2012).

2.2

Topographical and Aerial Survey

2.2.1

General
The project roads with a total length of approximately 364 km was covered by
colour aerial photographs to scale 1:8,000 in March 2010. Ground control
designed for aerial triangulation was carried out for subsequent line and
orthophoto mapping.
Two inter-visible permanent beacons with description and photo, consisting of an
iron pin in concrete 30 x 30 x 40 cm or a hole drilled in rock were constructed at
intervals of 3 km along the specified routes i.e. Roads 1, 2, 3, 4, and 5 to serve as
control for the inter-visible interim beacons which were constructed in between
these control beacons along the routes. The interim beacons consists of an iron
pin set in concrete 20 x 20 x 30 cm or a hole in rock when suitable.

2.2.2

References and Datum


Instruments and Software
Three units Leica GPS Receivers System 300
SKI software version 2.3
One Wild NA2 Automatic Level
One Wild A0 Automatic Level
One Zeiss NI2 Automatic Level

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

Two units Geodimeter 400 Total stations


One Garmin, Etrex, handheld GPS receiver

References
Datum
Projection
Grid
Units

:
:
:
:

Arc 1960 (NEW)


Transverse Mercator
UTM, Zone 36 N
Metric

Datum Points in Plan and Height


UP50
E = 569809.367
N = 51853.173
51X1
E = 485710.686
N = 152493.050
52X2
E = 509491.943
N = 126569.501
52X3
E = 510506.248
N = 113620.011
53X2
E = 598100.184
N = 146594.827
53X8
E = 607124.549
N = 112349.993
53X10
E = 592040.310
N = 131016.272
54X3
E = 635475.290
N = 131108.840
64X1
E = 640423.259
N = 86844.067
64X2
E = 624537.248
N = 109977.442
62GP1 E = 518178.070
N = 110401.090
74GP1 E = 614717.168
N = 35615.815
K2
E = 535978.005
N = 60268.398
K3
E = 532200.518
N = 56074.307

Z = 1148.182 Ground level


Z = 1486.205 Ground level
Z = 1502.050 Ground level
Z = 1064.210 Brass bolt
Z = 1179.330 Brass bolt

UP50 Pillar destroyed, but holes in rock after anchor iron found and restored to
within 5 cm.
51X1 Pillar destroyed, but holes in rock after anchor iron found and restored to
within 5 cm.
52X2 Pillar destroyed, but holes in rock after anchor iron found and restored to
within 5 cm.
52X3 Pillar destroyed, but holes in rock after anchor iron found and restored to
within 5 cm.
53X2 Pillar destroyed, but holes in rock after anchor iron found and restored to
within 5 cm.
53X8 Pillar destroyed, but holes in rock after anchor iron found and restored to
within 5 cm.
53X10 Pillar destroyed, but holes in rock after anchor iron found and restored to
within 5 cm.
54X3 Pillar destroyed, but holes in rock after anchor iron found and restored to
within 5 cm.
64X1 Pillar destroyed, but holes in rock after anchor iron found and restored to
within 5 cm.
64X2 Pillar destroyed, but holes in rock after anchor iron found and restored to
within 5 cm.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

62GP1 Short ground pillar with brass bolt found intact.


74GP1 Short ground pillar with brass bolt found intact.

2.2.3

K2

Iron pin in concrete found intact.

K3

Iron pin in concrete found intact.

Ground Control And GPS Measurements


A total of 219 GPS Beacons were constructed as inter-visible pairs after every 3
km along the five road alignments divided as follows:
Musita-Lumino Road : ML01 ML44
Busia-Majanji Road : LM1- LM5 and LB1 LB12
A description card + photo was prepared for each of these points. Inter-visible
Beacons were also constructed between the GPS Beacons with a maximum length
not exceeding 500 m between the Beacons.
Static Differential GPS measurements in combination with double run spirit leveling
was deployed to obtain coordinates to cm accuracy in plan and height for the
photo control points as well as GPS Beacons used as control points for the
densification of beacons in between. This was coordinated using a Total station
and measured as traverses between the control points with closing errors not less
than 1:10,000 in plan. Double run spirit leveling was carried out to obtain reliable
heights also for these points.

2.2.4

Interim Beacons And Total Station Measurements Coordinates in


plan are based on the following Trig stations: MusitaLumino/Busia-Majanji Road : UP50, 74GP1, K2 and K3
Heights are based on the following Trig stations:
Musita-Lumino/Busia-Majanji Road : 74GP1 (brass bolt)

Static Differential GPS observations was carried out with observation times
between 20 to 30 minutes on every station to obtain Cartesian coordinates in the
WGS 84 system with subsequent transformation into the UTM System Arc 1960
datum using SKI software based on the control points mentioned above.
Heighting
Double run Spirit Levelling was carried out for all permanent Beacons, with relevels done for cases where error was greater than 10mm/km between forward
and backward levelling.
2.2.5

Aerial Survey
Flight Permission
Permission to fly over the project roads was obtained from Uganda Civil Aviation
Authority on: 8 February 2010 for a 3-month period up to 8 May 2010.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

10

Flight Dates
Aerial photography for Musita-Lumino/Busia-Majanji roads was undertaken on
11th March 2010 and completed on 13th March 2010 with flight altitude of 705m
above mean ground level
Equipment
Aircraft: Piper Navajo PA 31 reg. 5Y-MAP, white with blue stripes
Camera equipment: Wild RC-10
Flight planning equipment: IGI WIN MP
Navigation equipment: IGI CCNS NOVATEL DL-V3
Film used: Agfa AVIPHOT X 100PE1
Film processing and printing:FUGRO/BKS, Northern Ireland
2.2.6 Final Products
Final products delivered after aerial photography and post-processing included:

1. Colour aerial photography at 1:8,000 scale inclusive of a ground


GPS station operated simultaneously as the aerial photography was
undertaken.
2. Quick View digital orthophoto for a minimum of 1.5 km width.
3.

Digital photogrammetric line mapping for a 60 m wide corridor inclusive of


mapping streams 500 m upstreams and 500 m downstreams for a 100 m width
at 10 bridge sites.

Other deliverables included:


a) Hard and soft copy of the Aerial Photographs
b) Flight Plans
c) Caliberation Certificates
d) DTM and x, y , z ground points @ 5 m intervals
e) Detailed Survey Report
Both the horizontal and vertical accuracies achieved were within the tolerances
agreed with the Client, namely,
Horizontal :
Vertical :

As per ToR
+/- 70mm

2.3

Traffic Surveys

2.3.1

Terms of Reference
The ToR called for:

Assembling all traffic data on the project roads with a view to determine the
present pattern of traffic growth by vehicle class.

Agreement with UNRA on the location of and the number of traffic count
stations (an average at one per 20km, and at least 5km from major junctions)
where counts of motorized and non motorized vehicles, pedestrians and
animals best represent present road usage.
| FINAL Detailed Design Report_Rev.1-AUG.2012 |

11

Conducting classified counts at each location for a continuous period of not less
than five days 12-hour and two days (1 week day and 1 weekend) for 24-hour
taking into account fluctuations caused by local factors e.g. market days.
Determining traffic predictions by class for each station, for assumed low,
medium and high growth predictions.
Carrying out axle load survey over a minimum period of 3 days per road, which
was to include information on origin and destination of all vehicles stopped.
Classified counts were carried out in the months of March, April and May 2010.
2.3.2

Existing Traffic
Table 1 shows the historic data obtained from UNRA.

Table 1: Historical data obtained from UNRA

Road name

ADT
excludi
ng
motorcy
cles

ADT
includin
g
motorcy
cles

ADT NMT

Musita-Mayuge-NankomaNamayingo-Lumino (U)

78

552

2628

Busia Majanji (U)

63

263

1540

Table 1 shows that the road has a high number of NMT and motorcycles traffic.
2.3.3

Traffic Counts
Manual classified counts were carried at seven stations for seven days, from 25th
to 31st March 2010. Night counts were carried for one weekday and one weekend
day at each station.
The locations are described in Table 2 below and shown in Appendix 2A. The
scope of non-motorized traffic (NMT) included bicycles, pedestrians and carts. The
results from the study are attached in Appendix 2B.
It was assumed that no traffic would be diverted from the alternative routes since
these routes are shorter than the project road.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

12

Table 2: Traffic Count Stations


Locations

Dates

1. 5km after Lumino

th

25
2010

2. 5km before Busia


3. 5km before Namayingo
4. 5km before
(NMT)

Namayingo

st

March,

Classified
Count

th

March,

Classified
Count
(Night
Count)

31

th

Type of survey

26 27
2010

5. 5km from Mayuge


6. 5km from Musita
7. 5km before Lumino

12h counts were expanded to 24h using the ratios of 24h to 12h traffic for each
vehicle type and separately for weekday and weekend traffic. The details are
shown in Table 3.
Table 3: Observed ratio of 12 to 24 hour traffic
Station
number

Station location

Week day

Week end

12 hour traffic as a
percentage of 24 hour
traffic

12 hour traffic as a
percentage of 24 hour
traffic

5km after Lumino

87.3%

80.6%

5km before Busia

90.0%

88.2%

71.0%

74.0%

5km before
Namayingo
5km from Mayuge

76.1%

69.5%

5km from Musita

77.7%

76.4%

5km before Lumino

73.9%

79.7%

2.3.4

Base Traffic
Table 4 shows the observed ADT at each of the counts station.

Table 4: Summary of observed ADT at Count Stations


Station
no
1
2
3

4
5
6

Count
station
5km after
Lumino
5km before
Busia
5km before
Namayi
ngo
5km from
Mayuge
5km from
Musita
5km before
Lumino

Direction A

Direction B

Both directions

Directional
distribution
Vehicles PCU

Vehicles

PCU

Vehicles

PCU

Vehicles

PCU

117

147

120

173

237

319

49:51

46:54

1,010

1,173

1,078

1,274

2,089

2,446

48:52

48:52

472

578

473

671

945

1,249

50:50

46:54

408

539

420

536

828

1,075

49:51

50:50

706

1,153

724

1,236

1,430

2,389

49:51

48:52

607

761

442

579

1,049

1,340

58:42

57:43

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

13

As noted from Table 4, traffic increases towards the towns and trading centers
such Busia and Musita.
The traffic surveys were conducted in the period February May 2010. Therefore
the observed ADT needed to be factored for the season to arrive at the Annual
Average Daily Traffic (AADT). However due to the absence of such data, a
seasonal factor of 1 was assumed.
Using the assumed seasonal factor of 1 (one), the AADT was calculated using the
equation below.
=
Where
AADT Average Annual Daily Traffic.
ADT Average Daily Traffic.
Figure 2 below shows estimated base year traffic composition at each of the study
locations.

2500

AADT

2000
1500
1000
500
0
5km after
Lumino

5km before 5km before 5km from


Busia
Namayingo Mayuge
Sation name
AADT (with Motorcycles)

5km from
Musita

5km before
Lumino

AADT (without motorcycles)

Figure 2: Base year traffic composition at each of the study locations.

The proportion of motorcycles to the other traffic is high as seen from Figure 2.
Appendix 2C contains details of the estimated AADT at each of the locations along
the project roads.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

14

2.3.5

Traffic Growth
In order to estimate the AADT in the project period, the Consultant needed to
determine the traffic growth rate over this period. This growth is represented by a
growth in normal traffic, diverted traffic and generated traffic.

2.3.6

Growth in normal traffic


To derive growth in normal traffic, analysis of either historical traffic data over the
years or traffic proxies can be used.
Deriving traffic growth from traffic data involves analysis of the growth of the
various traffic classes over a long period of say 10-20 years. This growth will give a
trend in the growth of traffic over the years. This trend is then used to project the
traffic growth in the project period. It was noted that analysis of historical data was
not feasible as there was no adequate historical data.
Traffic growth using traffic proxies involves the comparison of traffic growth with
proxies such as fuel consumption, vehicle registration trends, GDP growth etc.
Appendix 4D shows the trends in growth of the various traffic proxies as well as
the derived traffic growth trends.

2.3.7

Diverted Traffic
It was assumed that no traffic would be diverted from the alternative road since the
project road was longer in distance than the alternative road.

2.3.8

Generated traffic
Generated traffic is additional traffic which will occur in response to the provision or
improvement of a road. This will in the short term arise from increased number of
trips of existing vehicles or generation of new trips which were never present
before the improvement of the road. In the long term the traffic generation will be
due to increased economic activity along the project road after it has been
improved / upgraded.
Derivation of generated traffic is shown in Appendix 2D.
These factors were used in the derivation of generated traffic at the various study
locations.

2.3.9

Projected Traffic growth


It was assumed that road construction shall commence in the year 2011 and end
in 2015. Projections were made for a design period of 15 years and 20 years.
Therefore projections were made up to the year 2030 and 2035 using the
corresponding growth factors.
Results obtained are shown in Appendices 2E.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

15

2.3.10 Origin/Destination Surveys


OD Survey Locations
Table 5 shows the locations used for the survey.
Table 5: Origin Destination Survey Locations
Station
no.
1
2
3

OD stations, Motorized
traffic
5Km from Musita (Bufulubi)
5km before Busia (Dabani)

OD station, Non motorized


traffic

5Km from Namayingo (Buyima)

At these locations, a 7 day - 12 hour Origin Destination Survey was conducted.

Data Collection and Compilation


The OD survey was carried out during the month of April 2010 using enumerators
hired and trained from along the project road.
Information gathered through road side interviews of vehicle drivers was analyzed
to understand the origin-destination characteristics of traffic plying the project
roads. Since these interviews were conducted on a sample of vehicles, the
collected information was expended to reflect the total volume of traffic plying on
the road on that particular day.
To analyze the traffic interactions between the various sub-regions of the country
and outside of it, the spatial delineation of the entire region is needed for
convenience of analysis. For this study, it was felt that the district/sub county
boundaries would be a convenient unit of spatial delineation as each district/sub
county has documented information about its demographic and socio-economic
indicators.
Station 1: 5km from Musita (Bufulubi)
a. Trip Frequency

Figure 3 shows the frequency of trips made through 5 km from Musita

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

16

Percent of trips made

100%
90%

Several times a day

80%

Once per day

70%

Several times a week

60%

Once a week

50%

Several times a month

40%
30%

Once a month

20%

Several times a year

10%

Once a year

0%

Rarely

Vehicle type

Figure 3: Frequency of trips made through 5 km from Musita


As seen in Figure 3, Lorries capacity > 3.5 tons and motorcycles make several trips a day
while the large buses make one trip per day through the study point.
b. Trip purpose

Figure 4 shows the purpose of trips made through the study point.

Percentageof trips

As noted in Figure 4, most of the trips are made for business while the least trips are
made for Leisure/Social purposes.
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%

To/from Home
To/From Work
To/From School
Business
Shopping
Government / Official
Leisure / Social
Tourism
Other

Vehicle type

Figure 4: Purpose of trips made through 5km from Musita.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

17

c. Vehicle occupancy

Number of passengers

Observed passenger occupancy in various types of vehicles plying through the study
location is shown in Figure 5.
80
70
60
50
40
30
20
10
0

Vehicle type

Figure 5: Observed passenger occupancy per vehicle passing through the study location
It was noted that both the medium buses and the large buses provide motorized transport
along the project road.
Station 2: Dabani (5km before Busia)
a. Trip Frequency

Percentage trips made

Figure 6 shows the frequency of trips made to through the study point.
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%

Several times a day


Once per day
Several times a week
Once a week
Several times a month
Once a month
Several times a year
Once a year
Rarely

Vehicle type

Figure 6: Trip frequency at 5km from Busia

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

18

As can be seen from the Figure 6, Lorries and motorcycles make several trips a day
b. Trip purpose

Percentagetrips

Figure 7 shows purpose of trips made through the study location.


100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%

To/from Home
To/From Work
To / From School
Business
Shopping
Government / Official
Leisure / Social
Tourism
Vehcile type

Other

Figure 7: Purpose of trips made through the study location

From Figure 4.6, the greatest percentage of trips is made for Business followed by
to/from work or home. The least trips are made for Tourism and Leisure/Social.
c. Occupancy of Vehicles

Figure 87 shows the observed passenger occupancy in various types of vehicles


passing through the study point.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

19

Number of passengers

50
40
30
20
10
0

Vehicle type

Figure 8: Average Vehicle Occupancy for vehicles through study point


Vehicle occupancy at this station is lower than that at 5km from Musita.
It can be concluded that
Lorries and motorcycles make several trips a day while the large buses make one
trip per day through the study point,
Most of the trips through the project road are made for business while the least
trips are made for Leisure/Social purposes.
Small buses, medium buses and the large buses provide motorized transport
along the project road.
Station 3: 5km from Namayingo (Buyima) NMT
a. Trip Frequency

Figure 9 shows the frequency of trips made to through the study point.
Trips by Non motorized traffic are mostly made several times a day and once a day.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

20

Percent of trips made

100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%

Several times a day


Once a day
Several times a week
Once a week
Several times a month
Once a month
Several times a year
Once a year
Bicycle

Pedestrian

Cart

Rarely

Vehicle type

Figure 9: Frequency of trips made through the study point.

b.

