You are on page 1of 168

2011

PMP EXAM GUIDE


Project Management Professional

PANKAJ SHARMA
PMP,PRINCE 2 PRACTIONER

PMP EXAM GUIDE

PMP

EXAM
GUIDE

PANKAJ SHARMA

Project Management Body of Knowledge , Fourth Edition (PMBOK Guide) 2008


Project Management Institute, Inc.

PMP EXAM GUIDE

ABOUT THE AUTHOR


Pankaj Holds Master degree in computer engineering from Birla Institute of technology and
Science, Pilani (India) and is a certified PMP, ITIL v3 and a Prince2 practitioner. Enriched with
long industry experience, coupled with excellent professional track record, Pankaj is extremely
passionate about sharing his professional knowledge and experience. He has coached employees
from the companies IBM, Accenture, Deloitte, Birlasoft, HCL, TCS and Indian defense forces
(Army, Navy and Indian Air force). Presently he is Chief Technology Officer for Connoisseur
Consulting Solutions Pvt Ltd and in the current role he is responsible for IT and business
Strategy management.
An energetic and enthusiastic project management consultant and trainer with over 15 years of
practical hands-on project and program management experience in managing and directing mid
and large sized IT program/projects involving distributed teams in Manufacturing, HR and
healthcare verticals across US, Europe and UK geography.

PMP EXAM GUIDE

CONTENTS OVERVIEW
CONTENTS OVERVIEW ______________________________________________________________ 4

Introduction to PMP Examination _______________________________________________ 7


Introduction to PMI _______________________________________________________________ 8
Purpose of PMBOK Guide __________________________________________________________ 8
Why Become a Certified PMP ________________________________________________________ 9
PMP Examination _________________________________________________________________ 9
PMI Principles ___________________________________________________________________ 12

Project Management Framework _______________________________________________ 15


Project __________________________________________________________________________ 16
Why Projects Fail? ________________________________________________________________ 18
Project Management ______________________________________________________________ 18
Organizational Structure ___________________________________________________________ 22
The Project Life Cycle ______________________________________________________________ 24
Project Management Knowledge Areas _______________________________________________ 28

Project Integration Management _______________________________________________ 36


Project Integration Management ____________________________________________________ 37
Develop Project Charter ____________________________________________________________ 38
Develop Project Management Plan ___________________________________________________ 42
Direct and Manage Project Execution _________________________________________________ 43
Monitor and Control Project Work ___________________________________________________ 45
Perform Integrated Change Control __________________________________________________ 46
Close Project or Phase _____________________________________________________________ 48

Project Scope Management ____________________________________________________ 50


Project Scope Management _________________________________________________________ 51
Collect Requirements ______________________________________________________________ 52
Create WBS ______________________________________________________________________ 56
Verify Scope _____________________________________________________________________ 58
Control Scope ____________________________________________________________________ 59
4

PMP EXAM GUIDE

Project Time Management ____________________________________________________ 61


Project Time Management _________________________________________________________ 62
Define Activities __________________________________________________________________ 63
Sequence Activities _______________________________________________________________ 65
Estimate Activity Resources _________________________________________________________ 68
Estimate Activity Duration __________________________________________________________ 70
Develop Schedule _________________________________________________________________ 72
Control Schedule _________________________________________________________________ 77

Project Cost Management _____________________________________________________ 80


Project Cost Management __________________________________________________________ 81
Estimate Costs ___________________________________________________________________ 82
Determine Budget ________________________________________________________________ 85
Control Costs ____________________________________________________________________ 87
Earned value Management (EVM) ____________________________________________________ 88

Project Quality Management __________________________________________________ 93


Project Quality Management________________________________________________________ 94
Plan Quality _____________________________________________________________________ 96
Perform Quality Assurance _________________________________________________________ 99
Perform Quality Control ___________________________________________________________ 101

Project Human Resource Management _________________________________________ 106


Project Human Resource Management_______________________________________________ 107
Develop HR Plan _________________________________________________________________ 108
Acquire Project Team _____________________________________________________________ 111
Develop Project Team ____________________________________________________________ 113
Manage Project Team ____________________________________________________________ 115
Organization Theories ____________________________________________________________ 118

Project Communication Management __________________________________________ 122


Project Communication Management _______________________________________________ 123
Identify Stakeholders _____________________________________________________________ 124

PMP EXAM GUIDE

Plan Communication _____________________________________________________________ 126


Distribute Information ____________________________________________________________ 128
Manage Stakeholder Expectations __________________________________________________ 130
Report Performance ______________________________________________________________ 132

Project Risk Management ____________________________________________________ 135


Project Risk Management _________________________________________________________ 136
Plan Risk Management____________________________________________________________ 137
Identify Risks ___________________________________________________________________ 139
Perform Qualitative Risk Analysis ___________________________________________________ 142
Perform Quantitative Risk Analysis __________________________________________________ 145
Plan Risk Responses ______________________________________________________________ 148
Monitor and Control Risks _________________________________________________________ 151

Project Procurement Management _____________________________________________ 154


Project Procurement Management __________________________________________________ 155
Plan Procurements _______________________________________________________________ 156
Conduct Procurements____________________________________________________________ 159
Administer Procurements _________________________________________________________ 161
Close Procurements ______________________________________________________________ 163

Professional Responsibility and Ethics___________________________________________ 166


Introduction ____________________________________________________________________ 167
Ensure Integrity _________________________________________________________________ 167
Contribute to PM Knowledgebase and Community _____________________________________ 167
Respect Diversity ________________________________________________________________ 168

PMP EXAM GUIDE

Introduction

Introduction to
PMP Examination
Introduction to PMP Examination

Introduction to
PMP Examination

Introduction to PMI
Purpose of Guide to PMBOK Guide
Why Become a Certified PMP
PMP Examination
PMI Principles

PMP EXAM GUIDE

Introduction to PMI

PMI is headquartered in USA, founded in 1969

Worlds leading not-for-profit project management association

Over 288,000 Members across 170 countries

Advocates Best Practices in Project, Program and Portfolio Management

Credentials

Certified Associate in Project Management (CAPM)

Project Management Professionals (PMP)

Program Management Professional (PgMP)

PMI Risk Management Professional (PMI-RMP )

PMI Scheduling Professional (PMI-SP )

Purpose of PMBOK Guide

The SUM of knowledge within the profession of project management

Includes widely applied practices and innovations

Constantly evolving

The knowledge and practices are applicable to most projects

PMBOK Guide is used as a reference for professional development programs

Structure of PMBOK Guide

Section I The Project Management Framework

Section II The Standard for Project Management of a Project

Section III The Project Management Knowledge Areas


8

PMP EXAM GUIDE

Program based on Newly Launched Fourth Edition of PMBOK Guide

Why Become a Certified PMP

Widely recognized Project Management Certification

Worldwide Recognition of your knowledge of Project Management

Demonstrates Proof of Professional Achievement

Improves the way you manage your Projects

Increases your Marketability

Displays your willingness to pursue Growth

Increases Customer Confidence

Valued Globally across Industry Verticals & Companies

PMP Examination

PMP EXAM GUIDE

PMP Examination

Source: PMI Credential Handbook

PMP Examination Type of Questions

Scenario based

Situational

Using attached illustrations such as Network Diagram

Definitions

Fill in the Blanks

Formulas and Computing


10

PMP EXAM GUIDE

Negative descriptors such as Except

Two likely Answers

Roadmap to Become a PMP

11

PMP EXAM GUIDE

PMI Principles

A Project does NOT exists without a CHARTER

The Project Scope includes all of the work and ONLY the work

Activities are estimated by the Team

Lessons learnt are collected throughout the Project

Establish the extent of completion if the Project is terminated prematurely

Work Breakdown Structure is the basis for all planning activities

Quality is not an afterthought.it should be BUILT-IN

Project Management Plan drives how the Project work will be carried out

Risks are identified throughout the Project

Identify all Stakeholders to prevent Changes

Use Historical Information for Planning

Project Manager spends most of his/her time Communicating

Save Scope, Schedule and Cost baselines for comparison

Protect the Buyer and the Seller relationship to work as a Team

Set-up formal Change Control System

Prefer Preventive actions over Corrective actions

Project Manager should preserve his integrity

12

PMP EXAM GUIDE

13

PMP EXAM GUIDE

Chapter 1

Project Management
Framework

Project Management
Framework

Projects and Operations


Project Management
Organizational Structure
Project Life Cycle
PMBOK Guide Knowledge Areas

14

PMP EXAM GUIDE

Project Management
Framework
Project Management Framework

Learning Objectives
After the completion of this chapter, the learner will be
able to:
Explain the PMBOK Guide project management
concepts
Explain why projects are undertaken
Describe the phases of the project life cycle
Describe the five project management process groups
Name the nine knowledge management areas
Map the process groups and the nine knowledge areas

15

PMP EXAM GUIDE

Project

Definition A project is a temporary endeavor undertaken to create a unique product or


service.
as per

PMBOK
Guide
All organizations perform work as projects or as operations. There is a thing line between the
two but still both share the following common characteristics:

Are performed by people


Constrained by resources
Are planned, executed and managed

Temporary
Temporary means that every project has a definite beginning and end. It does not mean that the
duration is short. Some projects can last for years. The projects end when the objectives of the
project have been achieved or it is clear that the project objectives cannot be met.

Unique
Unique means that the product or service or result is different from other product or service or
result. Projects are unique even if the category of the product it creates is a large domain. For
example, buildings are constructed but every such building that is created is unique because of
the difference in location, raw materials, contractors, and so on.

Progressive Elaboration
You learn about the project as it progresses. The specifications of the product become clear as
you move further and requirements become clearer. This is also called proceeding in steps.

Example of Projects

Building a new office


Designing a new product or service
Creating an advertisement campaign
Creating a new process with a business unit
16

PMP EXAM GUIDE

Moving from one building to another


Designing a space vehicle

Project

A temporary endeavor means that every project has a definite


beginning and end.
Unique means that the product or service or result is different
from other product or service or result.
Progressively elaborated - proceeding in steps

Projects versus Operations


Operations are ongoing and produce repetitive products, services, or results. Operations work is
ongoing that sustains the organization over time.

Operations and projects differ in the way that operations are ongoing but projects are
temporary.
Operations are repetitive in nature while projects create a unique product or service.
Operations objective is to sustain business while project closes after the objectives are
achieved.

Examples of Operations

Assembly line production


Call center operations Help desk, customer service, and so on
PROJECTS

OPERATIONS

Temporary

Ongoing

Unique

Repetitive

Closes after attaining the objectives

Objective is to sustain business

Prototyping the new car model

Assembly line production

17

PMP EXAM GUIDE

Why Projects Fail?

Lack of clearly defined purpose


Inexperienced project Managers
Poor estimation of duration and cost
Cultural and ethical misalignment
Poor requirements and scope management
Lack of coordination of resources and activities
Poor communication
Inadequate planning of scope, schedule, resources, cost, risk and quality
Lack of progress and quality control

Project Management

Definition Project Management is the application of knowledge, skills, tools and


as per
techniques to project activities to meet the project requirements.
PMBOK
Guide
The project team carries out the work needed to complete the project, while the project manager
schedules, monitors, and controls the various project tasks. The project manager requires
knowledge, performance, and personal skills to perform better at their jobs.
The typical work of a project manager involves:

Requirements gathering
Managing stakeholder expectations
Managing project constraints including scope, quality, schedule, resources, budget, and
risk.

18

PMP EXAM GUIDE

What is the role of a Project Manager?


The role of a Project Manager is to achieve project objectives. It is different from the role of a
functional or operations manager. The functional manager provides management oversight for an
administrative area. The operations managers are accountable for a facet of the core business.
A project manager should have knowledge and skills in the areas of Project Management,
Specific Application Area, and General Management.
For effective project management, the project manager should have:
1. Knowledge: This relates to what the project manager knows about project management.
2. Performance: This relates to what the project manager is able to accomplish by using
this knowledge.
3.
Personal Skills: This relates how the project manager behaves when managing the
project (attitudes, core personality characteristics, and leadership. To sum up the ability
to guide the project team while achieving project objectives and balancing the project
constraints.
A project manager spends about 90% of time communicating.

Project Stakeholders
Project stakeholders are individuals and organizations involved in the project that will be directly
or indirectly impacted by the project. The stakeholders may have positive or negative influence
on the outcome of the project.

19

PMP EXAM GUIDE

The stakeholders must be identified early in the project. This is often a difficult task. The project
manager needs to manage the expectations of the key stakeholders to successfully complete the
project.
Key stakeholders include:

Project Manager
Customer / User
Performing organization
Project team members
Project management team
Sponsor
Influencers
PMO

Apart from the above, there are other categories of stakeholders such as external and internal
stakeholders, team members and their families, government agencies, and so on.

Project, Portfolio and Program Management

Portfolio :
A portfolio refers to a collection of projects or programs and other work that
Definition are grouped together to facilitate effective management of that work to meet
as per
strategic business objectives.

PMBOK
Program:
Guide
A program is defined as a group of related projects managed in a coordinated
way to obtain benefits and control not available from managing them
individually.

Programs

Collection of related projects


Controls are implemented and managed in a coordinated way
Collective benefits are realized
Each project has a project manager
20

PMP EXAM GUIDE

Portfolios

Projects share resources and depends on the outcomes of other projects

Collection of programs and projects


Projects meet a specific business goal or objective
Includes weighing the value of each project against the portfolios strategic
objective
Ensures efficient use of resources

Project Management Office (PMO)

Centralized units to oversee project and programs within the organization


Establishes and maintains the standards of project management methodologies
Support managers in planning, estimating, risk management and provide trainings

Project Management Office (PMO)


A project management office (PMO) is an organization body or entity assigned various
responsibilities related to the centralized and coordinated management of those projects
under its domain.

21

PMP EXAM GUIDE

Organizational Structure
Functional
Organization

Weak Matrix
Organisation

Balanced Matrix
Organisation

Strong Matrix Projectized


Organisation Organisation

PMs Title

Expediter

Expediter/
Coordinator

Project Manager

Project
Manager

Project
Manager

Decision
Making
Power

Functional
manager

Functional
manager plays
a major role,
but PM will
make decisions

PM and the
Functional
Manager will
have equal
power

Project
Manager

Project
Manager

Resources

From within
a Dept.

Project
members are
from different
departments

Project members
are from
different
departments

Project
members are
from different
departments

Project
based only

Resource
Allocation

As needed

Only 25% will


be assigned to
the projects

About 50% will


be assigned to
the projects

About 80%
will be
assigned to the
projects

About
100% will
be assigned
to the
projects

Resources
Reports to

Functional
manager

Functional
manager

Two manager
(FM and PM)

Project
Manager

Project
Manager

PM Reports
to

Functional
manager

Functional
manager

Functional
manager and
his/her senior
manager

Company
Senior manager

Company
senior
manager/
higher
authority

After Project
Completion

Team go
back to their
Dept. (home)

Team go back
to their Dept.
(home)

Team go back to
their Dept.
(home)

Team go back
to their Dept.
(home)

No home
move to
different
project or
get laid off

Source: A Guide to the Project Management Body of Knowledge, Fourth Edition (PMBOK Guide) 2008 Project Management Institute, Inc.
All Rights Reserved.

