You are on page 1of 64

[B] TECHNICAL SPECIFICATION FOR THE ITEM.

Item No. 1

Site Clearance, Loosening and recompacting at OMC the original ground/


sub grade up to the required depth as directed by the Engineer and as per
Technical Specifications MORTH Clause 201, 301 & 305.
CLEARING AND GRUBBING

1.1

Scope
This work shall consist of cutting, removing and disposing of all materials
such as trees, bushes, shrubs, stumps, roots, grass, weeds, top organic soil not
exceeding 150 mm in thickness, rubbish etc., which in the opinion of the
Engineer are unsuitable for incorporation in the works, from the area of road
land containing road embankment, drains, cross-drainage structures and such
other areas as may be specified on the drawings or by the Engineer, it shall
include necessary excavation, backfilling of pits resulting from uprooting of
trees and stumps to required compaction, handling, salvaging, and disposal of
cleared materials. Clearing and grubbing shall be performed in advance of
earthwork operations and in accordance with the requirements of these
Specifications.
The Loosening, grading and recompacting of the original ground and sub
grade is required to be carried out for excavation for Road way and Earth work
for embankment for Road. The Loosening of the sub grade will be carried out
to a depth as directed by the Engineer in Charge. The loosening of the sub
grade will be carried out minimum to a depth of 10 cm.

1.2

Preservation of Property / Amenities


Roadside trees, shrubs, any other plants, pole lines, fences, signs, monuments,
buildings, pipelines, sewers and all highway facilities within or adjacent to the
highway which are not to be disturbed shall be protected from injury or
damage. The Contractor shall provide and install at his own expense, suitable
safeguards approved by the Engineer for this purpose.
During clearing and grubbing, the Contractor shall take all adequate
precautions against soil crosion, water pollution, etc., and where required,
undertake additional works to that effect vide MORTH Clause 306. Before
start of operations, the Contractor shall submit to the Engineer for approval,
his work plan including the procedure to be followed for disposal of waste
materials etc. and the schedules for carrying out temporary and permanent
erosion control works as stipulated in MORTH Clause 306.3

1.3

Methods, Tools and Equipments


Only such methods, tools and equipment as are approved by the Engineer and
which will not affect the property to be preserved shall be adopted for the
64

Work. If the area has thick vegetation/roots/trees, a crawler or pneumatic tyred


dozer of adequate capacity may be used for clearace purposes. The dozer shall
have ripper attachments for removal of tree stumps. All trees, stumps, etc.,
falling within excavation and fill lines shall be cut to such depth below ground
level that in no case these fall within 500 mm of the subgrade. Also, all
vegetation such as roots under-growth, grass and other deleterious matter
unsuitable for incorporation in the embankment/subgrade shall be removed
between fill lines to the satisfaction of the Engineer. On areas beyond these
limits, trees and stumps required to be removed as directed by the Engineer
shall be cut down to 1 m below ground level so that these do not present an
unsightly appearance.
All branches of trees extending above the roadway shall be trimmed as
directed by the Engineer.
All excavations below the general ground level arising out of the removal of
trees, stumps, etc. shall be filled with suitable material and compacted
thoroughly so as to make the surface at these points conform to the
surrounding area.
Ant-hills both above and below the ground, as are liable to collapse and
obstruct free subsoil water flow shall be removed and their workings, which
may extend to several meters, shall be suitably treated.
1.4

Disposal of Materials
All materials arising from cleaning and grubbing operations shall be the
property of Government and shall be disposed of by the Contractor as
hereinafter provided or directed by the Engineer.
Trunks, branches and stumps of trees shall be cleaned of limbs and roots and
stacked. Also boulders, stones and other materials usable in road construction
shall be nearly stacked as directed by the Engineer. Stacking of stumps,
boulders, stones etc., shall be done at specified spots with all lifts and upto a
lead of 1000 m.
All products of clearing and grubbing which in the opinion of the Engineer,
cannot be used or auctioned shall be cleared away from the roadside in a
manner as directed by the Engineer. Care shall be taken to see that unsuitable
waste materials are disposed of in such a manner that there is no likelihood of
these getting mixed up with the materials meant for embankment, subgrade
and road construction.

1.5

Measurements for Payment


Clearing and grubbing for road embankment, drains and cross-drainage
structures shall be measured on area basis in terms of square meter. Clearing
and grubbing of borrow areas shall be deemed to be a part of works
preparatory to embankment construction and shall be deemed to have been
included in the rates quoted for the embankment construction item and no

65

separate payment shall be made for the same. Cutting of trees upto 300 mm in
girth including removal of stumps and roots, and trimming of branches of trees
extending above the roadway shall be considered incidental to the clearing and
grubbing operations. Removal of stumps left over after trees have been cut by
any other agency shall also be considered incidental to the clearing and
grubbing operations.
Cutting, including removal of stumps and roots of trees of girth above 300 mm
and backfilling to required compaction shall be measured in terms of number
according to the sizes given below :i)
ii)
iii)
iv)

Above
Above
Above
Above

300 mm to 600 mm
600 mm to 900 mm
900 mm to 1800 mm
1800 mm

For this purpose, the girth shall be measured at a height of 1 metre above
ground or at the top of the stump if the height of the stump is less than one
meter from the ground.
1.6

Rates

1.6.1

The Contract unit rates for the various items of clearing and grubbing shall be
payment in full for carrying out the required operations including full
compensation for all labour, materials, tools, equipment and incidentals
necessary to complete the work. These will also include removal or stumps of
trees less than 300 mm in girth as well as stumps left over after cutting of trees
carried out by another agency, excavation and back-filling to required density,
where necessary, and handling, salvaging, piling and disposing of the cleared
materials with all lifts and up to a lead of 1000 m.

1.6.2

The contract unit rate for cutting (including removal of stumps and roots ) of
trees of girth above 300 mm shall include excavation and backfilling to
required compactions, handling, salvaging piling and disposing of the cleared
materials with all lifts and up to a lead of 1000 m.

1.6.3.

Where a Contract does not include separate items of clearing and grubbing,
the same shall be considered incidental to the earthwork items, and Contract
unit prices for the same shall be considered as including clearing and grubbing
operation.

1.6.4

The measurements will be taken in length and breadth carried out and will be paid in
Sq.m. basis.

66

Item No. 2

Earthwork for embankment from borrow area within all lead as


approved by the Engineer in charge, including breaking clods, dressing
with all leads and lift and compacting the same at OMC in layers not
more than 200 mm thick, including rolling with vibratory roller of 8 to 12
tonnes weight including watering to obtain M.D.D etc. complete.
MORTH Clause 305.

2.0

EMBANKMENT CONSTRUCTION

2.1

General

2.1.1

Description :
These Specifications shall apply to the construction of embankments including
subgrades, earthen shoulders and miscellaneous backfills with approved
material obtained from roadway and drain excavation, borrow pits or other
sources. All embankments, subgrades, earthen shoulders and miscellaneous
backfills shall be constructed in accordance with the requirements of these
Specifications and in conformity with the lines, grades, and cross-sections
shown on the drawings or as directed by the Engineer.

2.2

Materials and General Requirements

2.2.1

Physical requirements :

2.2.1.1

The materials used in embankments, subgrades, earthen shoulders and


miscellaneous backfills shall be soil, moorum, gravel, a mixture of these or
any other material approved by the Engineer. Such materials shall be free of
logs, stumps, roots, rubbish or any other ingredient likely to deteriorate or
affect the stability of the embankment/ subgrade.
The following types of material shall be considered unsuitable for
embankment:
a. Materials from swamps, marshes and bogs;
b. Peat, Log, stump and perishable material; any soil that classifies as OL,
OI, OH or Pt in accordance with IS : 1498.
c. Materials susceptible to spontaneous combustion;
d. Materials in a frozen condition;
e. Clay having liquid limit exceeding 70 and plasticity index exceeding 45;
and
f. Materials with salts resulting in leaching in the embankment.

2.2.1.2.

Expansive clay exhibiting marked swell and shrinkage properies (free


swelling index exceeding 50 per cent when tested as per IS : 2720 Part
40) shall not be used as a fill material. Where an expansive clay with
acceptable free swelling index value is used as fill material, subgrade and
top 500 mm portion of the embankment just below subgrade shall be nonexpansive in nature.

67

2.2.1.3.

Any fill material with a soluble suplhate content exceeding 1.9 grams of
sulphate (expressed as SO2) per litre when tested in accordane with BS : 1377
Test 10, but using at 2:1 water-soil ratio shall not be deposited within 500 mm
or other distance described in the Contract of concrete, cement bound
materials or other cementitious materials forming part of the Permanent
Works.
Materials with a total sulphate content (expressed as SO3) exceeding 0.5 per
cent by mass when tested in accordance with BS : 1377 Test 9 shall not be
deposited within 500 mm or other distances described in the Contract, of
metallic items forming part of the Permanent Works.
2.2.1.4.
The size of the coarse material in the mixture of earth shall
ordinarily not exceed 75 mm when being placed in the embankment and 50
mm when placed in the sub grade. However, the Engineer may at his
discretion permit the use of material coarser than this also if he is satisfied that
the same will not present any difficulty as regards the placement of fill
material and its compaction to the requirements of these Specifications. The
maximum particle, size shall not be more than two-thirds of the compacted
layer thickness.

2.2.1.5.

Ordinarily, only the materials satisfying the density requirements given in


MORTH Table 300-1 shall be employed for the construction of the
embankment and the subgrade.
MORTH Table 300-1

DENSITY REQUIREMENTS OF EMBANKMENT AND SUBGRADE MATERIALS


Sr. No.

Type of Work

Embankment up to 3 meters height,


not subjected to extensive flooding.
Embankment exceeding 3 metres
height or embankments of any
height subject ot long periods of
inundation
Subgrade and earthen shoulders /
verges / backfill

Max. laboratory dry unit weight when


tested as per IS : 2720 (Part 8)
Not less than 15.2 kN/cum
Not less than 16.0 kN/cum

Not less than 17.5 kN/cum

Notes :
1. This Table is not applicable for lightweight fill material e.g. cinder, fly ash
etc.
2. The Engineer may relax these requirements at his discretion taking into
account the availability of materials for construction and other relevant
factors.
3. The material to be ued in subgrade should also satisfy design CBR at the
dry unit weight applicable as per Table 300-2.

68

2.2.2.

General Requirements :

2.2.2.1

The materials for embankment shall be obtained from approved sources with
preference given to materials becoming available from nearby roadway
excavation or any other excavation under the same contract.
The work shall be so planned and executed that the best available materials are saved for the subgrade and the embankment portion just below the
subgrade.

2.2.2.2.

Borrow materials :
Where the materials are to be obtained from designated borrow areas, the
location, size and shape of these areas shall be as indicated by the Engineer
and the same shall not be opened without his written permission. Where
specific borrow areas are not designated by the Employer/the Engineer,
arrangement for locating the source of supply of material for embankment and
subgrade as well as compliance to environmental requirements in respect of
excavation and borrow areas as stipulated, from time to time by the Ministry
of Environment and Forests, Government of India and the local bodies, as
applicable, shall be the sole responsibility of the Contractor.
Borrowpits along the road shall be discouraged. If permitted by the Engineer,
these shall not be dug continuously. Ridges of not less than 8 m width should
be left at intervals not exceeding 300 m. Small drains shall be cut through the
ridges to facilitate drainage. The depth of the pits shall be so regulated that
their bottom does not cut an imaginary line having a slope of I vertical to 4
horizontal projected from the edge of the final section of the bank, the
maximum depth in any case being limited to 1.5 m. Also, no pit shall be dug
within the offset width from the toe of the embankment required as per the
consideration of stability with a minimum width of 10 m.
Haulage of material to embankments or other areas of fill shall proceed only
when sufficient spreading and compaction plant is operating at the place of
deposition.
No excavated acceptable material other than surplus to requirements of the
Contract shall be removed from the site. Should the Contractor be permitted to
remove acceptable material from the site to suit his operational procedure,
then he shall make good any consequent deficit of material arising therefrom.
Where the excavation reveals a combination of acceptable and unacceptable
materials, the Contractor shall, unless otherwise agreed by the Engineer, carry
out the excavation in such a manner that the acceptable materials are
excavated separately for use in the permanent works without contamination
by the unacceptable materials. The acceptable materials shall be stockpiled
separately.

69

The Contractor shall ensure that he does not adversely affect the stability of
excavation or fills by the methods of stockpiling materials, use of plants or
siting of temporary buildings or structures.
The Contractor shall obtain representative samples from each of the identified
borrow areas and have these tested at the site laboratory following a testing
programme approved by the Engineer. It shall be ensured that the subgrade
material when compacted to the density requirements as in MORTH Table
300-2 shall yield the design CBR value of the subgrade
MORTH Table 300-2
COMPACTION REQUIREMENTS FOR EMBANKMENT AND SUBGRADE
Sr. No.

Type of Work

1
2
3

Subgrade and earthen shoulders


Embankment
Expansive Clays
a) Subgrade and 500 mm portion
just below the subgrade.
b)

Remaining
embankment

portion

of

Relative compation as percentage of


max. laboratory dry density as per
IS : 2720 ( Part 8 )
Not less than 97
Not less than 95
Not allowed
Not less than 90

The Contractor shall at least 7 working days before commencement of


compaction submit the following to the Engineer for approval :
I

The values of maximum dry density and optimum moisture content obtained
in accordance with IS : 2720 (Part : 7) or (Part 8) as the case may be,
appropriate for each of the fill materials he intends to use.

II

A graph of density plotted against moisture content from which each of the
values in (I) above of maximum dry density and optimum moisture content
were determined.

