Method Statement

ERECTION OF TOWER
This Method Statement describes the specific safe working methods which will be used to
carry out the described work. It gives details of work procedure with control measures to
counter health and safety issues related to this work. The listed content of this Method
Statement cannot be changed/ modified subjected to job scope/customer specifications
without the prior permission of LBU /LPG Manager, Erection Head, Safety co ordinator and
Project Manager. But task specific method statement once finalized & approved, that
should not be modified during work execution.
Project Name
Site /Location

400/132 KV SUB-STATION PROJECT AT NTPC


SOLAPUR
132 KV Transmission Line from NTPC Solapur to Ujani.

Planned schedule of
Activity
Method Statement No.

02/05/2014 to 31/12/2014
ABB/TOWER STRUCTURE/
TL/02

Rev. No.

Risk Assessment Ref.


No.

NABB/PS//OHS/JSEA/003
002 dated 22.10.2014

Rev. No.

Title :-

2( Proposed Dated 25.10.14


)

Erection of Tower Structure-132KV-TL

Scope of work: - Supply,Civil,Erection, Testing and Commissioning of 132 KV Transmission Line from NTPC
SOLAPUR to Ujjani .

Drawing
References:Technical
Specification
Document
References:Certification of Plant
etc.

Refer Attached List(Drg. No)

Detail of Sub
contractors Involved
:-

M/S Unitech Power Transmission Ltd. Office Address- 136,Udyog Vihar, Phase-1,
Gurgaon-122016, Haryana.
Tel:0124-4571000/4571001
Mr. Rajesh Pillai-Project Manager
Mr.Anil Adappa/Mr. Kumar

Technical Spec. VI[Part-1&2] & Part-V

Hydra Regd. No.CG07NA3635 [M/s Unitech power Transmission


Ltd]
Date Of Testing 01/04/2014 Valid Till date

Method Statement Prepared By :


C P Singh (Site Manager)

Signature

Date

Method Statement Reviewed By:Mr. ANUJ MAHAJAN (Project


Manager)
Mr. ARJUN SINGH ( Chief Project
Page 1

Method Statement

Manager)
Method Statement Approved By:-

1.0 Introduction (Describe purpose of the work, Give details of type and scope of work
being carried out, work parties involved (include working hours). Client requirements/
specifications, Local legislation Enforcement authorities requirements i.e. The Police, Civil
Defence, Environment Agency* (EIA) to be considered with reference to scope of work.
Purpose of the work: Construction of 132kV Transmission Line(From NTPC
Solapur to Ujani)
Scope of Work:
-Segregation , Shifting of 132kV tower structure and hardware to the work
place .
Erection of 132 Tower Structure.
Working hours: 8 Hours a day
Client Specification: Ref customer specification- Tech. Spec. Section VI [Part 1 &
2] & Part IV
2.0 Location of Work (Give site address and precise location on site where work is to be

carried out. Give details of any other locations in the proximity of the works which may
affect the safety of the work or be affected by the work considering Surrounding
Environment and what measures will be used to control these risks e.g. segregation,
warning notices, fencing, Structural stability precautions)
Work to be carried out in 123KV Transmission Line(D/C & S/C) at Different Locations
From NTPCC To Ujani.

3.0 Safety Document /Specific Approval Required (Details of any safety documents
or specific approval (i.e. Client specific approval) required to undertake the work)

Site Specific Risk Assessment


PTW & Tool Box Talk in consultation with customer
PSS OHSAS Manual
OHS COP
ABB Site manual, Part-1 & 2

4.0 Access & Egress to the work area: Give details of any special access or egress
arrangements (i.e. Ladders/MEWPS/Scaffold/Trestles/Step Ladder etc.) that will be used
Page 2

Method Statement

including any obstruction/restriction in safe access to work area. Consider the site access
from the public road onto and around the site before vehicles arrive on site, taking into
account the site traffic management plan, the designated work area for delivery vehicles
and the storage area for materials

Compacted WBM / Kaccha Road available some locations.