22

PMP EXAM GUIDE

Organization Types Advantages and Disadvantages

Org. Type

Advantages

Disadvantages

Matrix

Highly visible project objectives

Not cost effective because of extra administrative


personnel

Better Project Manager control over


resources

More than ONE boss for project teams

Better coordination

More complex to monitor and control

Team members maintain a home

Higher potential for conflict and duplication of effort


and functional managers have different priorities

Team members report to one supervisor


and clearly defined career paths

No career path in Project Management

Easier management of specialists

People place more emphasis on their functional


specialty to the determent of the project

Efficient project organization

No Home when project is completed

More effective communication than


functional

Duplication of facilities and job functions

Loyalty to the project

Lack of professionalism in disciplines and less


efficient use of resources

Functional

Projectized

23

PMP EXAM GUIDE

The Project Life Cycle


All projects, large or small, can be mapped to the following life cycle:

Starting the project


Organizing and preparing
Carrying out the project work
Closing the project

A typical life cycle shows the following characteristics:

Stakeholder influence and risk are more at the start of the project and decrease as project moves
towards closure.
Cost and staffing levels are low at the start, peak as project moves into execution and finally drop
as project inches towards closure.
The cost of changes increases and correcting errors increases as the project moves towards
closure.

Process Management Process Groups


The five process groups include:

1.
2.
3.
4.
5.

Initiating - process group authorizes the project


Planning - process group plans the course of action to achieve objectives
Executing - process group uses the resources to carry out project tasks
Monitoring - process group measures progress to identify variances
Closing - process group formalizes product acceptance and closure

Though the five project management process groups appear as discrete elements, in
reality they overlap with each other.
The application of project management processes is iterative in nature and is repeated
during the project life cycle.

24

PMP EXAM GUIDE

Process Management Process Groups

Source: A Guide to the Project Management Body of Knowledge, Fourth Edition (PMBOK Guide) 2008 Project
Management Institute, Inc. All Rights Reserved.

Project Management Process Groups

25

PMP EXAM GUIDE

Project Management Process Groups Interaction


Source: A Guide to the Project Management Body of Knowledge, Fourth Edition (PMBOK Guide) 2008 Project Management Institute, Inc.
All Rights Reserved.

Initiating Process Group

Conduct cost-benefit analysis


Determine and define the business needs and the project scope
Know the project boundaries and constraints
Identify high level risks
Understand the required project organization structure
Estimate budget and resource requirements
Assign a project manager
Obtain the project charter approval
Formally authorize to start a new project or phase

Planning Process Group

Determine how you will plan and develop the project management plan
Develop the project requirements in detail and agree the final scope
Determine the required project activities and their sequencing
Develop schedule using estimated resources and costs
26

PMP EXAM GUIDE

Agree what quality standards will be met by the project and how
Define how project staffing will be done
Establish the communication requirements and how it will be fulfilled
Identify what can go wrong and the plans to deal with them
Document what products or services will be acquired from outside the project
Gain formal approval and buy-in from everybody involved in the project

Executing Process Group

Execute activities in the project plan


Procure required project resources
Complete work packages
Document lessons learnt
Implement approved changes, corrective and preventive actions
Ensure processes are followed
Hold team building activities and boost morale and efficiency
Manage resource allocation and utilization
Hold progress review meetings and distribute progress reports
Keep everyone focused on the project goals

Monitoring & Control Process Group

Measure project performance using the documented technique in the plan


Identify variances and recommend corrective actions to get back on track
Approve changes, defect repair, corrective and preventive actions
Resolve conflicts and issues
Manages changes to scope, time and cost
Perform impact analysis to approve or reject changes
Obtain formal acceptance of deliverables from the customer
Monitor the status of risks and identify new risks have emerged
Measure team member performance

Closing Process Group

Confirm all project requirements are met


Obtain formal acceptance of product from the customer
Hand over the completed deliverables to the operations team
Compile lessons learnt
Measure customer satisfaction
27

PMP EXAM GUIDE

Archive project data and information for future reference


Release resources

Project Management Knowledge Areas


The 42 Processes within the 5 Process Groups, are mapped into 9 Project Management
Knowledge Areas:

28

PMP EXAM GUIDE

Processes

Initiation

Planning

Execution

Monitoring &
Control

Close Out

Develop Project
Charter

Develop Project
Management Plan

Direct and Manage


Project Execution

Monitor and
Control Project
Work

Close Project or
Phase

Knowledge
Areas
Integration
Management

Perform Integrated
Change Control

Scope Management

Scope Planning

Scope Verification

Scope Definition

Scope Control

Create WBS

Time Management

Activity Definition

Schedule Control

Activity Sequencing
Activity Resource
Estimating
Activity Duration
Estimating
Schedule Development

Cost

Estimate Costs

Cost Control

Management

Estimate Budgets

Quality Management

Quality Planning

Perform Quality
Assurance

Perform Quality
Control

Human Resource

Human Resource
Planning

Acquire Project
Team

Manage Project
Team

Management
Develop Project
Team
Manage Project
Team

29

PMP EXAM GUIDE

Communication
Management

Identify
Stakeholders

Communications
Planning

Information
Distribution

Report Performance

Manage
Stakeholders
Expectation

Risk

Risk Management
Planning

Monitor & Control


Risk

Management
Risk Identification
Qualitative Risk Analysis
Quantitative Risk
Analysis
Risk Response Planning

Plan Procurement

Procurement
Management

Conduct
Procurement

Administer
Procurements

Close
Procurement

Source: A Guide to the Project Management Body of Knowledge, Fourth Edition (PMBOK Guide) 2008 Project Management Institute, Inc.
All Rights Reserved.

Project Integration Management

Processes that integrates the different elements of project management


Coordinates the project work is done correctly and in the right order
Ensures changes are properly controlled and managed
Comprises of the following processes:

Develop Project Charter


Develop Project Management Plan
Direct and Manage Project Execution
Monitor and Control Project Work
Perform Integrated Change Control
Close Project or Phase

Project Scope Management

Ensures project includes all of the work and only the work required
Identifies, defines and controls the project work
Verifies that the deliverables meet the specified criteria
Comprises of the following five processes:
30

PMP EXAM GUIDE

Collect Requirements
Define Scope
Create WBS
Verify Scope
Control Scope

Project Time Management

Processes concerning with the timely completion of the project


Determines the time and the order in which project work will be done
Controlling to ensure everything gets done on time
Comprises of the following six processes:

Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Develop Schedule
Control Schedule

Project Cost Management

Processes to ensure the project stays within the budget


Determines the project budget
Controls the changes to the project budget
Comprises of the following three processes:

Estimate Costs
Determine Budget
Control Costs

Project Quality Management

Processes that ensures the project will satisfy the agreed quality standards
Identifies the relevant standards and how they will be met
Assurance activities to ensure the agreed processes are followed
Monitoring project results to determine compliance
Comprises the following three processes:

Plan Quality
31

PMP EXAM GUIDE

Perform Quality Assurance


Perform Quality Control

Project Human Resource Management

Processes that organize and manage the project team


Identifies the required roles on the project
Obtains the human resources needed to complete the work
Enhance competencies and performance
Comprises of the following four processes:
Develop Human Resource Plan
Acquire Project Team
Develop Project Team
Manage Project Team

Project Communication Management

Processes to ensure timely distribution of project information


Determines the information needs of the project stakeholders
Makes the information available in timely manner
Collecting and distributing project performance information
Comprises of the following processes:

Identify Stakeholders
Plan Communications
Distribute Information
Manage Stakeholder Expectations
Report Performance

Project Risk Management

Processes to deal with the unexpected when it does happen


Identifying events that might affect the project
Developing plan and actions to deal with those event
Comprises of the following six processes:

Plan Risk Management


Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Responses
Monitor and Control Risks
32

PMP EXAM GUIDE

Project Procurement Management

Processes to purchase or acquire the products and services


Selecting who will supply the required products and services
Planning and administering the contracts
Comprises of the following processes:

Plan Procurements
Conduct Procurements
Administer Procurements
Close Procurements

Professional Responsibility

A PMP must follow the Project Management Institute Code of Ethics and
Professional Conduct
The responsibilities includes:

Doing the right things


Making good choices
Keep learning and getting better
Respecting others culture
Covers legal, ethical and professional behavior of a PMP

33

PMP EXAM GUIDE

34

PMP EXAM GUIDE

Chapter 2

Project Integration
Management

Project Integration
Framework

Develop Project Charter


Develop Project Management Plan
Direct and Manage Project Execution
Monitor and Control Project Work
Perform Integrated Change Control
Close Project or Phase

35

PMP EXAM GUIDE

Project Integration
Management
Project Integration Management
Learning Objectives
After the completion of this chapter, the learner will be
able to:
List the various processes of Project Integration
Management
Describe the process of Develop Project Charter
Describe the process of Develop project plan
Describe the process of Direct and Manage Project
Execution.
Describe the process of Monitor and Control Project
Work
Describe the process of Perform Integrated Change
Control
Describe the process of Close Project Or Phase
Explain the various project selection methods
Explain the components of a project management plan

36

PMP EXAM GUIDE

Project Integration Management

Definition Project Integration Management includes the processes and activities needed
as per
to identify, define, combine, unify, and coordinate the various processes and
PMBOK project management activities within the Project management process Groups.
Guide

Project Integration Management: Process Groups

Project Integration
Framework

Develop Project Charter


Develop Project Management Plan
Direct and Manage Project Execution
Monitor and Control Project Work
Perform Integrated Change Control
Close Project or Phase

37

PMP EXAM GUIDE

Develop Project Charter

Definition The process of developing a document that formally authorizes a project or a


as per
phase and documenting initial requirements that satisfy the stakeholder's
PMBOK needs and expectations.
Guide
Key Points about Project Charter

The approved Project Charter formally initiates a project.


The Project Manager should be preferably assigned during creation of the Project
Charter.
Project Charter gives the project manager authority to spend and commit corporate
resources
It provides high-level requirements for the project.

Inputs: Develop Project Charter

Project statement of work A project statement of work (SOW) is a narrative


description of products, services, or results to be supplied. The SOW is provided by
the sponsor. In case of external customer, the SOW can be part of Request for
Proposal (RFP), Request for Information (RFI) or the contract. The SOW provides
the information on business need, product scope and how the project fits into the
strategic plan.
Business case: The business case document explains the importance of the project from
business standpoint. It involves cost-benefit analysis to find whether the project is worth
doing or not.

Contract: This is the input if project is being done for an external customer.

Enterprise environmental factors: These include organization structure, market


conditions, and so on.

Organization process assets: These include policies and procedures, templates,


historical information, and lessons learned database.

38

PMP EXAM GUIDE

Tools & Techniques: Develop Project Charter

Expert Judgment: Involves talking to all the experts on the project to identify inputs to
the charter. These can include the subject matter experts, external consultants, PMO and
other important stakeholders.

Outputs: Develop Project Charter

Project Charter: The Project Charter documents the business need and the following
information:
o Project purpose
o Project objectives and success criteria
o High-level requirements, project description, and risks
o Summary milestone schedule
o Summary budget
o Assigned project manager
o Name of the sponsor authorizing the charter

Project Selection Methods

Benefit Measurement Model (also called Comparative approach )

Payback Period
Cost Benefit Analysis
Scoring Models
Net Present Value (NPV)
Internal Rate of Return (IRR)

Mathematical Models (also called Constrained Optimization)


Use linear, dynamic, non-linear, multi-objective programming to solve problem

1. Payback period the amount of time to recover your cost. It compares the initial
investment to the cash inflows expected over the life of the product.
o For example, Initial investment on a project is Rs. 4,00,000, Expected cash
inflows: Rs. 50,000 per quarter for first two years, Rs. 100,000 per quarter
thereafter.
39

PMP EXAM GUIDE

What is the payback period?

Cash inflows = Rs. 50,000 x 4 (quarters in a year) = Rs. 2, 00,000 per year for
first two years. Hence, year 1 inflow = Rs. 2, 00,000, year 2 inflow = Rs. 2,
00,000. Total Rs. 4, 00,000 in 2 years

o So payback is reached in 2 years.

2. Benefit Cost Ratio (BCR) or profitability Index: This is the ratio of project benefit and
the project cost.
o BCR = Revenue / Cost
o Select the project with a higher BCR

3. Present Value (PV): is the expected future cash flows expressed in todays monetary
value
o PV = FV / (1+r) n
o For example, Calculate the Present Value of $ 100,000 received three years from
now. The interest rate is 10 percent.
o PV = 100000 / (1+10/100)3 = $ 75,131

4. Net Present value (NPV) is the sum total of the Present Value of Cash Inflows
Present Value of Cash Outflows
o If NPV > 0, accept the project
o Or select the project with the greater NPV

5. Internal Rate of Return: The rate of interest at which the revenues and costs are equal.
o Select the project with a higher IRR.

40

PMP EXAM GUIDE

6. Return on Investment (ROI): A return ratio that compares the net benefits of a project/
product, verses its total cost.
o ROI = Operating Income / Investments

41

PMP EXAM GUIDE

Develop Project Management Plan

Definition Develop Project Management Plan is the process of documenting the actions
as per
necessary to define, prepare, integrate, and coordinate all subsidiary plans.
PMBOK
Guide

Inputs: Develop Project Management Plan

Project charter: explained earlier

Outputs from planning processes: Outputs from other project management planning
areas are used as an input to the project management plan. These include scope, cost,
time, quality, risk, human resource, communication, and procurement plans.

Enterprise environmental factors: explained earlier


Organizational process assets: explained earlier

Tools & Techniques: Develop Project Management Plan

Expert Judgment: explained earlier

Outputs: Develop Project Management Plan

Project management plan: The project management plan is a combination of subsidiary


plans. There is one sub subsidiary plan for each of the knowledge areas. These include
o Project scope management plan
o Schedule management plan
o Cost management plan
o Quality management plan
o Human resource management plan
o Communication management plan
o Risk management plan
o Procurement management plan
Note: The Project Management Plan is not the same thing as a project schedule.

42

PMP EXAM GUIDE

Direct and Manage Project Execution

Definition Direct and manage Project Execution is the process of performing the work
as per
defined in the project management plan to achieve the project's objectives.
PMBOK
Guide

Inputs: Direct and Manage Project Execution

Project management plan: The project management plan is a combination of subsidiary


plans.

Approved change requests: These are authorized and documented changes to the
project scope.

Enterprise environmental factors: explained earlier


Organizational process assets: explained earlier

Tools & Techniques: Direct and Manage Project Execution

Expert judgment: explained earlier

Project management information system: An information system consisting of the


tools and techniques used to gather, integrate, and disseminate the outputs of project
management processes. It is used to support all aspects of the project from initiating
through closing, and can include both manual and automated systems.

Outputs: Direct and Manage Project Execution

Deliverables: are anything that you produce during the course of project activities.

Work performance information: refers to the information generated as the project


progresses: These include status reports, progress reports and so on.

Change requests: Change requests are issued when there are issues during project.
These can result in change in scope, time, cost, quality and other factors.
43

PMP EXAM GUIDE

Project management plan updates: Update to the various subsidiary plans

Project document updates: Update to the various project documents.

44

PMP EXAM GUIDE

Monitor and Control Project Work

Definition Monitor and Control project Work is the process of tracking, reviewing, and
as per
regulating the progress to meet the performance objectives defined in the
PMBOK project management plan.
Guide

Inputs: Monitor and Control Project Work

Project management plan: explained earlier


Performance reports: explained earlier
Enterprise environmental factors: explained earlier
Organizational process assets: explained earlier

Tools & Techniques: Monitor and Control Project Work

Expert judgment: explained earlier

Outputs: Monitor and Control Project Work

Change requests: explained earlier


Project management plan updates: explained earlier
Project documented updates: explained earlier

45

PMP EXAM GUIDE

Perform Integrated Change Control

Definition Perform Integrated Change Control is the process of reviewing all change
as per
requests, approving changes and managing changes to the deliverables,
PMBOK organizational assets, project documents, and the project management plan.
Guide

Change Control Systems

Every documented change request must be either approved or rejected by an authorized


person.
Some changes require approval by the Change Control Board (CCB).
Any approved changes may required adjusting the scope, time, and resource requirements

Configuration Management
Configuration management system provides a standardized, effective, and efficient way to
centrally manage approved changes and baselines within the project.

