5.
Rs.
4,77,000
1,71,000
84,000
13,00,000.
6.
Given :
Raw materials consumed
Direct labour
Manufacturing expenses
Office and administration over heads
Prepare a statement of cost of production.
7.
Ascertain the prime cost, works cost, cost of production, total cost and profit from the under
mentioned figures :
Direct Materials Rs.5,000; Direct Labour Rs.3,500; Factory Expenses Rs.1,500;
Administration Expenses Rs.800; Selling Expenses Rs.700 and Sales Rs.15,000.
8.
Rs.
4,00,000
2,80,000
53,000
1,85,000
9.
The Received side of the Stores Ledger Account shows the following particulars :
Jan. 1
Opening Balance
:
500 units @ Rs. 4
Jan. 5
Received from vendor :
200 units @ Rs. 4.25
Jan. 12
Received from vendor :
150 units @ Rs. 4.10
Jan. 20
Received from vendor :
300 units @ Rs. 4.50
Jan. 25
Received from vendor :
400 units @ Rs. 4
Issues of material were as follows :
Jan. 4200 units; Jan.10400 units; Jan.15100 units; Jan.19100 units; Jan.26200 units;
Jan.30250 units.
Issues are to be priced on the principle of First in First Out. Write out the Stores Ledger
Account in respect of the materials for the month of January.
September 6
September 20
September 27
100
700
400
units at
units at
units at
Rs.1.10
Rs. 1.20
Rs. 1.30
September
September
September
9
22
30
500
500
500
units
units
units
13. Bharat Manufacturing Company uses copper wire which is purchased from the market as
and when necessary. The following purchases and issues were made during the month of
January, 2006 :
Jan. 1
Opening balance 300 kgs. at Rs. 25 per kg.
Jan. 3
Purchased 500 kgs. at Rs. 26.60 per kg. (Purchase Order No. 101).
Jan. 4
Issued 220 kgs. (Material Requisition No. 201).
Jan. 10
Issued 440 kgs. (Material Requisition No. 202).
Jan. 20
Purchased 490 kgs. at Rs. 23 per kg. (Purchase Order No. 102).
Jan. 25
Issued 300 kgs. (Material Requisition No. 203).
Jan. 26
Surplus 20 kgs. returned to store out of quantity issued on January 4
(Material Requisition Note No. 20).
Prepare Stores Ledger Account for the above transactions according to LIFO method of
pricing issue of materials.
14. The following transactions occur in the purchase and issue of a material :
January 19
Purchased
100
at Rs. 5.00 each
February 4
Purchased
25
at Rs. 5.25 each
February 12
Purchased
50
at Rs. 5.50 each
February 14
Issued
80
March 6
Purchased
50
at Rs. 5.50 each
March 20
Issued
80
March 27
Purchased
50
at Rs. 5.75 each
Record the above in Stores ledger using FIFO method of pricing.
15. Show the Stores Ledger entries as they would appear when using the weighted average
method in connection with the following transactions :
Units
Price Rs.
April 1
Balance in hand b/f
300
2.00
April 2
Purchased
200
2.20
April 4
Issued
150
April 6
Purchased
200
2.30
April 11 Issued
150
April 19 Issued
200
April 22 Purchased
200
2.40
April 27 Issued
150
16. Given :
Materials supplied to site on 1-4-2009
Wages paid
Rs.
3,75,000
4,37,500
Cost of plant
62,500
Work certified
9,00,000
Cash received on account
6,75,000
Work completed but not certified
25,000
st
Plant on the site on 31 March 2010
50,000
Contract price
15,00,000
You are required to prepare contract account.
17. The following particulars related to a contract under taken by Ajit Engineers.
Rs.
Materials sent to site
85,349
Labour engage on site
74,375
Plant installed at site
15,000
Materials returned to stores
549
Work certified
1,95,000
Cost of work not certified
4,500
Materials on hand at the end of the year
1,882
Value of the plant at the end of the year
11,000
The contract price has been agreed at
2,50,000
Cash received from the contractors
1,80,000
You are required to prepare contract account and contractee account.