Trip purpose

Percentage trips made

Figure 10 below shows the purpose of vehicles moving along the project road.
100%

To/from Home

90%

To/From Work

80%

To/From School

70%

Business

60%
50%

Shopping

40%

Government / Official

30%

Leisure/Social

20%

Tourism

10%

Other

0%
Bicycle

Pedestrian

Carts

Vehicle type

Figure 10: Purpose of Non Motorized vehicles moving along the project road
From Figure 10, the greatest percentage of the Non motorized vehicle trips are
made for the Business (45%) and to/from home trips (24%). There are no trips
made for tourism.
Other information derived from this survey included the following;
Origin and Destination characteristics
Cargo type
Traffic generating zones
Passenger origin and destination
| FINAL Detailed Design Report_Rev.1-AUG.2012 |

21

Passenger trip frequency


Passenger trip purpose
Passenger employment
Appendix 2F contains a summary of the results obtained from this study.

2.3.11 Axle Load Survey


Survey Methodology
A three day traffic axle load survey and counts was carried at Nabigingo out along
the project road between 6th May and 22nd May 2010.
Weighing was done for both directions simultaneously using a portable
weighbridge to Transport Research Laboratories (TRRL) specifications.
The vehicles weighed were:
I.

Medium Buses

II.

Large Buses

III.

Medium Goods Vehicles

IV.

Heavy Goods Vehicles.

V.

Very Heavy Goods Vehicles

Data Collection and Compilation


The axle load survey was carried out during the month of May 2010 using
enumerators hired and trained from along the project road. These were assisted
by trained axle load equipment operators. The logistics and supervision of the
surveys were managed by a Traffic Engineer.
The traffic of eligible vehicles along the project road is not high to warrant
sampling. All vehicles eligible were thus weighed.
Equivalence Factors
The axle load so obtained was used to calculate Equivalence Factors (E.F.) using
Liddle's formula as follows:
E.F = (Ls/8200)4.5 ..........1
In computing the average equivalence factors for each vehicle type, each two lane
was considered separately.

Tables 6 and 7 show the summary of axle load for each direction respectively.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

22

Table 6: Axle load for Vehicles from Musita


Vehicle
category

Average gross
weight

Average equivalence
factor (80KN)

Total
vehicles

LGV (1.2)

4.26

0.07

22

MGV(1.2)

4.10

0.00

Total

23

Table 7: Axle load for vehicles to Musita


Vehicle
category

Average gross
weight

Average equivalence
factor (80KN)

Total
vehicles

LB 1.2

14.68

1.69

LT 1.2

5.38

0.11

18

MB 1.2

4.77

0.01

MT 1.2

18.65

9.61

Total

28

2.3.12 Overloading
Figures 11 and 12 show the level of overload for the vehicles weighed at this station.

Figure 11: Level of overload from Musita

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

23

Figure 12: Level of overload to Musita

Table 8 shows the level of overload for each of the axle load configuration along
this road.
It is deduced that the level of overload from Busia is higher than that to Busia.

Table 8: Level of overload along Musita Nankoma Lumino Busia/Majanji


Axle
configuration

Axle load

Axle load

>5 tons >8 tons


To Busia

>10 tons

LB (1.2)
LT (1.2)

6.8

MB (1.2)
MT (1.2)

>5 tons >8 tons


From Busia

>10 tons

91.7

25

8.3

11.1

50

50

50

2.3.13 Cumulative Equivalent Standard Axles (CESA)


The Cumulative Equivalent Standard Axles were estimated based on the assumed
growth rates as summarized in Table 9.
Table 9: Adopted Traffic Growth rates for LB, LGV, MGV and HGV
Growth Scenario

20102013

20142018

20192023

20242030

20242035

Pessimistic

4.7

6.8

4.4

2.9

2.9

Realistic

4.7

8.5

5.6

3.8

3.8

Optimistic

4.7

10

6.8

4.6

4.6

It was assumed that the construction works will commence in 2011 and last for 4
years.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

24

Based on these growth factors the Cumulative Equivalent Axles were determined
by road section using the formula below.
=

365(1 + )
1

Tables 10 and 11 give the equivalent standard axles in the periods 2015-2030 and
2015-2035 respectively.
Table 10: Equivalent Standard axles in the period 2015-2030.
Count station

Equivalent Standard Axles period 2015-2030 (x 1 million)


Direction A

Direction B

Pessimistic

Realistic

Optimistic

Pessimistic

Realistic

Optimistic

5km after Lumino

0.44

0.49

0.56

0.00

0.00

0.00

5km before Busia

2.25

2.57

2.91

0.03

0.03

0.04

5km

before
Namayingo
5km from Mayuge

1.86

2.13

2.41

0.01

0.02

0.02

1.86

2.13

2.41

0.01

0.02

0.02

5km from Musita

10.10

11.57

13.11

0.01

0.01

0.01

5km before Lumino

1.71

1.96

2.22

0.03

0.03

0.04

Table 11: Equivalent Standard axles in the period 2015-2035.


Count station

Equivalent Standard Axles period 2015-2035


Direction A

Direction B

Pessimistic

Realistic

Optimistic

Pessimistic

Realistic

Optimistic

5km after Lumino

0.62

0.73

0.84

0.00

0.00

0.00

5km before Busia

3.22

3.79

4.40

0.04

0.05

0.06

5km

before
Namayingo
5km from Mayuge

2.66

3.13

3.64

0.02

0.02

0.03

2.66

3.13

3.64

0.02

0.02

0.03

5km from Musita

14.43

16.98

19.73

0.02

0.02

0.02

5km before Lumino

2.46

2.89

3.35

0.04

0.05

0.05

2.3.14 Summarized Road Usage


Estimated Number of Passengers using the Road
This was estimated from the Average Annual Daily Traffic (AADT) and the average
vehicle occupancy.
Table 12 shows the number of passengers passing through the study locations
using motorized transport per day.
Table 12: Passengers passing through
the study locations (using motorized transport) per day
Study location
5km from Musita
5km before Busia

Passengers
day
4,177
4,076

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

per

25

It is noted that there are more passengers moving the 5km from Musita that 5km
from Busia.
Estimated Cargo Tonnage using the Road
This was estimated from the Average Annual Daily Traffic (AADT) as determined
during the traffic survey and axle load weight less the tare weight as determined
from the axle load survey.
Figure 13 shows the cargo passing each study location along the project roads per
day.

Cargo per day, tonnes

1,600
1,400
1,200
1,000
800
600
400
200
0
5km from
Musita

5km from
Mayuge

5km before
Namayingo

5km before
Busia

Station name

5km after
Lumino
towards
Majanji

5km before
Lumino

Figure 13: Cargo passing through each study point along the project roads

2.3.15 Sensitivity Analysis


As part of the ToR, for the final pavement design, the Consultant was required to;
1.

Increase the design axle load by 5% or more if historical and present


overload data does not indicate a progressive tightening of overload
controls.

2.

Carry out a sensitivity analysis on the axle load and traffic ADT variation
(+/-5%, +/-10% and +/-40%) and assess how this affects the pavement
designs.

Appendix 2G shows results from the analysis.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

26

2.4

Soils and Materials Investigations

2.4.1

General
The materials investigations were conducted in accordance with the Terms of
Reference. It consisted of site reconnaissance, field exploration and analysis of the
findings of the field exploration.
The Draft Final Soils and Materials Report has been produced as a separate
Volume. The following is the summary.

2.4.2

Sub-grade Soil Investigation


The sub-grade soil investigation along the existing road alignment comprised subgrade soil sampling by means of trial pits, DCP testing and laboratory testing.
Trial Pits
Trial pits were excavated at two (1) kilometre interval on alternate side of the
carriageway to depths of generally 1 m.
The pits were dug to varying depths from the surface to sub-grade level with a total
of 180 pits dug over the total road length of the five project roads of 365 km.
The vertical profile of the pavement in each trial pit was recorded and
representative sub-grade sample taken for laboratory testing. The trial pit logs are
included in the Soils and Materials Report.
DCP Investigations
DCP tests were conducted at intervals of 500m as stipulated in the ToR to
measure the in-situ bearing strength (CBR) of the sub-grade. Standard DCP
apparatus with the following parameters was employed:
570mm dropping height
8 kg falling weight
60 tipped cone having 20mm diameter
To avoid weak spots (thin layers) from being overlooked and to identify layer
boundaries fairly accurately, readings were taken at 1-5 blow intervals, depending
on the rate of penetration.
Swamp Investigations
There are no major swamps along Musia-Lumino/Busia-Majanji roads.

2.4.3 Gravel and Hardstone Sources


Field Exploration
The field exploration for this project consisted of:
- Assessment of the suitability and extent of the material source.
- Excavation of trial pits.
- Logging of the layers encountered.
| FINAL Detailed Design Report_Rev.1-AUG.2012 |

27

- Retrieval of samples for laboratory testing.


- Backfilling of the trial pits.
At each site, trial pits were excavated and depths of overburden and gravel were
logged. In some instances, material was sampled from rock outcrops, talus, or
existing quarries, in which cases, test pit excavation was not required. The
volumes of both overburden and gravel were also estimated.
Gravel and Hardstone Sources
A total of 20 existing or potential gravel sources and 3 rock sources were
identified and investigated along Musita-Lumino/Busia-Majanji road as listed
below:
Table 13: Borrow Pits and Quarries
Road No.

Road/Link Name

No. of
Borrow
Pits

No. of
Quarries

E1.1

Musita Lumino

13

E1.2

Busia Majanji

TOTAL

20

The location of the materials sources are included in Appendix 3.


2.4.4

Laboratory Testing
Mobile Laboratory
As a requirement under the Contract, the Consultant fabricated a mobile laboratory
in a 40-foot container at its offices in Kampala. Upon completion of fabrication and
fitting out the laboratory was transported and erected at the compound of UNRAs
regional offices in Jinja.
Testing
Gravel Samples
Samples of sub-grade material recovered from trial pits and samples from the
gravel sources were transported to the mobile laboratory in Jinja where they were
subjected to the following tests:
- Natural moisture content determination
- Particle size analysis
- Atterberg limits
- Moisture content Dry density relationship (BS 1377 test method)
- CBR (4-day soak compacted at 90%, 95% and 98% MDD)
- Swell tests

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

28

Rock Samples
During the detailed design stage one potential quarry from each of the five project
roads was drilled down to 15 m.
Along Musita-Lumino road, there is an existing commercial quarry at Km 2+600 at
Lugolole. Besides a sample from a stockpile of existing crushed aggregate, a hole
was drilled down to 15 m. Sample of the crushed aggregate and the rock core
from the drilled hole were taken to the Ministry of Works central testing laboratory
at Kireka where they were tested for:
- Specific Gravity
- Ten Percent Fines Value (TFV) - dry
- Ten Percent Fines Value (TFV) wet
- Water adsorption
- Sodium Sulphate Soundness
- Bitumen affinity
The test results are included in the Soils and Materials Report. Summaries of the
results are given in Appendix 3.

2.5

Hydrological Studies

2.5.1

Objectives
The objectives of the services as per the terms of reference (TOR) issued to the
Consultants are:

2.5.2

General Objective
To undertake hydrological and hydraulic assessment for the project roads
under Lot E
To prepare Hydrological Reports as per the Terms of Reference

2.53

Specific Objectives
Collect and compile hydrological data for the project roads
Carry out hydrological analysis for various drainage basins and channels
traversed by the road,
Computation of design discharges for the existing and proposed drainage
structures along the roads
Preparation of hydrological report for the project

2.5.4

Background
A detailed hydrological study of LoT E roads was carried out in accordance with
the Road Drainage Design Manual (RDDM) - Vol. 2: Drainage Design procedures

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

29

and methodologies including other hydrological analysis methods. Among the


available methods in the RDDM, the TRRL East African Flood Model and Flood
Frequency Analysis Methods (Log-Pearson III Distribution) have been considered
to be the most appropriate methods given the available data.
2.5.5

Hydrological Analysis Criteria and Practices


The Road Drainage Design Manual (2005) guidelines require a designer to
develop a clear understanding of the existing drainage conditions for a given
assignment before determining the capacity of the existing cross and lateral
drainage structures.
Among the initial understandings is the production of a concept map illustrating the
drainage system, catchment delineation and existing utilities during the
investigation. The manual suggests a wide ranging number of methods that can be
adopted to determine the design discharges for drainage design based on the
circumstances encountered. It is required that the choice of return period to be
selected for the design of drainage structures should be made by the designer in
relation to cost of facility, risk associated with damages associated with large
events etc.
Minor drainage structures e.g. side ditches are to be designed to carry a 10-year
flood while major ones must be evaluated for the 25-100 year storm. The RDDM
(Table 3.2) suggests suitable return periods for various structural categories.
Whenever possible, it is required that adequate openings are provided to limit
backwater effects and excessive bed scour.
The TRRL East African Model has been widely applied and found to be more
relevant in East Africa since a number of small catchments were extensively
studied prior to establishing the required parameters for its application.

2.5.6

Hydrological Analysis Methodology


In undertaking the hydrological study and analysis, the following operations are
undertaken:
(a) Visual inspection and capacity assessment of all existing cross drainage
structures
(b) Review, collection and analysis of all existing data including rainfall and runoff
records
(c) Catchment area delineation
(d) Catchment characteristics determination (e.g. quantification of key catchment
parameters - catchment area, mainstream length and slope for all existing and
proposed road crossings)
(e) Analysis of rainfall and flow data
(f) Selection of hydrologic procedure (e.g. determination of TRRL design
parameters (soil cover, land use, etc.) in accordance with the provisions of the
Road Drainage Design Manual
(g) Return period adoption

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

30

(h) Peak flow or discharge estimation


2.5.7

Data Collection
The following data sets were collected during the fieldwork in Uganda and some
had already been collected and compiled for the project.
(a) Topographic Maps of scale: 1:50,000 and 1:250,000: [Source: GIS Database SMEC Office in Uganda]
(b) Meteorological data: [Source: Ministry responsible for Meteorological data in
Uganda]
(c) Hydrological and Flood Flow Data: [Source: Ministry responsible for Water
Resources]
(d) Uganda Soil Map of scale 1:1,500,000: [Source: SMEC Office in Uganda]
(e) Digital Elevation Model (DEM): [GIS Database - SMEC Office in Uganda]
(f) Site visit inspection and assessment information

2.5.8

Topography, Catchment Area Delineation and Watershed Parameters


To investigate the information and data, the essential items like relief type,
catchment parameter or the streams along the route, data pertaining to roughness
and runoff coefficients, topographic maps, land use and land cover, soil and
geomorphology maps, the field visit inspection and assessment were used. In the
study of the watershed characteristics, extensive study has been done using
topographic maps (1:50,000) for all the watercourse catchments draining across
the roads.
The catchment areas have been delineated from the topographic maps and Digital
elevation model (DEM) for Uganda. The process includes the digitization of the
stream networks from topographic map, and georeferencing to UTM coordinate
system, datum Arc 1960, Spheroid 1880. The DEM for Uganda and the digitized
river networks are then uploaded in the ArcHydro tool in ArcGIS 9.3 to delineate
the watersheds.
The GPS location for the various roads drainage crossings as determined during
field visit are uploaded and superimposed on the delineated watersheds. Further
onscreen digitization is done to clearly define the watersheds to respective road
drainage points followed by determination of catchment parameters such as area,
catchment length and slope, length of mainstream from the remotest point to the
crossings, elevation differences and stream slope.