5.0 Role & Responsibilities of Personnel/Parties Involved in activities:- Clearly


define role and responsibilities of all personnel involved in activity i.e. Site management
staff including subcontractors parties- Main contractor Project/Site Manager, Sub
Contractor Site Manager, Project Engineer, OHS staff , Competent Supervisory Staff)
ABB Site management Staff:
Site manager: Mr. C P Singh
Site Safety Coordinator: Mr. Asit B Giri
M/S UNITECH POWER TRANSMISSION LTD. (Contractor) Site management Staff:
Project Manager: Mr. Rajesh Pillai
Site Manager: Mr. Anil Adappa
Civil Engineer: Mr.Kumar
Site Supervisor: Mr. Narendra singh / Mr.S K Mishra/Mr. Arun Roy
Safety Officer: Mr. Vargees
Site Manager :-

Check for the isolation of area for erection


Check the Work permit from ABB (Client if required in
case of shut down job).
Coordination with Client /Erection Agency/Safety
Departments for continuous monitoring of activity.
Check the weather condition before start of work.
Ensure tool box talk is done before start of the work
Check fitness of worker visually.
Check the materials availability and tested tools & tackles
with Proper lifting Machinery.
Present of Contractor Erection Engineer/Erection
Supervisor/Certified Safety Supervisor for continuous
monitoring of activity in work location.
Barricading of area during erection of work.
Check the proper illumination in yard for night work.N/A Height work is not Permitted in night.
Page 3


Erection
Engineer :-

Method Statement

Cross check the location before start the activities


involved height work.

Check the Work permit from ABB/Client.


Check the weather condition before start of work.
Check fitness of worker visually.
Check the materials availability and tested tools & tackles
with Proper lifting Machinery.
Present of Contractor Erection Engineer/Erection
Supervisor/Certified Safety Supervisor for continuous
monitoring of activity in work location.
Barricading of area during erection of work.
Access route to be decided and communicated to all
concerned.
Check the proper illumination in yard for night work.
N/A Height work is not Permitted in night.

Safety Officer /
Warden:-

Check the weather condition before start of work.


Arrange Tool Box meeting with staff and workers before
starting the activity.
Check fitness of worker visually.
Check for any underground / OH cables in the area and
isolation if required.
Check the Work permit from ABB/Client.
Work Permit to be issued after checking the safety
requirements of lifting Machinery, tools & tackles
arrangements.
Close monitoring of activities involved height work and
emergency preparedness.
Barricading requirements to be decided and
communicated to concerned.
Check House Keeping.
Check the proper illumination for night work.
N/A Height work is not Permitted in night.

6.0 Working/Activity Description:- It is important that all operatives should have clear
idea of those operational sequences and responsible supervisor must verify their
competency prior to their engagement in operation.
6.1 Pre-Testing Checks
Page 4

Method Statement

OHS Induction
Work specific Training
Ground condition in & around work place

6.2 Resources (Equipment , tools including manpower) Details i.e. Equipment and
Tools, specific operational equipment, test kits, lifting resources, Details of materials to be
used in operation, Details of the manpower allocated to the task, e.g. titles, qualifications,
competences, direct manpower, contractors. Details of plant, tools and equipment to be
used for the work, including the availability of relevant statutory documents, checks or
inspections etc. Details of fencing, barriers, cones, chains, dangers notices, warning signs
etc.

Machinery tools & tackles material as per list attached below.


Skilled Manpower for manual/Hydra/Crane/ Tractor trolley/truck shifting of
material from storage yard to place of erection.
Approval to do work in Extended hours by BU Manager Height work not
allowed in Extended Hours
Proper Illumination if working in extended hours with required permission

6.3 Details of Permits to Work required for activity: List out applicable Permits in
sequence of work, for eg. PTW(Permit to work), SFT, LAP(Limited access permit)

Check for Work permit from Customer if the work to be performed under
shutdown.
ABB work permit to be issued after checking the safety requirements.
Tool Box Talk prior to start of work.

6.4 Operational Sequence of work (i.e. Test Procedure) :- Full description of the
work, setting out the methodology in a sequential manner, including any reference to any
identified operational restraints. Also refer here sec. 5.0 responsibilities part for every
step of work sequence).
Unloading /Shifting and Erection of Structure
Sr.
No
.

Activity

Details of

Job sequence

Risk Involved

Control Checks

Page 5

Method Statement

Unloading
and
shifting of
lattice
structure
Tower/Be
am

1. Unloading of material on an
identified place of storage.
2. Identification of structure
material.
3. Segregation of all material
as per Bill of Material.
4. Shortage \ Damage report
to be prepared.

