SARCO JV

GOLEN GOL HYDROPOWER PROJECT

Doc No.

DAT
E

REVISI
ON

PAG
E

SITE WORK METHOD STATEMENT


FOR
GRANULAR SUB BASE AND AGGREGATE
BASE

Golen Gol Hydropower Project

01/01/201
5

SARCO JV
GOLEN GOL HYDROPOWER PROJECT

Doc No.

DAT
E

REVISI
ON

PAG
E

01/01/201
5

TABLE OF CONTENTS
Topic------------------------------------------------------------------------------Page

1.0 OBJECTIVE --------------------------------------------------------------3


2.0 SCOPE
-------------------------------------------------------------------3
3.0
REFRENCE---------------------------------------------------------------3
4.0
RESPONSIBILITIES-----------------------------------------------------4
5.0

EQUIPMENT------------------------------------------------------------5

6.0

MAN POWER-----------------------------------------------------------

5
7.0 SAFETY, HEALTH & ENVIRONMENTAL ISSUES
-----------------6
8.0 METHODOLOGY
------------------------------------------------------7 -9
9.0
10

REINSTATEMENT, ATTACHEMENT ----------------------------

SARCO JV
GOLEN GOL HYDROPOWER PROJECT

1.0

2.0

Doc No.

DAT
E

REVISI
ON

PAG
E

01/01/201
5

OBJECTIVE
The purpose of this method statement is to define the
procedure to ensure
that the proposed materials and
workmanship to be used at the above site are complying with
the condition/requirements as stipulated in Technical
Specifications.
SCOPE

The purpose of this method statement is to describe the activities and methods,
which will be used to carry out the placing of sub base and aggregate base.

3.0REFRENCE

Technical Specification Volume

Construction Drawings
Methodology for granular sub base and aggregate base

.0 RESPONSIBILITIES
The responsibilities for the implementation of this Method Statement are
assigned as follows:
Project Manager

He has the responsibility to approve


this document, and he is responsible
for the implementation of this method
statement

Construction Manager

He has the responsibility to make sure


that the production activities are in
line with this document and he has to
allocate all the resources needed for
their implementation.

Technical Services Manager

He verifies this document before its


issue. He prepares and distributes this
method statement at all the person
involved in that work. He is also
responsible for the distribution of any
technical document needed for the
execution of the work.

Supervisor

They verify that the work is done in

SARCO JV
GOLEN GOL HYDROPOWER PROJECT

Doc No.

DAT
E

REVISI
ON

PAG
E

01/01/201
5

accordance with this document.


Surveyor

He marks the position, Height of the


layers and he must verify the same
with the related drawings.

Quality Control Manager

He coordinates and controls with his


staff the quality control inspectors
activities; he supports the Technical
Services Manager in coordination
between the Quality Control activities
with the laboratory and the survey.
He is responsible for the distribution of
the Quality Inspection and Testing
Plan.

Safety Officer and Inspectors

They have the responsibility to


implement all the foreseen safety
measures in order to prevent
accidents.

5.0 EQUIPMENT
Excavator
loader
Grader
Roller
Dozer
Dump Truck
Total Station
Service Vehicle for General Workers
6.0

MANPOWER
Supervising Engineer
Foreman
Operator
Driver
Skilled Workers
surveyor

01
02
11
04
15
01

SARCO JV
GOLEN GOL HYDROPOWER PROJECT

Survey helpers
Safety Officer

7.0

Doc No.

DAT
E

REVISI
ON

PAG
E

01/01/201
5

04
01

SAFETY,HEALTH & ENVIRONMENTAL ISSUES


Conditions and precautions listed in the project specifications
shall be followed as maximum.
All staff involved with the project shall be inducted on the
safety, health and environmental issues associated with the
work.
Only trained personnel with relevant experience shall be
allowed to handling machinery.
Appropriate Safety Signboards, barriers and lighting shall be
and other safeguards shall be provided as required by the
nature of and location of the worker. All operations shall be
carried out in accordance with the safety requirements.
All field personnel shall use PPE safety requirements like
safety shoes helmets, cover all, goggles and dust mask, etc.
as required.
Precaution and protection that Important habitats, including
protected habitats and species, can be lost during the
construction phase both through direct loss during site
clearance or indirectly due to loss through pollution and/or
disruption

8.0

METHODOLOGY

. Construction method the sequence of the work to be carried out shall


be as follows:1. Making of subgrade
2. Placing of Sub base
3. Placing of aggregate Base
2. Placing of Sub base

SARCO JV
GOLEN GOL HYDROPOWER PROJECT

Doc No.

DAT
E

REVISI
ON

PAG
E

01/01/201
5

1. Prior to placing any Sub base material, the underlying subgrade shall
be shaped and compacted in accordance to the specifications
2. The material shall be placed over the full width of the formation to the
required thickness as shown in the drawings in one layer or more, each
layer not exceeding 200mm compacted thickness.
3. In case of, space for diversion not available, than 1 st place the sub base
material in one side of center line. And after the complete approval the
consultant, start work other side of center line.
4. Each layer of Sub base shall be process as necessary to bring its moisture
content to a uniform level throughout the material suitable for compaction.
5. The Sub base shall be compacted using suitable compaction equipment
approved by the Engineer to not less than 98% of the maximum dry density.
6. The top of Sub base shall have the required thickness, shape, super
elevation, levels and grades as required in the drawings and shall be within
the tolerances as specified in the specifications.
7. In the course of the construction, the level shall be checked using auto level
or total station , set out at regular interval along both sides of the road width
8. Every layer shell be checked by the consultant jointly. And after the
consultant approval start placing the next layer.

3. Placing of aggregate Base


1. Prior to placing any aggregate base material, the underlying sub base shall
be shaped and compacted in accordance to the specifications.
2. The crush Aggregate base material shell be approved by consultant.
3. The material shall be placed over the full width of the formation to the
required thickness as shown in the drawings in one layer or more, keep
each layer thickness according to consultant approval.
4. In case of, space for diversion not available, than 1 st place the aggregate
base material in one side of center line. And after the complete approval the
consultant, start work other side of center line.
5. The aggregate base shall be compacted using suitable compaction
equipment approved by the Engineer.
6. The crushed aggregate base shall be from approved sources.
7. After the compaction the level shall be checked using auto level or total
station with consultant both side and centerline of the road with in the
tolerances as specified in the specifications.

I. REINSTATEMENT
All surface of roads, fields, paths, etc., whether public or private,
which are affected by the operations shall be restored.

SARCO JV
GOLEN GOL HYDROPOWER PROJECT

Doc No.

DAT
E

REVISI
ON

PAG
E

01/01/201
5

Upon completion of reinstatement work, all soil heaps, rubbishes,


and the like form the site shall be removed.

ATTACHMENT
A.
B.
C.
D.
E.

Grp pipe Layout plan & X-Section


Survey Check List
Site inspection Check list
Earth work Check list
Check Request