The four Districts of Mayuge, Iganga, Bugiri and Busia have two main drainage
systems of Lake Victoria and Lake Kyoga.
The Lake Victoria drainage system consists of Lake Victoria, River Nalioba,
Nasigombe-Nalwire- Hone and Sango-Sio. The Lake Kyoga drainage system is
constituted by River Lumboka and River Malaba wetland system. Other wetland
| FINAL Detailed Design Report_Rev.1-AUG.2012 |

31

systems can be traced in Mayuge District such as Lumbuye wetland system in


Mpungwe Sub County and Kyankuzi wetland system in Baitabongwe Sub County.
The small streams inform of swamps and marshes cutting across the project road
feed into these wetland systems. The area can therefore be summed as having
wetlands and several networks of swamps.
There are both surface and underground water sources, wetlands and rivers
forming part of the boundaries between villages, Sub Counties and/or Districts in
form of valleys. (Busia District Local Government Three Year Development Plan
2008/9-2009/10).
2.5.8

Watershed Characteristics
General Characteristics
The watersheds draining to project road have distinct characteristics largely due to
their geographical location, climate and land use characteristics. The relatively
common aspect is that the watersheds are intensively cultivated, human settled
and predominantly rolling.
The Musita-Lumino/Busia-Majanji roads are characterized by:
Natural vegetation similar to tropical forest/ grassland.
Swampy areas
Tropical climate with rainfall having two seasons i.e. from March to
June and from September to November (Bimodal)
Agriculture (sugar canes, maize, cassava, sweet potatoes, millet and
sorghum), Cattle rearing and mining like gold, uranium, iron core, lake
sand and oil.
The delineated catchments are given in Appendix 4.
Soil Type
According to Uganda Soil Map, the soil type of the project area are characterized
as Ferrallitic soils (sandy loam and sandy clay loams) especially in lowland areas,
Ferrisols, Humid Ferrallitic and Halomorphic soils in areas surrounding Mt. Elgon.
The soils covering most of the project area are mainly loamy and sand loams with
spots of clay at the valley areas. These soils have fine texture with rather loose
structure, which are easily eroded and leached. The soil types can be summarized
as;
Yellow-red sandy, clay loam soils varying from dark grey to dark. These occur
on gently undulating hilly topography.
Brown yellow clay loams with laterite horizon with a variety of dark brown to
dark grayish brown. These occur on flat ridge tops or as of undulating
topography.
Light grey- white mottled loamy soils with laterite horizon ground, structuresless loamy sands. These are acidic-allocative and mainly found on lower and
bottom slopes.
Clay soils are limited to the swamps in the valleys.
(Busia District State of Environment Report, 2005 and Bugiri District
Development Plan 2009/10-2011/2012).

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

32

Climate
Uganda has a typically tropical climate with little variation in temperature
throughout the year. Distinctive wet and dry seasons characterize the climate of
Uganda. Uganda's equatorial climate provides plentiful sunshine, moderated by
the relatively high altitude of most areas of the country. Mean annual temperatures
range from about 16C in the southwestern highlands to 25C in the northwest; but
in the northeast, temperatures exceed 30C about 254 days per year. Daytime
temperatures average about eight to ten degrees warmer than nighttime
temperatures in the Lake Victoria region, and temperatures are generally about
fourteen degrees lower in the southwest.
Except in the northeastern corner of the country, rainfall is well distributed. The
southern region has two rainy seasons, usually beginning in early April and again
in October. Little rain falls in June and December. In the north, occasional rains
occur between April and October, while the period from November to March is
often very dry. Mean annual rainfall near Lake Victoria often exceeds 2,100 mm,
and the mountainous regions of the southeast and southwest receive more than
1,500 mm of rainfall yearly. The lowest mean annual rainfall in the northeast
measures about 500 mm.
Temperature
Available temperature data for the project area have been collected. Figure 7.1
provides the monthly Minimum, Maximum, and Average Temperature for the Jinja
Meteorological Station.

35.0

Air Temperature (oC)

30.0
25.0
20.0
15.0
10.0
5.0
0.0

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Max.

29.1

30.1

29.1

28.1

27.6

27.3

27.4

27.9

28.4

28.7

28.3

28.3

Min.

17.0

17.4

18.0

17.9

17.7

17.1

16.4

16.4

16.8

17.2

16.9

16.6

Mean 23.1

23.7

23.6

23.0

22.6

22.2

21.9

22.2

22.6

22.9

22.6

22.5

Figure 14: Mean Monthly Maximum, Minimum and Average Temperature at Jinja
Met. Station for the period (1999 2008)

Rainfall
Available rainfall data for the study area have been collected from the Department
of Water Resources in Uganda. Table 14 presents the mean monthly rainfalls at
the Jinja and Ikulwe stations.
| FINAL Detailed Design Report_Rev.1-AUG.2012 |

33

These rainfall stations were considered to have data of sufficient length that are
important in deriving statistical information for the determination of the design
rainfall at specific recurrence interval, covering a period of 39 and 22 years,
respectively.
Table 14: Mean monthly rainfall (mm)
Months

Station

Jan

Feb

Mar

Apr

May

Jun

Jul

Jinja

75.9

70.2

144.4

190.7

143.6

64.1

64.6

Ikulwe

63.1

55.4

119.7

151.1

127.0

83.1

56.9

Aug

Sep

Oct

Nov

Dec

Total

97.6

108.9

123.0

153.8

85.5

1322.2

84.6

78.1

115.1

138.2

111.6

1184.0

Table 15 presents the maximum daily (24-hours) rainfall at the six stations. These
rainfall stations were considered to have data of sufficient length that are important
in deriving statistical information for the determination of the design rainfall at
specific recurrence interval. The records for Jinja and Ikulwe cover 39 and 22
years respectively.
Table 15: Maximum daily rainfall data (mm)
Jinja
Year
Rainfall
Year
Rainfall
1960/61
1982/83
56.5
1961/62
1983/84
43.0
1962/63
1984/85
83.0
1963/64
1985/86
60.5
1964/65
1986/87
54.9
1965/66
1987/88
29.7
1966/67
1988/89
43.8
1967/68
1989/90
79.6
1968/69
1990/91
70.8
1969/70
87.4 1991/92
40.8
1970/71
89.8 1992/93
53.7
1971/72
101.3 1993/94
76.6
1972/73
69.9 1994/95
116.7
1973/74
46.4 1995/96
112.1
1974/75
60.5 1996/97
39.9
1975/76
111.0 1997/98
78.6
1976/77
72.9 1998/99
117.5
1977/78
60.4 1999/00
73.2
1978/79
67.0 2000/01
62.1
1979/80
78.0 2001/02
73.1
1980/81
68.5 2002/03
65.7
1981/82
57.6 2003/04
94.8
2004/05
99.7
2005/06
103.4
2006/07
85.1
2007/08
47.5
2008/09

Ikulwe
Year
1960/61
1961/62
1962/63
1963/64
1964/65
1965/66
1966/67
1967/68
1968/69
1969/70
1970/71
1971/72
1972/73
1973/74
1974/75
1975/76
1976/77
1977/78
1978/79
1979/80
1980/81
1981/82

Rainfall
57.0
62.0
60.0
45.3
62.5
36.0

Year
1982/83
1983/84
1984/85
1985/86
1986/87
1987/88
1988/89
1989/90
1990/91
1991/92
1992/93
1993/94
1994/95
1995/96
1996/97
1997/98
1998/99
1999/00
2000/01
2001/02
2002/03
2003/04
2004/05
2005/06
2006/07
2007/08
2008/09

Rainfall
33.9
60.9
56.5
44.5
34.5
56.2
52.1
37.2
31.5
84.6
67.8
49.8
46.2
57.0
62.0
46.2

Table 16 presents the important statistics of the rainfall data from the two stations
with the most reliable and long records.
| FINAL Detailed Design Report_Rev.1-AUG.2012 |

34

Table16: The important rainfall statistics data


Station
Code
Name
Jinja Met. Station
Ikulwe Farm Institute

89330430
89330390

Highest Lowest
(mm)
117.5
84.6

(mm)
0.0
0.0

Mean
()
(mm)
72.6
52.0

Stdev
Coef. of
()
Variation
(Cv)
(mm)
22.7
0.3
13.0
0.3

Coef. of
Skew
(Cs)
0.970
0.767

300

Rainfall (mm)

250
200
150
100
50
0
Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Months
Jinja

Ikulwe

Figure 15: Mean Monthly Rainfall of the stations with good rainfall records
Stream flows
Existence of gauged stream flow data of sufficient length (at least 10 years), permits
estimates of the peak discharge in terms of its probability of frequency of occurrence
by employing statistical methods. In the study area, such data are not readily
available, except for Manafa River that has some gauged data spanning for 11 years
(1999-2009). The yearly maximum daily flow data were extracted from the daily time
series for each year and analysed to estimate the flood design discharges at a specific
return period (e.g. 100 years).
For un-gauged catchments, the rainfall data of the project surrounding area were
used to compute design rainfall and used in the TRRL East African Food Model to
estimate the design flood discharge at their corresponding delineated catchment
crossing points. For catchments with no properly defined channels/streams,
extrapolation of design flow was made using drainage area ratios provided the areas
had similar characteristics and within the same metrological zone.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

35

2.6

Swamp Investigations
The locations of swamps or marshy areas along the Musita-Lumino/Busia-Majanji
roads were visited in order to provide a preliminary assessment of their likely
impacts upon the design of these roads.
Along Musita-Lumino road 14 no. low lying marshy areas were identified. There
are no swamps along the route.

2.7

Drainage Investigations

2.7.1 Assessment of Existing Drainage Structures


A visual assessment of the drainage structures was carried out by the
Bridge/Drainage Engineer and the Hydrologist.
Each minor and major drainage structure was inspected and relevant basic
measurements were taken. Data on hydraulic performance and history of any
overtopping and history of rehabilitation measures undertaken were collected from
local residents and branch of the ministry of works.
Moreover, observations were made relating to:

Hydraulic performance
Physical condition
Possible causes of damage
Materials used for construction and their performance
Period of service
Possible reasons for poor performance
Possibility of maintenance or repair
Performance in respect to traffic safety
Replacement options

A detailed photographic inventory and assessment of all the existing drainage


structures are prepared following the field inspection. These schedules are
included in Appendix 5A and 5B.
2.7.2

Classification of Drainage Structures


For the purpose of this project, all drainage structures are classified in two broad
classes namely, minor and major drainage structures.
Minor Structures
Minor drainage structures are those pipes having single or multiple cell opening
either made from concrete or corrugated metal sheet (Armco) and all the road side
drainage facilities.
Major Structures
Structures included in Major Structures category are box culverts, slab culverts
and reinforced concrete /composite/ steel / bridges.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

36

Slab culverts are those with top slab resting on abutments done separately, and
box culverts are those having monolithic top slab, bottom slab and the vertical
walls.
2.7.3

Side Ditches
Stone pitched side channels and flow checks are found along a certain sections of
the project roads. Some are recently constructed and are in very good condition.
But in general it is observed that due to lack of regular repair, water flows out of the
channel damaged the road pavement and make it difficult for road users. Please
refer to Appendix 5A for details.

2.7.4

Pipe Culverts
According to the structures inventory data, we found out that there are over 300
existing pipe culverts along all the project routes. The majority of the existing pipe
culverts are made from either reinforced concrete with internal diameter ranging
from 300mm to 1000mm or Armco sheet ranging from 600mm to 2000mm internal
diameter. Please refer to Appendix 5A and 5B for details.

`
During assessment of the drainage structures along the project route, the following
major deficiencies or problems were observed at pipe culverts:
Damaged or missing headwalls
Siltation in pipes due to low invert level
Poor workmanship at the head walls and at pipe joints.
Insufficient length of pipes as compared to the width of the road
Insufficient hydraulic capacity
Lack of regular cleaning
Missing or damaged aprons and energy dissipaters at inlets and outlets
2.7.5

Box Culverts
More than six box/slab culverts are found along the entire project route. Please
refer to Appendix 5A for details.
The following major deficiencies or problems were observed at box/slab culverts
during the assessment:
Deteriorated slab concrete
Cracked, damaged abutments and wing walls
Insufficient hydraulic capacity
Eroded bank and scoured bed.
Damaged inlet and outlet aprons (either broken down or dislodged)

2.7.6

Bridges
All drainage structures where the top slab is exposed for direct contact to traffic
wheel load regardless of their span are categorized as bridges. More than 10
bridges are identified for the entire project. The following table demonstrates the
current condition of the existing bridges.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

37

2.7.7

Existing Bridges
There are no existing bridges along Musita- Lumino road.

2.7.8

Summary
The following summary is made based on the assessment of drainage structures
along the entire project roads.
Drainage is a major issue along the project roads and it is the prime factor for
the road damage. And almost in all cases existing drainage facilities are found
inadequate.
A certain sections of the roads traverse through major flood plains and marshy
areas. And in most cases these roads are over-topped during the regular rainy
season.
Inadequate opening size of most pipe culverts provided, forced the placement
of additional pipes by the side of the existing ones which has done little in
alleviating the drainage problem but reducing the riding quality of the road.
Luck of enough cover over pipe culverts resulting either broken concrete pipes
or tiered Armco pipes
Insufficient length of structures provided resulting in narrow road section
Poor overall workmanship and lack of regular maintenance
Long year of service
Inadequate structural capacity

2.8

Environmental and Social Studies

2.8.1

General
An Environmental and Social Impact Assessment was carried out for the project
roads and surrounding areas during 2010/2011, with a summary of the findings
presented below.
Detailed assessment of the impacts upon the project and the mitigation measures
are given in the Final ESIA Report.

2.8.2

Geographical Location
The Musita-Lumino/Busia-Majanja roads are situated in the Eastern part of
Uganda. They traverse four already established districts of Mayuge, Iganga, Bugiri
and Busia Districts and the newly approved District of Namayingo which is to be
carved out of Bugiri District.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

38

2.8.3

Biophysical Environment
The topography of the project area is relatively flat with high ridges and isolated
hills, adulating lowlands and perch vents with a few higher residual features.
In terms of geology, the project area is made up of Precambrian rocks with bare
granitic rocks at several places heavily eroded. The soils covering most of the
project area are mainly loamy and sand loams with spots of clay at the valley
areas.
It has two main drainage systems of Lake Victoria and Lake Kyoga. According to
Busia District State of Environment Report, 2005.
The area has noted fluctuations in rainfall figures over the last seven years. In
October-December 1997, Busia and the neighboring districts experienced heavy
rains (El-Nino), with figures averaging ten times the normal and resulting in
disastrous flooding.
The mean annual maximum temperature in the project area is 28.70C and the
mean annual minimum is 16.20C. The mean monthly maximum is 270C, while the
mean minimum sometimes falls to 160C especially at dawn (early morning).
The vegetation observed in the project area has undergone considerable changes
and this can be attributed to continuous cultivation, burning or clearing for different
purposes.
The project road is not very rich in faunal diversity given the level of interference
inflicted upon the natural vegetation; the would-be in habitats of this diversity.

2.8.4

Socio-economic and Cultural Environment


According to the 2002 Population and Housing Census, the total population in the
16 Sub Counties through which the road traverses is 123,669 persons of which
59,271 are males and 64,398 are females and the average household size is 5
persons.
The results indicate that the general literacy levels within the project area are very
low as the majority of the households (49.6%) did not exceed primary level.
The majority of the households (80.3%) along the road in all the four districts are
married while 19.7% are not married.
The major ethnic groups in the project area are Basoga (45.4%), Basamia (26.8%),
Banyole (12.5%), Japadhola (4.4%), Iteso (3.1%), and Bagwere (2.5%). Other ethnic
groups in the area include Baganda, Bagisu, Badama, Bakenye and Lugbara.
As regards religion, the majority of the population in the four districts belongs to the
Anglican/protestant and Moslem religions followed by Catholics.
The most common land tenure system in the project area is customary. The land is
comprised of farming land, settlements, manmade forests and swamps. In terms of
size, the results indicate that the average land size owned by the households in
the project area is 2 acres.
The predominant economic activity is subsistence agriculture. The main crops
grown include maize, rice, sugarcanes, bananas, cassava, sweet potatoes and

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

39

beans. The main cash crops are cassava, rice and sugarcanes. According to the
household survey, the average monthly income for households in the project area
is UGX 163,300 while the average annual income is UGX 1,908,000.
Most (36%) of the households in the project area are temporary made of mud and
wattle, 35.6% are semi permanent and 28.4% are permanent. Most of the
permanent structures are found in trading centres.
The main source of water is public boreholes 56.5%, followed by protected
springs/wells (19.9%), 15.7% depend on unprotected springs/wells, 2.9% depend
on privately owned boreholes. Other water sources include stand posts, valley
tanks/earth dams and others buy from water vendors.
2.8.5

Predicted Environment and Social Impacts


There are several positive impacts that might accrue as a result of the upgraded the
road and these include the following:

Creation of job opportunities to the local unskilled persons as well as


skilled persons in the community.
Improved accessibility to markets.
Easy and comfortable transportation.
Improved transport and communication after construction of the road.
Improved market for locally available resources needed for road
construction e.g. stones, sand, gravel among others.
Land value appreciation
Increased retention of qualified personnel
Increase beauty of the area.
Increased trade between districts, regions and Kenya.
Improved road drainage infrastructure and general discharge of storm
water from the road/carriageway.

However a number of negative impacts were also identified as described below.


Biophysical impacts will include increased noise, deterioration of air quality,
aesthetics, vegetation clearing ,forest degradation in areas as in KyebandoMayuge,Mpumu and Lumino having planted forests of bamboo, pines and
ornamental trees by the road side, impacts from quarrying and gravel mining
activities.
Social impacts identified include high social expectations, loss of structures which
will include graves, about 1,561 structures which are temporary, semi permanent
and permanent in nature. In addition, several institutions will also be affected
through loss of land, structures and these include about 51 educational institutions,
13 health centres, and religious places among others. The acquisition of about 1,285
acres of land will lead to loss of land for many households and this will greatly affect
their livelihood as the majority depends on agriculture as the main source of income.
Note: The actual number of affected property will be established during the
preparation of the Resettlement Action Plan.
Other potential negative impacts include the influx of people especially during the
construction. This will bring about an increase in the spread of sexually transmitted
diseases like HIV/AIDS, syphilis, gonorrhea among others, increased stress on
social services like education, water and health. Community or public infrastructure
like water sources, electricity lines will be disrupted.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

40

However, all the social impacts represent a potentially more serious effect of the
project. All impacts of the project have however been found to be manageable
provided mitigation measures which have been proposed are implemented.
Table 17 below shows the predicted negative environmental and social impacts
without mitigation.

