Journal of Applied Sciences Research, 5(11): 1904-1914, 2009

© 2009, INSInet Publication

Project Management Maturity Model (PMMM) in Developing On-line Statistical Process


Control Software: An Integrated Approach

M. A. Wazed and Shamsuddin Ahmed

Department of Engineering Design & Manufacture, Faculty of Engineering, University of Malaya


(UM), 50603 Kuala Lumpur, Malaysia.

Abstract: Project Management concept is gaining increasing popularity to product developers,


manufacturers, and especially Engineers because of its uniqueness in versatility and its ability to control
time and costs most efficiently. W ith the ever growing competitive market, project commencement lead
time is becoming a more and more crucial issue. Project management maturity model (PMMM) can
integrate the pertinent aspects and contribute to the cost and time management. This paper covers all
aspects of managing a real time engineering statistical process control (SPC) software development project,
ranging from project conceptualization to cost control, risk management and performance measurement.
Along the way, various tools and techniques have been used. The main conclusions drawn out of this
work are that all aspects of project management should be considered in an integrated manner. Should
any one of them be overlooked, it may cause poorer results. W ith project management approach and SPC
solution, any project may be managed within the scheduled time and the budgeted costs.

Keywords: Project management, Management maturity model, Statistical process control

INTRODUCTION At times, it often takes several meetings before the


management decides that the project approach should
Project Management is the planning, organizing, be led by a project manager. The internal resources of
directing, and controlling of resources for a finite the organization then are generally tapped. The project
period of time to complete specific goals and receives the assets - both human capital and monetary.
objectives. In the day to day work environment, project After estimating these, the progress of the project in
management is one of the most efficient ways to do terms of resource usage and expenditure are closely
business. In business environment change is constant, monitored till completion. Termination of the project
competition between organizations is vital, and the takes place only after post-completion work is carried
need for more complex and customer-focused out.
products/service are necessary. The term is better In recent years, there has been a considerable
understood to the construction and infrastructure change in the world economic situation. Many
developers and less familiar to the manufacturing manufacturing companies have begun to change their
personnel and software producers. It has evolved as an management ways. These ways stress the systematic
answer to some of the management problems that use of statistical methods for continual improvement.
result from complex business and production systems. This has led to a great demand for statistical
In the past, changes did not occur as quickly, and an knowledge among in manufacturing industry. Therefore,
organization could adjust and develop new products, statistical methods are important for product quality
processes, and systems through the use of the classical improvement, communicating data, manufacturing
line organization. As the needs increase and the process control and developing a product in a
systems and processes used to develop, responses to systematic approach.
the changing environment become more complex, the Statistical Process Control (SPC) chart is one of
ability of functional organizations to respond effectively the famous SQC tools. It was introduced by W alter A.
is even more difficult. Organizations normally institute Shewart in 1942 and popularized by Dr. W . Edwards
project management when complex or non-routine jobs Deming in Japan in 1950. SPC chart is used where
that cut across departmental lines need to be data collected on a sampling basis is plotted
completed. chronologically on a chart, and used to distinguish the

Corresponding Author: M. A. Wazed, Department of Engineering Design & Manufacture, Faculty of Engineering, University
of Malaya (UM), 50603 Kuala Lumpur, Malaysia (Phone: 60-143-605425;
E-mail: awazed@gmail.com.
1904
J. Appl. Sci. Res., 5(11): 1904-1914, 2009