18. Given :
Notional Profit
Work Certified
Work Uncertified
Cash received
Contract Price
How much amount of profit to be transferred to P & L A/c ?
Rs.
Rs.
Rs.
Rs.
Rs.
60,000
4,00,000
30,000
2,80,000
8,00,000
19. Given :
Contract Price
Work Certified
Estimated Profit
Calculate the Profit to be shown in Profit & Loss Account.
Rs.
Rs.
Rs.
10,00,000
9,50,000
1,20,000
20. Given : Cash received Rs. 4,80,000 (80% of Work certified); Notional Profit Rs. 50,000;
Contract Price Rs. 30,00,000.
Calculate the profit to be shown in Profit & Loss Account.
21. A contractor has under taken a contract on 1.4.2009 for Rs.2,70,000. On 31.3.2010 the
position of that contract was as follows:
Rs.
Materials charges
58,000
4
Wages
General charges
Plant installed
Works certified
Cash received
Work uncertified
The plant was installed on the date of the commencement of the
depreciation on plant @ 10% p.a. Prepare contract a/c.
1,12,400
2,800
16.000
1,60,000
1,20,000
8,000
contract charges
22. The contract ledger of a company showed the following expenditure on account of Contract
No. 786 at 31st March, 2010.
Rs.
Materials
94,000
Wages
1,03,000
Plant1
2,000
Establishment charges
6,700
Materials on hand
4.000
The contract was commenced on 1-4-2009 and the contract price was Rs. 4,50,000. Cash
received on a/c to date was Rs. 1,72,000 representing 80% of the work certified the
remaining 20% being retained until completion. The value uncertified was Rs. 4,500.
Prepare an a/c in respect of the contract showing the profit to date assuming depreciation on
plant at 10% p.a. and state the proportion of profit and company would be justified in taking
to the credit of the Profit & Loss account.
23. Product X is produced after three distinct processes. The following information is obtained
from the accounts of a period:
Items
Total
Process I
Process II
Process III
Rs.
Rs.
Rs.
Rs.
Direct materials
2,200
1,800
300
100
Direct wages
400
100
200
100
Direct expenses
500
300
200
Production overhead incurred is Rs.800 and is recovered on 200% of direct wages.
Production during the period was 100 kgs. There was no opening or closing stocks. Prepare
process cost accounts.
24. A product passes through three stages of production and the product of each category
becomes the raw material for the next stage. Further raw materials are also added at each
stage. During March 2010, 2,000 units of finished product were produced with the following
expenditure.
Stage A
Stage B
Stage C
Materials (Rs.)
20,000
16,000
8,000
Labour (Rs.)
16,000
24,000
12,000
Direct expenses (Rs.)
1,200
2,000
800
Indirect expenses amounted to Rs.2,600. It is to be apportioned on the basis of labour. Main
raw material issued to stage A (besides above) was worth Rs. 12,000. Prepare the process
5
cost account showing the cost per unit at each stage and the total cost of finished product at
the final stage.
25. The product of a manufacturing concern passes through two processes A and B and then to
finished stock. It is ascertained that in each process normally 5% of the total weight is lost
and 10% is scrap which from process A and B realises Rs.80 per ton and Rs.200 per ton
respectively. The following are the figures relating to both the processes.
Process A
Process B
Materials in tons
1,000
70
Cost of material per ton (Rs.)
125
200
Wages (Rs.)
28,000
10.000
Manufacturing expenses (Rs.)
8,000
5,250
Output in tons
830
780
Prepare process accounts showing cost per ton of each process. There is no stock or work in
progress in process.
26. A product passes through two distinct Processes A and B and then to finished stock. The
output of process A passes direct to B and that of B passes to Finished product. From the
following information you are required to prepare Process accounts.
Process A Rs.
Process B Rs.
Materials consumed
12,000
6,000
Direct labour
14,000
8,000
Manufacturing expenses
4,000
4,000
Input to process A (units)
10,000
Input to process A' (value)
10,000
Output (units)
9,400
8,300
Normal loss (% of input)
5%
10%
Value of normal loss (per 100 units)
8
10.
27. A product passes through three processes. The following information is extracted from cost
records relating to Process I :
Particulars
Rs.
