Professional Documents
Culture Documents
ES-14-202-01
Number:
ES-14-202-01
Version Number:
5.0
Date Revised:
22 November 2013
Owner:
Manoj Thakur
Authoriser:
Manoj Thakur
New Owner
New Authoriser
Full Review of Document
TABLE OF CONTENTS
1.
SCOPE ....................................................................................................................................... 4
2.
3.
STANDARDS ............................................................................................................................ 5
Page 1 of 16
3.1
3.2
3.3
3.4
3.5
4.
5.
6.
7.
TOP SOIL.............................................................................................................................. 7
ORGANIC MATTER ........................................................................................................... 8
NON-ORGANIC MATTER.................................................................................................. 8
8.
9.
10.
BLASTING ................................................................................................................................ 9
11.
DE-WATERING ....................................................................................................................... 9
12.
BENCHING ............................................................................................................................... 9
13.
EXCAVATION ......................................................................................................................... 9
13.1
13.2
13.3
13.4
13.5
13.6
13.7
14.
FILLING .................................................................................................................................. 11
14.1
14.2
15.
16.1
16.2
16.3
16.4
17.
MATERIAL ........................................................................................................................ 11
PLACEMENT ..................................................................................................................... 11
COMPACTION....................................................................................................................... 12
15.1
15.2
16.
GENERAL ............................................................................................................................ 9
TEMPORARY SUPPORT .................................................................................................... 9
UNSTABLE GROUND ...................................................................................................... 10
EXCAVATION IN ROCK .................................................................................................. 10
TRENCHES FOR SERVICES ............................................................................................ 10
OVER-EXCAVATION ....................................................................................................... 10
SURPLUS EXCAVATED MATERIAL ............................................................................. 10
GENERAL .......................................................................................................................... 13
FORMATION LEVEL ........................................................................................................ 13
SUBGRADE LEVEL .......................................................................................................... 13
BATTER SLOPES AND LINES ........................................................................................ 13
INSPECTION .......................................................................................................................... 14
Page 2 of 16
18.
TESTING ................................................................................................................................. 14
18.1
18.2
18.3
GENERAL .......................................................................................................................... 14
FREQUENCY OF TESTING ............................................................................................. 14
REJECT WORK .................................................................................................................. 15
19.
REINSTATEMENT ................................................................................................................ 15
20.
20.1
20.2
20.3
Tables
TABLE 1 FILL MATERIAL MINIMUM COMPACTION REQUIREMENT.................................................................. 12
TABLE 2 COMPACTION TESTING FREQUENCY ................................................................................................. 15
Page 3 of 16
1.
SCOPE
This Standard covers the general requirements for site clearance, excavation, filling, compaction,
inspection, testing and finishing of earthworks.
2.
DEFINITION OF TERMS
2.1
CONTRACTOR / VENDOR
2.2
SUB-CONTRACTOR
A third party to be employed by the Contractor / Vendor, who has been approved by the
Responsible Officer.
2.3
CSBP
CSBP Limited
2.4
WORKS
The scope of works that a Contractor is or may be required to execute under an agreement
including variations and remedial work.
2.5
Ground or material, which is unsuitable for the purpose of the Works, includes:
2.6
LINE OF INFLUENCE
A line which extends downwards and outwards at 45 from the bottom edge of a footing, slab or
pavement, defining the extent of foundation material having an influence on the stability or support
of the footings, slab or pavement.
2.7
ROCK
Rock is defined as any monolithic material with a volume greater than 0.5 m, or rock in solid beds
or compact stratified layers, which will require drilling and blasting or wedging for its removal.
Page 4 of 16
Note:
Soft or disintegrated rock, which can be removed with hand tools or by power operated
excavation equipment, shall not be classified as rock.
Classification of rock shall be subject to the approval of the Responsible Officer.
2.8
SUBGRADE
The trimmed or prepared portion of the formation, on which the pavement, slab or footing is
constructed.
2.9
TOPSOIL
The upper layers of soil containing more than 1% by weight of organic matter.