controlled and non-controlled variation from sample-to- input sampling data, view control chart, attend to out-
sample. Control limits and some zone tests are used to of-control (OOC) events and perform sampling plan.
determine out of control conditions. Any out of control Besides two workstations are there for production
point will signal a variation caused by special cause office and QC office with additional features such as
that can be linked to the cause of a problem. system and user configuration, reporting and analysis.
This paper presents a case study on use of project MEX perform engineering analysis on out of
management maturity model approach to implement control (OOC) events: i) Periodic in-process SPC
online in-process SPC monitoring software in a W afer reporting; ii) Periodic in-process SPC Review (sampling
Fabrication Company. This SPC software development plan, control limits and out of control Analysis); iii) In
project is named as MEX (fictitious name). Each of the process SPC activities Trail; and iv) Data archiving.
steps of project management maturity model is Figure 3 and Fig. 4 show that manual SPC charting
followed and discussed. The application of SPC is and proposed online in-process SPC software (i. e.
highly significant in the manufacturing arena nowadays. MEX) activity flow charts respectively. Figure 5 shows
SPC is a very useful method in industries and SPC the major modules of M EX. The team structure and the
software could be a solution to the majority of graphical user interface of MEX are shown Fig. 6 and
manufacturing problems for better control and use of Fig. 7 respectively. Table 1 shows the team members’
existing corporate resources. The implied objectives roles and responsibilities of the MEX project.
are: i) to automate the current workflow in the
production floor; ii) to ensure an effective out of Project M anagement Approach for M EX: In project
control feedback systems; and iii) to provide a more management approach, a standard series of diagrams
effective solution all over the processes through online and documents such as work breakdown structure,
in-process SPC implementation to the company. Gantt Chart & PERT Chart can be used to assist in the
process of product based planning. These can act as a
Perspective of M EX: Company ‘DXS’ is a silicon p o w e rful a id to a na lyz ing , s c h e d uling and
wafer fabrication company, using SPC chart to achieve communicating different aspects of the overall project
better process control for outgoing product since 2004. plans. Gantt and PERT charts are the visualization
Figure 1 shows the evolution of SPC application in the tools commonly used by project managers to control
Company. Online in-process SPC System (i.e. MEX) is and administer the tasks required to complete a project.
an integrated software system that provides company A complex project is made manageable breaking it
an IT infrastructure to enhance the effectiveness and down into individual components in a hierarchical
efficiency throughout the processes in the production structure, known as work breakdown structure. Such a
floor. MEX allows collecting real-time control data structure defines tasks that can complete independently
across the plant at every stage of the wafer of other tasks, facilitating resource allocation,
manufacturing process. It facilitates everyone to have assignment of responsibilities, and measurement and
a current, accurate picture of what is happening in the control of the project. A Gantt chart lists tasks in a
process. It alarms and signals when any parameter goes project on a timeline with their interdependencies. It is
out of control (OOC) or any exception is allowed by especially useful for planning tasks in a project, and
production engineers. It can compare performance, monitoring progress as the project goes on. Gantt
identify problem areas and accelerate decision making. charts emphasize time rather than task relationships. A
Historical reports can store, run and use for analysing PERT chart, in comparison to Gantt chart, looks more
p ro b lem s and com paring p e rfo rm a nc e fo r like a flow chart and concentrates on the relationships
benchmarking. between tasks (especially their dependencies) and less
on the timeline. PERT charts emphasize task
M EX Software System: Online in-Process SPC system relationships rather than time. The work breakdown
acts as a standalone application that helps the structure and PERT chart for MEX project are shown
production floor in implementing the SPC during the in Fig. 8 and Fig. 9 respectively.
processes. At high-level architectural view (Fig. 2), it
consists of a SPC server which interacts with AS 400 Budgeting and Cost Control: Budgeting and cost
server and Lotus Note server as well as all client PCs. control is one of the most important aspects in any
This client-server architecture allows the SPC server to project management because it is a time-limited and
act as a central controller that controls the cost-limited activity. Company, itself or may
communication between client PCs with other servers. assign/appoint contractor to design and implement a
There are twelve client workstations placed in new project. If company decides to design and
production floor to allow user to setup control plan, implement a new project itself, then the management