Table 17:Overall Impact Assessment


Study

Value/vulnerability
of the
Environment
Component

Magnitude of impacts

Overall impact
Assessment (without
mitigation measures)

Scale

Low/Med./High

Negative
Positive
High Medium Little/No Med. High

-Planning Phase
Social Expectations

--

Land use

--

--

Large negative impact(---)


--

Medium negative (--)

Construction Phase
Employment

--

--

Medium positive (++)

Increased market

--

--

Medium positive (++)

Soil erosion
Installation of road
furniture
Aesthetic value
Waste generation
(soil
&vegetation
material and
other solid
waste)
Potential cont. of
water sources
Drainage &
wetlands
Air quality
Noise
Impacts of quarry
devt.
Vegetation &
forests
Disruption of
wildlife
Influx of people
Increased STDs &
HIV/AIDS
Displacement &
loss of
housing

-----

--

--

Minimal/No impact (0)

--

Medium positive (++)

---

Small negative (-)


Medium negative (--)

--

Minimal or No impact (0)

--

--

--

---

--

Medium negative (--)


Large negative (---)
Large negative (---)

---

--

--

--

Small negative (-)


--

--

---

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

Minimal or No impact (0)

Minimal or No impact (0)


Medium negative (--)
Medium negative (--)
Large negative (---)

41

Study

Value/vulnerability
of the
Environment
Component

Magnitude of impacts

Overall impact
Assessment (without
mitigation measures)

Scale

Low/Med./High

Negative
Positive
High Medium Little/No Med. High

-Land acquisition
Educational
vulnerable groups
Disruption of
water supply
Disruption of other
infrastructure
Agriculture
Health and Safety
other economic
activities
Impact on Gender

-----

Large negative (---)


Medium negative (--)
Medium negative (--)
Medium negative (--)

-
---

--

---

--

Medium negative (--)

---

--

Large negative (---)


Medium negative (--)
Small negative (-)

---

Cultural Heritage
-Operational and Maintenance (O&M)
Transport & com.
Staff retention
Land appreciation
Access to HC
Loss of livelihood
Community
conflicts
Increased
Accidents
Air pollution from
bitumen
during resurfacing
Poor silt disposal

--

Medium negative (--)

--

Small negative

--

----

----

------

--

Large positive (++)


Small positive (+)
Medium negative (++)
Small positive (+)
Minimal or No impact (0)
Minimal or No impacts (0)

--

Medium negative(--)

--

--

Medium negative (--)

--

--

Medium negative(--)

Details of proposed mitigation measures are detailed in the Final ESIA Report.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

42

DETAILED DESIGN

3.1

Geometric Design

3.1.1

Introduction
In developing the design for the upgrading of Musita-Lumino and Busia-Majanji
roads, the objectives as set out in the Terms of Reference were considered in
detail.
A number of alignment options were developed with due regard to the following
considerations;
Design manual criteria
Balance between cut and fill
Minimise land take
Affordable and acceptable accommodation works for frontages
Minimise utility protection/relocation
Avoid geological, hydrological and environmental problems
Avoid extensive and expensive bridge works
Protect vulnerable road users
Provide in-build safety measures
Provide adequate road users facilities

The resulting alignment options were further assessed by our resettlement and land
acquisition team and discussed extensively with the Client before a final option was
approved and considered for detailed design.
3.1.2

Design Standards
The geometric design of the project road was carried out as per the guidelines
contained in the Ugandan MoWH&C Road Design Manual of July 2005. This was
in accordance with the requirements of the TOR, and as confirmed by UNRA.
The Manual was complimented by recognized design manuals from neighboring
counties including;
Kenyas Road Design Manual Part 1: Geometric Design Manual
Tanzanias Draft Road Manual
Code of Practice for Geometric Design (SATCC-1998) Trunk Road
Design Standards

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

43

Lot E roads have been packaged into the following contracts;


1. Package 1:

Road E1.1 Musita-Lumino and Road E1.2 Busia


Majanji

2. Package 2A: Road E2.1 Tirinyi Pallisa and Road E2.2 Pallisa
Kumi
3. Package 2B: Road E2.3 Pallisa Kamonkoli
4. Package 3: Road E3 Bumbobi - Bubulo Busumbu Lwakhakha
5. Package 4: Road E4 Namagumba Budadiri Nalugugu
6. Package 5: Road E5 Kamuli - Bukungu
Package 1 comprises two links, Musita Lumino and Busia Majanji.
The Musita Lumino link starts from Musita trading center along the Jinja-Iganga
highway. It continues on an eastwards direction passing through Mayuge,
Nankona, Buyinja and ends at Lumino trading center.
The Busia Majanji link commences at Busia town continuing southwards
through Dabani, Masafu Lumino and ending at Majanji on the shores of Lake
Victoria.
The project road is an alternative link between Jinja and Busia town and also
serves as a link to a number of landing sites along Lake Victoria including
Majanji, Lufudu, Omenya, Wakawaka and Kigandala. From Lumino, one can also
access Lwanda border post which has been earmarked for upgrading by Uganda
Revenue Authority (URA).
On the basis of the Design Manual, the project road can be classified as Class C
or a Primary road. These are described as roads linking provincially important
centers to each other or to a higher class roads (urban/rural centers). They
provide linkage between districts, local centers of population and development
areas with higher class road. Their major function is to provide both mobility and
access
A paved Class II road standard was adopted for the geometric design of the
project road; the applicable geometric design standards for which are presented
in Figure 4.2a and 4.2b of Section 4 of the Design Manual and reproduced below
as Table 18 and Table 19 for ease of reference.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

44

Table 18:

Road Design Classes


Maximum Design speed

Capacity
[pcu x
1,000/day]

Road-way
width[m]

Ia Paved

12 - 20

Ib Paved

Design
Class

Functional
Classification

Kph
Level

Rolling

Mountainous

20.80-24.60

120

100

80

6 10

11.0

110

100

80

II Paved

48

10.0

90

70

60

III Paved

26

8.6

80

70

50

A Gravel

48

10.0

90

80

70

B Gravel

26

8.6

80

60

50

6.4

60

50

40

C Gravel

Table 19 :

Road Design Classes (continued)

Design class

Right of Way
width [m]

Road way
width [m]

Ia Paved
Ib Paved
II Paved
III Paved
A Gravel
B Gravel
C Gravel

60
60
50
50
40
30
30

20.80-24.60
11.0
10.0
8.6
10.0
8.6
6.4

3.1.3

Carriage way
Lane
No. of
Width
width
lane
[m]
[m]
14.6
3.65
4
7.0
3.5
2
6.0
3.0
2
5.6
2.8
2
6.0
3.0
2
5.6
2.8
2
4.0
4.0
1

Shoulder
width [m]

Median
width
[m]

2 x 2.5
2 x 2.0
2 x 2.0
2 x 1.5
2 x 2.0
2 x 1.5
2 x 1.2

1.2 5.0
-

Design Speed
The road sections between Musita and Lumino and Busia Majanji has been
classified as flat, having gradients not exceeding 5.5%. A design speed of 90 kph
has been recommended as per the Design Manual Table 6-15. It should however
be noted that many sections of the existing road are long and straight and higher
speeds than these will be possible.
Through the more populated centres along the route, the design speed of 90 kph
has been maintained for the selection of appropriate geometric elements,
however the posted speed limit of 50 kph has been set for pedestrian safety.
Table 20 is a schedule of centers where it has been proposed that the traffic
speed be regulated through the installation of road signage, speed bumps and
rumble strips. Other centres noted along the project road and for which the

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

45

design speed may only be regulated by installing appropriate traffic signs are
listed in Table 20 below.

TABLE 20 -

SECTIONS WITH DESIGN SPEED OF 50 Km/h


REGULATED BY BUMPS AND RUMBLE STRIPS

Road E 1.1 Musita-Lumino


FROM
Km

TO

0 + 000

Km

0 + 400

LOCATION
Musita Bypass

Km 12 + 800

Km 14 + 000

Mayuge Township

Km 35 + 100

Km 37 + 500

Nankoma Township

Km 46 + 900

Km 48 + 600

Muterere

Km 50 + 500

Km 52 + 100

Bukoli

Km 56 + 500

Km 57 + 600

Namavundu

Km 62 + 400

Km 63 + 500

Buyinja

Road E1.2 : Busia-Majanji


FROM

TO

LOCATION

Km

0 + 000

Km

1 + 300

Busia Town

Km

5 + 800

Km

6 + 500

Dabani

Km

7 + 800

Km

9 + 300

Masafu

Km

19 + 100

Km 19 + 600

Lumino

Km

26 + 500

Km 26 + 732

Majanji

TABLE 21

SECTIONS WITH 50Km/h REGULATED SPEED USING ONLY


TRAFFIC SIGNS

Road E1.1 : Musita-Lumino


FROM

TO

LOCATION

Km

1 + 700

Km

2 + 600

Lugolole

Km

6 + 000

Km

6 + 500

Bufulumbi

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

46

Km 16 + 300

Km 16 + 800

Maina

Km 20 + 200

Km 21 + 300

Mpunge

Km 26 + 100

Km 26 + 600

Bunalwenyi

Km 30 + 100

Km 30 + 700

Bwamula

Km 32 + 700

Km 33 + 600

Itakaibolu

Km 41 + 200

Km 42 + 000

Namabingo.

Km 66 + 700

Km 67 + 300

Lunyo

Km 72 + 200

Km 72 + 500

Bwaniha

Road E1.2 : Busia-Majanji


FROM

TO

LOCATION

Km 13 + 700

Km 14 + 600

Mailo Eight

Km 15 + 700

Km 16 + 100

Mailo Seven

Given these design speeds, the horizontal alignment adopted has been chosen
to suit the topography and minimize overall cost, whilst the vertical alignment is
very much governed by drainage requirements and the need to raise
embankments at low lying areas or wetlands.

3.1.4 Design Departures


The design speed and the recommended geometric elements were adopted as
much as possible, however in sections where the terrain required expensive and
uneconomical earthworks or the resulting cost of acquisition became too high,
design departures were recommended.
As stated above both Musita Lumino and Busia Majanji roads can be
classified as flat with a recommended design speed of 90 km/h.
However along the Musita Lumino road at Km 0+250 a horizontal curve of
200m radius has been proposed as opposed to the minimum of 320m
recommended for a 90 km/h. This has been done to provide a straight approach
to the main junction with adequate sight distance. This has been mitigated by
recommending 50 km/h speed limit signs.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

47

Between Km 44+700 and 45+900 a steep grade of 6.7% is encountered. It has


therefore been necessary to reduce the design speed at this section to 70 km/h
in order to save on expensive earthworks that may be required to maintain a 90
km/h design speed over the section.

3.1.5

Cross-Section
The Road Design manual proposes a cross section of 3m lanes and 2m
shoulders totaling 10m for a Design Class II Paved road. This is presented in
Table 4-2b of the manual. However, in consideration of safety, the anticipated
traffic growth and further consultations with UNRA, it was agreed that a cross
section comprising 3.5m lanes and 1.5m shoulders in the rural areas and 2m in
Urban/Trading areas be adopted for the project road..
Additional separated Service Lanes and Pedestrian walkways have been
proposed at locations given in Table 22 below:
TABLE 22 SECTIONS WITH PEDESTRIAN WALKWAYS

FROM

TO

LOCATION

Km 12 + 800

Km 14 + 000

Mayuge Township

Km 35 + 100

Km 37 + 500

Nankoma Township

Km 46 + 900

Km 48 + 600

Muterere

Km 50 + 500

Km 52 + 100

Bukoli

Km 56 + 500

Km 57 + 600

Namavundu

3.1.6 Embankment Design


In order to reduce earthworks and shoulder works to a minimum, the following
embankment slopes have been proposed
for fill height hf < 1 m = 1:4 (vertical:horizontal)
for fill height hf > 1 m = 1:2
for cut height hc < 1 m = 1:2
for cut height hc > 1 m = 1:2

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

48

It should be noted, however, that such an approach does have safety


ramifications. From a safety perspective side slopes of 1 in 6 for embankment
are recommended to reduce the likelihood of vehicle overturning. In terms of
stability, a slope of 1 in 2 is stable for the embankments heights proposed for the
project.
The steeper slopes tend to perform better in terms of erosion, as the quantity of
water landing on the slope during rain is less. The water running off the road
clearly travels faster down the slope and causes an erosion channel, probably
more so than on a flatter slope. Where this occurs, chutes are to be provided to
cater for the run-off.
It has also been recommended that the pavement layer construction should be
extended to cover the full width of the shoulders in order to meet the following
principal objectives:
(a) to enable heavy goods vehicles to pass each other safely making use of the
full road width;
(b) to make provision for the high level of cycle and pedestrian traffic along the
project road; and
(c) to prevent damage to and erosion of the shoulder and carriageway edge.
3.1.7 Adopted Design Parameters and Standards
The following parameters and standards have been adopted in the designs:

Design life:

20 years.

Cross-section:

7.0 m wide carriageway at 2.5% normal camber (3% at flat


sections)
2.0 m wide shoulders at 4.0 % normal crossfall
1.0 m wide side drain.

Design Speed Parameters:


Design Speed

90 Km/h

70 Km/h

Min. Horizontal Radius

320 m

185 m
7%

Max. Superelevation
Max Gradient (Absolute)

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

5.5%

7.5%

49

0.4-0.6 max

Rate of Change of
Superelevation

71

31

90 Km/h

70 Km/h

41

25

Stopping Sight Distance (SSD)

170 m

111 m

Passing sight Distance

750 m

550 m

Minimum Crest Curve Kmin


(stopping sight distance)
Design Speed
Minimum Sag Curve Kmin

3.1.7

Summary of Adopted Design Speeds


Musita Lumino:
Km 0+000 44+700: Flat terrain - Design speed = 90 km/h
Km 44+700 45+900: Rolling terrain Design speed = 70 km/h
Km 45+900 77+140: Flat terrain Design speed = 90 km/h
Busia Majanji:
Km 0+000 26+811: Flat terrain Design speed = 90 km/h

3.1.8

Design Road Alignment

3.1.8.1 General

The geometric characteristics of the existing road alignment were obtained from
ground data capture generated from aerial photography surveys.

During this exercise, control points were established alongside the road. This
data was ultimately tied onto the National grid system. Ground data capture was
generated at 5 m square grids and covering a corridor of 35m either side of the
existing centreline. This data was then imported into AutoCAD Civil 3D software
to generate a digital ground model of the route corridor.
A geometric record of the plan and profile of the existing road, both for the
assessment and creation of a model to act as the basis for the alignment designs
were then carried out.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

50

3.1.8.2 Selection of Alignment

The following principles were adopted during selection of the appropriate


alignment for the preliminary design:
Conformity to the specified geometric design parameters.
The alignment was designed to conform to or surpass the geometric
design parameters as recommended in the design manual.
Follow the general corridor of the existing road.
The general approach to the route alignment was to use the corridor of
the existing road as much as possible. This was done to retain the
present social function with minimum disruption to existing and long-term
residents. Minor realignments were however introduced to improve the
road geometry and remove potentially dangerous curves. This was also
done at locations of new bridges.
Keep the works within the existing right of way.
In most sections, the alignment design was carried out to follow the
existing road as much as possible to enable the use of existing
pavement materials to form new a subgrade.
Improve junctions.
In order to improve safety at the approach junctions, the project road
has been realigned to approach the main highway at a right angles.
Re-align at trading centres.
There are a number of large trading centers along some of the project
roads with heavy population and agricultural activities. The possibility of
having a bypass at some of these centers was investigated. Preliminary
realignments outside the centers were designed. These were then
presented to the Resettlement and Land Acquisition specialist who also
visited the project road to evaluate the impact of the bypasses against
keeping the alignment through the centers, compensating where
necessary and maintaining the current social function of the road.
A section-by-section description of the existing road features and proposed
realignments follows.

