You are on page 1of 6

SIMHAPURI ENERGY PRIVATE LIMITED ( SEPL) HYDERABAD

2 X 135 MW THERMAL POWER PLANT PHASE 1


ABB LIMITED

220V DC CHP BATTERY BANK AND CHARGER


SIZING CALCULATION

Doc Ref.No.
3VYN591603-03
Page 1 of 6

220V DC CHP BATTERY BANK AND CHARGER


SIZING CALCULATION

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.
ABB eBoP.

SIMHAPURI ENERGY PRIVATE LIMITED ( SEPL) HYDERABAD


2 X 135 MW THERMAL POWER PLANT PHASE 1
ABB LIMITED

Doc Ref.No.
3VYN591603-03

220V DC CHP BATTERY BANK AND CHARGER


SIZING CALCULATION

Page 2 of 6

REVISION STATUS SHEET


REV. NO.

DATE

DESCRIPTION

R0

02.09.2009

FOR APPROVAL

03.09.2009

FOR APPROVAL ( Revised as per Dasturco Comments dated 02.09.2009 vide


letter no. 372A)

16.10.2009

Revise as per DCPL Comments vide


dated15.10.2009

R1

R2

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.
ABB eBoP.

SIMHAPURI ENERGY PRIVATE LIMITED ( SEPL) HYDERABAD


2 X 135 MW THERMAL POWER PLANT PHASE 1
ABB LIMITED

1.

220V DC CHP BATTERY BANK AND CHARGER


SIZING CALCULATION

Doc Ref.No.
3VYN591603-03
Page 3 of 6

ENGG. REFERENCE DOCUMENTS

MPL ABB Technical Contract Document


Design Basis Report ABB Doc. 3VYN931101-A R1
IEEE Std. 485 & IS :1651
Key One Line diagram- ABB Doc. 3VYN931101-R2
GPSPL DC load list as confirmed by Dasturco vide letter no.110A dated 13.07.2009.
Dasturco drawing of Typical DC distribution -26298-00-00-ELE-0002- Rev.E

2. PROJECT DATA

Voltage rating of 220V System

Voltage variation
Fault Level
System
Ambient Temperature

3. SYSTEM DESCRIPTION

: 220V (Nominal)
: 242V ( Max. System Voltage)
: + 10 % To - 15 %
: 25 kA at DCDB Level
: Un-grounded
: 39.6 degree C Max.
: 20.0 degree C Min.

The Power plant comprises Two Generating units. For each unit, dedicated DC supply
system is envisaged.

One CHP battery bank shall feed the DC supply to following DC loads of 2 X 135MW.
A. CHP MV Switch gear
B. CHP LV System ( Service Transformer + LV Board)
C. DC Lighting

DC system for CHP comprises of One battery bank set and Two Float cum boost charger
connected to DC distribution Board. in line with Dasturco Specification.

The batteries & charger shall be so designed that the maximum fault level on DCDB is limited
to 25 KA.

The battery and battery charger combinations shall be such as to ensure continuity of D.C
supply at load terminals without even momentary interruption.

Under normal condition CHP MV Switchgear shall receive the supply from corresponding
Unit MV board and the TIE breaker in between both section shall be in OFF condition.

Complete blackout condition considered therefore all Motors Feeders on 6.6 KV MV switchgear shall be tripped by sensing under voltage condition on respective bus.

Similarly, all 415V Breaker controlled Motors shall Trip on receiving command from under
voltage relay of Bus PT panel of respective LV Switchgear and this will happen only when
associated up-stream breaker tripping is completed.

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.
ABB eBoP.

SIMHAPURI ENERGY PRIVATE LIMITED ( SEPL) HYDERABAD


2 X 135 MW THERMAL POWER PLANT PHASE 1
ABB LIMITED

Doc Ref.No.
3VYN591603-03

220V DC CHP BATTERY BANK AND CHARGER


SIZING CALCULATION

Page 4 of 6

4. BATTERY SELECTION / SIZING CRITERIA


The batteries are considered as lead acid type with tubular positive plates (HDP II) in line with
specification requirement.
Battery sizing and cell selection is based on IEEE: 485 & IS 1651. While estimating battery capacities the following is considered:
A. Design Margin of 20 %

