Professional Documents
Culture Documents
ERECTION OF TOWER
This Method Statement describes the specific safe working methods which will be used to
carry out the described work. It gives details of work procedure with control measures to
counter health and safety issues related to this work. The listed content of this Method
Statement cannot be changed/ modified subjected to job scope/customer specifications
without the prior permission of LBU /LPG Manager, Erection Head, Safety co ordinator and
Project Manager. But task specific method statement once finalized & approved, that
should not be modified during work execution.
Project Name
Site /Location
Planned schedule of
Activity
Method Statement No.
02/05/2014 to 31/12/2014
ABB/TOWER STRUCTURE/
TL/02
Rev. No.
NABB/PS//OHS/JSEA/003
002 dated 22.10.2014
Rev. No.
Title :-
Scope of work: - Supply,Civil,Erection, Testing and Commissioning of 132 KV Transmission Line from NTPC
SOLAPUR to Ujjani .
Drawing
References:Technical
Specification
Document
References:Certification of Plant
etc.
Detail of Sub
contractors Involved
:-
M/S Unitech Power Transmission Ltd. Office Address- 136,Udyog Vihar, Phase-1,
Gurgaon-122016, Haryana.
Tel:0124-4571000/4571001
Mr. Rajesh Pillai-Project Manager
Mr.Anil Adappa/Mr. Kumar
Signature
Date
Method Statement
Manager)
Method Statement Approved By:-
1.0 Introduction (Describe purpose of the work, Give details of type and scope of work
being carried out, work parties involved (include working hours). Client requirements/
specifications, Local legislation Enforcement authorities requirements i.e. The Police, Civil
Defence, Environment Agency* (EIA) to be considered with reference to scope of work.
Purpose of the work: Construction of 132kV Transmission Line(From NTPC
Solapur to Ujani)
Scope of Work:
-Segregation , Shifting of 132kV tower structure and hardware to the work
place .
Erection of 132 Tower Structure.
Working hours: 8 Hours a day
Client Specification: Ref customer specification- Tech. Spec. Section VI [Part 1 &
2] & Part IV
2.0 Location of Work (Give site address and precise location on site where work is to be
carried out. Give details of any other locations in the proximity of the works which may
affect the safety of the work or be affected by the work considering Surrounding
Environment and what measures will be used to control these risks e.g. segregation,
warning notices, fencing, Structural stability precautions)
Work to be carried out in 123KV Transmission Line(D/C & S/C) at Different Locations
From NTPCC To Ujani.
3.0 Safety Document /Specific Approval Required (Details of any safety documents
or specific approval (i.e. Client specific approval) required to undertake the work)
4.0 Access & Egress to the work area: Give details of any special access or egress
arrangements (i.e. Ladders/MEWPS/Scaffold/Trestles/Step Ladder etc.) that will be used
Page 2
Method Statement
including any obstruction/restriction in safe access to work area. Consider the site access
from the public road onto and around the site before vehicles arrive on site, taking into
account the site traffic management plan, the designated work area for delivery vehicles
and the storage area for materials
Erection
Engineer :-
Method Statement
Safety Officer /
Warden:-
6.0 Working/Activity Description:- It is important that all operatives should have clear
idea of those operational sequences and responsible supervisor must verify their
competency prior to their engagement in operation.
6.1 Pre-Testing Checks
Page 4
Method Statement
OHS Induction
Work specific Training
Ground condition in & around work place
6.2 Resources (Equipment , tools including manpower) Details i.e. Equipment and
Tools, specific operational equipment, test kits, lifting resources, Details of materials to be
used in operation, Details of the manpower allocated to the task, e.g. titles, qualifications,
competences, direct manpower, contractors. Details of plant, tools and equipment to be
used for the work, including the availability of relevant statutory documents, checks or
inspections etc. Details of fencing, barriers, cones, chains, dangers notices, warning signs
etc.
6.3 Details of Permits to Work required for activity: List out applicable Permits in
sequence of work, for eg. PTW(Permit to work), SFT, LAP(Limited access permit)
Check for Work permit from Customer if the work to be performed under
shutdown.
ABB work permit to be issued after checking the safety requirements.
Tool Box Talk prior to start of work.
6.4 Operational Sequence of work (i.e. Test Procedure) :- Full description of the
work, setting out the methodology in a sequential manner, including any reference to any
identified operational restraints. Also refer here sec. 5.0 responsibilities part for every
step of work sequence).
Unloading /Shifting and Erection of Structure
Sr.
No
.
Activity
Details of
Job sequence
Risk Involved
Control Checks
Page 5
Method Statement
Unloading
and
shifting of
lattice
structure
Tower/Be
am
1. Unloading of material on an
identified place of storage.
2. Identification of structure
material.
3. Segregation of all material
as per Bill of Material.
4. Shortage \ Damage report
to be prepared.
2.
Shifting
and
Erection
of Main
Leg
Member.