1905
J. Appl. Sci. Res., 5(11): 1904-1914, 2009

assigns a project team, lead by a project manager. The Progressive M ilestone Payment Schedule (Table 5).
team may assign one or more vendors to perform This schedule is planned before the project commences
certain tasks. MEX is developed using the concept of in order to monitor the cost usage closely during the
project team (Fig. 6) lead by a project manager. project itself. The planned date of completion is based
Bottom-up budgeting is a method where elemental on the project schedule prepared earlier.
activities and their schedules, descriptions and labour The operating cycle is composed of four phases: i)
skill requirements are used to construct detailed budget work authorization and release; ii) cost data collection
requests. An ad hoc committee is formed to manage and reporting; iii) cost analysis; and iv) reporting
the project (refer to work breakdown structure, Fig. 8). (Customer and management). W hen these phases
They who are familiar with specific activities are combined with the planning cycle, they constitute a
requested to provide cost estimates (Table 2). Estimates closed system network that forms the basis for the
are made for each activity in terms of labour time, management cost and control system. Project work
materials and so on. The estimates are then converted authorization form, is a contract that contains the
to an appropriate budget. Before a budget is approved narrative description, organization, and time frame for
by the top management, the project manager presents each W BS level. This multipurpose form is used to
a cost estimate to them, which consists of managing release the contract, authorize planning, record detail
director, financial controller, plant director and heads of description of the work outlined in the work breakdown
department. The estimate is done based on several structure, and release work to the functional
quotations received from suppliers. departments.
The estimated budget is presented to the top If a cost centre needs additional time or man-
management in the form of a capital expenditure hours, then a cost account change notice (CACN) form
request (CER) report. O nce the CER has signed by all must be initiated, usually by the requesting cost centre
the relevant personnel, the finance department shall and approved by the project office. However, there was
keep a record and return the form to the project no cost account change encountered throughout this
manager indicating that the budget has been approved. MEX project. Actual cost for work performed (ACW P)
and B udgeted cost for work performed (BCW P) for the
Cost Benefit Analysis: In calculating the project project are accumulated in detailed cost accounts by
amortization, projects that are completed within a year cost centre and reported to the project team and
are simply evaluated by payback period. The payback management every month. Budgeted cost for work
period is the exact length of time needed for the scheduled (BCW S) is the budgeted amount of cost for
company to recover its initial investment as calculated work scheduled to be accomplished plus the amount or
from expected savings. The major rejection and level of effort scheduled to be completed in a given
payback period are shown in Table 3. The expected time period The cost is controlled by variances: i) cost
savings resulting from this project is mainly generated variance (BCW P - ACW P) and schedule variance
from improved process yield. (BCW P – BCW S). A negative variance indicates a
behind-schedule condition.
Actual cost: After the budget has been approved (RM The values of the variances are used to indicate
498,160.75), the contractor is selected and actual cost the status of the project in terms of cost and schedule.
is obtained. The actual price of the entire MEX project From the Fig. 10 starting cost variance is zero, which
as given by the contractor is shown in Table 4. The means that the budgeted cost and actual cost are equal.
balance (RM 45,100.45) is only an initial expected So there is no over-spending. A positive cost variance
balance which may not remain the same when indicates that the amount of budget still exceeds the
unexpected events occur that incur costs. actual cost, so more spending is allowed. A negative
variance indicates a cost overrun condition. But there
Cost Control: As the project progresses, costs must be is no negative variance in this project, which shows a
monitored and evaluated to identify areas of good cost control. It is observed that there is a
unacceptable cost performance. Cost control is done by negative schedule variance. This means that the
monitoring costs, recording data and also analyzing the budgeted cost for work schedule (BCW S) has exceeded
data in order to take corrective action before it is too the amount of budgeted cost for work performed. A
late. Cost control is actually a subsystem of the negative variance indicates a behind-schedule condition.
management cost and control system (MCCS). The A zero variance indicates that the project item is
MCCS is represented as a two-cycle process: a exactly on schedule. A positive schedule variance
planning cycle and an operating cycle. In the case of shows that the project is commencing even earlier than
MEX, the planning cycle has been implemented by a the planned schedule.

