TECHNICAL PROPOSAL CONTENT


In the technical proposal, the economic operator shall specify the concrete way that follows the
fulfillment of the contract in accordance with the requirements of the specifications (not limited to
them), presenting in this respect:
V.1. Design their own solution based on the Specification, which will necessarily include:
1.1. HISTORY STUDY - SUBSTANTIATION STUDY FOR FUTURE INTERVENTIONS
1.1. WRITTEN PARTS
a) Identification of cultural resources through the essential aspects of the historical evolution
- Current and Historical Context
- Legal protection regime
- Analysis of urban fabric
- Detailing the historical functions
- Analysis of the built object
- Parcel and object in relation to the historical evolution of the urban context
- Historical Landmarks and architecture
- Cultural resource
b) Substantiation study for future interventions
- Restrictions, permissiveness and recommendations for future interventions generated by cultural
resource
1.2 . DRAWINGS
a) Identification of cultural resources through the essential aspects of historical
evolution :
- Legal protection regime
- Evolution of streets and parceled according to historical plans
- Excerpts from historical plans of Reference
- Dating the built according to information from historical plans
- Alignments Evolution according to historical plans
- Planimetric Evolution of the building : basement, ground floor , 1st floor , 2nd floor ,
3rd floor, attic
- Documentary photography interior / exterior
b ) Substantiation study for future interventions:
- Restrictions , permissiveness and plan recommendations basement, ground floor ,
1st floor , 2nd floor , 3rd floor, attic
- Restrictions , permissiveness and recommendations elevations .
Wording requirements:
- documentation shall specify the literature that led to the preparation of the study
- documentation will specify the documentation extracted from funds archives.
- documentation drawn will draw on the support of surveying .
- The scale of the drafting of the substantiation of intervention will become so
indicated permissitions and restrictions to be explicit and eloquent
1.2. SURVEYING ARCHITECTURE
1.2.1 DRAWINGS
a) Site plan (overlaid on cadastral plans indicating the traffic situation and
surroundings)
b) Plans of all levels
c) All building facades
d Characteristic Sections - minimum 3
Technical requirements:
- All documentation shall be submitted in electronic format .dwg and print
- All drawn parts will be written for a minimum scale 1:100, with the exception of

situation plans, framing plans - 1:500 or 1:2000


All items will include:
- Axes, partitions, exterior closures, carpenters
- Indicative of the rooms, the rooms surfaces, finishes indications
- Marking accesses and their type

1.3. PROJECT FOR THE TECHNICAL PROPOSAL OF ARCHITECTURE


1.3.1 WRITTEN PARTS
a) General technical memorandum with the functional description and objective organization
b) Scenario for fire safety
c) Quantity lists of works
1.3.2 DRAWN PARTS
a) Site plan (overlaid on cadastral plans indicating the traffic situation and surroundings)
b) Plan plotting
c) Plans for all levels of infrastructure
d) Plans for all levels of superstructure
e) Plans for floors / ceilings - material representation
f) All building facades
g) Characteristic sections - minimum 3
h) Distribution finishes
i) Painting interior and exterior joinery
j) Exterior Images - Perspectives
Technical requirements:
- All documentation shall be submitted in electronic forma .dwg t and print
- All drawn parts will be written for a minimum scale 1:100, with the exception of
situation plans, framing plans - 1:500 or 1:2000
- All parts book will be written in coordination with projects proposed plant resistance
and binding and shall contain:
- Axis structure, partitions, exterior closures, carpenters
- Indicative of the rooms, the rooms surfaces, finishes indications
- Signs and markings circulation plans and infrastructure plans situation
- Furniture fixed, mobile and semi-furnished, sanitary
- Marking accesses and type, an indication of the fire resistance of structural elements,
according to the scenario of fire safety and equipment PSI
- Indication of fire departments
- there will be mentioned on the boards: class importance, importance category,
degree of fire resistance, fire risk
1.4. PROJECT OF THE TECHNICAL PROPOSAL OF FACADE RESTORATION
The technical proposal shall be prepared in accordance with the historical studies on
protected architectural elements and according to the documentation and permission
restrictions.
1.4.1 WRITTEN PARTS
- Study on the causes of degradation of the surfaces and research of the surfaces indoor / outdoor and photo documentary
- Technical report on the analysis of the main categories of material that goes into the
facades, the microscopic analysis of samples / samples
- Memorandum artistic components will include: general data, site characteristics,
building characteristics, the proposed solutions for restoring facades through the
deficiencies and degradation analyzed the requirements of quality
1.4.2 DRAWINGS
- Survey of face degradation indicating degradation categories and areas of
intervention