Inputs: Perform Integrated Change Control

Project management plan: explained earlier


Work performance information: explained earlier
Change requests: explained earlier
Enterprise environmental factors: explained earlier
Organizational process assets: explained earlier

Tools & Techniques: Perform Integrated Change Control

Expert judgment: explained earlier


Change control meetings: A change control board is responsible for meeting and
reviewing the change requests and approving or rejecting those change requests.

46

PMP EXAM GUIDE

Outputs: Perform Integrated Change Control

Change request status updates: Change requests, if approved are implemented and the
status is updated in change request log.

Project management plan updates: : explained earlier


Project document updates: : explained earlier

47

PMP EXAM GUIDE

Close Project or Phase

Definition Close Project or Phase is the process of finalizing all activities across all of the
as per
project Management Process Groups to formally complete the project or
PMBOK phase.
Guide

Inputs: Close Project or Phase

Project management plan: explained earlier


Accepted deliverables: The deliverables that have been accepted as part of Verify
Scope.
Organizational process assets: explained earlier

Tools & Techniques: Close Project or Phase

Expert judgment: explained earlier

Outputs: Close Project or Phase

Final product service or results transition: Refers to the final product, service or result
that the project was authorized to produce.

Organizational process assets update: This includes updates to the various


organizational process assets that include the project files, project or phase closure
documents and lessons learned database.

48

PMP EXAM GUIDE

Chapter 3

Project Scope
Management

Project Scope
Management

Collect Requirements
Define Scope
Create WBS
Verify Scope
Control Scope

49

PMP EXAM GUIDE

Project Scope
Management
Project Scope Management

Learning Objectives
After the completion of this chapter, the learner will be
able to:

List the processes for project scope management


Describe the process of requirements gathering
Describe the process of defining project scope
Decompose project scope into work breakdown structure
Describe the process of verify scope
Describe how to control the project scope changes

50

PMP EXAM GUIDE

Project Scope Management

Definition Project Scope management includes the processes required to ensure that the
as per
project includes all the work required, and only the work required, to complete

PMBOK
the project successfully.
Guide

Project Scope Management: Process Groups

Project Scope
Management

Collect Requirements
Define Scope
Create WBS
Verify Scope
Control Scope

The term scope may refer to:

Product Scope: The features and functions in a product, service, or result.


Project Scope: The work that needs to be done in order to deliver a product, service or
result with the specified features and functions.

The product scope is measured against the requirement and project scope is measured against the
project plan.
The success of the project is dependent on how well the requirements are captured. These
requirements include the product requirements as well as the project requirements. Product
requirements include the technical and other specifications of the product whereas project
requirements include the business and project management requirements.

51

PMP EXAM GUIDE

Collect Requirements

Definition Collect Requirements is the process of defining and documenting stakeholders'


as per
needs to meet the project objectives.
PMBOK
Guide

Inputs: Collect Requirements

Project charter: The Project Charter is a summary document of what the project is
supposed to accomplish. This serves as key document to create the requirements
document.

Stakeholder register: Is the list of all the stakeholders. You need to gather requirements
from the all the stakeholders using different techniques such as interviews,
questionnaires, surveys and so on.

Tools & Techniques: Collect Requirements

Interviews: This is a one-to-one interaction with the stakeholders to understand the exact
needs.

Focus groups: This involves a group of people to discuss their needs with you.

Facilitated workshops: This is a structured technique where a moderator leads a group


through brainstorming together. The cross-functional teams work together and decide on
a common understanding and goals.
For example, Joint Application Development (JAD) sessions are used in the software
development industry. In manufacturing sector, Quality Function Deployment (QFD) is
used to arrive the critical characteristics of anew product.

Group creativity techniques: Some of the group creativity techniques include:


1. Delphi Technique: In Delphi Technique, a group of anonymous users is asked to
provide answers to specific questions. A moderator shares the ideas with everybody
and the iterations continue to settle down on a list of requirements from all.
52

PMP EXAM GUIDE

2. Mind maps: This is a excellent technique to visualize how the ideas relate to each
other.
3. Affinity Diagrams: This is a way to group same kind of ideas together in a group.
4. Brainstorming: This is the most common way of collecting the requirements where a
group of people sit down together to think of new ideas.
5. Nominal Group technique: This is a way of brainstorming where you write down
the ideas and then all vote for the best ones.

Group decision making techniques: There are various methods of arriving at a decision.
These include:
1.
2.
3.
4.

Unanimity: Everyone agrees in this case.


Majority: More than half of the people decide.
Plurality: The idea that gets the most votes.
Dictatorship: One person decides here.

Questionnaires and surveys: Use this method to elicit response from a larger set of
people.

Observations: Sometimes just observing the users gives an idea of the needs or how to
solve the problem.

Prototypes: Prototypes are scaled down versions of the product.

Outputs: Collect Requirements

Requirements documentation: Requirements documentation includes the business


need, project objectives, functional requirements, non-functional requirements, and
quality and acceptance criteria. It also includes the assumptions and constraints.

Requirements management plan: The requirements management plan describes how


the requirements will be managed through the project.

Requirements traceability matrix: This document describes where the requirements


came from. This document helps in creation of specific test cases.
53

PMP EXAM GUIDE

Define Scope

Definition Define Scope is the process of developing a detailed description of the project
as per
and product.

PMBOK
Guide

Inputs: Define Scope

Project charter: explained earlier


Requirements documentation: explained earlier
Organizational process assets: explained earlier

Tools & Techniques: Define Scope

Expert judgment: explained earlier


Product analysis: It involves better understanding the product or the project.

Alternatives identification: This is about exploring different ways to do the project


work. This might include licensing some part or outsourcing some part of the project to
external vendors.

Facilitated workshops: explained earlier

Outputs: Define Scope

Project scope statement: The scope statement tells you what to do (and what not to do).
The scope statement covers the following important items:

Project Objectives
Product Scope Description
Project Requirements
Exclusions
Deliverables
Acceptance Criteria
Constraints
Assumptions

Project document updates: Any updates to the project documents.


54

PMP EXAM GUIDE

Progressive Elaboration Versus Scope Creep

Progressive elaboration should not be confused with scope creep.

Progressive elaboration: Adding more details to the already defined scope and
not increasing the project scope.

Scope creep: Adding features and functionality (project scope) without


addressing the effects on time, costs, and resources, or without customer
approval.

55

PMP EXAM GUIDE

Create WBS

Definition The process of subdividing project deliverables and project work into smaller,
as per
more manageable components.
PMBOK
Guide
Work Breakdown Structure (WBS): Deliverable-oriented hierarchical decomposition of work.
It organizes and defines the total scope of the project.
Work Package: The lowest level WBS components that contain planned work. A work package
can be schedules, cost estimated, monitored and controlled.

Note: Work outside the WBS is outside the scope of the project.

Project

Phase 1 Phase 2 Phase 3


Figure: Work Breakdown Structure (WBS)

56

PMP EXAM GUIDE

Inputs: Create WBS

Project scope statement: explained earlier


Requirement documentation: explained earlier
Organizational process assets: explained earlier

Tools & Techniques: Create WBS

Decomposition: Decomposition is the subdivision of project deliverables into smaller,


more manageable components until the work and deliverable are defined at the work
package level.

Outputs: Create WBS

Work breakdown structure: is a deliverable-oriented hierarchical decomposition of


work. It organizes and defines the total scope of the project. The WBS is decomposed
into smaller, more manageable components until the work and deliverable are defined at
the work package level. It is the lowest level WBS components that contain planned
work.
Control accounts are established at work package level. Control account is used to
integrate scope, cost and schedule. It is also used for earned value measurement.

Work breakdown structure dictionary: WBS dictionary provides detailed description


of each WBS element.

Scope baseline: An approved version of the detailed scope statement, work breakdown
structure (WBS), and its associated WBS dictionary.

Project document updates: explained earlier

57

PMP EXAM GUIDE

Verify Scope

Definition The process of formalizing acceptance of the completed project deliverables


as per
PMBOK
Guide

Inputs: Verify Scope

Project management plan: explained earlier


Work performance information: explained earlier
Requirements documentation: explained earlier
Requirements traceability matrix: explained earlier
Organizational process assets: explained earlier

Tools & Techniques: Verify Scope

Inspection: Inspection includes measuring and verifying to determine whether work and
deliverables meet requirements and product acceptance criteria.

Outputs: Verify Scope

Accepted deliverables: Deliverables that meet the acceptance criteria are signed-off by
the customer.

Change requests: If the deliverables that are not accepted, a change request is raised.
The change request goes for approvals.

Project document updates

58

PMP EXAM GUIDE

Control Scope

Definition The process of monitoring the status of the project and product scope and
as per
managing changes to the scope baseline.

PMBOK
Guide

Inputs: Control Scope

Project management plan: explained earlier


Work performance information: explained earlier
Requirements documentation: explained earlier
Requirements traceability matrix: explained earlier
Organizational process assets: explained earlier

Tools & Techniques: Control Scope

Variance Analysis: Variance analysis is used to measure the variation of key parameters
from the original scope baseline.

Outputs: Control Scope

Work performance measurements: explained earlier


Organizational process assets updates: explained earlier
Change requests: explained earlier
Project management plan updates: explained earlier
Project document updates: explained earlier

59

PMP EXAM GUIDE

Chapter 4

Project Time
Management

Project Time
Management

Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Duration
Develop Schedule
Control Schedule

60

PMP EXAM GUIDE

Project Time
Management
Project Time Management

Learning Objectives
After the completion of this chapter, the learner will be able to:

List the various time management process


Describe the process of Define Activities
Describe the process of Sequence Activities
Describe the process of Estimate Activity Resources
Describe the process of Estimate Activity Durations
Describe the process of Develop Schedule using various tools
Describe the process of Control Schedule
Apply Critical Path Method to create schedule

61

PMP EXAM GUIDE

Project Time Management

Definition Project Time Management includes the processes required to manage timely
as per
completion of the project.

PMBOK
Guide

Project Time Management: Process Groups

Project Time
Management

Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Duration
Develop Schedule
Control Schedule

62

PMP EXAM GUIDE

Define Activities

Definition Define Activities is the process of identifying the specific actions to be


as per
performed to produce the project deliverables.
PMBOK
Guide

Inputs: Define Activities

Scope Baseline: The scope baseline consists of project deliverables, assumptions and
constraints which are important inputs to the activities.
Enterprise Environmental Factors: explained earlier
Organizational Process Assets: It includes various templates and the lessons learned
databases.

Tools & Techniques: Define Activities

Decomposition: Decomposition refers to subdividing the work-packages to activities.

Rolling Wave Planning:


o Rolling wave planning is the process of planning for a project in waves as the
project becomes clearer and unfolds. It is a multi-step, intermittent process,
like waves - because we cannot provide the details very far out in our
planning.
o Work packages that are further in the future are planned at only a high level.
o Work packages that are closer in time are planned in detail.
o We end up saving a lot of planning time by not planning things that have a
relatively high chance of never reaching execution.
o Helpful in large or long-term projects where there is some uncertainty about
continuing with the project beyond a certain point in time.

Templates: Templates refers to using the WBS of the similar projects that are being
used in the organization.

Expert Judgment: using the opinion of the project managers who have done similar
projects earlier.

63

PMP EXAM GUIDE

Outputs: Define Activities

Activity List: This is the list of activities that need to be done to complete the project.

Activity Attributes: Activity attributes comprise of the information required for each
activity. This includes the description of each activity, predecessor activities, successor
activities, and any constraints.

Milestone List: A milestone is an important event in a project. These are important from
the point of tracking the project.

64

PMP EXAM GUIDE

Sequence Activities

Definition Sequence Activities is the process of identifying and documenting relationships


as per
among the project activities.

PMBOK
Guide

Inputs: Sequence Activities

Activity List: explained earlier


Activity Attributes: explained earlier
Milestone List: explained earlier
Project Scope Statement: explained earlier
Organizational Process Assets: explained earlier

Tools & Techniques: Sequence Activities

Precedence Diagramming Method (PDM):


o Also called Activity on Node (AON)
o Uses boxes or rectangles as Nodes to represent Activities
o Connect boxes with Arrows which represent Dependencies
o Does not use dummy activities
o Includes all 4 relationships (FF, FS, SS, & SF)

These four relationships include:


1. Finish-to-Start. The initiation of the successor activity depends upon the completion
of the predecessor activity.
2. Finish-to-Finish. The completion of the successor activity depends upon the
completion of the predecessor activity.
3. Start-to-Start. The initiation of the successor activity depends upon the initiation of
the predecessor activity.
4. Start-to-Finish. The completion of the successor activity depends upon the initiation
of the predecessor activity.
In PDM, finish-to-start is the most commonly used type of precedence relationship. Startto-finish relationships are rarely used.

65

PMP EXAM GUIDE

Task Relationships

Dependency Determination:

1. Mandatory dependencies are those that are inherent in the nature of the work being
done. They often involve physical limitations. For example, Superstructure after the
foundation.
Mandatory dependencies are also called hard logic dependencies.
2. Discretionary dependencies are those that are defined by the project management
team.
Discretionary dependencies are usually defined based on knowledge of:
o Best practices within a particular application area.
o Some unusual aspect of the project where a specific sequence is desired, even
though there are other acceptable sequences.
o Discretionary dependencies may also be called preferred logic, preferential logic,
or soft logic.
3. External dependencies are those that involve a relationship between project
activities and non-project activities.
o For example, Regulatory dependencies

66

PMP EXAM GUIDE

Applying Leads and Lags: A lead allows acceleration of the successor activity
whereas, lag allows a delay in the successor activity.

Schedule Network Templates: Standard schedule network templates can be used for
expediting the creation of schedule network templates.

Outputs: Sequence Activities

Project Schedule Network Diagrams: Project schedule network diagrams are


schematic displays of the projects schedule activities and the logical relationships
among them, also referred to as dependencies.
o Can be produced manually or by using project management software.
o Can include full project details, or have one or more summary activities.
o Summary narrative accompanies the diagram and describes the basic approach
used to sequence the activities

Project Document Updates: Updates to any project documents.

67

PMP EXAM GUIDE

Estimate Activity Resources

Definition Estimate Activity Resources is the process of estimating the type and quantities
as per
of material, people, equipment or supplies required to perform each activity.

PMBOK
Guide

Inputs: Estimate Activity Resources

Activity List: explained earlier


Activity Attributes: explained earlier
Resource Calendars: It includes the availability of the resources during various time
periods of the project.

Enterprise Environmental Factors: explained earlier


Organizational Process Assets: explained earlier

Tools & Techniques: Estimate Activity Resources

Expert Judgment: explained earlier


Alternatives Analysis: Alternatives analysis refers to the evaluation of various
alternatives available of estimating activity resources. These can include skill and
experience of the resources and also the different tools available for project execution.

Published Estimating Data: This includes published data for estimation available for
different industries.

Bottom-up Estimating: Involves subdividing large subset into smaller activities and ity
estimating each activity. Aggregation of all the activity estimates leads to the final
estimate.