1906
J. Appl. Sci. Res., 5(11): 1904-1914, 2009

Table 1: Team m em bers’ roles and responsibilities


N o Com pany Com m ittee Roles & Responsibilities
1 Vendor & Custom er Steering Com m ittee Providing m anagem ent support to the team ; A pprove Functional Specification; A pprove
U serAcceptance Testing; Resolve critical issues.
2 Vendor Project M anager: In-charge of overall project tim eline, cost and custom er satisfaction; U pdate on status;
M anage project to achieve m ilestones; Resolve problem s and issues
----------------------------------------------------------------------------------------------------------------------------------------------
SPC consultant Application and SPC functional specification review and advice
----------------------------------------------------------------------------------------------------------------------------------------------
Technical Consultant D esign & codes review and advice
----------------------------------------------------------------------------------------------------------------------------------------------
System analyst System analysis and design and Test planning
----------------------------------------------------------------------------------------------------------------------------------------------
Team Leader D esign & Code Review; Technical Research and D evelopm ent; Integration testing
Coders/Software
Engineers
3 Client Project M anager: Coordinate users and internal team for requirem ent capturing, testing and im plem entation;
Attend project status m eeting and update to m anagem ent; Coordinate functional spec, U ser
acceptance testing (U AT) review and approval; Coordinate Hardware, software and
network installation at shop floor.
----------------------------------------------------------------------------------------------------------------------------------------------
U ser Representatives Coordinate and provide system requirem ents; Conduct system test; Coordinate actual
im plem entation.
----------------------------------------------------------------------------------------------------------------------------------------------
Electronic data Providing technical docum entation and requirem ents for AS400 and e -m ail server;
processing (ED P) Coordinate AS400 & e-m ail server testing; Provide support in actual im plem entation.
representatives
----------------------------------------------------------------------------------------------------------------------------------------------
Project Representative: Coordinate network cabling, power points and hardware installation

Table 2: Cost estim ate


No Item Estim ated am ount
1.0 Software Solution – inclusive of:- 216,000.00
-------------------------------------------------------------------------------------------------------------------------------------------------------------------
Requirem ent study 10,000.00
-------------------------------------------------------------------------------------------------------------------------------------------------------------------
Solution design 70,000.00
-------------------------------------------------------------------------------------------------------------------------------------------------------------------
Software developm ent & testing 80,000.00
-------------------------------------------------------------------------------------------------------------------------------------------------------------------
System im plem entation 20,000.00
-------------------------------------------------------------------------------------------------------------------------------------------------------------------
3-days on-site standby support during pilot run 8,000.00
-------------------------------------------------------------------------------------------------------------------------------------------------------------------
O ne training session 8,000.00
-------------------------------------------------------------------------------------------------------------------------------------------------------------------
Com puter software 15,000.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
2.0 N etworking Infrastructure 100,000.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
3.0 IT H ardware: Com puters and accessories 130,160.75
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
4.0 Supporting Software & H ardware 52,000.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Grand Total 498,160.75

Table 3: Breakdown of m ajor rejects in the wafer m anufacturing process


N o. N ature of rejection % reduction
---------------------------------------------------------------------------------------------------------------------
W ithout SPC W ith M EX Reduction in rejection
1 Contam ination 0.10 0.09 0.01
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
2 Lapping scratch 1.60 1.49 0.11
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
3 W ire m ark 1.30 1.21 0.09
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
4 Flatness out of specification 3.20 2.99 0.21

1907
J. Appl. Sci. Res., 5(11): 1904-1914, 2009

Table 3: Continue
5 Surface strain 0.60 0.56 0.04
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
6 O thers 0.80 0.75 0.05
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Total current rejection 7.60 7.10 0.50
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
M onetary rejection value 4,548,600.00 4,248,392.00 300,207.0
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Total investm ent 498,160.75
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Payback period 1.659 years (considering unit price U S$45; and production rate 350,000 pieces of wafer in a
m onth and US$1=RM 3.8)

Table 4: The actual price of the entire M EX project


No Item Am ount (RM )
1.0 M EX Software Solution – inclusive of:- 209,119.20
Requirem ent study; Solution design; Software developm ent & testing; System
im plem entation; 3-days on-site standby support during pilot run; O ne training
session; IBM D B2 U D B Express 8.1 with 12 CAL; M S W indows Server 2003
Standard; W indows Server 2003 Open D D evice CAL
----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
2.0 N etw orkin g In f r a s t r u c t u r e (U TP N etw ork P oin t; UTP B ackbone; F i b r e -o p t i c B ackbone; E le c t r i c a l)
87,350.00
----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
3.0 IT H ardware: Com puters and accessories 118,130.10
----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
4.0 Supporting Software & H ardware 38,461.00
----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Grand Total 453,060.30