3.1.9

Alignment Details

3.1.9.1 Road E1.1 : Musita-Lumino


(A)

Horizontal Alignment

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

51

(1)

Realignment of the junction at Musita (Km 0 + 000 to Km 0+400)

The project road joins the Jinja Iganga highway at a skew angle. The taxis
stop at the junction to pick up passengers and despite the provision of
deceleration and acceleration lanes, the junction still remains a safety hazard.
In order to improve safety at the approach junction, the following solution has
been proposed:
The project road has been realigned to approach the main highway at a
right angle with the junction some 200m from the existing junction;
Care was taken to locate the realignment where there would be minimal
compensation and affected buildings;
A 6 m wide service road with 1 m shoulder has been proposed for Musita
trading center, however to restrict motorist from joining the main road
through this access road it has been proposed that it be blocked at the
current junction by constructing a deep lined-side drain.
A right-turn lane has been provided to enable safe maneuver of heavy
goods vehicles. Acceleration and deceleration lanes have also been
provided and appropriate taxi-bays.
(2)

End of Musita Bypass to the start of Lumino Bypass


(Km 0+400 to Km 76 + 400)

The existing alignment along this section of the road is generally has long
straights with gentle curves. A roundabout has been proposed at Mayuge Km
13+166 to improve the traffic flow at the four intersecting roads.
Mayuge
A bypass was initially proposed between Km 12+800 to 15+100. A review of
the proposed bypass by the Resettlement and Land Acquisition Specialist
revealed that it impacted a health center at Km 12+800 together with several
buildings, a mosque and a church at Km 13+400 and a heavily populated area
with homesteads and cultivated land. It was agreed that the alignment be
passed through the available 25m ROW through the center, set the Right of
Way at 30m and at least compensate for the affected structures on one side.
Nankoma
A bypass was proposed from Km 34+750 to 37+200. It was found to impacted
Nankoma Primary school, Nankona HC-IV including a new outpatient
department as well as buildings and cultivated land.
After confirming that the existing road corridor within the town was between 22
to 29m, it was agreed that the centreline be passed through the town and
affected structures be compensated.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

52

Namavundu
The proposed bypass at this center was between Km 56+100 to 58+100. It was
found to impact Kifuyo CoU Primary School as well as a church and many
homesteads. The existing road corridor within the town was found to vary
between 24 to 30m. It was therefore agreed that the alignment be passed
through the town and after fixing the ROW at 30m, the affected structures be
compensated.
(3)

Lumino By-pass (Km 76 + 400 to Km 77 + 129)

The existing road through Lumino trading center is very narrow and
inappropriate for the anticipated high volume of traffic and pedestrian safety.
A bypass has been proposed to connect to the Busia Majanji road at a right
angle improving the visibility splay at the junction and road user safety. A
roundabout has been recommended for this junction to provide a link
connecting to the existing Lumino-Lwanda road.
A service road comprising 6 m carriageway and 1 m shoulders have been
proposed to serve the shops and the business community at Lumino.
(4)

Lwanda Link Road

A link road connecting to the existing Lumino Lwanda road from the end of
the Musita Lumino road has been proposed. This is in anticipation of the
soon-to-be expanded Lwanda border post.
(B) Vertical Alignment
The terrain along the Musita Lumino road can be classified as follows;
Km 0+000 44+700: Flat Recommended design speed = 90 kph
Km 44+700 45+900: Rolling Recommended design speed = 70 kph
Km 45+900 77+140: Rolling Recommended design speed = 90 kph

The digital terrain model (DTM) generated from survey data was used to
produce the existing ground profile along the centreline of the horizontal
alignment.
A vertical alignment was then designed to comply with the recommended
design speeds and the vertical profile parameters as provided for in the
Geometric Design Standard for Type II paved road.
(C) Gradients
Km 0+000 44+700

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

53

The terrain between Km 0+000 and 64+000 of the project road is generally flat
with gradients between 0.0 and 5.2%, however the section from Km 44+780 and
45+880 has a steep drop with a gradient of 6.7%. This is still within the
recommended maximum gradient for rolling terrain.

Km 44+700 45+900
The section has a steep drop of 6.7% grade and can therefore be classified as
rolling. This has necessitated a design departure as earlier discussed.
Km 45+900 77+140
The road section between Km 45+900 and 73+700 is generally flat with
gradients ranging between 0.5 and 5.0%.
3.1.9.2 Road E1.2 : Busia-Majanji
(A)

Horizontal Alignment

No major realignment has been proposed for this road. The existing alignment
has gentle curves which accommodated the design parameters. A roundabout
has been proposed at the start of the project along the Busia Iganga road to
control the traffic flow from the border post, Tororo and Iganga.
A second roundabout has been proposed for the junction at Lumino to control
the traffic to Lumino center, Majanji and Lwanda.
At Majanji the administration had earlier requested the design consultant to
consider extending the project road upto the existing landing site which has
recently been rehabilitated. On subsequent discussions with UNRA, it was
agreed that the request be considered.
The road section ends at Km 26+847.
(B) Vertical Alignment
Km 0+000 26+847
As mentioned before, the terrain over this road section is generally flat with
gradients ranging from 0.0 to 4.1%.
Details of the horizontal and vertical alignment design for the entire project are
presented in 3.1.10 Low Lying Area
The project route traverses substantial stretches of lowlying areas nd
marshland. The upgraded road has been designed to have an embankment

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

54

height of at least 2.5 m in height to minimize the effects of water rising up


beneath the sealed pavement through capillary action. The embankments
supporting the existing gravel surfaced road are generally only one to one and
a half metres in height.
The wetlands and low lying areas were noted at the following sections of
Musita Lumino road:

From Km

To Km

Length
(m)

DESCRIPTION

4 + 900

5 + 200

300

Marsh

6+650

7+350

700

Marsh

10+400

10+600

200

Marsh

15+800

15+950

150

Marsh

18+700

18+900

200

19+600

19+800

200

Marsh

21+050

21+150

100

Marsh

22+250

22+400

150

Marsh

23+700

24+200

500

Marsh

28+550

28+870

150

Marsh

34+100

34+600

500

Marsh

37+650

38+050

400

Marsh(Rice
Paddies)

40+000

40+400

400

Marsh(Rice
Paddies)

54+050

54+150

100

Marsh

54+800

54+950

150

Marsh

Swamp(seasonal)

SOIL TYPE
Silty/Sandy
Clay
Silty/Sandy
Clay
Silty/Sandy
Clay
Silty/Sandy
Clay
Silty/Sandy
Clay
Silty/Sandy
Clay
Silty/Sandy
Clay
Silty/Sandy
Clay
Silty/Sandy
Clay
Silty/Sandy
Clay
Silty/Sandy
Clay
Silty/Sandy
Clay
Silty/Sandy
Clay
Silty/Sandy
Clay
Silty/Sandy
Clay

Along Busia Majanji road, the following low lying areas were identified:

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

55

Km 6+800 7+100 : 300m


Km 14+750 12+000 : 250m
Km 17+250 17+500 : 250m
Km 21+400 21+700 : 300m

3.1.11 Junctions and Accesses


Intersections have been proposed as per the Design manual guidelines as well
as considering the traffic flows and the design speed.
The following intersections/junctions have been proposed for Musita Lumino
link. In addition, several access junctions providing access to properties adjacent
to the project road have also been proposed.
CHAINAGE

SIDE

JUNCTION TYPE

DESCRIPTION

Km 0+000

START

Type-C

Start of the Project road

Km 0+140

LHS

Type-B

Access to Musita

Km 2+100

CROSS

Type-A

At Lugolole

Km 13+166

R/ABOUT

Type-D

At Mayuge

Km 20+925

CROSS

Type-A

At Mpuge

Km 26+210

CROSS

Type-A

At Bunalwenyi

Km 30+490

LHS

Type-A

At Bwamula

Km 35+800

LHS

Type-A

To Buwunga

Km 36+160

RHS

Type-A

At Nankoma

Km 47+470

CROSS

Type-A

At Muterere

Km 51+540

LHS

Type-A

At Bukoli

Km 63+300

LHS

Type-A

To Bulesa

Km 63+300

RHS

Type-A

To Lugala

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

56

Km 66+760

RHS

Type-A

At Lunyo

Km 76+670

LHS

Type-B

To Lumino

Km 77+129

R/ABOUT

Type-D

At Lumino

Along the Busia Majanji road intersections have been proposed at the following
locations:

CHAINAGE

SIDE

JUNCTION TYPE

DESCRIPTION

Km 0+000

START

Type-D (roundabout)

At Busia

Km 19+660

RHS/LHS

Type-D (roundabout)

To Musita/Lwanda

Km 26+732

RHS

Cross junction

To Landing site

3.1.12 Footpaths, Busbays and Road Furniture


3.1.12.1 General

Segregated 2m wide footpaths/cycle paths are proposed at trading centres with


high level of non-motorized traffic (NMT) and pedestrian traffic.

The footpaths/cycle paths will be separated from the main carriageway and
shoulders by an open Invert Block Drain (IBD).
Bus bays will be provided at all trading centres, near institutions (e.g. schools,
colleges, health clinics, etc) and near all major junctions.
Traffic calming measures including rumble strips, bumps and appropriate
warning signs will be provided where considered necessary to enhance safety.
3.1.13 Service Roads
Due to ROW constraints and safety requirements, the horizontal alignment has
been designed to bypass both Musita and Lumino trading centers. In order to
access these centers 6m wide access roads with 1m shoulders have been
proposed as follows:
Musita 460m
Lumino 588m

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

57

In addition, service roads have also been proposed at the following trading
centers to minimise conflict between local traffic and through traffic. Table
below lists the locations and centres where service roads are proposed.

Location
MAYUGE
NANKOMA
MUTERERE
BUKOLI
NAMAVUNDU

Position

From Km To Km

LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS

13+300
13+300
35+200
35+200
47+250
47+250
50+800
50+800
56+800
56+800

13+900
13+900
36+000
36+000
47+800
47+800
51+400
51+400
57+500
57+500
TOTAL

Length (m)
600
600
800
800
550
550
600
600
700
700
6,500

Along the Busia Majanji section service roads have been proposed at Busia
town and Majanji trading center.
3.1.14 Climbing Lanes
3.1.14.1 Introduction

The need for Climbing Lanes has been assessed using guidelines contained in
the Kenyas Road Design Manual Part 1: Geometric Design of Rural Roads.
The Manual stipulates that Climbing lanes should be introduced where
longitudinal gradients are long enough and steep enough to cause significant
increase in speed difference between cars and heavy vehicles.

In assessment of the need for a Climbing Lane the following guidelines are
considered:
i.

Climbing lanes are NOT required for roads with AADT < 2000 p.c.u. in
Design year 10 and in all Class D(secondary) and E(minor) roads even if
AADT exceeds 2000 p.c.u. in Design Year 10.

ii. Where passing opportunities are limited on the gradients, then Climbing
lanes must be considered on all A(International trunk roads),B(National
trunk roads) and C(primary roads) Class roads with AADT between 2000
and 6000 p.c.u.
iii. Climbing Lanes is required on roads with AADT>6000 in Design Year 10.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

58

3.1.14.2 Assumptions and Application

Where Climbing lanes are required, they shall be introduced as follows:


In Class A roads, where the speed of a typical heavy vehicle falls by 15
kph from that speed which the same vehicle would maintain in a level or
downhill section of the same road.
In Classes B and C roads they are applied where speed drops by 20 kph.
For design purpose, it may be assumed that the highest obtainable speed
on a level or downhill section of road for a typical heavy vehicle will be
80% of the Design Speed or 80 kph whichever is the lower.
Climbing lane shall be terminated when the speed of a typical heavy
vehicle reaches the speed at which the Climbing lane was introduced.
Where Climbing Lanes are required, the widths of the traffic lanes and
adjacent shoulders shall be reduced.
The introduction and termination of a Climbing lane shall be effected by
tapers of 60m but this not considered as part of the Climbing Lane.
The start and end of Climbing lane section is calculated based on the
performance of a typical heavy vehicle of power to weight ratio 90 kg/h.p.
on various gradients.
For the Year 10 Design traffic in p.c.u., the highest forecast traffic flow for
each road section was used and converted to p.c.u. using conversion
factors listed in Chapter 3 page 3.9 and considering rolling terrain of the
Kenya Design Manual Part 1.
i.
ii.
iii.
iv.
v.

Passenger cars 1.0


Light Goods vehicle 1.5
Medium Goods Vehicle 5.0
Heavy Goods vehicle 8.0
Buses 4.0

3.1.14.3 Assessment of Climbing Lane Need

Lot E roads have been assessed based on Class C road as specified in the
Kenya Design Manual.
ROAD E1.1: MUSITA LUMINO
Road Class C
Year 10 Traffic = (4x34+1.5x342+5x812+8x44) = 5061 p.c.u. in Year 20
(2030)
Need for CL evaluation = Yes
Assume Design Speed = 90 km/h

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

59

Typical heavy vehicle speed on level or downhill section = 80% of 90


km/h = 72 km/h
CL to be introduced when heavy vehicle speed drops to = 72 20 = 52
km/h

LENGTH
(m)

SLOPE
(%)

DISTANCE
TO START
OF CL (m)

MINIMUM
LENGTH
OF CL (m)

4+900

1100

400

700

Provide 900m
Climbing
Lane-LHS?

10+800

11+240

440

300

140

Not Economical

16+000

16+400

400

400

NA

Not required

16+900

17+400

500

400

100

Not Economical

21+200

21+500

300

400

NA

Not required

27+700

28+100

400

400

NA

Not required

30+000

30+360

360

300

60

Not Economical

30+600

30+900

300

400

NA

Not required

30+900

31+300

400

300

100

Not Economical

31+000

31+300

300

300

NA

Not required

31+400

32+000

600

400

200

Not Economical

39+500

40+000

500

300

200

Not Economical

40+500

41+200

700

400

300

Not Economical

43+300

44+500

1200

400

800

Provide 1000m
Climbing LaneLHS

44+700

46+000

1300

200

1100

Provide 1400m
Climbing LaneRHS

46+100

46+600

500

400

100

Not Economical

55+100

55+600

500

400

100

Not Economical

58+800

59+200

400

400

NA

Not required

76+700

77+000

300

300

NA

Not required

FROM

TO

(Km)

(Km)

3+800

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

COMMENT

60

ROAD-1.2: BUSIA MAJANJI


Road Class C
Year 10 Traffic = (4x15+1.5x360+5x134+8x11) = 1358 pcu in Year 20
(2030)
Need for CL evaluation = No
Assume Design Speed = 90 km/h
Typical heavy vehicle speed on level or downhill section = 80% of 90
km/h = 72 km/h
CL to be introduced when heavy vehicle speed drops to = (72 20) = 52
km/h
LENGTH
(m)

SLOPE
(%)

DISTANCE
TO START
OF CL (m)

MINIMUM
LENGTH
OF CL (m)

10+840

240

400

NA

Not required

17+340

540

400

140

Not Economical

FROM

TO

(Km)

(Km)

10+600
16+800

3.2

Pavement Design

3.2.1

Introduction

COMMENT

The project roads are intended to be upgraded to bitumen standard with 7.0m
carriageway and 2.0m wide shoulders both sides.
The pavement design of the project roads is based on the Ministry of Works,
Housing and Communications Road Design Manual Vol. 3: Pavement Design,
Part I: Flexible Pavements (July 2005).
3.2.2

Design Period
The economical analysis of the project roads is based on a 20 year analysis
period. Hence a 20 year pavement design period has been adopted.
It does not mean that at the end of the design period the pavement will be
completely worn out, but strengthening may be required so that it continues to
carry traffic satisfactorily for a further period. However, some routine

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

61

maintenance is expected to be performed on regular basis throughout the design


period to curtail major distress propagation.

3.2.3

Pavement Design Input Data


Climate
All the project roads fall in the tropical rain zone and have most rains in March to
June and August to November. They are therefore in the predominantly wet
regions.
Traffic Loading Class
The traffic loading classes for the different roads were obtained from the traffic
count studies. It is found that all the project roads fall between T1 and T4 Traffic
Load Classes.
Traffic Loading classes are as stipulated in the design manual:

Design traffic
loading
(E80 x 106
<0.3
0.3-0.7
0.7-1.5
1.5-3.0
3.0-6.0
6.0-10
10-17
17-30

Traffic
load
class
T1
T2
T3
T4
T5
T6
T7
T8

3.2.3 Subgrade
The subgrade soils were tested for soaked CBR determination. These CBR
values were analysed and design CBR and soil subgrade classes were obtained.
Subgrade Strength Classes are as stipulated in the design manual:

Design
CBR %

Subgrade
Strength
Class

2
3-4
5-7
8-14

S1
S2
S3
S4

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

62

15-29
30+

S5
S6

3.2.4 Soft spots and Marshy areas


Where such sections are encountered (outside swampy sections) a selected fill
material or rock fill is assumed necessary to raise the subgrade design CBR to
8%. The selected fill material shall need to be a minimum depth of 450mm, and
care should be taken to ensure that there are no weak materials underlying this
layer which may lead to detrimental performance.
3.2.5

Pavement Materials
Pavement materials were obtained during field investigation. It was found that
plenty of lateritic gravels are available along the project roads. These gravels are
suitable for stabilization with cement or lime.
Field investigation also revealed the availability of rock sources along the project
roads, these rocks will be suitable for crushed stone base, and bituminous
pavement works.