Project Management Software: Involves estimating using software tools such as


spreadsheets and other automated tools.

68

PMP EXAM GUIDE

Outputs: Estimate Activity Resources

Activity Resource Requirements: It is the type and number of resources required for
each activity.

Resource Breakdown Structure: It is the hierarchical structure of resource category and


resource type. For example for labour category, high-skilled and medium-skilled.

Project document Updates: Updates to various related project documents.

69

PMP EXAM GUIDE

Estimate Activity Duration

Definition Estimate Activity Durations is the process of approximating the number of


as per
work periods needed to complete individual activities with estimated resources.
PMBOK
Guide

Inputs: Estimate Activity Duration

Activity List: explained earlier


Activity Attributes: explained earlier
Activity Resource Requirements: explained earlier
Resource Calendars: explained earlier
Project Scope Statement: explained earlier
Enterprise Environmental Factors: explained earlier
Organizational Pocess Assets: explained earlier

Tools & Techniques: Estimate Activity Duration

Expert Judgment: explained earlier


Analogous Estimating: explained earlier

Parametric Estimating: Parametric modeling involves using project characteristics in a


mathematical model to calculate project costs. These models can be simple or complex
depending on the project.

Three - point Estimates: Also called Program Evaluation and Review Technique
(PERT). PERT uses three estimates to arrive at a range for activity time.
o Most Likely - The activity duration based on the realistic effort assessment.
o Optimistic - The activity duration based on the best-case scenario for the
activity.
o Pessimistic - The activity duration based on the worst-case scenario for the
activity.
Expected Time = (Optimistic + 4 * Most Likely + Pessimistic) / 6

70

PMP EXAM GUIDE

Reserve Analysis: Reserve analysis means keeping some reserve time or buffer for time
overruns. This duration is the percentage of overall duration and called contingency
reserve.

Outputs: Estimate Activity Duration

Activity Duration Estimates: are the quantitative assessments of the likely number of
work periods that will be required to complete an activity.

Project Document Updates: Updates to various related project documents.

71

PMP EXAM GUIDE

Develop Schedule

Definition Develop Schedule is the process of analyzing activity sequences, durations,


as per
resource requirements, and schedule constraints to create the project schedule
PMBOK
Guide

Inputs: Develop Schedule

Activity List: explained earlier


Activity Attributes: explained earlier
Project Schedule Network Diagrams: explained earlier
Activity Resource Requirements: explained earlier
Resource Calendars: explained earlier
Activity Duration Estimates: explained earlier
Project Scope Statement: explained earlier
Enterprise Environmental Factors: explained earlier
Organizational Process Assets : explained earlier

Tools & Techniques: Develop Schedule

Schedule Network Analysis: It is a analytical technique that uses critical path method,
critical chain method, what-if analysis, and resources leveling to calculate the early and
late start and finish dates for the uncompleted portions of project activities.

Critical Path Method: Critical Path is the path with the longest duration. A delay in any
one of the activities on the critical path activities leads to the delay in the entire project.
Float: The float for an activity is the amount that its duration can slip without causing the
project to be delayed. The float for any activity on the critical path is zero.
Calculate the early start, early finish, late start, and late finish using forward pass and
backward pass.
When two paths intersect, for the forward pass use the larger value, and for the
backward pass use the smaller value.

72

PMP EXAM GUIDE

Critical Chain Method: Critical chain is a schedule network analysis technique that
modifies the project schedule to account for limited resources.

Resource Leveling: Resource leveling is necessary when resources have been overallocated, has been assigned two activities at the same time, or a critical resource is
available only during certain times.
Resource leveling causes the critical path to change in most cases.

What-if Scenario Analysis: What-if analysis involves using various scenarios and
finding their impact on the schedule.

Applying Leads and Lags: explained earlier

Schedule Compression: Schedule compression involves shortening the project schedule


without affecting the project scope. The techniques are:
1. Crashing: This is done by adding more resources along the critical path. Crashing
does not always produce a viable alternative and often results in increased cost.
2. Fast-tracking: It involves doing activities in parallel that would normally be done in
sequence. Fast tracking often results in re-work and increase risk.

Scheduling Tool: Using scheduling tools and software programs to create network
diagrams.

Outputs: Develop Schedule

Project Schedule: It includes the project start and end dates and provides the prediction
of duration of the entire project. Project schedule can be represented in tabular form or
the following graphical formats:
o Milestone Chart
o Bar Chart
o Schedule Network Diagram

Schedule Baseline: It is an approved version of the schedule that is used to compare the
planned and actual progress.

73

PMP EXAM GUIDE

Schedule Data: Schedule data includes the supporting data apart from the milestones,
activities, assumptions and constraints.

Project Document Updates: Updates to the various project documents.

74

PMP EXAM GUIDE

Network Diagram Development

Critical Path Method

Forward Pass Early Start, Early Finish

75

PMP EXAM GUIDE

Backward Pass Late Start, Late Finish

Critical Path Longest Path, Zero Float

76

PMP EXAM GUIDE

Control Schedule

Definition Control Schedule is the process of monitoring the status of the project to
as per
update project progress and managing changes to the schedule baseline.
PMBOK
Guide

Inputs: Control Schedule

Project Management Plan: explained earlier


Project Schedule: explained earlier
Work Performance Information: This includes the project status and progress reports.
Organizational Process Assets: explained earlier

Tools & Techniques: Control Schedule

Performance Reviews: Performance reviews involve measuring the Earned Value


Calculations Schedule Variance (SV) and the Schedule Performance Index (SPI).
These values provide valuable information on the performance of the project.

Variance Analysis: This involves comparing the planned versus actual dates. This is
very important. In case of any problems, corrective action can be taken.

Project Management Software: explained earlier


Resource Leveling: explained earlier
What-if Scenario Analysis: explained earlier
Adjusting Leads and Lags: explained earlier
Schedule Compression: explained earlier
Scheduling Tools: explained earlier

Outputs: Control Schedule

Work Performance Measurements: explained earlier


Organizational Process Assets Updates: explained earlier
Change Requests: explained earlier
77

PMP EXAM GUIDE

Project Management Plan Updates: explained earlier


Project Document Updates: explained earlier

78

PMP EXAM GUIDE

Chapter 5

Project Cost
Management

Project Cost
Management
Estimate Costs
Determine Budget
Control Costs

79

PMP EXAM GUIDE

Project Cost
Management
Project Cost Management

Learning Objectives
After the completion of this chapter, the learner will be able to:

List the various cost management process


Describe the process of Estimate Costs
Describe the process of Determine Budget
Describe the process of Control Costs
Apply the concept of Earned Value Management in given scenarios

80

PMP EXAM GUIDE

Project Cost Management

Definition Project Cost Management includes the processes involved in estimating,


as per
budgeting, and controlling costs so that the project can be completed within the

PMBOK
approved budget.
Guide

Project Cost Management: Process Groups

Project Cost
Management
Estimate Costs
Determine Budget
Control Costs

Project Cost Management Plan

Subsidiary plan of the Project Management Plan


Produced during Develop Project Management Process
Defines how the project costs will be planned, managed and controlled
Documents how the cost management processes will be planned
Provides guidance on how the cost estimates should be developed
Determines how cost performance will be measured
Defines how cost variances will be determined and managed
Identifies how costs progress reporting will be done
Documents cost change control procedure

81

PMP EXAM GUIDE

Estimate Costs

Definition Estimate Costs is the process of developing an approximation of the monetary


as per
resources needed to complete project activities.
PMBOK
Guide

Inputs: Estimate Costs

Scope baseline: The scope statement lists the project objectives and deliverables along
with other information required for the project. The information is required in creating
the cost estimate.

Project schedule: The project schedule provides the information on the duration of the
project, which is another input for cost estimate.
Human resource plan: Information about the cost of various resources adds to the cost
estimate.

Risk register: Keeping track of the risks and hence the costs required to tackling them.

Enterprise environmental factors: Published commercial information, supplier


databases help in the costing for various material and resource costs.

Organizational process assets: Historical information about projects and company


costing policies are used in estimating the project costs.

Tools & Techniques: Estimate Costs

Expert judgment: Expert judgment involves using historical information as well as


talking to experts on the subject matter.

Analogous estimating: Also called Top-down Estimating. In bottom-up estimating,


first you break down the project into activities and then add them up. Top-down is the
opposite of this. You compare the project as a whole with a similar project and arrive at a
cost estimate. This is less accurate than bottom-up estimation.

82

PMP EXAM GUIDE

Parametric estimating: Parametric modeling involves using project characteristics in a


mathematical model to calculate project costs. These models can be simple or complex
depending on the project.

Bottom-up estimating: This involves adding up the cost of individual activities or work
packages and rolling up to get the total costs. This is a much more accurate estimating
method than analogous estimating.

Three - point estimates: Also called Program Evaluation and Review Technique
(PERT). PERT uses three estimates to arrive at a range for activity cost.
o Most Likely - The cost of activity based on the realistic effort assessment.
o Optimistic - The cost of activity based on the best-case scenario for the activity.
o Pessimistic - The cost of activity based on the worst-case scenario for the activity.
Expected Cost = (Optimistic + 4 * Most Likely + Pessimistic) / 6

Reserve Analysis: Reserve analysis means keeping some reserve cash for cost overruns.
These costs that are the percentage of overall costs are also called contingency costs.

Cost of Quality: Cost of quality refers to the costs associated with quality related
activities.

PM Estimating Software: Project Mangers also use specialized estimating software like
spreadsheets to calculate costs.

Vendor Bid Analysis: Vendor bid analysis is required when projects are awarded based
on bids under competitive processes. Arriving at a cost estimate for individual modules /
sub-projects becomes important if part of the project is being outsourced to a vendor.

Outputs: Estimate Costs

Activity Cost Estimates: This is the cost of all the activities in the project. It includes the
cost of labor as well as the material costs.

Basis Of Estimates: This lists the rates and reasoning for arriving at various cost
estimates for the resources.

83

PMP EXAM GUIDE

Project Document Updates: The project plan documents are updated with the cost
estimates.

Some Important Cost Definitions


1. Benefit Cost Ratio: This is the ratio of project benefit and the project cost.
2. Net Present Value (NPV): NPV takes the time value of money into account and is
used to decide if it is worth doing the project.
3. Opportunity Cost: When there is a decision to be made between two opportunities, the
opportunity cost is the value / money forgone for the not doing the project.
4. Internal Rate of Return: The amount of money the project will return to the company
funding it.
5. Depreciation: This is the rate at which the project loses value over time.
6. Lifecycle Costing: Life Cycle Costing takes into account not just the cost of
development of a project but also the cost of supporting during the lifecycle.

Rough Order of Magnitude (ROM) The cost estimation with an accuracy of + 50 %, -50 %.

Types of Cost

Direct Cost- any cost that is identified specifically with a particular final cost objective.
Indirect Cost: any cost not directly identified with a single, final cost objective (more
than one project).
Fixed Cost: A periodic charge that does not vary with business volume.
Variable Cost : Cost that fluctuates based on the business volume

84

PMP EXAM GUIDE

Determine Budget

Definition Determine Budget is the process of aggregating the estimated costs of


as per
individual activities or work packages to establish an authorized cost baseline.
PMBOK
Guide

Inputs: Determine Budget

Activity Cost Estimates: explained earlier


Basis Of Estimates: explained earlier
Scope Baseline: explained earlier
Project Schedule: explained earlier

Resource Calendars: Resource calendars provide information on the resources


availability. This is also used to arrive at project duration.

Contracts: If the project work is contracted, then contract is an important input to the
budget.

Organizational Process Assets: explained earlier

Tools & Techniques: Determine Budget

Cost aggregation: The individual activity estimates are rolled up into work package
levels which are further rolled till the project level. This is used to arrive at the project
budget.

Reserve analysis: Budget reserve analysis can help in arriving at both the management
and the contingency reserve.

Expert judgment: explained earlier

Historical relationships: Historical relationships (for example used in Parametric


Modeling and Analogous Estimates) are also used in budget estimates.

85

PMP EXAM GUIDE

Funding limit reconciliation: Since the funds are limited, the project manager needs to
complete the project within the budget. If this cannot be achieved, a scope change might
be required or funding limit increased.

Outputs: Determine Budget

Cost performance baseline: This is a snapshot of the planned budget. The cost
performance baseline is used to compare the actual performance against the baseline.

Project funding requirements: The total funding requirements are the baseline cost and
the management reserve. It is important for the project manager to understand the funding
requirements during different phases of the project and how to secure them as well.

Project document updates: The various documents such as the cost management plan
need to be updated.

86

PMP EXAM GUIDE

Control Costs

Definition Control Cost is the process of monitoring the status of the project to update
as per
project budget and managing changes to the cost baseline.
PMBOK
Guide

Inputs: Control Costs

Project management plan: explained earlier


Project funding requirements: explained earlier
Work performance information: explained earlier
Organizational process assets: explained earlier

Tools & Techniques: Control Costs

Earned value management: EVM is used to measure the performance of the project
against the plan. (explained under the section EVM)
Forecasting: Forecasting uses the EVM numbers to decide on preventive or corrective
actions.

To-complete performance index (TCPI): TCPI calculation is used to figure out how
well the project needs to perform in future to stay within the planned budget.

Performance reviews: These are project team meetings where the various variances are
analyzed. EVM is used to calculate the variances.

Variance analysis: The variance between the planned the actual project performance.

Project management software: There are software available that help the project
manager to keep track of their budgets.

Outputs: Control Costs

Work performance measurements: These include the CV, SV, SPI, and CPI.

Budget forecasts: Estimate at Completion (EAC) value is calculated for budget forecast.
87

PMP EXAM GUIDE

Organizational process assets updates: explained earlier


Change requests: explained earlier
Project management plan updates: explained earlier
Project document updates: explained earlier

Earned value Management (EVM)


EVM is used to measure the performance of the project against the plan.
Important Terms
Planned Value (PV) also called Budgeted Cost of Work Scheduled (BCWS)
Earned Value (EV) also called Budgeted Cost of Work Performed (BCWP)
Actual Cost (AC) also called Actual Cost of Work Performed (ACWP)

88

PMP EXAM GUIDE

EVM Formulas List

Name

Formula

What is it?

