You are on page 1of 7

Foundation

Foundation is the part of structure below plinth level up to the soil. It is in direct contact
of soil and transmits load of super structure to soil. Generally it is below the ground
level. If some part of foundation is above ground level, it is also covered with earth
filling. This portion of structure is not in contact of air, light etc, or to say that it is the
hidden part of the structure.
Depth of Foundation
Depth of foundation depends on following factors.
1. Availability of adequate bearing capacity
2. Depth of shrinkage and swelling in case of clayey soils, due to seasonal changes which
may cause appreciable movements.
3. Depth of frost penetration in case of fine sand and silt.
4. Possibility of excavation close by
5. Depth of ground water table
6. Practical minimum depth of foundation should not be less than 50 cm. to allow
removal of top soil and variations in ground level.
7. Hence the best recommended depth of foundation is from 1.00 meter to 1.5 meter
from original ground level.
Footing
Footing is a structure constructed in brick work, masonry or concrete under the base of a
wall or column for distributing the load over a large area.
Width of Foundation/ Footings
The width of footings should be laid according to structural design. For light loaded
buildings such as houses, flats, school buildings etc having not more than two storeys,
the width of foundation is given below.
1. The width of footing should not be less than 75 cm for one brick thick wall.
2. The width of footing should not be less than 1 meter for one and half brick wall.
Different Processes in Foundation Work
The processes executed in the foundation works are given below.
1. Excavation of earth work in trenches for foundation.
2. Laying out cement concrete.
3. Laying the footing in case of raft or column construction.
4. Laying Anti termite treatment.

5. Laying Brick work up to plinth level.


6. Laying Damp proof course on the walls.
7. Refilling of earth around the walls
8. Refilling of earth in the building portion up to the required height according to plinth
level.

Precautions while designing Foundation


1.

A foundation should be designed to transmit combined dead load, imposed load


and wind load to the ground.

2.

Net loading intensity of pressure coming on the soil should not exceed the safe
bearing capacity.

3.

Foundation should be designed in such a way that settlement to the ground is


limited and uniform under whole of the building to avoid damage to the structure.

4.

Whole design of the foundation, super structure and characteristics of the ground
should be studied to obtain economy in construction work.

Ratio of Cement Concrete and Mortar for Foundation


1.

The cement concrete 1:8:16 is generally used in the foundation of walls in


construction work.

2.

In case of column raft cement concrete 1:4:8 is the best recommended ratio for it
in the foundation.

3.

For brick masonry cement mortar 1:4 to 1:6 is used as loading condition.

In case of column and raft footings up to plinth level cement concrete 1:2:4 or 1:1.5:3
are used.
Soil having Safe Bearing Capacity
Dry coarse and well graded dense sand have maximum shear resistance and maximum
bearing capacity. In general submerged soil and clay have less bearing capacity.

Precautions during Excavation of Foundation Work


The depth and width of foundation should be according to structural design.
1.

The depth of the foundation should not be less than 1 meter in case the design is
not available.

2.

The length, width and depth of excavation should be checked with the help of
center line and level marked on the burjis.

3.

The excavated material/ earth should be dumped at a distance of 1 meter from


the edges.

4.

Work should be done on dry soil.

5.

Arrangement of water pump should be made for pumping out rain water.

6.

The bottom layer of the foundation should be compacted.

7.

There should be no soft places in foundation due to roots etc.

8.

Any soft/ defective spots should be dug out and be filled with concrete/ hard
material

Fig: Excavation for foundation where root of tree exists

Fig: Excavation of wall in foundation root removed

Fig: Pit of root filled with hard material

Fig: Excavation of foundation of wall with a patch of soft soil

Fig: Excavation of wall foundation with soft soil removed

Fig: Pit of soft soil filled with hard material

Demarcation/layout Procedure for foundation:


The following procedure is recommended for demarcation of a building.

For layout of a building baseline is marked on the ground either from centre line
of the road or from any permanent building nearby. This line helps to mark out the
front of a building. Side baseline is also marked with the help of side structure or
road or it can be marked with the help of first baseline or boundary of the plot.

Fix temporary pegs at the centre line of walls/columns on both sides of walls and
columns in front and back side.
Fix peg at the centre line of walls/columns on both sides of wall and columns in
left and right side of front of building.

Check diagonals of the square or rectangle formed after fixing pegs.

Construct Burji or marking pillars with pegs at a distance of 1.5 meter to 2


meters and their top surface should be plastered.

Mark centre line on the top of Burjis with the help of thread (Soot) or with the
Thedolite in big projects and the diagonal and other dimension should be checked.

Level Burji on all corners of building and the top level is fixed at a proposed plinth
level.

Mark the foundation of walls/columns according to drawing on the ground with


the help of centerline marked on the Burji.

Mark foundation trenches on the ground with chalk powder.


Excavate the foundation of the walls /columns up to required level and the
excavation must be checked with the help of centre line and level burji to avoid any
complication later on.

Fig: Excavation for foundation under wall


Advantages of Layout with the help of Burjis

It saves time for measuring and setting of point again and again at the time of
construction.

It increases the efficiency of mason and foreman for doing their jobs.

Accuracy can be checked at any time at any step.

If any mistake is found, it can be easily be rectified at early stage. It is very


difficult to rectify the mistake in later.

Cross check can be done by senior engineer in minimum time.

A qualitative work is maintained.

Disadvantages for doing the work without layout


At some sites of work the contractor brings steel pieces, erects the same on the ground
and start the work of excavation. In due course these steel pieces are just discarded.
Thus no proper reference point is available while doing further jobs.

It involves extra time for measuring the offset again and again.

Accuracy can not be checked at early stage and it will be very difficult to rectify
the same in later stage.

It involves wastage of time and money while doing rectification. This also leads to
bad quality of work.

Materials used during Setting up of Layout


1.

Leveling Instrument

2.

Balli

3.

Long Nails

4.

Hammer

5.

Right Angle(Guniya)

6.

Steel Tape

7.

Thin Cotton Thread

8.

Bricks

9.

Cement

10.

Screen Sand

11.

Lime Powder

12.

Theodolite

You might also like