III

The Dry denisty-moisture content CBR relationships for light, intermediate


and heavy compactive efforts (light corresponding to IS : 2720 (Part 7), heavy
corresponding to IS : 2720 (Part 8) and intermediate in-between the two) for
each of the fill materials he inteds to use in the subgrade.
Once the above information has been approved by the Engineer, it shall form
the basis for compaction.

70

2.3.

Construction Operations

2.3.1

Setting Out :
After the site has been cleared to MORTH Clause 201, the work shall be
set out to MORTH Clause 301.3.1. The limits of embankment/subgrade
shall be marked by Fixing batter pegs on both sides at regular intervals
as guides before commencing the earthwork. The embankment/subgrade
shall be built sufficiently wider than the design dimension so that surplus
matenai may be trimmed, ensuring that the remaining material is to the
desired density and in position specified and conforms to the specified
side slopes.

2.3.2.

Dewatering :
If the foundation of the embankment is in an area with stagnant water, and
in the opinion of the Engineer it is feasible to remove it, the same shall be
removed by bailing out or pumping, as directed by the Engineer and the area
of the embankment foundation shall be kept dry. Care shall be taken to
discharge the drained water so as not to cause damage to the works, crops or
any other property. Due to any negligence on the part of the Contractor, if
any such damage is caused, it shall be the sole responsibility of the Contractor
to repair/restore it to original condition or compensate the damage at his own
cost.
If the embankment is to be constructed
apply.

2.3.3.

under water. Clause 3.4.6 shall

Stripping and storing topsoil :


In localities where most of the available embankment materials are not
conducive to plant growth, or when so directed by the Engineer, the topsoil
from all areas of cutting and from all areas to be covered by embankment
foundation shall be stripped to specified depths not exceeding 150 mm and
stored in stockpiles of height not exceeding 2 m for covering embankment
slopes, cut slopes and other disturbed areas where re-vegetation is desired.
Topsoil shall not be unnecessarily trafficked either before stripping or.
when in a stockpile. Stockpiles shall not be surcharged or otherwise loaded
and multiple handling shall be kept to a minimum.

2.3.4.

Compacting ground supporting embankment/subgrade:


Where necessary, the original ground shall be levelled to facilitate placement
of first layer of embankment, scarified, mixed with water and then compacted
by rolling so as to achieve minimum dry density as given in MORTH Table
300-2,

71

In case where the difference between the subgrade level (top of the subgrade
on which pavement rests) and ground level is less than 0.5 m and the ground
does not have 97 per cent relative compaction with respect to the dry density
as given in MORTH Table 300-2, the ground shall be loosened upto a level
0.5 m below the subgrade level, watered and compacted in layers in
accordance with Clauses 3.3.5 and 3.3.6 to not less than 97 per cent of dry
density as given in MORTH Table 300-2.
Where so directed by the Engineer, any unsuitable material occurring in the
embankment foundation shall be removed and replaced by approved
materials laid in layers to the required degree of compaction.
Embankment or subgrade work shall not proceed until the foundations for
embankment/subgrade have been inspected by the Engineer for satisfactory
condition and approved.
Any foundation treatment specified for embankments especially high
embankments, resting on suspect foundations as revealed by borehole logs
shall be carried out in a manner and to the depth as desired by the Engineer.
Where the ground on which an embankment is to be built has any of the
material types (a) to (f) in Clause 3.2.1, at least 500 mm of such material must
be removed and replaced by acceptable fill material before embankment
construction commences.
2.3.5.

Spreading material in layers and bringing to appropriate moisture


content
2.3.5.1.
The embankment and subgrade material shall be spread in
layers of uniform thickness not exceeding 200 mm compacted thickness
over the entire width of embankment by mechanical means, finished by a
motor grader and compacted as per Clause 3.3.6. The motor grader blade
shall have hydraulic control suitable for initial adjustment and maintain the
same so as to achieve the specific slope and grade. Successive layers shall not
be placed until the layer under construction has been thoroughly compacted to
the specified requirements as in MORTH Table 300-2 and got approved by the
Engineer. Each compacted layer shall be finished parallel to the final crosssection of the embankment.

2.3.5.2.

Moisture content of the material shall bechecked at the site of placement


prior to commencement of compaction; if found to be out of agreed limits, the
same shall be made good. Where water is required to be added in such
constructions, water shall be sprinkled from a water tanker fitted with
sprinkler capable of applying water uniformly with a controllable rate of flow
to variable widths of surface but without any flooding. The water shall be
added uniformly and thoroughly mixed in soil by blading, discing or
harrowing until a uniform moisture content is obtained throughout the depth
of the layer.

72

If the material delivered to the roadbed is too wet, it shall be dried, by aeration
and exposure to the sun, till the moisture content is acceptable for compaction.
Should circumstances arise, where owing to wet weather, the moisture content
cannot be reduced to the required amount by the above procedure,
compaction work shall be suspended.
Moisture content of each layer of soil shall be checked in accordance with
IS: 2720 (Part 2), and unless otherwise mentioned, shall be so adjusted,
making due allowance for evaporation losses, that at the time of
compaction it is in the range of I per cent above to 2 per cent below the
optimum moisture content determined in accordance with IS:2720 (Part
7) or IS:2720 (Part 8) as the case may be. Expansive clays shall, however,
be compacted at moisture content corresponding to the specified dry
density, but on the wet side of the optimum moisture content obtained
from the laboratory compaction curve.
After adding the required amount of water, the soil shall be processed by
means of graders, harrows, rotary mixers or as otherwise approved by the
Engineer until the layer is uniformly wet.
Clods or hard lumps of earth shall be broken to have a maximum size of 75
mm when being placed in the embankment and a maximum size of 50 mm
when being placed in the subgrade.
2.3.5.3.

Embankment and other areas of fill shall, unless otherwise required in the
Contract or permitted by the Engineer, be constructed .evenly over their full
width and their fullest possible extent and the Contractor shall control and
direct construction plant and other vehicular traffic uniformly over them.
Damage by construction plant and other vehicular traffic shall be made good
by the Contractor with material having the same characteristics and strength as
the material had before it was damaged.
Embankments and other areas of unsupported fills shall not be constructed
with steeper side slopes, or to greater widths than those shown in the
Contract, except to permit adequate compaction at the edges before trimming
back, or to obtain the final profile following any settlement of the fill and the
underlying material.
Whenever fill is to be deposited against the face of a natural slope, or sloping
earthworks face including embankments, cuttings, other fills and excavations
steeper than I vertical on 4 horizontal, such faces shall be benched as per
Clause 3.4.1 immediately before placing the subsequent fill.
All permanent faces of side slopes of embankments and other areas of fill
formed shall, subsequent to any trimming operations, be reworked and sealed
to the satisfaction of the Engineer by tracking a tracked vehicle, considered
suitable by the Engineer, on the slope or any other method approved by the
Engineer.

2.3.6.

Compaction

73

Only the compaction equipment approved by the Engineer shall be employed


to compact the different material types encountered during construction.
Smooth wheeled, vibratory, pneumatic tyred, sheepsfoot or pad foot rollers,
etc. of suitable size and capacity as approved by the Engineer shall be used for
the different types and grades of materials required to be compacted either
individually or in suitable combinations.
The compaction shall be done with the help of vibratory roller of 80 to 100 kN
static weight with plain or pad foot drum or heavy pneumatic tyred roller of
adequate capacity capable of achieving required compaction.
The Contractor shall demonstrate the efficacy of the equipment he intends to
use by carrying out compaction trials. The procedure to be adopted for these
site trials shall first be submitted to the Engineer for approval.
Earthmoving plant shall not be accepted as compaction equipment nor shall
the use of a lighter category of plant to provide any preliminary compaction to
assist the use of heavier plant be taken into account.
Each layer of the material shall be thoroughly compacted to the densities
specified in MORTH Table 300-2. Subsequent layers shall be placed only
after the finished layer has been tested according to Clause E17.2.2 and
accepted by the Engineer. The Engineer may permit measurement of field
dry density bya nuclear moisture/density gauge used in accordance with
agreed procedure and the gauge is calibrated to provide results identical to that
obtained from tests in accordance with IS: 2720 (Part 28). A record of the
same shall be maintained by the Contractor.
When density measurements reveal any soft areas in the
embankment/subgrade/earthen shoulders, further compaction shall be carried
out as directed by the Engineer. If inspite of that the specified compaction is
not achieved, the material in the soft areas shall be removed and replaced by
approved material, compacted to the density requirements and satisfaction of
the Engineer.
2.3.7.

Drainage
The surface of the embankment/subgrade at all times during construction
shall be maintained at such a cross fall (not flatter than that required for
effective drainage of an earthen surface) as will shed water and prevent
ponding.

2.3.8.

Repairing of damages caused by rain/spillage of water


The soil in the affected portion shall be removed in such areas as directed by
the Engineer before next layer is laid and refilled in layers and compacted
using appropriate mechanical means such as small vibratory roller, plate
compactor or power rammer to achieve the required density in accordance
with Clause 3.3.6. If the cut is not sufficiently wide for use of required

74

mechanical means for compaction, the same shall be widened suitably to


permit their use for proper compaction. Tests shall be carried out as directed
by the Engineer to ascertain the density requirements of the repaired area.
The work of repairing the damages including widening of the cut, if any,
shall be carried out by the Contractor at his own cost, including the arranging
of machinery/equipment for the purpose.
2.3.9.

Finishing operations
Finishing operations shall include the work of shaping and dressing the
shoulders/verge/roadbed and side slopes to conform to the alignment,
levels, cross-sections and dimensions shown on the drawings or as directed
by the Engineer subject to .the surface tolerance described in Clause E16.
Both the upper and lower ends of the side slopes shall be rounded off to
improve appearance and to merge the embankment with the adjacent terrain.
The topsoil, removed and conserved earlier (MORTH Clause 301.3.2 and
3.3.3) shall be spread over the fill slopes as per directions of the Engineer to
facilitate the growth of vegetation. Slopes, shall be roughened and moistened
slightly prior to the application of the topsoil in order to provide satisfactory
bond. The depth of the topsoil shall be sufficient to sustain plant growth, the
usual thickness being from 75 mm to 150 mm.
Where directed, the slopes shall be turfed with sods in accordance with
MORTH Clause 307. If seeding and mulching of slopes is prescribed, this
shall be done to the requirement of MORTH Clause 308.
When earthwork operations have been substantially completed, the road area
shall be cleared of all debris, and ugly scars in the construction area
responsible for objectionable appearance eliminated.

2.4.

Construction of Embankment and Subgrade under Special Conditions

2.4.1.

Earthwork for widening existing road embankment When an existing


embankment and/or subgrade is to be widened and its slopes are steeper than I
vertical on 4 horizontal, continuous horizontal benches, each at least 300 mm
wide, shall be cut into the old slope for ensuring adequate bond with the fresh
embankment/subgrade material to be added. The material obtained from
cutting of benches could be utilized in the widening of the
embankment/subgrade. However, when the existing slope against which the
fresh material is to be placed is flatter than 1 vertical on 4 horizontal, the
slope surface may only be ploughed or scarified instead of resorting to
benching.
Where the width of the widened portions is insufficient to permit the use of
conventional rollers, compaction shall be carried out with the help of small
vibratory rollers/plate compactors/power rammers or any other appropriate
equipment approved by the Engineer. End dumping of material from trucks for
widening operations shall be avoided except in difficult circumstances when

75

the extra width is too narrow to permit the movement of any other types of
hauling equipment.

2.4.2.

Earthwork for embankment and subgrade to be placed against sloping


ground :
Where an embankment/subgrade is to be placed against sloping ground, the
latter shall be appropriately benched or ploughed/scarified as required in
Clause 3.4.1 before placing the embankment/subgrade material. Extra
earthwork involved in benching or due to ploughing/scarifying etc. shall be
considered incidental to the work.
For wet conditions, benches with slightly inward fall and subsoil drains at the
lowest point shall be provided as per the drawings, before the fill is placed
against sloping ground.
Where the Contract requires construction of transverse subsurface drain at the
cut-fill interface, work on the same shall be carried out to MORTH Clause 309
in proper sequence with the embankment and subgrade work as approved by
the Engineer.

2.4.3.

Earthwork over existing road surface :


Where the embankment is to be placed over an existing road surface, the
work shall be carried out as indicated below :
1. If the existing road surface is of granular or bituminous type and lies within 1
m of the new subgrade level, the same shall be scarified to a depth of 50 mm
or more if specified, so as to provide ample bond between the old and new
material ensuring that at least 500 mm portion below the top of new
subgrade level is compacted to the desired density.
2. If the existing road surface is of cement concrete type and lies within 1
m of the new subgrade level the same shall be removed completely.
3. If the level difference between the existing road surface and the new
formation level is more than 1m, the existing surface shall be permitted to
stay in place without any modification.

2.4.4

Embankment and subgrade around structures


To avoid interference with the construction of abutments, wing walls or return
walls of culvert/bridge structures, the Contractor shall, at points to be
determined by the Engineer suspend work on embankment forming
approaches to such structures, until such time as the construction of the latter
is sufficiently advanced to permit the completion of approaches without the
risk of damage to the structure.