BAC

Budget at Completion

No formula its the


project budget

How much money youll


spend on the project

PV

Planned Value

PV = BAC* Planned %
Complete

What your schedule says


you should have spent

EV

Earned Value

EV = BAC * Actual %
Complete

How much of the projects


value youve really earned

AC

Actual Cost

What youve actually spent


on the project

How much youve actually


spent so far

SPI

Schedule Performance
Index

SPI = EV/PV

Whether youre behind or


ahead of schedule

SV

Schedule Variance

SV = EV-PV

How much ahead or behind


schedule you are

CPI

Cost Performance Index

CPI = EV/ AC

Whether youre within


your budget or not

CV

Cost Variance

CV = EV AC

How much above or below


your budget you are

EAC

Estimate at Completion

EAC = BAC/ CPI

ETC

Estimate to Complete

ETC = EAC AC

How much more money


you will spend on the
project

VAC

Variance at Completion

VAC = BAC EAC

Predicts what your


variance will be when the
project is done

89

PMP EXAM GUIDE

Interpreting EVM Numbers


Variance Analysis
1. Schedule Variance (SV): SV = EV PV

If SV is positive, the project is ahead of schedule, and


If SV is negative, the project is behind schedule

2. Cost Variance (CV): CV = EV AC

If CV is positive, the project is under budget, and


If CV is negative, the project is over budget

Indices
1. Schedule Performing Index (SPI): SPI = EV / PV

The project is ahead of schedule, if earned value is more than planned value.
That means, if SPI > 1, the project is ahead of schedule, and
If SPI < 1, the project is behind schedule

2. Cost Performing Index (CPI): CPI = EV / AC

The project is under budget, if earned value is more than actual cost.
That means, if CPI > 1, the project is under budget, and
If CPI < 1, the project is over budget

Forecasting
1. Estimate at Completion: EAC = AC + ETC
2. EAC forecast for ETC work performed at budgeted rate

EAC = AC + (BAC - EV)

3. EAC forecast for ETC work performed at present CPI

EAC = BAC / CPI

4. EAC forecast for ETC work considering both SPI and CPI factors

90

PMP EXAM GUIDE

EAC = AC + [(BAC - EV)/(CPI * SPI)]

To-complete Performance Index (TCPI)

Equation of TCPI based on the BAC: (BAC - EV) / (BAC - AC)


Equation of TCPI based on the EAC: (BAC - EV) / (EAC - AC)

91

PMP EXAM GUIDE

Chapter 6

Project Quality
Management

Project Quality
Management
Plan Quality
Perform Quality Assurance
Perform Quality Control

92

PMP EXAM GUIDE

Project Quality
Management
Project Quality Management

Learning Objectives
After the completion of this chapter, the learner will be
able to:

List the various quality management process


Describe the various quality tools
Describe the various quality principles
Describe the process of Plan Quality
Describe the process of Plan Quality Assurance
Describe the process of Plan Quality Control

93

PMP EXAM GUIDE

Project Quality Management

Definition
as per
PMBOK
Guide

Project Quality management includes the processes and activities of the


performing organization that determine quality policies, objectives, and
responsibilities so that the project will satisfy the needs for which it was
undertaken.

Project Quality Management: Process Groups

Project Quality
Management
Plan Quality
Perform Quality Assurance
Perform Quality Control

94

PMP EXAM GUIDE

Quality Management Principles

Customer Satisfaction
The product should not just satisfy the stated needs but also the some of the unstated needs of the
customer. Such requirements are common sense requirements like a product should not be made
from toxic stuff.

Fitness for Use


Fitness for use is about making sure that the product is fit for the customer needs. This concept
was propagated by Joseph Juran.

Conformance to requirements
This is one of the most important concepts for defining quality. This means that that the product
should meet the customer requirements. This also means that the product is as good as the stated
requirements. This highlights the importance of the requirements gathering.

Prevention over Inspection


Quality is concerned with Prevention over Inspection. Inspection is typically used to prove that
the system works (because youve put good quality practices in place), rather than a way to reject
the failures. A good point to remember is, Quality should be planned in not inspected in
because the cost of rework can be very high.

Quality and Grade


Quality is the sum of the characteristics of a product that allow it to meet or exceed the
expectations of the customer. Grade is a category or rank given to entities having the same
functional use but different technical characteristics. High-grade product will typically cost more
than the low-grade product.

95

PMP EXAM GUIDE

Plan Quality

Definition Plan Quality is the process of identifying quality requirements and/or


as per
standards for the project and product, and documenting how the project will
PMBOK demonstrate compliance.
Guide

Inputs: Plan Quality

Scope baseline: Scope baseline lists the requirements which include the product
specifications as well. This document also had the acceptance criteria that includes the
quality parameters listed.

Stakeholder register: Stakeholders register has the list of stakeholders who are
interested in the quality of the product.

Cost performance baseline: used to measure cost performance.

Schedule baseline: used to measure schedule performance.

Risk register: Risk register helps to identify risks that might affect quality.

Enterprise environmental factors: These include organization and government rules


and regulations related to quality.

Organizational process assets: This would include the company quality policy.

Tools and Techniques: Plan Quality

Cost-Benefit Analysis: A cost benefit analysis is required to check as to how much


quality activities will cost with respect to the gain for the company.

Cost of Quality (COQ): Cost of quality refers to the costs incurred during the life cycle
of the product. These include the cost of preventing nonconformance to requirements as
well as the cost of appraising the product or service for conformance to requirements.
o Conformance Costs: These include Prevention costs as well as Appraisal Costs
o Nonconformance Costs: These include Internal Failure Costs as well External
Failure Costs.

96

PMP EXAM GUIDE

Conformance Costs

Nonconformance Costs

Training
Processes
Testing and
Inspection
Audits

Rework
Fast tracking
Warranty
Product recalls

Control Charts: Are used to find out which process is contributing to quality problems.
This is generally used in manufacturing industry for repetitive processes.
There is an upper control limit and a lower control limit. There is also a mean. If the data
points are outside the limits, the process is out of control. This means the process needs
adjusting.

Benchmarking: In this, a reference point from another similar project from within or
outside company is used to compare the results. This is generally done for best practices
and improvement of products.

Design of experiments: is a statistical method to analyze the results of the experiments.


These results are used to find out how the deliverables can best meet the requirements.
For example, Project Managers might want to test what combination outsourcing work
and in-hour

Statistical sampling: This technique involves taking a representative sample for


inspection.

Flowcharting: It is a graphical representation of processes to find the areas where


defects can occur.

Proprietary quality management methodologies: these Include Six Sigma, Lean Six
Sigma. CMMI etc.
Additional quality planning tools: These include:
o Brainstorming
o Affinity Diagrams
o Nominal Group Techniques: brainstorming in small groups
o Matrix Diagrams: tables, spreadsheets that help analyze complex relationships
o Prioritization Matrices: diverse sets of issues are analyzed for priority.

97

PMP EXAM GUIDE

Outputs: Plan Quality

Quality management plan: The Quality management plan describes how the project
management team addresses quality.

Quality metrics: are the measurements that are taken throughout the project. These
measurements are used to measure the quality. For example, schedule variance or defect
density.

Quality checklists: Checklists are defect prevention tools that use a list of characteristics
/ specifications in a product. Mostly used during inspection.

Process improvement plan: is a plan for improving the process. The process is
monitored and checked for defects to create a improvement plan.

Project document updates: any updates are made to the subsidiary plans of the project
plan.

98

PMP EXAM GUIDE

Perform Quality Assurance

Definition Perform Quality Assurance is the process of auditing the quality requirements
as per
and the results from quality control measurements to ensure appropriate
PMBOK quality standards and operational definitions are used.
Guide

Inputs: Perform Quality Assurance

Project management plan: explained earlier


Quality metrics: explained earlier

Work performance information: This includes various performance reports such as


project progress reports, status reports, and variance reports. These reports serve as
important inputs for quality assurance.

Quality control measurements: These include the records of quality testing. These are
used for analysis.

Tools & Techniques: Perform Quality Assurance

Plan Quality and Perform Quality Control Tools & Techniques: The include the Plan
Quality and Perform Quality Control Tools & Techniques

Quality Audits: Quality Audits are conducted for the projects in a company to check
whether the projects are following the companies processes or not. These are structured
reviews with the objective to:
o Improve performances of the project
o Incorporate the best practices
o Identify nonconformance to processes and procedures
Quality audits can be done by internal auditors or third-party agencies.

Process Analysis: This is often utilized to understand and improve the processes.

Outputs: Perform Quality Assurance

Organizational Process Assets Updates


99

PMP EXAM GUIDE

Change Requests: Change requests can be used for corrective action / preventive action
/ defect repair.

Project Management Plan Updates: This is would include update to various subsidiary
plans that are part of the project management plan.

Project Document Updates; The documents such as quality audit reports, quality
processes and so on might require updates.

100

PMP EXAM GUIDE

Perform Quality Control

Definition Perform Quality Control is the process of monitoring and recording results of
as per
executing the quality activities to assess performance and recommend
PMBOK necessary changes.
Guide

Some Important Quality Terms

Prevention is keeping errors out of the process and Inspection is keeping errors out of
the hand of the customer.
Attribute Sampling is the result conforms, or it does not, whereas, Variable Sampling
is when the result is rated on a continuous scale that measures the degree of conformity.
Special causes are unusual events and Random causes are because of normal variation.
Tolerances means the result is acceptable if it falls within the range specified and,
Control Limits means that the process is in control if the result falls within the control
limits.

Inputs: Perform Quality Control

Project Management Plan: explained earlier


Quality Metrics: explained earlier
Quality Checklists: explained earlier
Work Performance Measurements: explained earlier
Approved Change Requests: Approved change requests can include changes such as
defect repair.
Deliverables: explained earlier
Organizational Process Assets: explained earlier

Tools & Techniques: Perform Quality Control


(The first seven are the seven basic tools of quality)

Cause and Effect Diagram: Also called Fishbone and Ishikawa diagrams. You list
all the possible causes of a defect.

101

PMP EXAM GUIDE

Cause A

:
explain
ed
earlier

Cause B

Cause C

explain
ed
earlier

:
explain
ed
earlier

111

Defect

111

111
Cause D

Cause E

explain
ed
earlier
111

Control Charts: explained earlier


Flowcharting : explained earlier

Histogram: A histogram is a vertical bar chart showing how often a particular variable
state occurred.

No. of defects in Software


20
15
10
5
0
Critical

High

Medium

Low

Pareto Chart: Also called the 80 / 20 Rule 80% of the defects are because of 20%
causes. Pareto charts help in figuring out the most important causes of the defects.

102

PMP EXAM GUIDE

Pareto diagram is a histogram, ordered by frequency of occurrence that shows how many
results were generated by type or category of identified cause.

Run Chart: These charts depict the trends in data as a line chart.

16
14
12
10
8
6
4
2
0
Critical

High

Medium

Low

Scatter Diagram: Scatter diagrams show the relationship two different variables. One
variable is plotted on the x-axis and the other is plotted on the y-axis. The pattern of their
intersecting points can graphically show relationship patterns.

3.5
3
2.5
2
1.5
1

0.5
0
0

103

PMP EXAM GUIDE

Statistical Sampling: explained earlier

Inspection: explained earlier

Approved Change Requests Review: All approved change requests should be reviewed
to verify that they were implemented as approved.

Outputs: Perform Quality Control

Quality Control Measurements: explained earlier


Validated Changes: explained earlier

Validated Deliverables: Every deliverable on the project needs to be inspected to make


sure it meets the quality standards.

Organizational Process Assets Updates: These include the lessons learned database as
well as the completed checklists.

Change Requests: explained earlier

Project Management Plan Updates: The various plans including the quality
management plan need to be updated.

Project Document Updates: The various documents need to be updated.

104

PMP EXAM GUIDE

Chapter 7

Project Human
Resource Management

Project Human Resource


Management

Develop HR Plan
Acquire Project Team
Develop Project Team
Manage Project Team

105

PMP EXAM GUIDE

Project Human
Resource Management
Project Human Resource Management

Learning Objectives
After the completion of this chapter, the learner will be able to:

List the various processes in Project Human Resource management


Describe the process of Develop Human Resource Plan
Describe the process of Acquire Project Team
Describe the process of Develop Project Team
Describe the process of Manage Project Team
Describe the various organizational development theories

106

PMP EXAM GUIDE

Project Human Resource Management

Definition Project Human Resource Management includes the processes that organize,
as per
manage, and lead the project team.

PMBOK
Guide

Project Human Resource Management: Process Groups

Project Human Resource


Management

Develop HR Plan
Acquire Project Team
Develop Project Team
Manage Project Team

107

PMP EXAM GUIDE

Develop HR Plan

Definition Develop Human Resource Plan is the process of identifying and documenting
as per
project roles, responsibilities, and required skills, reporting relationships, and
PMBOK creating a staffing management plan.
Guide

Inputs: Develop HR Plan

Activity Resource Requirements: The preliminary human resources requirements come


from the various activities in the WBS.

Enterprise environmental factors: These include the culture of the organization,


existing resource pools and the market conditions.

Organizational process assets: These include the hiring practices, organization


structure, and, and so on.

Tools & Techniques: Develop HR Plan

Organizational charts and Positional Descriptions: Various formats exist within


organizations. These include hierarchical, matrix-based or text-based formats. One can
use any of these or a combination. The most important thin is that the team members
should be very clear about their roles and responsibilities.
RACI chart is one such implementation of matrix-based formats.

108

PMP EXAM GUIDE

Person
Phase
Project Mgt
Analysis

Design
Develop
Testing

Tom

Peter

Sofia

Joseph

Kelly

R- Responsible, A- Accountable, C- Consult, I - Inform

Table: RACI Chart


Source: A Guide to the Project Management Body of Knowledge, Fourth Edition (PMBOK Guide) 2008 Project Management Institute, Inc.
All Rights Reserved.

Networking: Networking refers to the formal and informal interactions within the
company and outside to keep updated.

Organizational Theory: Various organization theories (to be discussed later in the


chapter)

Outputs: Develop HR Plan

Human Resource Plan: The human resource management plan includes the following:
o Staffing Management Plan: The staffing management plan is the most important
part of the HR plan. It includes the following:
1. Resource Histogram
2. Training Needs
3. Rewards and Recognition Program
4. Release Criteria
5. Acquisition Plan, and more

109

PMP EXAM GUIDE

o Roles and Responsibilities: Using RACI charts and other templates. (explained
above)
o Project Organization Charts: explained above

110

PMP EXAM GUIDE

Acquire Project Team

Definition Acquire Project Team is the process of confirming human resource availability
as per
and obtaining the team necessary to complete project assignments

PMBOK
Guide

Inputs: Acquire Project Team

Project management plan: explained earlier


Enterprise environmental factors: explained earlier
Organizational process assets: explained earlier

Tools & Techniques: Acquire Project Team

Pre - Assignment: In some cases, the project team members are assigned in the
beginning itself and they dont need to be negotiated. This is called pre-assignment.

Negotiation: Some resources are required from different functional teams and you need
to negotiate with the functional managers for assignment. Negotiation skills are required
for the same.

Acquisition: means getting teams from external vendors outside the company.
Virtual Teams: are teams that do not work at the same locations. The teams might be
located in different countries and time zones.

Outputs: Acquire Project Team

Project Staff Assignments: This is when you secure a team member and assign to a
specific role.

Resource Calendars: These provide information as to when the team member will be
working on the project.

111

PMP EXAM GUIDE

Project Management Plan Updates: The various documents related to HR plan need to
be updated based on the project information.

112

PMP EXAM GUIDE

Develop Project Team

Definition Develop Project Team is the process of improving the competencies, team
as per
interaction, and the overall team environment to enhance project performance
PMBOK
Guide

Inputs: Develop Project Team

Project Staff Assignments: explained earlier


Staffing Management Plan: explained earlier
Resource Calendars: explained earlier

Tools & Techniques: Develop Project Team

Interpersonal Skills: The soft-skills or the interpersonal skills are very important for
solving problems in the team.

Training: Training is very important for building the competencies in the domain /
technology required for the project success.

Team Building Activities: keeping the team together is the key to project success. Team
building can be formal training sessions and status meeting to informal off sites and lunch
together with the team.

Ground Rules: Ground rules are the expectations from team members regarding their
behavior within the team. These can be as simple as being on time in the meetings and
standards on quality and productivity.

Co-location: refers to team being located together in the same location to increase
communication and productivity.

Recognition and Rewards: Again, rewards and recognition is a important tool to


improve team morale. Rewards and recognition should be part of the complete project
cycle and not just on the completion of the project.

113

PMP EXAM GUIDE

Outputs: Develop Project Team

Team Performance Assessment: The project management teams do performance


assessments of the team members. These assessments can go as inputs for performance
appraisals and also for more trainings or coaching.

