Professional Documents
Culture Documents
FALCONDO REVISITED
Mr. Edwin de Jess Deveaux1 and Mr. Franscisco Geraldo Longo1
1
La Vega
Sabana del Puerto
Maimon
Falcondo
Plant
La Vega
Montaa
LA VEGA PROVINCE
MONSEOR NOUEL
PROVINCE
Bonao
Piedra
Blanca
60
Diluted Reserves
55
50
Projected Diluted Reserves
1.20 % Ni Cut - Off
40
Switch to
1.20 %Ni Cut-Off
35
Mine Planning
Ten-Year Forecast
30
Likely Scenario
1.20 %NiCut - Off
25
20
15
Projected Undiluted Reserves
1.20 %Ni Cut - Off
10
5
st
(1) 10 Year Forecast Dated Dec. 31 , 2003. Excludes Possible New Reserves to be Added By Future Reserve Definition Drilling
2027
2026
2025
2024
2023
2022
2021
2020
2019
2018
2017
2016
2015
2 014
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
1999
1 998
19 97
1996
1995
1994
1993
1992
1991
1990
0
1989
45
Summary
FALCONDO commenced operations in 1971. Ore reserves at June 2003 were 63,549,000 dry
metric tons: 1.19% Ni, at 1.20% Ni cut-off, with a mine life projected of 20 years. The annual
nickel production averages over 28,000 metric tons (Figure 3).
The richest ore is found in the finer size fractions. Consequently a rubbler plant is provided to
separate the fines from the coarse portion. All the material above 2 inches is rejected at the
rubbler mill. All the material below 2 inches is fed to the drying plant, where the material is
dried from 28% H2O (average) to 18% H2O.
The material then passes through 10 mm (3/8 inch) screens in closed circuit with 2 Barmac
crushers, one at each line. All the material below 10 mm is ore preparation product, and is
stored in 4 silos with 2,500 tonnes capacity each, prior to belt conveying to the process plant
The first stage at the process plant is reduction. The oxides are reduced after passing through
twelve vertical furnaces arranged in parallel. Finally, the reduced calcine product is melted in
two electric furnaces at 1,650 C where the ferro-nickel metal is separated from the slag. The
crude ferro-nickel is refined in a ladle refining system prior to casting into Ferrocone shapes.
The slag is discarded to slag dumps.
A power plant of 198 MW capacity supplies all the energy needed at the plant. Any excess is
sold to the national grid.
A 75-km. long pipeline (oleoduct) transports the oil from the Haina port to a topping unit at the
plant site. At the topping unit, gasoil and naphtha is produced, the latter being used mainly at
the process plant in the vertical reduction furnaces. Water for the process and power plants is
provided from a nearby river.
This paper describes improvements that have taken place in recent years for ore grade control,
methods of ore extraction and haulage and in environmental controls.
Geology Of The Deposit
The FALCONDO nickeliferous laterite deposit was formed by intense tropical weathering of
the parent bedrock serpentinized peridotite. Leaching of the more mobile elements was
followed by solution transport along preferred structures and permeable pathways and residual
concentration on the less mobile elements. In its present state, the FALCONDO nickel laterite
deposit can be classified into the following layers:
A zone: Chocolate brown limonite
B zone: Ochre brown limonite
C zone: Soft Serpentine
D zone: Hard Serpentine
E zone: Serpentinized Peridotite
F zone: Original rock
FALCONDO has utilized each of these layers: A and B (<1.20% Ni) layer is for reforestation
purposes; B, C, D and E (occasionally) layers are for mining purposes and E + F material is
used for road construction and/or road maintenance. (Table I).
Name
Limonite
(Superior
Limonite
Ochre-brown.
(Inferior
Reddish to
yellowish
Brown. Very
compact & clayey.
Some plasticity.
Laterite)
Soft
Serpentine
(Saprolite)
Hard
Serpentine
Green
Rocky
Other Comments
Chocolate-brown
Loose and friable.
Laterite)
B
Composition
Rocky
Unaltered
Ultramafics
<10%Fe. Lower %Ni than C & D zones. 50 - 70% by volume of massive angular
joint blocks (>25cms diameter).
Very high silica and magnesium. Very
USE: Commercial values or road
low sulfur and cobalt.
construction
Maximum silica and magnesium values
and minimum nickel, iron, cobalt
and sulfur.