Table 5: Progressive m ilestone paym ent schedule


Stage Event Planned Criteria of Com pletion Paym ent Percentage
Com pletion D ate of Total Cost (% )
1 Issue of Purchase Order (PO ) 5 Aug 2006 O fficial PO received by
GeniurSoft (Contractor) 20
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
2 Approval of Functional Specification 29 Sept 2006 Signed by S.E.H .
M anaging D irector 20
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
3 1st Phase hardware and software delivery 23 N ov 2006 D elivery acknowledged by
S.E.H . Project M anager 10
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
1st Phase on-site test
(Configuration & data entry) 10 D ec 2006 N o m ajor bugs within 2 weeks -
------------------------------------------------------------------------------------------------------------------------------------------------------------------------
2nd Phase on-site test
(Integration, Em ail & O O C) 10 D ec 2006 N o m ajor bugs within 2 weeks -
------------------------------------------------------------------------------------------------------------------------------------------------------------------------
3rd Phase on-site test
(Analysis & Reporting system ) 10 D ec 2006 N o m ajor bugs within 2 weeks -
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
4 Final hardware & software delivery 13 D ec 2006 S.E.H.ProjectM anager
signs upon delivery 10
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
5 Training 6 Jan 2007 All persons involved
attended training 20
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
6 U AT (U ser acceptance test) 13 Jan 2007 U AT approved by S.E.H .
Project O wner 10
------------------------------------------------------------------------------------------------------------------------------------------------------------------------
O perational test 21 Jan 2007 N o m ajor bugs within 1 m onth -
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
7 H and-over 28 Feb 2007 S.E.H . Project M anager
signs upon receipt 10
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Total paym ent 100

1908
J. Appl. Sci. Res., 5(11): 1904-1914, 2009

Fig. 1: Evolution of SPC application in Company DXS

Fig. 2: Architectural view of MEX

Fig. 3: Manual SPC activity flow chart.

Fig. 4: Online in-process SPC software (i. e. MEX) activity flow chart

1909
J. Appl. Sci. Res., 5(11): 1904-1914, 2009

Fig. 5: Main modules of MEX

Fig. 6: MEX team structure

Fig. 7: Example of graphical user interface of MEX

Fig. 8: W ork break down structure (W BS) for MEX development

1910
J. Appl. Sci. Res., 5(11): 1904-1914, 2009

Fig. 9: PERT chart for MEX development

Fig. 10: Graph of Cost variance and Schedule variance

Project Communication Plan: Project communications 3. Perfo rmance rep o rting— co llecting and
management includes the processes required to ensure disseminating performance information. This
timely and appropriate generation, co llection, includes status reporting, progress measurement,
dissemination, storage, and ultimate disposition of and forecasting.
project information. It provides the critical links among 4. Administrative closure— generating, gathering,
people, ideas, and information that are necessary for and disseminating information to formalize phase
success. Everyone involved in the project must be or project completion.
prepared to send and receive communications in the
project “language” and must understand how the These processes interact with each other and with
communications they are involved in as individuals the processes in the other knowledge areas as well. The
affect the project as a whole. For MEX the following communication methods that are used throughout this
communication plans are used: project include project status documents; project
planning and control documents; e-mail and meetings.
1. Communications planning— determining the Project status report consist of monthly report that are
information and communications needs of the send out to all team member on monthly basis to info
parties involve:who needs what information, overall progress of a project and reason of delay if
when will they need it, and how will it be given any. T his report also consists of an outstanding issue
to them. during the time of report preparation and upcoming
2. Informatio n d istribution— making needed activity for the next month. This report is prepared by
information available to project parties involve in project manager (client). Project planning and control
a timely manner. document is set of the document use throughout the