Enterprise Environmental Factors Updates: These would include updates to employee


training and skill records.

114

PMP EXAM GUIDE

Manage Project Team

Definition Manage Project Team is the process of tracking team member performance,
as per
providing feedback, resolving issues, and managing changed to optimize
PMBOK project performance
Guide

Inputs: Manage Project Team

Project staff assignments: explained earlier


Project management plan: explained earlier
Team performance assessment: explained earlier
Performance reports: explained earlier
Organizational process assets: explained earlier

Tools & Techniques: Manage Project Team

Observation and Conversation: part of the communication skills, you need to use
observation and conversation to effectively manage the team.

Project Performance Appraisals: Project appraisals are important for giving feedback
to the team members, clarifying the role conflicts if any, and also rewarding the good
work. This becomes more important in case of projects which are longer in duration. The
team should be aware of the issues so that they can work towards the common goal of
project success.

Conflict Management: Conflict management is an important skill required by a project


manager. There can be various reasons of conflicts within a project team. Few of the
important ones include.
o Schedule
o Cost
o Resources
o Personality conflicts
o Project priorities

There are six general techniques of resolving conflict:


o Collaborating: taking view of all; leads to consensus
o Problem-solving: taking an approach of examining alternatives; win-win solution
for all
115

PMP EXAM GUIDE

o
o
o
o

Compromising: trying to satisfy all by an agreement acceptable to all.


Forcing: making your own decisions by using power
Smoothing: temporary solution to please all; no lasting solution
Withdrawing: avoiding the situation; no solution

Issues Log: is a document list of issues with the resolution dates and responsibilities.

Interpersonal Skills: explained earlier

Outputs: Manage Project Team

Enterprise environmental factors: explained earlier


Organizational process assets update: explained earlier
Change requests: explained earlier
Project management plan updates: explained earlier

116

PMP EXAM GUIDE

Types of Power

Legitimate Power
o Also known as Formal Power or Positional Power
o Power comes from being formally in charge of the project and the people

Reward Power
o Your ability to give award a bonus or another kind of reward in order to motivate
team members.

Expert Power
o You are the subject matter expert
o The team respects you for your expertise in a specific area, and gives you
credibility because of that

Referent Power
o You are standing in for someone who has more position or power in the company
o Also comes from the charismatic personality of the project manager
o Can also come when you ally with a powerful person

Punishment Power
o You correct a team member for poor behavior. Always remember to do this oneon-one and in private.

117

PMP EXAM GUIDE

Organization Theories

Maslows Hierarchy of Needs: People are driven by a hierarchy of their needs. If your
lower level needs are satisfied, you tend to be motivated by higher level needs.
o
o
o
o
o

Self-actualization: Self-fulfillment, growth


Esteem: Respect, attention, appreciation
Social: Love, affection, approval
Safety: Security and freedom from harm
Physiological: Need for food, housing and clothing

Self
Actualization
Esteem

Social
Safety
Physiological

Herberzbergs Theory: also called Herzbergs Hygiene Theory because it deals with
Hygiene factors and motivating factors.
Hygiene factors
Salary
Compensation
Positive work conditions
Job security
Status
Company policy
Motivating Factors:
Responsibility
Work itself
Recognition
118

PMP EXAM GUIDE

Professional growth
Achievements
Self-actualization

Macgregors Theory X and Theory Y


Theory X - People are incapable and avoid responsibility. So, they need supervision to
do work
Theory Y - People are capable and motivated and ready to work without supervision.

Expectancy Theory

You need to give people an expectation of a reward in order to motivate them

The rewards or awards should be achievable, if they are impossible to achieve,


they will de-motivate them

People are motivated by achievements

People expect to be rewarded for achievements

McLellands Achievement Theory: People need achievement, power and affiliation to


be motivated.

Achievement is when someone performs well and is recognized for it

Power means he or she has a lot of control or influence in the company

Affiliation , a strong sense from being a part of a working team and having good
relationships with coworkers

Ouchis Theory

Formulated from Quality movement and Quality circles

Both Management and Workers need to be involved, and they should trust each
other

119

PMP EXAM GUIDE

Some important Human Resources Related Terms

Halo Effect

Extending the impression of a particular outstanding trait to influence the total


judgment of a person

For Example: Technical Architect to Management

120

PMP EXAM GUIDE

Chapter 8

Project Communication
Management

Project Communication
Management

Identify Stakeholders
Plan Communications
Distribute Information
Manage Stakeholder Expectations
Report Performance

121

PMP EXAM GUIDE

Project Communication
Management
Project Communication Management

Learning Objectives
After the completion of this chapter, the learner will be able
to:

List the processes for Project Communication Management


Describe the process Determine Stakeholders
Describe the process Plan communication
Describe the process Distribute Information
Describe the process Manage Stakeholder Expectation
Describe the process Report Performance

122

PMP EXAM GUIDE

Project Communication Management

Definition It includes the processes required to ensure timely and appropriate generation,
as per
collection, distribution, storage, retrieval, and ultimate disposition of project
PMBOK information.
Guide

Project Communication Management: Process Groups

Project Communication
Management

Identify Stakeholders
Plan Communications
Distribute Information
Manage Stakeholder Expectations
Report Performance

123

PMP EXAM GUIDE

Identify Stakeholders

Definition Identify Stakeholders is the process of identifying all people or organizations


as per
impacted by the project, and documenting relevant information regarding
PMBOK their interests, involvement, and impact on project success.
Guide
Stakeholders identification is crucial to the success of the project. The key stakeholders include:

Project manager
Sponsor
Customer
Project team members
Performing organization

Inputs: Identify Stakeholders

Project Charter: This document provides the information on sponsor of the project.

Procurement documents: The vendors and suppliers in the contract are the key
stakeholders.
Enterprise environmental factors
Organizational process assets

Tools & Techniques: Identify Stakeholders

Stakeholder analysis: This is a critical tool that involves interviewing the stakeholders.
One can divide the stakeholders into groups based on their involvement and need of
communication.

Expert Judgment: Involves talking to all the experts on the project to identify more
stakeholders

124

PMP EXAM GUIDE

Outputs: Identify Stakeholders

Stakeholder register: This document provides information on what value each


stakeholder gets out of the project.

Stakeholder management strategy: This involves creating a list of stakeholders and


their responsibilities, goals, expectations and concerns.
Stakeholder analysis involves the following steps:

List all the stakeholders


Classify all the listed stakeholders in the Power / Interest Grid with Stakeholders
(Figure on next page). The expectations of the stakeholders needs to be met as per
below:
o People with High Power and High Interest need to be closely managed as they
are the decision makers.
o People with High Power and Low Interest need to be satisfied.
o People with High Interest and Low Power should be kept informed.
o People with Low Interest and Low Power: they require the least amount of
attention.
High

Keep
Satisfied

Manage
Closely

Monitor

Keep
Informed

Power

Low
Low

Interest

High

Figure: Power / Interest Grid with Stakeholders


Source: A Guide to the Project Management Body of Knowledge, Fourth Edition (PMBOK Guide) 2008 Project Management Institute, Inc.
All Rights Reserved.

125

PMP EXAM GUIDE

Plan Communication

Definition Plan Communications is the process of determining the project stakeholder


as per
information needs and defining a communication approach.
PMBOK
Guide

Inputs: Plan Communication

Stakeholder register
Stakeholder management strategy
Enterprise environmental factors
Organizational process assets

Tools & Techniques: Plan Communication

Communications requirement analysis: This means analyzing the type of information


required by the stakeholders to make correct decisions. This means providing the right
amount of reports and not just sending too much information.

Communications technology: This has impact on how stakeholders are involved in the
project. This includes the factors such as:
1. Urgency of information: How frequently is the reporting required
2. Technology availability: Are the systems in place for the reporting requirements.
For example, are the web-based systems available if the reporting is time critical.
3. Project staffing: Are the team members trained on communication technology
available.
4. Project duration: Will the technology remain same throughout the project.

Communication models: In the basic communication model, the sender sends a message
to the receiver across a medium.

Sender
Receiver
Medium
Feedback
Noise
Encode

The person who needs to initiate the communication


The person who gets the message
The thing used to transmit the message
A response to a message
Something that interferes with the message
Modify a message so that it can be sent
126

PMP EXAM GUIDE

Decode

Modify a message that has been sent so that it can be understood

Communication methods: These include:


o Interactive communication
o Push
o Pull

Outputs: Plan Communication

Communication management plan: This is a subsidiary of the project plan and can be
highly detailed and complex. It can include details such as frequency of various reports,
the methods of communication, report formats, and more.

Project document updates: The various project documents requiring updates.

127

PMP EXAM GUIDE

Distribute Information

Definition Distribute Information is the process of making relevant information available


as per
to project stakeholders as planned.
PMBOK
Guide

Inputs: Distribute Information

Project management plan: It includes the communication plan

Performance reports: Includes the status reports.

Organizational process assets: It includes policies and procedures, any historical


information, and templates.

Tools & Techniques: Distribute Information

Communication methods: Communication methods can be formal or informal, verbal


or written.

Information distribution tools: Information can be distributed through electronic


communication (emails), web-based tools (Project Management Systems), or hard-copy
reports.

Outputs: Distribute Information


Organizational process assets updates: The updates include project reports and records,
stakeholder notifications, and lesson learned documentation.

128

PMP EXAM GUIDE

Additional Information

Nonverbal Communication
Means gestures, facial expressions, and physical appearance while
you are communicating your message

Para lingual Communication


Is the tone and pitch of your voice when you are telling people
whats going on with your project

Feedback
Is when you respond to communication

Active listening
When you give feedback to someone who is speaking

129

PMP EXAM GUIDE

Manage Stakeholder Expectations

Definition Manage stakeholder expectations is the process of communicating and working


as per
with stakeholders to meet their needs and addressing issues as they occur.
PMBOK
Guide

Inputs: Manage Stakeholder Expectations

Stakeholder register: This includes the list of stakeholders for the project.

Stakeholder management strategy: The document lists the goals and objectives of the
various stakeholders.

Project management plan: The Project management Plan contains the Communication
Plan. The communication plan lists the expectations of the stakeholders.

Issue log: The list of issues that happen during the project.

Change log: Is the list of changes that happen during the project. These changes and their
impact should be communicated to the right stakeholders.

Organizational process assets: These include various processes such as change control
procedures and historical information from earlier projects.

Tools & Techniques: Manage Stakeholder Expectations

Communication methods: Push, pull, and interactive. (explained earlier)

Interpersonal skills: Also referred as soft skills are used to keep the stakeholders
informed and working towards the common goal.

Management skills: Management is the act of directing and controlling a group of


people to achieve a common goal. The various management skills are: negotiating,
writing, speaking, and more.

130

PMP EXAM GUIDE

Outputs: Manage Stakeholder Expectations

Organizational process assets updated: Any lessons learned are updated.

Change requests: These are any changes to the project plan or other documents that
involve stakeholder communication.

Project management plan updates: Any approved changes need to be updated in the
communication plan, which is part of the project management plan.

Project document updates: Project documents requiring updates can include the
stakeholder register, stakeholder management strategy and issue log.

131

PMP EXAM GUIDE

Report Performance

Definition Report Performance is the process of collecting and distributing performance


as per
information, including status reports, progress measurements, and forecasts.

PMBOK
Guide

Inputs: Report Performance

Project management plan: Includes information on the project baselines.

Work performance information: Includes information such as deliverable dates and the
schedules.

Work performance measurement: Includes the metrics on planned versus actual of


the schedule and cost among others.

Budget forecasts: Is an important input for the project reports.

Organizational process assets: These can include various report templates.

Tools & Techniques: Report Performance

Variance analysis: Analyzing the performance data with respect to the baseline.

Forecasting methods: Use Earned Value and other forecasting methods to check
whether the project is within budget and schedule.

Communication methods: Decide on pull, push or interactive methods of


communication.

Reporting systems: A system to keep track of time and money spent on the work.

132

PMP EXAM GUIDE

Outputs: Report Performance

Performance reports: These reports provide the status and the progress of work
compared to the baseline. Common formats include bar charts and variance analysis. The
details can include issues and risks, work completed during the current period and also
work planned for the next period and more.

Organizational process assets updates: Lessons learned are updated so that they
become part of historical database.

Change request: Change requests are generated when you report performance. You need
to recommend Corrective and Preventive actions to the team.

Channels of Communication
Number of Communication Channels

Channels = n(n-1)/2 , where n is the number of people on the project

If there are five people on the project, then we have 10 communication channels.
This is calculates as follows: 5*(5-1) /2 = 10

Number of Communication Channels

133

PMP EXAM GUIDE

Chapter 9

Project Risk
Management

Project Risk
Management

Plan Risk Management


Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Responses
Monitor and Control Risks

134

PMP EXAM GUIDE

Project Risk
Management
Project Risk Management

Learning Objectives
After the completion of this chapter, the learner will be
able to:
List the various risk management processes
Describe the process of Identifying Risks
Describe the process of Perform Qualitative Risk
Analysis
Describe the process of Perform Quantitative Risk
Analysis
Describe the process of Plan Risk Responses
Describe the process of Monitor and Control Risks

135

PMP EXAM GUIDE

Project Risk Management

Definition Project Risk Management includes the processes of conducting risk


as per
management planning, identification, analysis, response planning, and

PMBOK
monitoring and control on a project.
Guide
A Risk is any uncertain event or condition that might affect your project. Risk might have a
positive as well as a negative outcome.
The objectives of Project Risk Management are to increase the probability and impact of positive
events, and decrease the probability and impact of negative events in the project.

Project Risk Management: Process Groups

Project Risk
Management

Plan Risk Management


Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Responses
Monitor and Control Risks

136

PMP EXAM GUIDE

Plan Risk Management

Definition Plan Risk Management is the process of defining how to conduct risk
as per
management activities for a project.
PMBOK
Guide

Inputs: Plan Risk Management

Project scope document: The project scope statement contains the details of project
deliverables and their acceptance criteria. This document is an important document for
identifying the risk.

Cost management plan: It includes the processes involved in estimating, budgeting, and
controlling costs so that the project can be completed within the approved budget.

Schedule management plan: This document defines how schedule contingencies will be
reported and assessed.

Communications management plan: This document defines the interactions that will
occur on the project and determines who will be available to share information on various
risks and responses at different times

Enterprise environmental factors: Factors include the company culture and existing
systems that are dealt with and used by the project manager to run the project. The other
factors that can influence this process are risk attitudes and tolerances that describe the
degree of risk that an organization will withstand.

Organizational process asset: that can influence this process include risk categories,
common definitions of concepts and terms, risk statement formats, standard templates,
roles and responsibilities, authority levels for decision making, lessons learned and
stakeholder register.