The zoning description is referred to at FALCONDO as the Ideal Profile of Laterites. But the
area has been strongly faulted and folded and frequently pockets of one zone can be seen inside
another. This is referred to as the Real Profile of Laterites.
The peridotite ultramafic rocks found in the deposit are classified as:
Grade control is very important to the FALCONDO operation, since the deposit is very
heterogeneous. There are several aspects to applied grade control at FALCONDO:
1)
Drilling
The method now used is rotary percussion with down-the-hole hammer. The particles cut by the
drill bit, on the hammer, are pushed to the surface, by air, where they are collected in two metal
boxes located around the drill rod string. Samples are quartered and placed in bags to be sent
to the laboratory for chemical analyses. The three drilling machines are track-mounted with
attached air compressors to supply the air for the movement of the machine as well as for the
rotary percussion.
There are two main types of drill holes:
Reserve Estimation Drill Holes: These holes are 50 meters spaced. A sample is taken for each
meter drilled. The information gained is used for the estimation of the official reserves. It is also
used for the long-term 18 month and 10 year forecasts. Past drilling practice used an Air Flush
diamond drill.
Production Drill Holes: These holes are spaced at 12.5 meters. A sample is taken every two
meters. The information gained is used for grade control while mining. It is also used for shortterm forecasts. In the past, production samples were taken every meter.
As of November 2003, 58,804 meters has been drilled. The average drilling depth was 14.8 m,
with a performance of 10.5 m/hr, and a utilization of 62.9%.
In the past, drilling was carried out 24 hours/day and an additional crew was utilized to take
channel samples. Samples were quartered only at the laboratory. This practice was changed, as
follows:
The night shift for the drilling crew was eliminated, reducing labour costs without affecting
production. The helper of the morning crew, while the operator is drilling, is focused on
preparing the area to have a good production in the next shift: building access, etc. Now, the
drillers take the channel samples, instead of an additional crew.
Outsourcing of the equipment repair and maintenance has increased the mechanical
availability. (See Figure 5)
Automatic generation of maps (AUTOCAD) has saved a lot of time. Now, the Drilling
Supervisor can spend more time at the field and more people have copies of these maps.
Projects:
Drilling machine with air compressor integrated (Not attachable, but integrated). This is
in-progress.
Other evaluations
Ground Probing Radar (GPR) to detect the contact between the rock and the lateritic soil is
being evaluated
$80,000.00
Costo por
Metros
Perforados
$70,000.00
Metros
Perforados
$60,000.00
$50,000.00
$40,000.00
$30,000.00
$20,000.00
$4.77
$5.48
$4.65
$6.33
$5.84
$10,000.00
$1997
1998
1999
2000
2001
2)
Mine Planning
The assays of the drill hole samples are received in the mine planning unit after they are
validated at the drilling unit. The information in this database is used to:
At the beginning of the 1990s the Geological Information System (SIG, in Spanish) was
created. SIG is an in-house developed software, in FoxPro database. From this database,
the mineralized range is calculated and updated automatically, as well as the ore reserves.
Geological maps, cross sections, etc. are also generated automatically with this program, in
AutoCAD base.
Recently, the FoxPro database was transferred to an Oracle database, with web base, giving
more security, reliability and flexibility to the system.
Determining the density by type of ore (A, B, C, D, E and F) and application in mine
planning is now routine. Before, an average of the densities of the different types of ore was
used.
FALCONDO applies the Canadian regulations of estimating and reporting ore reserves with
2 geologists affiliated to the Association of Professional Geoscientists of Ontario (APGO).
Projects
GPS is now routinely used to update the elevations and receive a quick feedback to produce
accurate mining forecasts.
Other evaluations
A Geostatistical system to estimate reserves was evaluated. At present, the in-house "
developed software is still being used.
3)
Approximately, every 3 days the filling of a 50,000 metric tons capacity bay (ore storage) is
forecast. At each shift, there are 2 geological technicians in the field, who control the quality of
the ore mined at the mining fronts. To do that, they use visual control and information from the
geological maps and bay forecast (drill hole information) and channel samples.
There is also a senior geological technician who supervises the geological technicians, by
giving them all the tools and information needed, and who is also responsible for making the
bay readjustment. The bay readjustment consists of calculating the tonnages and
percentages of each element needed to finish the bay with all the parameters as required by the
process plant. The technicians select the appropriate available mining fronts and must include
adequate and realistic tonnages.
