You are on page 1of 67

Project: BELLWORTH

Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

01 PILING (ALL PROVISIONAL) - NOT APPLICABLE


PILING (ALL PROVISIONAL) - NOT APPLICABLE

To Collection:
CostX

Vincent Tan Associates

1/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

01 PILING (ALL PROVISIONAL) - NOT APPLICABLE

Unit

Rate

Total
(Continued)

COLLECTION
Page 1/1:
01 PILING (ALL PROVISIONAL) - NOT APPLICABLE
Carried to Summary:

CostX

Vincent Tan Associates

1/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

02 WORK BELOW LOWEST FLOOR FINISHES - NOT APPLICABLE


02 WORK BELOW LOWEST FLOOR FINISHES - NOT
APPLICABLE

To Collection:
CostX

Vincent Tan Associates

2/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

02 WORK BELOW LOWEST FLOOR FINISHES - NOT APPLICABLE

Unit

Rate

Total
(Continued)

COLLECTION
Page 2/1:
02 WORK BELOW LOWEST FLOOR FINISHES - NOT
APPLICABLE
Carried to Summary:

CostX

Vincent Tan Associates

2/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

03 STRUCTURAL FRAME AND UPPER FLOOR - NOT APPLICABLE


03 STRUCTURAL FRAME AND UPPER FLOOR - NOT
APPLICABLE

To Collection:
CostX

Vincent Tan Associates

3/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

03 STRUCTURAL FRAME AND UPPER FLOOR - NOT APPLICABLE

Unit

Rate

Total
(Continued)

COLLECTION
Page 3/1:
03 STRUCTURAL FRAME AND UPPER FLOOR - NOT
APPLICABLE
Carried to Summary:

CostX

Vincent Tan Associates

3/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

04 ROOF TRUSSES - NOT APPLICABLE


04 ROOF TRUSSES - NOT APPLICABLE

To Collection:
CostX

Vincent Tan Associates

4/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

04 ROOF TRUSSES - NOT APPLICABLE

COLLECTION
Page 4/1:
04 ROOF TRUSSES - NOT APPLICABLE
Carried to Summary:

CostX

Vincent Tan Associates

4/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

05 EXTERNAL WALLS - NOT APPLICABLE


05 EXTERNAL WALLS - NOT APPLICABLE

To Collection:
CostX

Vincent Tan Associates

5/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

05 EXTERNAL WALLS - NOT APPLICABLE

Unit

Rate

Total
(Continued)

COLLECTION
Page 5/1:
05 EXTERNAL WALLS - NOT APPLICABLE
Carried to Summary:

CostX

Vincent Tan Associates

5/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

06 EXTERNAL WALL FINISHES - NOT APPLICABLE


06 EXTERNAL WALL FINISHES - NOT APPLICABLE

To Collection:
CostX

Vincent Tan Associates

6/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

06 EXTERNAL WALL FINISHES - NOT APPLICABLE

Unit

Rate

Total
(Continued)

COLLECTION
Page 6/1:
06 EXTERNAL WALL FINISHES - NOT APPLICABLE
Carried to Summary:

CostX

Vincent Tan Associates

6/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

07 WINDOWS - NOT APPLICABLE


07 WINDOWS - NOT APPLICABLE

To Collection:
CostX

Vincent Tan Associates

7/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

07 WINDOWS - NOT APPLICABLE

COLLECTION
Page 7/1:
07 WINDOWS - NOT APPLICABLE
Carried to Summary:

CostX

Vincent Tan Associates

7/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

08 ROOF COVERING - NOT APPLICABLE


08 ROOF COVERING - NOT APPLICABLE

To Collection:
CostX

Vincent Tan Associates

8/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

08 ROOF COVERING - NOT APPLICABLE

COLLECTION
Page 8/1:
08 ROOF COVERING - NOT APPLICABLE
Carried to Summary:

CostX

Vincent Tan Associates

8/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

09 RAINWATER INSTALLATION - NOT APPLICABLE


09 RAINWATER INSTALLATION - NOT APPLICABLE

To Collection:
CostX

Vincent Tan Associates

9/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

09 RAINWATER INSTALLATION - NOT APPLICABLE

Unit

Rate

Total
(Continued)

COLLECTION
Page 9/1:
09 RAINWATER INSTALLATION - NOT APPLICABLE
Carried to Summary:

CostX

Vincent Tan Associates

9/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

10 INTERNAL WALLS AND PARTITION

BRICK WALLS
Common clay brick; in cement mortar ( 1:6 ) with plasticiser;
including reinforced concrete stiffeners and extended
reinforcement welded back to column/stiffener
reinforcement at every second course and bonding ties as
shown on the drawing, described in the specification or as
otherwise necessary and mesh reinforcement at every fourth
course and including damp proof course
A

115mm thick

155

m2

300mm thick

23

m2

335

m2

39

m2

GYPSUM BOARD PARTITION


Design, supply and fix; dry partition complete with 12.5mm
thick "Boral" gypsum board complete with 80kg/m3 rock
wool insulation including all additional work in ends, angles,
intersections and abutment, timber/metal stud and all other
necessary support to manufacturer's approval
C

150mm thick

Design, supply and fix; dry partition complete with 12.5mm


thick "Boral" gypsum board including all additional work in
ends, angles, intersections and abutment, timber/metal stud
and all other necessary support to manufacturer's approval
D

150mm thick (CEO's room)

ANY OTHER ITEMS


i) ....................................
ii) ...................................
iii) ..................................

