Professional Documents
Culture Documents
3, August 1987
652
0885-8950/87/0800-0652$01.00O1987
IEEE
situation
still
persists,
653
after checking for the non-cornvergence that may result
because of the numerical formulation, it is presumed
that it is due to the fact that under given operating
conditions of the network, the A.C. load flow does not
have a solution. These non-convergence situations as
well as the low bus voltage situations described
earlier are illustrated using the following two power
systems:
(1)
(2)
[7].
FROM
AY(x) = J(x).Ax
old
new
where,
x
= solution
AY(x) =
J(x) =
Ax
a
Fig. 1.
(2) The
Assisted
Saskatchewan
Power
The single line diagram of
the Manitoba assisted Saskatchewan Power Corporation
(SPC) system is shown in Fig. 2. The system has 45
buses in total, of which 4 buses, The Pas, Roblin,
Manitoba
=
=
or
654
Bus 38
60
70
'66
711
us42
Bus 45
Hypoth-
~tical
167
9I
Reston
Bus 44
--
Bus 41
Bus 30
Represents
ut01
Hydro Assistance
'aIi
Fig. 2.
655
3.0 A
HEURISTIC
ALGORITHM
FOR
THE
CORRECTION
OF
While
TABLE I
A list of non-convergent outage contingencies
for the two test systems
IEEE RTS
Elements 6 and 27 Out
Elements 6 and 7 Out
Elements 23 and 29 Out
Elements 11 and 13 Out
Elements 24 and 28 Out
1
1
10
10
10
11
11
11
11
17
23
24
25
26
26
tlements 28
El ements 29
and
and
and
and
and
and
and
and
and
and
and
and
and
and
and
and
and
and
and
and
SPC System
10 Out
57 Out
19 Out
56 Out
66 Out
14 Out
34 Out
57 Out
Out
66
26
24
26
56
46
Out
Out
Out
Out
Out
70 Out
36 Out
36 Out
Elements
Elements
Elements
Elements
Elements
Elements
Elements
Elements
Elements
Elements
Elements
Elements
Elements
Elements
Elements
Elements
Elements
the
A.C.
load
flow,
if
the
3.2.
Line/Transformer
Outage Contingencies
El ements
Elements
El ements
Elements
El ements
Elements
El ements
Elements
El ements
Elements
El ements
Elements
El ements
Elements
El ements
iterating
adequacy indices
1 and 11 Out
5 and 26
10 and 34
10 and 57
11 and 13
11 and 18
11 and 56
11 and 60
16 and 26
18 and 57
23 and 26
25 and 34
26 and 37
26 and 51
28 and 29
28 and 41
29 and 41
Elements 38 and 65
Elements 58 and 59
Elements 64 and 65
41 Out
Elements 36
65 Out
El ements 54
63 Out
Elements 58
Outage of element 43 and any element outage
combination involving element 43.
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
10l
(1)
(2)
The
Out
deUgmined.
656
(3)
(4)
(2)
(3)
calculated.
Increase the
scheduled generation
proportionately
Fig. 4.
Decrease the
scheduled generation
proportionately
~ _-
Power
at
the
Voltage
(1)
iPig. 5.
657
4.0
(2)
(3)
TABLE II
Number of voltage violation contingencies for three
voltage levels
System description
IEEE RTS
SPC system
0.85
0.90
0.95
39
178
334
39
144
(4)
(5)
715
(1)
(2)
(3)
(4)
(5)
(1)
(2)
(3)
(4)
(5)
(6)
5.0 CONCLUSIONS
658
conjunction with the appropriate corrective <actions
Two simplified
has been presented i n this paper.
heuristic algorithms, that can be easily integrated
into the fast decoupled A.C. load flow have been
suggested f'or rescheduling the generating units and
for calculating the VAr rating of a power factor
violation
each
voltage
for
device
improvernent
has
techniques
The
incorporated
contingency.
successfully alleviated many of the voltage problems
cause
which
situations
non-convergent
and
the
discontinuities in the quantitative evaluation of
system adequacy indices. It should, however, be noted
that the effectiveness of the heuristic algorithms
presented in Section 3.0 depend on the availability of
real and reactive power at the -appropriate buses. In
this study it was assumed that the total installed
capacity at any bus is available for rescheduling.
