Professional Documents
Culture Documents
GC3101
June 2007
Page 1 of 10
TABLE OF CONTENTS
1.0
GENERAL ............................................................................................................ 3
2.0
3.0
4.0
Approved Manufacturers............................................................................ 3
4.2
5.0
6.0
Trans Mountain.......................................................................................... 4
Express...................................................................................................... 5
Platte ......................................................................................................... 6
5.2
5.3
5.4
5.5
5.6
Masking ..................................................................................................... 7
5.7
5.8
5.9
5.10
Re-Blasting ................................................................................................ 8
5.11
5.12
APPLICATION ...................................................................................................... 8
6.1
Manufacturers Requirements..................................................................... 8
6.2
6.3
6.4
Overspray .................................................................................................. 8
6.5
6.6
6.7
Revision 3
June 2007
Page 2 of 10
8.0
INSPECTION........................................................................................................ 9
7.1
7.2
7.3
GC3101
June 2007
Page 3 of 10
1.0 GENERAL
This standard prescribes the surface preparation and application of coating
materials to aboveground piping, fittings, valves, equipment, and structural steel.
It is applicable to coatings applied in both shop and field environments.
Aluminum, stainless steel, and galvanized fittings are to be left unpainted unless
specified by Kinder Morgan Canada Inc.
2.0
REFERENCE PUBLICATIONS
The following codes and standards (latest issue) shall form part of this
specification:
SSPC-PA-1
SSPC-SP-1
Solvent Cleaning
SSPC-SP-6
SSPC-SP-7
SSPC-SP-10
SSPC-SP-11
3.0
4.0
COATING SYSTEM
4.1
Approved Manufacturers
The specified coating systems are listed in Table 4.1.A. Deviations are
not allowed without prior approval in writing from the Kinder Morgan
Canada Inc. Designated Representative. The Contractor shall specify, at
the tender stage, all precleaning, blasting, and coating material to be
used. Film thickness for each material listed shall be in accordance with
the manufacturers specifications. The total paint system (both primer and
GC3101
June 2007
Page 4 of 10
Coat
Material
Primer Options
TopcoatOptions
Primer Options
Topcoat Options
Primer
8315 Series
Topcoat
834 Series
Primer
EP 421 HIBLD
Topcoat
EX2C
Primer
Topcoat
Primer
Carboguard 893
Topcoat
Carbothane 134HG
Primer
B67 Series
Topcoat
B65-300 Series
Primer
Valchem 13F62/13R62
Topcoat
Vthane Series 54
ICI/Devoe
International
Cloverdale
Endura
Sigma
Carboline
Sherwinn Williams
Valspar
4.2
Topcoat Colours
4.2.1 Trans Mountain
The topcoat colours designated by RAL numbers for Trans
Mountain Pipeline including the Puget Sound and the Jet Fuel
systems shall be as specified in Table 4.2.A.
Revision 3
June 2007
Page 5 of 10
Surfaces
Colour
RAL Number
White
RAL9003
Dark Green
RAL6005
Dark Green
RAL6005
Orange
RAL2008
Light Green
RAL6018
Coupling Guards
Orange
RAL2008
Yellow
RAL1021
Structural Steel
Black
RAL9005
Valve Body
(1)
(1)
Valve Handwheel
(1) For new facilities valves, actuators, and handwheels shall be white (RAL
9003).
4.2.2 Express
The topcoat color for all piping, components, and structural steel
covered by this standard for Express U.S. shall be tan designated
by U.S. Federal Standard (FS) 595B 20318. The topcoat colours
for Express Canada designated by RAL numbers shall be as
specified in Table 4.2.B.
TABLE 4.2.B EXPRESS CANADA TOPCOAT COLOURS
Surfaces
RAL Number
White
RAL9003
White
RAL9003
White
RAL9003
Valve Handwheel
Black
RAL9005
White
RAL9003
Black
RAL9005
Yellow
RAL1021
Structural Steel
Black
RAL9005
Revision 3
June 2007
Page 6 of 10
4.2.3 Platte
The topcoat colors designated by U.S. Federal Standard numbers
for Platte Pipeline shall be as specified in Table 4.2.C.