To Collection:
CostX

Vincent Tan Associates

10/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

10 INTERNAL WALLS AND PARTITION

COLLECTION
Page 10/1:
10 INTERNAL WALLS AND PARTITION
Carried to Summary:

CostX

Vincent Tan Associates

10/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

11 DOORS
SPECIAL CONTRACTOR'S DESIGNDED ALUMINIUM
GLAZING SYSTEM
Notes
Prices for Aluminium glazing system (curtain walling,
window, door and the like) shall include for the complete
installation including all supports, fixing accessories,
matching hardware, ironmongeries, sub-frame, glass,
louvre, glazing beads, gaskets, silicon, expansion and other
joints, fixing back to structure.
The Tenderer's design submission must be complete with
full specification, type of Aluminium glazing system,
thickness and type of glass, thickness of frame, specification
for powder coating, drawings for extrusion section, and all
necessary details to fulfill the tender.
Prices for Aluminium glazing system work shall include for
all necessary design work, mock ups, wind load testing and
structural integrity testing and Professional Engineer's
calculations and endorsement, obtaining all necessary
approvals and associated associated cost there of,
preparation of shop drawings and subsequent submittal to
Architect for approval. No work shall start on site unless the
above requirement of wind load testing and structural
integrity testing and Professional Engineer's calculations and
endorsement have been approved by the
Architect/Structural Engineer.
Shop drawings submitted by the Contractor for approval
must show location, type and size of supporting framework
and must clearly indicate method of fixing of supports
shown on the Architect's drawings which are indicative only
and have no design intent. Shop drawings must be approved
by the Architect before commencement of work on site.
The tenderer shall be required to carry out a sample
mock-up of Aluminium glazing system at site before
acceptance of tender by the Employer. This shall facilitate
the Employer for selection of the curtain walling. The
tenderer shall bear all cost to comply with this mock-up
requirement including the cost of subsequent removal of
mock-up from site if the tender is not successful.

To Collection:
CostX

Vincent Tan Associates

11/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

11 DOORS

FIXED GLASS PANEL


Design, fabricate, supply and install complete in position
fixed glass panel, complete with all matching hardware;
ironmongeries such as heavy-duty hinges, lockset, stay,
handles, fastener, etc, glazing beads and gaskets; and
including glass, setting blocks including building frames in
waterproof mortar (1:3 ) and pointing frames with approved
sealant.
A

Epoxy spray painted aluminium framed fixed glass panel ;


12mm thick clear tempered glass c/w 3m frosted film to
design

46

m2

ALUMINIUM FRAME GLASS DOOR


Design, fabricate, supply and install complete in position
aluminium frame door in epoxy spray paint, complete with
aluminium subframe, all matching hardware; ironmongeries
such as heavy duty hinges,lockset, pull handle, etc; glazing
beads and gaskets; and including glass, setting blocks
including building frames in waterproof mortar (1:3 ) and
pointing frames with approved sealant all to specification; as
per schedule and detail drawings.(Ironmongeries and glass
shall be measured together):B

2150mm x 2600mm aluminium frame double swing glass


door with 12mm thick clear tempered glass (D1)

no

900mm x 2600mm aluminium frame single swing glass door


with 12mm thick clear tempered glass (D2)

no

TIMBER DOOR
Timber door frame comprising wire ties, packing, grouting
and other fixing.; door head, door jamb and door leaf
comprising top and bottom frame and stile; laminated door
leaf; complete with approved application of gloss paint/
spray paint to all timber surfaces, as per schedule and detail
drawings. (Ironmongeries shall be measured separately)
D

900mm x 2400mm single leaf timber door (D3)

no

900mm x 2400mm single leaf timber door complete with


louver (D4)

no

1020mm x 2400mm single leaf hidden timber door with


10mm groove line (D5)

no

900mm x 2400mm single leaf timber door complete with


viewing panel (D7)

no

To Collection:
CostX

Vincent Tan Associates

11/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

11 DOORS

FIRE RATED DOOR


One hour rated fire door complete with intumescent strip,
timber door frame, sub-frame; door head, door jamb, and
architrave and door leaf complete with approved paint ;
preparing and apply aluminium wood primer sealer and two
coats of gloss paint ; to all timber surfaces, including all
ironmongery like lockset, hinges, door closer as schedule
and details drawings to Inspectorate Of Fire Services
Requirements.
A

900mm x 2400mm single leaf timber door complete with


viewing panel (D7a)

no

no

no

SLIDING TIMBER POCKET DOOR


Sliding timber pocket door complete with rail track, floor
guide including ironmongeries such as handle, locksets and
etc (Ironmongeries and glass shall be measured together):B

900mm x 2400mm timber sliding door with laminated


surface and 10mm groove line (D6)

FRAMELESS SLIDING GLASS DOOR


Design, fabricate, supply and install complete in position
frameless glass door, complete with all matching hardware;
ironmongeries such as heavy duty hinges, pivot hinges,
lockset, heavy duty double action floor spring, stainless steel
pull handle, sliding track, patch fitting, etc; all to
specification; (Ironmongeries shall be measured together):C

900mm x 2400mm sliding glass door with 12mm thick clear


tempered glass (D8)

To Collection:
CostX

Vincent Tan Associates

11/3

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

11 DOORS

FRAMELESS GLASS SCREEN


Design, fabricate, supply and install complete in position
frameless glass screen complete with all matching
hardware; ironmongeries such as heavy duty hinges, pivot
hinges, lockset, heavy duty double action floor spring,
stainless steel pull handle, stainless steel patch fitting,
U-channel, etc; all to specification and as Drawing.
(Ironmongeries and glass shall be measured together)
A

2450mm x 2100mm frosted glass shower screen with 10mm


thick tempered glass ; CEO Room

no

1100mm x 2100mm frosted glass shower screen with 12


mm thick tempered glass door ; Female and Male Toilet

no

ROLLER SHUTTER
Design, fabricate, supply and install complete in position
"SKB" or approved equivalent roller shutter complete with all
matching hardware; ironmongeries such as , lockset, heavy
duty , pull handle, roller track, casings, channels, brackets,
guide rails, removable mullions, locking device and all other
accessories, etc; including building frames in waterproof
mortar (1:3 ) and pointing frames with approved sealant all
to specification; to suit structural opening (Ironmongeries
shall be measured together) :C

Overall size 2000mm x 3300mm high

no

Overall size 2450mm x 3300mm high

no

R.C lintel including all necessary formwork and


reinforcement bar (Provisional)
E

115mm x 150mm

EXISTING DOOR
F

To make good of existing doors on ground floor, including


repainting, replacement of damaged sections and
accessories, and removal debris off site.

item

To Collection:
CostX

Vincent Tan Associates

11/4

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

11 DOORS

IRONMONGERY
Supply and fix only the following ironmongery including
providing matching screws for fixing to hardwood or set in
concrete
A

Door closer

11

no

Hinges

48

no

Leaver handle complete with lock

no

Handle complete with lockset

no

Conseal door closer

no

Push plate

no

Pull handle

no

ANY OTHER ITEMS


i) ....................................
ii) ...................................
iii) ..................................