76

Unless directed otherwise, the filling around culverts, bridges and other
structures upto a distance of twice the height of the road from the back of the
abutment shall be carried out independent of the work on the main
embankment. The fill material shall not be placed against any abutment or
wing wall, unless permission has been given by the Engineer but in any case
not until the concrete or masonry has been in position for 14 days. The
embankment and subgrade shall be brought up simultaneously in equal layers
on each side of the structure to avoid displacement and unequal pressure. The
sequence of work in this regard shall be got approved from the' Engineer.
The material used for backfill shall not be an organic soil or highly plastic clay
having plasticity index and liquid limit more than 20 and 40 respectively
when tested according to IS:2720 (Part 5). Filling behind abutments and wing
walls for all structures shall conform to the general guidelines given in
Appendix 6 of IRC:78 (Standard Specifications and Code of Practice for Road
Bridges-Section VII) in respect of the type of material, the extent of backfill,
its laying and compaction etc. The fill material shall be deposited in
horizontal layers in loose thickness and compacted thoroughly to the
requirements of MORTH Table 300-2.
Where the provision of any filter medium is specified behind the abutment, the
same shall be laid in layers simultaneously with the laying of fill material. The
material used for filter shall conform to the requirements for filter medium
spelt out in MORTH Clause 2502/309.3.2 (B) unless otherwise specified in
the Contract.
Where it may be impracticable to use conventional rollers, the compaction
shall be carried out by appropriate mechanical means such as small vibratory
roller, plate compactor or power rammer. Care shall be taken to see that the
compaction equipment does not hit or come too close to any structural
member so as to cause any damage to them or excessive pressure against the
structure.
2.4.5.

Construction of embankment over ground incapable of supporting


construction equipment :
Where embankment is to be constructed across ground which will not
support the weight of repeated heavy loads of construction equipment, the
first layer of the fill may be constructed by placing successive loads of
material in a uniformly distributed layer of a minimum thickness required to
support the construction equipment as permitted by the Engineer. The
Contractor, if so desired by him, may also use suitable geosynthetic material
to increase the bearing capacity of the foundation. This exception to normal
procedure will not be permitted where, in the opinion of the Engineer, the
embankments could be constructed in the approved manner over such
ground by the use of lighter or modified equipment after proper ditching and
drainage have been provided. Where this exception is permitted, the selection
of the material and the construction procedure to obtain an acceptable layer
shall be the responsibility of the Contractor. The cost of providing suitable
traffic conditions for construction equipment over any area of the Contract

77

will be the responsibility of the Contractor and no extra payment will be made
to him. The remainder of the embankment shall be constructed as specified in
Clause 3.3.
2.4.6.

Embankment construction under water :


Where filling or backfilling is to be placed under water, only acceptable
granular material or rock shall be used unless otherwise approved by the
Engineer. Acceptable granular material shall consist of graded, hard durable
particles with maximum particle size not exceeding 75 mm. The material
should be non-plastic having uniformity coefficient of not less than 10. The
material placed in open water shall be deposited by end tipping without
compaction.

2.4.7.

Earthwork for high embankment :


In the case of high embankments, the Contractor shall normally use the
material from the specified borrow area. In case he desires to use different
material for his own convenience, he shall have to carry out necessary soil
investigations and redesign the high embankment at his own cost. The
Contractor shall then furnish the soil test data and design of high embankment
for approval of the Engineer, who reserves the right to accept or reject it.
If necessary, stage construction of fills and any controlled rates of filling
shall be carried out in accordance with the Contract including installation of
instruments and its monitoring.
Where required, the Contractor shall surcharge embankments or other areas of
fill with approved material for the periods specified in the Contract. If
settlement of surcharged fill . results in any surcharging material, which is
unacceptable for use in the Fill being surcharged, lying below formation level,
the Contractor shall remove the unacceptable material and dispose it as per
direction of the Engineer. He shall then bring the resultant level up to
formation level with acceptable material.

2.4.8.

Settlement period :
Where settlement period is specified in the Contract, the embankment shall
remain in place for the required settlement period before excavating for
abutment) wingwall, retaining wall, footings, etc., or driving foundation piles.
The duration of the required settlement period at each location shall be as
provided for in the Contract or as directed by the Engineer.

2.5.

Plying of Traffic
Construction and other vehicular traffic shall not use the prepared surface of
the embankment and/or subgrade without the prior permission of the Engineer.
Any damage arising out of such use shall, however, be made good by the
Contractor at his own expense as directed by the Engineer.

78

2.6.

Surface Finish and Quality Control of Work


The surface finish of construction of subgrade shall conform to the
requirements of Clause E16. Control on the quality of materials and works
shall be exercised in accordance with Clause E17.

2.7.

Subgrade Strength

2.7.1.

It shall be ensured prior to actual execution that the borrow area material to be
used in the subgrade satisfies the requirements of design CBR.

2.7.2.

Subgrade shall be compacted and finished to the design strength consistent


with other physical requirements. The actual laboratory CBR values of
constructed subgrade shall be determined on undisturbed samples cut out
from the compacted subgrade in CBR mould fitted with cutting shoe or on
remoulded samples, compacted to the field density at the Field moisture
content.

2.8.

Measurements for Payment


Earth embankment/subgrade construction shall be measured separately by
taking cross sections at intervals in the original position before the work
starts and after its completion and computing the volumes of earthwork in
cubic metres by the method of average end areas.
The measurement of fill material from borrow areas shall be the difference
between the net quantities of compacted Fill and the net quantities of suitable
material brought from roadway and drainage excavation. For this purpose, it
shall be assumed that one cu.m. of suitable material brought to site from road
and drainage excavation forms one cu.m. of compacted fill and all bulking or
shrinkage shall be ignored.
Construction of embankment under water shall be measured in Cu.m.
Construction of high embankment with specified material and in specified
manner shall be measured in cu.m.
Stripping including storing and reapplication of topsoil shall be measured in
cu.m.
Work involving loosening and recompacting of ground supporting
embankment/subgrade shall be measured in cu. m.
Removal of unsuitable material at embankment/subgrade foundation and
replacement with suitable material shall be measured in cu.m.

79

Scarifying existing granular/bituminous- road surface shall be measured in


square metres.
Dismantling and removal of existing cement concrete pavement shall be
measured vide MORTH Clause 202.6.
Filter medium and backfill material behind abutments, wing walls and other
retaining structures shall be measured as Finished work in position in cu.m.
2.9.

Rates

2.9.1.

The Contract unit rates for the items of embankment and subgrade
construction shall be paid in full for carrying out the required operations
including full compensation for :
i.

Cost of arrangement of land as a source of supply of material of


required quantity for construction unless provided otherwise in the Contract;

ii.

Setting out;

iii.

Compacting ground supporting embankment/subgrade except where removal


and replacement of unsuitable material or loosening and recompacting is
involved,

iv.

Scarifying or cutting continuous horizontal benches 300 mm wide on side


slopes of existing embankment and subgrade as applicable;

v.

Cost of watering or drying of material in borrow areas and/or embankment


and subgrade during construction as required;

vi.

Spreading in layers, bringing to appropriate moisture content and compacting


to Specification requirements;

vii. Shaping and dressing top and slopes of the


including rounding of corners,

embankment and subgrade

viii. Restricted working at sites of structures;


ix.

Working on narrow width of embankment and subgrade;

x.

Excavation in all soils from borrow pits/designated borrow areas including


clearing and grubbing and transporting the material to embankment and
subgrade site with all lifts and leads unless otherwise provided for in the
Contract;

xi.

All labour, materials, tools, equipment and incidentals necessary to complete


the work to the Specifications;

xii. Dewatering; and

80

xiii. Keeping the embankment/completed formation free of water as per MORTH


Clause 311.
2.9.2.

In case the Contract unit rate specified is not inclusive of all leads, the unit
rate for transporting material beyond the initial lead, as specified in the
Contract for construction of embankment and subgrade shall ..be inclusive of
full compensation for all labour, equipment, tools and incidentals necessary
on account of the additional haul or transportation involved beyond the
specified initial lead.

2.9.3.

MORTH Clause 301.9.5 shall apply as regards Contract unit rates for items of
stripping and storing top soil and of reapplication of topsoil. 3.9.4. Clause
301.9.2 shall apply as regards Contract unit rate for the item of loosening
and recompacting the embankment/subgrade foundation.
2.9.4. MORTH Clauses 301.9.1 and 3.8 shall apply as regards Contract
rates for items of removal of unsuitable material and replacement with suitable
material respectively.
2.9.5. The Contract unit rate for scarifying existing granular/bituminous road
surface shall be payment in full for carrying out the required operations
including full compensation for ail labour, materials, tools, equipment and
incidentals necessary to complete the work. This will also comprise of
handling, salvaging, stacking and disposing of the dismantled materials within
all lifts and upto a lead of 1000 m or as otherwise specified.
2.9.6. MORTH Clause 202.7 shall apply as regards Contract unit rate for
dismantling and removal of existing cement concrete pavement.

2.9.7.

The Contract unit rate for providing and laying filter material behind
abutments shall be payment in full for carrying out the required operations
including all materials, labour, tools, equipment and incidentals to complete
the work to Specifications.

2.9.8.

Clause 3.4.6 shall apply as regards Contract unit rate for construction of
embankment under water.

2.9.9.

Clause 3.4.7 shall apply as regards Contract unit rate for construction of high
embankment. It shall include cost of instrumentation, its monitoring and
settlement period, where specified in the Contract or directed by the Engineer.

81

Item No. 3

Box cutting the road surface to proper slope and camber for making abase of
road work including removing the excavated stuff and disposing on road or
side slope as directed upto 50 mt lead etc. complete as per technical
specification MORTH clause 301.

EXCAVATION FOR ROADWAY AND DRAINS

3.1

Scope
This work shall consist of excavation, removal and satisfactory disposal of all
materials necessary for the construction of roadway, side drains and
waterways in accordance with requirements of these Specifications and the
lines, grades and cross-sections shown in the drawings or as indicated by the
Engineer. It shall include the hauling and stacking of or hauling to sites of
embankment and subgrade construction, suitable cut materials as required, as
also the disposal of unsuitable cut materials in specified manner, trimming and
finishing of the road to specified dimensions or as directed by the Engineer.

3.2

Classification of Excavated Material

3.2.1

Classification :
All materials involved in excavation shall be classified by the Engineer
in the following manner :

(a)

Soil
This shall comprise topsoil, turf, sand, silt, loam, clay, mud, peat, black cotton
soil, soft shale or loose moorum, a mixture, a mixture of these and similar
material which yields to the ordinary application of pick, spade and or shovel,
rake or other ordinary digging implement. Removal of grade orany other
nodular material having dimension in any one direction not exceeding 75 mm
occurring in such strata shall be deemed to be covered under this category.

(b)

Ordinary Rock (not requireing blasting) This shall include :


(i)

(ii)

(iii)

rockt ypes such as laterites, shales and conglomerates, varieties of limestone


and sandstone etc., which may be quarrried or split with crow bars, also
including any rock which in dry state may be hard, requiring blasting but
which, when wet, becomes soft and manageable by means other than blasting:
macadam surfaces such as water bound and bitumen/tar bound; soling of roads
paths etc and hard core; compact moorum or stabilised soil requiring grafting
tool or pick or both and shovel, closely applied; gravel and cobble stone
having maximum dimension in any one direction between 75 and 30 mm.
lime concrete, stone masonry in lime mortar and brick work in lime/cement
mortar below ground level, reinforced cement concrete which may be broken
up with crow bars or picks and stone masonry in cement mortar below ground
level; and

82

(iv)
(c)

boulders which do not require blasting having miximum dimension in any


direction of more than 300 mm found lying loose on the surface or embeded in
river be, soil, talus, slope wash and terrace material of dissimilar origin.
Hard Rock ( Requiring Blasting )
This shall comprise :

(i)
(ii)
(iii)
(d)

any rock or cement concrete for the excavation of which the use of mechanical
plant and/ or blasting is required;
reinforced cement concrete (reinforcement cut through but not separated from
the concrete) below ground level; and
boulders requiring blasting.
Hard Rock (blasting prohibited)
Hard rock requiring blasting as described under (c) but where blasting is
prohibited for any reason and excavation has to be carried out by chiselling,
wedging or any other agreed method.

(e)

Marshy Soil
This shall include soils like soft clays and peats excavated below the orginal
ground level of marshes and swamps and soils excavated from other areas
requiring continuous pumping or bailing out of water.

3.2.2

Authority for Classification :

The classification ofexcavation shall be decided by the Enginer and his decision shall be final
and binding on the Contractor. Merely the use of explosives in excavation will
not be considedred as a reason for higher classification unless blasting is
clearly necessary in the opinion of the Engineer.
3.3

Construction Operations

3.3.1

Setting Out :

After the site has been cleared as per MORTH clause 201, the limits of excavation shall be
set out true to lines, curves, slopes grades andsections as shown on the
drawings or as directed by the Engineer. The Contractor shall provide all
labour survey instruments and materials such as strings, pegs , nails, bamboos,
stones, lime, mortar, concrete etc., required in connection with the setting out
of works and theestablishement of bench marks. The Contractor shall
beresponsible for the maintencance of bench marks and other marks and
stakes as longas in the opinion of the Engineer, they are required for the work.
3.3.2

Stripping and storing topsoil :

When so directed by the Engineer, the topsoil existing over the sites of excavation shall be
stripped to specifieddepths constituting Horizon A and stockpiled at
designated locations for re-use in covering embankment slopes, cut slopes,

83

berms and other disturbed areas where re-vegetation is desired. Prior to


stipping the topsoil, all trees, shrubs etc shall beremved along with therir roots,
with approval of the Engineer.
3.3.3

Excavation General
All excavations shall be carried out in conformity with the direction laid herein-under and in a manner approved by the Engineer. The work shall be so
done that the suitable materials available from excavation are satisfactorily
utilized as decided upon beforehand.
While planning or executing excavations, the Contractor shall take all
adequate precautions against soil erosion, water pollution etc. as per
MORTH Clause 306, and take appropriate drainage measures to keep
the site free of water in accordance with MORTH Clause 311.
The excavations shall conform to the lines, grades, side slopes and levels
shown on the drawings or as directed by the Engineer. The Contractor shall
not excavate outside the limits of excavation. Subject to the permitted
tolerances, any excess depth/ width excavated beyond the specified
levels/dimensions on the drawings shall be made good at the cost of the
Contractor with suitable material of characteristics similar to that removed and
compacted to the requirements of MORTH Clause 305.
All debris and loose material on the slopes of cuttings shall be removed. No
backfilling shall be allowed to obtain required slopes excepting that when
boulders or soft materials are encountered in cut slopes, these shall be
excavated to approved depth on instructions of the Engineer and the resulting
cavities filled with suitable material and thoroughly compacted in an approved
manner.
After excavation, the sides of excavated area shall be trimmed and the area
contoured to minimise erosion and ponding, allowing for natural drainage to
take place. If trees were removed, new trees shall be planted, as directed by
the Engineer. The cost .of planting new trees shall be deemed to be
incidental to the work.