The geological technicians receive in-house training to visually estimate the nickel content
and other elements such as % Fe and SiO2/MgO ratio. They do that based on the physical
characteristics of the ore, mainly the color, texture, weight and friability.
The geological technicians make the decisions on ore or waste during the grade control at the
mining fronts and give instructions to the truck drivers where the material is to be hauled from
amongst several possibilities:
to the dump slip. If it is mineable ore (>1.20% Ni) and fits the required chemical
parameters at that moment,
to waste stockpiles,
to limonite stockpile, or
to stripping stockpiles
Note: If it is mineable ore, but is not required at the moment, it is left at the mining front.
A key factor for decision-making in grade control is the sampling at the face of the mining
front. Urgent Samples are sent to the laboratory when quick feedback is required of the nickel
content of a material that visually appears to have low nickel content. Urgent samples are taken
on the occasion when there are doubts about other elements such as % Fe, SiO2/MgO.
Each truck, filled with ore, is weighed and grab-sampled. A composite sample is sent to the
laboratory each 4 hours (two per shift).
The sampler gives feedback to the shovel operators about the weight of the truck, although most
of the mining trucks have weightometers integrated into the machine. The sampler also ensures
that the truck number and weight, operator name, etc. are registered on the computer.
Improvements in grade control
FALCONDO introduced the following changes in the grade control function:
Low-grade ore stockpiles now form part of the plant feed. Presently, mining is being carried
out from 1.20 to 1.39% Ni stockpiles. This material was previously stockpiled when the
mine cut-off was 1.40% Ni.
Detection and mining of pockets of ore not included in the ore reserves (20 millions tonnes
from 1971 to 1996, 14 millions tonnes from 1997 to 2002, were mined over what was
estimated in the ore reserves).
Increase of internal dilution and low-grade ore, extracted from the mining fronts. 19.1%
internal dilution plus low-grade ore has been extracted (November 2003).
Geological Production System (SPG in Spanish) computerized system allows the geological
technician to quickly handle more information. This has reduced the time needed at the
office and now the senior geological technician is investing this additional time in
supervising activities.
Operational efficiency was gained because the mine no longer requires a geological
technician and a mine supervisor by area (Peguera, Caribe and Ortega). Instead there are
Jefes de Turno (shift bosses), who are in charge of the grade control, as well as of
everything related with the operations at their areas.
Lowering the bench height decreases the dilution in the mining activity as an example from
10 m to 7 m and then to 5 m. A 7 m bench height is maintained where the mineralized layer
is thicker (Loma Caribe and Loma Ortega).
Internal audits are routinely conducted of the sampling procedures, as well as to the process
of filling a truck with ore.
Projects
FALCONDO has the following ongoing projects in the grade control function:
Projects aimed at decreasing the percentage of waste reaching the dump slip.
Laptop computers, integrated to the network so that the geological technicians are able to
see all the information (including maps) in the field. Presently, they are taking with them
hard copies with all that information.
Portable X-ray analyzer (X-met), with the objective of providing quick in-the-field
analytical results of the nickel and iron content of the material at the bench.
Ore Extraction And Haulage
Mining is by direct excavation with front shovel and backhoe. No blasting is used in the mining
activities. The mining benches are 5 m. high, except Loma Caribe and Loma Ortega (7 m).
There are two main mining methods:
Mining with front shovel: A hydraulic front excavator cuts the ore directly from the mining
front and loads the off-highway trucks (55- and 90-tonne capacity). A bulldozer is used to
condition the mining fronts, to lower the bench height and to break the rocks at the benches.
This method is better for the visual control, since the geological technician has an excellent
view of the mineralized face. This method is commonly used when the information
indicates a good distribution of the ore all along the forecasted area, and when there is ore
from top to bottom at the bench.
Mining with backhoe: A backhoe cuts the ore directly from the lower bench and fills the
trucks. A bulldozer is used to feed the ore to the shovel.
This method is better to mine selectively some isolated pockets of ore. Besides, to open a new
bench with backhoe, no ramp construction is needed, which makes this option very useful when
going to a lower bench is needed quickly.