1. Contact with rough


edge.
2. Fall of material.
3. Failure of lifting
equipment.
4. Slippage of material.
5. Toppling of
crane/hydra bcoz of
uneven access.

1. Ensure work permit is


issued.
2. Ensure work specific
tool box/training
3. PPE (Hand Gloves,
Helmet, shoes) used.
4. Allow only authorize
person to work.
5. Check the condition and
load test report of all
lifting tools /crane.
6. Use proper size of
rope/slings/Belt as per
weight of Material to be
Lifted.
7. Ensure the
transportation route
must be firmed and
levelled.

2.

Shifting
and
Erection
of Main
Leg
Member.

1. Shift the structure, nuts,


bolts and washers as per
Bill of Material near to the
place of Erection.
2. Clear the area near the
foundation and check the
anchor bolts of foundation.
3. Assemble the main leg
member up to 2-3 section.
4. Fix and tighten the step
bolts in criss cross manner
in all the leg member for
the movement of a person.
5. Provide the vertical life line
in all the 4 leg member and
keep 1 spare for change
over.
6. Erect the main leg member
by crane / Hydra and
provide guide rope 2 side.
7. Remove the rope from
crane/hydra hook by
climbing thro step bolts.
8. Level the main leg member
by water tube.

1. Tilting of Main leg


member.
2. Fall of Material/Tools.
3. Fall of worker.
4. Failure of lifting
material.
5. Toppling of
Crane/Hydra.
6. Communication gap
between Supervisor
and crane operator.

1. All lifting tools /


equipment must have
valid test certificate.
2. Check the capacity of
crane/hydra and weight
of Material.
3. PPE (Hand Gloves, Full
body harness ( energy
Absorber)with 2 lanyard
having opening
minimum 80mm,
Helmet, shoes) used.
4. Engineer/supervisor
needs to be present till
completion of work.
5. Allow only authorize
/Trained person to
work.
6. Ensure work specific
tool box/Training..
7. Check the condition and
load test report of all
lifting tools /crane.
8. Use proper size of
rope/slings/Belt as per
weight of Material to be
Lifted.
Page 6

Method Statement
9. All persons should away
from the lowering
material.
10. The load should be
guide by the guide rope
to prevent toppling.

3.

Erection
of cross
members
up to
section 23

1. Assemble 2/3 members as


per the drawing.
2. Provide the packing washer
where ever required.
3. Lift the above members and
fix it on the main leg
member.
4. Complete the fixing of cross
members up to 2-3 section
of main leg member.

1. Tilting of Main leg


member.
2. Fall of Material/Tools.
3. Fall of worker.
4. Failure of lifting
material.
5. Injury due to rough
edge of members.
6. Toppling of
Crane/Hydra.
7. Communication gap
between Supervisor
and crane operator.

1. All lifting tools /


equipment must have
valid test certificate.
2. Check the capacity of
crane/hydra and weight
of Material.
3. PPE (Hand Gloves, Full
body harness( Energy
absorber) with 2 lanyard
having opening min
80mm, Helmet, shoes)
used.
4. Engineer/supervisor
needs to be present till
completion of work.
5. Allow only authorize
/Trained person to
work.
6. Check the condition and
load test report of all
lifting tools /crane.
7. Use proper size of
rope/slings/Belt as per
weight of Material to be
lifted.

Page 7


4.

Erection
of Derick
and fixing
of Balance
leg/cross
members.

Method Statement

To lift the next Section of


Tower, the following steps
to be followed :
1. The Derrick will have
horizontal MS rod of
12mm dia x 200 Long
welded 100 mm from top
& bottom of Derrick. This
rod will pass through the
hole and welded at two
ends. One pulley P1 is
fitted to this rod using a
rope for lifting the load.
2. Provide 2 -3 side guide
rope on the derrick.
3. Fix one Pulley P2 on the
top of the Main member
A already erected
(previous section).
4. Provide 2/3 life line on
the Main member A
through which derrick to
be lifted.
5. Fix one pulley P3 at the
bottom of the leg member
at the foundation level
for ease in hoisting the
derrick.
6. Lift the derrick using
Pulley P1 up to the level
of main member A with
the help of pulley P2
fixed on the top of main
member.
7. Positioning ropes should
be used to loosely tie the
derrick and the Main leg
member at two places so
as to avoid tilting during
hoisting of the derrick.
8. 2 trained workmen shall
ascend on the Main

1.
2.
3.
4.

