Professional Documents
Culture Documents
Michael Haney
Matthew Loffman
Steve Robertson
Douglas-Westwood
costs are rising at a much faster rate than free
cash fow. This is not a sustainable. A Goldman
Sachs study highlighted the impact very clearly
the returns for oil majors (measured in terms
of cash return on cash invested) are at their lowest levels since 1999.
E&P companies will have to do something
about cost infation for projects to be viable.
They will not have the luxury of ever-rising
oil price increases to mask the impact of project over-runs.
Actual
United States
Canada
Outside North America
900,000
Capital spending ($s in millions)
800,000
Estimates
700,000
600,000
500,000
400,000
300,000
200,000
100,000
0
1985
1988
1991
1994
1997
2000
2003
2006
2009
2012
2015
FPSO OUTLOOK
$20
GR
CA 13)
.9% -20
10 999
(1
$15
$10
0.9% CAGR
(1985-1999)
$5
Source: IEA, Barclays Research
$0
85 87 88 89 90 91 92 93 94 95 96 97 98 00 01 02 03 04 05 06 07 08 09 10 11 13
19 19 19 19 19 19 19 19 19 19 19 19 19 20 20 20 20 20 20 20 20 20 20 20 20 20
We understand.
We are your global work team.
If you work in the projects, facilities, and construction discipline of the upstream
oil and gas industry, now is the time to join the Society of Petroleum Engineers.
Weve developed new products and services focused on your technical and
professional needs, including the Oil and Gas Facilities magazine.
And, with 110,000+ members around the world, you will never meet a new challenge alone.
FPSO OUTLOOK
Project A
Project B
Operator Contracting
Project C
Project D
Project E
Project F
Project G
Project H
Project I
Total
14
Material Costs
Engineering Scope
Yard Availability
14
2
1
2
0.5
Equipment Package
Integration
1.5
20.5
22
5
0.5
3
9.5
28.5
Subsea Equipment
Equipment Installation
Commissioning
0.5
1
Source: Douglas-Westwood
Financing
11
Political/Unpreventable
Total Delay (Months)
6.5
3
18
18
13
52
17
14
18
13
146
$5,060
$35
$88
$375
$80
$90
$500
$132
$420
$6,780
$6,200
$44
$132
$675
$190
$240
$1,017
$200
$669
$9,367
$1,140
$9
$44
$300
$110
$150
$517
$68
$249
$2,587
23%
26%
50%
80%
138%
167%
103%
52%
59%
38%
Extra Cost %
Project complexity
Every offshore feld is different and therefore requires different production infrastructure. Each feld has particular characteristics;
production curve, water depth, oil and gas
mix, API gravity, well numbers and locations,
pressure ratings, responses to enhanced recovery techniques, lifetime estimates, and so
on. The different nature of each offshore development project has led to a feet of uniquely
designed FPSO solutions. Such a variance
increases the complexity of supplying FPSOs;
more so than in other areas of the oil and gas,
such as drillships and supply vessels.
Field owners need to have comfort that
their feld is being optimally exploited. This is
particularly true of national oil companies who
steward hydrocarbon resources in their waters.
As NOCs lead developments in critical producing regions, this factor has become more
prominent, ensuring that subsea infrastructure,
topsides equipment, and FPSOs are designed
for the maximum production possible. Strong
competition among the majors in offshore plays
supports governments capacities to place stringent targets and other requirements.
Accurately evaluating reservoir potential is
an industry-wide challenge. Unique geological
features, extended production lives, and lack
of information at the start of the evaluation process complicate estimates. Reliance on early
and limited data is necessary, but has a strong
impact on production infrastructure. A higher
proportion of development capital is required
up front, and the observed impacts on FPSO
design have been negative and severe. Based
DurabandNC
THE WORLDS MOST TRUSTED HARDBANDING
www.hardbandingsolutions.com
hbs300@hardbandingsolutions.com
FPSO OUTLOOK
Regulation issues
Local content
The FPSO supply chain further suffers from local content requirements. While benefts to local communities must be a priority, the execution of these plans in diverse regions threatens the advancement of
technology and supply chain effciency in critical markets. Reliance on
inexperienced shipyards to complete complex integration of hull and topsides has led to eye-watering delays and cost additions in the past fve
years, and this will continue to grow unless there are signifcant changes.
Related issues around availability of engineers, experience of procurement personnel, and the supply of minor necessary equipment all continue to contribute to complications in FPSO delivery.
Organizational learning
The research highlights the lack of institutional experience among
FPSO operators. In drilling projects, repeated delivery allows operators and contractors to build experience and develop repeatable
practices. However, few companies have completed enough FPSO
projects to institutionalize lessons learned. In addition, key FPSO
personnel often change frms from one project to the next. These
lessons of past projects need to be learned as an industry, if near
future demand for FPSOs is to be met.
Stand: 2341J
Stand: 1446
Often, the sheer size of the projects brings additional complications. With FPSOs costing hundreds of millions of dollars, lease operators are required to raise such signifcant volumes of capital that
the fnancial health of the company is at risk on each project. This
is not sustainable, even in the short-term. This is particularly true
when, after cost overruns are distributed, many projects originally
considered quite proftable end up instead making substantial losses.
FPSO OUTLOOK
Drilling industry
comparison
The high level of oil company involvement
in the organization of FPSOs contrasts with the
drilling industry, where operators outsource
operations to specialist contractors. Contracting practice allows oil companies to incentivize
drillers who offer bundled solutions, limiting
the hands-on decision-making involvement
of the operators. By shifting administrative
responsibility to drillers, the web of decision
making has become far simpler compared
with the production side. Whether elements
of this approach could be transferred remains
to be explored. Given oil company culture
and typically higher levels of involvement in
production decisions, oil companies will need
to increase their responsibility for that supply
chain, particularly when it breaks down.
Next steps
Re-addressing the Why is anything going
to change now? question requires examination of the current ethos and belief systems
within the supplier community. Offshore production is often conservative in adopting new
technologies and practices. A mentality exists
that there is no alternative to the current practice, often based on almost mythical stories of
failed past attempts at change, or on a handful
of individual experiences over the years.
There is little doubt that emotional factors
are instrumental in driving contractors decisions across the board, ranging from equipment selection to evaluation processes. The
diffculty now is that demand outstrips supply
to the extent that the supply chain simply is not
sustainable, and these challenges are increasing, not decreasing. There is a pressing need
to address supply chain concerns, and this will
involve a serious, rational examination of options with no room for hearsay or hunches.
Approximately 100 new FPSOs will need
to be built by the end of 2017, representing
a 50%+ growth in feet size. The supply chain
will not meet demand over the next fve
years or further into the future unless substantial changes are made in the industry.
The industry value chain will need to be
restructured. Leasing contractors FPSOs
are major, multi-billion dollar investments.
Observing the growth of leasing as a procurement model for FPSOs, contract risk terms
equate to operators using some contractors as
a bank, hedging their investments. With leasing contractors suffering across the board,
there may be an opportunity for them to refocus, potentially separating into technology
development and own and operate groups.
Project repeatability is another way to
improve FPSO supply. Project methods that
build on industry knowledge of delivery and
operations can improve execution quality
and effciency. The interviews with oil companies and others suggest that beginning
each major project from a blank sheet of
paper may not be necessary if safe and effective alternatives are developed.
Oil companies have an important role in
nurturing the supply chain beneath them,
Hardbanding Support
From Hardbanding Solutions by Postle
IMPROVING STANDARDS
On-Site Training for New Applicators
Applicator Testing, Qualication & Licensing
www.hardbandingsolutions.com
hbs300@hardbandingsolutions.com