To haul the material from Loma Ortega (48 km) the ore is sent in 50-tonne off - highway trucks
to a Transfer Area, where the 45-tonne capacity highway trucks are filled with a front loader
and the ore hauled to the plant.
As of November 2003 our heavy equipment fleet consists of:
23
10
20
3
20
20
3
5
2
Off-Highway trucks
Hydraulic excavators
Bulldozers
Front Loaders
Highway Trucks
Trailers
Graders
Water Trucks
Lowboys
Increasing the trucks from 40- and 55-tonne capacity to 90-tonne capacity.
Increasing the size of the dozers from D-7 and D-8 to D-9 CAT bulldozers.
Production Engineering System (SIP in Spanish) computerized system has helped the
efficiency of clerks and samplers and is an excellent source of timely information.
Since 2001 blasting has been used occasionally to increase the speed of the development
activities.
Surveying is now conducted with total stations, instead of the original surveying transits
Staff now uses conventional GPS to update the topography at the mining fronts.
Projects
FALCONDO has the following ongoing projects in the mine operation:
Mining the dryers reject stockpiles. This material was stockpiled when previously mining at
higher cut-off grades.
Evaluating the use of GPS (Global Positioning System) by the surveying team to update
how advancement is progressing at the mining fronts.
Environment
FALCONDO is an ISO 14001 Certified Company. The main environmental issues that are
controlled are:
Sediment Control
Presently, there are 14 earth sediment dams, which guarantee that the sediments suspended
in the running waters are retained inside FALCONDO properties and are not going to the
surrounding waters. There are permeable and not permeable dams. In streams with
permanent water running we build permeable dams. But in streams where only the
rainwater runs we build not permeable dams, especially if there is agriculture or cattle
land.
Dust Control
Five water trucks (2 in Loma Ortega) are used to water the access roads.
Operation
Country
Reserves
(Mt)
Ni%
%Ni
recov./pay.
Mining
Cash
C1
Oper.
C2
Tcash
C3
Margin
Soroawko
Indonesia
97.0
1.69
141.1
0.27
1.40
2.00
2.17
0.86
BHP Billiton
Cerro Matoso
Colombia
46.9
1.93
110.8
0.11
1.35
1.67
1.95
0.81
PT Aneka Tambang
Pomalaa
Indonesia
21.2
2.42
23.0
0.25
1.75
1.90
1.99
0.80
Codemin
Niquelandia
Brazil
5.4
1.37
14.4
0.22
1.58
1.82
2.10
0.50
FALCONDO
Bonao
Dominican Rep.
60.7
1.14
60.7
0.24
2.32
2.48
2.51
0.33
Loma de Nquel
Venezuela
41.4
4.48
43.0
1.63
2.12
2.45
0.24
SLN
Doniambo
New Caledonia
54.0
2.70
125.7
0.12
1
0.39
2.21
2.38
2.53
0.11
Larco
Larymna
Greece
48.0
1.05
43.0
0.43
2.30
2.85
3.02
-0.17
PT Inco
FALCONDO is a relatively high-cost operation. And the reasons for that are:
Pyrometallurgical Plant. It consumes a lot of energy, making the process very expensive.
Ore Reserves. After 32 years of operation the nickel content and tonnages have decreased.
Location/Logistics. Because it is located on an island, high levels of supplies and
inventories are kept and many varied ancillary facilities had to be built to guarantee some
services; for examples, a power plant, topping unit, oleoduct, water distribution system,
laboratory.
No by-products. Different from hydrometallurgical operations that are producing cobalt as a
by-product, FALCONDO only produces nickel.
The main goal at FALCONDO is to lower the operational costs. To attain this goal, the
company is focused on operating at the highest efficiency. The Mine department has achieved
this higher efficiency through:
Providing more efficient equipment and technology, thus helping to reduce the manpower
requirements.
Optimizing the ore reserves administration.
Adding new reserves.
Improving computer the system and programs.
Quality systems.
Outsourcing repair and maintenance services.
Training.
FALCONDO, despite the high fuel costs (U.S$1.92/pound at November 2003) and low-grade
nickel, is a profitable operation. It is still a very important ferronickel producer supported by
efficient personnel.
References
1.
2.
3.
4.
Deveaux, Edwin; Fras, Jos R.; Longo, Francisco. Dominican laterite production :
Mining to metal. Laterite Workshop. March, 1995.
5.
6.
7.
8.
9.