To Collection:
CostX

Vincent Tan Associates

11/5

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

11 DOORS

COLLECTION
Page 11/1:
Page 11/2:
Page 11/3:
Page 11/4:
Page 11/5:
11 DOORS
Carried to Summary:

CostX

Vincent Tan Associates

11/6

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

12 FLOOR FINISHES

INTERNALLY
IN-SITU FLOOR FINISHES;
WATERPROOFING SYSTEM
"Fosroc Brushbond" cementitious waterproofing system or
approved equivalent and including additional layer to floor
trap, pipe outlet and scupper drain all as per manufacturer's
instruction and Engineer's drawings
A

To floor of wet areas

32

m2

To wall of shower area

24

m2

To floor of wet areas; 300mm high upturn;

34

To Collection:
CostX

Vincent Tan Associates

12/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

12 FLOOR FINISHES

Pavior
SCREEDS; INTERNALLY
Cement and sand (1:3)
To floor; to receive various finishes
A

25mm thick

497

m2

497

m2

497

m2

CP1 - SUMINOE Triple Fresh II carpet tiles or approved


equivalent ; 500mm x 500mm size; laid to pattern
To floor
B

Supply ( including overheads and profit on supply and


wastage and breakage)
Supply
Wastage and breakage

RM

Overheads and profit

RM _______

Total

RM

RM _______

Fixing ( breakdown to rate given below )


Insert breakdown to fixing rate below:Sundry material for bedding,

RM

adhesive, grouting and the like and


cleaning, polishing & protecting
after laying
Labour, plant, equipment,

RM

tools and all other cost


Plywood & plastic sheet

RM

protection
Overheads and profit
Total

RM ________
RM _ ______

To Collection:
CostX

Vincent Tan Associates

12/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

12 FLOOR FINISHES

Pavior
SCREEDS; INTERNALLY
Cement and sand (1:3)
To floor; to receive various finishes
A

25mm thick

32

m2

32

m2

32

m2

CP2 - CARPET IDEAS Raw-Foundry carpet tiles or


approved equivalent ; 500mm x 500mm size; laid to pattern
To floor
B

Supply ( including overheads and profit on supply and


wastage and breakage)
Supply
Wastage and breakage

RM

Overheads and profit

RM _______

Total

RM

RM _______

Fixing ( breakdown to rate given below )


Insert breakdown to fixing rate below:Sundry material for bedding,

RM

adhesive, grouting and the like and


cleaning, polishing & protecting
after laying
Labour, plant, equipment,

RM

tools and all other cost


Plywood & plastic sheet

RM

protection
Overheads and profit
Total

RM ________
RM _ ______

To Collection:
CostX

Vincent Tan Associates

12/3

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

12 FLOOR FINISHES

Pavior
SCREEDS; INTERNALLY
Cement and sand (1:3)
To floor; to receive various finishes
A

25mm thick

m2

m2

m2

ST1 - CITATAH AMS Black Forest marble in matt finishes or


approved equivalent ; 50mm x 50mm size; laid to pattern
To floor
B

Supply ( including overheads and profit on supply and


wastage and breakage)
Supply
Wastage and breakage

RM

Overheads and profit

RM _______

Total

RM

RM _______

Fixing ( breakdown to rate given below )


Insert breakdown to fixing rate below:Sundry material for bedding,

RM

adhesive, grouting and the like and


cleaning, polishing & protecting
after laying
Labour, plant, equipment,

RM

tools and all other cost


Plywood & plastic sheet

RM

protection
Overheads and profit
Total

RM ________
RM _ ______

To Collection:
CostX

Vincent Tan Associates

12/4

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

12 FLOOR FINISHES

Pavior
SCREEDS; INTERNALLY
Cement and sand (1:3)
To floor; to receive various finishes
A

25mm thick

ST2 - CITATAH AMS Black Forest marbles in polish finishes


or approved equivalent ; laid to pattern
To floor ; approximate width 150mm
B

Supply ( including overheads and profit on supply and


wastage and breakage)
Supply
Wastage and breakage

RM

Overheads and profit

RM _______

Total

RM

RM _______

Fixing ( breakdown to rate given below )


Insert breakdown to fixing rate below:Sundry material for bedding,

RM

adhesive, grouting and the like and


cleaning, polishing & protecting
after laying
Labour, plant, equipment,

RM

tools and all other cost


Plywood & plastic sheet

RM

protection
Overheads and profit
Total

RM ________
RM _ ______

To Collection:
CostX

Vincent Tan Associates

12/5

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

12 FLOOR FINISHES

Pavior
SCREEDS; INTERNALLY
Cement and sand (1:3)
To floor; to receive skirting
A

100mm high

ST2 - CITATAH AMS Black Forest marbles in polish finishes


or approved equivalent ; laid to pattern
100mm high to skirting
B

Supply ( including overheads and profit on supply and


wastage and breakage)
Supply
Wastage and breakage

RM

Overheads and profit

RM _______

Total

RM

RM _______

Fixing ( breakdown to rate given below )


Insert breakdown to fixing rate below:Sundry material for bedding,

RM

adhesive, grouting and the like and


cleaning, polishing & protecting
after laying
Labour, plant, equipment,

RM

tools and all other cost


Plywood & plastic sheet

RM

protection
Overheads and profit
Total

RM ________
RM _ ______

To Collection:
CostX

Vincent Tan Associates

12/6

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

12 FLOOR FINISHES

Pavior
SCREEDS; INTERNALLY
Cement and sand (1:3)
To floor; to receive various finishes
A

25mm thick

93

m2

93

m2

93

m2

TL2 - NIRO Lead Grey GMY 06 Matt tiles or approved


equivalent ; 300mm x 600mm size; laid to pattern
To floor
B

Supply ( including overheads and profit on supply and


wastage and breakage)
Supply
Wastage and breakage

RM

Overheads and profit

RM _______

Total

RM

RM _______

Fixing ( breakdown to rate given below )