TABLE 4.2.C PLATTE TOPCOAT COLORS
Surfaces
Color
FS Number
Gray
595B 16440
Blue
595B 25184
Valve Body
Gray
595B 16440
Gray
595B 16440
Valve Handwheel
Blue
595B 25184
Gray
595B 16440
Gray
595B 16440
Yellow
595B 33655
Structural Steel
Gray
595B 16440
5.0
SURFACE PREPARATION
5.1
Surface Irregularities
Before commencing blast cleaning all weld spatter, flux, slag, laminations,
burred edges, and sharp projections shall be ground off. Rough hand
welds shall be ground to minimum 3 mm () radius or to the acceptance
of Kinder Morgan Canada Inc.
5.2
Pre-Blast Cleaning
All oil, grease, and other deleterious matter shall be removed by chemical
cleaning per SSPC-SP-1 prior to any preparation and/or coating
application. Bio-degradable water based degreasers shall be used for
pre-blast cleaning at all Kinder Morgan Canada facilities.
5.3
Blast Cleaning
All structural steel and hand rails to be coated shall receive a Commercial
Blast Cleaning in accordance with SSPC-SP-6. All other surfaces to be
coated shall receive a Near White Metal Blast Cleaning in accordance with
SSPC-SP-10.
5.4
Revision 3
June 2007
Page 7 of 10
5.6
Masking
Care shall be exercised in blast cleaning to avoid damage to equipment
(ie. flange faces, nameplates, gauges, instruments, electrical controls, and
coated conduit) not intended for coating application. All masking shall be
removed at the completion of blasting and coating activities.
5.7
Surface Contamination
Care shall be taken to ensure freshly blasted surfaces are not
contaminated. At the discretion of Kinder Morgan Canada, Surface
Contamination Analysis Tests (SCAT) for the presence of soluble
chlorides may be required after abrasive blasting. Where the measured
chloride level is greater than 10 ppm, cleaning measures such as washing
and rinsing to reduce chloride contamination to acceptable levels shall be
performed.
5.8
5.9
Coating Contamination
Special care shall be taken to ensure that blasting abrasive or foreign
matter is not allowed to contaminate freshly applied coating. All foreign
matter shall be completely removed from an existing coat before
application of a new coat. Any coating so contaminated shall be removed
and replaced.
GC3101
June 2007
Page 8 of 10
6.0
5.10
Re-Blasting
Where rusting or blooming occurs, the metal surfaces shall be re-blasted
to remove all rust and blooming. Surfaces shall be blown free of blasting
abrasives before the surface is primed.
5.11
5.12
APPLICATION
6.1
Manufacturers Requirements
The manufacturers written requirements for coating, mixing, handling,
application, curing, and overcoating shall be mandatory.
6.2
6.3
6.4
Overspray
For surface applications at Kinder Morgan Canada Inc. facilites, any
surface inadvertently contaminated with overspray or otherwise displaced
coating shall be cleaned or recoated at no extra cost to Kinder Morgan
Canada Inc.
6.5
Handling or Shipping
The coating Manufacturers hard dry cure requirements must be met
before any handling or shipping can be performed.
GC3101
June 2007
Page 9 of 10
7.0
6.6
6.7
INSPECTION
7.1
Daily Reporting
For the duration of the work, daily coating/inspection reports included with
this specification shall be completed. Alternatively, a similar form preapproved by Kinder Morgan Canada Inc. may be used. Ambient
conditions shall be recorded a minimum of four times per day or as
requested by Kinder Morgan Canada.
7.2
Inspection Equipment
The contractor shall have the following inspection equipment calibrated
and available for use:
7.3
Pre-job meeting;
After blast cleaning and prior to priming;
After priming and prior to application of topcoat;
Final inspection including submission and acceptance of all quality
control documentation.
Revision 3
June 2007
Page 10 of 10
8.0
Date
SURFACE PREPARATION
Spec. Standard
Condition
Air Temperature
Wet Bulb Temp.
Relative Humidity
Steel Temperature
Dew Point
Wind Direction
Wind Speed
Time
Time
Time
Time
Time
C/F
C/F
%
C/F
C/F
kph/
mph
ANCHOR PROFILE MEASUREMENTS
Min.
Max.
Mean
Comments:
COATINGS
Coat
Paint
Manufacturer
Name &
Description
Description
Batch
Application
Number
Method
Color
MDFT
Before
This
Coat
W.F.T.
Min
Max
1.
2.
Coat
M.D.F.T.
Min
Max
Mixing
Thinning
1.
2.