Tilting/Fall of Derrick.
Fall of Material/Tools.
Fall of worker.
Failure of lifting
material.
5. Injury due to rough
edge of members.

1. All lifting tools /


equipment & winch /
Hydra must have valid
test certificate.
2. Provide the overlap of
derrick and main
member by 1 to 1.5 Mtr.
3. PPE (Hand Gloves, Full
body harness with 2
lanyard having opening
min 80mm, Helmet,
shoes) used.
4. Engineer/supervisor
needs to be present till
completion of work.
5. Allow only authorize
/Trained person to
work.
6. Check the condition and
load test report of all
lifting tools /crane.
7. Use proper size of
rope/slings/Belt as per
weight of Material to be
lifted.
8. Use tool bag to carry
hand tools & small nuts
and bolts.
9. Ensure fall arrestor
along the leg with rope
grab.

Page 8

Method Statement

member A using
independent life line.
They shall anchor
themselves using double
lanyard. They shall guide
the derrick during
upward movement.
9. Now,remove the rope
from the top of the
derrick and Connect the
to the bottom of the
derrick.
10.During this transition
period, the derrick shall
be fastened by
positioning ropes to the
main member.
11.Now hoist the derrick
upwards using pulley P2
& P3 upto a level till the
overlap of Main member
A & derrick shall be 11.5 Mtr.
12.Now, the top of the
derrick shall be above
the main member A.
13.Tie/fasten the derrick
with the main member A
by rope at 2/3 places
keeping a over lap of 1 to
1.5 Mtr between main
member and derrick.
14.Remove the pulley P2
from Main member A.
.
Lifting of Main member (B)
of next section
15. Provide the vertical life line
with fall arrestor and step
bolt in all the main member
to be lifted.
Page 9

Method Statement

16. Fix pulley P2 on the top of


the main member to be
lifted. (This is required for
lifting the derrick to the
next section.)
17. Lift the Main member (B)
with the pulley provided on
the top of derrick and fix it
on Main member (A) with
proper cleat plate/angle as
per drawing
18. Remove the rope on the
Main member (B) by
climbing on the step bolts.

19.While descending, the


step bolts on the Main
member ( B) used to
climb are removed. This
is to facilitate the fixing
of cross bracings.

20.Lift all the other main


members as per the
above sequence.
21. Provide the cross members
and gusset plate.
22. This completes the erection
of second section of the
Tower.
23. Continue the same till the
completion of tower up
peak.
24. Remove the derrick and
other lifting material etc.
25. Tighten all the bolts/nuts
of the tower.
26. Once again align the tower
and provide the check nut
on the anchor bolt.

6.5 Isolation Requirements:- Before starting the work, identify the work area
demarcation and accordingly isolate it from other part of operational interference.
Responsible supervisor should cross verify adequate isolation arrangements for safe
operation prior to receive Permit to work and if PTW not applicable then before start of
Page 10

Method Statement

operation during pre-check survey. Accordingly adequate caution tag/signs to be


provided.

Check for any underground / overhead Cables prior to start of activity.


If so, Isolate same and get permit before start of work.
Barricading to be done near the place of erection.
Area to be levelled near the foundation.

6.6 Final Checks & restoration of work area after completion of work :Those checks to be carried out by responsible supervisor in witness of his line
hierarchy by use of specific checklist of certain operational checks and once those
completed satisfactory, PTW(if applicable) to be closed and isolation arrangements to
be restored by removing barricades/cautionary tags.

Remove all the site worker staff from site


Remove any balance material.
Remove all tools and Plants.
Closing of Work Permit after completion of activity.

7.0 Task Specific Hazards: - Refer to Task Specific Risk Assessment and attach in
appendix
Attachment: - List of tools and plants.
In addition, please provide below control measures in risk assessment (as applicable).

Page 11


Fall Protection
Measures:
(Where work at height
cannot be avoided)
Electrical Safety
Measures

Method Statement

Use Full Body Harness with double lanyard to be used.


Provide vertical life line / fall arrestor.

(1) For electrical connections ensure with ELCB, MCB & three
core double insulated cable.
(2) Area Illumination is to be ensured for extended hours

works.
Lifting Safety
Measures

Use of specified Crane and Hydra according to Load Chart, Lifting


belts and D-shackles capacity.