Tools & Techniques: Plan Risk Management

Planning Meetings and Analysis: This involves meetings with the project stakeholders
to identify the risks. These meetings should keep happening throughout the project.
137

PMP EXAM GUIDE

Outputs: Plan Risk Management

Risk Management Plan: describes the various risk management processes that will be
implemented, monitored and controlled throughout the project lifecycle. It can include
the following:
Methodology Defines the approaches, tools and the data sources that may be used
to perform risk management on the project
Roles and Responsibilities Defines the lead, support and risk management team
membership for each type of activity in the risk management plan, assigns people to
these roles and clarifies their responsibilities
Budgeting - Assigns resources and estimates costs needed for risk management for
inclusion in the project cost baseline
Timing Defines when and how often the risk management process will be
performed through out the project life cycle and establishes risk management
activities to be included in the project schedule.
Risk Categories provides a structure that ensures a comprehensive process of
systematically identifying risks to a consistent level of detail and contributes to the
effectiveness and quality of Identify risks process. An organization can use a
previously prepared categorization of typical risk. A risk breakdown structure (RBS)
is one approach to providing such a structure, but it can also be addressed by simply
listing the various aspects of the project. The risk categories may be revisited during
the Identify risks process. A good practice is to review the risk categories during the
Risk Management Planning process prior to their use in Identify risks process. Risk
categories based on prior projects may need to be tailored, adjusted or extended to
new situations before those categories can be used on the current project.
Risk Probability and Impact: This helps you figure out how big is the impact of
risk. The classification for risks from very low to very high can be used.
Revised stakeholder tolerances should be documented.
Reporting Formats: Describes the format and the content of the risk response plan.
Tracking: Documents if and how risk processes will be audited.

138

PMP EXAM GUIDE

Identify Risks

Definition Identify Risks is the process of determining which risks may affect the project
as per
and documenting their characteristics.

PMBOK
Guide

Inputs: Identify Risks

Risk management plan: explained earlier

Activity cost estimates: provide a quantitative assessment of likely cost to complete


schedule activities and ideally are expressed as a range, with the width indicating the
degree of risk
Activity duration estimates: are useful in identifying risks related to the time
allowances for activities or project as a whole, with the width of the ranges of these
estimates indicating the relative degree of risk.

Scope baseline: baseline is a component of scope statement which should be evaluated


as potential causes of project risk.

Stakeholder register: contains information on stakeholders, which will be useful in


interviewing the key stakeholders for their inputs to this process.

Cost management plan: contains information related to cost management which is an


important input to Identify risk process as the project specific approach may generate or
alleviate risk by its nature or structure.

Schedule management plan: contains information related to the schedule management


plan which is an important input to Identify risk process as the project specific approach
may generate or alleviate risk by its nature or structure

Quality management plan: contains information related to the quality management plan
which is an important input to Identify risk process as the project specific approach may
generate or alleviate risk by its nature or structure.

139

PMP EXAM GUIDE

Project documents: that may be useful while identifying risks are assumptions log, work
performance reports, network diagrams, baselines and other project information that may
be useful in identifying risks.

Enterprise environmental factors: explained earlier


Organizational process assets: explained earlier

Tools & Techniques: Identify Risks

Documentation Reviews: includes structured review of the project documentation,


which may include project files, project plans, assumptions, historical information, and
other information from the project level as well as individual activity level. It is also
essential to identify the quantity of plans and the consistency between the plans.

Information Gathering Techniques:


o Brainstorming session is conducted by a facilitator and a group of Subject
Matter Expert (SMEs), who perform brainstorming and arrive at a comprehensive
list of project risks. Identified risks are categorized by the type of risks. A risk
breakdown structure (RBS) can be used as a framework for risk identification.
o Delphi Technique is conducted by a facilitator and a group of experts, who are
given a questionnaire to fill. The results are collected and summarized and the
results are again circulated to get feedback from the experts.
o Interviewing is one of the main sources of risk gathering techniques where
experienced project managers, stakeholders and subject matter experts are
interviewed for risk identification.
o Root Cause identification involves identifying the causes of risks and improves
the understanding of the risk. It sharpens the definition of the risk and allows
grouping risks by causes. Effective risk response can be developed if the root
cause of the risk is addressed

Checklist Analysis: can be based on historical information gathered from earlier similar
projects. The lowest level of Risk Breakdown Structure (RBS) can also be used as a
checklist. Checklists can be updated at the end of the project completion to add new risks,
if any. Checklists are not a very much efficient method of identifying risks.

Assumption Analysis: reviews the validity of assumptions defined in the project to


ensure that risks are not missed due to inaccuracy or incompleteness of the assumption.
140

PMP EXAM GUIDE

Assumptions are tested for their validity. The consequences that might occur if the
assumptions were false are also analyzed. In such cases the assumptions are considered as
risks.

Diagramming Techniques: These may include:


o Cause and effect diagrams (also known as Ishikawa or fishbone diagrams):
useful for identifying the causes of risks.
o System or Process flowcharts: Show how various elements of a system
interrelate and the mechanism of causation.
o Influence diagrams, which are graphical representation of situations showing
causal influences

SWOT Analysis: This lets you analyze the Strengths, Weaknesses, Opportunities and
Threats to identify the probable risk events

Expert Judgment: explained earlier

Outputs: Identify Risks

Risk Register: The identified risks are mentioned in the document called a Risk Register,
which becomes a component of the project management plan. Following items can be
included in the Risk Register.
List of identified risks The list can state the EVENT that may occur, the IMPACT
and if CAUSE, EVENT may occur, then listing of EFFECT. Root causes of the risk
events can also be listed
List of potential responses If identified during the process of risk identification,
responses should be documented and it may be a useful input to the plan Risk
Responses process

Identified Risks

Potential Responses

Risk Register

141

Root causes

PMP EXAM GUIDE

Perform Qualitative Risk Analysis

Definition Perform Qualitative Risk Analysis is the process of prioritizing risks for
as per
further analysis or action by assessing and combining their probability of
PMBOK occurrence and impact.
Guide

Inputs: Perform Qualitative Risk Analysis

Risk Register: explained earlier


Risk Management Plan: explained earlier
Project Scope Statement: explained earlier
Organizational Process Assets: explained earlier

Tools & Techniques: Perform Qualitative Risk Analysis

Risk Probability and Impact Assessment: It examines the likelihood that each specific
risk will occur and evaluates the potential effect of any of the project objectives such as
time, cost, scope or quality. It also evaluates the positive opportunities and negative
threats. To assess the probability and impact of each risk, a meeting or interview with
subject matter experts either internal or external to the organization is conducted where
levels are assigned to each risk and also the potential effects of these risks is evaluated in
case the risk occurs

Probability and Impact Matrix: assigns ratings to each risk and classifies them for
either performs quantitative risk analysis or plan risk responses. Ratings are assigned to
risks based on the combination of probability and impact. The risk may guide in
providing risk responses as indicated below:

Risks that have a negative impact on the project objectives if they occur (threats) and
that are in the high risk (black zone of the matrix), may require priority action and
aggressive response strategies.
Threats in low risk (medium gray zone) may not require proactive management
action beyond being placed on a watch list or adding a contingency reserve.
For opportunities, those in the high-risk (black zone) that can be obtained most easily
and offer the greatest benefit should, therefore be targeted first Opportunities in the
low-risk (Medium gray zone) should be monitored
142

PMP EXAM GUIDE

Source: A Guide to the Project Management Body of Knowledge, Fourth Edition (PMBOK Guide) 2008 Project Management Institute, Inc.
All Rights Reserved.

Risk Data Quality Assessment: It involves determining the quality or usefulness of the
data collected to evaluate the risk as per the risk management plan. It involves examining
degree to which the risk is understood, and the accuracy, quality, reliability and integrity
of the data about risk. If data quality is unacceptable, it may be necessary to gather
higher-quality data.

Risk Categorization: Project risks can be categorized by the source of risk (e.g., using
the RBS), areas of the project affected (e.g. ,using the WBS) or other useful category
(e.g. , project phase, etc.) to determine areas of the project most exposed to the effects of
uncertainty. Grouping risks by common root causes can lead to developing effective risk
responses.

Risk Urgency Assessment: determines how soon the potential risks may occur, and it
also identifies near- term responses for those risks.

Expert Judgment: explained earlier

Outputs: Perform Qualitative Risk Analysis

Risk register updates: Risk register is initiated during identify risk process, and is
updated with information from Perform Qualitative Risk Analysis.
143

PMP EXAM GUIDE

Following are the updates from Perform Quantitative Risk Analysis:


o Relative ranking or priority list of the project risks. The probability and
impact matrix can be used to classify risks according to their individual
significance. The project manager can then use the prioritized list to focus
attention on those items of high significance to the project, where responses can
lead to better project outcomes. Risk may be listed by priority separately for cost,
time, scope and quality as organizations may value one objective over another. A
description of the basis for the assessed probability and impact should also be
included for the assessed risks.
o Risk grouped by categories can reveal common root cause of the risk or project
areas requiring particular attention.
o Cause of risk or project areas requiring particular attention. Discovering
concentrations of risk may improve the effectiveness of risk.
o List of risks requiring response in the near-term. Those risks that require an
urgent response and those that can be handled at a later date may be put into
different groups.
o List of risks for additional analysis and response. Some risks might warrant
more analysis , including perform qualitative risk analysis as well as response
action
o Watch-lists of low priority risks. Risks that are not assessed as important in the
Qualitative Risk Analysis process can be placed on a watch-list for continued
monitoring
o Trends in qualitative risk analysis results. As the analysis is repeated , a trend
for particular risks may become apparent and can make risk response or further
analysis more or less urgent/important

144

PMP EXAM GUIDE

Perform Quantitative Risk Analysis

Definition Perform Quantitative Risk Analysis is the process of numerically analyzing the
as per
effect of identified risks on overall project objectives.
PMBOK
Guide

Inputs: Perform Quantitative Risk Analysis

Risk Register: explained earlier


Risk Management Plan: explained earlier
Cost Management Plan: explained earlier
Schedule Management Plan: explained earlier
Organizational Process Assets: explained earlier

Tools & Techniques: Perform Quantitative Risk Analysis

Data gathering and representation techniques:


o Interviewing: Experienced project managers, stakeholders and subject matter experts
are interviewed to quantify the probability and impact of risks on project objective.
During interviewing different kind of probability distribution are used. In case a
triangular one is used then the three values for 3 point estimates are taken as input
from the SMEs which is used to quantify risk for each element.
o Probability distributions: Are commonly of two types Continuous distribution and
Discrete distributions

Quantitative risk analysis and modeling techniques: Commonly used techniques in


Quantitative Risk Analysis and Modeling techniques include:
o Sensitivity analysis. This aid in determining which risks have the most potential
impact on the project. It examines the extent to which the uncertainty of each project
element affects the objective being examined when all other uncertain elements are
held at their baseline values. Sensitivity analysis can be done by using the Tornado
diagram.
145

PMP EXAM GUIDE

o Expected monetary value (EMV) analysis is a statistical concept that calculates the
average outcome when the future includes scenarios that may or may not happen (i.e.
analysis under uncertainty). The EMV of opportunities will generally be expressed as
positive values while those of risks will be negative. EMV is calculated by
multiplying the value of each possible outcome by its probability of occurrence and
adding them together.

Source: A Guide to the Project Management Body of Knowledge, Fourth Edition (PMBOK Guide) 2008 Project Management
Institute, Inc. All Rights Reserved.

146

PMP EXAM GUIDE

o Modeling and Simulation: A project simulation uses a model that translates the
uncertainties or potential risks specified at a detailed level of the project into their
potential impact on project objectives.
Simulation techniques compute the project model using the inputs such as cost or
schedule to determine the probability distribution. Simulation techniques should be the
preferred one for predicting schedule or cost risks as compared to other techniques
Simulations are typically performed using the Monte Carlo technique. In a simulation, the
project model is computed many times (iterated) with the input values randomized from a
probability distribution function (e.g. cost of project elements or duration of schedule
activities) chosen for each iteration from the probability distribution of each variable. A
probability distribution is then calculated.

Expert Judgment: explained earlier

Outputs: Perform Quantitative Risk Analysis

Risk Register Updates: The register initiated in the Identify Risks process and is
updated in Perform Qualitative Risk Analysis process. The risk register is a component of
the project management plan. Updates include the following components:
o Probabilistic analysis of the project. Estimates are made of potential project
schedule and cost outcomes, listing the possible completion dates and costs with their
associated confidence levels. This output typically expressed as a cumulative
distribution is used with stakeholder risk tolerances to permit qualification of the cost
and time contingency reserves
o Probability of achieving cost and time objectives. With the project facing the risks,
the probability of achieving project objectives under the current plan can be estimated
using quantitative risk analysis results
o Prioritized list of quantified risks. This list of risks includes those that pose the
greatest threat or present the greatest opportunity to the project. These include the
risks that require the greatest cost contingency and those that are most likely to
influence the critical path.
o Trends in quantitative risk analysis results. As the analysis is repeated a trend
may become apparent that leads to conclusions affecting risk responses

147

PMP EXAM GUIDE

Plan Risk Responses

Definition Plan Risk Responses is the process of developing options & actions to enhance
as per
opportunities and to reduce threats to project objectives
PMBOK
Guide

Inputs: Plan Risk Responses

Risk Register: explained earlier


Risk Management Plan: explained earlier

Tools & Techniques: Plan Risk Responses

Strategies for Negative Risks or Threats:


o Avoid. Risk avoidance involves changing the project management plan to
eliminate the threat posed by an adverse risk, to isolate the project objectives from
the risks impact or to relax the objective that is in jeopardy, such as extending the
schedule or reducing scope. Some risks that arise early in the project can be
avoided by clarifying requirements, obtaining information, improving
communication or acquiring expertise.
o Transfer. Risk transference requires shifting the negative impact of a threat,
along with ownership of the response to a third party. Transferring the risk simply
gives another party responsibility for its management, it doesnt eliminate it. Risk
transference nearly always involves payment of a risk premium to the party taking
on the risk. Transference tools can be quite diverse and can include but are not
limited to the use of insurance, performance, bonds, warranties, guarantees etc.
o Mitigate. Risk Mitigation implies a reduction in the probability and impact of an
adverse risk event to an acceptable threshold. E.g. Conducting more tests, a more
stable supplier etc
o Accept. This includes passive or active acceptance. Passive acceptance requires
no action , the most common active acceptance strategy is to establish a
contingency reserves, including amounts of money or resources to handle known
or unknown threats/ opportunities

Strategies for Positive Risk or Opportunities:

148

PMP EXAM GUIDE

o Exploit .This strategy may be selected for risks with positive impacts where the
organization wishes to ensure that the opportunity is realized. This strategy seeks
to eliminate the uncertainty associated with a particular upside risk by making the
opportunity definitely happen. Directly exploiting responses include assigning
more talented resources to the project to reduce time to completion or to provide
better quality than originally planned.
o Share. Sharing a positive risk involves allocating ownership to a third party who
is best able to capture the opportunity for the benefit of the project. E.g. forming
risk-sharing partnerships, teams, special-purpose companies or joint ventures,
which can be established with the express purpose of managing opportunities.
o Enhance . This strategy modifies the size of an opportunity by increasing
probability and /or positive impacts and by identifying and maximizing key
drivers of these positive-impact risks. Seeking to facilitate or strengthen the cause
of the opportunity and proactively targeting and reinforcing its trigger conditions,
might increase the probability
o Accept. Accepting an opportunity is being willing to take advantage of it if it
comes along, but not actively pursuing it.

Contingent Response Strategy: Some responses are designed for use only if certain
events occur. For some risks, it is appropriate for the project team to make a response
plan that will only be executed under certain predefined conditions, if it is believed that
there will be sufficient warning to implement the plan. Events that trigger the
contingency response such as missing intermediate milestones or gaining higher priority
with a supplier, should be defined and tracked.

