Professional Documents
Culture Documents
Part 1
October 16, 2013
Walter Worthley, PE, Chief Engineer, Valley Joist
Bruce Brothersen, PE, Engineering Manager, Vulcraft
SJI Webinars
Learning Objectives
Teach how to determine who the original manufacturer was and whether
they can provide any additional documentation.
Show how to verify the original design loads and evaluate the joist for the
new loads.
Introduction
Introduction (contd)
Evaluation and Modification of joists are required for many reasons:
Building renovations
Addition of roof top units
Conveyor loads
Field deviations Dimensional changes
Other changes not contemplated in the original design
Damage to the joists
Present procedures
Suggest details for modification or strengthening
10
Glossary of Terms
11
Connection
Deck
Design Load
Design Strength
End Diagonal or Web
End Welds
Existing Member
Filler
Joint
Joist
Joist Girder
Glossary of Terms
12
Load
LRFD (Load and Resistance
Factor Design)
Material
Nominal Strength
Preload Force
Reinforcing Member
Required Strength
Resistance Factor,
Safety Factor,
Slenderness Ratio
Span
Chapter 1
Evaluation of Existing Joist Strength
Determine Capacity of Existing Joist System
13
14
Joist Drawings
Structural Drawing
Erection Drawing
15
Designation
Joist Spacing
Designation
Joist Spacing
Mark Number
16
17
18
Field Investigation
Helpful and Required Information
19
Field Investigation
Type of Web Members
Rod webs
Crimped Angle webs
Angles welded to the outside of chords
Cold-formed sections
20
Welded Connections
Weld Sizes and Lengths are designed for the original design requirement,
not the overall strength of the member.
21
Shortspans
Longspans
Joist Girders
K-Series
LH-Series
G-Series
DLH-Series
BG-Series
KCS-Series
VG-Series
22
Field Investigation
Type of Chord Members
23
Double Angles
Separation distance
Fillers or ties
Cold-formed sections
Rods
Splices
Field Investigation
Other Items to Note
24
25
26
27
28
29
30
31
32
33
34
35
36
37
Add-Load
A single vertical concentrated load which occurs at any one panel point
along the joist chord. This load is in addition to any other gravity loads.
38
Bend-Check Load
A vertical concentrated load used to design the joist chord for the additional
bending stresses resulting from this load being applied at any location
between the joist panel points. This load shall be accounted for in the
specified joist designation, uniform load of Add-load. It is used only for the
additional bending check in the chord and does not contribute to the overall
axial forces within the joist.
39
40
41
42
KCS joists
43
Analysis Considerations
To Analyze Joist Capacity
44
45
Load Diagram
46
Example 1.1
Shear Envelope for 24K7 Joist
47
Example 1.1
Moment Diagram for 24K7 Joist
48
49
TC
Segment
Number
24K7
Revised Loading
9937
11319
9477
10861
16924
19704
16924
19704
22207
25863
22207
25863
25374
29194
25374
29194
26429
29548
10
26429
29548
11
25374
27841
12
25374
27841
13
22207
24038
14
22207
24038
15
16924
18132
16
16924
18132
17
9477
10075
18
9937
10532
50
BC Segment
24K7
Revised Loading
Number
13525
15606
19834
23322
24054
27948
26165
29600
26165
28955
24054
26202
19834
21352
13525
14426
51
Web
Number
2
2D
3
4
V2
5
6
V3
7
8
V4
9
10
V5
10R
9R
V6
8R
7R
V7
6R
5R
V8
4R
3R
2DR
2R
24K7
Axial
Force
+
11021
-
1128
-
5608
+
4709
-
600
-
4033
+
3287
-
635
-
2560
+
1828
-
638
-1828
+
1828
-
635
+
1828
-1828
-
638
+
1828
-
2560
-
635
+
3287
-
4033
-
600
+
4709
-
5608
-
1128
+
11021
Revised
Loading
Axial
Force
+
12539
-
1133
-
6555
+
5662
-
606
-
4998
+
3510
-
581
-
2882
+
2061
-
948
-2061
-2061
-
665
+
2061
-2061
-
649
+
2265
-
2990
-
645
+
3711
-
4450
-
610
+
5120
-
6011
-
1135
+
11668
Field Repairs
52
Field Repairs
53
54
Evaluate the actual member to see what the actual member capacity
might be.
Evaluate any conservative design assumptions to see if a more accurate
condition occurs.
Evaluated the length and placement of weld.
Determine the risk of repair verses the in place capacity.
Use Engineering Judgment.
Example 1.1a
Original Loads
Revised Loads
55
Assume 20 psf DL
Assume 30 psf LL
Assume 5 joist spacing
Total uniform load 250 plf
Assume 15 psf DL
Assume 30 psf LL
Assume 5 joist spacing
Total uniform load 225 plf
Example 1.1a
Load Diagram
56
Example 1.1a
Top Chord Review
57
TC
Segment
Number
24K7
Revised Loading
9937
10327
9477
9916
16924
18015
16924
18015
22207
23646
22207
23646
25374
26661
25374
26661
26429
26911
10
26429
26911
11
25374
25309
12
25374
25309
13
22207
21822
14
22207
21822
15
16924
16443
16
16924
16443
17
9477
9129
18
9937
9541
Example 1.1a
Bottom Chord Review
58
BC Segment
24K7
Revised Loading
Number
13525
14256
19834
21342
24054
25547
26165
26989
26165
26344
24054
23802
19834
19373
13525
13076
Example 1.1a
Web Review
59
Web
Number
2
2D
3
4
V2
5
6
V3
7
8
V4
9
10
V5
10R
9R
V6
8R
7R
V7
6R
5R
V8
4R
3R
2DR
2R
24K7
Axial
Force
+
11021
-
1128
-
5608
+
4709
-
600
-
4033
+
3287
-
635
-
2560
+
1828
-
638
-1828
+
1828
-
635
+
1828
-1828
-
638
+
1828
-
2560
-
635
+
3287
-
4033
-
600
+
4709
-
5608
-
1128
+
11021
Revised
Loading
Axial
Force
+
11441
-1021
-5998
+
5194
-546
-4598
+
3184
-518
-2627
+1879
-885
-1879
-1879
-602
+
1879
-1879
-586
+
2083
-2736
-582
+
3384
-4049
-551
+
4652
-5454
-1021
+
10570
Example 1.1b
A check of the roof materials found that the actual roof dead load,
including an allowance for the joist weight, is 15 psf.
60
Example 1.1b
The
roof
live
load
can
then
be
calculated
based
on
IBC
EquaRon
16-26
Lr
=
LoR1R2
where:
Lo
=
20
psf
R1
=
1.2
-
0.001At
and
At
=
6
x
40
=
240
sq.
W.
=
1.2
-
0.001(240)
=
0.96
R2
=
1
(for
roof
slope
<
1:12)
then:
Lo
=
20(0.96)(1)
=
19.6
psf
and
the
joist
LL
=
19.6(6)
=
115.2
plf
DL
=
15(6)
=
90
plf
61
Example 1.1b
The manufactured joist can now be checked using the actual design loads
DL = 90 plf & LL = 116 plf along with the two additional 500# loads.
10'-0"
5'-0"
500#
500#
215 plf
62
Example 1.1b
Top Chord Review
63
TC Segment
24K7
Revised Load
Number
9937
9440
9477
9116
16924
16719
16924
16719
22207
21962
22207
21962
25374
25078
25374
25078
26429
24859
10
26429
24859
11
25374
23344
12
25374
23344
13
22207
20101
14
22207
20101
15
16924
15129
16
16924
15129
17
9477
8321
18
9937
8645
Example 1.1b
Bottom Chord Review
64
Comparison of Bottom
Chord axial forces for 24K7
joist and for same joist with
revised loads.
All Bottom Chord panels are
acceptable.
BC Segment
24K7
Revised
Loads
Plus
Conc.
Loads
Number
13525
13188
19834
19819
24054
23673
26165
24969
26165
24318
24054
21938
19834
17831
13525
11995
Example 1.1b
Web Review
65
Web
Number
2
2D
3
4
V2
5
6
V3
7
8
V4
9
10
V5
10R
9R
V6
8R
7R
V7
6R
5R
V8
4R
3R
2DR
2R
24K7
Axial
Force
+
11021
-
1128
-
5608
+
4709
-
600
-
4033
+
3287
-
635
-
2560
+
1828
-
638
-1828
+
1828
-
635
+
1828
-1828
-
638
+
1828
-
2560
-
635
+
3287
-
4033
-
600
+
4709
-
5608
-
1128
+
11021
Actual
Loads
Axial
Force
+
10458
-745
-5626
+4880
-496
-4283
+2961
-522
-2364
+1941
-449
-1674
-1674
-536
+1674
-1674
-529
+1942
-2539
-513
+3136
-3733
-488
+4330
-5077
-741
+9577
Chapter 2
Methods of Supporting Additional Load
Options Before Strengthening
66
Chapter 2
Methods of Supporting Additional Load
Options Before Strengthening
67
Load Distribution
Member with Suitable Stiffness Required
68
Load Distribution
Relative Stiffness is Defined by Beta
K S)
(
=4
( 4EI )
Eq. 2-1
Where,
K = stiffness of the joist, kips/in.
S = spacing of the joists, in.
E = modulus of elasticity for the beam, ksi
I = moment of inertia of the beam, in.4
= characteristic parameter, 1/in.
69
Load Distribution
K S)
(
=4
( 4EI )
If S is less than /4
The spacing limit is not exceeded
S = spacing of the joists, in.
If the length of the beam is less than 1/
The beam may be considered rigid
Joist reactions may be determined by static equilibrium.
70
71
72
Hang new underhung monorail beam from the bottom chord of several
joists
Joists are 30K12 spanning 36-0
Joists are spaced 2-6 o.c.
Monorail adds a 1200 lb. concentrated load
Concentrated load located 10-0 from joist end
73
74
I j ,eff
476
=
= 414 in.4
1.15
K=
From AISC Manual of Steel Construction, Table 3-23 for a simple beamconcentrated load at any point:
2
K=
75
3EI j, eff L
P
P
K= =
=
2 2
Pa b
a2b2
3EI j, eff L
Pa b
3EIL
= 11.0 k in.
K S)
11.0 30
(
=4
=4
= 0. 0101 in.1
( 4EI ) ( 4) (29000) (301)
Check if spacing,
S = 30 in. < 77.6 in.
76
S<
= 77.6 in.
4
Therefore, OK
77
Therefore, OK
1
< in.
78
79
Cost
Time
Difficulty of repair
Effectiveness of repair
Skill of workman
80
Existing interferences
Piping, electrical conduits, other interferences
Removing or relocating could be at a greater expense than reinforcement
Camber
May need to reduce camber in new joists
Joists can be ordered with shallower seat depths and then shimmed in
the field
The joist can be supplied with a splice so two individual pieces can be
installed and bolted at the center
Lateral Stability of the joist top chord
Shoot pins through the chord, decking, and slab
Rely on bridging to provide lateral support
81
82
83
Questions
www.steeljoist.org