3.3.4.

Methods, tools and equipment :


Only such methods, tools and equipment as approved by the Engineer shall be
adopted/used in the work. If so desired by the Engineer, the Contractor shall
demonstrate the efficacy of the type of equipment to be used before the
commencement of work.

3.3.5.

Marsh Excavation :
The excavation of soils from marshes/ swamps shall be carried out as per the
programme approved by the Engineer.

84

Excavation of marshes shall begin at one end and proceed in one direction
across the entire marsh immediately ahead of backfilling. The method and
sequence of excavating and backfilling shall be such as to ensure, to the extent
practicable, the complete removal or displacement of all muck from within the
lateral limits called for on the drawings or as staked by the Engineer, and to
the bottom of the marsh, Firm support or levels indicated.
3.3.6.

Excavation of road shoulders/verge/median for widening of pavement or


providing treated shoulders :
In works involving widening of existing pavements or providing treated
shoulders, unless otherwise specified, the shoulder/verge/median shall be
removed to their full width and to levels shown on drawings or as
indicated by the Engineer. While doing so, care shall be taken to see that no
portion of the existing pavement designated for retention is loosened or
disturbed. If the existing pavement gets disturbed or loosened, it shall be
dismantled and cut to a regular shape with -sides vertical and the
disturbed/loosened portion removed completely and relaid as directed by the
Engineer, at the cost of the Contractor:

3.3.7

Excavation for surface/sub-surface drains :


Where the Contract provides for construction of surface/sub-surface drains to
MORTH Clause 309, excavation for these shall be carried out in proper
sequence with other works as approved by the Engineer.

3.3.8

Sides
If slips, slides, over-breaks or subsidence occur in cuttings during the process
of construction, they shall be removed at the cost of the Contractor as ordered
by the Engineer. Adequate precautions shall be taken to ensure that during
construction, the slopes are not rendered unstable or give rise to recurrent
slides after construction. If
Finished slopes slide into the roadway
subsequently, such slides shall be removed and paid for at the Contract rate
for the class of excavation involved, provided the slides are not due to any
negligence on the part of the Contractor. The classification of the debris
material from the slips, slides etc. shall conform to its condition at the time of
removal and payment made accordingly regardless of its condition earlier.

3.3.9

Dewatering :
If water is met with in the excavations due to springs, seepage, rain or other
causes, it shall be removed by suitable diversions, pumping or bailing out and
the excavation kept dry whenever so required or directed by the Engineer.
Care shall be taken to discharge the drained water into suitable outlets as not
to cause damage to the works, crops or any other property. Due to any
negligence on the part of the Contractor, if any such damage is caused, it
shall be the sole responsibility of the Contractor to repair/restore to the
original condition at his own cost or compensate for the damage.

85

3.3.10.

Disposal of excavated materials :


All the excavated materials shall be the property of the Employer, The
material obtained from the excavation of roadway, shoulders, verges, drains,
cross drainage works etc., shall be used for filling up of (i) roadway
embankment, (ii) the existing pits in the right-of-way and (iii) for landscaping
of the road as directed by the Engineer, including levelling and spreading with
all lifts and lead upto 50 m and no extra payment shall be made for the same.
All hard materials, such as hard moorum, rubble, etc., not intended for use as
above shall be stacked neatly on specified land as directed by the Engineer
with all lifts and lead upto 50m.
Unsuitable and surplus material not intended for use within the lead specified
above shall also, if necessary, be transported with all lifts and lead beyond
initial 50 m, disposed of or used as directed by the Engineer.

3.3.11.

Backfilling :
Backfilling of masonry /concrete/hume pipe drain excavation shall be done
with approved material after concrete/ masonry/hume pipe is fully set and
carried out in such a way as not to cause undue thrust on any part of the
structure and/or not to cause differential settlement All space between the
drain walls and the side of the excavation shall be refilled to the original
surface making due allowance for settlement, in layers generally not
exceeding 150 mm compacted thickness to the required density, using suitable
compaction equipment such as mechanical tamper, rammer or plate compactor
as directed by the Engineer.

3.4.

Plying of Construction Traffic


Construction traffic shall not use the cut formation and finished subgrade
without the prior permission of the Engineer. Any damage arising out of such
use shall be made good by the Contractor at his own expense.

3.5.

Preservation of Property
The Contractor shall undertake all reasonable precautions for the protection
and preservation of any or all existing roadside trees, drains, sewers or other
sub-surface drains, pipes, conduits and any other structures under or above
ground, which may be affected by construction operations and which, in the
opinion of the Engineer, shall be continued in use without any change. Safety
measures taken by the Contractor in this respect, shall, be got approved
from the Engineer. However, if any of these objects is damaged by
reason of the Contractor's negligence, it shall be replaced or restored to the
original condition at his expense. If the Contractor fails to do so, within the
required time as directed by the Engineer or if, in the opinion of the Engineer,
the actions initiated by 'the Contractor to replace/restore the damaged
objects are not satisfactory, the Engineer shall arrange the replacement/

86

restoration directly through any other agency at the risk and cost of the
Contractor after issuing a prior notice to the effect.
3.6.

Preparation of Cut Formation


The cut formation, which serves as a subgrade, shall be prepared to receive
the sub-base/base course as directed by the Engineer.
Where the material in the subgrade (that is within 500 mm from the lowest
level of the pavement) has a density less than specified in Table 300-2, the
same shall be loosened to a depth of 500 mm and compacted in layers in
accordance with the requirements of MORTH Clause 305.
Any unsuitable material encountered in the subgrade level shall be removed
as directed by the Engineer and replaced with Suitable material compacted in
accordance with MORTH Clause 305.
In rocky formations, the surface irregularities shall be corrected and the levels
brought up to the specified elevation with granular base material as directed by
the Engineer, laid and compacted in accordance with the respective
Specifications for these materials. The unsuitable material shall be disposed of
in accordance with Clause 4.3.11. After satisfying the density requirements,
the cut formation shall be prepared to receive the subbase/base course in
accordance with MORTH Clauses 310 and 311 to receive the sub-base/base
course.

3.7.

Finishing Operations
Finishing operations shall include the work of properly shaping and dressing
all excavated surfaces.
When completed, no point on the slopes shall vary from the designated slopes
by more than 150 mm measured at right angles to the slope, except where
excavation is in rock (hard or soft) where no point shall vary more than 300
mm from the designated slope. In no case shall any portion of the slope
encroach on the roadway.
The finished cut formation shall satisfy the surface tolerances described in
Clause E16.
Where directed, the tops oil removed earlier and conserved (Clauses 4.3.2
and MORTH Clause 305.3.3) shall be spread over cut slopes, where feasible,
berms and other disturbed areas. Slopes may be roughened and moistened
slightly, prior to the application of topsoil, in order to provide satisfactory
bond. The depth of topsoil shall be sufficient to sustain plant growth, the usual
thickness being from 75 mm-to 100 mm.

87

3.8.

Measurements for Payment


Excavation for roadway shall be measured by taking cross-sections at
suitable intervals in the original, position .before the work starts and after its
completion and computing the volumes in cu. m. by the method of average
end areas for each class of material encountered. Where it is not feasible to
compute volumes by this method because of erratic location of isolated
deposits, the volumes shall be computed by other accepted methods.
At the option of the Engineer, the Contractor shall leave depth indicators
during excavations of such shape and size and in such Positions as directed
so as to indicate the original ground level as accurately as possible. The
contractor shall see that these remain intact till the final measurements are
taken.
For rock excavation, the overburden shall be removed first so that necessary
cross-sections could be taken for measurement. Where cross section
measurements could not be taken due to irregular configuration or where the
rock is admixed with other classes of materials, the volumes shall be
computed on the basis of stacks of excavated rubble after making 35 per cent
deduction therefrom. When volumes are calculated in this manner for
excavated material other than rock, deduction will be to the extent of 16 per
cent of stacked volumes.
Works involved in the preparation of cut formation shall be measured in units
indicated below :
(i)

Loosening and recompacting the loosened material at


subgrade

(ii)

Loosening and removal of unsuitable material and replacing Sq.m.


with a suitable material and compacting to required density
Preparing rocky subgrade
Sq.m
Stripping including storing and reapplication of topsoil
Cum
Disposal of surplus material beyond initial 1000 m lead
Cum

(iii)
(iv)
(v)

Sq.
m.

3.9

Rates

3.9.1.1

The Contract unit rates for the items of roadway and drain excavation shall be
payment in full for carrying out the operations required for the individual
items including full compensation for :

(i)
(ii)

Setting out ;
Transporting the excavated materials and depositing the same on sites of
embankments, spoil banks or stacking as directed within all lifts and lead upto
1000 m or as otherwise specified;
Trimming bottoms and slopes of excavation;
Dewatering;
Keeping the work free of water as per MORTH Clause 311; and

(iii)
(iv)
(v)

88

(vi)

All labour, materials, tools, equipment, safety measures, testing and


incidentals necessary to complete the work to Specifications.
Provided however where presplitting is prescribed to achieve a specified slope
in rock excavation, the same shall be paid for vide MORTH Clause 303.5.

3.9.1.2

The Contract unit rate for loosening and recompacting the loosened materials
at subgrade shall include full compensation for loosening to the specified
depth, including breaking clods, spreading in layers, watering where necessary
and compacting to the requirements.

3.9.1.3

Clause 4.9.1 and MORTH Clause 305.8 shall apply as regards Contract unit
rate for item of removal of unsuitable material and replacement with suitable
material respectively.

3.9.1.4

The Contract unit rate for item of preparing rocky subgrade as per Clause 4.6
shall be full compensation for providing, laying and compacting granular base
material for correcting surface irregularities including all materials, labour and
incidentals necessary to complete the work and all leads and lifts.

3.9.1.5

The Contract unit rate for the items of stripping and storing topsoil and of
reapplication of topsoil shall include full compensation for all the necessary
operations including all lifts, but leads upto 1000 m.

3.9.1.6

The Contract unit rate for disposal of Surplus earth from roadway and drain
excavation shall be full compensation for all labour, equipment, tools and
incidentals necessary on account of the additional haul or transportation
involved beyond the initial lead of 1000 m.

89

306

Item No. 4
Collecting, carting and stacking Coarse sand ( CBR not less
then 10 %) at site of work etc. complete.

307

4.1

Scope

This work shall consist of collecting carting & stacking coarse sand at site of
work as directed by Engineer In charge.
4.2

Material.
The material to used for the work shall be natural sharp clean graded sand
( CBR not less than 10 %).

4.2.1

The material should be free from organic or other deuterious constituents &
confirm the grading have given in Table 1000-2.

4.2.2

The material for the purpose shall be of approved quality. Any materials,
which are found inferior, shall be rejected and the contractor shall remove
such rejected materials from the site at his own cost. The material shall be
approved by the Executive Engineer or his authorised agent.

4.2.3

River or nala or sea sand required for the work shall be clear , sound,
properly, graded, free from organic materials silt clay etc. and shall be got
approved by the Engineer in charge. The sand shall be well graded.

4.3

Measurement for payment


The item shall be measured in cubic meter for the complete item of work.
Stacking shall be done by filling standard size boxes of 2mt. x 1.5mt. x 0.5mt.
size. No deduction shall be made for voids from the grade measurements.

4.4

Rate
The contract unit rate for collecting carting of stacking of coarse sand
including all materials labour tools. Equipments for construction and other
incidental cost necessary to complete the work.

90

308

Item No. 5
Collecting, carting and stacking stone dust at site of work
etc. complete.

309

5.1

Scope

This work shall consist of collecting carting & stacking stone dust at site of
work as directed by Engineer In charge.
5.2

Material.

5.2.1

The material to be used for the work shall be free from organic impurities &
have a plasticity index not grater than 6 .

5.2.2

The material should be graded within the limit indicated the Table 500-9.
Is Sieve(mm)
0.6
0.3
0.075

5.3

Cumulative percent passing


100
95-100
85-100

Measurement for payment


The item shall be measured in cubic meter for the complete item of work.
Stacking shall be done by filling standard size boxes of 2mt. x 1.5mt. x 0.5mt.
size. No deduction shall be made for voids from the grade measurements.

5.4

Rate
The contract unit rate for collecting carting of stacking of stone dust including
all materials labour tools. Equipments for construction and other incidental
cost necessary to complete the work.

91

310

Item No. 6
Collecting, carting and stacking machined crushed B.T.
metal 25mm 90mm size at site of work etc. complete.

311

6.1

Scope

This work shall consist of collecting carting & stacking machine crused BT
metal. Size 45mm to 90mm at site of work as directed by Engineer In charge.
6.2

Material.

6.2.1

Thefield of M.C.B.T. Metal shall be of approved quarry as shown on the


quarry chart as well as approved by the Executive Engineer prior to collection.