Insert breakdown to fixing rate below:Sundry material for bedding,

RM

adhesive, grouting and the like and


cleaning, polishing & protecting
after laying
Labour, plant, equipment,

RM

tools and all other cost


Plywood & plastic sheet

RM

protection
Overheads and profit
Total

RM ________
RM _ ______

To Collection:
CostX

Vincent Tan Associates

12/7

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

12 FLOOR FINISHES

Pavior
SCREEDS; INTERNALLY
Cement and sand (1:3)
To floor; to receive skirting
A

100mm high

48

48

48

TL2 - NIRO Lead Grey GMY 06 Matt tiles or approved


equivalent ; 300mm x 600mm size; laid to pattern
100mm high to skirting
B

Supply ( including overheads and profit on supply and


wastage and breakage)
Supply
Wastage and breakage

RM

Overheads and profit

RM _______

Total

RM

RM _______

Fixing ( breakdown to rate given below )


Insert breakdown to fixing rate below:Sundry material for bedding,

RM

adhesive, grouting and the like and


cleaning, polishing & protecting
after laying
Labour, plant, equipment,

RM

tools and all other cost


Plywood & plastic sheet

RM

protection
Overheads and profit
Total

RM ________
RM _ ______

To Collection:
CostX

Vincent Tan Associates

12/8

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

12 FLOOR FINISHES

INTERNALLY

TIMBER FLOOR
TS1 - Timber ply in NIPPON Puritan Black NP N 1982 spray
paint ; including hardwood backing
A

To floor ; approximate width 300mm

80

100mm high to skirting

207

LAMINATED FLOOR
LM3 - HOMAPAL ; 8222 laminated board or approved
equivalent ; laid to pattern : including hardwood backing
C

To floor ; approximate width 315mm

100mm high to skirting

m2

RAISE FLOOR SYSTEM


Design, supply and install HPL finish brand 'S'Vin SV
1000HPL Raised Floor System comprising of floor panels,
panel lock understructure, adjustable ms pedestal,
bracketing ; including all necessary openings for passage
trunking, power, conduits, all accessories and side
enclosure panel ; all as per manufacturer's instruction and
Architect's approval.
E

150mm high ; to Server Room

To Collection:
CostX

Vincent Tan Associates

12/9

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

12 FLOOR FINISHES

DROP & RISER


Extra over for drop to selected cement render
A

Generally

Item

Extra over for drop to selected tiles


B

Generally

Item

Extra over for drop to selected marble


C

Generally

Item

DIVIDING STRIPS
Dividing strips; embedded at junction of different finishes
D

Stainless steel dividing strips, to flush with floor finishes

ANY OTHER ITEMS

10

i) .
ii)
iii) ...

To Collection:
CostX

Vincent Tan Associates

12/10

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

12 FLOOR FINISHES

COLLECTION
Page 12/1:
Page 12/2:
Page 12/3:
Page 12/4:
Page 12/5:
Page 12/6:
Page 12/7:
Page 12/8:
Page 12/9:
Page 12/10:
12 FLOOR FINISHES
Carried to Summary:

CostX

Vincent Tan Associates

12/11

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

231

m2

1,168

m2

"LM3" Laminate to dry partition wall comprising 10mm


groove line and including all necessary accessories and
fixings as per drawing no. LD/1st/BF/609 (CEO's room)

34

m2

"LM1" Laminate to dry partition wall including all nescessary


accessories and fixings as per drawing no. LD/1st/BF/608
(CEO's room)

11

m2

Rate

Total

13 WALL FINISHES

IN-SITU WALL FINISHES; INTERNALLY


PLASTER FINISH
Plaster; cement and sand (1:3) with plasticiser; trowelled
finish including galvanised steel edge ruler, corner bead and
angle bead at corner/ edge/ angle and M.S. metal lath fixed
between different surface of brickwork and concrete
To wall and column
A

19 mm thick

INTERNAL PAINTING
Emulsion paint; preparing and apply one coat alkali resisting
primer and two finishing coats of NIPPON Eggshell NPOW
1012P emulsion paint in accordance with manufacturer's
instruction; on ceiling surfaces
B

To wall and column

LAMINATED SURFACE
C

EXISTING WALL FINISHES


E

To make good of existing wall finishes at staircase area,


including chipping off damaged plastering / painting, clean,
replastering and repainting to match new wall finishes,
including removal off site all debris.

item

To Collection:
CostX

Vincent Tan Associates

13/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

13 WALL FINISHES

INTERNAL PLASTER AND WALL TILES


Backing; cement and sand (1:3); to receive various finishes:
to pattern
To wall and column
A

20 mm thick

125

m2

125

m2

125

m2

TL 1 - NIRO White GWV 01 Matt or approved equivalent ;


300mm x 600mm size ; laid to pattern
To wall and column
B

Supply ( including overheads and profit on supply and


wastage and breakage)
Supply

RM

Wastage and breakage

RM

Overheads and profit

RM ____________

Total

RM ____________

Fixing ( breakdown to rate given below )


Insert breakdown to fixing rate below:Sundry material for bedding,

RM

adhesive, grouting and the like and


cleaning, polishing & protecting
after laying
Labour, plant, equipment,

RM

tools and all other cost


Plywood & plastic sheet

RM

protection
Overheads and profit

RM ____________

Total

RM ____________

To Collection:
CostX

Vincent Tan Associates

13/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

(Continued)

13 WALL FINISHES

Total

ANY OTHER ITEMS


i) ...................................
ii) ...................................
iii) ..................................

