Professional Documents
Culture Documents
‡`k I gvby‡mi
‡mevq
TENDER DOCUMENT
FOR
SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF
OPTICAL FIBRE CABLE NETWORKS FOR CHUADANGA TO
DARSHANA
i
39. Tender: Clarification..................................................................17
40. Tenderer: Contacting the Employer..........................................18
41. Tender: Responsive ness..........................................................18
42. Tender: Non-conformities,Errors, and Omissions....................19
43. Tender: Correction of Arithmetical Errors.................................19
44. Tender: Preliminary Examination..............................................19
45. Tender: Technical Evaluation....................................................20
46. Tender: Financial Evaluation.....................................................20
47. Tender: No Negotiation.............................................................21
48. Tender: Comparison..................................................................21
49. Tenderer: Post-qualification......................................................22
50. Tenders: Employer’s Right to Accept or to Reject Any or All....22
G. Contract Award...................................................................................22
51. Award Criteria............................................................................22
52. Notification of Award.................................................................22
53. Performance Security................................................................23
54. Contract Signing........................................................................23
55. Advising Unsuccessful Tenderers.............................................23
56. Adjudicator.................................................................................24
57. Tenderer’s Right to Complain....................................................24
Section 2. Tender Data Sheet.......................................................................25
A. General.....................................................................................25
B. Tender Document....................................................................25
C. Evaluation and Qualification Criteria....................................25
D. Preparation of Tender.............................................................27
E. Submission of Tender............................................................28
F. Opening and Evaluation of Tender.......................................29
G. Award of Contract...................................................................29
Section 3. General Conditions of Contract.................................................30
A. General................................................................................................30
1. Definitions..................................................................................30
2. Contract Documents..................................................................32
3. Corrupt, Fraudulent, Collusive or Coercive Practices...............32
4. Interpretation.............................................................................34
5. Documents Forming the Contract and Priority of Documents. .35
6. Eligibility.....................................................................................36
7. Governing Language.................................................................36
8. Governing Law........................................................................36
9. Gratuties / Agency fees.............................................................36
10. Joint Venture, Consortium or Association (JVCA)....................36
11. Confidential Information............................................................37
12. Communic ations and Notices..................................................37
13. Copyright...................................................................................38
14. Assignment................................................................................38
15. Sub-Contracting........................................................................38
ii
16. Other Contractors......................................................................38
17. Contractor’s Responsibil- ities...................................................38
18. Employer’s Responsibil- ities....................................................38
19. Scope of Works.........................................................................39
20. Contract Price............................................................................39
21. Engineer’s Decisions.................................................................39
22. Queries about the Contract conditions......................................39
23. Delegation.................................................................................39
24. Contractor’s Personnel..............................................................39
25. Approval of the Contractor’s Temporary Works........................40
26. Instructions................................................................................40
27. Site Investigation Reports.........................................................40
28. Possession of the Site...............................................................40
29. Access to the Site......................................................................40
30. Safety, Security and Protection of the Environment.................40
31. Discoveries................................................................................41
32. Welfare of Labour......................................................................41
33. Child Labour..............................................................................41
34. No Night and Friday Work.........................................................41
35. Employer’s and Contractor’s Risks...........................................41
36. Employer’s Risks.......................................................................42
37. Contractor’s Risks.....................................................................42
38. Insurance...................................................................................43
39. Taxes and Duties......................................................................43
40. Limitation of Liability..................................................................43
41. Force Majeure...........................................................................44
B. Time Control........................................................................................44
42. The Works to Be Completed by the Intended Completion Date44
43. Programme of Works................................................................44
44. Pro Rata Progress.....................................................................45
45. Early Warning............................................................................45
46. Extension of the Intended Completion Date.............................45
47. Acceleration...............................................................................46
48. Delays Ordered by the Engineer...............................................46
49. Management Meetings..............................................................46
C. Quality Control....................................................................................47
50. Contractor to Construct the Works............................................47
51. Works open to Inspection..........................................................47
52. Identifying Defects.....................................................................47
53. Tests..........................................................................................47
54. Examination of Work before covering up..................................47
55. Correction of Defects.................................................................47
56. Uncorrected Defects..................................................................47
D. Cost Control........................................................................................48
57. Bill of Quantities.........................................................................48
58. Changes in the Quantities.........................................................48
59. Variations...................................................................................48
60. Payments for Variations............................................................48
iii
61. Cash Flow Forecasts.................................................................49
62. Payment Certificates.................................................................49
63. Payments...................................................................................49
64. Compensation Events...............................................................51
65. Change in Laws and Regulations.............................................52
66. Price Adjustment.......................................................................53
67. Retention...................................................................................53
68. Liquidated Damages.................................................................54
69. Bonus........................................................................................54
70. Advance Payment.....................................................................54
71. Performance Security................................................................55
72. Dayworks...................................................................................55
73. Cost of Repairs..........................................................................55
iv
1.7 Bill of Quantities for outside Plant........................................87
1.8 The detailed design & drawings of outside plant 88
1.9 Ordering of Materials...........................................................89
1.10 Deviation from specifications...............................................89
1.11 Modification of the specifications.........................................89
1.12 Work Priority........................................................................89
1.13 Interim Inspection/Test & Provisional Acceptance Test......89
1.14 As-built Drawings................................................................90
1.15 Guarantee Period................................................................90
1.16 Compensation ....................................................................90
Chapter-2 Design Principle..............................................91
2.1 General...............................................................................91
2.2 Design principle of civil work..............................................91
2.2.1 Manhole.............................................................................91
2.2.2 Handhole...........................................................................93
2.2.3 Underground Conduit.........................................................93
2.3 Design principle of subscriber cable network.....................94
2.3.1 Structure of subscriber cable network................................94
2.3.2 Transmission requirement for subscriber lines..................94
2.3.3 Application of cond. diameter for subscriber network........95
2.3.4 Primary cable design.........................................................95
2.3.5 Secondary cable design....................................................96
2.3.6 Cross-connection Cabinet & distribution area...................97
2.3.7 Coding systems for cables, cabinets and DPs..................98
2.3.8 Pair assignment to cabinet & distribution point.................98
2.3.9 Direct service area............................................................98
2.3.10 Distribution point( DP )....................................................98
2.3.11 Design of DP and cabinet areas.....................................99
2.3.12 Application of Distribution point......................................100
2.3.13 Splicing & Branching of buried and Conduit cable.........100
2.4 Determining of direction of cable placing........................100
2.5 Splicing............................................................................101
2.6 MDF Cable termination....................................................101
v
Section 8 Technical Specification for Cable Work........................109
vi
2.4 Terminal Block..............................................................134
2. 4.1 Size.................................................................................134
2.4.2 Jumper Terminations......................................................134
2.4.3 Protection........................................................................134
2.4.4 Push testing facilities.......................................................134
2.5 Jumper Wire..................................................................135
2.5.1 Conductor........................................................................135
2.5.2 Insulation.........................................................................135
2.5.3 Twisting...........................................................................135
2.5.4 Electrical requirement.....................................................135
2.5.5 Packing...........................................................................135
2.6 Cross-Connection Cabinet...........................................135
2.6.1 General...........................................................................135
2.6.2 Cabinet Housing..............................................................136
2.6.3 Expected Life..................................................................137
2.6.4 Termination Module of CCC...........................................137
2.6.5 Test.................................................................................139
2.6.6 Foundation......................................................................139
2.6.7 Identification....................................................................140
2.6.8 Cabinet Card...................................................................140
2.6.9 Packing...........................................................................140
2.7 Distribution Point..........................................................140
2.7.1 General...........................................................................140
2.7.2 Type & Capacity..............................................................141
2.7.3 Construction of Distribution Point....................................141
2.7.4 Requirement of Materials................................................142
2.7.5 Testing............................................................................142
2.7.6 Drop wire rings................................................................143
2.7.7 Packing...........................................................................143
2.8 Galvanized Steel Pipe...................................................143
2.8.1 General..........................................................................143
2.8.2 Galvanizing.....................................................................143
2.8.3 Structure..........................................................................143
2.8.4 Size & Load strengths.....................................................144
2.8.5 Other treatment...............................................................144
2.9 Splicing Closure & Connector for Metallic Cable......145
2.9.1 Splicing Closure..............................................................145
2.9.2 25-pair Modular connector..............................................149
2.9.3 2-wire Connector.............................................................151
2.10 Warning Tape................................................................153
2.11 Drop Wire ......................................................................154
2.11.1 General .........................................................................154
2.11.2 Conductors......................................................................154
2.11.3 Insulation.........................................................................154
2.11.4 Electrical requirement.....................................................154
2.12 Grounding Materials.....................................................154
2.12.1 General...........................................................................154
2.12.2 Groundings Rods ( Electrodes )......................................154
2.12.3 Grounding Wire...............................................................155
2.12.4 Grounding Clamps..........................................................155
vii
2.12.5 Packing.......................................................................... 155
1.1 General...........................................................................164
1.2 Manholes........................................................................166
1.3 Excavation for Manhole and/or Conduit..........................168
1.4 Excavation in Water........................................................170
1.5 Demolition and Rebuilding of existing manhole..............170
1.6 Installation of Conduit......................................................171
1.6.1 General...........................................................................171
1.6.2 Laying practice for rigid PVC Pipes................................172
1.6.3 Conduit termination of Manhole ....................................173
1.6.4 Application of Conduit Plug.............................................174
1.6.5 Jointing practice for rigid PVC pipes...............................174
1.6.6 Jointing practice for rigid PVC & GI Pipes.......................174
1.6.7 Installation of Polyvinyl Rope..........................................174
viii
1.6.8 Arrangement of Conduit in adjacent portion to Manhole,
Handhole, Cable trench and/or Cable chamber..............174
1.6.9 Mandrel Test...................................................................175
1.7 Backfilling.................................................................175
1.8 Restoration of Road Footway..................................176
1.9 Cable Chamber........................................................176
1.10 Bridge Attachments..................................................177
1.11 Culvert Crossing......................................................177
1.12 Railway/ Highway Crossing.....................................178
ix
Annexure-C Abbreviations....................................................................218
x
Invitation for Tenders
[for use when there is a SINGLE lot in a package
This is the website format and as used for published advertisement.
It is included in this document for information only]
xi
Madaripur-Barishal Route and 2)B-baria-
Hobiganj-Maulavibazar-Sylhet Route
24 Brief Description of Related Services < type in name >
Lot Identification of Lot Location Price of Tender Completion
No Tender Security Time in
Documen Amount Weeks /
t (Tk) months
(Tk)
25 1 <type in>
2
PROCURING ENTITY DETAILS
29 Name of Official Inviting Tender < type in name >
30 Designation of Official Inviting < type in name >
Tender
31 Address of Official Inviting Tender < type in name >
32 Contact details of Official Inviting < Tel. No.> <Fax No.> <e-mail>
Tender
33 The procuring entity reserves the right to accept or reject all tenders
<select> : these fields are “pop-up” fields and the procuring entity will only have to
select the correct name, address or date in order to complete the form.
<type in name> : these fields are to be completed by typing in the relevant data.
xii
Invitation for Tenders
[for use when there are MULTIPLE lots in a package
This is the website format and as used for published advertisement.