Others (please
provide details)

Lunch break 1 Hr and Portable water container availability is need


to be ensured.

Hazardous
Substances:
(Attach MSDS if
required)

N/A

N/A

N/A

N/A

N/A

N/A

8.0

N/A

Emergency Provisions: - Relevant operational possibility of a programme in the case of


emergency situation i.e. electrical supply restoration. In addition emergency response
provisions i.e. first aiders, fire fighting, first aid arrangements, nearest onsite/offsite
emergency response also to be considered during emergency planning.
1)
2)
3)
4)

Site Supervisor has to report any incident to Site Manager immediately.


Supervisor has to take off control over the danger and rescue over the incident
Site manager has to inform to the first aider
First aider to reach at spot with first aid box and stretcher and provide first aid
treatment and raise siren in case of emergency
5) Site manager to call ambulance (if required)
6) Site manager alerts to Doctor and asked for treatment (if required)
7) Site manager to inform Project Manager, client and concern government
authorities if required

Page 12

Method Statement

Asit B Giri
Mobile No: 09766090757
ABB Site Office , ESSEL Office &
NTPC First Aid Centre
CITY HOSPITAL
Phone No- 0217-2315155 /
2315156

9.0 Waste Disposal/Housekeeping and Environmental issues :- Details waste


disposal processes and or housekeeping activities, Details of environmental impacts and
control measures.
Our scope of work does not involve disposal of hazardous substances. Our works
will generate negligible wastage. Those too will not be harmful and will be
disposed of in the proper manner at designated place.

10.0 Personal Protective Equipment (PPE) :- PPE requirements for the task

YES/NO

Yes

Yes

Yes

No

No

No

No

11.0 Amendments and additional information:- Should any part of this method
statement require amendment or alteration, this must be notified for agreement by all
relevant parties prior to it being enforced.

13.0 Communication of method statement and signing off register: Communicate


to all relevant parties (via a toolbox talk) and ensure it is signed by all personnel.
Emergency response plan and contact number displayed at all work locations and also
communicated during Tool box meeting.
Persons involved with the work

Page 13

Method Statement

I undersigned have read, discussed and fully understand the above method statement and
risk assessment on activity and will adhere to all method of work and condition set down.
Name

Company

H S SHARMA
C P Singh
ASIT B GIRI

ABB India Ltd

Site Manager

ABB India Ltd

Rajesh Pillai

M/s Unitech Power


Transmission Ltd.
M/s Unitech Power
Transmission Ltd.
M/s Unitech Power
Transmission Ltd.
M/S Unitech Power
Transmission Ltd

Site safety
supervisor
Project Manager

Anil Adapa
Jojy Varghese
Pawar

Designation

Date & Signature

Site Manager
Safety Officer
Store In-Charge

ANNEXURE for Point no- 6.2 (T & P Details)


TOOLS REQUIRED FOR TOWER/BEAM
ERECTION
Sr No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19

Man power / Tools


Erection Gang 15 person
Derrick
Wire Rope 12 mm 200 Mtrs
Poly propelyne rope
Torque Wrench
Double Pulley ( Set )
Single Pulley
Slings 1 Mtrs
Slings 2 Mtrs
Rope pieces ( 2M to 5M)
D shackle
Crow bar
Spanner set
Plier
Hammer
Jute Bag
Cotton hand gloves
Hydra/Crane/Winch
Machine/Truck/Tractor
Vertical life line / fall arrester

Required
1
2
2
8
4
4
4
4
4
LS
4
1

Remark

Bundle (200 Mtrs)


Open able
For fixing Pulley

For fixing Pulley

4
2
2
LS
20 Pair
1 No

For Shifting and lifting the


material

5 No.
Page 14

Method Statement

ANNEXURE OF LIST OF REFERENCE DRAWINGS


ABB
Document No.