Method Statement
9. All persons should away
from the lowering
material.
10. The load should be
guide by the guide rope
to prevent toppling.
3.
Erection
of cross
members
up to
section 23
Page 7
4.
Erection
of Derick
and fixing
of Balance
leg/cross
members.
Method Statement
1.
2.
3.
4.
Tilting/Fall of Derrick.
Fall of Material/Tools.
Fall of worker.
Failure of lifting
material.
5. Injury due to rough
edge of members.
Page 8
Method Statement
member A using
independent life line.
They shall anchor
themselves using double
lanyard. They shall guide
the derrick during
upward movement.
9. Now,remove the rope
from the top of the
derrick and Connect the
to the bottom of the
derrick.
10.During this transition
period, the derrick shall
be fastened by
positioning ropes to the
main member.
11.Now hoist the derrick
upwards using pulley P2
& P3 upto a level till the
overlap of Main member
A & derrick shall be 11.5 Mtr.
12.Now, the top of the
derrick shall be above
the main member A.
13.Tie/fasten the derrick
with the main member A
by rope at 2/3 places
keeping a over lap of 1 to
1.5 Mtr between main
member and derrick.
14.Remove the pulley P2
from Main member A.
.
Lifting of Main member (B)
of next section
15. Provide the vertical life line
with fall arrestor and step
bolt in all the main member
to be lifted.
Page 9
Method Statement
6.5 Isolation Requirements:- Before starting the work, identify the work area
demarcation and accordingly isolate it from other part of operational interference.
Responsible supervisor should cross verify adequate isolation arrangements for safe
operation prior to receive Permit to work and if PTW not applicable then before start of
Page 10
Method Statement
6.6 Final Checks & restoration of work area after completion of work :Those checks to be carried out by responsible supervisor in witness of his line
hierarchy by use of specific checklist of certain operational checks and once those
completed satisfactory, PTW(if applicable) to be closed and isolation arrangements to
be restored by removing barricades/cautionary tags.
7.0 Task Specific Hazards: - Refer to Task Specific Risk Assessment and attach in
appendix
Attachment: - List of tools and plants.
In addition, please provide below control measures in risk assessment (as applicable).
Page 11
Fall Protection
Measures:
(Where work at height
cannot be avoided)
Electrical Safety
Measures
Method Statement
(1) For electrical connections ensure with ELCB, MCB & three
core double insulated cable.
(2) Area Illumination is to be ensured for extended hours
works.
Lifting Safety
Measures
Others (please
provide details)
Hazardous
Substances:
(Attach MSDS if
required)
N/A
N/A
N/A
N/A
N/A
N/A
8.0
N/A
Page 12
Method Statement
Asit B Giri
Mobile No: 09766090757
ABB Site Office , ESSEL Office &
NTPC First Aid Centre
CITY HOSPITAL
Phone No- 0217-2315155 /
2315156
10.0 Personal Protective Equipment (PPE) :- PPE requirements for the task
YES/NO
Yes
Yes
Yes
No
No
No
No
11.0 Amendments and additional information:- Should any part of this method
statement require amendment or alteration, this must be notified for agreement by all
relevant parties prior to it being enforced.
Page 13
Method Statement
I undersigned have read, discussed and fully understand the above method statement and
risk assessment on activity and will adhere to all method of work and condition set down.
Name
Company
H S SHARMA
C P Singh
ASIT B GIRI
Site Manager
Rajesh Pillai
Site safety
supervisor
Project Manager
Anil Adapa
Jojy Varghese
Pawar
Designation
Site Manager
Safety Officer
Store In-Charge
Required
1
2
2
8
4
4
4
4
4
LS
4
1
Remark
4
2
2
LS
20 Pair
1 No
5 No.
Page 14
Method Statement
Description of Document
STRUCTURE DRAWINGS
3VIN100471T4564
ABB/ADN/STR-02
3VIN100471T4563
ABB/ADN/STR-01
3VIN100471T4565
ABB/ADN/STR-03
3VIN100471T4571
3VIN100471T1548
3VIN100471T4572
3VIN100471T1549
3VIN100471T4573
3VIN100471T1550
3VIN100471T4574
3VIN100471T1551
3VIN100471T4575
3VIN100471T1552
3VIN100471T4576
3VIN100471T1553
3VIN100471T4577
3VIN100471T1554
3VIN100471T4578
3VIN100471T1555
3VIN100471T4566
3VIN100471T1556
3VIN100471T4567
3VIN100471T1557
3VIN100471T4570
3VIN100471T1560
3VIN100471T4568
3VIN100471T1558
3VIN100471T4569
3VIN100471T1559
3VIN100471T1561
3VIN100471T1562
3VIN100471T1564
3VIN100471T1563
3VIN100471T1565
3VIN100471T1566
3VIN100471T1568
3VIN100471T1567
3VIN100471T1569
Method Statement
Page 16