It is included in this document for information only]
GOVERNMENT OF THE PEOPLE’S REPUBLIC OF BANGLADESH
1 Ministry/Division Post and Telecommunications V
2 Agency BTCL V
3 Procuring Entity Name MD, BTCL
4 Procuring Entity Code Not used at present
5 Procuring Entity District Dhaka V
6 Invitation for < select V Works V < select V
> >
7 Invitation Ref No < type in name >
8 Date < select > V
KEY INFORMATION
9 Procurement Method OTM V < select V
>
FUNDING INFORMATION
10 Budget and Source of Funds GOB V
11 Development Partners (if None
applicable)
PARTICULAR INFORMATION
12 Project / Programme Code (if 5/5405/7000
applicable)
13 Project / Programme Name (if Internet Information Network Expansion
applicable) Project
14 Tender Package No. < type in name >
15 Tender Package Name < type in name >
Date
16 Tender Publication Date < select > V
17 Tender Last Selling Date < select > V
Date Time
18 Tender Closing Date and Time < select > V < select > V
19 Tender Opening Date and Time < select > V < select > V
20 Name & Address of the office(s) Address
- Selling Tender Document < type in name >
(Principal)
- Selling Tender Document < type in name >
(Others)
- Receiving Tender Document < type in name >
- Opening Tender Document < type in name >
21 Place / Date / Time of < type in name >
Pre-Tender Meeting (Optional) Date Time
< select > V < select > V
INFORMATION FOR TENDERER
22 Eligibility of Tenderer Eligible Tenderers having
experience of implementing OFC
installation works as described in
relevant clauses of the Tender
document
xiii
23 Brief Description of Goods or Works Supply, Installation, Testing &
Commissioning of optical fibre cable
network works in Chuadanga to
Darshana Route
24 Brief Description of Related Services < type in name >
Lot Identification of Location Price of Tender Completio
No Lot Tender Security n
Docume Amount Time in
nt (Tk) Weeks /
(Tk) months
25 1 SUPPLY, CHUADANGA 5000/- 3 lakh 3 months
INSTALLATION, DISTRICT
TESTING AND
COMMISSIONING
OF OPTICAL
FIBRE CABLE
NETWORKS IN
CHUADANGA TO
DARSHANA
ROUTE
26 2 < type in name > < type in name <type in> <type in> <type in>
>
27 3 < type in name > < type in name <type in> <type in> <type in>
>
28 4 < type in name > < type in name <type in> <type in> <type in>
>
PROCURING ENTITY DETAILS
29 Name of Official Inviting Tender < type in name >
30 Designation of Official Inviting < type in name >
Tender
31 Address of Official Inviting Tender < type in name >
32 Contact details of Official Inviting < Tel. No. > < Fax No. > < e-mail >
Tender
33 The procuring entity reserves the right to accept or reject all tenders
<select> : these fields are “pop-up” fields and the procuring entity will only have to
select the correct name, address or date in order to complete the form.
<type in name> : these fields are to be completed by typing in the relevant data.
xiv
Section 1. Instructions To Tenderers
A. General
1. Scope of 1.1 The Employer, as indicated in the Tender Data Sheet (TDS)
Tender issues this Tender Document for the procurement of Works and
Related Services incidental thereto as specified in the TDS and
as detailed in Section 6: Bill of Quantities. The name of the
Tender and the number and identification of its constituent lot(s)
are stated in the TDS.
2. Source of 2.1 The Employer has been allocated public funds as indicated
Funds in the TDS and intends to apply a portion of the funds to
eligible payments under the Contract for which this Tender
Document is issued.
2.2 For the purpose of this provision, “public funds” means any
monetary resources appropriated to procuring entities under
Government budget, or revenues generated by statutory
bodies and corporations, or aid grants and credits put at the
disposal of procuring entities by the development partners
through the Government.
4. Eligible 4.1 This Invitation for Tenders is open to eligible Tenderers from
Tenderers all countries, except for any specified in the TDS.
4.7 The Tenderer shall have the legal capacity to enter into the
Contract.
4.9 The Tenderer shall have fulfilled its obligations to pay taxes
and social security contributions under the relevant national
laws and regulations.
5. Eligible 5.1 All materials, equipment and services to be supplied under the
Materials, Contract are eligible, unless their origin is from a country
Equipment specified in the TDS.
and
Services
5.2 For purposes of this clause, “origin” means the place where the
materials and equipment are mined, grown, produced or
manufactured, or the place from which the related services are
supplied.
6. Site Visit 6.1 The Tenderer, at the Tenderer’s own responsibility and risk, is
encouraged to visit and examine the Site and obtain all
information that may be necessary for preparing the Tender
and entering into a Contract for performance of the Works.
6.3 The costs of visiting the Site shall be at the Tenderer’s own
expense
B. Tender Document
7. Tender 7.1 The Sections comprising the Tender Document are listed below,
Document: and should be read in conjunction with any Amendment issued in
accordance with ITT Clause 10.
Sections
Section 1 Instructions to Tenderers (ITT)
Section 2 Tender Data Sheet (TDS)
Section 3 General Conditions of Contract (GCC)
7.2 The Employer will reject any tender submission if the Tender
Document was not purchased directly from the Employer, or
through its agent as stated in the TDS.
8.2 The Employer shall forward copies of its response to all those
who have purchased the Tender Document, including a
description of the enquiry but without identifying its source.
10. Tender 10.1 At any time prior to the deadline for submission of Tenders, the
Document: Employer, for any reason, on its own initiative or in response to a
Amendment clarification request in writing from a Tenderer, having purchased
the Tender Document, may amend the Tender Document by
issuing an amendment.
13. Financial 13.1 The Tenderer shall have the following minimum level of
Criteria financial capacity to qualify for the performance of the Works
under the Contract.
(a) the average annual construction turnover as specified in
the TDS during the period specified in the TDS; and
(b) the minimum Tender capacity as specified in the TDS.
14. Personnel 14.1 The Tenderer shall have the following minimum level of
Capacity personnel capacity to qualify for the performance of the Works
under the Contract:
(a) a Construction Project Manager with qualifications and
experience as specified in the TDS;
(b) the minimum number of Engineers with qualifications and
experience as specified in the TDS; and
(c) other key staff with qualifications and experience as
specified in the TDS.
15. Equipment 15.1 The Tenderer shall own or have assured access through
Capacity lease, hire, or other such method, of the essential equipment,
in full working order, as specified in the TDS.
16. Joint 16.1 The figures for each of the partners of a JVCA shall be added
Venture, together to determine the Tenderer’s compliance with the
Consortium minimum qualifying criteria; however, for a JVCA to qualify, each
or of its partners must meet at least twenty-five (25) percent of
Association minimum criteria for an individual Tenderer, and the partner in
(JVCA) charge at least forty (40) percent of those minimum criteria.
Failure to comply with this requirement will result in rejection of
the JVCA Tender. SubContractors’ experience and resources
will not be taken into account in determining the Tenderer’s
compliance with the qualifying criteria.
D. Tender Preparation
17. Tender: 17.1 A Tenderer shall submit only one (1) Tender for each lot, either
Only one individually or as a partner in a JVCA. A Tenderer who submits
18. Tender: 18.1 The Tenderer shall bear all costs associated with the
Preparation preparation and submission of its Tender, and the Employer
Costs shall not be responsible or liable for those costs, regardless
of the conduct or outcome of the Tendering process.
19. Tender: 19.1 The Tender, as well as all correspondence and documents
Language relating to the Tender shall be written in the English or Bangla
language, unless specified otherwise in the TDS. Supporting
documents and printed literature furnished by the Tenderer that
are part of the Tender may be in another language, provided
they are accompanied by an accurate translation of the relevant
passages in the English or Bangla language, in which case, for
purposes of interpretation of the Tender, such translation shall
govern.
19.2 The Tenderer shall bear all costs of translation to the governing
language and all risks of the accuracy of such translation.
20. Tender: 20.1 The Tender prepared by the Tenderer shall comprise the
Contents of following:
Tender (a) the Tender Submission Sheet (Form W-1);
(b) the priced Bill of Quantities of each lot in
accordance with ITT Clauses 21 and 23 and 24;
(c) Tender Security in accordance with ITT Clause 31;
(d) alternative Tenders, if permissible, in accordance
with ITT Clause 22;
(e) written confirmation authorizing the signatory of
the Tender to commit the Tenderer, in accordance
with ITT Clause 32;
(f) documentary evidence in accordance with ITT
Clause 25 establishing the Tenderer’s eligibility to
Tender, including the Tenderer Information Sheet
(Form W-2);
(g) documentary evidence in accordance with ITT
Clause 28 establishing the Tenderer’s qualifications
to perform the Contract, if its Tender is accepted;
(h) description of work method and schedule in
accordance with ITT Clause 27; and
(i) any other document as specified in the TDS.
21. Tender: 21.1 The Tenderer shall submit the Tender Submission Sheet (Form
Submission W-1) furnished in Section 5: Tender and Contract Forms. This
Sheet and document shall be completed without any alterations to its
21.2 The Tenderer shall submit the priced Bill of Quantities using the
form furnished in Section 6: Bill of Quantities. If in preparing its
Tender, the Tenderer has made errors in the unit price or the
total price, and wishes to correct such errors prior to submission
of its Tender, it may do so, but shall ensure that each correction
is suitable initialled by the authorised person of the Tenderer
and that a statement shall be made as to the total number of
corrections made, at the end of the priced Bill of Quantities.
23. Tender: 23.1 The prices and discounts quoted by the Tenderer in the Tender
Prices and Submission Sheet (Form W1) and in the Bill of Quantities shall
Discounts conform to the requirements specified below.
23.2 The Tenderer shall fill in rates and prices for all items of the
Works described in the Bill of Quantities (BOQ). Items against
which no rate or price is entered by the Tenderer will not be
paid for by the Employer when executed and shall be deemed
covered by the rates for other items and prices in the BOQ.
23.4 The Tenderer shall quote any unconditional discounts and the
methodology for their application in the Tender Submission
23.5 Unless otherwise provided in the TDS and the PCC, the rates
and prices quoted by the Tenderer are subject to adjustment
during the performance of the Contract in accordance with
the provisions of GCC Clause 66. The Tenderer shall furnish
the indices and weightings for the price adjustment formulae
in the PCC. The Employer may require the Tenderer to justify
its proposed indices and weightings.
23.7 All duties, taxes and other levies payable by the Contractor
under the Contract, or for any other causes, as of the date
twenty-eight (28) days prior to the deadline for submission of
Tenders, shall be included in the rates and prices and the
total Tender Price submitted by the Tenderer.
25. Documents 25.1 The Tenderer shall submit documentary evidence to establish
Establishing its eligibility in accordance with ITT Clause 4, and in particular,
Eligibility of shall:
the Tenderer (a) complete the eligibility declarations in the Tender
Submission Sheet (Form W-1), included in Section 5,
Tender and Contract Forms; and
(b) if in accordance with ITT Sub-Clause 4.2, the Tenderer is
an existing or intended JVCA, it must submit the
Tenderer Information Sheet (Form W-2) and a copy of
the JVCA Agreement, or a letter of intent to enter into
such an agreement. The respective document shall be
signed by all legally authorised signatories of all the
parties to the existing or intended JVCA, as appropriate.
27. Documents 27.1 The Tenderer shall furnish a Technical Specification including a
Establishing statement of work methods and schedule and any other
the information as stipulated in TDS, in sufficient detail to
Conformity of demonstrate the adequacy for the Tenderers’ submission to
the Technical meet the work requirements and the completion time.
Specification
28. Documents 28.1 Tenderers shall submit documentary evidence to meet the
Establishing qualification criteria specified in Sub-Section C, Qualification
the Criteria of the ITT.
30. Tender: 30.1 Tenders shall remain valid for the period specified in the TDS
Validity after the date of Tender submission prescribed by the
Employer, pursuant to ITT Clause 34. A Tender valid for a
shorter period shall be rejected by the Employer as non
responsive.
31. Tender: 31.1 The Tenderer shall furnish as part of its Tender, a Tender
Security Security in original form (Form W-3) and in the amount specified
in the TDS.
