CODE P.T. 05
Ex. no.1 from 6
Page 1 from11
1. SCOPE :
This Procedure establishes the execution norms, technological phases
and the required conditions for execution of concrete works, accordingly to
the quality requirements foreseen in standards and norms.
2. APPLICABILITY
The provisions of this Procedure apply for concrete works at structures
from the construction objective, which influence the strength, stability and
service conditions.
3 . REFERENCES
Standard SR EN ISO 9001 / 1995,
Law no. 10 / 1995 concerning the quality in constructions,
Decision of the Government of Romania no.728 : 1994
Regulations concerning the certification of the quality for
construction products used in constructions
Norm NE 012 / 1999 Practice code for the execution of the
concrete, reinforced concrete and prestressed concrete works,
Norm C 56 / 1985 Verification of the quality and the reception of
the construction works and afferent installations,
Technical specifications, execution documents.
The standards collection reffering to the cement and concrete
testing.
4. PRECEDING CONDITIONS
Elaboration and knowledge of this procedure;
Ensurance of qualified and ackowledged personnel;
Ensuring the rythmically agregates, cement, additives supply
system;
Ensuring the preparation, haulage and pouring equipment for the
concrete;
The qualitative acceptance of excavation works, shutterings,
reinforcements, as required;
Attenting staff for the equipments, qualified, ackowledged and
verified to respect the actual technical norms, execution
technologies, labour safety and fire prevention.
Assurance of the necessary resources and facilities for the
management activities in Quality Assurance;
ELABORATED
VERIFIED
APPROVED
DATE
EDITION - REVISION
0
1 2 3 4
5
6 7 8 9
METHOD STATEMENT
FOR CONCRETE POURING
CODE P.T. 05
Ex. no.1 from 6
Page 2 from11
VERIFIED
APPROVED
DATE
EDITION - REVISION
0
1 2 3 4
5
6 7 8 9
METHOD STATEMENT
FOR CONCRETE POURING
CODE P.T. 05
Ex. no.1 from 6
Page 3 from11
VERIFIED
APPROVED
DATE
EDITION - REVISION
0
1 2 3 4
5
6 7 8 9
METHOD STATEMENT
FOR CONCRETE POURING
CODE P.T. 05
Ex. no.1 from 6
Page 4 from11
ELABORATED
VERIFIED
APPROVED
DATE
EDITION - REVISION
0
1 2 3 4
5
6 7 8 9
METHOD STATEMENT
FOR CONCRETE POURING
CODE P.T. 05
Ex. no.1 from 6
Page 5 from11
ELABORATED
VERIFIED
APPROVED
DATE
EDITION - REVISION
0
1 2 3 4
5
6 7 8 9
METHOD STATEMENT
FOR CONCRETE POURING
CODE P.T. 05
Ex. no.1 from 6
Page 6 from11
VERIFIED
APPROVED
DATE
EDITION - REVISION
0
1 2 3 4
5
6 7 8 9
METHOD STATEMENT
FOR CONCRETE POURING
CODE P.T. 05
Ex. no.1 from 6
Page 7 from11
8.4
JOINTS
The joints will be avoided as much as possible, the pouring will
be made without interruptions at each level or between two
expansion joints.
When the joints cannot be avoided, their position should be
established by the project or by execution procedure.
The number of joints must be minimal in order to avoid the
weakening (which may appear at inadequate treated joints) of the
structure to bending and shearing efforts . Also, the protection of
reinforcement to corrosion is diminished at joints, the permeability of
corrosive agents being increased.
The joints will be placed in areas where the sectional efforts
(derived from the design service loads) are minimal.
The following requirements are to be stipulated:
the surface of the joints shall be properly cleaned,
removing the concrete that wasnt well compacted, the
created cement film and impurities
the surfaces at the smooth joints that werent realised with
sheet shall be processed by chiselling (except the plates)
The surface of the fresh concrete shall be washed with
water. The previously poured concrete must respect the
saying the concrete should be saturated with water but
its surface should remain aired
8.5
THE STRIKING
The construction elements can be struck only when the
concrete reach a certain strength (maturation degree).
There will be taken into account the special conditions of
striking of concrete elements under the influence of frost
in the hardening phase (for unprotected concrete)
The striking may be performed only after the concrete
attains a sufficient strength to take over (partially or fully)
the design loads
The suggested magnitude of the concrete strength after
which the striking may begin is:
- The lateral parts of the shutterings can be removed after the
strength of the concrete has reached 2.5 N / mm 2, thus
avoiding deterioration of the surfaces and edges. The
shuttering for the interior surfaces at the plates and beams
ELABORATED
VERIFIED
APPROVED
DATE
EDITION - REVISION
0
1 2 3 4
5
6 7 8 9
METHOD STATEMENT
FOR CONCRETE POURING
CODE P.T. 05
Ex. no.1 from 6
Page 8 from11
SRI 32,5
SRI 42,5
STRIKING TERM
in days, at the temperature ( C )
+5
2
2
+ 10
1 1 /2
1
+ 15
1
1
Cement type
Surrounding temperature ( C )
Beams having span till 6.00 m
Beams having span > 6.00 m
ELABORATED
VERIFIED
SRI 32,5
+5
+10
+15
6
5
4
10
8
6
APPROVED
DATE
SRI 42,5
+5
+10
+15
5
5
3
6
5
4
EDITION - REVISION
0
1 2 3 4
5
6 7 8 9
CODE P.T. 05
Ex. no.1 from 6
METHOD STATEMENT
FOR CONCRETE POURING
Page 9 from11
In table 3 there are presented the minimum terms for safety props
removing\
TEHNOLOGICAL CONDITIONS
Cement type
Surrounding temperature ( C )
Beams having span till 6.00 m
Beams having span 6 m...12 m
Beams having span > 12.00 m
+5
18
24
36
SRI 32,5
+ 10 + 15
14
9
18
12
28
18
+5
10
14
28
SRI 42,5
+ 10 + 15
8
5
11
7
21
14
8.6
VERIFIED
APPROVED
DATE
EDITION - REVISION
0
1 2 3 4
5
6 7 8 9
METHOD STATEMENT
FOR CONCRETE POURING
CODE P.T. 05
Ex. no.1 from 6
Page 10 from11
VERIFIED
APPROVED
DATE
EDITION - REVISION
0
1 2 3 4
5
6 7 8 9
METHOD STATEMENT
FOR CONCRETE POURING
CODE P.T. 05
Ex. no.1 from 6
Page 11 from11
VERIFIED
APPROVED
DATE
EDITION - REVISION
0
1 2 3 4
5
6 7 8 9