Expert Judgment: explained earlier

Outputs: Plan Risk Responses

Risk Register Updates: Components of the Risk register at this point include:
o Identified risks their descriptions, areas of the project (e.g. WBS element) affected,
their causes (e.g. RBS element) and how they may affect project objectives
o Risk owners and their assigned responsibilities
o Output from the Perform Qualitative and Perform Quantitative Risk Analysis
processes, including prioritized lists of project risks and probabilistic analysis of the
project
o Agreed upon response strategies
o Specific actions to implement the chosen response strategy
o Symptoms and warning signs of risks occurrence
o Budget and schedule activities required to implement the chosen responses
149

PMP EXAM GUIDE

o Contingency reserves of time and cost designed to provide for stakeholders risk
tolerance.
o Contingency plans and trigger that call for their execution
o Fallback plans for use as a reaction to a risk that has occurred and the primary
response proves to be inadequate
o Residual Risks that are expected to remain after planned response have been taken as
well as those that have been deliberately accepted
o Secondary risks that arise as a direct outcome of implementing a risk response
o Contingency reserves that are calculated based on the quantitative analysis of the
project and the organizations risk thresholds.

Risk Related Contract decision: Contractual agreements, such as agreements for


insurance, services and other items as appropriate can be prepared to specify each partys
responsibility for specific risks, should they occur.

Project Management Plan Updates: explained earlier

Project Document Update: explained earlier

150

PMP EXAM GUIDE

Monitor and Control Risks

Definition Monitor & Control Risks is the process of implementing risk response plans,
as per
tracking identified risks, monitoring residual risks, identifying new risks, and
PMBOK evaluating risk process effectiveness throughout the project.
Guide

Inputs: Monitor and Control Risks

Risk Register: explained earlier


Project Management Plan: explained earlier
Work Performance Information: explained earlier
Performance Reports: explained earlier

Tools & Techniques: Monitor and Control Risks

Risk reassessment indicates reassessing the identified risks and identification of new
risks as defined in the risk management plan. Project risk reassessment should be
performed regularly and it can be included as an agenda item at the project status
meetings.

Risks audits are scheduled audits that document the effectiveness of risk responses with
respect to their dealing with identified risks and their associated root causes. This aids in
determining the effectiveness of the risk management process.

Variance and trend analysis Performance data provides the data for variance and trend
analysis. Using this data and applying the earned value analysis and similar methods of
project variance and trend analysis; it is possible to monitor the overall project
performance.

Technical performance measurement. This involves identifying the variance in the


technical performance from the planned technical schedule. Any variance from the
defined milestone(s) can aid the project team to forecast the degree of success in
achieving the projects scope.

Reserve analysis. During the planning phase, contingency reserves are defines as a part
of risk response plan. During execution some of the reserves get exhausted. This tool
determines if the remaining reserves are sufficient to tackle the remaining risks.

Status meetings. Status review meetings help in monitoring the risks


151

PMP EXAM GUIDE

Outputs: Monitor and Control Risks

Risk Register [Updates]: An updates risk register contains:


o Outcomes of risk reassessments, risk audits, and periodic risk reviews. These
outcomes may include updates to probability, impact, priority, response plans,
ownership and other element of the risk register. Outcomes can also include closing
risks that are no longer applicable.
o The actual outcomes of the projects risk and of risk responses that can help project
manager plan for risk throughout the organization as well as on future projects. This
completes the record of risk management on the project and it is an input to the close
project process, and becomes a part of the project closure documents.

Organizational Process Assets Updates: explained earlier


Change Requests: explained earlier
Project Management Plan Updates: explained earlier
Project Document Updates: explained earlier

152

PMP EXAM GUIDE

Chapter 10

Project Procurement
Management

Project Procurement
Management

Plan Procurements
Conduct Procurement
Administer Procurements
Close Procurements

153

PMP EXAM GUIDE

Project Procurement
Management
Project Procurement Management

Learning Objectives
After the completion of this chapter, the learner will be
able to:

List the various procurement management processes


Describe the process of Plan Procurements
Decide between make versus buy situations
Describe the process of Conduct procurements
Describe the process of Administer Procurements
Describe the process of Close Procurements
List various types of contracts
Create various procurement related documents

154

PMP EXAM GUIDE

Project Procurement Management

Definition Project Procurement Management includes the processes necessary to


as per
purchase or acquire products, services, or results needed from outside the

PMBOK
project team
Guide

Project Procurement Management: Process Groups

Project Procurement
Management

Plan Procurements
Conduct Procurement
Administer Procurements
Close Procurements

155

PMP EXAM GUIDE

Plan Procurements

Definition Plan procurements is the process of documenting project purchasing decisions,


as per
specifying the approach and identifying potential sellers.
PMBOK
Guide

Inputs: Plan Procurements

Scope Baseline: explained earlier


Requirements Documentation: explained earlier

Teaming Agreements: Teaming agreements are legal contractual agreements between


two or more entities to form a partnership of joint venture, or some other arrangement as
defined by the parties.

Risk Register: explained earlier


Risk-related Contract Decisions: explained earlier
Activity Resource Requirements: explained earlier
Project Schedule: explained earlier
Activity Cost Estimates: explained earlier
Cost Performance Baseline: explained earlier
Enterprise Environmental Factors: explained earlier
Organizational Process Assets: explained earlier

Tools & Techniques: Plan Procurements

Make-or-Buy Analysis: Make-or-buy analysis is required when the organization


needs to decide whether to do the work in-house or through external agencies or
vendors. There are number of factors that need consideration. The factors include the
costs as well as the in-house capability.

When decisions are made to buy versus leasing options, both the direct as well as
indirection costs related to purchase are taken into consideration.

Expert Judgment: explained earlier


Contract Types: There are different types of contracts.
o Fixed Price Contracts

Fixed Price (FFP) means that you are going to pay one amount regardless
of how much it costs the contractor to do the work
156

PMP EXAM GUIDE

Fixed Price Plus Incentive Fees (FPIF) means that you are going to pay
a fixed price for the contract and give a bonus based on some performance
goal

Fixed Price with Economic Price Adjustment (FP EPA) This type
of contract is used in case of long term contracts, where pre-defined
adjustments are made every year based on some reliable financial index.

o Cost Reimbursable Contracts

Cost Plus Fixed Fee (CPFF) you pay the seller back for the costs
involved in doing the work, plus you agree to an amount that you will pay
on top of that.

Cost Plus Award Fee (CPAF) you agree to pay the legitimate costs but
the majority of the fee is based on performance of the seller based on the
subjective criteria set in the contract. This cannot be subject to appeals.

Cost plus incentive fee (CPIF) means you will reimburse costs on the
project and pay a pre-determined incentive fee based upon performance
goals set in the contract.

o Time and Materials

Time and Materials (T&M) means that you will pay a rate for each of
people working on your project plus their material costs. The Time part
means that the buyers pay a fixed rate for labor.

Outputs: Plan Procurements

Procurement Management Plan: It is a subsidiary element of the Project Management


Plan. The Project Procurement Management Plan comprises of the following key
information:
o
o
o
o
o
o

Standard procurement documents that need to be used


Make versus buy decisions
The contract types
Any constraints and assumptions for the contract
List of pre-qualified sellers to be used, and
More

A procurement plan may be formal or informal, highly detailed or broadly framed, based
on the needs of the project.

Procurement Statement of Work: This is the detail of the work to be contracted.

157

PMP EXAM GUIDE

Make-or-Buy Decisions: Decision of make-or-buy analysis

Procurement Documents: Procurement documents are used to solicit proposals from


prospective sellers. The terms bid, quotation, and tender are used when the source
selection criteria is based on price. Other common names for different procurement
documents include:
o Invitation for Bid (IFB) - A type of procurement document whereby the buyer
requests a potential seller to provide various pieces of information related to a product
or service or seller capability.
o Request for Proposal (RFP) - A type of procurement document used to request
proposals from prospective sellers of products or services. In some application areas,
it may have a narrower or more specific meaning.
o Request for Quotation (RFQ) - A type of procurement document used to request
price quotations from prospective sellers of common or standard products or services.
Sometimes used in place of request for proposal and in some application areas, it may
have a narrower or more specific meaning.
o Invitation for negotiation
o Invitation for sellers initial response
The procurement documents should always include the relevant procurement SOW,
description of the desired form of the response, and any contractual provisions.

Source Selection Criteria: Source selection criteria are used to select the seller.

Change Requests: explained earlier

158

PMP EXAM GUIDE

Conduct Procurements

Definition The process of obtaining seller responses, selecting a seller and awarding a
as per
contract.

PMBOK
Guide

Inputs: Conduct Procurements

Project Management Plan: explained earlier


Procurement Documents: explained earlier
Source Selection Criteria: explained earlier
Qualified Seller List: explained earlier
Seller Proposals: This includes the proposals by the sellers in response to the RFQs
and RFIs.
Project Documents: explained earlier
Make-or-Buy Decisions: explained earlier
Teaming Agreements: explained earlier
Organizational Process Assets : explained earlier

Tools & Techniques: Conduct Procurements

Bidder Conferences: These are also called vendor conferences or pre-bid conferences.
These involve the meetings with prospective sellers before submission of proposal. The
objective of the meeting is for clear understanding of the requirements and to avoid any
preferential treatment.

Proposal Evaluation Techniques: This would involve evaluating sellers responses to


check if the proposal is appropriate for the work.

Independent Estimates: In some cases, the buyer would create the estimates themselves
and also by the third-parties. These would be compared with the sellers responses for
final selection.

Expert Judgment: explained earlier

159

PMP EXAM GUIDE

Advertising: This involves placing an advertisement for getting in touch with sellers. In
government-funded projects, this is a requirement.

Internet Search: Using internet to search for approximate price range of the product is
also a practice. This is not useful in case of complex procurement.

Procurement Negotiations: This involves negotiating with the sellers on the various
terms of the contract. The project managers do not do the negotiations themselves. They
work closely with the legal department of the company for these negotiations.

Organizational Process Assets: explained earlier

Outputs: Conduct Procurements

Selected Sellers: The selected sellers are the list of sellers who have qualified based on
their proposals.

Procurement Contract Award: A procurement contract is awarded to each seller in the


form of a purchase order or some other document. This is a legal binding agreement and
has all the details for the contract.

Resource Calendars: This includes the contracted staff resource calendars.

Change Requests: explained earlier


Project Management Plan Updates: explained earlier
Project Documents Updates: : explained earlier

160

PMP EXAM GUIDE

Administer Procurements

Definition The process of managing procurement relationships, monitoring contact


as per
performance, and making changes and corrections as needed.
PMBOK
Guide

Inputs: Administer Procurements

Procurement Documents: explained earlier


Procurement Management Plan: explained earlier
Contract: explained earlier
Performance Reports: explained earlier
Approved Change Requests: explained earlier
Work Performance Information: explained earlier

Tools & Techniques: Administer Procurements

Contract Change Control System: This involves process to change the procurement
contract. It can involve the approvals, paperwork and the dispute resolution
mechanism required for the change control.

Procurement Performance Reviews: These include the structured review of seller


with respect to the terms in the contract. It can involve quality reviews of the product
as well audits of the sellers processes.

Inspection and Audits: Inspections and audits are conducted by the buyer to ensure
quality of the procurement as defined in the contract. Nonconformance can be raised
and the supplier can be penalized based on the terms in the contract.

Performance Reporting: This includes the performance reports by the seller which
are used by the buyer to monitor the project work.

Payment Systems: Payment system refers to how the payments are made to the
seller. The Accounts Payable system of the buyer makes the payments after the
payments are validated and authorized.

Claims Administration: Claims arise when there is some dispute between the buyer
and the seller. The contracts have terms and conditions on how the disputes should be
resolved and since the contract is a legal document, the claims need to be settled as
per the terms in the contract.
161

PMP EXAM GUIDE

Record Management System: There are a lot of documents or records generated by


a contract. These can include timesheets, invoices, receipts, memos, emails and so
on. There should be a system in place to store these.

Outputs: Administer Procurements

Procurement Documentation: Procurement documentation includes the documents that


are maintained in the record management system. It not just includes the documents
detailed above but also technical documentation, warranties etc.

Organizational Process Assets Updates: This includes updated to various documents


related to procurement documentation.

Change Requests: explained earlier

Project Management Plan Updates: Updates to the various subsidiary plans.

162

PMP EXAM GUIDE

Close Procurements

Definition The process of completing each project procurement.


as per
PMBOK
Guide

Inputs: Close Procurements

Project Management Plan: explained earlier.


Procurement Documentation: explained earlier.

Tools & Techniques: Close Procurements

Procurement Audits: This refers to the structured review of the complete process of
procurement. It is used to document the lessons learned database and also for the future
contacts.

Negotiated Settlements: All the terms of the contract need to be completed. This
includes any claims or disputes arising of the contract.

Record Management System: explained earlier

Outputs: Close Procurements

Closed Procurements: Close procurements involves buyer providing the seller with a
formal written notice that the contract has been completed.

Organizational Process Assets Updates: This includes updated to the lessons learned
database and procurement file.

163

PMP EXAM GUIDE

Negotiations Techniques

Deadline: imposing a deadline to reach an agreement

Stalling: one party may claim that an agreement cannot be finalized


because of his limited authority

Fair and Responsible: a negotiator may claim that the price for a
product is equitable because thats what another company is paying.

Delay: are useful when tempers are beginning to flare, to divert from a
subject, etc (Ex: arrival of refreshments, request for recess etc)

Withdrawal: one party may attack an issue, then retreat

Arbitration: a third party may be brought in when agreement cannot be


reached. (out of court settlement)

Fait Accompli: a party may claim that what is being asked for has
already been accomplished and cannot be changed

164

PMP EXAM GUIDE

Chapter 11

Professional Responsibility
And Ethics

Professional Responsibility
And Ethics
Project Management Institute Code of
Ethics and Professional Conduct
Ensure Integrity
Contribute to PM Knowledge Base
Respect Diversity

165

PMP EXAM GUIDE

Professional Responsibility
And Ethics
Professional Responsibility and Ethics
Learning Objectives
After the completion of this chapter, the learner will be
able to:
Understand Project Management Institute Code of Ethics
and Professional Conduct.
Understand Professional Responsibility and Ethics

166

PMP EXAM GUIDE

Introduction
Everyone who is a PMP must follow the Project Management Institute Code of Ethics and
Professional Conduct.

Professional responsibility and ethics involves:

Ensure Integrity
Contribute To PM Knowledgebase
Respect Diversity

Ensure Integrity

Follow the right processes and procedure.


You must identify stakeholders and understand their requirements.
Do not put personal gain over the needs of the project.
Tell truth in reports, conversations, and other communications.
Follow copyright and other applicable laws, report violations.
Do not divulge organizational data to unauthorized parties.
Prevent conflict of interest or appearance of conflict of interest.
Do not give or take bribe, or inappropriate gifts.
Do the right thing and follow right process.
Determine and understand needs of all stakeholders.
Look for competing or conflicting needs and interests and reconcile differences.
Determine options for fair resolution of conflicts among the stakeholders.

Contribute to PM Knowledgebase and Community

Perform research on the project done within your organization for the purpose of
discovering best practices.
Share lessons learned.
Write articles on Project Management.
Support education of the project team members and other stakeholders.
Coach and mentor team members.

167

PMP EXAM GUIDE

Gain knowledge of project management best practices and other technical and people
management skills.
Look for new information and practices that help the organization or its projects.
Continue to learn about the industry where you work.
Understand your weaknesses and strengths, plan your own professional development, and
continue to learn.

Respect Diversity

Understand cultural differences.


Understand communication preferences of the stakeholders, work ethics and practices of
the team members belonging to different regions, and nations.
Prevent cultural shock by training and advance research.
Provide training to the team members from different cultural backgrounds in order to
help them.
Understand each other and work like a cohesive group.
Follow the practices of other countries as long as they do not violate laws and human
rights.

168

You might also like