32. Tender: 32.1 The Tenderer shall prepare one (1) original of the documents
Format and comprising the Tender as described in ITT Sub-Clause 20.1 and
Signing clearly mark it “ORIGINAL.” In addition, the Tenderer shall
prepare the number of copies of the Tender, as specified in the
TDS and clearly mark each of them “COPY.” In the event of
any discrepancy between the original and the copies, the
original shall prevail.
32.2 The original and each copy of the Tender shall be typed or
written in indelible ink and shall be signed by the person duly
authorized to sign on behalf of the Tenderer. This authorization
shall consist of a written authorization and shall be attached to
Tender Document for OFC Network of Info-bahan Project
Page 14 of 147
the Tenderer Information Sheet (Form W-2). The name and
position held by each person signing the authorization must be
typed or printed below the signature. All pages of the original
and of each copy of the Tender, except for un-amended printed
literature, shall be numbered sequentially and signed or initialled
by the person signing the Tender.
E. Tender Submission
33. Tender: 33.1 The Tenderer shall enclose the original in one (1) envelope and
Sealing and all the copies of the Tender in another envelope, duly marking
Marking the envelopes as “ORIGINAL” and “COPY.” These two (2)
envelopes shall then be enclosed in one (1) single outer
envelope.
33.2 The inner and outer envelopes shall:
(a) bear the name and address of the Tenderer;
(b) be addressed to the Employer at the address specified in
the TDS;
(c) bear the name of the Tender and the Tender Number as
specified in the TDS; and
(d) bear a statement “DO NOT OPEN BEFORE…………...”
the time and date for Tender opening as specified in the
TDS..
33.3 If all envelopes are not sealed and marked as required by ITT
Sub-Clause 33.2, the Employer will assume no responsibility for
the misplacement or premature opening of the Tender
34. Tender: 34.1 The Employer must receive the Tenders at the address specified
Submission in ITT Sub Clause 33.2 with no later than the date and time
Deadline specified in the TDS.
34.3 The Employer may, at its discretion, extend the deadline for the
submission of Tenders by amending the Tender Document in
accordance with ITT Clause 10, in which case all rights and
obligations of the Employer and Tenderers previously subject to
the deadline shall thereafter be subject to the new deadline as
extended.
35. Tender: 35.1 Any Tender received by the Employer after the deadline for
36. Tender: 36.1 A Tenderer may modify, substitute or withdraw its Tender after it
Modification has been submitted by sending a written notice, duly signed by
, the same authorized representative, and shall include a copy of
Substitution the authorization in accordance with ITT Sub-Clause 32.2,
or (except that no copies of the withdrawal notice are required). The
Withdrawal corresponding substitution or modification of the Tender must
accompany the respective written notice. The written notice must
be:
(a) submitted in accordance with ITT Clauses 32 and 33
(except that withdrawal notices do not require copies), and
in addition, the respective envelopes shall be clearly
marked “MODIFICATION”, “SUBSTITUTION”, OR
“WITHDRAWAL”; and
(b) received by the Employer prior to the deadline prescribed
for submission of Tenders, in accordance with ITT Clause
34.
36.4 Tenderers may only offer discounts to, or otherwise modify the
prices of their Tenders by including Tender modifications in the
original Tender submission, or by submitting Tender
modifications in accordance with ITT Sub-Clause 30.1.
37. Tender: 37.1 The Employer shall open the Tenders in public, including
Opening modifications or substitutions made pursuant to ITT Clause 36, at
the time, on the date, and only at the one place specified in the
TDS. Tenders for which an acceptable notice of withdrawal has
been submitted pursuant to ITT Clause 36 shall not be opened.
Tenderers or their authorised representatives shall be allowed to
attend and witness the opening of Tenders, and shall sign a
register evidencing their attendance.
38. Tender: 38.1 After the opening of Tenders, information relating to the
Confidentiality examination, clarification, and evaluation of Tenders and
recommendations for award shall not be disclosed to Tenderers
or other persons not officially concerned with the evaluation
process until after the award of the Contract is announced.
39. Tender: 39.1 The Employer may ask Tenderers for clarification of their
Clarification Tenders in order to facilitate the examination and evaluation of
Tenders. The request for clarification and the response shall be
in writing, and any changes in the prices or substance of the
Tender shall not be sought, offered or permitted, except to
confirm the correction of arithmetical errors discovered by the
Employer in the evaluation of the Tenders, in accordance with
ITT Clause 43.
40. Tenderer: 40.1 Following the opening of the Tenders and until the Contract is
Contacting signed no Tenderer shall make any unsolicited communication
the to the Employer or try in any way to influence the Employer’s
Employer examination and evaluation of the Tenders.
42. Tender: 42.1 The Employer may regard a Tender as responsive even if it
Non- contains minor deviations that do not materially alter or depart
conformities from the characteristics, terms, conditions and other requirement
, Errors, set forth in the Tender Document or if it contains errors or
and oversights that are capable of being corrected without affecting
Omissions the substance of the Tender.
43. Tender: 43.1 Provided that the Tender is substantially responsive, the
Correction Employer shall correct arithmetical errors on the following
of basis:
Arithmetical (a) if there is a discrepancy between the unit price and the
Errors line item total price that is obtained by multiplying the unit
Tender Document for OFC Network of Info-bahan Project
Page 18 of 147
price and quantity, the unit price shall prevail and the line
item total price shall be corrected, unless in the opinion of
the Employer there is an obvious misplacement of the
decimal point in the unit price, in which case the total price
as quoted shall govern and the unit price shall be
corrected;
(b) if there is an error in a total corresponding to the addition
or subtraction of subtotals, the subtotals shall prevail and
the total shall be corrected; and
(c) if there is a discrepancy between words and figures, the
amount in words shall prevail, unless the amount
expressed in words is related to an arithmetical error, in
which case the amount in figures shall prevail subject to
(a) and (b) above.
43.3 Any Tenderer that does not accept the correction of errors, as
determined by the application of ITT Sub-Clause 43.1, shall be
disqualified and its Tender Security may be forfeited.
44. Tender: 44.1 The Employer shall firstly examine the Tenders to confirm that all
Preliminary documentation requested in ITT Clause 20 has been provided,
Examination and to determine the completeness of each document submitted.
45. Tender: 45.1 The Employer shall secondly examine the Tender to confirm that
Technical all terms and conditions specified in the GCC and the PCC have
Evaluation been accepted by the Tenderer without any material deviation or
reservation.
45.2 The Employer shall evaluate the technical aspects of the Tender
submitted in accordance with ITT Clauses 26 and 27, to confirm
that all requirements specified in Section 7: General
Specifications and Section 8: Particular Specifications of the
Tender Document have been met without any material deviation
or reservation.
45.3 If, after the examination of the terms and conditions and the
technical aspects of the Tender, the Employer determines that
the Tender is not substantially responsive in accordance with ITT
Sub-Clause 41.3, it shall reject the Tender.
47. Tender: No 47.1 No negotiations shall be held with the lowest or any other
Negotiation Tenderer.
48. Tender: 48.1 The Employer shall compare all substantially responsive
Comparison Tenders to determine the lowest-evaluated Tender, in
accordance with ITT Clause 46.
49. Tenderer: 49.1 The Employer shall determine to its satisfaction whether the
Post- Tenderer that is selected as having submitted the lowest
qualification evaluated and substantially responsive Tender is qualified to
perform the Contract satisfactorily.
G. Contract Award
51. Award 51.1 The Employer shall award the Contract to the Tenderer
Criteria whose offer is substantially responsive to the Tender
Document and that has been determined to be the lowest
evaluated Tender, provided further that the Tenderer is
determined to be qualified to perform the Contract
satisfactorily.
52. Notification 52.1 Prior to the expiration of the period of Tender validity, the
of Award Employer shall notify the successful Tenderer, in writing, that its
Tender has been accepted.
52.3 The Notification of Award shall state the value of the proposed
Contract, the amount of the Performance Security, the time
within which the Performance Security shall be submitted and
the time within which the Contract shall be signed.
53. Performance 53.1 Within fourteen (14) days of the receipt of Notification of
Security Award from the Employer, the successful Tenderer shall
furnish the Performance Security for the due performance of
the Contract in the amount specified in the TDS using for that
purpose the Performance Security Form (Form W-6)
furnished in Section 5: Tender and Contract Forms.
54. Contract 54.1 At the same time as the Employer issues the Notification of
Signing Award, the Employer shall send the Contract Agreement and all
documents forming the Contract, to the successful Tenderer.
55. Advising 55.1 Upon the successful Tenderer’s furnishing of the Performance
Unsuccessful Security pursuant to ITT Clause 53, and signing of the Contract
Tenderers pursuant to ITT Clause 54, the Employer shall also notify all
other Tenderers that their Tenders have been unsuccessful.
56. Adjudicator 56.1 The Employer proposes the person named in the TDS to be
appointed as Adjudicator under the Contract, at an hourly fee
and for those reimbursable expenses specified in the TDS.
57. Tenderer’s 57.1 Any Tenderer has the right to complain if it has suffered or
Right to may suffer loss or damage due to a breach of a duty imposed
Complain on the Employer by the Public Procurement Regulations 2003
(PPR).
57.3 If not satisfied with the outcome of the administrative review, the
Tenderer may complain to the Review Panel pursuant to Regulation
53 of the PPR.
ITT Clause Amendments of, and Supplements to, Clauses in the Instructions to
Tenderers
A. General
ITT 4.1 Tenderers from the following countries are not eligible: Israel
ITT 5.1 Materials, equipment and service from the following countries are not eligible:
Israel.
B. Tender Document
ITT 7.2 The following are authorised agents of the Employer for the purpose of issuing
the Tender Document: None.
ITT 9.1 A Pre- Bid meeting will be held on as mentioned (if any) in Tender Notice.
ITT 13.1(a) The required average annual turnover shall be greater than Taka 1.25 crore
during the period of last Five (5) years for each lot.
ITT The minimum Tender Capacity shall be: Taka 1.00 crore.
13.1(b)
ITT 13.2 The minimum amount of free funds (liquid assets) and / or credit facilities net
of other Contractual commitments of the successful Tenderer shall be Taka
60 lakh.
ITT 14.1(a) The Construction Project Manager shall have the following qualifications and
experience:
5 (five) years experience of completing similar type of Project having
educational qualification minimum Bachelor Degree.
ITT 14.1(b) The Minimum number of Engineers with qualifications and minimum
experience shall be as follows:
1) Civil Engr. (3 yrs. related experience) : 1 Nos
2) Elect./Mech. Engr. (3 yrs.related experience) : 1 Nos.
3) Diploma Civil Engr. ( 3 yrs related experience) : 2 Nos.
4) Dipl. Elect/ Mech./Power Engr. (3 yrs related exp.) : 2 Nos.
ITT 14.1(c) Other key staff (Drafts man, masons, optic fiber jointer etc.) with requisite
qualification and experience shall be not less than 10 nos. A list of such
personnel along with Bio-data & attested photo shall be submitted with the
Tender.
ITT 15.1 In order to ensure the quality work and compete the work in time, the
Tenderer shall own or have assured access of the minimum no. of essential
Tender Document for OFC Network of Info-bahan Project
Page 26 of 147
equipment, in full working order for each lot as follows:
1) Cable Lifter - 2 Nos.
2) GPS Receiver device - 2 No.
3) Powerful OFC blowing machine - 1 Nos.
4) OFC Splicing machine - 2 Nos.
5) Sweep rod ( 300m each) -2 set
6) Truck (5 Ton Capacity) - 2 Nos.
7) Powerful Winch Machine - 2 Nos.
8) Pulling Coil (300m each) - 3 Nos.
9) Measuring Wheel - 4 Nos.
10) OTDR - 2 Nos.