Materials introduced in units
1,000
Rate per unit (Rs.)
10.00
Labour cost (Rs.)
8,000
Overhead expenses (Rs.)
3,500
Normal process losses
5%
Sale of normal process loss per unit (Rs.)
3
Actual output units
950
Prepare process account showing clearly calculation of normal and abnormal losses or gains
if any.
28. Given :
6
32. Given :
No. of bus
No. of trips
Distance covered (one way)
No. of days in a month
Seating capacity
Occupancy rate
Calculate Passenger kilometers.
10
2 each
30 k.m.
30
40
80%
33. From the following particulars calculate B.E.P. and P/V ratio.
Rs.
Fixed Expenses
1,50,000
Variable Cost per unit
10
Selling Price per unit
15
34. From the following data, calculate B.E.P. and P/V ratio.
Selling Price per unit
Variable Manufacturing Cost per unit
Variable Selling Cost per unit
Fixed Factory Overheads
Fixed Selling Cost
Rs.
40
25
0.3
1,80,000
35. Given :
Fixed overhead Rs. 2,40,000
Variable cost per unit Rs. 15
Selling price per unit Rs. 30.
Find out : (a) Break even sales units, and (b) if the selling price is reduced by 10%, what will
be the new break even point ?
36. Profit
Rs. 200
Sales
Rs. 2,000
Variable cost
75% of sales
(a) Find out Break even sales ; and (b) what would be the sales volume to earn a profit of
Rs. 500.
37. From the following figures, you are required to calculate (i) P/V Ratio, (ii) Break Even Sales
Volume (iii) Margin of Safety and (iv) Profit.
Sales Rs. 4,000; Variable cost Rs. 2,000; Fixed cost Rs. 1,600.
38. Given :
Rs.
Break even volume
8,000
Fixed costs
3,200
Find out profit when sales are Rs. 10,000.
39. Calculate the break-even point from the following figures.
Rs.
Sales
3,00,000
Fixed expenses
75,000
Direct Materials
1,00,000
Direct Labour
60,000
Direct expenses
40,000.
40. From the following data, calculate the break-even point :
Rs.
Selling price per unit
20
Direct Materials cost per unit
8
Direct Labour cost per unit
2
Variable overhead per unit
3
Fixed overheads (total)
28,000
If sales are 20% above the break-even point, determine the net profit.
41. From the following figures, calculate the sales required to earn a profit of Rs. 1,20,000.
Rs.
Sales
6,00,000
Variable costs
3,75,000
Fixed costs
1,80,000.
42. From the following data, calculate :
(a) Break-even point expressed in sales rupees.
(b) Number of units to be sold to earn a profit of Rs. 60,000 a year.
Selling price
Rs. 20 per unit
Variable manufacturing cost
11 per unit
Variable selling cost
3 per unit
Fixed costs
Standard
Units
Price (Rs.)
1,010
1.0
410
1.5
350
2.0
Materials
A
B
C
Units
1,080
380
380
Actual
Price (Rs.)
1.2
1.8
1.9
47. From the data given below, calculate material usage variance.
Consumption for 100 units of product
Raw Materials
Standard
Actual
A
40 units @ Rs. 50 per unit
50 units @ Rs. 50 per unit
B
60 units @ Rs. 40 per unit
60 units @ Rs. 45 per unit.
48. From the following data, calculate labour cost and efficiency variances :
The budgeted labour force for producing product A is: i) 20 Semi-skilled workers @ p. 75
per hour for 50 hours; ii) 10 Skilled workers @ Rs. 1.25 per hour for 50 hours.
The actual labour force employed for producing A is: i) 22 Semi-skilled workers @ p. 80
per hour for 50 hours; ii) 8 Skilled workers @ Rs. 1.20 per hour for 50 hours.
49. Compute material price, usage and mix variances from the data given below :
Material
X
Y
Qty.
Kgs.
6.00
2.00
Standard
Unit Price
Rs.
1.50
3.50
Total
Rs.
9.00
7.00
Qty.
Kgs.
5.00
1.00
Actual
Unit Price
Rs.
2.40
6.00
Total
Rs.
12.00
6.00
10
11