To Collection:
CostX

Vincent Tan Associates

13/3

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

13 WALL FINISHES

COLLECTION
Page 13/1:
Page 13/2:
Page 13/3:
13 WALL FINISHES
Carried to Summary:

CostX

Vincent Tan Associates

13/4

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

571

m2

35

m2

Rate

Total

14 CEILING FINISHES

INTERNALLY
FIBROUS PLASTER CEILING
Approved fibrous plaster ceiling including design, supply
and fix galvanised metal suspension system suspended
from slab/purlin and steel wire hanger; all to manufacturer's
instructions and setting out symmetrically from centre of
room including forming opening and including cutting and
fitting around column, air-conditioning diffuser, lights, and
the like and additional secondary support beneath air
conditioning duct, including vertical cornices, light trough,
bulkhead, access panel, u-channel, etc as shown on
drawings.
To ceiling including bulkhead, light trough, cornice, access
panel ;
A

not exceeding 3.5m above floor level

WATER RESISTANT FIBROUS PLASTER CEILING


Approved water resistant ceiling including design, supply
and fix galvanised metal suspension system suspended
from slab/purlin and steel wire hanger; all to manufacturer's
instructions and setting out symmetrically from centre of
room including forming opening and including cutting and
fitting around column, air-conditioning diffuser, lights, and
the like and additional secondary support beneath air
conditioning duct, including vertical cornices, light trough,
bulkhead, access panel, u-channel, etc as shown on
drawings.
To ceiling including bulkhead, light trough, cornice, access
panel ;
B

not exceeding 3.5m above floor level

To Collection:
CostX

Vincent Tan Associates

14/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

14 CEILING FINISHES

BORAL UNISPAN PLASTER BOARD CEILING


Approved 12 mm thick Boral Unispan plaster board ceiling
including design, supply and fix galvanised metal
suspension system suspended from slab/purlin and steel
wire hanger; all to manufacturer's instructions and setting
out symmetrically from centre of room including forming
opening and including cutting and fitting around column,
air-conditioning diffuser, lights, and the like and additional
secondary support beneath air conditioning duct, including
vertical cornices, light trough, bulkhead, access panel,
u-channel, etc as shown on drawings.
To ceiling including bulkhead, light trough, cornice, access
panel ; CEO's Office
A

not exceeding 3.5m above floor level

32

m2

39

m2

INTERNALLY
SKIM COAT ; SMOOTH FINISH
Approved equivalent skim coat finish and trowelled smooth;
all in accordance with manufacturer's instructions
To soffit of ceiling and soffit and sides of beams
B

3 mm thick; not exceeding 3.50m above floor level

To Collection:
CostX

Vincent Tan Associates

14/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

14 CEILING FINISHES

INTERNAL PAINTING
Emulsion paint; preparing and apply one coat alkali resisting
primer and two finishing coats of NIPPON Eggshell NPOW
1012P emulsion paint in accordance with manufacturer's
instruction; on ceiling surfaces
To fibrous plaster ceiling
A

not exceeding 3.50m above floor level

571

m2

35

m2

32

m2

39

m2

To water resistant fibrous plaster ceiling


B

not exceeding 3.50m above floor level


To Boral Unispan plaster board ceiling

not exceeding 3.50m above floor level


To skim coat ceiling

not exceeding 3.50m above floor level

ANY OTHER ITEMS


i) ........................................................
ii) ........................................................
iii) ........................................................

To Collection:
CostX

Vincent Tan Associates

14/3

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

14 CEILING FINISHES

COLLECTION
Page 14/1:
Page 14/2:
Page 14/3:
14 CEILING FINISHES
Carried to Summary:

CostX

Vincent Tan Associates

14/4

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

10

m2

25

m2

23

10

m2

25

m2

23

Rate

Total

15 STAIRCASE FINISHES AND RAILING


INTERNALLY
PLASTER
Skim coat; smooth finish
to soffit of landing
A

Generally
to soffit and sloping surface of staircase

Generally
to edges of staircase

300mm wide

Emulsion paint; preparing and apply one coat alkali resisting


primer and two finishing coats of NIPPON eggshell NPOW
1012P emulsion paint in accordance with manufacturer's
instruction; on plastered surfaces
to soffit of landing
D

Generally
to soffit and sloping surface of staircase

Generally
to edges of staircase

300mm wide

To Collection:
CostX

Vincent Tan Associates

15/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

15 STAIRCASE FINISHES AND RAILING

Pavior
SCREEDS; INTERNALLY
Cement and sand (1:3)
To tread; to receive various finishes
A

225mm wide

90

90

90

TL2 - NIRO Lead Grey GMY 06 Matt tiles or approved


equivalent ; 300mm x 600mm size; laid to pattern
225mm wide to tread
B

Supply ( including overheads and profit on supply and


wastage and breakage)
Supply
Wastage and breakage

RM

Overheads and profit

RM _______

Total

RM

RM _______

Fixing ( breakdown to rate given below )


Insert breakdown to fixing rate below:Sundry material for bedding,

RM

adhesive, grouting and the like and


cleaning, polishing & protecting
after laying
Labour, plant, equipment,

RM

tools and all other cost


Plywood & plastic sheet

RM

protection
Overheads and profit
Total

RM ________
RM _ ______

To Collection:
CostX

Vincent Tan Associates

15/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

15 STAIRCASE FINISHES AND RAILING

Pavior
SCREEDS; INTERNALLY
Cement and sand (1:3)
To riser; to receive various finishes
A

165mm high

99

99

99

TL2 - NIRO Lead Grey GMY 06 Matt tiles or approved


equivalent ; 300mm x 600mm size; laid to pattern
165mm high to riser
B

Supply ( including overheads and profit on supply and


wastage and breakage)
Supply
Wastage and breakage

RM

Overheads and profit

RM _______

Total

RM

RM _______

Fixing ( breakdown to rate given below )


Insert breakdown to fixing rate below:Sundry material for bedding,

RM

adhesive, grouting and the like and


cleaning, polishing & protecting
after laying
Labour, plant, equipment,

RM

tools and all other cost


Plywood & plastic sheet

RM

protection
Overheads and profit
Total

RM ________
RM _ ______

To Collection:
CostX

Vincent Tan Associates

15/3

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

15 STAIRCASE FINISHES AND RAILING

Pavior
SCREEDS; INTERNALLY
Cement and sand (1:3)
To staircase; to receive nosing tiles
A

Generally

99

99

99

TL2 - NIRO Lead Grey GMY 06 Matt tiles or approved


equivalent ; 300mm x 600mm size; laid to pattern
To nosing
B

Supply ( including overheads and profit on supply and


wastage and breakage)
Supply
Wastage and breakage

RM

Overheads and profit

RM _______

Total

RM

RM _______

Fixing ( breakdown to rate given below )