6.2.2

The M.C.B.T. metal shall be hard, tough,, sound, durable, black trap field
metal of close texture, free from decay and weathering. Each piece of the
stone shall be angular and roughly cubical in shape and round elongated or
flaky material shall be rejected. No round or oblong pebblesor angular chips
larger or smaller than specified size shall be allowed.

6.2.3

All unsound weathered or disintegrated stone obtained from the upper surface
layer of the quarry or other layer of boulders shall be rejected. The physical
requirement for standard size metall shall conform to the test results indicated
in given table.
Test
(a) Los Angeles
Abrasion Value
Aggregate impact
value
(b) Flakiness Index

Test Method
IS 2386 Part IV

Requirement
50 % (maximum)

IS 2386 Part IV
or Is 5640
IS 2386 Part I

40% (Maximum)
15% (maximum)

6.2.4

The M.C.B.T. metal shall be as nearly uniform in size as possible and shall
confirm to following minimum requirements of passing through the rings..

6.2.5

wherever and doubt exists as to whether the above requirement are satisfied in
whole or part. The contractor shall be screened the collection of M.C.B.T.
metal if so ordered by the Executive Engineer and for which no extra
payments shall be claimed by the contractor.
Any collection which does not fully satisfy the above requirements is liable to
be rejected altogether.

6.2.6

92

6.3

Measurement for payments.


The item shall be measured in cubic meter for the complete item of work as
directed by Engineer Incharge. Stacking shall be done by filling standard size
boxes of 2mt. x 1.5mt. x 0.5mt. size. No deduction shall be made for voids
from the grade measurements.

6.4

Rate
The contract unit rate for collecting carting & stacking of (45-90) B.T.
metal including all material labour tools equipments for construction & other
incidental cost necessary to complete the work.

93

312

Item No. 7
Spreading the stone aggregates for soling and W.B.M. in
two layers each of 100mm including filling the interstice forming the
surface to required grade and camber.

313

7.1

314

This work shall consist of spreading the stone aggregates for soling and
W.B.M. in two layers each of 100mm including filling the interstice forming
the surface to required grade and camber.

7.2

Construction Operation

Scope

The sub-base material of grading specified in the Contract shall be spread on


the prepared sub grade as approved by the Engineer.
When the sub-base material consists of combination of materials mentioned in
MORTH Clause 401.2.1, mixing shall be done mechanically by the mix-inplace method.
Manual mixing shall be permitted only where the width of laying is not
adequate for mechanical operations as in small-sized jobs. The equipment
used for mix-in-place construction shall be a rotavator or similar approved
equipment capable of mixing the material to the desired degree. If so desired
by the Engineer, trial runs with the equipment shall be carried out to establish
its suitability for the work.
Moisture content of the loose material shall be checked in accordance with IS :
2720 (Part 2) and suitably adjusted by sprinkling additional water from a truck
mounted or trailer mounted water tank and suitable for applying water
uniformly and a controlled quantities to variable widths of surface or other
means approved by the Engineer so that, at the time of compaction, it is from
1 percent above to 2 percent below the optimum moisture content
corresponding to IS : 2720 (Part 8). While adding water, due allowance shall
be made for evaporation losses, After water has been added, the material shall
be processed by mechanical or other approved means like disc harrows,
rotavators until the layer is uniformly wet.
7.3

Measurement for payments.


The item shall be measured in cubic meter for the complete item of
work as directed by Engineer Incharge.

7.4

Rate
The contract unit rate for Spreading the stone aggregates for soling and
W.B.M. in two layers each of 100mm including filling the interstice forming
the surface to required grade and camber including all material labour tools
equipments for construction & other incidental cost necessary to complete the
work.

94

315

Item No. 8
Spreading the blindage of road crust filling the gaps in
metal and leveling to camber and gradient.

316

8.1

317

This work shall consist of Spreading the blindage of road crust filling the gaps
in metal and leveling to camber and gradient.

7.3

Construction Operation

7.3.1

Spreading of material shall be started after the full supply in particular K M is


collected., measured and recorded in the measurement books. Permission of
the Engineering in charge shall be obtained before spreading.

7.3.2

It shall be seen that the formation is dressed to the required camber and grade.
If the blindage is to be spread over the metaled surface then the spreading
shall be uniform and as its has to act as binding surface it shall be used for
filling the interstices of metal and forming a smooth running surface as far as
possible.

8.3

Measurement for payments.

Scope

The item shall be measured in cubic meter for the complete item of
work as directed by Engineer Incharge.
8.4

Rate
The contract unit rate for collecting carting & stacking of (45-90) B.T. metal
including all material labour tools equipments for construction & other
incidental cost necessary to complete the work.

95

318

Item No. 9
Rolling and consolidation water bound macadam (except
laterite and kanker) including watering not exceeding 150mm thickness in
layers including binding materials including filling in dipression which
occures during the process (B) with Vibratory road roller exceeding 8
tonnes and not exceeding 12 tonnes.

319

9.1

320

This work shall consist Rolling and consolidation water bound macadam
(except laterite and kanker) including watering not exceeding 150mm
thickness in layers including binding materials including filling in dipression
which occures during the process (B) with Vibratory road roller exceeding 8
tonnes and not exceeding 12 tonnes.

7.4

Construction Operation

Scope

Rolling shall be carried out by vibratory roller of 8 to 12 tonnes capacity.


Rolling shall commence at the lower edge and proceed towards the upper edge
longitudinally for portions having unidirectional crossfall and super elevation
and shall commence at the edges and progress towards the centre for portions
having crossfall on both sides.
Each pass of the roller shall uniformly overlap not less than one-third of the
track made in the preceding pass. During rolling, the grade and crossfall
(camber) shall be checked and any high spots or depressions, which become
apparent, corrected by removing or adding fresh material. The speed of the
roller shall not exceed 5 km per hour.
Rolling shall be continued till the density achieved is at least 98 percent of the
maximum dry density for the material determined as per IS : 2720 (Part 8).
The surface of any layer of material on completion of compaction shall be
well closed, free from movement under compaction equipment and from
compaction planes, ridges, cracks or loose material. All those, segregated or
otherwise defective areas shall be made good to the full thickness of layer and
re-compacted.
9.3

Measurement for payments.


The item shall be measured in Smt for the complete item of work as
directed by Engineer Incharge.

9.4
321

Rate
The contract unit rate for Rolling and consolidation
water bound macadam (except laterite and kanker) including watering not
exceeding 150mm thickness in layers including binding materials including
filling in dipression which occures during the process (B) with Vibratory road
roller exceeding 8 tonnes and not exceeding 12 tonnes including all material
labour tools equipments for construction & other incidental cost necessary to
complete the work.

96

322

Item No. 10 Providing, laying, spreading and compacting graded stone


aggregates (machine cut) of size 75 micron - 53 mm from approved
quarry to wet mix macadam specifications as per mix design including
premixing the material with water to OMC in mechanical mix i.e. pug
mill / four bin feeder, storage silo of required capacity, carriage of mix
material by tipper to site, laying by mechanical paver in uniform layers to
achieve 200 mm thick layer compacting in layers of not more than 100
mm for base course on a well prepared sub base and compacting with
vibratory roller of 8 to 10 tonnes weight roller to achieve the desired
density including lighting, guarding, barricading and maintenance of
diversion etc. complete. as per technical specification MORTH clause 406.

323

10.1

Scope

This work shall consist of laying and compacting clean, crushed, graded
aggregate and granular material, premixed with water, to a dense mass on a
prepared subgrade / sub-base / base or existing pavement as the case may be in
accordance with the requirements of these specifications. The material shall be
laid in one or more layers as necessary to lines, grades and cross-sections
shown on the approved drawings or as directed by the Engineer.
The thickness of a single compacted Wet Mix Macadam layer shall not be less
than 75 mm. When vibrating or other approved types of compacting
equipment are used, the compacted depth of a single layer of the sub-base
course may be increased to 200 mm upon approval of the Engineer.
10.2

Materials

10.2.1

Aggregates

10.2.2

Physical requirements :
Coarse aggregates shall be crushed stone. If crushed gravel . shingle is used,
not less than 90 per cent by weight of the gravel. shingle pieces retained on
4.75 mm sieve shall have at least two fractured faces. The aggregates shall
conform to the physical requirements set forth in MORTH Table 400-10
below.
MORTH Table 400-10

Physical Requirements of Coarse Aggregates for


Wet Mix Macadam for Sub-base / Base Courses
Sr.
No.
1

Test
*Los
Angeles
Abrasion value

Test Method
IS : 2386 (Part 4)

97

Requirements
40 percent (Max.)

Sr.
No.

Test

Test Method

or
*Aggregate
Impact value
Combined
Flakiness
and
Elongation
indices (Total)

IS : 2386 (Part 4)
or IS : 5640
IS : 2386 (Part 1)

Requirements

30 percent (Max.)
30 percent (max.)

* Aggregate may satisfy requirements of either of the two tests.


** To determine this combined proportion, the flaky stone from a
representative sample should first be separated out. Flakiness index is
weight of flaky stone metal divided by weight of stone sample. Only the
elongated particles be separated out from the remaining (non-flaky) stone
metal. Elongation index is weight of elongated particles divided by total
non-flaky particles. The value of flakiness index and elongation index so
found are added up.
If the water absorption value of the coarse aggregate is greater than 2
percent, the soundness test shall be carried out on the material delivered to
site as per IS : 2386 (Part 5).
10.2.1.2

Grading requirements :
The aggregates shall conform to the grading given in MORTH Table 400-11.

MORTH Table 400-11


Grading Requirements of Aggregates for Wet Mix Macadam
IS Sieve

Designation

53.00
45.00
26.50
22.40
11.20
4.75
2.36
600.00
75.00

mm
mm
mm
mm
mm
mm
mm
micron
micron

Percent by
weight passing
the IS sieve
100
95-100
60-80
40-60
25-40
15-30
8-22
0-8

Materials finer than 425 micron shall have Plasticity Index (PI) not
exceeding 6.

98

The final gradation approved within these limits shall be well graded from
coarse to fine and shall not vary from the low limit on one sieve to the high
limit on the adjacent sieve or vice versa.

10.3

Construction Operations

10.3.1

Preparation of base : MORTH Clause 404.3.1 shall apply.

10.3.2

Provision of lateral confinement of aggregates :


While constructing wet mix macadam, arrangement shall be made for the
lateral confinement of wet mix. This shall be done by laying materials in
adjoining shoulders along with that of wet mix macadam layer and following
the sequence of operations described in MORTH Clause 407.4.1.

10.3.3

Preparation of mix

Wet Mix Macadam shall be prepared in an approved mixing plant of suitable capacity having
provision for controlled addition of water and forced / positive mixing
arrangement like pugmill four bin feeder or pan type mixer of concrete
batching plant. For small quantity of wet mix work, the Engineer may permit
the mixing to be done in concrete mixers.
Optimum moisture for mixing shall be determined in accordance with IS :
2720 (Part 8) after replacing the aggregate fraction retained on 22.4 mm
sieve with material of 4.75 mm to 22.4 mm size. While adding water, due
allowance should be made for evaporation losses. However, at the time of
compaction, water in the wet mix should not vary from the optimum value by
more than agreed limits. The mixed material should be uniformly wet and no
segregation should be permitted.
10.3.4

Spreading of mix :
Immediately after mixing, the aggregates shall be spread uniformly and evenly
upon the prepared subgrade / sub-base / base in required quantities. In no case
should these be dumped in heaps directly on the area where these are to be laid
nor shall their hauling over a partly completed stretch be permitted.
The mix may be spread either by a paver finisher or motor grader as directed
by Engineer-in-Charge. For portions where mechanical means can not be used,
manual means as approved by the Engineer shall be used. The motor grader
shall be capable of spreading the material uniformly all over the surface. Its
blade shall have hydraulic control suitable for initial adjustments and
maintaining the same so as to achieve the specified slope and grade.

99

The paver finisher shall be self-propelled, having the following features :(i) Loading hoppers and suitable distribution mechanism.
(ii) The screed shall have tamping and vibrating arrangement for initial
compaction to the layer as it is spread without rutting or otherwise marring
the surface profile.
(iii)The paver shall be equipped with necessary control mechanism so as to
ensure that the finished surface is free from surface blemishes.
The surface of the aggregate shall be carefully checked with templates and all
high or low spots remedied by removing or adding aggregate as may be
required. The layer may be tested by depth blocks during construction. No
segregation of larger and fine particles should be allowed. The aggregates as
spread should be of uniform gradation with no pockets of fine materials.
10.3.5

Compaction :
After the mix has been laid to the required thickness, grade and cross fall /
camber the same shall be uniformly compacted, to the full depth with
approved roller. For a compacted single layer upto 200 mm, the compaction
shall be done with the help of vibratory roller of 8 to 10 tones capacity. The
speed of the roller shall not exceed 5 km/h.
In portions having unidirectional cross fall / super elevation, rolling shall
commence from the lower edge and progress gradually towards the upper
edge. Thereafter, roller should progress parallel to the centre line of the road,
uniformly over-lapping each preceding track by at least one third width until
the entire surface has been rolled. Alternate trips of the roller shall be
terminated in stops at least 1 m away from any preceding stop.
In portions in camber, rolling should begin at the edge with the roller running
forward and backward until the edges have been firmly compacted. The roller
shall then progress gradually towards the centre parallel to the centre line of
the road uniformly overlapping each of the preceding track by at least onethird width until the entire surface has been rolled.
Any displacement occurring as a result of reversing of the direction of a roller
of from any other cause shall be corrected at once as specified and / or
removed and made good.
Along forms, kerbs, walls or other places not accessible to the roller, the
mixture shall be thoroughly compacted with mechanical tampers or a plate
compactor, skin patching of an area without scarifying the surface to permit
proper bonding of the added material shall not be permitted.
Rolling should not be done when the subgrade is soft or yielding or when it
causes a wave-like motion in the sub-base / base course or subgrade. If
irregularities develop during rolling which exceed 12 mm when tested with a 3
metre straight edge, the surface should be loosened and premixed material
added or removed as required before rolling again so as to achieve a uniform

100

surface conforming to the desired grade and crossfall. In no case should the
use of unmixed material be permitted to make up the depressions.
Rolling shall be continued till the density achieved is at least 98 percent of the
maximum dry density for the material as determined by the method outlined in
IS: 2720 (Part 8).
After completion, the surface of any finished layer shall be well-closed free
from movement under compaction equipment or any compaction planes,
ridges, cracks and loose material. All loose, segregated or otherwise defective
areas shall be made good to the full thickness of the layer and recompacted.
10.3.6

Setting and drying :


After final compaction of wet mix macadam course, the road shall be allowed
to dry for 24 hours.

