PROJECT MEMBERS:
GIRIPRASAD.K
JAYAKUMAR.M
PANDIYARAJAN.P
SAYEDNISHAN BASHA
PROJECT GUIDE:
Mr. VIGNESH.R
Abstract:
Bus-stand is an essential component of urban transport facilities which defines the beginning
or end of the line for the transportation system. It normally requires a size-able land in a
strategic part of an urban area. A well planned or managed bus-terminal will act as catalyst to
the social and economic development of the surrounding areas. On the other hand, busterminal is an asset to an area as it may act as catalyst to economic and social development of
the surrounding areas. However, poorly planned and sited terminal for buses may generate
traffic problems as well as deteriorating the quality of life of the affected surroundings. This
project focuses mainly the structural design of whole bus terminal. As with engineering and
operational aspects of terminal facilities the focus would be on the design to fulfill traffic
capacity requirement and operational efficiency to operators and passengers. The proposed
far side terminating bas terminal model which located outside city centre may have added
advantages such as reducing unnecessary congestion and improving the environment.
Objectives:
This project have following main objectives:
Conducting research on the existing bus terminal of a city and proposing a new model of bus
terminal according to findings
1. Architectural planning of whole bus-terminal
2. Planning and design of complete bus-terminal
3. Design of a steel garage for bus repairing house and bus storage
4. Design of pavement
5. Material estimation of the whole project
6. Car parking management
Description of the Project:
2. In terms of waiting area, mostly it is strategic because the plan at bus-terminal is properly
well managed and not suitable for the users and customers.
3. Information on trips and services are well managed.
4. Public facilities such as toilets, telephone are inadequate.
5. Lack of facilities for staff such as office and control room, storage of personal belongings,
rest room, toilets and so on.
6. Lacking of proper as well as modern repairing house and bus storage garage.
I designed a complete bus-terminal including a terminal building design, a steel garage design
by using roof truss system and the rigid pavement design of terminal area and finally gave
some feedback to improve car parking management.
SLAB DESIGN
SLAB1:
Side ratio:
Ly/Lx=11.19/5.375
=2.08>2
Hence it is one way slab.
Effective depth:
Span/Basic value=5.375/25
=215mm.
d =215+20
=235mm.
Effective span:
Effective span=d + clear cover
=0.215+5.375
=5.59m.
Load calculation:
=1.5KN/m2
Live load
=4KN/m2
Total load
=11.375KN/m2
Design load
=11.375*1.5
=18KN/m2.
Bending moment:
Mu=WL2/8
=18*5.592/8
=70.3KN.m.
Maximum shear =WL/8
=18*5.59/8
=12.57KNm.
Depth required:
Mu=Q*b*d2
d=
Mu
Qb
dreq=160mm.
dprovide=drequired
Hence it is safe.
Main reinforcement:
Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]
70.3*106=0.87*415*Ast*215[1-415*Ast/20*1000*215]
Ast=1002.7mm2.
Spacing:
Main reinforcement=3d or 300mm
=3*215 or 300
=645 or 300
=300mm.
Distribution reinforcement=5d or 450mm
=5*215 or 450mm
=1075 or 450mm
=450mm.
Curtailment:
Curtailment=0.1*Effective span
=0.1*5.59
=0.559m.
Check for shear:
=vu/b.d
=12.57*103/1000*215
=0.058N/mm2.
Percentage of steel=Ast*100/b.d
=1002.7*100/1000*215
=0.466.
From IS456:2000 pg.no:73
=0.46
=1.12*0.46
=0.51.
< K*
Hence it is safe.
Hence for main reinforcement provide 10mm at 300mm c/c.
Hence for distributive reinforcement provide 8mm at 450mm c/c.
SLAB 2:
Side ratio:
Ly/Lx=9.69+1.50/5.03=2
2<22
Hence it is one way slab.
Effective Depth:
Span =5.03/25
d=201.2mm
D=201.2+20
221.2mm
Effective span=d+clear span
=0.2212+5.03
=5.2512m
Load Calculation:
Self wt. of slab= 0.2212*1*25
= 5.53KNM2
Floor finish
= 15 KN/M2
Live Load:
=4 KN/M2
=11.03*1.5
=17 KN/M2
Design Load= 17KN/M2
Bending Moment:
=Wl2/8
=17*103*5.2512/8
=53.59 KN/M2
Maximum Shear:
Vu=wl/2
=17*103*5.25/2
= 42.63KN.M
Depth Required:
Mu=Q.bd2
D=140mm
Dprovide>Drequired
Hence it is safe
Main reinforcement:
Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]
53.59*106=0.87*415*Ast*201.2[1-415*Ast/20*1000*201.2]
Ast=804.37mm2.
Spacing:
Main reinforcement=3d or 300mm
=3*201.2 or 300
=300mm
Curtailment:
Curtailment=0.1*Effective span
=0.1*5.2512
=0.525m.
Check for shear:
=vu/b.d
=42.563*103/1000*201.2
=0.21N/mm2.
Percentage of steel=Ast*100/b.d
=804.37*100/1000*201.2
=0.39.
From IS456:2000 pg.no:73
=0.4272
=1.1576*0.4272
=0.49.
< K*
Hence it is safe.
Hence for main reinforcement provide 10mm at 300mm c/c.
Hence for distributive reinforcement provide 8mm at 450mm c/c.
SLAB3:
Side ratio:
Ly/Lx=11.19/10.52
=2.16>2
Hence it is one way slab.
Effective depth:
Span/Basic value=5.26/25
=210.4mm.
d =210.4+20
=230.4mm.
Effective span:
Effective span=d + clear cover
=0.230+5.26
=5.49m.
Load calculation:
Self weight of slab=0.230*1*25
=5.76KN/m2
Floor finish
=1.5KN/m2
Live load
=17KN/m2
Design load
=18KN/m2.
Bending moment:
Mu=WL2/8
=17*5.492/8
=64.05KN.m.
Maximum shear =WL/8
=17*5.49/8
=46.66KNm.
Depth required:
Mu=Q*b*d2
d=
Mu
Qb
dreq=160mm.
dprovide=drequired
Hence it is safe.
Main reinforcement:
Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]
64.05*106=0.87*415*Ast*210.4[1-415*Ast/20*1000*210.4]
Ast=928mm2.
Spacing:
Main reinforcement=3d or 300mm
=3*215 or 300
=300mm.
Distribution reinforcement=5d or 450mm
=450mm.
Curtailment:
Curtailment=0.1*Effective span
=0.1*5.49
=0.549m.
Check for shear:
=vu/b.d
=46.66*103/1000*210.4
=0.22N/mm2.
Percentage of steel=Ast*100/b.d
=928*100/1000*210.4
=0.44.
From IS456:2000 pg.no:73
=0.45
=1.14*0.46
=0.51.
< K*
Hence it is safe.
Hence for main reinforcement provide 10mm at 300mm c/c.
Hence for distributive reinforcement provide 8mm at 450mm c/c.
SLAB4:
Side ratio:
Ly/Lx=11.19/7.43
=1.50<2
Hence it is two way slab.
Effective depth:
Span/Basic value=7.2/25
=288mm.
d =288+20
=308mm.
Effective span:
Effective span=d + clear cover
=0.3+7.43
=7.73m.
Load calculation:
Self weight of slab=0.32*1*25
=8KN/m2
Floor finish
=0.75KN/m2
Live load
=4KN/m2
Design load
=28.68KN/m2.
Bending moment:
Mx=x*Wu*Lx
=0.068*28.38*7.432
=107.66KN.m.
My=y*Wu*Lx
=0.035*13.125*7.432
=55.41KN.m.
Depth required:
Mu=Q*b*d2
d=
Mu
Qb
dreq=197.5mm.
dprovide>drequired
Hence it is safe.
Main reinforcement:
Longer span
Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]
107.66*106=0.87*415*Ast*300[1-415*Ast/20*1000*300]
Ast=1074mm2
Shorter span:
Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]
55.41*106=0.87*415*Ast*300[1-415*Ast/20*1000*300]
Ast=531mm2
.Spacing:
=vu/b.d
=106.54*103/1000*300
=0.35N/mm2.
Percentage of steel=Ast*100/b.d
=531*100/1000*300
=0.177
From IS456:2000 pg.no:73
=0.30
=1.1*0.30
=0.30.
< K*
Hence it is safe.
Hence for main reinforcement provide 10mm at 300mm c/c.
Hence for distributive reinforcement provide 8mm at 450mm c/c.
SLAB5:
Side ratio:
Ly/Lx=4.5/3.345
=1.345<2
Hence it is two way slab.
Effective depth:
Span/Basic value=3345/25
=140mm.
d =140+25
=165mm.
Effective span:
Effective span=d + clear cover
=0.14+3.345
=3.485m.
Load calculation:
Self weight of slab=0.16*1*25
=4KN/m2
Floor finish
=0.75KN/m2
Live load
=4KN/m2
Design load
=13.125KN/m2.
Bending moment:
Mx=x*Wu*Lx
=0.0778*13.125*3.3452
=11.42KN.m.
My=y*Wu*Lx
=0.043*13.125*7.432
=6.31KN.m.
Depth required:
Mu=Q*b*d2
d=
Mu
Qb
dreq=140mm.
dprovide>drequired
Hence it is safe.
Main reinforcement:
Longer span
Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]
11.42*106=0.87*415*Ast*140[1-415*Ast/20*1000*140]
Ast=234mm2
Shorter span:
Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]
6.31*106=0.87*415*Ast*140[1-415*Ast/20*1000*140]
Ast=127mm2
.Spacing:
Main reinforcement=3d or 300mm
=300mm.
Distribution reinforcement=5d or 450mm
=450mm.
Curtailment:
Curtailment=0.1*Effective span
=0.1*3.345
=0.3345m.
Check for shear:
=vu/b.d
=21.95*103/1000*300
=0.156N/mm2.
Percentage of steel=Ast*100/b.d
=127*100/1000*140
=0.09
From IS456:2000 pg.no:73
=0.28
=1.3*0.28
=0.117.
< K*
Hence it is safe.
Hence for main reinforcement provide 10mm at 300mm c/c.
Hence for distributive reinforcement provide 8mm at 450mm c/c.
SLAB6:
Side ratio:
Ly/Lx=4.5/3.23
=1.393<2
Hence it is two way slab.
Effective depth:
Span/Basic value=3230/25
=130mm.
d =130+25
=155mm.
Effective span:
Effective span=d + clear cover
=0.13+3.23
=3.36m.
Load calculation:
Self weight of slab=0.155*1*25
=4KN/m2
Floor finish
=0.75KN/m2
Live load
=4KN/m2
Design load
=13.125KN/m2.
Bending moment:
Mx=x*Wu*Lx
=0.0627*13.125*3.232
=8.59KN.m.
My=y*Wu*Lx
=0.035*13.125*3.232
=4.80KN.m.
Depth required:
Mu=Q*b*d2
d=
Mu
Qb
dreq=56mm.
dprovide>drequired
Hence it is safe.
Main reinforcement:
Longer span
Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]
8.59*106=0.87*415*Ast*130[1-415*Ast/20*1000*130]
Ast=189mm2
Shorter span:
Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]
4.80*106=0.87*415*Ast*130[1-415*Ast/20*1000*130]
Ast=104mm2
.Spacing:
Main reinforcement=3d or 300mm
=300mm.
Distribution reinforcement=5d or 450mm
=450mm.
Curtailment:
Curtailment=0.1*Effective span
=0.1*3.23
=0.3230m.
Check for shear:
=vu/b.d
=21.19*103/1000*130
=0.163N/mm2.
Percentage of steel=Ast*100/b.d
=104*100/1000*140
=0.074
From IS456:2000 pg.no:73
=0.28
K=1.30
K*
=1.3*0.28
=0.117.
< K*
Hence it is safe.
Hence for main reinforcement provide 10mm at 300mm c/c.
Hence for distributive reinforcement provide 8mm at 450mm c/c.
SLAB7:
Side ratio:
Ly/Lx=9.46/9.46
=1<2
Hence it is two way slab.
Effective depth:
Span/Basic value=9460/25
=380mm.
d =380+25
=415mm.
Effective span:
Effective span=d + clear cover
=0.38+9.46
=9.84m.
Load calculation:
Self weight of slab=0.415*1*25
=10.375KN/m2
Floor finish
=0.75KN/m2
Live load
=4KN/m2
Design load
=22.68KN/m2.
Bending moment:
Mx=x*Wu*Lx
=0.062*13.125*9.462
=72.82KN.m.
My=y*Wu*Lx
=0.062*13.125*9.462
=72.62KN.m.
Depth required:
Mu=Q*b*d2
d=
Mu
Qb
dreq=162mm.
dprovide>drequired
Hence it is safe.
Main reinforcement:
Longer span
Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]
72.82*106=0.87*415*Ast*380[1-415*Ast/20*1000*380]
Ast=628mm2
Shorter span:
Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]
72.82*106=0.87*415*Ast*380[1-415*Ast/20*1000*380]
Ast=628mm2
.Spacing:
Main reinforcement=3d or 300mm
=300mm.
Distribution reinforcement=5d or 450mm
=450mm.
Curtailment:
Curtailment=0.1*Effective span
=0.1*9.46
=0.946m.
Check for shear:
=vu/b.d
=62.80*103/1000*380
=0.163N/mm2.
Percentage of steel=Ast*100/b.d
=628*100/1000*380
=0.014
From IS456:2000 pg.no:73
=0.28
=1.0*0.28
=0.28.
< K*
Hence it is safe.
Hence for main reinforcement provide 10mm at 300mm c/c.
Hence for distributive reinforcement provide 8mm at 450mm c/c.
=200 KN/M2
=70 KN
=105 KN
=115X103/200x103
=1100x1100
=1200x1200
=1300x1300
=1400x1400
=1500x1500
Total load on footing with its
self.wt
Up word soil pressure
=
--------------------------------------------------Area
of footing
105x103
= --------------- x1500
=105 KN/M
1500
Factored moment
Soil pressure x area x centre of area
0.49/2)x0.375/2
= 105x(1
=14.86 KN.m
Final d
= 120mm
= 120+40+40
Min Asc
<
Asc provide
=1/4 x 16
=6mm
= 6 mm
Say lateral ties
=6 mm
PITCH
Le Ast of the following
Le Ast lateral dimensions
16 x smallest dia
=16 x 10 = 160mm
= 48 x 6 = 288mm
TO FIND AST
Mu
d[1-Ast x fy/bd x fck]
=0.87 x fy x Ast x
= 1x 0.11
= 0.11 m
DESIGN OF COLUMN
RECTANGULAR COLUMN:
Column size 660*490
Working load
=1500KN
Design load
=2250KN
Pu
Let Ag
=660x490
=323400mm2
Asc required:
Ac
=Ag-Asc
Ac
=323.4x103- Asc
Asc
Provide 6 nos 20mm dia provided
=6 x 202 x /4
Asc provided
=1884.95 mm2
% Ast
Min Asc
=0.8 x 1884.95
=1507.96mm2
Max Asc
=6% of Asc
=6 x 1884.95
=11309.7mm2
CHECK:
Min Asc
<
Asc provide
<
Max Asc
0.8%
<
1.34%
<
6%
SLENDERNESS RATIO:
Effective depth
=3.35 m
=le / b
=3.35 / 0.49
=6.836 < 12
It is short column.
Provisions of lateral lines
=1/4 x 20 = 5 mm
2.Dia of lateral
= 6 mm
= 16 x 20 = 320mm
=48 x 6 = 288mm
Say pitch
=288 mm
490-(40+40+10)
SQUARE COLUMN
Column size 490 x 490
Working load
=1200KN
Design load
=1800KN
Pu
Ag
= 490x 490
=240100 mm2
Asc Required
Ac
=Ag Asc
Ac
Pu
Asc
=1323.18mm2
Asc
=1884 mm2
%Ast
CHECK:
0.6
<
Ac provide
<
0.8%
OK.