Insert breakdown to fixing rate below:Sundry material for bedding,

RM

adhesive, grouting and the like and


cleaning, polishing & protecting
after laying
Labour, plant, equipment,

RM

tools and all other cost


Plywood & plastic sheet

RM

protection
Overheads and profit
Total

RM ________
RM _ ______

To Collection:
CostX

Vincent Tan Associates

15/4

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

15 STAIRCASE FINISHES AND RAILING

Pavior
SCREEDS; INTERNALLY
Cement and sand (1:3)
To skirting profile of tread and riser
A

100mm high generally

52

52

52

TL2 - NIRO Lead Grey GMY 06 Matt tiles or approved


equivalent ; 300mm x 600mm size; laid to pattern
100mm high to skirting profile of tread and riser
B

Supply ( including overheads and profit on supply and


wastage and breakage)
Supply
Wastage and breakage

RM

Overheads and profit

RM _______

Total

RM

RM _______

Fixing ( breakdown to rate given below )


Insert breakdown to fixing rate below:Sundry material for bedding,

RM

adhesive, grouting and the like and


cleaning, polishing & protecting
after laying
Labour, plant, equipment,

RM

tools and all other cost


Plywood & plastic sheet

RM

protection
Overheads and profit
Total

RM ________
RM _ ______

To Collection:
CostX

Vincent Tan Associates

15/5

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

15 STAIRCASE FINISHES AND RAILING

Pavior
SCREEDS; INTERNALLY
Cement and sand (1:3)
To landing slab; to receive various finishes
A

Generally

10

m2

10

m2

10

m2

TL2 - NIRO Lead Grey GMY 06 Matt tiles or approved


equivalent ; 300mm x 600mm size; laid to pattern
To landing slab
B

Supply ( including overheads and profit on supply and


wastage and breakage)
Supply
Wastage and breakage

RM

Overheads and profit

RM _______

Total

RM

RM _______

Fixing ( breakdown to rate given below )


Insert breakdown to fixing rate below:Sundry material for bedding,

RM

adhesive, grouting and the like and


cleaning, polishing & protecting
after laying
Labour, plant, equipment,

RM

tools and all other cost


Plywood & plastic sheet

RM

protection
Overheads and profit
Total

RM ________
RM _______

To Collection:
CostX

Vincent Tan Associates

15/6

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

15 STAIRCASE FINISHES AND RAILING

MILD STEEL RAILING


To make good existing Railing comprising MS hollow
handrail; steel post and baluster and bottom rail; and
painting to metal surface; top baluster/ post fish tailed & cast
into concrete to Architect's specification and approval
A

To existing Staircase

ANY OTHER ITEMS

Item

i) .
ii)
iii) ...

To Collection:
CostX

Vincent Tan Associates

15/7

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

15 STAIRCASE FINISHES AND RAILING

COLLECTION
Page 15/1:
Page 15/2:
Page 15/3:
Page 15/4:
Page 15/5:
Page 15/6:
Page 15/7:
15 STAIRCASE FINISHES AND RAILING
Carried to Summary:

CostX

Vincent Tan Associates

15/8

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

16 SUNDRIES

SANITARY FITTINGS
Supply and fix only the following approved sanitary fittings
and accessories including assembling, bedding, plugging
and fixing with matching screws, jointing and connecting to
services, soil and waste pipe
A

Water Closet; TOTO OMNI, Model CW868NJ, Dual Flush


(6/3L), SW1

no

Water Closet; TOTO OMNI, Model


CW862NJWS/SW862JP, SW11

no

Hand Bidet; TOTO THX20MCRB hand bidet set in chrome,


SW2 and SW12

no

Floor trap; LECO-GRATE LG-16-CS.WA floor drain with


cockroach trap, SW3

no

Floor trap; ANFT103SF 150mm x 150mm Stainless steel


floor grating with anti-cockroach, SW13

10

no

Paper holder; TOTO TX703ARR "Rei R" Paper Holder, SW4

no

Paper holder; ABTA2801 Brass chrome finished wall


mounted toilet roll holder, SW14

no

Robe Hook; TOTO TS118WSB Double Robe Hook, SW5

no

Robe Hook; ADP4306 Brass chrome finished wall mounted


double robe hook, SW15

no

Basin; TOTO Model LW647CJ Semi-Recessed Basin set,


SW6

no

Basin; TOTO Model LW642CJ Square Semi-Recessed,


SW16

no

Basin mixer; TOTO TX109LRS "Rei S" cold pillar tap, SW7

no

Basin mixer; TOTO DONNA Series TX109LD Single Lever ,


SW17

no

Shower head and mixer; TOTO SHOWER TOWER Model


TMC95R, SW9

no

Shower head and mixer; TOTO DONNA Series TX433SD


Single Lever Shower, SW19

no

Soap holder; TOTO TX2AV1B Corner Soap Dish, SW10

no

To Collection:
CostX

Vincent Tan Associates

16/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

16 SUNDRIES

SANITARY FITTINGS (CONT'D)


Supply and fix only the following approved sanitary fittings
and accessories including assembling, bedding, plugging
and fixing with matching screws, jointing and connecting to
services, soil and waste pipe (Cont'd)
A

Soap holder; ABTA2805 Brass chrome finished wall


mounted soap basket, SW20

no

Soap Dispenser, SW24

no

Tower rack; A&E ANBTA2811 towel shelf with bar in Matt


Finished, SW25

no

Soap Dispenser, SW26

no

Wall Mounted Hand Dryer, SW27

no

Urinal; TOTO U57M Urinal Bowl with Moslem Nozzle &


Strainer, SW28

no

Single bowl drainer; A&E OCKS102/OCK002 Oreco Single


bowl single drainer inset type kitchen sink in stainless steel
c/w big waste

no

Sink Tap; A51000/HSS01 E1, Table mounted sink tap c/w


high swivel spout (HSS01), c/w locker 1 1/2 PVC bottle trap

no

To Collection:
CostX

Vincent Tan Associates

16/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

16 SUNDRIES

MIRROR
Supply and fix 6mm thick clear mirror complete with
aluminium framing all round including fixing bracket and all
accesories.
A