11) Mobile Generator (5 KVA) - 2 Nos.
12) Steel Shuttering Material - 400 Sq-ft
13) Decoiler - 2 Nos.
The Tenderer shall enclose a list of own construction machineries &
accessories to the Tender. BTCL evaluation team so formed can verify this
list during the evaluation.
D. Preparation of Tender
ITT 19.1 The Tender, as well as all correspondence and documents relating to the
Tender shall be in the Bangla or English.
ITT 20.1(i) The Tenderer shall submit with its Tender the following additional
documents:
1) Clause by Clause compliance schedule to all the
clauses (Including sub-clauses) of Section 7 and 8 of
the Tender Document as per Annex-A.
2) List of Deviations as per Annex-B.
3) All other documents listed in the Tender Notice.
ITT 23.5 The prices quoted by the Tenderer shall be fixed for the duration of the
Contract.
ITT 23.6 Tenders are being invited for one lot under a single package
&
ITT 46.5
ITT 31.1 The amount of the Tender Security shall be Taka 3.00 lakh.
ITT 32.1 In addition to the original document of the Tender, two (2) additional
copies shall be submitted.
E. Submission of Tender
ITT 33.2 (c) The Tender and Tender No.: As mentioned on the front page of the document.
ITT 33.2 (d) Do not open before the date & time as of the Invitation for Tender or as of
subsequent corrigendum (if any ).
ITT 34.1 For Tender submission purposes only, the Employer’s address is:
Director (Procurement)
Sher-e-Bangla Nagar Telephone Exchange Annex. Bldg.
BTCL, Sher-e-Bangla Nagar, Dhaka.
ITT 37.1 The Tender opening shall take place at: At Director ( Procurement ) office
Address:
Director (Procurement)
Sher-e-Bangla Nagar Telephone Exchange Annex. Bldg.
BTCL, Sher-e-Bangla Nagar, Dhaka.
Time & Date: as of the Invitation for tender or as of subsequent
corrigendum (if any ).
G. Award of Contract
ITT 56.1 The case will be referred to the Managing Director, BTCL.
ITT 56.2 The dispute case will be referred to the Managing Director BTCL.
ITT 57.2 The name and address of the office where complaints to the Procuring Entity
under Regulation 51 are to be submitted is:
Managing Director
Bangladesh Telecommunications Company Limited
Telejogajog Bhaban
37/E, Eskaton Garden, Dhaka.
Bangladesh.
A. General
1. Definitions 1.1 The following words and expressions shall have the
meaning hereby assigned to them. Boldface type is used to
identify the defined terms:
(a) The Adjudicator is the person
appointed jointly by the Employer and the Contractor to
resolve disputes in the first instance, as provided for in
GCC Sub-Clause 82.2.
(b) Bill of Quantities means the priced and
completed Bill of Quantities forming part of the Tender.
(c) Compensation Events are those
defined in GCC Clause 64.
(d) Completion Certificate means the
Certificate issued by the Engineer as evidence that the
Contractor has executed the Works in all respects as
per drawing, specifications and Conditions of Contract.
(e) The Completion Date is the date of
completion of the Works as certified by the Engineer, in
accordance with GCC Clause 74.
(f) Contract Agreement means the
Agreement entered into between the Employer and the
Contractor, together with the Contract Documents
referred to therein, including all attachments,
appendices, and all documents incorporated by
reference therein to execute, complete, and maintain
the Works.
(g) Contract Documents means the
documents listed in GCC Clause 5, including any
amendments thereto.
(h) Contractor means the natural person,
private or government enterprise, or a combination of
the above, whose Tender to carry out the Works has
been accepted by the Employer and is named as such
in the PCC and the Contract Agreement, and includes
the legal successors or permitted assigns of the
Contractor.
(i) Contract Price means the price
payable to the Contractor as specified in the Contract
Agreement, subject to such additions and adjustments
thereto or deductions therefrom, for the execution,
completion and maintenance of the Works in
accordance with the provisions of the Contract.
(j) The Contractor’s Tender is the
2. Contract 2.1 Subject to the order of precedence set forth in GCC Sub-
Documents Clause 5.1, all documents forming the Contract (and all
parts thereof) are intended to be correlative,
complementary, and mutually explanatory.
4. Interpretation 4.1 In interpreting the GCC, singular also means plural, male
also means female or neuter, and the other way around.
Headings in the GCC shall not be deemed part thereof or be
taken into consideration in the interpretation or construance
of the Contract. Words have their normal meaning under the
language of the Contract unless specifically defined.
4.4 Severability
(a) If any provision or condition of the Contract is prohibited or
rendered invalid or unenforceable, such prohibition,
invalidity or unenforceability shall not affect the validity
or enforceability of any other provisions and conditions
of the Contract.
10. Joint Venture, 10.1 If the Contractor is a joint venture, consortium, or association,
Consortium or all of the parties shall be jointly and severally liable to the
Association Employer for the fulfilment of the provisions of the Contract and
(JVCA) shall designate one party to act as a leader with authority to
bind the joint venture, consortium, or association. The
composition or the constitution of the joint venture, consortium,
or association shall not be altered without the prior consent of
the Employer.
11.2 The Employer shall not use such documents, data, and other
information received from the Contractor for any purposes
unrelated to the Contract. Similarly, the Contractor shall not
use such documents, data, and other information received
from the Employer for any purpose other than the design,
construction, or other work and services required for the
performance of the Contract.
11.4 The above provisions of GCC Clause 11 shall not in any way
modify any undertaking of confidentiality given by either of the
parties hereto prior to the date of the Contract in respect of the
Works or any part thereof.
13. Copyright 13.1 The copyright in all drawings, documents, and other materials
containing data and information furnished to the Employer by
the Contractor herein shall remain vested in the Contractor, or,
if they are furnished to the Employer directly or through the
Contractor by any third party, including Contractors of
materials, the copyright in such materials shall remain vested
in such third party.
14. Assignment 14.1 The Contractor shall not assign, in whole or in part, its
obligations under the Contract, except with the Employer’s
prior written consent.
15. Sub- 15.1 The Contractor shall obtain approval of the Employer in writing
Contracting of all Sub-Contracts to be awarded under the Contract if not
already specified in the Tender. Sub-Contracting shall in no
event relieve the Contractor from any of its obligations, duties,
responsibilities, or liability under the Contract.
16. Other 16.1 The Contractor shall cooperate and share the Site with other
Contractors Contractors, public authorities, utilities, the Engineer and the
Employer between the dates given in the Schedule of Other
Contractors, as referred to in the PCC. The Contractor shall
also provide facilities and services for them as described in the
Schedule. The Employer may modify the Schedule of Other
Contractors, and shall notify the Contractor of any such
modification.
17. Contractor’s 17.1 The Contractor shall execute and complete the Works and
Responsibil- remedy any defects therein in conformity in all respects with
ities the provisions of the Contract Agreement.
18. Employer’s 18.1 The Employer shall pay the Contractor, in consideration of the
Responsibil- execution and completion of the Works and the remedying of
ities defects therein, the Contract Price or such other sum as may
become payable under the provisions of the Contract at the
times and in the manner prescribed by the Contract
Agreement.
18.2 The Employer shall make its best effort to assist the Contractor
in obtaining, if required, any permit, licence, and approvals
from local public authorities.
21. Engineer’s 21.1 Except where otherwise specifically stated in the PCC, the
Decisions Engineer will decide Contractual matters between the
Employer and the Contractor in its role as representative of
the Employer.
22. Queries about 22.1 The Engineer will clarify queries on the Conditions of
the Contract Contract.
conditions
23. Delegation 23.1 The Engineer may delegate any of his duties and
responsibilities to his representative except to the
Adjudicator, after notifying the Contractor, and may cancel
any delegation, without retroactivity, after notifying the
Contractor.
24. Contractor’s 24.1 The Contractor shall employ the key personnel named in the
Personnel Schedule of Key Personnel, as referred to in the PCC, to
carry out the functions stated in the Schedule or other
personnel approved by the Engineer.
25. Approval of 25.1 The Contractor shall submit Specifications and Drawings
the showing the proposed Temporary Works to the Engineer,
Contractor’s who is to approve them, if they comply with the Specifications
Temporary and Drawings.
Works
25.2 The Contractor shall be responsible for design of Temporary
Works.
26. Instructions 26.1 The Contractor shall carry out all instructions of the Engineer
that comply with the applicable laws where the Site is
located.
27. Site 27.1 The Contractor, in preparing the Tender, shall rely on any Site
Investigation Investigation Reports referred to in the PCC, supplemented
Reports by any information available to the Tenderer.
28. Possession of 28.1 The Employer shall give possession of the Site, or parts of
the Site the Site, to the Contractor on the date(s) stated in the PCC.
If possession of a part is not given by the date stated in the
PCC, the Employer will be deemed to have delayed the start
of the relevant activities, and this will be a Compensation
Event.
29. Access to the 29.1 The Contractor shall allow the Engineer and any person
Site authorised by the Engineer access to the Site and to any
place where work in connection with the Contract is being
carried out or is intended to be carried out.
30. Safety, 30.1 The Contractor shall throughout the execution and
Security and completion of the Works and the remedying of any defects
Protection of therein:
the (a) have full regard for the safety of all persons entitled to be
Environment upon the Site and keep the Site and the Works in an
orderly state;
(b) provide and maintain at the Contractor’s own cost all
Tender Document for OFC Network of Info-bahan Project
Page 40 of 147
lights, guards, fencing, warning signs and watching for
the protection of the Works or for the safety on-site, and
(c) take all reasonable steps to protect the environment on
and off the Site and to avoid damage or nuisance to
persons or to property of the public or others resulting
from pollution, noise or other causes arising as a
consequence of the Contractors methods of operation.
32. Welfare of 32.1 The Contractor shall provide proper accommodation to his
Labour labourers and arrange proper water supply, conservancy and
sanitation arrangements at the site in accordance with
relevant regulations, rules and orders of the government.
33. Child Labour 33.1 The Contractor shall comply with the applicable minimum age
labour laws and requirements of (including applicable treaties
which have been ratified by) the Government of Bangladesh
regarding hazardous forms of child labour.
34. No Night and 34.1 The Contractor shall not perform any work on the Site on the
Friday Work weekly rest day (Friday), or during the night, or on any
religious or public holiday, without the prior written approval
of the Engineer.
35. Employer’s 35.1 The Employer carries the risks that the Contract states are
and Employer’s risks and the Contractor carries the risks that the
Contractor’s Contract states are Contractor’s risks.
Risks
37. Contractor’s 37.1 From the Start Date until the Defects Correction Certificate
Risks has been issued, the risks of personal injury, death, and loss
of or damage to property (including, without limitation, the
Works, Plant, Materials, and Equipment) which are not
Employer’s risks are Contractor’s risks.
38.3 If the Contractor does not provide any of the policies and
certificates required, the Employer may effect the insurance
which the Contractor should have provided and recover the
premiums the Employer has paid from payments otherwise
due to the Contractor or, if no payment is due, the payment
of the premiums shall be a debt due.
39. Taxes and 39.1 The Contractor shall be entirely responsible for all taxes,
Duties duties, license fees, and other such levies imposed outside and
inside Bangladesh.
41. Force 41.1 The Contractor shall not be liable for forfeiture of its
Majeure Performance Security, liquidated damages, or termination for
default if and to the extent that its delay in performance or other
failure to perform its obligations under the Contract is the result
of an event of Force Majeure.
B. Time Control
42. The Works to 42.1 The Contractor may commence execution of the Works on
be Completed the Start Date and shall carry out the Works in accordance
by the with the Programme submitted by the Contractor, as
Intended updated with the approval of the Engineer, and complete
Completion them by the Intended Completion Date.
Date
43. Programme of 43.1 Within the time stated in the PCC, the Contractor shall
Works submit to the Engineer for approval a Programme showing
the general methods, arrangements, order, and timing for all
the activities in the Works. The programme may be in the
form of an Implementation Schedule prepared in Microsoft
Project or in any other software programme acceptable by
the Employer.
44. Pro Rata 44.1 The Contractor shall maintain Pro Rata progress of the
Progress works. Progress to be achieved shall be pursuant to GCC
Sub- Clause 43.1 and shall be determined in terms of the
value of the works done
45. Early Warning 45.1 If at any time during performance of the Contract, the
Contractor or its Sub Contractors should encounter events,
circumstances conditions that may adversely affect the
quality of the work, increase the Contract Price or delay the
execution of the Works, the Contractor shall promptly notify
the Engineer in writing of the delay, its likely duration, and its
cause. As soon as practicable after receipt of the
Contractor’s notice, the Engineer shall evaluate the situation,
and the Contractor shall cooperate with the Engineer in
making and considering proposals for how the effect of such
an event or circumstance can be avoided or reduced. The
Engineer may require the Contractor to provide an estimate
of the expected effect of the future event or circumstance on
the Contract Price and Completion Date. The Contractor
shall provide the estimate as soon as reasonably possible.
46. Extension of 46.1 The Engineer shall extend the Intended Completion Date if a
the Intended Compensation Event occurs or a Variation is issued which
Completion makes it impossible for Completion to be achieved by the
Date Intended Completion Date without the Contractor taking
steps to accelerate the remaining work, which would cause
the Contractor to incur additional cost. The Engineer shall
notify the Contractor accordingly, with a copy of the
Employer.
47. Acceleration 47.1 When the Employer wants the Contractor to finish before the
Intended Completion Date, the Engineer will obtain priced
proposals for achieving the necessary acceleration from the
Contractor. If the Employer accepts these proposals, the
Intended Completion Date will be adjusted accordingly and
confirmed by both the Employer and the Contractor.
48. Delays 48.1 The Engineer may instruct the Contractor to delay the start
Ordered by or progress of any activity within the Works.
the Engineer
49. Management 49.1 Either the Engineer or the Contractor may require the other
Meetings to attend a management meeting. The business of a
management meeting shall be to review the plans for
remaining work and to deal with matters raised in
accordance with the early warning procedure.
50. Contractor to 50.1 The Contractor shall construct and install the Works in
Construct the accordance with the Specifications and Drawings as
Works scheduled in GCC Sub-Clause 5.1.
51. Works open to 51.1 All works under the Contract shall at all times be open to
Inspection inspection and supervision of the Engineer, and the
Contractor shall ensure presence of its representatives at
such inspections provided proper advance notice is given by
the Engineer.
52. Identifying 52.1 The Engineer shall check the Contractor’s work and notify
Defects the Contractor of any Defects that are found. Such checking
shall not affect the Contractor’s responsibilities. The
Engineer may instruct the Contractor to search for a Defect
and to uncover and test any work that the Engineer considers
may have a Defect.
53. Tests 53.1 If the Engineer instructs the Contractor to carry out a test
not specified in the Specification to check whether any work
has a Defect and the test shows that it does, the Contractor
shall pay for the test and any samples. If there is no Defect,
the test shall be a Compensation Event.
54. Examination 54.1 No part of the Works shall be covered up or put out of view
of Work without the approval of the Engineer. The Contractor shall
before give notice in writing to the Engineer whenever any such part
covering up of the Works is ready for examination and the Engineer shall
attend to such examination without unreasonable delay.
55. Correction of 55.1 The Engineer shall give notice to the Contractor, with a
Defects copy to the Employer, of any Defects before the end of the
Defects Liability Period, which begins at Completion, and is
defined in the PCC. The Defects Liability Period shall be
extended for as long as Defects remain to be corrected.
56. Uncorrected 56.1 If the Contractor has not corrected a Defect within the time
Defects specified in the Engineer’s notice, the Engineer will assess
the cost of having the Defect corrected, and the Contractor
will pay this amount.
D. Cost Control
57. Bill of 57.1 The Bill of Quantities shall contain items for the
Quantities construction, installation, testing, and commissioning work to
be done by the Contractor.
58. Changes in 58.1 If the final quantity of the work done differs from the
the Quantities quantity in the Bill of Quantities for the particular item by more
than twenty-five percent (25%), provided the change exceeds
one percent (1%) of the Initial Contract Price, the Engineer
shall adjust the rate to allow for the change.
60. Payments for 60.1 The Contractor shall provide the Engineer with a quotation
Variations for carrying out the Variation when requested to do so by the
Engineer. The Engineer shall assess the quotation, which
shall be given within seven days of the request or within any
longer period stated by the Engineer and before the Variation
is ordered.
61. Cash Flow 61.1 When the Programme is updated, the Contractor shall
Forecasts provide the Engineer with an updated cash flow forecast.
62. Payment 62.1 The Contractor shall submit to the Engineer monthly
Certificates statements of the estimated value of the work executed less
the cumulative amount certified previously.
62.4 The value of work executed shall comprise the value of the
quantities of the items in the Bill of Quantities completed.
63. Payments 63.1 Payments shall be adjusted for deductions for advance
payments and retention. The Employer shall pay the
Contractor the amounts certified by the Engineer within
twenty-eight (28) days of the date of each certificate. If the
Employer makes a late payment, the Contractor shall be paid
interest on the late payment in the next payment. Interest
shall be calculated from the date by which the payment
should have been made up to the date when the late payment
is made at the prevailing rate of interest for commercial
borrowing established in Bangladesh.
63.3 Items of the Works for which no rate or price has been
entered in will not be paid for by the Employer and shall be
deemed covered by other rates and prices in the Contract.
65. Change in 65.1 Unless otherwise specified in the Contract, if between the
Laws and date twenty-eight (28) days before the submission of Tenders
Regulations for the Contract and the date of the last Completion
certificate, any law, regulation, ordinance, order or bylaw
having the force of law is enacted, promulgated, abrogated,
or changed in Bangladesh (which shall be deemed to include
any change in interpretation or application by the competent
authorities) that subsequently affects the Completion Date
and/or the Contract Price, then such Completion Date and/or
Contract Price shall be correspondingly increased or
decreased, to the extent that the Contractor has thereby been
affected in the performance of any of its obligations under the
Contract.
65.2 The Engineer shall adjust the Contract Price on the basis
of the change in the amount of taxes, duties, and other levies
payable by the Contractor, provided such changes have not
already been accounted for in the price adjustment as defined
in GCC Clause 64 and/or reflected in the Contract Price.
66.2 If the value of the index is changed after it has been used
in a calculation, the calculation shall be corrected and an
adjustment made in the next payment certificate. The index
value shall be deemed to take account of all changes in cost
due to fluctuations in costs.
67. Retention 67.1 The Employer shall retain from each payment due to the
Contractor the proportion stated in the PCC until completion
of the whole of the Works.
68. Liquidated 68.1 The Contractor shall pay liquidated damages to the
Damages Employer at the rate per day stated in the PCC for each day
that the Completion Date is later than the Intended
Completion Date for the works or for any part thereof. In
respect of the value of the delayed works the total amount of
liquidated damages shall not exceed the amount defined in
the PCC. The Employer may deduct liquidated damages
from payments due to the Contractor. Payment of liquidated
damages shall not affect the Contractor’s liabilities.
69. Bonus 69.1 The Contractor shall be paid a Bonus calculated at the rate
per calendar day if stated in the PCC for each day (less any
days for which the Contractor is paid for acceleration) that the
Completion is earlier than the Intended Completion Date.
The Engineer shall certify that the Works are complete,
although they may not be due to be complete.
70. Advance 70.1 If so specified in the PCC, the Employer shall make
Payment advance payment to the Contractor in the amounts and by the
dates stated in the PCC against provision by the Contractor of
an Unconditional Bank Guarantee in a form and by a bank
acceptable to the Employer in an amount equal to the
advance payment. The Guarantee shall remain effective until
the advance payment has been repaid, but the amount of the
Guarantee shall be progressively reduced by the amounts
repaid by the Contractor. Interest will not be charged on the
advance payment.
74. Completion 74.1 The Contractor shall request the Engineer to issue a
certificate of Completion of the Works, and the Engineer will
do so upon deciding that the work is completed.
75. Taking Over 75.1 The Employer shall take over the Site and the Works within
seven (7) days of the Engineer issuing a Certificate of
Completion.
76. Final Account 76.1 The Contractor shall supply the Engineer with a detailed
account of the total amount that the Contractor considers
payable under the Contract before the end of the Defects
Liability Period. The Engineer shall issue a Defects
Correction Certificate and certify any final payment that is
due to the Contractor within fifty-six (56) days of receiving
the Contractor’s account if it is correct and complete. If it is
not, the Engineer shall issue within fifty-six (56) days a
schedule that states the scope of the corrections or
additions that are necessary. If the Final Account is still
Tender Document for OFC Network of Info-bahan Project
Page 54 of 147
unsatisfactory after it has been resubmitted, the Engineer
shall decide on the amount payable to the Contractor and
issue a payment certificate.
77. As-built 77.1 If “As Built” Drawings and/or operating and maintenance
Drawings and manuals are required, the Contractor shall supply them by
Manuals the dates stated in the PCC.
80. Property 80.1 All Materials on the Site, Plant, Equipment, Temporary
Works, and Works shall be deemed to be the property of
the Employer if the Contract is terminated because of the
Contractor’s default.
82.2 Adjudication
(a) If the Contractor believes that a decision taken by the
Engineer was either outside the authority given to the
Engineer by the Contract or that the decision was
wrongly taken, the decision shall be refereed to the
Adjudicator within fourteen (14) days of notification of
the Engineer’s decision in writing.
(b) The Adjudicator named in the PCC is jointly appointed
by the parties. In case of disagreement between the
parties, the Appointing Authority designated in the PCC
shall appoint the Adjudicator within fourteen (14) days of
receipt of a request from either party.
(c) The Adjudicator shall give its decision in writing to both
parties within twenty-eight (28) days of a dispute being
referred to it.
(d) The Contractor shall make all payments (fees and
reimbursable expenses) to the Adjudicator, and the
Employer shall reimburse half of these fees through the
regular progress payments.
(e) Should the Adjudicator resign or die, or should the
Employer and the Contractor agree that the Adjudicator
is not functioning in accordance with the provisions of
the Contract; a new Adjudicator will be jointly appointed
by the Employer and the Contractor. In case of
disagreement between the Employer and the Contractor
the Adjudicator shall be designated by the Appointing
Authority designated in the PCC at the request of either
party, within fourteen (14) days of receipt of a request
from either party.
GCC The Start Date will be the date of signing of the Contract.
1.1(ae)
GCC 1.1(ai) The Works consist of the items as described in Section:6 “ Bill of
Quantities” of this document.
GCC 4.5 The date of successful completion of PAC for any site shall be
considered as the completion date of that site.
GCC 5.1(i) The following documents also form part of the Contract:
16.1 Schedule of Other Contractors
24.1 The Schedule of Key Personnel
27.1 Site Investigation Reports and also finalised BoQ &
Memorandum of understanding (MOU).
GCC 6.1 Contractors that are a national of, or registered in, the following
countries are not eligible: Israel
GCC 12.1 The Employer’s address for the purpose of communications under
this Contract is :
Divisional Engineer
Microwave Maintenance Division-1
BTCL, Ramna, Dhaka.
GCC 27.1 OFC drawing of each of the sites will be available at the Divisional
Engineer’s office mentioned above.
GCC 28.1 The Divisional Engineer shall provide OFC drawings & possession
for all the sites within 10 ( ten) days from the date of signing the
Contract.
(b) The minimum cover for insurance of the Works and of Plant and
Materials in respect of the Contractor’s faulty design is Nil.
GCC 68.1 The liquidated damages for the whole of the Works are 0.05% of the
Damage of final Contract Price per day.
any org.
utility or The maximum amount of liquidated damages for the whole of the
others Works is 10% of the final Contract Price.
GCC 77.1 The date by which “as-built” drawings are required is 15 days before
PAT.
GCC 77.2 The amount to be withheld for failing to produce “as-built” drawings
and/or operating and maintenance manuals, test reports, line
information sheet by the date required is taka 10.00 lakh.
GCC 79.1 The percentage to apply to the value of the work not completed,
representing the Employer’s additional cost for completing the
Works, is 10% of the Contract value.
Form Title
Tender Forms
Contract Forms
To:
We, the undersigned, offer to execute in conformity with the Conditions of Contract
and associated Contract Documents, the following Works and Related Services, viz:
If applicable under ITT Sub-Clause 23.1, in case we are awarded a Contract for more
than one lot in the package, the discount/cross-discount offered and the methodology
for its application is:
The amount of the advance payment required is [insert percentage] of the Contract
Price.
Our Tender shall be valid for the period stated in the Tender Data Sheet and it shall
remain binding upon us and may be accepted at any time before the expiration of that
period. A Tender Security in the amount stated in the Tender Data Sheet is attached
in the form of a [state pay order, bank draft, bank guarantee] valid for a period of 28
days beyond the Tender validity date.
We declare that ourselves, and any SubContractors or Contractors for any part of the
Contract, have nationalities from eligible countries and that the materials, equipment
and related services will also be supplied from eligible countries. We also declare that
the Government of Bangladesh has not declared us, and any Sub-Contractors or
Contractors for any part of the Contract ineligible on charges of engaging in corrupt,
fraudulent, collusive or coercive practices. Furthermore, we are aware of ITT Clause 3
concerning this and pledge not to indulge in such practices in competing for or in
executing the Contract.
We understand that you are not bound to accept the lowest evaluated Tender or any
other Tender that you may receive.
Signed
A. Individual Tenderers
Proprietorship
Address
e-mail address
2.3 Major items of Contractor’s Equipment proposed for carrying out the works.
List all information requested below. Refer also to ITT Sub-Clause 15.1
Item of equipment Description, make Condition (new, Owned, leased
and age (years) good, average, (from whom?) or
poor) and to be purchased
quantity available (from whom?)
(a)
(b)
(c)
Personnel Information
3.1 Financial reports or balance sheets or profit and loss statements or auditors’
reports or bank references for the past (5 years) with documents or a
combination of these demonstrating availability of liquid assets. List below
and attach copies.
3.2 Evidence of access to financial resources to meet the qualification
requirements, liquid assets, lines of credit, etc. List below and attach copies of
supporting documents.
3.3 Name, address, and telephone, telex, and facsimile numbers of banks that
may provide references if contacted by the Employer
3.4 Information on litigation in which the Tenderer is, or has been, involved:
4.1 Each Member of a JVCA shall provide all the information requested in the
form above, Sections 1-3.
4.2 Attach a power of attorney for each of the authorising signatories of the
Tender on behalf of the JVCA.
4.3 Attach the Agreement among all Members of the JVCA (and which is legally
binding on all Members), which shows that:
(a) all Members shall be jointly and severally liable for the execution of
the Contract in accordance with the Contract terms;
(b) one of the Members will be nominated as being in charge,
authorised to incur liabilities, and receive instructions for and on
behalf of any and all Members of the joint venture; and
(c) the execution of the entire Contract, including payment, shall be
done exclusively with the Member in charge
4.4 Attach the statement as per clause ITT 4.4
Signature Signature
[Name of Contractor]
This is to notify you that your Tender dated [insert date] for the execution of the Works
for [name of project/Contract] for the Contract Price of Tk [amount in figures and in
words], as corrected and modified in accordance with the Instructions to Tenderers is
hereby accepted by [name of Employer].
You are requested to proceed with the execution of the Works on the basis that this
Notification of Award shall constitute the formation of a Contract, which shall become
binding upon you furnishing a Performance Security within fourteen (14) days, in
accordance with ITT Clause 53, and signing the Contract Agreement within twenty-
one (21) days, in accordance with ITT Clause 54.
We attach the Contract Agreement and Particular Conditions of Contract for your
perusal and signature.
Signed
Date:
WHEREAS the Employer invited Tenders for certain works, viz, [brief description of
works] and has accepted a Tender by the Contractor for the execution of those works
in the sum of Taka [Contract price in figures and in words] (hereinafter called “the
Contract Price”).
2. The documents forming the Contract shall be interpreted in the following order
of priority:
a. the signed Contract Agreement;
b. the letter of Notification of Award
c. the completed Tender Submission Sheet as submitted by the Tenderer;
d. the priced Bill of Quantities as submitted by the Tenderer;
e. the Particular Conditions of Contract;
f. the General Conditions of Contract;
g. the Particular and General Specifications;
h. the Drawings, and;
i. any other document listed in the PCC as forming part of the Contract.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed
in accordance with the laws of Bangladesh on the day, month and year first written
above.
Print Name
Title
Address
[this is the format for the Performance Security to be issued by a scheduled bank
of Bangladesh in accordance with ITT Clause 53]
To:
We have been informed that [name of Contractor] (hereinafter called “the Contractor”)
has undertaken, pursuant to Contract No [reference number of Contract] dated [date
of Contract] (hereinafter called “the Contract”), the execution of works [description of
works] under the Contract.
Signature Signature
[Not Applicable]
[this is the format for the Advance Payment Guarantee to be issued by a scheduled
bank of Bangladesh in accordance with PCC Clause 70]
To:
We have been informed that [name of Contractor] (hereinafter called “the Contractor”)
has undertaken, pursuant to Contract No [reference number of Contract] dated [date
of Contract] (hereinafter called “the Contract”), the execution of works [description of
works] under the Contract.
We further agree that no change, addition or other modification of the terms of the
Contract to be performed, or of any of the Contract documents which may be made
between the Employer and the Contractor, shall in any way release us from any
liability under this guarantee, and we hereby waive notice of any such change,
addition or modification.
Signature Signature
[The Contractor must submit rates for Materials & Services separately as per Summery Price
of this Tender Document ]
■ Chaudanga - Darshana
Unit
Sl. Name of Item Unit Quantity Total(Tk)
Price(Tk)
A Underground Conduit Material
110mmPVC Conduit Route 2-way with Sand & Concrete Slab, spacer,
1 Metre 0
protection etc. in kacha and semi-pacca road (UC-P-V2-S/HS)
110mmPVC Conduit Route 2-way with Sand & Concrete Slab, spacer,
2 Metre 1,110
protection etc. in pacca road (UC-P-V2-M)
40mm HDPE Pipe conduit(included pulling string) with Sand & Bricks
3 Metre 23,945
Protection in kacha and semi-pacca road (UC-H-V1-S/HS)
40mm HDPE Pipe conduit(included pulling string) with Sand & Bricks
4 Metre 0
Protection in pacca road (UC-H-V1-M)
5 40mm HDPE (with pulling string) 1-way Sub-Duct (UC-SD1-C) Metre 357
6 40mm HDPE (with pulling string) 3-way Sub-Duct (UC-SD3-C) Metre 1,452
Unit
Sl. Name of Item Unit Quantity Total(Tk)
Price(Tk)
D Underground Conduit Service Work
110mmPVC Conduit Route 2-way with Sand & Concrete Slab,spacer,
1 Metre 0
protection etc. in kacha road (UC-P-V2-S)
110mmPVC conduit Route 2-way with Sand & Concrete Slab,spacer,
2 Metre 0
protection etc. in semi-pacca (hard sole) road (UC-P-V2-HS)
110mmPVC Conduit Route 2-way with Sand & Concrete Slab,spacer,
3 Metre 1,110
protection etc. in pacca road (UC-P-V2-M)
40mm HDPE Pipe conduit(included pulling string) with Sand & Bricks
4 Metre 23,945
Protection in kacha road (UC-H-V1-S)
40mm HDPE Pipe conduit(included pulling string) with Sand & Bricks
5 Metre 0
Protection in semi-pacca (hard sole) road (UC-H-V1-HS)
40mm HDPE Pipe conduit(included pulling string) with Sand & Bricks
6 Metre 0
Protection in pacca road (UC-H-V1-M)
7 40mm HDPE (with pulling string) 1-way Sub-Duct (UC-SD1-C) Metre 357
8 40mm HDPE (with pulling string) 3-way Sub-Duct (UC-SD3-C) Metre 1,452
120mm DWC 1-way Culvert crossing attachment with concrete
9 Metre 55
encasement (UC-CC-V1)
120mm DWC 1-way Bridge crossing attachment with concrete
10 Metre 0
encasement (UC-B-V1)
11 120mm DWC 1-way Bridge crossing attachment Clamp Steel (UC-B-V1) Metre 17
Unit
Sl. Name of Item Unit Quantity Total(Tk)
Price(Tk)
Unit
Sl. Name of Item Unit Quantity Total(Tk)
Price(Tk)
F Hand-hole Service
Unit
Sl. Name of Item Unit Quantity Total(Tk)
Price(Tk)
6 Racking Structure for MSU/RSU including cable tray each 2
Unit
Sl. Name of Item Unit Quantity Total (Tk.)
Price (Tk)
Racking Structure Installation MSU/RSU including
6 cable tray each 2
(CR-MS/RS) (10m)
Single mode Optical Pig Tail, 3 metre
7 each 48
(OC-P3)_adapter (FC-PC) 1way
Sub-Total for OFC Accessories (E1-E11)
In figure Taka;
In word Taka :
For Optical Fiber Cable and Out Site Plant (OSP) works
The OF cable will be standard single mode type (G.652D) and suitable for both duct as
well as direct buried installation. The fiber should be suitable for 155 Mbit/s, 622 Mbit/s,
2.5/10 Gbit/s, 10 Gbit/s Transmission at 1310nm and 1550 nm wave lengths.
7.2.1 The Optical Fiber dimensional and transmission characteristics as well as Test
methods should comply with latest version of ITU – T Recommendation G.652D.
1. The Optical fiber shall confirm to the latest relevant ITU-Recommendations and the
requirements as specified in this document.
2. The Fiber shall comply with the design data given in ITU- Recommendation G.652D.
Any disagreement of clauses 7.3.1-7.3.2 will be treated as “Critical deviation” for each of
such disagreement.
Item Construction
Type Single Mode
Core Germanium doped Silica
Cladding Silica
Material
Dual Layers of UV-cured Acrylate, Color
Coating
coded
Optical Fiber cables to be proposed by the bidder for this bid are of 24 core meeting
following specifications.
Any disagreement/deviation from the sub-head “Type” under item head of the clause-
7.5 shall be treated as “Change of Substance”. Any disagreement/deviation from the
specifications of the items Strength member, Inner sheath thickness, Outer sheath
thickness and armoring thickness of the clause-7.5 shall be treated as “Critical
Deviation”. And any disagreement/ deviation from the specifications of the items
other than above of the clause-7.5 shall be considered as “Major Deviation”.
Each fiber shall be identified by providing suitable individual colors having good fact
color properties. Colorless fibers shall not be accepted.
A number of protected optical fiber shall be stranded together in such a way that, if
the mechanical and temperature limits are exceeded during transportation, Storage,
handling, installation and operation the fibers will remain undamaged.
1. The space around the fibers and fillers shall be completely filled with jelly/grease
throughout the cable length.
