Boiler Light Up Start Up Power plan

Installation, testing and commissioning of station batteries along with


associated battery chargers
The temporary 400 Volt supply for battery charger may be arranged
from construction power available at site, which will ultimately be fed
from regular 400 Volt switchboards.
Installation, testing and commissioning of 4 nos. 11 KV switchboards in
33 / 11 KV sub-station for extending startup power at 11 KV to main 11
KV switchboards OCA, OCB, 1CA and 1CB through 11 KV 3 core 300 mm 2
cable
To install 16 MVA, 11 / 6.6 KV station service transformer just outside Arow near column no 10 11 and commissioning
Charging 6.6 KV station service switchboards
Installation of 2.5 MVA station and unit PCC transformers
Charging of station and unit PMCCs at 415 Volt so that 415 V supplies
will be extended to boiler MCC
Installation of DCS panels in main control room and cabling for essential
services required for boiler light up.
Identification of essential services for Boiler Light Up
Commissioning of DCS batteries including DCS battery chargers.
Power Supply to ID & FD Fan
Power Supply to APH
Power Supply to Fuel Oil System

Arrangement of DM and ACW System


Raw water supply to clarifloculator by operating intake pumping station
pumps
Commissioning of clarifloculators (HRSSC)for making available clarified
water which shall be fed to ACW system through service water piping
and for making available DM water required for boiler and DMCCW
system for steam generator
Readiness of Condensate Storage Tanks (at least 1 no.) with completion
of piping from CST to boiler fill pump for boiler filling
A return piping of size 300 NB is required to be laid down by DBPL
from ACW Hot water header up to clarified water storage tanks
Fuel Oil System:

The piping from fuel oil tanks up to the fuel oil pressurizing and
forwarding pumps (supplied by BHEL) is required to be completed by
L&T.
The fuel oil pressurizing pumps are required to be installed and are to
be commissioned by BHEL for which 400 V supply shall be arranged by
L&T from 400 V switchboards being installed in the fuel oil pump house
The fuel oil piping from fuel oil pump house up to the boiler is required
to be got completed through BHEL for which the readiness of the pipe
rack PR-4 is required
Availability of ID and FD Fan:
Mechanical readiness is required to be ensured for 1 ID and 1 FD fan
including oil system and oil flushing etc.
The DMCCW system for cooling of ID fan and FD fan
11 KV cabling including protection cabling is required to be completed
for 1 ID and 1 FD fan for their operation from local / DCS including
commissioning of VFD system for ID fan
Bottom Ash Hopper:
Readiness of bottom ash hoper with refractory lining with seal truf
arrangement is required to be ensured
Compressed Air System:
At least one compressor is required to be made ready and
commissioned for supply of instrument / service air required for various
systems.

Idenntification of various system requiring instrument and service Air for


Boiler Light Up
Fire System for Boiler Operating Floor

The fire hydrant system is required to be made available with


commissioning of booster pumps for feeding fire hydrant at boiler
platform. Since the fire hydrants pumps are yet to be installed by L&T as
such this system may have to be charged by using another available
pump which can develop pressure around 6 Kg/cm 2

Status as on