PM Report

Date

Site Name:
Site ID

Zone

Basic Details
Sl.No

Description

Entry to Site

Security availability

Verify site registers & log books and update

Site Premises cleanliness

Any other issues

Tenancy with Operator

DG Reading(HRS)

EB Reading(KWH)

OK/NO/NA

Infra Utilities
Sl.No

Description

Signage Verification

Aviation lamps working

LA Pole verticality

LA & supply cabling (physical look)

Door, Lock & Stopper Operation

Room Temperature & Humidity

AC functioning

Fire fighting Eqpt.

All lights inside the shelter

10

Functinality of all external alarms from the site

11

Rain protection

12

Cleanliness of equipment room

13

Any other issues

OK/NO/NA

Air conditioner & Powers Utilities


Sl.No

Description

Cooling effect

Auto / Manual mode Controller

Room Temperature

Visual inspection of AC cabling

PMU functioning

Auto / Manual mode functioning of PMU

Visual inspection of AC cabling

Earth pits properly maintained

Earth to Neutral Voltage (Measured value)

10

EB Power and DG Power (Measured Value)

11

DG Functioning and Condition

12

Electricity meter functinality

13

Power plant internal alarms

14

Current reading

15

Voltage reading

OK/NO/NA

16

Battery bank capacity

17

Cell voltage (after discharging the battery 1/2 hour)

18

Visual inspection of Battery bank & Power plant

19

Check each rectifier Functioning

20

LVD setting done(LVD1/LVD2)

21

Any other issues

BTS
Sl.No

Description

BTS Configuration

Check for input voltage

Check for Alarms

Check for LED status

Cabinet door locking

Environment Alarm extension

Visual inspection

Check for dust, if required clean the filter

Cleanliness of DDF

10

RF Antenna & its pole Physical check

11

RF Cabling physical look

12

Any other issues

13

BTS Fondation Measurement

14

Hardware discrepancy

OK/NO/NA

Microwave Radios
Sl.No

Description

TX Protection(1+0/1+1/ring)

Hop on NMS

Cascading Hop Detail

TTSL MUX Dropping Port

Check for input voltage

Check for Alarms

Performance Monitor

Check the logs

Check for alarm extension if applicable

10

Check for node visibility on NMS

11

Check for patch code connection

12

Cleanliness of DDF

13

Whether DDF data updated ?

14

Check for dust, if required clean the filter

15

MW Antenna & its pole Physical check

16

Labelling done(pole/cable)

17

MW Cabling physical look

18

Receive level issue

19

Any other issues

Far End ID-

Designed - Tx Power

OK/NO/NA

Rx level

Achieved Rx Level

VSWR MEASUREMENT
Sl Nos

Cable

Tx/Rx A

Rx A

Tx/Rx B

Rx B

Tx/Rx C

Rx C

VSWR

EXTERNAL POWER ALARMS


Seq No.

Alarm

Power Plant Major alarm

EB Power Fail

AC power failure alarm

DG Running

Rectifier fail

Battery Discharged

Aircon 1 Failure

Aircon 2 Failure

Fire System abnormal

10

Dg fails to start

11

Door open

12

High temp

Status

PUNCH POINTS:

Tech Name :

Signature

FLE Name :

Signature

Infra Site Name :Infra Site ID:Infra Provider :Remarks / Values

Remarks / Values

Remarks / Values

Remarks / Values

Remarks / Values

Current-Tx Power +22.5, Rx level-40.6dbm

FREQUENCY(mhz)

Loop