3.2.6

Pavement Design Catalogue


The pavement design catalogue to be adopted for the design shall be as
obtained from Chart W2 (Granular base/Cemented subbase) and Chart W3
(Cemented base/Cemented subase). (Road Design Manual Vol. 3: Pavement
Design, Part I: Flexible Pavements).
The pavement layer thicknesses given in charts shall be adjusted to provide layer
thickness which is convenient during construction, and also increase thicknesses
of lower layers which are cheaper than the upper layers.
However care has to be taken to ensure that the proposed layers are structurally
superior to those of the charts.
The pavement structures presented in these charts represent alternate
construction approaches differing basically in base course and surfacing
materials. These are expected to render equal quality to road user perception
cost.

3.2.7

Pavement Structural Design


Two options for the pavement structure have been provided.
Option no. 1:

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

63

The pavement structure is composed of Granular Base Course on Cemented


Subbase Course. The surfacing given is asphalt concrete.
This pavement is much durable with minimal maintenance. However, the
construction cost for the asphalt concrete is much higher compared to that of
surface dressing.
Option 2:
The pavement structure in this option is composed of Cemented base and
Cemented subbase, the surfacing is Double surface dressing.
This option was not considered further during the detailed stage as the Client
indicated its preference for Option 1 that uses asphalt concrete for bituminous
surfacing
3.2.8

Design Traffic Loading


Traffic studies show cumulative number of standard axles as follows:
Estimated traffic growth rate (pessimistic) = 8.7x106
Estimated traffic growth rate (realistic)
= 8.99x106
Estimated traffic growth rate (optimistic)
= 9.37x106
Estimated traffic growth rate (realistic)
of the pavement structure
Traffic class obtained is:

3.2.9

= 8.99x106 is adopted for the design

T6

Design Subgrade CBR


Analysis of soaked CBR test results for the road alignment subgrade soil
involves establishing the design CBR for the section as obtained from 90%-ile
chart.
The 90%-ile value for a section is the CBR value which 10% of the test results
fall below. This is obtained by plotting a graph of CBR values (arranged in
ascending order) against the test number and obtain the CBR value
corresponding to
d = 0.1 x (n-1)
where d = is the value in the horizontal axis starting from sample 1
n = number of tests used in the design.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

64

70
65
60
55
50
45
40
35
30
25
20
15
10
5
0

n = 34 tests
d = 0.1 x (n-1)
= 3.3
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34

CBR (%)

DESIGN CBR (Road no.1 Musita-Lumino)

TEST

Figure 16 : Musita-Lumino Subgrade Analysis


From the above figure, the design CBR = 6%
DESIGN CBR FOR (Road no. 1 Busia - Majanji)

70
60

CBR (%)

50
40
30

n = 9 tests
d = 0.1 x (n-1)
= 0.8

20
10
0
1

TEST

Figure 17 : Busia-Majanji Subgrade Analysis

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

65

From the above figure, the design subgrade CBR = 6%


3.2.10 Design Subgrade Class
The design subgrade class is presented in summary below.

Musita -Lumino
Chainage
S/No

From

Design
CBR
(%)

Subgrade
Class

(Km)

90th
percentile
value

74

S3

Road
Length

90th
percentile
value

Design
CBR
(%)

Subgrade
Class

To

0+000- 74+000

Busia Majanji
Chainage
S/No
1

Road
Length

From

To

(Km)

2+000- 26+000

24

S3

3.2.11 Proposed Pavement Structure


From design chart Chart W2 (T6, S3), the following has been adopted.

Pavement layer

Type of material

Layer
thickness
50 mm

SURFACING

AC(Asphalt Concrete)

BASE COURSE

GB(Granular Base)

150 mm

SUBBASE

CSB(Cemented Subbase)

175 mm

IMPROVED SUBGRADE

G15 (Natural Gravel CBR >15%)

125 mm

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

66

3.3

Drainage Design

3.3.1

Design Return Period


The frequency of the flood for the design of drainage structures depends on the
risk to be taken, that defines the degree of risk that we run in designing a
structure during the anticipated service life. Therefore, the estimation of the
design floods considered the ERA Drainage Design Manual, 2002 (in Road
Design Manual, Vol.2 Drainage Design, 2005) which is summarized in Table 23.

Table 23: Design Average Recurrence Intervals for Flood/Storm (yrs) by Geometric
Design Criteria (Source: ERA Drainage Design Manual, 2002 in Road
Design Manual, Vol.2 Drainage Design, 2005)
Structure Type

Gutters and Inlets*


Side Ditches
Ford/Low-Water Bridge
Culvert, pipe (see Note)
Span < 2m
Culvert, 2m < span < 6m
Short Span Bridges 6m < span < 15m
Medium Span Bridges 15m < span <
50m
Long Span Bridges spans > 50m
Check/Review Flood

Paved Ia,
Paved Ib,
Paved II
10/5
10
25

Geometric Design Standard


Paved III,
Paved III,
Gravel A
Gravel B

Gravel C

2
10
10

2
5
5

5
5
5

50
50
100

25
50
50

10
25
50

10
25
50

100
200

100
200

100
100

100
100

Note 1: Span in the above table is the total clear-opening length of a structure. For example, the span
for a double 1.2-meter diameter pipe is 2.4 meters, and the design storm frequency is therefore
culvert, 2m<span <6m. Similarly a double box culvert having two 4.5 meter barrels should use the
applicable design storm frequency for a short span bridge and a bridge having two 10-meter spans is a
medium span bridge.

3.3.2

Frequency Distribution Models


In flood frequency analysis, the objective is to estimate a flood magnitude
corresponding to any required return period of occurrence. The resulting
relationship between magnitude and return period is referred as the Q-T
relationship. Return period, T, may be defined as the time-interval (on the
average) for which a particular flood having magnitude Q T (also known as
quantile) is expected to be exceeded.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

67

In this work, a compatible distribution model has been considered for


hydrological analysis. The comparison between the goodness of fit assessments
for different distributions indicate that the Gumbel Extreme Type I distribution is
more reasonable and reliable to the hydrologic events and has been widely used
for estimating the design rainfall at any given return period. Therefore, the rainfall
frequency analysis has been carried out using Gumbel Type I frequency
distribution.
A general equation for frequency analysis of hydrologic events is given as
(Chow, 1964).
The equation for the quantile estimate is given by:

RT = + KT

[Equation 1]

where
RT = daily rainfall amount for return period T
= central tendency from fitted probability distribution
= standard deviation from fitted probability distribution
KT = reduced variate of the probability distribution depending on
return period and sample size read from probability distribution
tables
For Generalized Extreme Value (GEV) distribution which best fitted the data for
most stations, KT can be estimated from:

= (= )

[Equation 2]

The analysis has been carried out for return period of 10, 25, 50 & 100 years as
per design standard of the project. Table 24 presents the estimated design
rainfall
at
different
return
period.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

68

Table 24: Estimates of design rainfall at different return periods


Quantile for Return Period (T), QT [mm]

Station
Name

Jinja

Station
Code

89330430

Statis.
Distrib.
T

10000

1000

100

20

10

1.5

1.33

1.3

1.11

1.05

1.02

0.01

0.1

10

20

50

67

75

80

90

95

98

GEV

157.2

142.9

125.6

110.1

101.8

82.3

72.6

62.9

57.3

53.5

43.5

35.2

25.9

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

69

3.3.3

Design Flood Estimation


The term design flood refers to the flood hydrograph or peak discharge value that
is finally adopted as the basis for design after giving due consideration to the
flood characteristics, frequency and damage potential, including economic and
other related factors.
By make use of the estimated design rainfall, watershed characteristics and
physical data from field visit, the design floods for the different road drainage
watersheds were calculated. The adopted models are discussed hereunder.

3.3.4

Runoff Models
Despite of the model used, accurate estimation of the design discharge depends
on accurate assessment of the various parameters used in the model. Among
the parameters include the flow data, rainfall data, catchments area and
characteristics such as mainstream length and slope, curve number, coefficient
roughness, time of concentration, length of the channel and slope and catchment
land use and cover. In this study, the TRRL East African Flood Model (ungauged catchment) and Frequency analysis (gauged catchment) were used.

3.3.5 Frequency analysis


There exist different types of frequency distributions in frequency analysis
models. The most applicable type of models for peak flood analysis, Log Pearson
Type III distribution programmed in Excel spreadsheet was used.
Table 25: Estimate of design floods at different return period
Flood Frequency Calculations using log-Pearson Analysis III
(period of record 1999-2009)
Return Period
(years)
2
5
10
25
50
100
200

Skew Coefficient
K (-0.0403)
0.0068
0.8436
1.2772
1.7369
2.0322
2.2962
2.5381

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

Discharge
Q (m3/s)
46
64
76
91
102
113
125

70

3.3.6

The TRRL East African Flood Model


The TRRL East African Flood Model has been recommended as the most
appropriate model for the estimation of design floods for the different un-gauged
catchments in East Africa and has been widely used.
In the TRRL model, the base time is assumed to be the time from 1 per cent of
peak flow on the rising limb to 10 per cent of peak flow on the falling limb of the
hydrograph. For East African catchments, it has been found to vary between 2.7
and 11.0 unlike the US hydrographs, where the ratio of base time to time to peak
is approximately 3.0. Owing to wide range, the use of a single hydrograph base
on time to peak was therefore considered not appropriate.
A much more stable ratio was found to be the peak flow (Q) divided by the
average flow measured over the base time (Q) (Peak Flow Factor).

F=

[Equation 3]

Q
The peak flow was estimated if the average flow during the base time of the
hydrograph can be calculated.

The total volume of runoff is given by:

RO = (P
Where:

Y )C A * A *10 3 (m3)

[Equation 4]

P = rainfall (mm) during time period equal to the base time


Y = initial retention
CA = contributing are coefficient
A = catchment area (km2)

If the hydrograph base time is measured to a point on the recession curve at


which the flow is one tenth of the peak flow, then the volume under the
hydrograph is approximately 7 per cent less than the total runoff.
The average flow (Q) is therefore given by:

Q=

0.93 * RO
3600 * TB

[Equation 5]

Where:
TB = hydrograph base time (hrs.)

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

71

Estimates of Y and CA are required to calculate RO and lag time K to calculate


TB.
Initial Retention (Y)
In arid and semi arid zones an initial retention of 5 mm is considered, and zero
elsewhere

Contributing Area Coefficient (CA)


Contributing area coefficient is a coefficient that reflects the effects of the
catchment wetness and the land use. A grassed catchment at field capacity is
taken as a standard value of contributing area coefficient. The design value of
the contributing area coefficient was estimated from the following equation.

C A = C S * CW * C L

[Equation 6]

Where: CS = the standard value of contributing area coefficient for a grassed


catchment at field capacity
CW = the catchment wetness factor
CL = the land use factor
The three factors are given in Tables 5.2, 5.3, and 5.4 of the TRRL Laboratory
Report 706 (Tables 26, 27 and 28 below).

Table 26: Standard Contributing Area Coefficient (wet zone catchment, short grass
cover)
(Source: TRRL Laboratory Report 706)
Soil Type
Catchment Slope
Very Flat
< 1.0 %
Moderate
1-4 %
Rolling
4-10 %
Hilly
10-20 %
Mountainous > 20 %

Well Drained

0.09
0.10
0.11
0.12

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

Slightly Impeded
Drainage
0.15
0.38
0.45
0.50

Impeded Drainage
0.30
0.40
0.50

72

Table 27: Catchment Wetness Factor (Source: TRRL Laboratory Report 706)
Catchment Wetness Factor

Rainfall Zone

Perennial Streams

Ephemera Streams

1.0
1.0
0.75
0.60

1.0
1.0
0.50
0.30

Wet Zone
Semi Arid Zone
Dry Zones (except West.
Uganda)
West Uganda

Table 28: Land Use Factor (Base assumes short grass cover)
(Source: TRRL Laboratory Report 706)
Land Use
Largely bare soil
Intense cultivation (particularly in valleys)
Grass cover
Dense vegetation (particularly in valleys)
Ephemeral steam, sand filled valley
Swamp filled valley
Forest

Land Use Factor


1.50
1.50
1.00
0.50
0.50
0.33
0.33

Catchment lag Time (K)


The appropriate values of lag time were estimated from Table 29. Care was take
in assessing which category to place a given catchment, as generally only small
areas on either side of the stream are contributing to the flood hydrograph.

Table 29: Catchment Lag Time (Source: Table 5.5 of TRRL Laboratory Report 706)

Catchment Type
Arid
Very steep small catchments (slope > 20 %)
Semi arid scrub (large bare soil patches)
Poor pasture
Good pasture
Cultivated land (down to river bank)
Forest, overgrown valley bottom
Papyrus swamp in valley bottom

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

Lag Time (K) in hrs


0.1
0.1
0.3
0.5
1.5
3.0
8.0
20.0

73

Base Time
The rainfall time (TP) is the time during which the rainfall intensity remains at high
level. This was approximated by the time during which 60 per cent of the total
rainfall occurs. Using the general intensity duration frequency equation,

i=

a
(0.33 + t d ) c

[Equation 7]

The time to give 60 per cent of the total rainfall is given by solving equation 7.
c

t 24.33

0.6 = d
24 td + 0.33

[Equation 8]

Values for the various rainfall zones of East Africa are given in Table 30.
Table 30:

Rainfall Time (TP) for East African 10 year Storm


(Source: Table 5.6: TRRL Laboratory Report 706)

Zone

Index 'c'

Inland zone
Coastal zone
Kenya Aberdare Uluguru Zone

0.96
0.76
0.85

Rainfall time (TP)


(hr)
0.75
4.0
2.0

The flood wave attenuation (TA) was estimated from equation 9.

TA =

0.028 L
1

[Equation 9]

Where:
L = length of main stream (km)
Q = average flow during base time (m3/s)
S = average slope along main stream
The base time was estimated as:

TB = TP + 2.3K + T A

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

[Equation 10]

74

The iterative/ trial and error solution was carried out. Initially TA was assumed
zero, and two iterations were considered adequate. Knowing Q and F, the peak
was calculated using equation 3.
The following pages illustrate the computation process using the TRRL East African
Flood Model in one of the drainage catchment. The same approach programmed in
excel spreadsheet was used in the computation of the design floods in other
watersheds.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

75

a)

Catchment characteristics:
Catchment area, A (km2)
8.623
km2
Land slope, S =
0.045
Main stream average Slope, Sc =
0.032
Major stream flow length, L (m)
4016
m
Land use: Gently sloping catchment, cultivated down to river channel banks (sugarcane, maize, cassava)
and settlement

b)

Catchment Lag time (K):

Arid
Very steep small catchments (>20%)
Semi arid scrub (bare soil patches) =
Poor Pasture =
Good pasture =
Cultivated land (down to river banks)
Forest, overgrown valley bottom
Papyrus swamp in valley bottom

0.1
0.1
0.3
0.5
1.5
3
8
20

c)

STD Contributing area coefficient Cs =


Soil type (Slightly impended drainage)
Catchment slope (Rolling 4-10%)

0.45

d)

Antecedent Rainfall zone


NYANZA UG

e)

hr

TRRL Table 4 pp 18
TRRL Fig 15: soil zones

Potential ET

5.6

mm/day

2 day antecedent
7 day antecedent
Soil Moisture recharge

21.1
48.4
60.9

mm
mm
Mm

Catchment wetness factor, Cw


Rainfall Zones

Wet zones
Semi arid zone
Dry zones
(exept West
Uganda)
West Uganda

TRRL 706_Table 7
pp 20

TRRL Table 3 pp
17
TRRL Fig.
14

TRRL 706_
Table 3-pp17 &
Table 5-pp 19

Catchment wetness factor (Cw)


Perennial Ephemeral
streams
strea
ms
1
1
1
1
0.75
0.5
0.6

0.3

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

76

f)

Land use factor CL


Largely bare soil
Intense cultivation (Particularly in valleys)
Grass cover
Dense vegetation (particularly in valleys)
Ephemeral stream, sand filled valley
Swamp filled valley
Forest

1.5
1.5
1.5
1
0.5
0.5
0.33
0.33

g)

Contributing area coefficient, CA = (Cs*Cw*CL)

0.675

h)

Initial Retention, Y
If
Semi arid or West Uganda

5
5

Elsewhere, Y =
i)

0.75

Rainfall time, Tp for EA 10 year storms:

mm

TRRL 706
Page 11 (summary,
(h)) and Fig.14

hrs

TRRL 706_Fig 16 &


Table 8

0.75
0.96

Design rainfall during time interval (TB), P (mm):


10 year daily point rainfall =

k)

Eqn 8 , TRRL

Inland zone Tp =
Index, "n" =
j)

TRRL Table 6 pp 19

108.16

mm

1st Iteration of Base time, TB (hr): (Tp + 2.3K + TA)

7.65

hr

Assuming 1st Iteration


Rainfall during base time RTB =

TA =

RTB = (TB/24)*(24/(TB + 0.33))^n * R10/24

100.53

mm/d

Index, n for 10 yr design storm

0.96

hr

10 yr max average daily rainfall, R10/24

108.16

mm/d

TRRL Eq 12

Where:

Area Reduction Factor, ARF =


1- 0.04*T^(-1/3) *A^(0.5)
Area, A
8.62
Time, T = TB =
7.65
ARF =
0.94
Average rainfall, (P) = ARF * RTB
94.53
l)

Volume of runoff, RO (m3) = (CA * (P - Y) * A * 1000)

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

TRRL 706_Fig 16 &


Table 8

km2
hr
mm/d

521125.67 m3

TRRL Eqn 6

77

m) Average flow

Qav =

(0.93*RO/(3600*TB)

=17.60 m3/sec

TRRL Eq 13

nd

TB (2 approximation iterative procedure)


ITERATION OF Qav and TB
TB
Qav
17.5979
7.65
17.5959
7.6509
17.5959
7.6509

TA
0
0.0009
0.0009

New values after Iteration:


10
year daily point rainfall R10/24 =
Rainfall during base time, RTB = (TB/24)*(24/(TB + 0.33))^n * R10/24

n)

Area Reduction Factor, ARF =


1- 0.04*T^(-1/3) *A^(0.5)
Area, A
Time, T = TB =

8.62
7.65

km2
hr

ARF =
Average rainfall, (P) = ARF * RTB

0.94
94.53

mm

Volume of runoff, RO (m3) =

521131.95 m3

(CA * (P - Y) * A * 1000)

Average flow, Qav =


o)

108.16 mm/d
= 100.53 mm/d

(F* Qav)
DESIGN PEAK FLOW , Q =
Where peak flood factor, F is given as:
Computed
For K < 0.5 hr,
For K > 1.0 hr,
Therefore
Design Peak flow for T= 25, 50, 100 years
Peak Discharge Factor

K=
F=
F=
Q10 =

Q100:Q2

2.075

Q50:Q2

1.825

Q25:Q2
Q10:Q2
Q100:Q10
Q50:Q10
Q25:Q10

1.667
1.490
1.393
1.225
1.119

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

17.60

m3/sec

40.47
2.3
3
2.8
2.3
40.47

m3/sec

TRRL Eqn 6

TRRL Eqn 5

hr

m3/sec

TRRL
Laboratory
Report 623
Appendix
1,
Fig. 3

Q100
Q50
Q25

56.36
49.56
45.27

m3/s
m3/s
m3/s

78

3.1.8

Design Discharges

Tables 31 and 32 present the design discharges of the project road under the
project for the different return periods.

