Professional Documents
Culture Documents
S T R U C T U R E S
Using the sloped layer method to construct a roller-compacted concrete (RCC) dam
enables each layer of RCC to be placed within the initial set time of the previous
layer.This improves horizontal lift joint strength and impermeability, significantly
enhancing the safety of the dam.
he roller-compacted concrete (RCC) technique introduced to dam construction in the 1980s has
achieved significant time and cost savings compared to conventional methods of concrete placement and consolidation. International interest in
RCC dam design and construction
continues to increase, and new techniques for design and construction are
being developed, particularly to accommodate higher dams. RCC dams are
reaching 200 meters in height: the 192meter, 396-MW Miel 1 Dam in Colombia was completed in 2002; the
192-meter, 4,200-MW Longtan Dam in
China is under construction; and the
Brian Forbes, C.P. Eng., MIE Australia,
is manager of dams engineering for
GHD Pty Ltd., Consulting Engineers,
Brisbane, Australia. He is internationally recognized for his work in
RCC dam design and construction,
and has served on the review boards
for some of the worlds highest RCC
dams.
Figure 1
This figure shows how a 3.0-meter lift in an RCC dam can be constructed in
0.3-meter-thick sloped layers, which can be placed within the initial set time
of the RCC in the previous layer.
2 HRW / July 2003
For example, suppose one were using 3meter-high forms and producing RCC
with an initial set time of two hours at a
rate of 500 cubic meters per hour; then,
for the sloped layer to be placed within
the initial set time, the slope S (horizontal on vertical) of a 0.3-meter-thick
RCC layer would have to be:
S < 2x500
Wx3x0.3
i.e., approximately 1,000
W
Figure 2
the step formed behind. Using this stepprecast block-steel plate system would
appear to be ideal where more than one
step is required to match the selected lift
height. Relocation of the blocks and
steel plate is simple and repetitive; it can
be easily achieved with a few laborers
and a small mobile crane or front-end
loader.
The sloped layer method has been
shown to work well in conjunction
with grout-enriched RCC used for
At Jiangya Dam, each sloped layer was placed first at the downstream stepped
form with the dumping-spreading-compacting procedures progressing across
the dam to the upstream face. Here the width of the dam is approximately
50 meters.
4 HRW / July 2003
Conclusion