DESIGN OF LINTEL CUM SUNSHADE
Live load
= 1 KN/M2
= 0.6 m
Width of spacing
= 1m
DESIGN CONSTANTS:
M15 / Fe 415
M.F
= 12
Eff. Span
= 0.6 m
=61.22 + 15 + 10/2
=81.22 mm
Say D
=85 mm
=65 mm
= 1 KN/M2
=0.75 KN/M2
Self wt.
(D x R cc = 0.825 x 25)
=2.125 KN/M2
Total load
=3.875 KN/M2
= 5.813 KN/M2
Fd =3.875 x 1.5
Consider 1 m length
B.M
=Fd x 12 / 2
=5.813 x 0.62
=1.0463KN.M
22.49 mm
= d provided
=0.12 / 100 x b x D
Ast provision
=45 mm2
=235.62 mm2
Maximum Ast
=0.04 x bd
=0.4 x 1000 x 85
=3400 mm2
SPACING:
S
Max spacing
DISTRIBUTION:
Min Ast
=102 mm2
Spacing
Max spacing = 5 x 65
=325 mm
=0.87 x fy x / 4 bd
=0.87 x 415 x 10 / 4 x 1.6 x 1
=564.14 mm
Provide ld = 570 mm
DESIGN OF LINTEL:
D
= 1 / 10 x span
= 1 / 10 x 1000
= 100 mm
D
=100+25+10/2
=130 mm
Eff. Span
=clear span + d
= 1000 + 100
= 1100mm
Height of triahgle
\
= 0.866 x 1.1
= 952.6 mm
= 76.559 mm
BM
2. BM due to load form slab
RA = RB = fdx 1/2
=7.55 x 0.77 / 2
=0.298 KN
BM
=1.971 x 1.1 / 6 = 0.361 KN.M
3. BM due to self wt of lintel
W
=0.23 x 0.11 x 25 = 0.748 KN/M
BM
=0.748 x 1.12 / 8 = 0.113 KN.M
4. BM due to load from sunshade =3.875 x 0.6
=2.325 KN/M
=2.325 x 1.1 / 8
=0.352 KN.M
Total load
AST PROVISION:
Min Ast
Astreqd
43.431 Ast2 36105 Ast + 1.334 x 106
=0
=44.88 mm2
Ast reqd.
Provide 2 nos. 10 mm
Ast
=157.03 mm2
Max. Ast
=0.04 bd
=0.04 x 230 x 130
=1196 mm2
=1.695 x 1.5
=2.543 KN.
=Vu / bd
=2.54 x 103 / 230 x 100
=0.11 N/mm2
=2.5 N/MM2
c max
v
<
c max.
= 100 Ast / bd
= 100 x 157.08 / 230 x 100
=6.683%
v
=0.519 N/mm2
= 1.5 m
LINTEL DESIGN:
D
=1/10 x span
= 1 / 10 x 1500
=150 mm
= 150+25+10/2
=180mm
Provide
=150 mm
EFFECTIVE SPAN(I):
=C.Span + d
=1.5 + 0.15
=1.65 mm.
Ht of triangle = 0.8661
=0.8661 x 1.65
=1.429 m
X / 1650 /2
=34.06 mm
Self wt of lintel
4. BM due to sunshade
Total moment
Factored moment
35mm
< d provided
AST PROVISION:
Min Ast
=0.85 bd / fy
=0.85 x 230 x 150 / 415
=70.66 mm2
Ast required
3.191 x 106 = 0.87 x 415 x 150 x Ast [ 1.415 x Ast / 15 x 230 x 10 ]
=62 mm2
Max Ast
`
=3.456 x 1.5
=5.184 KN
=5.18 KN
Nominal sheastress( v )
= Vu / bd
=5.184 x 103 / 230 x 150
=0.151 N/MM2
=2.5 N/MM2
c max
v
<
c max.
c
v
<
=Asv x fy / 0.46
=100.53 x 415 x / 0.4 x 230
=453.48mm
=0.75 x 150
=112.5 mm
3. 450mm
Provide 8 mm 2 legged stripes spacing @ 110 C\C.