2.10
HEAVY EQUIPMENT
Any equipment larger than a 100 kg vertical rammer or a 500mm plate compactor.
3.
STANDARDS
The Contractor shall perform the Works in accordance with this Standard, the latest issue of
reference standards and Contractor regulations for on-site work. Should there be a conflict between
the Works, Statutory Requirements and the Standards, the Contractor shall notify the Responsible
Officer in writing for resolution. In general, the most stringent requirements will prevail.
3.1
ES-14-101-02
Drawing Management
ES-14-101-03
Drawing Preparation
ES-14-101-04
Drawing Numbering
ES-14-202-19
ES-14-602-05
Underground Piping
ES-14-602-08
Irrigation Piping
ES-14-902-01
3.2
GM-10-020-04
GM-11-031-51
GM-11-036-04
Excavations
3.3
9900-2-0600/002
9900-2-0600/003
9900-2-0600/004
Page 5 of 16
3.4
AUSTRALIAN STANDARDS
AS 1289
AS 2187
3.5
OTHER PUBLICATIONS
DEC
4.
GEOTECHNICAL INVESTIGATION
Where required, the Contractor shall carry out a geotechnical investigation, using a suitably
qualified and experienced geotechnical engineer engaged by the Contractor, to verify that the
subgrade has sufficient capacity and stiffness to support the proposed structures. The Contractor
shall conform to the requirements of the geotechnical engineer.
5.
SETTING OUT
5.1
LICENSED SURVEYOR
A licensed surveyor, engaged by the Contractor, shall carry out the following activities prior to
commencement of any earthworks
5.1.1
Control Marks
The licensed surveyor shall establish survey control marks, which shall remain undisturbed for the
duration of the Works. The Contractor shall reinstate any which are damaged or disturbed during
construction.
5.1.2
Verify Levels
The licensed surveyor shall verify the levels shown on the earthworks and site preparation
drawings.
5.1.3
The licensed surveyor shall establish and peg out cut and fill boundaries, based on the earthworks
and site preparation drawings.
5.1.4
The existence of services, structures and any other obstruction within the site clearing area shall be
checked, identified and recorded.
Page 6 of 16
5.1.5
Hand Digging
Where excavation work crosses existing services, the surveyor shall clearly mark on the ground the
areas that shall be hand dug. The extent of hand excavation shall be:
Two (2) metres either side of existing services where the precise location is known.
Five (5) metres either side of an estimated service location. Once the precise location of
existing services within the ten-metre band has been established, hand excavation can be
reduced to two (2) metres either side of the existing service.
5.2
CONTRACTOR
In addition to the survey work carried out by the licensed surveyor, the Contractor shall carry out
the following activities.
5.2.1
The Contractor shall clearly mark all trees and flora, nominated by the Responsible Officer, which
are to be protected against damage and remain undisturbed throughout the Works construction
activities.
5.2.2
Temporary Marks
The Contractor shall complete all other setting out and levelling as required. Temporary set out
marks shall be left in place until all activities, which require their presence, are completed.
6.
The Contractor shall carry out the Works in accordance with the Department of Environment and
Conservation dust control guidelines Land Development Sites and Impacts on Air Quality, and to
the satisfaction of the Responsible Officer.
Contractor procedures for spoil stabilisation and dust control shall be submitted to the Responsible
Officer for approval, at least seven (7) days prior to commencement of any earthworks. The
Contractor shall not proceed with any related work until the Responsible Officer had approved the
procedures.
7.
SITE CLEARING
Site clearing shall be carried out in advance of any construction activities and shall include the
removal of foreign material and nominated vegetation from within the clearing limits.
7.1
TOP SOIL
Where specified, the Contractor shall carefully remove topsoil from areas nominated and relocate it
to approved locations, sufficiently clear of the works being constructed so as to ensure that the
stockpile is not contaminated by construction activities.