1911
J. Appl. Sci. Res., 5(11): 1904-1914, 2009

project implementation such as change request form, select metrics and risk indicators. These measures will
requisition request, project schedule and etc. These not only enable managers to identify, prioritize, track,
communications also cater for detailed planning of an and mitigate risks, but will also serve to gauge the
activity such as training plan, testing plan, and software effectiveness of the risk management process.
bugs report. E-mail are use for inter and intra office The risk management process is straightforward
communication to distribute any information on a need and, from a process standpoint, one of the easier
to know basis for all team member. Meetings call for disciplines to plan and implement. Projections are that
discussing any outstanding issue (as need basis) and a fully functional process including policy, plan,
also for project progress reporting (monthly basis). procedures, essential training tool loaded with an initial
set of risks and an initial risk identification session can
Conflict M anagement: Conflict in project management be completed within 30 days of identification of the
is inevitable. The potential for conflict in information requirement. Cultural acceptance and integration of the
systems development projects is usually high because process where it is a valued and essential management
it involves individuals from different backgrounds and tool supported and used effectively by management
orientations working together to complete a complex may take years to achieve. Policy and underlying
task. The cause of conflict in team projects can be commitment; Designate risk coordinator and risk
related to differences in values, attitudes, needs, officers; Identify risks; Analyze risks; Prioritize risks;
expectations, perceptions, resources, and personalities. Report risks; and Establish a risk reserve are very
Proper skills in dealing with conflict can assist project important issues to manage the risk. In MEX project,
managers and other organization members to handle the authors used Failure Mode and Effect Analysis
and effectively resolve conflicts. Conflict management (FMEA) as the risk assessment tool.
is a critical issue of project management, in which if
left uncontrolled, conflict can literally tear a project Change M anagement: As a project progresses, the
apart. In order for conflict to be effectively managed people involved with the project develop a better
by the project managers in MEX, conflict management understanding of what the end product should be and
plan is establish and clear channel for conflict what they need to do to produce the product. This
resolution is made to all parties (Fig. 11). Five modes increased understanding manifests itself as changes to
for conflict resolution are used to solve conflict during the stage activities, and changes to the products. This
the project implementation. T hese modes are will disrupt the project and stage schedules, project and
Confronting, Compromising, Smoothing, Forcing, and stage costs, project scope. Such changes cannot always
Avoiding. be avoided, but their impact can be predicted and
controlled. A change control cycle for the MEX project
R isk A ssessment and M anagement: Software management plan start with initiation of change by
applications have grown in size and complexity member of the project team (Fig. 12). A project
covering many human activities of importance to member can request change regarding to the job under
society. Unfortunately developing software is still a their supervision by firstly issuing a change request
high-risk activity. There have been many approaches to form. The form will then be submitted to the project
improving this situation, mostly focused on increasing m a n a g e r s ( V e n d o r a n d c l i e n t) d u r in g th e
productivity via improvements in technology or communication meeting. Upon officially receive the
management. Despite the recent improvements change request; the change request loop will be
introduced in software processes and automated tools, initiated by the project manager and he will review the
risk assessment for software projects remains an change request with the parties involve for the change
unstructured problem dependent on human expertise. item. Alternative and specific requirement will
Solving the risk assessment problem with indicators determine during this review. At the end of the review,
measured in the early phases would constitute a great ranking classification will be provided and the effect of
benefit to software engineering. the change on the project cost and timeline is estimated
during this stage. After the review, project manager
Risk M anagement Plan and Process: Effective risk will decide on the status of the change request either
management involves a continuous process of risk it is approved, rejected or defer to a specific date in
identification, assessment mitigation, monitoring, and the future. If it is approved, verification will be done
c o n tin ge n cy p lanning th ro u g ho u t th e syste m after the changes are implemented. Total of four (4)
development, fielding, and Post-Deployment Software changes requested during the period of the project:
Support (PDSS) phases. The risk management process three (3) cases with influence to overall project cost
should include monitoring of key development and and one (1) case for schedule change to accommodate
management practices through the implementation of unexpected delay.

