WORK PROCEDURE

PROJECT: PROJECT NAME


SECTION:
CONCRETING
SUBJECT:
CONCRETE PAVINGS

1.

Ref No. CONC/07


PAGE 1 OF 2
DATE OF ISSUE
Dec. 2012
BY:
QA/QC ENGINEER
APPROVED BY:
QEHS MANAGER
ACTION VERIFY

SCOPE
The scope of this procedure covers the control of
installation of in-situ concrete paving surfaces
including finishes to ensure compliance with the
contract specifications.

2.

PROCEDURE

.1

All activities connected with concrete pavings will be Project


carried out in accordance with the contract Manage
specifications.
In
any
circumstances
where r
specifications are not provided or unclear, clarification
will be sought from the Consultants representative.

Request
for
Informati
on

.2

Where necessary a method statement shall be Project


prepared
and
approved
by
the
Project Manage
Director/Manager. It shall include:
r

Approved
Method
Statemen
t

i)

.3

.4

The agreed tolerance on level and surface


regularity.
ii)
Site protection and safety.
iii)
Mix design details for wearing surfaces.
iv)
Method of placing, compacting and finishing
concrete.
Project
v)
Method of curing.
Enginee
r
Source certificates of basic constituents of concrete to
be obtained from the supplier to verify compliance
with the specifications.
Ensure that the proposed sequence of work is Project
commenced in compliance with the contract Manage
programme. While framing the construction schedule, r
additional allowance shall be made for the following:
i)
ii)

Laying under floor services,


Curing and drying of the base concrete before
the flooring is laid.

Source
Certificat
es

Contract
Programm
e

PROJECT: PROJECT NAME


SECTION:
CONCRETING
SUBJECT:
CONCRETE PAVINGS

.5
Special care while laying concrete finishes and wearing
surfaces:

Ref No. CONC/07


PAGE 2 OF 2
DATE OF ISSUE
Dec. 2012
BY:
QA/QC ENGINEER
APPROVED BY:
QEHS MANAGER
ACTION VERIFY
Gen.
Forema
n

i)

Where a structural concrete slab itself forms the


flooring or where a topping is laid monolithically
or bonded to a hardened base, the wearing
surface shall be adequately protected against
damage during subsequent building operations.

ii)

In hot or drying conditions, care shall be taken


that the concrete mixes do not stiffen or dry out Gen.
to an extent that prevents full compaction. After Forema
compaction and finishing, the surface shall not n
be allowed to dry out quickly and this may be
achieved by protection by plastic sheeting or
other suitable means. In addition where concrete
is laid in the open, its surface shall be protected
from the effects of the sun and wind to limit the
risk of cracking.

iii)

Compaction of concrete shall be carried out in


such a way that an excess of `laitance is not Gen.
brought to the surface.
Forema
n
For the highest abrasion resistance, the final
trowelling shall be made when considerable
pressure is required to make any impression on Gen.
the surface. However excessive trowelling should Forema
be avoided to prevent the production of a n
polished or slippery finish. Water shall not be
applied between trowelling operations as this
may cause surface weakness.

iv)

Curing shall be done as specified.

v)

When topping is laid separately and bonded, the Site


surface of the base shall be thoroughly prepared Engr

CONC/07/
A

CONC/07/
A

CONC/07/
A

CONC/07/
A

PROJECT: PROJECT NAME

SITE NO.:

CHECK SHEET FOR CONCRETE PAVINGS


SUBCONTRACTOR:
SECTION
OF
_________________
STAGE

PREPARATION

CONCRETE LAYING

Sheet No.

CLIENT
WORK

_________________________________
ITEM

1. Establish datums for finished level of


finished surface.
2. Check mix design details.
3. Check materials (cement and
aggregate) to specification.
4. Check surface preparation.
APPROVAL TO PROCEED.

LOCATION

Checke
d
by
SE/SU
PE
PE
GF
QA/QC

5. Check compaction (no bleeding shall


occur).
6. Check an excess of `Laitance is not
brought
to the surface.

GF

7. Check surface finishing

GF

8. Check curing technique being


followed.

SE

9. Check finished levels are within


tolerance.

SE

10. Protect surface against damage.


11. Check adhesion between concrete
topping and
base by tapping for hollowness.

GF

APPROVAL TO PROCEED

QA/QC

GF

SE

QA/QC Quality Assurance/Quality Control, PE - Project Engineer, SE - Site Engineer,


SU Surveyor, GF General Foreman

Date