- Survey of internal degradation indicating degradation categories and areas of


intervention
1.5. RESISTANCE PROJECT
1.5.1 WRITTEN PARTS
a) Technical Memorandum on resistance
b ) Calculation roundup will contain at least :
- Establish load calculation
- Predimensioning infrastructure elements according to the regulations in force :
Interior and exterior walls
Slabs ( thick slab tiles and beams)
Trays
- Calculation of complete infrastructure necessary enclosure in accordance with NP
-124 : 2010 - " Standard for the design of geotechnical works support"
- Predimensioning structural elements of infrastructure based on determined efforts of
a spatial computing
- Predimensioning structural elements of the superstructure on the basis of results
from a calculation of spatial efforts
- Integration of the proposed solution in the current situation
- Preliminary checks on the lateral stiffness of the structure
- The proposed solution will be according to the existing one
a ) Bill of Quantities for structural strength
1.5.2 DRAWINGS
a) Plan site and layout support
b ) Plan slab formwork
c ) proposed plans of formwork of all levels of infrastructure
d ) reinforcement drawings and reinforcement details of all levels of infrastructure
e) Plans of the superstructure formwork
f ) Plans arming and reinforcing details superstructure
g ) Sections characteristic - at least 2
Technical requirements:
- All documentation shall be submitted in electronic format .dwg and print
- All parts book will be written for a minimum scale of 1:100 , all details will be drawn
at a minimum scale of 1: 50 / 1:20
- All parts book will be written in coordination with architectural projects and proposed
plans and considering the existing situation
1.6. INSTALLATION PROJECT
1.6.1 WRITTEN PARTS
a) The technical memoirs specialties installations
b) Calculation summaries
c) List of main equipment
d) Technical data sheets main equipment
e) Quantity lists of works
1.6.2 DRAWINGS
a) Functional Scheme
b) Plans of all levels of infrastructure
c) Floor plans, 1st floor, 2nd floor, 3rd floor, attic
d) Scheme columns installations
e) Schematic diagram low voltage
f) Schematic diagram BMS
Technical requirements:
- All documentation shall be submitted in electronic format .dwg and print
- All drawn parts will be written for a minimum scale 1:100
- All drawn parts will be written in coordination with strength and architecture projects

V.2. Description of works to be executed , technological operations and equipment


used to achieve them , as well as:
- Description of works for construction safety , labor protection , environmental
protection ;
- The values entered in the summary will be supported by demand estimates prepared
in accordance with rules and regulations in force on the standard documentation
preparation and presentation currency supply.
V.3. Plan for the execution of works ( POEL ) . The tenderer shall submit the plan for
the execution of works, given mainly rigor applied in the implementation of the system
description works applicability. Plan for the execution of works submitted by each
bidder will have a structure to cover all organizational elements on the execution of
the work such an action plan on signaling, protection, marking work, temporary work /
history / temporary running on the contract period (location, description of work
temporary / preparatory and technology needed to ensure the execution of the
investment both on land and in areas outside the occupied temporarily ), effective
execution of the work plan, working methods, their phasing throughout the period of
execution ( by category of work , including graphics ), schedule (daily / weekly /
monthly ), personal use for execution ( staff , numbers , graphics distribution during
execution ), providing technical execution ( means transportation , equipment ,
graphical distribution during execution ), plan organizational measures for ensuring
the maintenance of the yard tidy and in order; technical execution specific procedures
of all work covered by the agreement , according to specifications.
V.4. Quality plan for execution of works : The bidder shall submit quality assurance
program which will include: a description of the quality system, including procedures
relating to quality system (PS ) , applied to the work / technology set , description of
technical procedures for the execution of the main objects and categories of works
which is to be applied to achieve the investment objective quality control plan,
verification and testing. Construction quality program should ensure the specific
requirements : strength and stability, fire safety , operational safety, noise protection,
environmental protection, energy saving .
V.5. Plan to ensure health and work safety, prevention and fire fighting plan ( PSSM +
PSI) This will include : General measures of prevention and protection during the
construction works, collective protective measures, personal protection measures,
measures taken in case of fire, accident, accidental pollution; persons responsible for
implementing the above measures, data for institutions with authority in the field: fire,
rescue, civil defense agency environment.
V.6. Environmental Plan ( PM );
V.7. Risk Management Plan (identification , quantification and risk management);
V.8. Gant chart of the contract as the " baseline " ( the original graphic assumed ) .
The Gant chart will highlight the activities of allocating financial resources offered on
cost centers and specialists for achieving each activity .
All reference standards ( Romanian standards , norms for execution of works ,
technical prescriptions , etc.). Both those mentioned in the specifications specialties
in memoirs, notes on drawings, applicable in their updated form , and the effect at the
time of the works are part of the general specification of tasks. Any changes that occur
during the legislation and regulations relating ( the emergence of new standards,
cancellation and replacement of existing standards , etc. . ) will apply in accordance
with the law. In such cases, the contractor is obliged to request to the Investor to apply
the necessary modifications. The bidder will complete the Declaration on own
responsibility on compliance throughout the execution of the contract, where it will be
awarded to the tenderer, working conditions and labor protection measures in
accordance with the law on safety and health at work in Romania, as well as any other
rules, to the extent that they will occur in the period mentioned above.
Detailed information on the regulations in force at the national level and that relates to
labor conditions, labor protectio , safety and health can be obtained from the Labour

Inspectorate or from the Internet - www.inspectmun.ro/Legislatie/legislatie.html.


To check the technical compliance of the works and services offered by the technical
specifications of the beneficiary's requests, the economic operator is required to
submit the technical proposal, all of the characteristics that define the work sand
services from the offer. The technical proposal shall be signed by the authorized
person of the economic operator - will have a firm and legally binding on all the
content validity established by the contracting authority. Elements of the technical
proposal shall be presented in detail in correlation with the Specification Manual and
the Requirements of the Beneficiary.