Page 7 of 16
7.2
ORGANIC MATTER
All organic matter including trees, logs, shrubs and roots shall be cleared from within the limits of
the clearing, unless directed otherwise by the Responsible Officer. Refer to Section 5.2.
All stumps and roots over 75 mm diameter, shall be grubbed out to a minimum depth of 600mm
below the expected subgrade surface level, unless specified otherwise in the Works or as directed
by the Responsible Officer. Grubbed holes shall be backfilled and compacted to the density of the
surrounding undisturbed soil.
No material shall be burnt on site.
Note:
7.3
Trees to be retained shall be adequately protected at all times and particular care taken to
avoid any damage to roots, trunks or branches. If directed by the Responsible Officer,
earth-moving equipment shall be kept clear of trees and hand excavation and compaction
methods adopted.
NON-ORGANIC MATTER
All non-organic material including concrete, masonry, boulders and rubbish shall be cleared from
within the limits of the clearing, unless directed otherwise by the Responsible Officer.
Unless specified otherwise in the Works or by the Responsible Officer, the Contractor shall dispose
of cleared materials at an approved landfill facility.
8.
In areas where there are existing underground services, the Contractor shall use extreme care and
take all necessary precautions to ensure the services are not damaged during excavation and
compaction activities. Existing services shall be located by hand excavation before mechanical
excavation is used. Refer to Section 5.1.5 for details.
The Contractor shall provide temporary construction supports for existing services where
necessary. Details to be approved by the Responsible Officer and the owner of the existing
services, before work commences.
9.
EXISTING STRUCTURES
In areas where there are existing structures, the Contractor shall use extreme care and take all
necessary precautions to ensure the structure and footings are adequately supported and protected
from damaged during excavation and compaction activities.
If excavation is adjacent to or is required below the line of influence of an existing footing, the
Contractor shall use methods including underpinning if required, to maintain the support of the
footing to the satisfaction of the Responsible Officer. Details of proposed support methods shall be
submitted to the Responsible Officer for approval at least seven (7) days prior to excavation.
Page 8 of 16
10.
BLASTING
No blasting shall be carried out, unless the Responsible Officer has given written approval. All
blasting will be in accordance with statutory requirements, local authority by-laws and Australian
Standard AS 2187.2 Use of Explosives. The most stringent requirements will prevail.
11.
DE-WATERING
The Contractor shall take all necessary action and supply all equipment to remove or divert, as
specified by the Responsible Officer, any surface and sub-soil water from the works. This will
include the provision of trenches, sumps, pumps and well points as required, to maintain the work
area to the approval of the Responsible Officer. Water shall be disposed of or diverted in a manner,
which will not damage adjacent property or interrupt work in progress.
12.
BENCHING
If fill is to be placed on a surface that slopes more than 1:4, the surface shall be benched to form a
key for the fill.
13.
EXCAVATION
13.1
GENERAL
Excavation work shall be carried out safely and in accordance with the requirements of the
following CSBP Guide Manuals:
GM-10-020-04
GM-11-031-51
GM-11-036-04
Excavations
Excavations shall be carried out to the depths, gradients, widths, batters and dimensions as shown
on the drawings or as necessary to permit placing and removal of formwork, drainage and dewatering facilities, and to carry out cleaning, inspection and testing activities.
The bottoms of excavations shall be flat, at the required grade for full load bearing and shall be
kept free and clean of loose materials, water and rubbish.
13.2
TEMPORARY SUPPORT
The Contractor shall be responsible for the design, installation and removal of all temporary works,
required to maintain the excavated surface in its original position.
Note:
Any remedial work required resulting from insufficient temporary support shall be the
Contractors responsibility.
Page 9 of 16
13.3
UNSTABLE GROUND
If excavation to the nominated depth reveals unstable ground, the Responsible Officer may order
further excavation to more stable strata or initiate other remedial methods to satisfy design loading
conditions.
13.4
EXCAVATION IN ROCK
Foundations that are designed to bear on solid rock shall be provided with a level or stepped level
surface. All loose or weathered rock shall be cut back to solid rock.