Restriction can, however, be imposed on any generating
bus after making minor modifications in the algorithm
The availability of
presented in Section 3.1.
reactive power can be made possible by installing VAr
supplying devices at appropriate buses in a power
network.
This may, however, involve extra capitol
Decision regarding the trade-off
expenditures.
between the quality of the power supply and the
additional investment should be made judiciously by
system planning engineers and system managers.
6.0 REFERENCES
1.
3.
4.
5.
6.
7.
8.
TABLE III
MVAr rating of a power factor improvement device
for the IEEE RTS
9.
11.
3
4
6
8
9
108
15
42
203
35
6
4
9
11
14
& 7 out
& 7 out
& 10 out
& 13 out
& 15 out
72
25
68
7 out
72
9 & 10 out
11 & 13 out
25
6 &
68
10.
7 out
6 &
9 & 10 out
11 & 13 out
TABLE IV
MVAr rating of
imnprovernent device
for the SPC system
.,- -
--_--
0.85
0.95
Line
Line
Line
Bus MVAr Contingency MVAr Contingency MVAr Contingency
3
13
14
15
16
18
19
69
76
30
23
45
31
12
12
39
12
20
22
23
24
109
47
17
25
38
25
9
5
11
10
10
10
10
58
25
58
58
58
27
20
28
1
43
1
43
58
&
&
&
&
&
&
&
&
&
&
&
57
57
57
57
57
59
34
59
59
59
35
13.
a power factor
5
6
7
8
12
12.
out
out
out
out
out
out
out
out
out
out
out
& 40 out
& 36 out
& 43 out
& 45 out
& 43 out
& 45 out
& 59 out
4
69
76
24
23
45
20
12
20
11
10
10
10
10
58
25
58
58
58
&
&
&
&
&
&
&
&
&
&
57
5'7
57
57
57
59
34
59
59
59
out
out
out
out
out
out
out
out
out
out
17
20 & 40 out
28 & 36 out
& 43 out
43 & 45 out
13
43 & 45 out
12
82
47
t & 43 out
52
76
24
18
45
11
10
10
10
10
58
&
&
&
&
&
&
out
out
out
out
out
out
out
20
9
9
20
25
58
58
58
12
82
28 & 36 out
28 & 36 out
1 & 43 out
43 & 45 out
1 & 43 out
43 & 45 out
47
17
9
13
&
&
&
&
57
57
57
57
57
59
34
59
59
59
out
out
out
Discussion
M. G. Lauby (MAPP CC, Minneapolis, MN): The authors are to be
complimented on their paper presenting techniques to produce reasonable
analysis techniques for voltage adequacy assessment. I have a few
questions.
The discusser has many times wondered if the sole application of the
fast decoupled load flow (FDLF) for adequacy assessment would result
in a number of unsolved cases, though there is a solution, which many
times occurs when contingency enumeration is being performed. Namely,
though the FDLF is tolerant of the starting voltage vector, it can subsequently diverge because the starting poitit is not adequate enough for
solution. Many times a Gauss-Seidel technique is used to gain a better
starting vector in these cases. The authors have presented an application of Iwamoto et al. which they indicate will resolve this problem.
Unfortunately, this could not be demonstrated in the paper, as all conditions which diverged actually had no reasonable solution. Have the
authors continued their investigations with this technique and could they
demonstrate that an unsolved case using the FDLF is subsequently solved
using the FDLF with the Iwamota et al. technique?
I can appreciate the heuristic algorithms implemented for with adequacy
assessment where only one reasonable solution is required and minimization of generation shift or losses is not needed. Can it be demonstrated
that these algorithms are quicker, based on CPU requirements, than