3. The jelly/grease shall not affect the color of the primary coating, easily removed and
shall be non-toxic, free from bad smelt and shall not affect the human skin.
4. The jelly/grease shall comply with the standard test procedure/ requirement.
5. Cross wounded core binding yarns will be applied during the stranding of the cable
core and Cable core will be wrapped with a non-hygroscopic core wrapping tape
helically/longitudally with minimum 10 % overlap.
1. Cable identification mark along the length of the cable and distance marking shall be
provided in meters.
6. Optical Fiber cable should operate normally under the following environmental
conditions:-
1. The splice closer shall be waterproof type, which will accommodate the joint part of the
cable, should be suitable for installation in manhole or hand hole or be directly
buried.
3. The material of the sleeve for the closer shall consist of plastic material containing the
glass fiber. The metal material for the closer shall be anti-corrosive & anti-rusting.
a. No leakage of air for 24 hours after applying 0.5 ± 0.1 kg/cm gas pressure.
b. No invasion of water after 1 hour with 1.0 ± 0.1 kg/cm water pressure.
c. No malfunction for 1 minute at 1500 V DC between metal core and closer surface.
5. Splice closures should be easy to open with the no special or specific tools and should
he reusable without the necessity of cable cutting.
6. The joint closure must be 4 way. It should be possible to make 4 way interconnection
to different directions with the closure.
8. Full technical and constructional details of the closure are to be given along with the
Bid.
1. The optical distribution / termination frame shall be rack (19 inch. Standard rack)
mounted type and will be installed in suitable position in the equipment room.
2. Optical I Links in the optical distribution / termination frame shall be high grade
FC/PC type.
3. There shall be easy access for splicing and provision for maintenance facility.
4. There shall be provision for cable entry either from above or from the left hand side,
allowing the station cable to enter the bay either from above or below.
6. There shall be provision for inspection or cleaning the internal fiber connectors.
7.12.1 Civil Work for Underground Conduit (UC) : On the basis of the indicative
underground Conduit (UC) Network DWG (Drawing) and “Scope of Works” which are
described in this chapter, Contractor(s) shall conduct detailed survey, design,
quantify final BoQ (Bill of Quantity) and supply, install, test, commission and
provide other required services.
7.12.2.1 HDPE pipe shall be of following minimum standard and shall have to satisfy
following technical specifications.
(d) The manufacturer of the offered HDPE duct must have valid ISO 9000 and 14001
certification.
Test
No Item Unit Value
Standard
1 Material Density 930 to 958 kg/ m2 at 270 C ASTM D1238
ISO2505/
2 Heat Reversion Dimension shall not change by more than 3%
ASTM D1238
3 Crash Resistance Deflection with load not greater than 10% ASTM D2412
ASTM F2160/
4 Tensile strength Newton/mm2 Min. 20
BS 2782
ASTM F2160/
5 Elongation at break % Min. 350
BS 2782
Environmental Stress
6 Cracking Resistance Duct shall not crack or split ASTM D1693
(ESCR)
7 Impact Strength No crack or split D2444
Hydro Static Pressure
8 No swelling, leakage or bursting ISO1167
Test
9 Coefficient of friction <0.1
Any disagreement of clause 7.12.2.1 (a) and/or serial number 10 & 13 (including sub-clauses)
of above specifications mentioned in clause 7.12.2.1 (b) of HDPE duct shall be considered as
“Critical deviation” and any disagreement of other items of the above specifications of
HDPE duct shall be considered as “Major Deviation”.
No Parameter Specification
1 Construction There shall be no sharp edges, burs or surface projections
Outside Diameter 120 ± 2.2mm
2
Inside Diameter Minimum 90mm
3 Wall thickness 2.0mm
>450N @ 5% defln. After the test, there shall be no crack
4 Compression Test allowing the ingress of light or water between the inside &
the outside.
There shall be no crack allowing the ingress of light or
5 Impact Test
water between the inside & the outside
Samples bend to 90 degree to a radius of 2(two) meters. A
6 Bending Test
ball of dia 95% of ID will pass freely.
7 Length Minimum 12 meter
8 Color Black
Any disagreement of serial number 1, 2 of above specifications of DWC HDPE duct shall be
considered as “Major deviation” and any disagreement of serials 3-6 of above
specifications of HDPE duct shall be considered as “Minor Deviation”.
8 Appropriate non-metallic couplers will be used to join two pieces of HDPE duct for a
locked and air sealed assembly and will be suitable for direct buried application.
Couplers will be push-fit type and no other tools or heating will be required to use
these couplers.
7.12.3.1 The pipes shall be welded or seamless, free from dents and internal roughness.
7.12.3.2 The ends of pipes shall be reamed to prevent abrasion against cable.
7.12.3.4 The pipes shall be jointed together by means of a coupler of the same material as the
pipes.
7.12.3.5 After the forming operations, the pipes and couplers shall be hot-dip-galvanized to
meet the requirements.
7.12.3.6 The detailed dimensions of f100 mm GI pipe are as shown in the following table:
7.12.4.1 Material
(1) The pipe and coupler shall be manufactured by an extrusion process from material
composed of polyvinyl chloride polymer to which suitable additives are added.
(2) No constituent material which will adversely affect long term mechanical strength,
creep, fabrication, solvent-welding and weathering properties of the PVC, shall be
used.
(3) PVC raw material must include 92%-95% of pure resin. The tolerated adjuncts (in the
limits of 5%-8%) as stabilizers, filler, colorings, anti-oxidizers, etc, must be free from
any plasticizer or volatile components.
(6) PVC compound shall contain stabilizer, lubricant, filler and pigment consisting of
standard polymers.
(7) The pipes and couplers must have resistance to acid, alkalis, oxidizing and reducing
agent, weather and rust.
(8) The pipes and couplers must remain unaffected by fungus, bacteria and termites.
7.12.4.2 Requirement
3) Both end of the pipe shall be cut exactly perpendicular to the pipe axis and shall be free
from chips and edges.
7.12.4.3 Dimensions
The detailed dimensions of 110mm PVC pipe are as shown in the following table;
(2) In exceptional circumstances (rocky areas, due to other utility services etc) where
digging below to required depth is not possible due to different reasons, cable/ duct
may be laid with appropriate protection at lesser depth with the prior permission of
BTCL.
2) Empty PVC/HDPE duct openings should be properly sealed off with rubber/plastic
end cap.
(4) Manholes
1) In city/town areas where new 4-way PVC duct to be laid along the road,
manholes instead of hand holes are to be constructed.
2) The type of manholes and the inside dimensions should be as follows and the
location of manholes are to be approved by BTCL.
Unit : cm
Type Length Width Depth Wall & Floor thickness
S1(straight type) 220 130 180 20
a) Inside Dimensions
i) Length : ±2.5 cm
ii) Width : ±1.5 cm
iii) Height : ±1.5 cm
3) All ducts entry to the manhole should be done using bell mouth with rubber end
cap with appropriate holes for ducts entering. All unused duct entry through bell
mouth must be sealed by rubber end cap.
4) The manhole shall be equipped at the time of construction with frame and
covers, ladders, pulling-in irons, steps, cable racks and nameplates.
a) The concrete, when made with ordinary Portland cement, shall attain a
minimum compressive strength on 28-days of 2100N/cm²(210kg/cm²), or,
b) When made with high early strength Portland cement, it shall acquire the
same strength in seven (7) days. (Test to be performed on cylindrical type
concrete specimen of size 150mm X 300mm)
c) The slump range for the concrete used in manholes and foundation
construction shall be between 8 and 15cm, when using vibrator.
7) The concrete shall be deposited, not thrown, in its intended position as quickly
as possible just after being mixed sufficiently,
9) The concrete, once mixed, shall be used within 60 minutes (1hour). After one
hour, any remaining concrete shall be condemned and shall not be used.
10) The bottom pit shall be tamped and carefully leveled and be covered with
approximately 50mm of lean concrete on the layer of approximate 100mm of
gravel.
11) Cement mortar shall consist of one (1) measure of Portland cement and two (2)
measures of sand. While the composition of concrete mixing material ratio will
be;
12) After the concrete has been placed, for the purpose of curing the concrete slab
shall be protected so as to limit the loss of moisture from the surface.
13) The concrete shall cover with saturated sackcloth or similar material and kept
moist for a period of seven (7) days.
14) Removal of forms shall not be permitted earlier than five (5) days after
concrete pouring, upon removal of forms surrounding area of the manholes
shall be immediately backfilled.
15) Interim restoration and backfilling shall not commence until the work to be
carried out and has been approved by BTCL.
17) Each manhole will be equipped with 1 manhole cover, 1 manhole ladder, 1
sump pit cover, 4 pulling in iron, 2 sets of cable rack (each set contain 3
vertical and 3 horizontal racks/brackets), and required hook, nut and bolt to fix
these cable racks and brackets.
(5) Hand-holes
1) Hand holes to secure splice closures and excess cable length as well as for ease
of drawing of optic cable shall have to be constructed.
2) Hand holes should be constructed in the following way:-
Reinforced concrete hand holes placed on a concrete or gravel foundation to
prevent their sinking in the soil are to be used.
b) Composition of concrete:
Stone chips (20 mm downgraded): sand (Sylhet): Portland cement
= 3:1.5:1
3) Duct entry to the handhole should be done using bell mouth with rubber end cap
with appropriate hole for HDPE ducts. All unused duct entry through bell mouth
must be sealed by rubber/plastic end cap.
2) Contractor will assist the purchaser for obtaining permits after ascertaining the type of
permits are required and carry out formalities. The permit may include Municipal
Authorities, R&H Dept. Rail way Dept., Electricity, Water, Sewerage, Gas, etc. Necessary
application and payments to respective authorities will be made by the purchaser.
3) BTCL shall pay compensation bill claimed by the government, semi-government and
4) Contractor shall obtain all pertinent records from the electric company, water supply,
gas Supply Company and sewerage authority and other underground utilities organization
in order to plant his work and safe guard of other utilities.
5) Contractor shall take all precautions necessary for safety of general public and for
protective and preserving any and all temporary or permanents utilities.
10) If any obstructions which interfere with excavation of manhole and handhole site or
conduit trench are encountered, Contractor shall consult with BTCL about modification of
drawing to be initiated.
11) Contractor shall dispose all excavated materials except what to be used for
backfilling.
12) Contractor shall at all times adequately protect the sides of the excavation against
cave-in. sheeting and shoring supporting work shall be applied at contractor’s expense,
where required by BTCL, and / or considered to be necessary.
13) Contractor shall confer with the proper road administrative authority and ensure that
the proposed depth of manhole and hand holes, conduits conform to the final grades of
carriageways and footways.
14) Contractor shall excavate insofar as possible to comply with the trench width
requirements as detailed in the drawings given in Section 9. Any excess in this width,
unless specifically authorized by BTCL, shall be at his own expense. This includes extra
restoration expenses or pavements, macadam’s and /or tiles.
15) Upon completion of trenching, all manholes and handholes which will contain
metallic sheath cable shall be earthed as illustrated in the drawings given in Section 9.The
trench shall be so arranged as to avoid any dip profile of conduit and be arranged with
smoothly and gradually descending grade so as to terminate conduits at the specified
location of the manhole and handhole as shown in “outside plant construction drawings”
16) Contractor shall at his own expense protect and support any type of utility services
like pipe, conduit, cable, wire or any other item of telephone and other services of foreign
exposed or encountered during the excavation. Contractor is obligated to restore all times to
their original conditions and to the satisfaction of BTCL and owners of such plants as
shown in the “Outside plant construction drawings” which will be provided by
Contractor and approved by BTCL.
In addition to the general procedural requirements stated above, the contractor shall
have to conduct all installation works related to underground conduits abiding by the
following specific procedures. Any deviation from these procedures shall have to be
pre-approved by BTCL.
1) Trench walls shall be vertical. Widths of trenches for HDPE duct shall be
minimum required to install HDPE ducts and protective bricks. In case of
underground HDPE duct, the widths of trenches are max 30 cm for both bottom
and top for 1-way duct. Widths of trenches for 4-way PVC duct shall be
minimum required to install 4-way PVC ducts and protective slabs. In case of
underground 4-way PVC duct, the widths of trenches are max 45 cm at bottom
and maximum 55 cm at top. Unnecessary disturbance of surrounding earth shall
be avoided wherever possible.
2) The excavated trench shall be straight horizontally at its height level. Zigzag
trench will not be allowed.
3) After proper excavation, the bottom of the trench shall be properly tamped,
carefully leveled, compacted and dried.
4) The contractor shall ensure that there are no sharp materials or leftover garbage
inside the trench.
5) For all major roads, railway and waterway crossings, manhole and hand holes
shall be constructed at either side of such crossings with instruction of BTCL.
6) Where the 4 X 110mm PVC route is running, they shall be supported by spacers
firmly at every 2 meter interval.
8) Duct Integrity Test shall be performed with 10 Bar air pressure for 100% of
the 1-way HDPE duct route before laying of optic cable through the duct.
There shall not be any drop of Air pressure within a pressurization duration
of 5 (five) minutes during the test.
40 mm Gravel filling
(100mm for man-hole)
20 mm compact Sand
or sifted soil filling Prepared tamped excavated level
3) Metal forms, with error free surfaces and proper attachments shall be used for all
structures.
4) All RCC & CC works shall be constructed by ready mixed or site-mixed concrete.
5) The contractor shall confirm that before start of the concrete deposition the bed of the
structure is completely dry.
6) For other working procedures on concrete work such as concrete mixing, placing,
curing, form removing and protections, Contractor shall refer to 7.2.4.1 (4).
“Common Criteria” In this clause and criteria of “Manhole” accordingly.
7) BTCL may order three (3) test specimens (cylindrical type) from each of the
structures. Whenever such test specimens are ordered, they shall be properly marked
with paint showing the date of making, proportion of mix and the name of the
structure for which the specimen will be taken for inspections tests as required. The
contractor, at its own cost, shall arrange for testing of those specimens either from
Bangladesh University of engineering and technology or Bangladesh standard testing
institution. (as per decision given by BTCL during relevant time).
The marker posts shall be installed at each handhole location with the feature
illustrated in the drawings given in Section 9. The marker will be situated at a
Length: 50 cm
Width: 30 cm
Thickness: 8 cm
c) Composition of concrete:
Picket Brick chips (20 mm downgraded): Sand (Coarse, FM 0.8): Portland cement
= 4:2:1
1) The cable shall be installed either in existing PVC ducts with existing or new HDPE
sub-duct or in new HDPE duct depending upon actual site condition.
2) Fiber optic cables in bridges and culverts etc. should be placed in 40mm HDPE and
the HDPE duct itself will be placed inside a 130mm DWC pipe.
3) The contractor shall lay the optical cables alongside the roads and highways keeping
distance as maximum as possible from the edge side of road to protect OFC from
damage during expansion of the road with following conditions but not limited to.
a) 130mm DWC pipe duct will be fixed to bridge /culvert using galvanized
clamps with royal bolts at each 1m distance where the bridge/culvert
authorities do not permit to place the duct at the inner side of the
bridge/culvert. But where possible 130mm DWC pipe duct should be
placed on the footway of the bridge/culvert. 130mm DWC pipe should be
covered with concrete (17 cm x 17 cm).
5) At every cable joints, the steel tape of in and out bound cable end shall be
electrically bonded and earthed through connecting to the M.H or H.H earthing lead
wire.
3) The following types of cables may be used for entering into exchange premises
and transmission stations:
4) Cables entering buildings must end with branching or termination splices placed
in durable closures or junction boxes, well protected against unauthorized
interference.
5) Cables installed in cable tray, shafts, risers or very steep ducts should be fastened
with grips at intervals no greater than 6m. In case of longer shafts (above 30m),
reinforcement with a layer of aramid yarn or glass fiber should be made.
6) Cables installed in shafts longer than 10 m should be filled with non-dripping gel
or have partitioned cores, preventing gel from dripping inside cable coatings.
Partitions should be made of epoxide resins or materials with similar sealing
characteristics and should be distributed at intervals not longer than 10m. The
bottom section of a cable in a shaft should be joined to the outgoing cable in such
a way that the junction prevents leakage of gel.
Any disagreement of clause 7.2.5.3 (including sub clauses) will be treated as “Major
deviation”.
2) The minimum splice distance between splices shall be not less than 2 km. The average
splice distance should be stated on the As-Built document.
9) Installation documentation
1) Installation drawing (As-Built drawing) should be supplied (in hard & soft copy) by the
contractor upon completion of the construction. The drawing should be supported by
accurate data on the following:
a) Route drawing with actual distance (both route distance and OFC distance)
between joints, manhole, handhole, direction change, bridge/culvert/water cross
etc.
b) Location of each manhole and handhole showing correct Latitude and Longitude
c) Location of excess cable length
d) Location of each splice
e) Latitude & Longitude of each turning point in the route
2) Documentation should also include the result of all tests, including the following;
a) Reflectometric graph, tested bi-directionally from both ends of regeneration
section.
b) Optical path loss after installation and before installation.
2) Following cable installation but prior to fiber splicing, all fibers have to
be unidirectionally tested by means reflectometer to verify fiber
continuity.
1) Prior to the site installation work, contractor shall submit the test results of OFC to
be used to the project office as per instruction mentioned in clause 7.2.6.1.1 and
also as per the following table.
Test
Test item Testing at Performance Remark
Method
Continuity To verify any error
Back 1310nm:
test, post during cable
Scattering 1550nm:
placement blowing/pulling
To justify the
Post Back 1310nm:
integrity of
splicing test Scattering 1550nm:
1310±20nm splicing
1550±29nm Quality inspection
Total 1310nm:
Cut Back prior to
attenuation 1550nm:
termination
Final For acceptance
1310nm:
Acceptance Intersection after completion of
1550nm:
Test a hope/entire work
7.12.7.1 Installation, Testing, Commissioning of OFC network systems and spur links meeting
the specification shall be entire responsibility of the contractor.
7.12.7.2 For any disagreement or proposal violating scope of works under this chapter,
the bid will be treated as Critical Deviation.
8.1 During evaluation of the Bids, the Tender Evaluation Committee (TEC) will
examine non-conformities/deviations of the submitted bids and evaluate them
according to the criteria as set forth in Section-1 of this tender document. In
addition to that Non-responsiveness of a bid shall also be determined using the
following criteria;
8.1.2 Any item of “Critical Deviation” shall earn a score of 20 (twenty) penalty point.
8.1.3 Any item of “Major Deviation” shall earn a score of 5 (five) penalty point.
8.1.4 Any item of “Minor Deviation” shall earn a score of 1 (one) penalty point.
8.1.5 By adding up the penalty points of each evaluated bid by TEC, if it is found that
the bid has earned 50 (fifty) or more penalty points then that bid shall be
treated as “Non-Responsive”.
8.1.6 The bid offer found to be containing any item of “Change of Substance” shall
also be treated as “Non-Responsive”.
8.2 Acceptance Test of works and supplied goods: Acceptance test will be
divided into two parts. One is Provisional Acceptance Test (PAT) and other is
Final Acceptance Test.
8.2.1 The bidder shall be totally responsible for arrangement of all equipment, consumables,
test gears and measuring equipment required for the PAT. All costs for this service
shall be quoted and failure to quote shall be considered that the bidder proposes to
provide this service totally "free of charge" to BTCL.
8.2.2 For the acceptance test of the related goods [especially for supplied HDPE ducts,
DWC HDPE ducts, PVC pipe & Manhole cover], the bidder shall submit a copy of
the performance test certificate(s) of the goods to the project office and the PAT
team. For foreign goods/materials, the bidder shall perform this test from BUET
through the project office and such performance test certificate(s) of the goods will be
issued by BUET. But in the case of locally manufactured goods, the bidder shall
arrange factory test(s) of those goods/materials in manufacturing premises for BTCL
engineer(s) and the BTCL engineer(s) will issued quality certificate/performance test
certificate(s) of them. Such certificate(s) will be considered or acceptable to PAT team.
8.2.4 The bidder’s engineer shall be liable to make necessary arrangement to complete any
kinds of possible tests for asserting the specifications requested by PAT members
during PAT.
8.2.5 In addition to this, the bidder has to provide per diem cost to PAT engineers as per
the following:
a) Number of BTCL’s PAT Engineers for each lot: Maximum 5 (five) persons.
b) Number of days allowed for per diem charge : 7 (Seven) working days per
person for the sites
c) Per diem charge to BTCL’s PAT Engineers : Taka 1000 per person per day
d) Other facilities : Transportation
However, the bidder shall note that, if necessary, any or all PAT can continue for more
than the above scheduled period; but, in such case, the bidder shall not be liable to
pay per diem for those additional days.
8.2.7 After satisfactory completion of PAT subsequent payment of that part of the whole
work may be made to the contractor according to the payment terms & conditions of
this tender. Based on the recommendation of the PAT team, the Project Director may
issue PAC hop by hop or a single PAC for the whole work under same lot.
8.3.1. After completion of the PAT, the Engineers of the Bidder will take prompt necessary
steps to remove all types of defect/faults of the works and replace all types of faulty
goods/materials at their own cost. At the end of the “Performance Guarantee Period
for the Contract”, the overall performance of the woks and related supplied
goods/materials will be reviewed and this review shall be termed as “Final Acceptance
Test (FAT)”.
8.3.2. The review shall include (but not limited to) the required working reliability and
performance standards of the goods/materials to meet tender specifications. The
bidder’s responsibility is to resolve all shortcomings mentioned in PAT reports and to
remove of all pending & outstanding faults or shortages encountered during the
Performance Guarantee Period for the Contract. When this FAT becomes due, the
bidder shall make an official request to BTCL for starting of the FAT and BTCL shall
start the FAT within one month after receipt the request from the bidder.
8.3.3. The bidder shall be responsible for arrangement of all equipment, consumables, test
gears and measuring equipment required (if any) for such review tests. All costs for
materials and service (if any) shall be quoted and failure to quote shall be considered
that the bidder proposes to provide this service totally "free of charge" to BTCL.
8.4 Payments: As per Clause: GCC-63, the Employer shall pay the Contractor the
amounts certified by the Engineer within twenty-eight (28) days of the date of each
Tender Document for OFC Network of Info-bahan Project
Page 111 of 149
certificate. The maximum amount to be certified by the Engineer in different stages for
satisfactory progress of the work will be as follows:
1. 50% of the total amount of the price of material used for the works completed as per
BoQ.
2. 50% of the total amount of the price of OSP service works completed as per BoQ.
3. After issuing PAC of each hop, payment of remaining 50% of the total amount of price
of material and service works of that hop will be made. In any case, if the PAC can not
be issued due to some unavoidable circumstances for which the contractor is not
liable; BTCL may consider making a part payment of the completed materials and
service works for which PAC could not be issued.
8.5 Requirement of user’s certificates for the offered brand of OFC and HDPE
duct:
List of Deviation(s)
c)
7.2.3 Tests and measurements
7.2.6.1
Notes on Drawings
7. Accessories
8.ODF
700m
OC-C12
9.2.1-
9.2.1- STANDARD
STANDARD TRENCH
TRENCH SECTIONAL
SECTIONAL DIAGRAM
DIAGRAM (1/2)
(1/2)
9.2.8- O.D.F