Refer to Section 2.7 for definition of rock.
13.5
Trenches shall be excavated to the depth specified on the drawings and in accordance with the
following CSBP Engineering Standards:
UNDERGROUND SERVICE
Underground Cabling
13.6
OVER-EXCAVATION
Any over-excavation of subgrade under future concrete footings or bearing walls shall be reported
to the Responsible Officer and the subgrade restored with Grade S15 concrete at the Contractors
expense. No other material shall be used without the written approval of the Responsible Officer.
Any other areas of over-excavation shall be restored by the Contractor, as directed and to the
satisfaction of the Responsible Officer.
13.7
Excavated material that is in excess of requirements or is unsuitable for filling or backfilling shall
be removed from the works area and disposed of by the Contractor as directed by the Responsible
Officer.
Refer to Section 2.5 for definition of unsuitable material.
Page 10 of 16
14.
FILLING
14.1
MATERIAL
Fill material shall be Responsible Officer-approved, clean and uniform granular material free from
rubbish, building rubble, organic matter, excessive clay or silt, stones and lumps remaining on a
25mm sieve and any other contaminants as determined by the Responsible Officer.
Borrow fill material shall be obtained only from Responsible Officer-approved or designated
borrow areas.
Fill material shall have a moisture content that is suitable for compaction. Refer to Section 15 for
details.
14.2
PLACEMENT
14.2.1 General
Embankments and filling material shall be placed systematically in 300mm thick horizontal layers
across the full width of the works. Layers up to a maximum thickness of 600mm may be placed if
the Contractor can demonstrate to the satisfaction of the Responsible Officer that proposed
compacting equipment and methods are capable of achieving the required standard of compaction
for the whole depth of fill to be placed.
Each layer shall be uniformly compacted to the required density in accordance with Section 15,
before the next layer is placed.
14.2.2 Restricted Areas
In restricted areas where use of powered equipment is not feasible, the fill shall be placed in layers
up to a maximum thickness of 150mm.
14.2.3 Structures
Fill shall be uniformly and simultaneously placed around embedded structures, culverts etc to avoid
differential lateral side loading.
14.2.4 Retaining Walls
Fill material shall not be placed behind a retaining wall, until the retaining wall is fourteen (14)
days old, unless otherwise directed by the Responsible Officer, and until the material in front of the
retaining wall has been compacted.
Page 11 of 16
15.
COMPACTION
15.1
GENERAL REQUIREMENTS
Each layer of fill material shall be uniformly compacted to the required density as specified in
Table 1, before the next fill layer is placed.
LOCATION OF FILL MATERIAL
COMPACTION REQUIREMENT
Embankments
15.2
SPECIFIC REQUIREMENTS
a.
Compaction of backfill material over underground process and services piping shall be in
accordance with CSBP Engineering Standard Underground Piping (ES-14-602-05).
b.
Fill layers, placed around embedded structures, culverts etc to be simultaneously compacted
on both sides, to avoid differential loading.
Page 12 of 16
c.
In areas where there are existing structures and underground services, the Contractor shall
use extreme care and take all necessary precautions to ensure they are not damaged by
compaction operations.
d.
In restricted areas where power rolling is not feasible, mechanical tampers or other
Responsible Officer - approved compaction methods shall be used.
e.
Fill placed within one (1) metre of finished concrete work shall be compacted with
Responsible Officer - approved hand-held mechanised compaction equipment.
f.
Heavy equipment shall not be used to compact fill, bounded by the back of any retaining
wall and a plane behind the wall sloping at 45 upwards from the base of the wall.
16.
16.1
GENERAL
All earthworks shall be finished to a reasonably smooth and uniform surface, and shall comply with
the tolerances specified in Sections 16.2, 16.3 and 16.4 unless specified otherwise in the Works or
by the Responsible Officer.