10.4

Opening to Traffic
Preferably no vehicular traffic of any kind should be allowed on the finished
wet mix macadam surface till it has dried and the wearing course laid.

10.5

Surface Finish and Quality Control of Work

10.5.1

Surface evenness :The surface finish of construction shall conform to the requirements of Clause
E16 of Quality Control Section.

10.5.2

Quality Control :Control on the quality of materials and works shall be exercised by the
Engineer in accordance with Section E.

10.6

Rectification of Surface Irregularity


Where the surface irregularity of the wet mix macadam course exceeds the
permissible tolerances or where the course is otherwise defective due to
subgrade soil getting mixed with the aggregates, the full thickness of the layer
shall be scarified over the affected area, reshaped with added premixed
material or removed and replaced with fresh premixed material as applicable
and recompacted in accordance with Clause 7.3. The area treated in the
aforesaid manner shall not be less than 5 m long and 2 m wide. In no case
shall depressions be filled up with unmixed and ungraded material or fines.

10.7

Arrangement for Traffic


During the period of construction, arrangement of traffic shall be done as per
direction of Engineer in Charge.

10.8

Measurements for Payment

101

Wet mix macadam shall be measured as finished work in position in M.T.


10.9

Rates
The contract unit rate for wet mix macadam shall be payment in full for
carrying out the required operations including full compensation for all
components listed in MORTH Clause 401.8.

102

324

Item No. 11 Collecting, carting and stacking machined crushed B.T.


metal 20 mm 40 mm size at site of work etc. complete.

325

11.1

Scope

This work shall consist of collecting carting & stacking machine crused BT
metal. Size 20 mm to 40 mm at site of work as directed by Engineer In charge.
6.3

Material.

6.3.1

Thefield of M.C.B.T. Metal shall be of approved quarry as shown on the


quarry chart as well as approved by the Executive Engineer prior to collection.

6.3.2

The M.C.B.T. metal shall be hard, tough,, sound, durable, black trap field
metal of close texture, free from decay and weathering. Each piece of the
stone shall be angular and roughly cubical in shape and round elongated or
flaky material shall be rejected. No round or oblong pebblesor angular chips
larger or smaller than specified size shall be allowed.

6.3.3

All unsound weathered or disintegrated stone obtained from the upper surface
layer of the quarry or other layer of boulders shall be rejected. The physical
requirement for standard size metall shall conform to the test results indicated
in given table.
Test
(c) Los Angeles
Abrasion Value
Aggregate impact
value
(d) Flakiness Index

6.3.4

Test Method
IS 2386 Part IV

Requirement
50 % (maximum)

IS 2386 Part IV
or Is 5640
IS 2386 Part I

40% (Maximum)
15% (maximum)

The M.C.B.T. metal shall be as nearly uniform in size as possible and shall
confirm to following minimum requirements of passing through the rings..

Sieve Size % by weight passing through


50
40
20
10
6.3.5

95-100
65-90
0-10
0-5

wherever and doubt exists as to whether the above requirement are satisfied in
whole or part. The contractor shall be screened the collection of M.C.B.T.
103

6.3.6
11.3

metal if so ordered by the Executive Engineer and for which no extra


payments shall be claimed by the contractor.
Any collection which does not fully satisfy the above requirements is liable to
be rejected altogether.
Measurement for payments.
The item shall be measured in cubic meter for the complete item of work as
directed by Engineer Incharge. Stacking shall be done by filling standard size
boxes of 2mt. x 1.5mt. x 0.5mt. size. No deduction shall be made for voids
from the grade measurements.

11.4

Rate
The contract unit rate for collecting carting & stacking of (20-40 B.T.
metal including all material labour tools equipments for construction & other
incidental cost necessary to complete the work.

104

Item No. 12 Collecting, carting and stacking machined crushed B.T. kapachi 12 mm 20
mm size at site of work etc. complete.
326

12.1

Scope

This work shall consist of collecting carting & stacking machine crused BT
kapachi. Size 12 mm to 20 mm at site of work as directed by Engineer In
charge.
6.4

Material.

6.4.1

Thefield of M.C.B.T. Kapachi shall be of approved quarry as shown on the


quarry chart as well as approved by the Executive Engineer prior to collection.

6.4.2

The M.C.B.T. kapachi shall be hard, tough,, sound, durable, black trap field
kapachi of close texture, free from decay and weathering. Each piece of the
stone shall be angular and roughly cubical in shape and round elongated or
flaky material shall be rejected. No round or oblong pebblesor angular chips
larger or smaller than specified size shall be allowed.

6.4.3

All unsound weathered or disintegrated stone obtained from the upper surface
layer of the quarry or other layer of boulders shall be rejected. The physical
requirement for standard size kapachi shall conform to the test results
indicated in given table.
Test
(e) Los Angeles
Abrasion Value
Aggregate impact
value
(f) Flakiness Index

6.4.4

Test Method
IS 2386 Part IV

Requirement
50 % (maximum)

IS 2386 Part IV
or Is 5640
IS 2386 Part I

40% (Maximum)
15% (maximum)

The M.C.B.T. kapachi shall be as nearly uniform in size as possible and shall
confirm to following minimum requirements of passing through the rings..

Sieve Size % by weight passing through


22.5
21
12.5
10
4.75
6.4.5

100
90-100
70-90
20-40
0-5

wherever and doubt exists as to whether the above requirement are satisfied in
whole or part. The contractor shall be screened the collection of M.C.B.T.

105

6.4.6
12.3

kapachi if so ordered by the Executive Engineer and for which no extra


payments shall be claimed by the contractor.
Any collection which does not fully satisfy the above requirement is liable to
be rejected altogether.
Measurement for payments.
The item shall be measured in cubic meter for the complete item of work as
directed by Engineer Incharge. Stacking shall be done by filling standard size
boxes of 2mt. x 1.5mt. x 0.5mt. size. No deduction shall be made for voids
from the grade measurements.

12.4

Rate
The contract unit rate for collecting carting & stacking of (12-20 B.T.
kapachi including all material labour tools equipments for construction &
other incidental cost necessary to complete the work.

106

327

Item No. 13 Collecting, carting and stacking machined crushed B.T.


Grit 6 mm 10 mm size at site of work etc. complete.

13.1

Scope
This work shall consist of collecting carting & stacking machine crused BT
Grit. Size 6 mm to 10 mm at site of work as directed by Engineer In charge.

6.5

Material.

6.5.1

The field of M.C.B.T. Grit shall be of approved quarry as shown on the quarry
chart as well as approved by the Executive Engineer prior to collection.

6.5.2

The M.C.B.T. Grit shall be hard, tough,, sound, durable, black trap field Grit
of close texture, free from decay and weathering. Each piece of the stone shall
be angular and roughly cubical in shape and round elongated or flaky material
shall be rejected. No round or oblong pebblesor angular chips larger or smaller
than specified size shall be allowed.

6.5.3

All unsound weathered or disintegrated stone obtained from the upper surface
layer of the quarry or other layer of boulders shall be rejected. The physical
requirement for standard size Grit shall conform to the test results indicated in
given table.
Test
(g) Los Angeles
Abrasion Value
Aggregate impact
value
(h) Flakiness Index

6.5.4

Test Method
IS 2386 Part IV

Requirement
50 % (maximum)

IS 2386 Part IV
or Is 5640
IS 2386 Part I

40% (Maximum)
15% (maximum)

The M.C.B.T. Grit shall be as nearly uniform in size as possible and shall
confirm to following minimum requirements of passing through the rings..

Sieve Size % by weight passing through


10
4.75
150
13.2.5

100
85-100
10-30

wherever and doubt exists as to whether the above requirement are satisfied in
whole or part. The contractor shall be screened the collection of M.C.B.T. Grit
if so ordered by the Executive Engineer and for which no extra payments shall
be claimed by the contractor.

107

13.2.6

Any collection which does not fully satisfy the above requirement is liable to
be rejected altogether.

13.3

Measurement for payments.


The item shall be measured in cubic meter for the complete item of work as
directed by Engineer Incharge. Stacking shall be done by filling standard size
boxes of 2mt. x 1.5mt. x 0.5mt. size. No deduction shall be made for voids
from the grade measurements.

13.4

Rate
The contract unit rate for collecting carting & stacking of (6-10 B.T.
Grit including all material labour tools equipments for construction & other
incidental cost necessary to complete the work.

108

328

Item No. 14 Collecting, carting and stacking bituminous 80-100 grade at


site of work including stacking etc. complete.

1.

Bitumen shall be procured directly from refinery by the Contractor. The


contractor shall make adequate arrangements for storing bulk asphalt at site.
The contractor will produce in original the bill of Refinery, all the gate passes
issued by the refinery and the number of transport tanker. The contractor will
also produce the Test Certificate regarding the grade of asphalt issued by
Refinery. The Department does not undertake to furnish Pn form (regarding
Sales Tax Concessions) for purchase of asphalt.

2.

On receipt and storage of bitumen. The bitumen shall be got tested in GERI
leboratory or other Laboratories approved by Department.

3.

The contractor will establish on site of work site laboratory in area not less
than 25 sq.m with pucca construction and equipped; with instruments to
enable to carry out the following tests.
1.
Penetration test as per I.S. 1203.
2.
Softing point test as per I.S.1204.
3.
Ductility test as I.S.1208.
4.
Viscocity test as per I.S.1206.
5.
Specification Gravity test as for I.S. 1202.
The above instruments should be certified as per I.S. standard, the same
should be regularly calibrated and should be maintained in efficient condition.

4.

The Registers for use, temperature and other quality requirements of bitumen
will be maintained at Plant site. The registers will be printed, as per formats
approved by Department and authorised for use by the Engineer incharge. The
entries in the registers will be made by the departmental representative and
signed by the contractor or his authorised representative.

5.

Frequency of Tests :
As regards quality of binder, three tests of one sample per two tankers will be
done on plant site. The tests will be carried out as per Table 900-4 of Section
900 of MORTH standard specifications. The frequency of use of
specifications will be as under.
No of Tanker
No of Tests.
Upto 10
One
10 to 20
Two
20 to 50
Three
50 to 100
Four
For further every 50 tanker
One

6.

The contract unit rate of supplying bitumen shall include


1.
Obtaining the bitumen from the Refinery
2.
Transporting to site.
3.
Storing, stacking and protecting
4.
Keeping record of supply and use and

7.

Measurement for Payment


The Payment shall be made on tonnage basis.

109

Item No. 15 Laying of built up spray grout base course in one layer with
bitumen at rate of 15 kg per 10 sqm and tack coat at rate of 5 kg per 10 sqm
with 0.50cum of stone aggregates per 10 sqm and using 0.13 cum. Of key
aggregates per 10 sqm excluding cost of materials bitumen and including
rolling and consolidationn et. Complete.
15.1

Scope
This work shall consists of a two layer composite construction of compacted
crushed coarse agrregates with application of bituminous binder aftereach
layer, and with key aggregates placed on top of the second layer, in
accordance with the requirements of these specification, to serve as base
course and in conformity with the lines, grades and cross- sections shown on
the drawings or as directed by the Engineer. The thickness of the course shall
be 75mm.
Built up spray grout shall be used in single course in pavement structure.

15.2

Materials

15.2.1

BITUMEN :
Clause 504.2.1 shall apply, where permitted by the engineer,an appropriate
grade of emulation complying with IS 8887 may be used.

15.2.2

Aggregates :
The coarse aggregate shall conform to Clause 504.2.2
The aggregate shall satisfy the physical requirements act out in Table 500-3.
The coarse and key aggregates for built-up spray grout shall conform to the
grading given in Table .
GRADING REQUIREMENTS FOR COARSE AND KEY AGGREGATES
FOR BUILT UP SPRAY GROUT.
Cumulative per cent by weight of total aggregate
Is Sieve
passing
Designation (mm)
Coarse Aggregate
Key Aggregate
53.0
100
26.5
40-75
22.4
100
13.2
0-20
40-75
5.6
0-20
2.8
0-5
0-5

15.3

Construction Operation

15.3.1

Weather and seasonal limitation :


The provisions of Clause 501.5.1 shall apply.

110

15.3.2

Equipment :
The provisions of Clause 505.3.2 shall apply.

15.3.3

Preparation of Base :
The base on which the built-up spray grout course is to be laid shall be
prepared, shaped and compacted to the specified lines, grades and crosssection inn accordance with Clause 501- 902 as appropriate. A prime coat
shall be applied in accordance with Clause 502 with approved primer as
directed by Engineer.

15.3.4

Tack coat :
A tack coat shall be applied in accordance with the procedure described in
Clause 503, as directed by Engineer.

15.3.5

Spreading and rolling coarse aggregates for the first layer :


Immediately after the application of prime or tack coat, the clean, dry and dust
free coarse aggregates shall be spread uniformly and evently, by mechanical
means, at the rate of 0.5 cu.m per 10 sq.m.area.
Immediately after spreading of the aggregates, the entire surface shall be
rolled with an 8-10 tonnes smooth wheel steel roller. Rolling shall commence
at the edges and progress towards the centre except in superelevated and unitdirectional cambered portions where it shall proceed from the lower edge to
the higher edge. Each pass of the roller shall uniformly overlap not less than
one-third of the track made in the preceding pass.
The surface of the layer shall be carefully checked, after rolling with a temple
and straight edge and shall be within the tolerances specified, andany
deficiencies corrected by reworking and recompacting the layer.
Care shall be taken not to over-compact the layer.

15.3.6

Application of binder First Spray :


The binder shall be heated to the temperature appropriate to the grade of
bitumen approved by the Engineer and sprayed on the aggregate at the rate of
15kg / 10 sqm (measured in terms of residual bitumen content) at a uniform
rate of spray by mechanical sprayers capable of spraying bitumen uniformly at
the specified rates and temperatures. Excessive deposits of binder caused by
stopping or starting of the sprayers or through leakage or for any other reason
shall be removed and made good.

111

15.3.7

Spreading and rolling of coarse aggregate for the second layer :


Immediately after the first application of the binder, the second layer of coarse
aggregates shall be spread and rolled in accordance with the procedure
detailed in Clause 506.3.5

15.3.8

Application of binder-second spray:


The second ;aggregate layer shall then the sprayed with binder at the rate of
15 kg/ 10 sq.m (measured in terms of residual bitumen content) in accordance
with Clause 506.3.6.

15.3.9

Application of key aggregate :


Immediately after the second application of binder, key aggregates shall be
spread uniformly and evenly, preferably by mechanical means, at the rate of
0.13cu.m /10 sq.m so as to cover the surface completely. The key aggregate
shall be clean, dry and free form dust and deleterious matter. If necessary, the
surface shall be swept to ensure uniform application of the key aggregates.
The entire surface shall then be rolled with an 8-10 tonnes smooth wheel steel
roller in accordance with Clause 506.3.5. While rolling is in progress,
additional key aggregates, where required, shall be spread by hand. Rolling
shall continue until the entire course is thoroughly compacted and the key
aggregates are firmly in position.

15.4

Surface finish and Quality Control :


The surface finish of construction shall conform to the requirements of Clause
902.All materials shall comply with the requirements of the relevant
provisions in Section 900 of the Specifications.

15.5

Final Surfacing :
The built up spray grout shall be provided with final surfacing within a
maximum of forty eight hours. If there is to be any delay, the course shall be
covered by seal coat to the requirement of Clause 513 before it is open to
traffic. Where the seal coatis required as a result of the selected method of
performing this operation, then it shall be considered incidental to the work
and shall not be paid for separately.

15.6

Arrangements for Traffic :


During the period of construction, arrangement for traffic shall be made in
accordance with the provisions of Clause 112.

15.7

Measurements for Payment


Build-kup spray grout shall be measured as finished work in square meters.

15.8

Rate
The contract unit rate for Built-up spray grout shall be payment in fully for
carrying out the required operations as specified. The rate shall include for, but
not necessarily be limited to the components listed in Clause 501.8.8.2(i) to
(xi).

112

329

Item No. 16 Providing and laying tack coat using bituminous binder @
rate 2.5 kg 10 sq.m of road surface using bitumen pressure sprayer etc.
complete including cost of asphalt .
16.1

16.1.1

TACK COAT

Scope
This work shall consist of the application of a single coat of low viscosity
liquid bituminous material to an existing bituminous road surface preparatory
to the superimposition of a bituminous mix, when specified in the Contract or
instructed by the Engineer.

16.1.2

Materials

16.1.2.1

Binder
The binder used for tack coat shall be bitumen emulsion complying with IS
8887 of a type and grade as specified in the Contract or as directed by the
Engineer. The use of cutback bitumen as per IS 217 shall be restricted only for
sites at sub-zero temperatures or for emergency applications as directed by the
Engineer.

16.1.3

Weather and Seasonal Limitations


Bituminous material shall not be applied to a wet surface or during a dust
storm or when the weather is foggy, rainy or windy or when the temperature in
the shade is less than 100C. Where the tack coat consists of emulsion, the
surface shall be slightly damp, but not wet. Where the tack coat is of cutback
bitumen, the surface shall be dry.

16.1.4

Construction

16.1.4.1

Equipment
The tack coat distributor shall be a self propelled or towed bitumen pressure
sprayer, equipped for spraying the material uniformly at a specified rate. Hand
spraying of small areas, inaccessible to the distributor, or in narrow strips,
shall be sprayed with a pressure hand sprayer, or as directed by the Engineer.

16.1.4.2

Preparation of base
The surface on which the tack coat is to be applied shall be clean and free
from dust, dirt, and any extraneous material) and be otherwise prepared in
accordance with the requirements of MORTH Clauses 501.8 and E16
Specifications for Quality Control as appropriate. (Immediately before the
application of the tack coat, the surface shall be swept clean with mechanical
broom, and high pressure air jet, or by other means as direction by the
Engineer.)

113

16.1.4.3

Application of tack coat


The application of tack coat shall be at the rate specified in the Contract, and
shall be applied uniformly) If rate of application of Tack Coat is not specified
in the contract then it shall be at the rate specified in MORTH Table 500-2.
(The normal range of spraying
Type of Surface
i)
ii)
iii)
iv)
a)
b)

Normal bituminous surfaces


Dry and hungry bituminous surfaces
Granular surfaces treated with primer
Non bituminous surfaces
Granular base (not primed)
Cement concrete pavement

Quantity of liquid bituminous


material in Kg per sq.m. area.
0.20 to 0.25
0.25 to 0.30
0.25 to .30
0.35 to 0.40
0.30 to 0.35

Temperature for a bituminous emulsion shall be 200C to 700C and for a


cutback, 500C to 800C if RC-70/MC-70 is used). Where a geosynthetic is
proposed for use, the provisions of MORTH Clauses 703.2 and 703.4.4 shall
apply. (The method of application of the tack coat will depend on the type of
equipment to be used, size of nozzles, pressure at the spray bar, and speed of
forward movement. The Contractor shall demonstrate at a spraying trial, that
the equipment and method to be used is capable of producing a uniform spray,
within the tolerances specified.

16.1.4.4

Where the material to receive an overlay is a freshly laid bituminous layer,


that has not been subjected to traffic, or contaminated by dust, a tack coat is
not mandatory where the overlay is completed within two days.
Curing of tack coat
The tack coat shall be left to cure until all the volatiles have evaporated before
any subsequent construction is started. (No plant or vehicles shall be allowed
on the tack coat other than those essential for the construction)
16.1.5

Quality Control of Work

For control of the quality of materials supplied and the works carried out, the
relevant provisions of Section E Specifications for Quality Control shall apply.
16.1.6
Arrangements for Traffic
During the period of construction, arrangements for traffic shall be made in
accordance with the provisions of MORTH Clause 112.
16.1.7
Measurement for Payment
Tack coat shall be measured in terms of surface area of application in square
meters
16.1.8

Rate
The rate quoted by the contractor for providing and laying tack coat as using
bituminous binder at rate of 2.5 kg /10 sq.mt.

114

330

Item No.17 Providing and laying bituminous macadam 50 mm


compacted thickness using specified graded crushed Black trap stone
aggregate as per MORTH gradation specifications using 80/100 bulk
bitumen for mixing at the rate of 3.5% (35 Kg./MT) by hot mix process
and hot laid process, using sencer paver finisher to the required camber
and grade and rolling with vibratory roller to achive desired density
including cost of clearing using mechanical cleaner & collecting dust
vaccume cleaner of required capacity disposing of the stuff withing 3 km
lead as directed and using fier wood, oil, kerosene, labour charges and
hire charges of the required machinery etc. complete.
17.2

17.2.1

BITUMINOUS MACADAM.

Scope
This work shall consist of construction in a single course having 50mm to
100mm thickness or in multiple courses of compacted crushed aggregates
premixed with a bituminous binder on a previously prepared base to the
requirements of these Specifications. Bituminous macadam is more open
graded than the dense graded bituminous materials described in MORTH
Clauses 507, 508 and 509.

17.2.2

Materials

17.2.2.1

Bitumen
The bitumen shall be paving bitumen of Penetration Grade complying with
Indian Standard Specifications for Paving Bitumen IS : 73, and of the
penetration indicated in MORTH Table 500 4.

17.2.2.2

Coarse aggregates
The coarse aggregates shall consist of crushed rock, crushed gravel or other
hard material retained on the 2.36 mm sieve. They shall be clean, hard,
durable, of cubical shape, free from dust and soft or friable matter, organic or
other deleterious matter. Where the Contractor's selected source of aggregates
have poor affinity for bitumen, as a condition for the approval of that source,
the bitumen shall be treated with approved anti-stripping agents, as per the
manufacturers recommendations, without additional payment. Before
approval of the source, the aggregates shall be tested for stripping.
The aggregates shall satisfy the physical requirements set forth in MORTH
Table 500-3. Where crushed gravel is proposed for use as aggregate, not less
than 90% by weight of the crushed material retained on the 4.75 mm sieve
shall have at least two fractured faces.

17.2.2.3

Fine aggregates
Fine aggregates shall consist of crushed or naturally occuring material, or a
combination of the two, passing 2.36 mm sieve and retained on 75 micron

115

sieve. They shall be clean, hard, durable, dry and free from dust, and soft or
friable matter, organic or other deleterious matter.
MORTH TABLE 500-3.
PHYSICAL REQUIREMENTS FOR COARSE AGGREGATES
FOR BITUMINOUS MACADAM
Property
Cleanliness
Particle shape
Strength
Durability
Water Absorption
Stripping
Water Sensitivity
Notes :1.
sample)
3.
7.

17.2.2.4

Test
Grain size analysis
Flakiness and Elongation Index
(Combined)
Los Angles Abrasion Value
Aggregate Impact Value
Soundness
Sodium Sulphate
Magnesium Sulphate
Water absorption
Coating and Stripping of
Bitumen
Aggregate Mixtures
Retained Tensile Strength

Specification
Max 5% passing 0.075 mm sieve
Max 30 %
Max 40%
Max 12 %
Max 18 %
Max 2 %
Minimum retained coating
95%
Min 80 %

IS ; 2386 Part 1
4.
IS ; 2386 Part 5
2.
IS ; 2386 Part 1
5.
IS ; 2386 Part 3
(the elongation test to be done only on non-flaky aggregates in the
IS ; 2386 Part 4*
6.
IS ; 6241
The water sensitivity test is only to be carried out if the minimum retained
Coating in the stripping test is less than 95%.
Aggregate may satisfy requirements of either of these two tests.
Aggregate grading and binder content
When tested in accordance with IS : 2386 Part 1 (wet sieving method), the
combined aggregate grading for the particular mixture shall fall within the
limits shown in MORTH Table 500-4 for the grading specified in the
Contract. The type and quantity of bitumen, and appropriate thickness, are also
indicated for each mixture type.

17.2.2.5

Proportioning of Material
The aggregates shall be proportioned and blended to produce a uniform
mixture complying with the requirements of MORTH Table 500-4. The binder
content shall be within a tolerance of 0.3 per cent by weight of total mixture
when individual specimens are taken for quality control tests in accordance
with the provisions of Section E.

17.2.3

Construction Operations.

17.2.3.1

Weather and seasonal limitations :


116

The provisions of MORTH Clause 501.5.1 shall apply.


MORTH TABLE 500-4
COMPOSITION OF BITUMINOUS MACADAM
Mix designation
Nominal aggregate
size Layer thickness
IS Sieve (mm)

19 mm
50 75 mm
Cumulative % by weight of total
aggregate passing

45
37.5
26.5
19
13.2
4.75
2.36
0.3
0.075
Bitumen content, % by
weight of total mixture
Bitumen grade

100
90-100
56-88
16-36
4-19
2-10
0-8
3.3 3.5
35 to 90

Notes ; 1.
Appropriate bitumen contents for conditions in cooler areas of
India may be up to 0.5 % higher subject to the approval of the Engineer.
17.2.3.2

Preparation of the base


The base on which bituminous macadam is to be laid shall be prepared, shaped
and compacted to the required profile in accordance with MORTH Clause
501.8 and E.16.3 as appropriate, and a prime coat, shall be applied in
accordance with MORTH Clause 502 where specified, or as directed by the
Engineer.
17.2.3.3

Tack Coat

A tack coat in accordance with MORTH Clause 503 shall be applied as


required by the Contract documents, or as directed by the Engineer.
17.2.3.4

Preparation and transportation of the mixture


The provisions of MORTH Clauses 501.3 and 501.4 shall apply.

17.2.3.5

Spreading
The provisions of MORTH Clauses 501.5.3 shall apply.
MORTH TABLE 500-5. MANUFACTURING AND ROLLING
TEMPERATURES

117

Bitumen
Penetration
35
65
90
17.2.3.6

Bitumen
Mixing(0C)
160-170
150 165
140 160

Aggregate
Mixing(0C)
160 175
150 170
140 165

Mixed
Material(0C)
170 Maximum
165 Maximum
155 Maximum

Rolling
(0C)
100 Min.
90 Min.
80 Min.

Laying
(0C)
130 Min.
125 Min.
115 Min.

Rolling
Compaction shall be carried out in accordance with the provisions of MORTH
Clauses 501.6 and 501.7. The rolling shall be carried out with the help of
vibratory roller of 8 to 10 tones capacity.
Rolling shall be continued until the specified density is achieved, or where no
density is specified, until there is no further movement under the roller. The
required frequency of testing is defined in Clause E.17 Specifications for
Quality Control.