Table 31: Summary of design floods for different return period


Road E1.1- Musita-Lumino
Design flood discharge (m3/s)
Chainage
Catch.
Catch.
from
Northing Easting
area
Ref.
(km2)
Musita
10-yr
25-yr
50-yr
100-yr
283
5+060
546926
55901
1.34
6.28
7.02
7.69
8.75
284
5+440
547329
55567
1.18
5.56
6.22
6.80
7.74
286
7+276
548534
54543
8.62
40.47
45.27
49.56
56.36
287
11+250
551778
51971
0.74
3.66
4.09
4.48
5.09
289
11+660
554420
50807
1.24
3.83
4.28
4.69
5.33
290
15+870
556063
50594
4.78
14.72
16.46
18.02
20.50
292
16+833
558983
50334
1.54
7.86
8.79
9.62
10.94
293
18+800
559865
50573
0.42
1.28
1.44
1.57
1.79
294
19+700
561223
50599
0.21
0.64
0.72
0.78
0.89
295
21+100
562439
50433
0.40
1.24
1.39
1.52
1.73
296
24+000
564029
50880
2.03
6.26
7.00
7.66
8.72
297
25+810
565785
50809
0.29
0.88
0.99
1.08
1.23
298
28+640
568503
50122
0.73
2.24
2.50
2.74
3.11
299
29+465
569306
50281
1.18
5.53
6.18
6.77
7.69
300
30+910
570662
50663
0.71
2.17
2.43
2.66
3.03
31+970
571704
50447
0.44
1.29
1.46
1.59
1.99
34+360
574025
50099
14.32
44.12
49.35
54.03
61.44
301
574151
50076
302
37+960
577490
50202
3.75
11.56
12.93
14.16
16.10
40+240
579850
50501
24.97
88.43
98.91 108.29 123.15
303-306
582090
50406
582238
50370
307
45+990
585222
49136
9.09
42.58
47.63
52.14
59.3
308
50+260
588250
46187
11.47
49.98
55.9
61.2
69.6
309
54+130
591146
41090
13.18
42.82
47.89
52.43
59.63
310
54+870
591696
43504
10.54
32.48
36.33
39.77
45.23
311
58+590
594212
40880
12.42
30.38
33.98
37.2
42.31
7.01
7.84
8.59
9.76
312
63+270
597842
38019
1.13
313
73+330
607154
35225
3.26
17.82
19.93
21.82
24.81
314
76+660
610229
36199
0.97
3.00
3.36
3.67
4.18

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

79

Table 32: Summary of design floods for different return period


Road E1.2- Busia-Majanji
Design flood discharge (m3/s)
Chainage
Catch.
Catch. area
from
Northing Easting
(km2)
Ref.
Busia
10-yr 25-yr
50-yr
100-yr
325
1+125
620283
51064
0.19
0.88
0.98
1.07
1.22
324
1+480
619949
50892
0.57
2.87
3.21
3.51
3.99
323
6+970
616014
47143
2.0
10.03
11.22
12.29
13.97
322
10+310
614350
44331
0.88
4.41
4.94
5.4
6.14
0.16
321
10+885
614081
43819
0.81
0.90
0.99
1.12
320
11+860
613606
42931
8.35
24.68
27.61
30.22
34.37
16+310
611423
38133
3.96
17.82
19.94
21.83
24.82
318
17+390
610871
36614
317
21+600
610325
34182
4.96
22.18
24.81
27.16
30.89
316
23+180
610300
32610
0.80
3.12
3.49
3.82
3.12
315
25+500
610374
30420
1.38
5.36
5.99
6.56
7.46

3.4 Structure Selection


3.4.1 Design Philosophy
Provision of efficient and adequate drainage system is extremely important for the
life of the road in terms of reducing maintenance cost and preventing adverse
environmental impacts. Inadequate drainage design will contribute highly to the
deterioration of the pavement structure. Areas to which attention should be given
could be categorized as surface and subsurface drainage along the road and
cross drainage.
The design of side ditches, culvert capacities and bridge waterway openings are
governed by the criteria specified in the UNRA manual.
The surface drainage system, which will take care of rain water from the
pavement surface, adjacent cut slopes and the ground cross fall will be treated by
proper cambering of the roadway and by the introduction of side ditches.
Minor drainage structures are specified as standard structures and are
recommended based on hydraulic efficiency, terrain condition, type of foundation
material, the safety of the surrounding dwellers and road traffickers.
Except for the bridges, standard drawings are adopted unless there is a call for
site specific design.
The type and size of drainage structure specified for a particular location is often
determined based on site specific conditions. But a generalized structures

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

80

selection effort is made to initially identify the benefits of a certain types of


structure based on the general prevailing local condition, like availability of local
material at the project vicinity, skilled labour, capacity of the construction industry
and cost efficiency.
Bridge is recommended where it is more economical than a culvert, perhaps due
to the need to bury a culvert under a high level of fill. They are also employed to
satisfy land use requirements, to mitigate possible environmental harm with a
culvert, to avoid floodway or irrigation canal encroachments, and to
accommodate large debris.
Culverts are used where bridges are not hydraulically required, where debris is
tolerable, and where they are more economical than a bridge. Culverts can be
concrete box culverts, concrete slab, reinforced concrete pipe culverts, or
corrugated metal culverts or plastic.
Concrete box/slab culverts are constructed with a square or rectangular opening,
and with wing walls at both ends. They are usually specified for larger flows,
where the area of the opening is larger than a practical pre-cast circular concrete
pipes. There may also be the case where the cost estimate of concrete box/slab

culverts constructed on site are less expensive than manufactured and/or


imported pipe culverts.

3.4.2 Bridges
The choice of a bridge type is a matter of
Safety
Environmental factors
Economics
Availability of local construction materials in enough quantity and quality
Availability of semi skilled and skilled labour in enough number to be
deployed for the project work
The current capacity of the construction industry
The possibility and ease of construction
The possibility, ease and frequency of regular maintenance
3.4.2.1 Bridge Material

The following table highlights the comparison of various bridge construction


materials that the consultant has taken into account in reaching a decision on the

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

81

Reinforced Concrete

Composite /steel& concrete/

Sand /available at the project route/

Sand /available at the project route/

Availability

Aggregate /can be crashed from

Aggregate /can be crashed from

of material

quarry within the project site/

quarry within the project site/

Cement /locally produced at Tororo/

Cement /locally produced at Tororo/

Reinforcement bars/ imported/

Reinforcement bars/ imported/

Steel
Steel profiles all /imported/

Steel profiles/imported/

Advantage

Disadvantage

Low cost

Structural advantage to reduce dead

Fast to assemble

Flexibility in design

load

No

Common practice

False work not required

work

Heavy self weight

Relatively higher cost

Higher cost

Takes quite some time to build

Needs regular maintenance effort

Needs regular maintenance

shuttering

and

false

Requires false work to be erected in

effort

the river course unless precast used

Some times required special


welding task

First

second

Priority &

can easily be done by the available

reason

skilled labor in the market

third

Concrete inputs are very easily


available within the project route
which can result in higher cost
reduction
Labour

intensive

hence

creates

money temporary jobs

Abutment/Wing walls
Reinforced Concrete

Masonry

Sand /available at the project route/

Stone /available at the project route/

Availability

Aggregate /can be crashed from quarry within the project

Sand /available at the project route/

of material

site/

Cement /locally produced at Tororo/

Cement /locally produced at Tororo/


Reinforcement bars/ imported/

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

82

Advantages

Freedom of having taller heights

Lower cost

Reduced self weight

economical for height less than 10m

Good to distribute load to weak foundation material

masonry work is a common practice can be done

No risk of quality, concrete is mixed at batching plants.

easily
do not require shuttering work

Disadvantage

Relative higher cost

Supervision difficulty in controlling the quality of

Requires shuttering & scaffolding work

mortar used

First
Priority

&

Better quality, long live despite the relative higher cost

reason

Second
Relative lower costs due to quality masonry
stone is available within the project route

selection of the type of material for the construction of all bridges in the project.
Incorporating the general factors for the choice of a bridge type above and taking
into consideration the following points:
1. evaluating the result of existing structures assessment
2. results of the detail geotechnical foundation investigation
3. discussions and approval made by the client /UNRA/
reinforced concrete for both super structure and abutments/wing walls is selected
for all new bridges of the entire project roads.
3.4.2.3 Bridge Structural System

Though the selection of the bridge system is mostly site specific, simply
supported structural bridge system with 12 meter length and its multiple, is
selected as a standard bridge for the entire project roads. The following important
points were considered in selecting the bridge system.
1. Standardizing is the TOR requirement
2. Standardizing minimizes cost by allowing repeated us of
forms, reduced effort in bar bending and easy to master the
details for the construction task force
3. Discussions made with UNRA bridge team

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

83

3.4.2.5 Bridge Construction System

In view of the topographic formation of the project routes and river crossings, the
design consultant opts to adopt precast superstructure standard system of
construction for all the new bridges for the entire project roads.
The following important additional points are also taken into consideration in
selecting the standard precast system.
1. The existence of new bridges in swamps crossings, demands
fast way of construction to finalize the construction of the
bridges during the dry period where the water flow is low
2. Risk of settlement and difficulty in using props to support
formworks on the soft bed material unless replaced.
3. The availability of hauling and lifting equipments, capacity of
the construction industry is assessed, discussed and agreed
with UNRA bridge team.

3.4.3 Slab/Box Culverts


As defined earlier, slab culverts are those with top slab resting on gravity type
abutments (usually masonry) each done separately, and box culverts are those
having monolithic top slab, bottom slab and the vertical walls.
Slab culverts are usually recommended in road sections having good foundation
or bed material with minimum risk of settlement and scouring at abutment
foundation.
Box culverts are proposed on areas where the foundation material is found weak
and to avoid any possibility of foundation failure.
After putting in to consideration the following points:
Considerable number culverts are required in areas where the
project roads intercept the swamps and their detail
geothechnical investigation revealed that the foundation
material at shallow depth is weak.
Having difficulty to control the quality of mortar to be used in
the formation of masonry abutments in case of slab culverts
The better quality and rigidity of the box culverts is demanded
and approved by the client.
Box culverts are selected for the entire project roads.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

84

To allow a repeated use of formwork and minimize cost and time, standard span
box sizes are adopted for the entire project roads. Their detailing is shown on the
standard box culverts in the book of drawings.

3.4.4 Pipe Culverts


The minimum size of pipe culvert proprosed to be used as cross-drainage on
entire project roads is 900mm in conformity with the UNRA drainage design
manual.
Because of economy, easy of production at site and durability standard concrete
pipe is selected to be used for the entire project roads. Their detail is shown in
the standard pipe culverts drawings
Concrete headwall is selected to be used for the pipe culverts in the entire road
project roads despite its relative higher cost after considering the following facts.
Better quality at relative higher cost than brick or masonry
Demanded and agreed by the client/UNRA/
The concrete head wall is designed in three different models to suite the smooth
inflow of water into the pipes. The selection is made site specific to avoid
potential scour at the inlet and outlet. Their detail is shown on the standard pipe
culverts in the book of drawings.
The table below highlights the comparison made between the various material
alternatives proposed for pipe culverts.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

85

Pipe options
Concrete
Material

Sand /available at the


project route/

Availability

Plastic
Imported

Head wall options


Armco
Imported

Aggregate /can be
crashed from quarry
within the project site/
Cement /locally
produced at Tororo/
Reinforcement bars/
imported/
Low cost

Advantage

Can be produced at
site
durable

Masonry
Stone /available at the
project route/
Sand /available at the
project route/
Cement /locally
produced at Tororo/

Brick

Concrete

Brick /everywhere
available at the project
route/

Sand /available at the


project route/

Sand /available at the


project route/
Cement /locally
produced at Tororo/

easy handling

easy handling

low cost

moderate cost

and transport

and transport

manageable to build
several culverts along
the route

manageable to build
several culverts along the
route

Aggregate /can be
crashed from quarry
within the project site/
Cement /locally
produced at Tororo/
Reinforcement bars/
imported/
better quality
extended life
easy to control material
quality

Disadvantage

handling

higher cost
could be
attacked by
chemicals

First
priority &
reason

Second

lower cost due to


availability of local
materials within the
project vicinity

higher cost
could be
attacked by
chemicals
possibility of
corrosion
mostly stolen
Third

difficult to control

requires plastering

relative higher cost

quality of mortar

lower durability

reqiures shattering

difficult to control quality


of mortar

First

Second

relative lower cost

higher durability
avoids at large hard
currency requirement

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

86

Third

3.4.5 Paved Side Ditches


Grouted stone pitching side ditches/ road gutters/, if well done and maintained
regularly, can serve the purpose they are intended for as the design consultant
looked around at the existing roads and on the main trunk roads.
Grouted stone pitching trapezoidal open channel side ditches are selected as
standard paved side ditches for road gradient exceeding 3% in the entire project
roads outside of town or trading centres. Very low relative cost as compared to a
precast or cast-insitu concrete paved ditch is the prime factor for the selection of
grouted stone pitching side ditches as standard.
However, paved side ditches in towns and trading centres need to be covered to
allow access for pedestrians and traffic at selected locations. To secure safe and
long lasting covered paved ditches the design consultant selected rectangular
reinforced concrete paved side ditches with cover at selected positions as
standard for all the towns and trading centres in the entire project roads. The
selection was also discussed and agreed with clients engineer team. Please refer
to book of drawings for the Standard Paved Side Ditches and Standard Paved
Side Ditches for Urban and Trading Centres for details.

3.5

Hydraulic Design

3.5.1 Minor Drainage Structures


3.5.1.1 Paved Side Ditches

The size of side drains is determined from the Mannings open channel equation,
Q=

(1/n)*A*(R2/3)*S1/2

Q=
A=
R=
s=
n=

discharge in m3/s
area of flow in m2
hydraulic radius
bed slope
roughness coefficient

Where,

And the depth of flow is kept 0.4m according to UNRA Drainage Manual to protect
possible saturation and erosion of road pavement. The channels from the road
surface are estimated using the rational formula:
Q=0.278*C*I*A
Where,
Q=
C=
I=
A=

Discharge in m3/s
Run off coefficient
Intensity of rainfall in mm/hr for 10min storm with ten years
return period
Area contributing to channel flow in Km2

Flow from connecting channels to these side drains is determined according to the
specific situation.