Provide Comments on Coating Appearance/Acceptance:
Storage
Holidays
Defects/Comments:
Revision 0
Page 1 of 11
TABLE OF CONTENTS
1.0
2.0
3.0
4.0
SCOPE ................................................................................................................. 3
REFERENCE PUBLICATIONS ............................................................................ 3
DEFINITIONS ....................................................................................................... 3
3.1
Contractor .................................................................................................. 3
3.2
Holiday ....................................................................................................... 3
3.3
Manufacturer .............................................................................................. 3
3.4
mdft ............................................................................................................ 3
3.5
SSPC ......................................................................................................... 3
GENERAL ............................................................................................................ 4
4.1
Supervision ................................................................................................ 4
4.2
Materials .................................................................................................... 4
4.2.1
4.2.2
4.3
5.0
6.0
7.0
General ...................................................................................................... 4
Storage ...................................................................................................... 4
General ...................................................................................................... 4
Abrasive Blast Materials ............................................................................ 4
Coating Containers and Waste Materials .................................................. 5
Final Clean-Up........................................................................................... 5
4.4
Labour........................................................................................................ 5
4.5
Limiting Atmospheric Conditions ................................................................ 5
COATING SYSTEM ............................................................................................. 6
5.1
Approved Manufacturers............................................................................ 6
SURFACE PREPARATION .................................................................................. 6
6.1
Surface Irregularities .................................................................................. 6
6.2
Pre-Blast Cleaning ..................................................................................... 6
6.3
Blast Cleaning ............................................................................................ 6
6.4
Blasting Equipment Grounding .................................................................. 6
6.5
Blast Cleaning Abrasive ............................................................................. 7
6.6
Masking ..................................................................................................... 7
6.7
Surface Contamination .............................................................................. 7
6.8
Incomplete Blasting Prior to Priming .......................................................... 7
6.9
Coating Contamination .............................................................................. 7
6.10 Re-Blasting ................................................................................................ 7
6.11 Dead Man Control ...................................................................................... 7
6.12 Alternate Cleaning Methods....................................................................... 7
APPLICATION ...................................................................................................... 8
Revision 0
Page 2 of 11
8.0
9.0
7.1
Rust Blooming ........................................................................................... 8
7.2
Spray Equipment ....................................................................................... 8
7.3
Film Continuity ........................................................................................... 8
7.4
Compressed Air Quality ............................................................................. 8
7.5
Air Pressure ............................................................................................... 8
7.6
Film Thickness ........................................................................................... 8
7.7
Coating Contamination .............................................................................. 8
7.8
Overspray .................................................................................................. 9
INSPECTION........................................................................................................ 9
8.1
Contractor's On-Site Supervisor, Quality Control ....................................... 9
8.2
Contractor's Inspection Equipment ............................................................ 9
8.3
Inspection Hold Points ............................................................................... 9
SAFETY DATA SHEETS ...................................................................................... 9
Revision 0
Page 3 of 11
1.0 SCOPE
This standard prescribes the surface preparation and application of coating
materials to external surfaces on buried piping and fittings. Aluminum, stainless
steel and galvanized fittings are to be left uncoated unless specified.
SSPC-SP-1
Solvent Cleaning
SSPC-SP-7
SSPC-SP-10
3.0 DEFINITIONS
3.1
Contractor
Contractor shall mean the coating applicator.
3.2
Holiday
A discontinuity that exhibits electrical conductivity when exposed to a specific
voltage.
3.3
Manufacturer
Manufacturer shall mean the coating manufacturer or supplier.
3.4
mdft
Units of measure for coating applications - mils dry film thickness (0.001
inches).
3.5
SSPC
SSPC stands for the Steel Structures Painting Council.
Revision 0
Page 4 of 11
4.0 GENERAL
4.1
Supervision
The Contractor shall have a full-time supervisor on site at all times during the
course of the work. The on-site supervisor is expected to be completely
familiar with conditions and constraints existing in the work area and shall
insure that all of the Contractor's personnel are aware of potential hazards.
4.2
Materials
4.2.1
General
The Contractor shall supply all thinners, cleaning and coating
materials in sufficient quantities to complete the Work.
The
Contractor shall be responsible for receiving and unloading these
materials. The Contractor shall keep a strict account of all materials
used during the course of the Work.
4.2.2
Storage
The Contractor shall insure that all containers are suitablely stored to
prevent damage to or rusting of the containers, and to preserve all
identifying labels and markings. Paint, thinners, and abrasive
materials in damaged or leaking containers shall be rejected and
shall be the responsibility of the Contractor.