Stockpiled topsoil shall be evenly graded over Responsible Officer-specified areas to a thickness
between 25mm and 100mm and shall blend in with adjoining undisturbed ground. All sticks,
stones, rubbish and surplus topsoil shall be gathered and removed from site by the Contractor.
16.2
FORMATION LEVEL
All cleared, excavated and filled areas shall be finished to the lines, grades and levels specified on
the drawings. Finished earthworks surface levels, which are not under concrete ground slabs and
footings shall not vary from the specified levels by more than 30mm.
16.3
SUBGRADE LEVEL
Subgrades to concrete ground slabs and footings shall be trimmed to the levels shown on the
drawings within the tolerances 15mm, +0mm.
16.4
At all levels the average batter slope shall not be steeper than the slope specified on the drawings.
Cut batter shall be constructed so that the toe of the batter is not more than 150mm outside the
batter line shown on the drawings.
Fill batters shall be constructed so that the toe of the batter is not more than 300mm outside the
batter line shown on the drawings.
Page 13 of 16
17.
INSPECTION
In areas where topsoil has been stripped and the area cleared of organic and foreign material, the
Contractor shall not commence cut and fill operations until the Responsible Officer has approved
the cleared area.
Unsuitable materials used as fill shall be rejected. Material shall be excavated and replaced with
satisfactory material and compacted as specified. Refer to Section 2.5 for definition of unsuitable
material.
Topsoil redistribution shall not commence until final contouring and grading or benching has been
inspected and approved by the Responsible Officer.
Acceptance of the Works is subject to satisfactory final inspection. Refer to Section 20.
18.
TESTING
18.1
GENERAL
All sampling, in-situ density testing of fill material, subgrade and graded areas, and other soil tests
as specified shall be carried out by a suitably qualified and approved NATA certified laboratory.
Testing shall be carried out in accordance with AS 1289 not later than 24 hours after compaction
has been completed for each layer. Where specified, results shall be verbally submitted to the
Responsible Officer prior to the placement of sub-base material. The NATA certified laboratory shall
within seven (7) days of testing, confirm test results in writing to the Responsible Officer and the
Contractor.
18.2
FREQUENCY OF TESTING
General
FREQUENCY OF TEST
The lesser of:
1 test every 5.0 m of fill or
every 10 linear metres of trench
Subgrade
Page 14 of 16
18.3
When specified by the Responsible Officer, random tests shall be carried out at locations
where compaction limits have been defined.
REJECT WORK
Where the field density of the compacted layer, as determined by test, is less than the specified
percentage compaction in Table 1, the layer shall be reworked and retested until the required
compaction is achieved.
19.
REINSTATEMENT
Existing ground surfaces outside the site clearing area, including paving, roadworks, lawn and
natural vegetation areas, that was removed, disturbed or damaged by earthwork activities, shall be
reinstated by the Contractor to match existing and adjacent ground, to the satisfaction of the
Responsible Officer. For reinstatement of roads and paving refer to CSBP Engineering Standard
Roads and Paving (ES-14-202-19).
Fences that were removed or damaged during the Works shall be reinstated in accordance with
CSBP Standard Drawings 9900-2-0600/002, 9900-2-0600/003 and 9900-2-0600/004.
Existing structures, footings and underground services damaged during the Works shall be repaired
to the satisfaction of the Responsible Officer and the owners of the facilities.
20.
20.1
Density and compaction test results issued by the approved NATA certified laboratory.
20.2
AS-BUILT DRAWINGS
Contractor prepared as-built earthworks survey for approval by the Responsible Officer. The
survey shall record any areas where unsuitable subgrade was removed and replaced.
Drawings shall be upgraded in accordance with approved survey results. Responsibility for revising
the drawings shall be specified in the Works.
Drawings recording the as-built details, shall be prepared / revised, numbered, approved and
handed over in accordance with CSBP Engineering Standards:
ES-14-101-02
Drawing Management
ES-14-101-03
Drawing Preparation
Page 15 of 16
ES-14-101-04
20.3
Drawing Numbering
FINAL INSPECTION
Page 16 of 16