17.2.4

Surface Finish and Quality Control of Work


The surface finish of the completed construction shall conform to the
requirements of Clause E.16. For control of the quality of materials supplied
and the works carried out, the relevant provisions of Section E shall apply.
17.2.5

Protection of the Layer

The bituminous macadam shall be covered with either the next pavement
course of wearing course, as the case may be, within a maximum of fortyeight hours. If there is to be any delay, the course shall be covered by a seal
coat to the requirement of MORTH Clause 513 before opening to any traffic.
The seal coat in such cases shall be considered incidental to the work and shall
not be paid for separately.
17.2.6

Arrangements for Traffic

During the period of construction, arrangements for traffic shall be made in


accordance with the provisions of MORTH Clause 112 of as directed by
Engineer in - Chrage.
17.2.7

Measurement for Payment


Bituminous macadam shall be measured as finished work in cubic meters, or
by weight in metric tonnes, where used as regulating course, or square meters
at the specified thickness as indicated in the Contract or shown on the
drawings, or as otherwise directed by the Engineer.

17.2.8

Rate
The contract unit rate for bituminous macadam shall be payment in full for
carrying out the required operations as specified.

118

Item No. 18 Providing and laying 20 mm thick mix seal surfacing using
specified graded crushed Black trap stone aggregates as per MORTH
gradation using 80/100 bulk bitumen for mixing @ 4.5% (45 KG/MT), by hot
mix process and hot laid process using sencer paver finisher to the required
camber and grade. Including rolling with vibratory roller to achieve desire
density including cost of clearing fusing mechanical cleaner & collecting dust
vacume cleaner of required capacity, disposing of the stuff within 3 km lead as
directed and using fier wood oil, kerosene, labour charges ;and hire charges of
machinaries etc. complete.
18.0

CLOSE GRADED
SURFACING

PREMIX

SURFACING

MIXED

SEAL

18.1.

Scope

18.1.1

This work shall consists of the preparation, laying and compaction of a closegraded premix surfacing material of 20 mm thickness composed of graded
aggregates premixed with a bituminous binder on a previously prepared
surface, in accordance with the requirements of these Specifications, to serve
as a wearing course.

18.1.2

Close graded premix surfacing shall be of Type A or Type B as specified in


the Contract documents.

18.2

Materials

18.2.1

Binder :
The provisions of MORTH Clause 511.1.2.1 shall apply.

18.2.2

Coarse aggregates :
The provisions of MORTH Clause 511.1.2.2 shall apply.

18.2.3

Fine aggregates :
The fine aggregates shall consist of crushed rock quarry sands, natural gravel
/ sand or a mixture of both. These shall be clean, hard, durable, un-coated,
mineral particles, dry and free from injurious, soft or flaky particles and
organic or deleterious substances.

18.2.4

Aggregate gradation :
The coarse and fine aggregates shall be so graded or combined as to conform
to one or the other grading shown in MORTH Table 500-26, as specified in
the contract.

119

MORTH TABLE 500-26. AGGREGATE GRADATION


IS Sieve
Designation
(mm)
13.2 mm
11.2 mm
5.6 mm
2.8 mm
0.090 mm
18.2.5

Cumulative per cent by weight of


total aggregate passing
Type B
100
88-100
31-52
5-25
0-5

Proportioning of materials :
The total quantity of aggregates used for premix surface shall be as indicated
in the item and bitumen used for premixing in terms of straight-run bitumen
shall be 80 / 100 bulk asphalt at ther rate of 5.103 % (51.03 kg/Mt).

18.3

Construction Operations
The provisions of MORTH Clause 511.1.3.1 through 511.1.3.5 shall apply.
The rolling shall be carried out with the help of vibratory roller of 8 to 10
tonnes capacity.

18.4

Opening to Traffic
Traffic may be allowed after completion of the final rolling when the mix has
cooled down to the surrounding temperature . Excessive traffic speeds should
not be permitted.

18.5

Surface Finish and Quality Control of Work


The surface finish of construction shall conform to the requirements of Clause
E16. For control on the quality of materials supplied and the works carried
out, the relevant provisions of Section E shall apply.

18.6

Arrangements for Traffic


During the period of construction, arrangements for traffic shall be in
accordance with the provisions of MORTH Clause 112.

18.7

Measurements for Payment


Close-graded premix surfacing, shall be measured as finished work, in cubic
meter or by weight in metric tonnes where used as regulating course of square
metters at the specified thickness as indicated in the contract or shown on the
drawing or as otherwise directed by the Engineer.

18.8

Rate
The contract unit rate for close-graded premix surfacing, shall be payment in
full for carrying out the required operations.

120

Item No. 19

Providing and laying Asphalt Painting using bituminous binder @ rate of


10 kg/ 10sq.m of road surface using bituminous pressure sprayer etc.
complete as per Technical Specification.

19.1.

Scope

19.2

This work shall consist of the application of a single coat of low viscosity
liquid bituminous material to the superimposition of bituminous treatment or
mix.
Materials

19.2.1

Primer:
The choice of a bituminous primer shall depends upon the porosity
characteristics of the surface to be primed as classified in IRC:16 These are
(i)
(ii)
(iii)

19.2.2

Surface of low porosity :such as wet mix macadam and water bound
macadam.
Surfaces of medium porosity : such as cement stabilised soil base.
Surface of high porosity : such as a gravel base.

Primer viscosity :
The type and viscosity of the primer shall comply with the requirements of IS
8887 , as sampled and tested for bituminous primer in accordance with these
standards. Guidance on viscosity and rate of spray is give in Table.
Type of Surface

Kinematic Viscosity of Primer


at 60o C
(Centistokes)

Low Porosity
Medium porosity
High porosity
19.2.3

30-60
70-140
250-500

Quantity of Liquid
Bituminous
Material per 10
Sq.m. (kg)
6 to 9
9 to 12
12 to 15

Choice of Primer :
The primer shall be bitumen emulsion, complying with IS 8887 of type and
grade as specified in the contract or as directed by the Engineer. The use of
medium curing cutback as per IS 217 shall be restricted only for sites at subzero temperatures or for emergency applications as directed by the Engineer.

19.3

Weather and Seasonal Limitations :


Bituminous primer shall not be applied to a wet surface (see 502.4.2) or during
a dust storm or when the weather is foggy, rainy or windy or when the
temperature in the shade is less than 10o C. Surface which are to receive
emulsion primer should be damp, but no free or standing water shall be
present.

19.4

Construction
121

19.4.1

Equipment:
The primer distributor shall be self-propelled or toward bitumen pressure
sprayer equipped for spraying the material uniformly at specified rates and
temperatures. Hand spraying of small areas, inaccessible to the distributor, or in
narrow strips shall be sprayed with a pressure hand sprayer, or as directed by
the Engineer.

19.4.2

Preparation of road Surface :


The surface to he primed shall be prepared in accordance with Clauses 501.8
and 902 as appropriate. Immediately prior to applying the primer the surface
shall be carefully swept clean of dust and loose particles, care being taken not
to disturb the interlocked aggregate. This is best achieved when the surface
layer is slightly moist (lightly sprayed with water and the surface allowed to
dry) and the surface should be kept moist until the primer is applied.

19.4.3

Application of bituminous primer :


The viscosity and rate of application of the primer shall be as specified in the
contract, or as determined by site trials carried out as directed by the Engineer.
Where a geosynthetic is proposed for use, the requirements of Clause 703.3.2
and 703.4 shall apply. The bituminous primer shall be sprayed uniformly in
accordance with Clause 501. The method for application of the primer will
depend on the type of equipment to be used size of nozzles, pressure at the
spray bar and speed of forward movement. The Contractor shall demonstrate at
a spraying trial, that the equipment and method to be used is capable of
producing a uniform spray, within the tolerances specified.

19.4.4

Curing of primer and opening to traffic :


A primer surface shall be allowed to cure for at least 24 hours or such other
period as is found to be necessary to allow all the volatiles to evaporate before
any subsequent surface treatment of mix is laid. Any unabsorbed primer shall
first be blotted with an application of sand, using the minimum quantity
possible. A primed surface shall not be opened to traffic other than that
necessary to lay the next course. A very thin layer of clean sand may be applied
to the surface of the primer, to prevent the primer picking up under the wheels
of the paver and the trucks delivering bituminous material to the paver.

19.4.5

Tack Coat

Over the primed surface, a tack coat should be applied in accordance with
Clause 503.

19.5

Quality Control of Work

122

For control of the quality of materials supplied and the works carried out, the
relevant provisions of Section 900 shall apply.
19.6

Arrangements for Traffic


During constructions operations, arrangements for traffic shall be made in
accordance with the provisions of Clause 112.

19.7

Measurement of Payment
Prime coat shall be measured in terms of surface area of application in square
meters.

19.8

Rate :
The contract unit rate for prime coat with adjustments as described in Clause
502.7 shall be payment in full for carrying out the required operations including
full compensation for all components listed in Clause 401.8 (I) to (v) and as
applicable to the work specified in these specifications. Payment shall be made
on the basis of the provision of prime coat at an application rate of 1 kg per
square meter, with adjustment, plus or minus, for the variation between this
amount and the actual amount approved by the Engineer after the preliminary
trials referred to in Clause 502.4.3.

123

Item No. 20 Providing, laying and jointing RCC NP3 hume pipes 300
mm dia under the road for crossing the future public utilities at every 200
mt. location as directed and as per Technical Specifications MORTH
clause 2900.

The contractor will make necessary arrangement for future public


utilities crossing the road by providing 300 mm dia RCC pipe at every 200 m
interval under the road and the pipe will be issued as directed. The pipe shall
be NP3 type pipe of 300 mm internal dia meter. Measurement will be taken in
meter and the payment will be made on linear meter of the pipe provided, laid.
The specification MORTH clause 2900 will be followed for this item.

124

Item No. 21

Providing and laying inter locking Paver Block flooring of 80 mm thick of


gray cement and grey color finished laid on 20mm (average) the. Base of
coarse sand laid over and jointed with grey cement slurry incl. Finished
etc. complete.

21.1.

Scope
This work shall consist of constructing interlocking paver block flooring with
the line levels and dimension as specified in the drawings.
Materials
The compressive strength of the interlocking paver block shall be minimum
400 kg/sq.cm and water absorption should be less than 6 % by weight.
Abrasion resistance should be less than 2 (maximum permissible value 3 mm )
same shall be manufactured by automatic press and compaction must included
vibration and pressing force not less than 200 tones. The blocks should be
steam cured.
Construction Operation :
Base on which the paver blocks to be laid shall be leveled and well compacted
with mechanical compactor Special care of consolidation shall be taken to
assure a permanent laying. The depth of the base shall be as per the design and
drawing. Base shall be leveled properly. It shall be done with long and strong
skreed board. Pipes or skreeding bar may also be used. A frame of steel
section shall be made to maintain the base. The skreed shall not be warped or
twisted.
The pavers shall be placed in the pattern as per framing and detail close
together. The space between the paver should be minimum and consistent. The
overall pattern shall be uniform. If require, then the stone shall be cut with a
splitter chiesel or masonary saw as require.
The pavers should then be tamped down and leveled with a vibrating plate
compactor. This will bring the pavers to their true grade as well as level the
stones. Sand will be forced into spaces to make stones firm and free of
movement. Dry fine sand shall be sweeped above the paver block.
Measurement for payment.
Paver Block flooring shall be measured in terms of surface area of application
in square meters.
Rate :
The contract unit rates for paver block flooring shall be payment in full
compensation for furnishing all materials, labour, tools, equipment for
construction and other incidental cost necessary to complete the work.

125

Item No. 22

Providing and laying kerbing for inter locking paver block flooring of
250 mm x 150 mm x 60 mm of gray cement and gray / color finished laid
on 10 cm (average ) th. Base of c.c. 1 :5:10 and laid over and jointed with
grey cement slurry incl. Finished etc. complete.

22.1.

Scope
This work shall consist of providing and laying kerbing for interlocking paver
block flooring (250 mm x 150mm x 60mm) with the line levels and dimension
as specified in the drawings.

22.2

Materials
Kerbing shall be provided in cement concrete of grade M 40 in accordance
with MORTH section 1700 of these specifications.

22.3

Types of construction.
The precast concrete blocks shall be used.

22.4

Equipment :
For precast kerb casting equipment of adequate capacity and controls, capable
of laying the kerbs in required cross-sections and producing a well compacted
mass of concrete free of voids and honeycombs by using plate / pocker
vibrator.

22.5

Construction operations.
Kerb shall be laid on firm foundation of cc 1:5:10 laid on extended width of
pavement. The foundation shall have a projection of 50 mm beyond the kerb
stone.
In the median portion in the straight reaches, the kerb shall be precast. In the
portions where footpath is provided and/or the slope of the carriageway is
towards median (as in case of superelevated portions), there shalll be sufficient
gap / recess left in the kerb to factilitate drainage openings.
After laying the precast kerbs, saw cut grooves shall be provided at 5m
intervals or as specified by the Engineer.
Kerbs on drainage ends such as long the footpath or the median in
superelevated portions, shall be cast with monolithie concrete channels as
indicated in drawings, the slope of the channel towards drainage pipes shall be
ensured for efficient drainage of the road surface.
Vertical and horizontal tolerances with respect to true line and level shall be
6mm.

126

22.6

Measurement for Payment :


Kerbing shall be measured in terms of surface area of application in running
meters.

22.7

Rate :
The contract unit rates for kerbing shall be payment in full compensation for
furnishing all materials, labour, tools, equipment for construction and other
incidental cost necessary to complete the work.

127

You might also like