Description of Document

STRUCTURE DRAWINGS
3VIN100471T4564
ABB/ADN/STR-02
3VIN100471T4563
ABB/ADN/STR-01
3VIN100471T4565
ABB/ADN/STR-03

765KV 7CA PORTAL DESIGN CALCULATION


765KV 7CA PORTAL FABRICATION DRAWING
765KV 7CB PORTAL DESIGN CALCULATION
765KV 7CB PORTAL FABRICATION DRAWING
765KV 7CC PORTAL DESIGN CALCULATION
765KV 7CC PORTAL FABRICATION DRAWING
765KV 7GWCB BEAM DESIGN CALCULATION
765KV 7GWCB BEAM FABRICATION DRAWING
765KV 7GWCC BEAM DESIGN CALCULATION
765KV 7GWCC BEAM FABRICATION DRG

3VIN100471T4571
3VIN100471T1548
3VIN100471T4572
3VIN100471T1549
3VIN100471T4573
3VIN100471T1550
3VIN100471T4574
3VIN100471T1551
3VIN100471T4575
3VIN100471T1552
3VIN100471T4576
3VIN100471T1553
3VIN100471T4577
3VIN100471T1554
3VIN100471T4578
3VIN100471T1555

400KV GANTRY STRUCTURE


DESIGN CALCULATION FOR 400KV BEAM MKD. - G1
FABRICATION DETAILS FOR 400KV BEAM MKD. - G1
DESIGN CALCULATION FOR 400KV BEAM MKD. - G2
FABRICATION DETAILS FOR 400KV BEAM MKD. - G2
DESIGN CALCULATION FOR 400KV TOWER MKD. - TC
FABRICATION DETAILS FOR 400KV TOWER MKD. - TC
DESIGN CALCULATION FOR 400KV TOWER MKD. - TH
FABRICATION DETAILS FOR 400KV TOWER MKD. - TH
DESIGN CALCULATION FOR 400KV TOWER MKD. - TI
FABRICATION DETAILS FOR 400KV TOWER MKD. - TI
DESIGN CALCULATION FOR 400KV TOWER MKD. - TJ
FABRICATION DETAILS FOR 400KV TOWER MKD. - TJ
DESIGN CALCULATION FOR 400KV TOWER MKD. - TM
FABRICATION DETAILS FOR 400KV TOWER MKD. - TM
DESIGN CALCULATION FOR 400KV TOWER MKD. - TN
FABRICATION DETAILS FOR 400KV TOWER MKD. - TN

3VIN100471T4566
3VIN100471T1556
3VIN100471T4567
3VIN100471T1557
3VIN100471T4570
3VIN100471T1560
3VIN100471T4568
3VIN100471T1558
3VIN100471T4569
3VIN100471T1559

765KV EQUIPMENT STRUCTURE


DESIGN CALCULATION FOR 765KV EQUIPMENT STRUCTURE MKD. - LA
FABRICATION DETAILS FOR 765KV EQUIPMENT STRUCTURE MKD. - LA
DESIGN CALCULATION FOR 765KV EQUIPMENT STRUCTURE MKD. - BPI
FABRICATION DETAILS FOR 765KV EQUIPMENT STRUCTURE MKD. - BPI
DESIGN CALCULATION FOR 765KV EQUIPMENT STRUCTURE MKD. - ISOLATOR
FABRICATION DETAILS FOR 765KV EQUIPMENT STRUCTURE MKD. - ISOLATOR
DESIGN CALCULATION FOR 765KV EQUIPMENT STRUCTURE MKD. - CT
FABRICATION DETAILS FOR 765KV EQUIPMENT STRUCTURE MKD. - CT
DESIGN CALCULATION FOR 765KV EQUIPMENT STRUCTURE MKD. - CVT
FABRICATION DETAILS FOR 765KV EQUIPMENT STRUCTURE MKD. - CVT
Page 15


3VIN100471T1561
3VIN100471T1562
3VIN100471T1564
3VIN100471T1563
3VIN100471T1565
3VIN100471T1566
3VIN100471T1568
3VIN100471T1567
3VIN100471T1569

Method Statement

400KV EQUIPMENT STRUCTURE


400KV EQUIPMENT STRUCTURE MKD - LA
400KV EQUIPMENT STRUCTURE MKD - BPI
400KV EQUIPMENT STRUCTURE MKD - CVT
400KV EQUIPMENT STRUCTURE MKD - ISOLATOR
400KV EQUIPMENT STRUCTURE MKD - CT
400KV EQUIPMENT STRUCTURE MKD - WT
400KV EQUIPMENT STRUCTURE MKD - LA - HIGH LEVEL
400KV EQUIPMENT STRUCTURE MKD - BPI - HIGH LEVEL
400KV EQUIPMENT STRUCTURE MKD - CT (High Level)

Page 16