R2

B. Ageing Factor of 1.25 %


C. End voltage of cell shall be not less than 1.85 Volt /cell during any time of the duty cycle.
D. Battery shall be rated for 10 hour discharge rate ( C10) as per manufacturer data. Battery load cycle shall be 1 hour.
E. Temp Correction Factor, Cft = 1+R[(27-t) / 100], where R=0.43 for 10 hrs discharge as
per table-2 of IS:1651, t = Electrolyte temp.=Min. site ambient temp (20 deg C) + incremental temp. of 10 deg C (as per Battery manufacturer recommendation ) = 30
deg C . Hence Cft= 0.98 . However, we have selected 1.0.
F. The enclosed battery sizing calculations is towards CHP DC system. The DC system
sizing calculation for Creek System Battery bank shall be submitted as a separate
document.
G. Continuous, momentary (0-1 min), continuous emergency (1-59 min) and Impulse
(59-60 min) loads is calculated and duly considered in battery duty cycle curve.
H. The duty cycle imposed on the battery shall include the following. All momentary loads
shall be treated as one minute load.

Continuous loads due to Energy Meters, Indication lights, Continuous energised


coils, Control Panels, Relays.

I.

Momentary loads due to switchgear operation, Valve operation.

Intermittent loads due to Motor starting requirements.

Tripping of Breaker, Starting of Lube oil pump are considered as 1st minute load of
duty cycle .

J. Control supply to Switchboards/ Panels are considered for the entire load of 1 hour.
Closing of Breaker is considered at last minute of duty cycle.

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.
ABB eBoP.

SIMHAPURI ENERGY PRIVATE LIMITED ( SEPL) HYDERABAD


2 X 135 MW THERMAL POWER PLANT PHASE 1
ABB LIMITED

220V DC CHP BATTERY BANK AND CHARGER


SIZING CALCULATION

Doc Ref.No.
3VYN591603-03
Page 5 of 6

5. CALCULATION
A. Battery Sizing Calculation
Input Parameters
1.

Type of Battery

2.

Mfg. of Battery

= Lead Acid
Any
= Approved
make

3.

Nominal System Voltage

= 220

4.

Maximum System Voltage

= +10

5.

Minimum System Voltage

= -15

6.

End Cell Voltage (ECV)

= 1.85

7.

Float Voltage

= 2.15

8.

Electrolyte Temperature

= 30

9.

Temperature Correction Factor

= 1.0

10.

Ageing Factor

= 1.25

11.

Design Factor

= 1.1

12.

No. of Duty Cycle

= 3

Nos

DETERMINATION OF NUMBER OF CELLS


Nominal system voltage
Float voltage

= 220 V
= 2.15 V

Maximum allowable voltage 220 + 10 %

= 242 V

Minimum allowable system voltage 220 - 15 %

= 187 V

Selected No. of Cells

= 110

Nos

Calculated Minimum System Voltages = (ECV x No. of Selected Cells)=1.85*110 =203.5V


Calculated minimum system voltage is greater than the allowable minimum system voltage.
Hence, the determination of no. of cells as 110 Nos. is justified.
Amperehour calculation of Battery is calculated as per guide line of IEEE-485 / IS-1651 and is
enclosed as Annexure-1.

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.
ABB eBoP.

SIMHAPURI ENERGY PRIVATE LIMITED ( SEPL) HYDERABAD


2 X 135 MW THERMAL POWER PLANT PHASE 1
ABB LIMITED

Doc Ref.No.
3VYN591603-03
Page 6 of 6

220V DC CHP BATTERY BANK AND CHARGER


SIZING CALCULATION

B. CHARGER SELECTION / SIZING CALCULATION


Annexure - 2
CONCLUSION

Type of battery

Lead Acid type with Tubular


Positive Plate ( HDP-II)

Application

CHP Battery bank

10 Hour rating at 27 deg. Cent to

120AH

1.85Volt / cell

R2

Quantity of Battery Bank

One

No. of Cell

110

Rating of Charger

40A

Configuration

FCBC

Quantity

2 X 100 % ( Total =2 Nos)

Enclosures :a. Annexure 1


b. Annexure 2
c. Annexure 3 (K Factor graph)
d. Annexure 4 (Load Cycle Graph )

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.
ABB eBoP.

You might also like