Overall size 1000mm x 1485mm

no

Overall size 1760mm x 1135mm

no

Overall size 1740mm x 1135mm

no

VANITY TOP
Reinforced concrete vanity top with ST2 - marble in polished
finish, including all necessary RC works, all support and
forming all opening as per drawing.
D

Overall size 1000mm (L) x 400mm (W)

no

Overall size 1740mm (L) x 400mm (W)

no

Overall size 1760mm (L) x 400mm (W)

no

TOILET CUBICLE
Supply and install 'CCG Toilet Cubicle' model CCG M5' toilet
cubicle partition and door consist of 12mm finished
thickness high pressure laminated with melamine resin
impregnated decoration paper on both sides, heavy duty
aluminium and all the necessary fittings, ironmongeries such
as lock, hook, hinges, door knob and adjustable legs in
accordance with manufacturer's detail
G

Toilet cubicle partition and door overall size 3145mm (W) x


2100mm (H) comprising 3 no. 600mm (W) x 1950mm (H)
doors; 2 no. 1370mm (W) x 2000mm (H) intermediate panel

no

Toilet cubicle partition and door overall size 1810mm (W) x


2100mm (H) comprising 3 no. 600mm (W) x 1950mm (H)
doors; 2 no. 1370mm (W) x 2000mm (H) intermediate panel
and end panel

no

Male toilet urinal partition overall size 250mm (W) x 750mm


(H)

no

To Collection:
CostX

Vincent Tan Associates

16/3

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

16 SUNDRIES

CURTAIN ROLLER BLIND


A

Supply and install curtain roller blind complete with


concealed heavy duty track, pulley accessories and all
associated works as per drawing

91

EXISTING COMPACTOR
B

To demolish /dismantle existing compactor from 14 numbers


to 9 numbers including debris from site, making good all
works disturbed as drawings

item

ANY OTHER ITEMS


i) .
ii)
iii) ...

To Collection:
CostX

Vincent Tan Associates

16/4

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

16 SUNDRIES

COLLECTION
Page 16/1:
Page 16/2:
Page 16/3:
Page 16/4:
16 SUNDRIES
Carried to Summary:

CostX

Vincent Tan Associates

16/5

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

17 BUILDER'S WORK IN CONNECTION WITH SERVICES

BUILDER'S WORK IN CONNECTION WITH SERVICES


(Please refer to BILL NO 2 - P.C. & Provisional Sum for
entitlement of payment)

Concrete formwork; sawn; temporary boxings, including


providing extra reinforcment.
In walls or slab, 100 to 150mm thick
A

for openings not exceeding 0.10m2

rate only

no

for openings 0.50 - 1.00m2

rate only

no

In beams, not exceeding 100mm diameter


C

; not exceeding 300mm thick

rate only

no

; 300 - 600mm thick

rate only

no

Coring openings in concrete; making good


In walls or slab, 100 to 150mm thick
E

for openings not exceeding 0.10m2

rate only

no

for openings 0.50 - 1.00m2

rate only

no

In beams, not exceeding 100mm diameter


G

; not exceeding 300mm thick

rate only

no

; 300 - 600mm thick

rate only

no

Sealing openings in concrete structures after services


installed; packing and sealing around ducts with fire rated
materials
In walls or slab, 100 to 150mm thick
J

for openings not exceeding 0.10m2

rate only

no

for openings 0.50 - 1.00m2

rate only

no

In beams, not exceeding 100mm diameter


L

; not exceeding 300mm thick

rate only

no

; 300 - 600mm thick

rate only

no

To Collection:
CostX

Vincent Tan Associates

17/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

17 BUILDER'S WORK IN CONNECTION WITH SERVICES

Cutting and forming openings in brick walls; including


providing and inserting precast concrete lintels; making
good

In walls; half brick thick

for openings not exceeding 0.10m2

rate only

no

for openings 0.50 - 1.00m2

rate only

no

Sealing openings in brick wallls after services installed;


packing and sealing around ducts with fire rated materials

In walls; half brick thick

for openings not exceeding 0.10m2

rate only

no

for openings 0.50 - 1.00m2

rate only

no

Starter bars
E

Drilling, apply expoxy grout; fix reinforcement bar; make


good all work disturbed 12 mm diameter bar; 450 mm girth

rate only

no

Drilling, apply expoxy grout; fix reinforcement bar; make


good all work disturbed 16 mm diameter bar; 450 mm girth

rate only

no

Drilling, apply expoxy grout; fix reinforcement bar; make


good all work disturbed 20 mm diameter bar; 450 mm girth

rate only

no

To Collection:
CostX

Vincent Tan Associates

17/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

17 BUILDER'S WORK IN CONNECTION WITH SERVICES

R.C. KERB
R.C Kerbs including concrete with reinforcement bar and
formwork.
A

to various size

rate only

no

Labour to brickwork
B

50mm x 25mm cutting grooves

rate only

no

100mm x 100mm cutting recessess

rate only

no

Labours to reinforce concrete work


D

50mm x 25mm cutting grooves

rate only

no

100mm x 100mm cutting recessess

rate only

no

ANY OTHER ITEMS


i) ...................................
ii) ...................................
iii) ..................................