4.3
General
The Contractor shall store, transport, and dispose of all waste
materials in accordance with all applicable Federal and Provincial
regulations.
The Contractor shall disclose, in writing, the proposed methods of
waste storage, transport, and disposal to Kinder Morgan Canada Inc.
not less than one week prior to the completion of the coating work.
The Contractor shall provide written confirmation that the methods
used were in accordance with the requirements listed above
(including copies of manifests and disposal facility receipts), to
Kinder Morgan Canada Inc. not more than one week after the waste
transport and disposal.
4.3.2
Revision 0
Page 5 of 11
4.3.4
Final Clean-Up
Upon completion of the coating work, the Contractor shall ensure that
the work area is in it's original clean state and that all equipment and
materials have been removed from Kinder Morgan Canada Inc.
property.
4.4
Labour
All surface preparation and application shall be carried out by tradesmen
skilled in the application of corrosion-resistant protective coatings.
4.5
b)
c)
d)
Revision 0
Page 6 of 11
Approved Manufacturers
The specified coating systems are listed in Table 5.1.A. Deviations are not
allowed without prior approval from Kinder Morgan Canada Inc. The
Contractor shall specify, at the tender stage, all precleaning, blasting, and
coating material to be used.
TABLE 5.1.A -- COATING SYSTEMS
Paint Manufacturer
Madewell
Material
Maximum
Quikset 1127
20
30
Standard 1103
25
35
Surface Irregularities
Before commencing blast cleaning all weld spatter, flux, slag, laminations,
burred edges, and sharp projections shall be ground off. Rough hand welds
shall be ground to minimum 3 mm radius.
6.2
Pre-Blast Cleaning
All oil, grease, and other deleterious matter shall be removed by chemical
cleaning with bio-degradable water based degreasers per SSPC-SP-1 prior
to any preparation and/or coating application.
6.3
Blast Cleaning
All surfaces to be coated shall receive a Near White Metal Blast Cleaning
in accordance with SSPC-SP-10.
6.4
Revision 0
Page 7 of 11
6.6
Masking
Care shall be exercised in blast cleaning to avoid damage to name plates,
gauges, instruments, electrical controls, and coated conduit.
Unless
otherwise specified, these surfaces shall not be painted.
6.7
Surface Contamination
Freshly blasted surfaces shall not be contaminated by workers' hands or
feet.
6.8
6.9
Coating Contamination
Special care shall be taken to ensure that blasting abrasive or dust is not
allowed to contaminate freshly applied coating. All dust and foreign matter
shall be completely removed from an existing coat before application of a
new coat. Any coating so contaminated shall be removed and replaced at
Contractor's expense.
6.10 Re-Blasting
No more surface shall be blasted than can be prime coated before visible or
detrimental re-rusting occurs. Blasted surfaces shall be prime painted by the
end of the same work day or before any rust bloom occurs.
6.11 Dead Man Control
Abrasive blast nozzles must be equipped with a fully operational "Dead Man
Control".
6.12 Alternate Cleaning Methods
Where blast cleaning is not practical, cleaning by power or hand tool
methods may be used upon specific approval by Kinder Morgan Canada Inc.
Revision 0
Page 8 of 11
7.0 APPLICATION
7.1
Rust Blooming
Where rusting or blooming occurs the metal surfaces shall be re-blasted to
remove all rust and blooming. Surfaces must be blown free of blasting
abrasives before the surface is primed.
7.2
Spray Equipment
Spray equipment suitable for the intended purpose shall be used. It shall be
capable of properly atomizing the paint to be applied and shall be equipped
with suitable pressure regulators and gauges in good working order. The air
caps, nozzles and needles shall be those recommended by the spray
equipment manufacturer for the paint being applied.
7.3
Film Continuity
All coatings shall be uniformly applied with adequate overlap of spray pattern
and be free of runs, sags, holidays, pinholes, voids, mud-cracking and other
anomalies.
7.4
7.5
Air Pressure
The atomizing air pressure at the gun shall be high enough to properly
atomize the paint, but not so high as to cause excessive fogging, loss of
solvent or overspray.
7.6
Film Thickness
The contractor shall provide the tradesmen applying coating materials with
wet film thickness gauges to ensure the application will result in the correct
final dry film thickness.
