Professional Documents
Culture Documents
5,000,000
2009
P1,350,0
00
3,150,00
0
400,0
00
275,0
00
2010
P2,250,0
00
400,0
00
2,000,00
0
2,100,00
0
Item
Cost incurred each year
Estimated costs to complete (at
year end)
Progress billing each year
Progress payments received each
year
4,500,000
2011
P400,0
00
Total
P4,000,0
00
2,600,00
0
2,625,00
0
5,000,00
0
5,000,00
0
of year 2, costs incurred include 100 for standard materials stored at the
site to be used in year 3 to complete the project. The contractor
determines the stage of completion of the contract by calculating the
proportion that contract costs incurred for work performed to date bear to
the latest estimated total contract costs. A summary of the financial data
during the construction period is as follows:
9,00
0
Year 2
9,0
00
2
00
9,2
00
Year 3
9,00
0
20
0
9,20
0
6,1
68
2,0
32
8,2
00
8,20
0
2,09
3
5,95
7
8,05
0
Estimated profit
Stage of completion
95
0
26%
1,0
00
74%
1,00
0
100%
Year 1
9,00
0
8,20
0