To Collection:
CostX

Vincent Tan Associates

17/3

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

17 BUILDER'S WORK IN CONNECTION WITH SERVICES

Unit

Rate

Total
(Continued)

COLLECTION
Page 17/1:
Page 17/2:
Page 17/3:
17 BUILDER'S WORK IN CONNECTION WITH SERVICES
Carried to Summary:

CostX

Vincent Tan Associates

17/4

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total

18 BUILT IN FURNITURE

FURNITURE AND ACCESSORIES


Supply and fix the following approved built-in furniture and
accessories including assembling, bedding, plugging and
fixing with matching screws, jointing and connecting in
position; including backing piece, all necessary supports; all
as per drawings
To first floor ;
A

BF 1 - Built in cabinet overall size 945mm x 450mm x


2600mm high

no

BF 2 - Built in cabinet overall size 1645mm x 450mm x


2600mm high

no

BF 3 - Built in cabinet overall size 3755mm x 450mm x


2600mm high

no

BF 4 - Built in cabinet overall size 7375mm x 450mm x


2600mm high

no

BF 5 - Built in cabinet overall size 3505mm x 450mm x


2600mm high

no

BF 6 - Built in cabinet overall size 2700mm x 600mm x


750mm high

no

BF 7 - Built in L-shaped cabinet overall size 2710mm x


450mm x 2600mm high + 1375mm x 500mm x 2600mm
high

no

BF 8 - Built in cabinet overall size 1100mm x 450mm x


2600mm high

no

BF 9 - Overall size 2360mm x 1500mm high comprising of


colour glass writing board with aluminium frame all round
and aluminium ledge for marker and duster

no

BF 11 - Built in cabinet overall size 4085mm x 480mm x


2600mm high

no

BF 12 - Built in cabinet overall size 1020mm x 600mm x


2600mm high

no

BF 14 - Built in cabinet overall size 4000mm x 450mm x


1020mm high

no

BF 15 - Built in cabinet overall size 3505mm x 450mm x


2600mm high

no

BF 16 -Overall size 3505mm x 150mm x 2600mm high


comprising of colour glass writing board complete with
aluminium frame all round and aluminium ledge for marker
and duster

no

BF 17 - Cork board overall size 4770mm x 50mm x 1200mm


high

no

To Collection:
CostX

Vincent Tan Associates

18/1

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

18 BUILT IN FURNITURE
Supply and fix the following approved built-in furniture and
accessories including assembling, bedding, plugging and
fixing with matching screws, jointing and connecting in
position; including backing piece, all necessary supports; all
as per drawings (Cont'd)
To first floor ;
A

BF 18 - Built in L-shaped cabinet overall size 4760mm x


450mm x 2600mm high + 4050mm x 600mm x 2600mm
high

no

BF 19 - Built in top cabinet overall size 3355mm x 350mm x


600mm high and bottom cabinet overall size 2605mm x
600mm x 850mm high

no

Vanity cabinet overall size 1000mm x 400mm x 615mm high


(CEO's toilet)

no

Vanity cabinet overall size 1760mm x 400mm x 615mm high


(Female's toilet)

no

To second floor ;
E

BF 1 - Built in cabinet overall size 6570mm x 450mm x


2600mm high

no

BF 2 - Built in cabinet overall size 2610mm x 450mm x


2600mm high

no

BF 3 - Built in cabinet overall size 2610mm x 450mm x


2600mm high

no

BF 4 - Built in cabinet overall size 4190mm x 450mm x


2600mm high

no

BF 5 - Built in cabinet overall size 3780mm x 450mm x


1020mm high

no

BF 6 - Built in shelve overall size 1500mm x 985mm x


900mm high

no

BF 7 - Built in L-shaped cabinet overall size 2815mm x


450mm x 2600mm high

no

BF 8 - Built in cabinet overall size 2850mm x 1045mm x


1020mm high

no

BF 9 - Built in cabinet overall size 3215mm x 450mm x


2600mm high

no

To Collection:
CostX

Vincent Tan Associates

18/2

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

18 BUILT IN FURNITURE

Supply and fix the following approved built-in furniture and


accessories including assembling, bedding, plugging and
fixing with matching screws, jointing and connecting in
position; including backing piece, all necessary supports; all
as per drawings (Cont'd)
To second floor ;
A

BF 10 - Built in U-shaped cabinet overall size 2705mm x


450mm x 2600mm high + 3370mm x 450mm x 2600mm
high + 2250mm x 900mm x 2600mm high

no

BF 11 - Cork board overall size 3000mm x 50mm x 1200mm


high

no

BF 12 - Overall size 3000mm x 1200mm high comprising of


colour glass writing board complete with aluminium frame all
round and aluminium ledge for marker and duster

no

BF 13 - Built in U-shaped cabinet overall size 2500mm x


600mm x 1050mm high + 1500mm x 600mm x 1050mm
high + 2245mm x 600mm x 1050mm high

no

Vanity cabinet overall size 1740mm x 400mm x 615mm high


(Male's toilet)

no

ANY OTHER ITEMS


i) ...................................
ii) ...................................
iii) ..................................

To Collection:
CostX

Vincent Tan Associates

18/3

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

Unit

Rate

Total
(Continued)

18 BUILT IN FURNITURE

COLLECTION
Page 18/1:
Page 18/2:
Page 18/3:
18 BUILT IN FURNITURE
Carried to Summary:

CostX

Vincent Tan Associates

18/4

Project: BELLWORTH
Building: ID PACKAGE 1

Item

Details: SOP 3 (ADD.1)

Description

Quantity

COLLECTION SUMMARY

PAGE NO

01 PILING (ALL PROVISIONAL) - NOT


APPLICABLE

1/1

02 WORK BELOW LOWEST FLOOR FINISHES NOT APPLICABLE

2/1

03 STRUCTURAL FRAME AND UPPER FLOOR NOT APPLICABLE

3/1

04 ROOF TRUSSES - NOT APPLICABLE

4/1

05 EXTERNAL WALLS - NOT APPLICABLE

5/1

06 EXTERNAL WALL FINISHES - NOT


APPLICABLE

6/1

07 WINDOWS - NOT APPLICABLE

7/1

08 ROOF COVERING - NOT APPLICABLE

8/1

09 RAINWATER INSTALLATION - NOT


APPLICABLE

9/1

10 INTERNAL WALLS AND PARTITION

10/1

11 DOORS

11/1 - 11/5

12 FLOOR FINISHES

12/1 - 12/10

13 WALL FINISHES

13/1 - 13/3

14 CEILING FINISHES

14/1 - 14/3

15 STAIRCASE FINISHES AND RAILING

15/1 - 15/7

16 SUNDRIES

16/1 - 16/4

17 BUILDER'S WORK IN CONNECTION WITH


SERVICES

17/1 - 17/3

18 BUILT IN FURNITURE

18/1 - 18/3

Unit

Rate

Total

Total Amount: