Professional Documents
Culture Documents
Data centres
In this month's engineering
services cost model, Davis
Langdon Mott Green Wall
reviews the principles of
data centre design and look
at the implications for the
services costs
bsjonline.co.uk 09.07
09.07 bsjonline.co.uk
Electrical services
Traditionally, the primary cost unit for a colocation centre was floor space. Now it is electrical power.
The availability, size and security of the power supply is the major selling point of a co-location centre. Power loads of 800-l,000W/m 2 are
available, but many operators are looking to
increase this to l,200-l,500W/m 2 . This standard represents the maximum theoretical load
if the technical areas were filled to capacity. In
practice, below-optimum use of rack space and
diversity of server operation mean this limit
may not be approached.
Mechanical services
75 cost model
Fire protection
Key issues for the fire protection system are:
Using VESDA systems that can detect very
early signs of a fire risk.
Gas suppression systems are commonly
specified but can be costly. The space must be
sealed to prevent gas escape, it must maintain
its integrity during discharge and there must be
a means of evacuating the gas afterwards.
Standard sprinkler systems are not used in
the technical areas, but water mist systems are
common. Provided the power is automatically
isolated and the water is pure, the equipment is
often unaffected once thoroughly dried. It
offers the advantages of localised activation
and gentle discharge. Water-based systems
should not hold water in the pipework unless
activated and activation should be on a per
head basis.
It is prudent to divide a data centre into separate technical areas with fire breaks between
and running off separate infrastructure to allow
containment of disaster effects.
Consideration should be given to a fire suppression system that can be triggered more
than once without the need for repriming.
Security
Security installations dealing with intrusion and
access control are necessarily extensive. As well
as physical barriers at the site and building
perimeters, there should be access control
within the building. Voids in floor and ceiling
zones should be secured to prevent unauthorised access.
Intensive CCTV installations linked to intruder detection will include monitoring of tenants'
areas. CCTV coverage of every aisle in technical
areas is becoming increasingly common.
Access control systems in co-location centres
Energy efficiency
There is a view that the increasing divergence
between rapid server computing performance
gains, which increase by a factor of three every
two years, and the far slower improvement in
energy efficiency, may soon call into question
the economic productivity of the co-location
data centre.
While power consumption per unit drops,
consumption actually increases, which results
in rapidly escalating electricity and site infrastructure costs for every server deployed, to
the point where these exceed the revenue
potential from letting the space.
This continued growth in power requirements may see buildings running out of power
and/or cooling capacity to meet this demand,
leading to an unplanned capital investment to
expand an existing centre or indeed build a
new one. The long-term solution is to improve
energy efficiency by at least equal the rate of
computational performance increase, through
higher energy efficiency of IT hardware components (increased research and development)
and the elimination of energy wastage (good
practice).
This will ultimately result in development of a
brief for a green data centre, identifying and
bsjonline.co.uk 09.07
76 cost model
Cost b r e a k d o w n
Item
Unit
Quantity
Rate
Total
m2
8,500
51,000
m2
8,500
76,500
m2
8,500
51,000
Item
127,500
127,500
Chilled water plant with redundancy of N+1 to provide 1000W/m 2 cooling to the technical space
Item
2,040,000
2,040,000
Chilled water distribution to data centre to freestanding to freestanding cooling units with associate
Item
2,987,200
2,987,200
Supply and extract ventilation to technical space, switchrooms and ancillary spaces, including grilles and diffusers
Item
2,120,000
2,120,000
Freestanding room air-conditioning units with redundancy of N+20% to technical space and switchrooms
Item
1,657,500
1,657,500
Air-conditioning to offices areas; two pipe fan coil with electric reheat
m2
550
210
115,500
Item
7,500
7,500
Item
27,500
27,500
m2
5,100
10
51,000
High voltage switchgear, transformers and distribution based on a requirement of a 6MVA dual supply
Item
500,000
500,000
Main and sub-main installation comprising of switchgear, power factor correction, cabling, busbar and distribution equipment
Item
2,000,000
2,000,000
Low voltage distribution to support areas directly fed from main LV panel
m2
550
18
9,900
m2
7,950
10
79,500
PDUs complete with isolating TX and an average of 160 SP outgoing ways, (based on 40 fed from UPS output panel)
Item
1,600,000
1,600,000
Item
750,000
750,000
Item
20,000
20,000
Underfloor power distribution to cabinet locations, based on a requirement of 3,200 cabinets dual fed
Item
2,300,000
2,300,000
m2
5100
25,500
m2
2850
15
42,750
Small power distribution to support areas; busbar and floorbox to office areas, wall mounted elsewhere
m2
550
35
19,250
Lighting installation
m2
8500
15
127,500
m2
8500
30
255,000
m2
550
50
27,500
m2
8500
10
85,000
Power and containment to cooling units in technical spaces, based on a required of 82 units with dual feeds
Item
120,000
120,000
Item
25,000
25,000
m2
2850
20
57,000
Power and containment to serve BMS, CCTV and fire alarm system in technical areas
m2
5100
10
51,000
IT containment to technical spaces, based on 600mm basket supported on channel run to cabinet locations
m2
5100
20
102,000
m2
550
15
8,250
Standby generator installation - 5 l,500kVA units, providing N+1 (rate based on 160/kVA)
Item
1,700,000
1,700,000
UPS installation - 1 6 x 800kVA (4 x 3.2MVA) static units, providing full (2N) redundancy; 10 min autonomy (based on 200/kVA)
Item
2,560,000
2,560,000
Item
1,600,000
1,600,000
Item
80,000
80,000
Item
100,000
100,000
Gas installations
Item
40,000
40,000
m2
8500
42,500
Lightning protection
m2
8500
17,000
99,750
Electrical installations
Protective installations
m2
2850
35
m2
550
30
16,500
m2
5100
220
1,122,000
Leak detection
m2
5100
20
102,000
Communications installations
Fully addressable fire and smoke detection and alarm system to plant and support areas
m2
3400
18
61,200
Allowance for interface of fire and smoke detection system with gaseous extinguishing installation
m2
5100
10,200
m2
5100
50
255,000
m2
8500
42,500
Item
1,500
1,500
CCTV installation to technical spaces, based on a full requirement of CCTV in all aisles between cabinets (160 fixed cameras)
Item
650,000
650,000
Item
70,000
70,000
Access control system to technical spaces; (25 readers); plant & support areas (18 readers); door entry system to support areas
Item
107,000
107,000
m2
8500
68,000
m2
8500
35
297,500
m2
7950
15
119,250
m2
8500
50
425,000
Total cost
09.07 bsjonline.co.uk
27,104,250