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

87

3.5.1.2 Pipe Culverts

The hydraulic capacity of existing pipe culverts has been obtained from the tables
in the UNRA Drainage Manual against their opening sizes, bed roughness of 0.015
and bed slop of 1% and allowing only 50% efficiency; please find these tables in
Appendix 9.19 of the same manual.
The discharge capacity of each and every pipe is compared with calculated
channel design discharge with 25 years recurrent period. We found that in most of
the cases the existing pipe culverts have inadequate hydraulic capacity to
accommodate the anticipated design discharge.
A table incorporating the opening sizes, type and hydraulic capacity of existing
pipe culverts, the corresponding design discharge, the new structure opening size
and its hydraulic capacity is prepared for detail clarification and presentation.
Except for the relief and local pipes all the new pipe culverts are checked against
head water depth ratio (Hw/D) greater than 1.2 to avoid scour damage to the inlet
side of the road embankment and also to avoid excessive flooding upstream
allowing 250mm free board below the road final level on the same table using HY8 computer software.
Please refer to the table in Appendix-6.

3.5.2 Major Drainage Structures


3.5.2.1 Box Culverts

Where the design discharge is found over the capacity of the maxmum size of
double pipe culverts, the box culvert is selected.

The preliminary size of all box culverts is verified using HY-8 computer software
after having the final road levels and bed slop. Both inlet and outlet control flows
shall be checked by applying the final invert level and available upstream flow
head after allowing 250mm free board below the road final level.
Based on the result obtained from the computer program and soil particle size of
the flow bed channel, bed protection work shall be recommended to avoid or
minimize bed erosion. Please refer Appendix 6.
The project box culverts schedule showing the following details of each and every
box is prepare:
the invert level,
culverts slope
flow direction
skew angle if any
culverts length and head wall quantities
additional protection work if there is any

| FINAL Detailed Design Report_Rev.1-AUG 2012 |

88

3.5.2.2 Bridges

Bridges are selected in defined river flows where there are existing bridges, the
design flow couldnt be accommodated by box culverts and at least to maintain the
opening size of the existing bridge and told by the local community repeated over
flooding even though not supported by the hydrology analysis. And in swamps
where, the design discharge is over the capacity of box culverts in series, to allow
passage of expected debris and to assure free movement of the aquatic life,
bridges are also recommended.

The capacity of the existing bridges and the preliminary opening size of the new
bridge required to accommodate the design discharge for each particular bridge
location is determined from the Mannings Equation for open channel flow and
allowing free board of 1.5m according to UNRA Manual.
Q=

(1/n) .A. R2/3 . S1/2

However, the preliminary bridge opening size is verified using WSPRO or HEC-2
software to insure the provided opening is safe against upstream flooding and
excessive flow velocity. Please refer to the bridge hydraulic calculations and
results in Appendix-4.
Scour at bridge location is very important for the safety of bridge. We studied the
local scour problems at those bridges where the bed material is other than rock
bed. The local scour at pier is a function of bed material size, flow characteristics,
fluid properties and the geometry of the pier.
The scour depth at pier as given by the CSU (Colorado State University) equation
is;

a
Ys = 2Y1K1K 2 K 3
Y1

0.65

Fr 0.43

Where;
Ys = scour depth
Y1 = flow depth directly upstream of the pier, [ft]
K1 = Correction factor for pier nose shape
K2 = Correction factor for angle of attack of flow
K3 = Correction factor for bed condition
a
= Pier width, [ft]
V1 = mean velocity of flow directly upstream of the pier, [ft/sec]
1/2
Fr1 = Froude number = V1/ (gy1)
For the constants and detail of the formula please refer to UNRAs drainage manual
section 10.8.3.

Where the demand for scouring protection, river training and bank protection work
exists their design is explained on the same sheet of the bridge hydraulic design.

| FINAL Detailed Design Report_Rev.1-AUG 2012 |

89

3.6

Structural Design

3.6.1 Minor Drainage Structures


3.6.1.1 Paved Side Ditches
Paved side ditches are constructed as v-shaped channel following the natural
stable soil slope except at towns and trading centres where rectangular channels
used. The rectangular channels are designed to resist lateral earth pressure and
traffic live loading at places where covering slab required. The concrete covers are
also designed to withstand the traffic live loading safely. Please refer to Appendix
6-Structural Design Calculations.
3.6.1.2 Pipe Culverts
Structural design of concrete pipes usually done at standard level so that they can
withstand the design live loading and the surrounding soil pressure safely. And
these designs are confirmed by laboratory testing according to standard
specification.
Standard concrete pipes sizes, detailed and specified according to AASHTO
standard specification M-170 or M-242 are adopted for this project.
Basically a minimum soil cover of 600mm is adopted to reduce the effect of
concentrated live load unless otherwise an additional slab is put on the top of the
pipe.
Class-C bedding is adopted for all concrete culvert pipes bedding for the entire
project unless otherwise Class-A or Class-B bedding is approved by the engineer
according to specific need.

3.6.2 Major Drainage Structures


3.6.2.1 Box Culverts
Box culvert structures are designed as rigid frame structural system. The following
loadings are considered in the design.
1.
2.
3.
4.

Earth pressure from surrounding backfill material


Weight of soil above
Design live loading
Weight of water if exists.

Design calculation is carried out for all box culverts which are selected as standard
for the project all according to UNRA Manual and BS5400 Standard. SAP 2000
software is used for the structural frame analysis. Please refer to Appendix 6Structural Design Calculations.
3.6.2.2 Bridges
List of New Bridges
No new bridges are required on Musita-Lumino/Busia-Majnaji roads.

| FINAL Detailed Design Report_Rev.1-AUG 2012 |

90

Material Quality
a) Concrete Quality
Concrete quality of Grade 30 (with characteristic strength 30MPa of 150mm cube
at 28 days according to BS 5400 section 5.1.4 table-5) is adopted for all the bridge
super and substructures in the entire project.
b) Reinforcement Quality
Reinforcement steel quality of Grade 460 (with minimum characteristic strength of
460MPa according to BS Cl 5.1.4 table-6) is adopted for all the bridge super and
substructures in the entire project.

Design Method
The bridge reinforced concrete members are design to the ultimate limit state
design and checked for crack width control and servicibility limit state all according
BS5400 Part-4 for concrete structures.
Bridge Loading
All the structural design loadings of the new bridges are considered according to
UNRA Bridge Design Manual together with BS5400 Part-2 for loading.
a) Live Loading
The bridge structure and its elements are designed to resist the more severe
effects of either:
Design HA loading (see UNRA 6.4.1) or
Design HA loading combined with design HB loading (see UNRA 6.4.2).
Where,
b) HA loadings
HA loadings are a formula loading representing normal traffic. It consists of a
uniformly distributed load/UDL/ and knife edge load /KEL/combined, or of a single
wheel load, including 25% impact.
The UDL shall be taken as 30kN per linear meter of notional lane for loaded lengths up to
30m, and for loaded lengths in excess of 30m it shall be derived from the equation.

( L)

W = 151 1

0.475

but not less than 9

Where, L is the loaded length (in m) and W is the load per meter of lane (in KN)
The KEL per notional lane shall be taken as 120kN.

c) Single Nominal Wheel


One 100kN wheel placed on the carriageway and uniformly distributed over a
circular contact area assuming an effective pressure of 1.1N/mm2 (i.e 340 mm
| FINAL Detailed Design Report_Rev.1-AUG 2012 |

91

diameters) shall be considered. Alternatively, a square contact area may be assumed,


using the same effective pressure (i.e. 300mm side).
d) HB loadings

Those derived from the nature of exceptional industrial loads (e.g. electrical
transformers, generators, pressure vessels, machine presses, etc.) One unit shall
be taken as equal to 10 KN per axle (i.e. 2.5 KN per wheel).
The overall length of the H B vehicle shall be taken as 10, 15, 20, 25 or 30 m for
inner axle spacing of 6, 11, 16, 21 or 26 m respectively, and the effects of the most
severe of these cases shall be adopted. The overall width shall be taken as 3.5 m.
The minimum number of units to be used shall be 25 units for all public highway
bridges. After having discussion and approval by UNRA 37.5 units of HB loading
are used for the design all the bridges in the entire project.

Fig 16: Dimensions of HB vehicles


e) Longitudinal Loading
The longitudinal load resulting from traction or braking of vehicles and shall be
taken the more severe of
1) The nominal load for HA shall be 8 kN/m of loaded length plus 200 kN,
subject to a maximum of 700 kN, applied to an area one notional lane
wide x the loaded length or
2) The nominal load for HB shall be 25 % of the total nominal HB load
adopted, applied as equally distributed between the eight wheels of two
axles of the vehicle, 1.8 m apart
and applied at the road surface in one notional lane only.
f) Accidental Load Due to Skidding
A single nominal point load of 250KN is considered in one notional lane only, acting
in any direction parallel to the surface of the highway.

| FINAL Detailed Design Report_Rev.1-AUG 2012 |

92

g) Wind Load

All the project bridges are categorized into terrain category 1 with velocity pressure
of 0.81KN/m2 structure height of 5m. However, wind load is not considered in our
design since all the bridges in the entire project are small at low level and wind
loading doesnt govern.
h) Live Load Surcharge
Live load surcharge for properly consolidated backfill material:
(a)
(b)
(c)

for HA loading : 10kN/m2;


for HB loading 37.5 units : 16.25kN/m2

i) Earthquake Loading
The project bridges are located in Zone 2 with acceleration coefficient (A) = 0.07
and iImportant classification(IC) of class I. Seismic performance category (SPC) =
2 and soil profile type II with site coefficient(S) = 1.2.
Detailed seismic analysis is not required for a single span bridge or for bridges
classified as SPC 1 & 2 (Cl.9.4.2 UNRA).
But the connection of the superstructure to the substructure shall be designed to
resist a horizontal seismic force equal to 0.20 times the dead load reaction force in
the restrained directions.
Bearing seats supporting the expansion ends of girders shall be designed to
provide a minimum support length N (in mm) measured normal to the face of an
abutment or pier, not less than that specified below:
N = 203 + 1.67L + 6.66H (mm)
where
L = length, in meters of the bridge deck to the adjacent expansion joint, or to
the end of the bridge deck.
H = average height, in meters of columns supporting the bridge deck to the next
expansion joint for abutments
H = column or pier height in meters for columns and/or piers

3.6.2.3 Substructure
Reinforced concrete type substructures designed to safely transfer all loads from
the superstructure to the underlying soil strata within its bearing capacity without
excessive setlement.
a) Pier
Twin wall type reinforced concrete pier with common footing pad and independent
hammer head beam seat is designed to safely transfer superstructure loads to the
foundation material for all the bridges in the entire. In the design all fractional
values are taken to the full numbers which allow us to have a few sizes for
construction simplicity and economy. Simi-circular shape edge is provided for a
better hydraulic performance and durability.
| FINAL Detailed Design Report_Rev.1-AUG 2012 |

93

The following loads are considered in the design processes.


1.
2.
3.
4.

Earthquake forces from the superstructure and the pier itself


Longitudinal forces from the superstructure
Self weight and dead load from superstructure
Live load reaction

Please refer to Appendix 6-Structural Design Calculations.

Figure 17 : Longitudinal Elevation

b) Abutment
Cantilever reinforced concrete abutment with 45 degrees flared wing walls is
designed to safely transfer all loads from the superstructure and the back fill soil to
the foundation material.
The following loads are considered in the design processes of abutments:
1.
2.
3.
4.
5.

Self weight and dead load reaction from superstructure


Live load reaction from superstructure
Traffic surcharge load
Lateral earth pressure
Longitudinal forces from the superstructure

Please refer to Appendix 6-Structural Design Calculations.


Figure 18 : Elevation

| FINAL Detailed Design Report_Rev.1-AUG 2012 |

94

3.6.2.4 Superstructure
Voided slab type superstructure is used for the standard bridge superstructure for
the entire project. The voided slab is split into mid and end pre-cast units to
facilitate the pre-cast production and having reduced lifting weight.
Figure 19 : Precast Units

Raised walkway with removable cover utility channel is provided on bothsides of


the carriage way.

Figure 20 : Precast Units

The lifting weight of the end unit is around 10 tons and 11 tons for the mid unit.
Carriage way width of 7.5meters with sidewalks way of 2.0meters width each side
is agreed with UNRA bridge engineers and provided for all the bridges in the entire
project. The total bridge width is therefore 11.5 meters. Accordingly two end units
and eight units of mid units are put side by side to formulate the total bridge width.

| FINAL Detailed Design Report_Rev.1-AUG 2012 |

95

Figure 21 : Bridge Cross-section

The pre-cast voided slab units are modeled and designed as single beam each
shearing the live load as the same way it is assumed distributed in sold slab. It is
assumed that the 10cm thick cast-insitu slab will fully helps in distributing the
wheel loads. Please refer to Appendix 6-Structural Design Calculations.

3.6.2.5 Bearings
No special type of bearing except PTFE/similar pads at each precast voided slab
beam at one of the two ends is provided to insure horizontal load transfer at one
end only. At the other end fixity can be achieved using steel dowels or any other
suitable system which be worked with the precast units.
3.6.2.6 Expansion Joints
No expansion joint detail is required for short span bridges like 12m span bridges.
3.6.2.7 Railings
Prefabricated steel tube sections which can be assembled at site and bolted to the
precast end unit are selected for the bridge railing. This can help to facilitate the
early completion of the bridge work. The steel railing is simple looking and can
easily be maintained after traffic damage.
All the railing components are designed to resist the specified design load
according to the manual. Please refer to Appendix 6-Structural Design
Calculations.
3.6.2.8 Deck Drainage
Deck drainages at every end quarter point of the span on both sides are provided.
200mm by 75mm rectangular galvanized steel hollow section is selected to allow
enough opening without clogging by silt for the perfect flow of water which is a
common major problem at most bridge sites.

| FINAL Detailed Design Report_Rev.1-AUG 2012 |

96

3.7

Quantity and Cost Estimation

3.7.1

Determination of Quantities
Determination of the quantities for the various aspects of the design has been
made for each of the five project roads.
Civil 3D road design programme has been used to produce the various road
component quantities up to wearing course level.
The cross-section costed is that detailed in the Book of Drawings, incorporating a
7.0 m wide carriageway with 1.5 m shoulders.
For all other items, quantities have been calculated based on preliminary design
requirements as determined from the site investigations.

3.7.2

Unit Rates
Considering the nature and extent of the Works to be undertaken for this project, it
is deemed that only highly experienced and well-equipped contractors could
successfully undertake and complete the works in a competent and satisfactory
manner. All costing, therefore, are based on this assumption.
The unit rates are based on the presumption of a non-restricted tender in which
contractors from countries with low foreign personnel costs and overheads, who
are - or have been - active in Uganda or elsewhere in the region, can be expected
to submit very competitive bids, with rates appreciably below conventionally
derived unit rates.
For the major construction items the unit rates have been derived from first
principles and compared with the rates in force on an ongoing project of a similar
nature being undertaken by the Client.
The breakdown of unit rates was presented in a separate volume during the
Preliminary Design stage and remains unchanged.

3.7.3

Provisions
Preliminary and General Items have been estimated at 10% of the Works Items,
whilst Dayworks have been estimated at 2% of the Works Items.
A 10% allowance has been made for physical contingencies and a 5% allowance
for financial contingencies during the period of construction.
The estimate is in Uganda Shillings and no separate provision is made for
escalation between the present and commencement of construction.
The cost of design has been omitted, whilst a 5% provision has been made for
construction supervision.
The estimated costs for land take, environmental mitigation and removal and
relocation of services have also been taken into account.

| FINAL Detailed Design Report_Rev.1-AUG 2012 |

97

3.7.4

Construction Cost Estimates


The draft final cost estimates for Musita-Lumino/Busia-Majanji roads are presented
separately in Volume 3A.

3.7.5

Road Construction Packages


Determination of the contract strategy to be adopted and the number of contract
packages will be undertaken in consultation with UNRA during detailed design
phase.
However, for the purposes of the study and taking due account of the geographical
locations of the five project roads and their respective lengths and the estimated
value of the construction works, it is anticipated that four contract packages will be
required, namely:
Package 1:

Musita-Lumino & Busia-Majanji roads (Total length = 101 km)

Package 2A: Tirinyi-Pallisa/Pallisa-Kumi roads (Total length = 64 km)


Package 2B: Pallisa-Kamonkoli road (Total length = 45 km)
Package 3:

Bumbobi-Bubulo-Busumbu-Lwakhakha (Total length = 44 km)

Package 4:

Namagumba-Budadiri-Nalugugu roads (Total Length = 29 km)

Package 5: Kamuli-Bukungu road (Total Length = (68 km)

Such an arrangement would allow smaller local or regionally based companies to


tender, whilst providing packages which individually or in combination would still
remain attractive for internationally based contractors. It would also enable
implementation and financing to be phased, should this prove to be more
attractive.

| FINAL Detailed Design Report_Rev.1-AUG 2012 |

98

You might also like