1912
J. Appl. Sci. Res., 5(11): 1904-1914, 2009

Fig. 11: Conflict management cycle for MEX.

Fig. 12: MEX change control cycle.

Fig. 13: Basic Feed Back Loop.

Performance M easurement: Performance measures Conclusions: After having studied this particular
quantitatively tell us something important about our project, it is found that several project management
products, services, and the processes that produce them. tools could be used in order to improve the project
They are a tool to help us understand, manage, and planning, monitoring and successful implantation itself.
improve what our organizations do. Performance Based on project data, the authors used and analyzed
measures let us know: How well we are doing; If we work breakdown structure, PERT/CPM diagram, cost
are meeting our goals; If our customers are satisfied; If benefit analysis, cost control, responsibility assignment
our processes are in statistical control; and If and matrix, conflict management and failure mode and
where improvements are necessary. A performance effect analysis.
measure is composed of a number and a unit of Planning and scheduling activity helped to assign
measure. The number gives us a magnitude (how responsibilities to a specially identified organizational
much) and the unit gives the number a meaning (what). e le m e n t, a n d e s ta b lis he s sc he d ule s fo r the
MEX project is measure to quantify a situation, to accomplishment of the work. The actual project
regulate, or to understand what affects things. It can commencement did not deviate very much from the
help worker understand and improve performance. It is planned schedule because of its systematic approach of
exciting to measure, to benchmark, and to stretch to do implementation. In budgeting and cost control, there
better. MEX, can develop control charts, auto generates was only delay in payment time as shown by the
and plot directly. W hile using manual SPC chart one schedule variance. This is because the project manager
must draw the chart by oneself. In MEX, when the purposely breakdown the payment by phase of software
results are plotted, values are observed in relation to delivery. In workforce management, the responsibility
the center (median) line. Once MEX show the output, assignment matrix help to clearly identify each person’s
it is in statistical control, the process is performing to job function so that there is no overlapping. Risk
its natural limits and can be improved only by system management performing with FMEA to enable all
improvements, which is a management function. The project members to be aware of the potential risks in
performance of the MEX project is measured based on the project and thus try to avoid them. Change
six categories: Effectiveness; Efficiency; Quality; management helps to create a systematic documentation
Timeliness; and Productivity. The basic feedback loop for future reference. Performance measurements make
shown in Fig. 13 presents a systematic series of steps sure that requirements are met along the way.
for maintaining conformance to goals/standards by A successful project management can be defined
communicating performance data back to the as having achieved the project objectives within time
responsible worker and/or decision maker to take and cost with the desired performance/technology level
appropriate action(s). and utilizing the assigned resources effectively and

1913
J. Appl. Sci. Res., 5(11): 1904-1914, 2009

efficiently. In any project-driven organization, 5. CMMI Product T eam, 2002. Capability Maturity
particularly large multi-national manufacturing Model Integration. Retrieved January 3, 2006,
companies, project management methodology is a must fromhttp://cmsu2.cmsu.edu/public/classes/sam/cis
for handling large projects to meet cost and time 4655/cmmi.pdf
constraints. 6. Gray, C.F. and E .W . Larson, Project
management: The manageriel process. 2000,
REFERENCES Singapore: Mc Graw-Hill.
7. Hughes, B. ans M . Cotterell, 2006. Software
1. George Eckes, ‘The Six Sigma Revolution: How project management. (4th ed.). London, UK:
General Electric and others turned process into McGraw-Hill.
profits’. 2001, New York NY, W iley. 8. Muriithi, N. and L. Crawford, 2003. Approaches
2. Hubert and Stuart Dreyfus, ‘Mind over M achine’. to project management in Africa: Implications for
1986, New York NY, Macmillan, The Free Press. international development projects, International
3. Harold Kerzner, ‘Strategic Planning for Project Journal of Project Management, 2(5): 309-319.
Management Using a Project Management
Maturity Model’. 2001, New York NY, W iley.
4. Aladwani, A. M. IT Project uncertainty, planning
and success: An empirical investigation from
Kuwait. Information Technology and People.
2002, 15(3): 210-226.