7.7
Coating Contamination
If in the judgment of Kinder Morgan Canada Inc.s representative a coating's
performance has been jeopardized by contact with rain, moisture
condensation, dust, or other foreign elements it shall be removed and
replaced.
Revision 0
Page 9 of 11
Overspray
Any surfaces contaminated by the Contractor with overspray or otherwise
displaced coating shall be cleaned or repainted to Kinder Morgan Canada
Inc.'s satisfaction.
8.0 INSPECTION
8.1
8.2
8.3
b)
c)
Revision 0
Page 10 of 11
SITE DESCRIPTION
Inspector
Date
Customer
Job Name
Area
Notes:
SURFACE PREPERATION
Pre Inspection Comments
Defects Corrected
Pre Cleaning Method
Equipment Used
Comments:
BLASTING ABRASIVE
Type/Grade of Abrasive
Spec. Standard
Condition
Air Temp
Relative Humidity
Steel Temp
Dew Point
Wind Direction
Wind Speed
km
Time
Time
Time
Time
Time
Revision 0
Page 11 of 11
Max.
Mean
Comments:
COATINGS
Coat
Paint Manufacturer
Name & Description
Description
Batch
Number
Application
Method
Color
MDFT
Before
This Coat
W.F.T.
Min
Max
1.
2.
3.
Coat
1.
2.
3.
M.D.F.T.
Min
Max
Mixing
Thinning
Storage
Holidays
Defects/Comments:
Revision 0
January 6, 2003
Page 1 of 1
1.0 SCOPE
This standard specifies the requirements additional to those of CSA Z245.20
External Fusion Bond Epoxy Coating for Steel Pipe. The numbering of Clauses
listed below refers to those in CSA Z245.20 unless otherwise indicated. Where
there is a conflict between these requirements and those specified by CSA, the
Kinder Morgan Canada Inc. requirement shall govern.
5.2.1 General
(d)
Material
3M
Scotchkote 6233
Dupont
Nap-gard 7-2501
Nap-gard 7-2500
Inspection Notice
Kinder Morgan Canada Inc. shall have unrestricted access to all plant and
test facilities, and may without providing the applicator notice, witness
coating application and testing.
Revision 3
Page 2 of 44
TABLE OF CONTENTS
1.0
SCOPE ................................................................................................................. 7
2.0
REFERENCED PUBLICATIONS.......................................................................... 8
3.0
DEFINITIONS ....................................................................................................... 9
4.0
3.1
3.2
3.3
NPS ........................................................................................................... 9
3.4
PN .............................................................................................................. 9
3.5
3.6
3.7
SMYS......................................................................................................... 9
PIPING DESIGN................................................................................................. 10
4.1
General .................................................................................................... 10
4.1.1
4.1.2
4.1.3
4.1.4
4.2
4.3
4.5
4.4
Revision 3
Page 3 of 44
5.0
Flanges .................................................................................................... 16
5.1.1
5.1.2
5.2
5.3
5.4
General .................................................................................................... 16
Hub design .............................................................................................. 16
Fittings ..................................................................................................... 16
5.2.1
5.2.2
5.2.3
5.2.4
5.2.5
5.2.6
General .................................................................................................... 17
End Preparations ..................................................................................... 18
6.0
Elbows ..................................................................................................... 19
Reducing Elbows ..................................................................................... 19
Miter Bends ............................................................................................. 19
Bends Made From Pipe ........................................................................... 19
General .................................................................................................... 19
6.1.1
6.1.2
6.1.3
6.1.4
6.1.5
6.1.6
6.1.7
6.1.8
6.1.9
6.2
Clearances............................................................................................... 21
6.2.1
6.2.2
6.2.3
6.2.4
Revision 3
Page 4 of 44
Valves ...................................................................................................... 24
6.3.1
6.3.2
6.3.3
6.3.4
6.3.5
6.3.6
6.3.7
6.3.8
6.3.9
6.3.10
6.3.11
6.3.12
6.3.13
6.3.14
6.3.15
6.4
6.5
General .................................................................................................... 29
Flange Loads ........................................................................................... 30
Piping Reducers ...................................................................................... 30
Restrictions on Elbows in Suction Piping ................................................ 30
Vertical Elbows in Suction Piping ............................................................ 30
Horizontal Elbows in Suction Piping ........................................................ 30
Temporary Strainers ................................................................................ 30
Vents and Drains ..................................................................................... 30
Pump Selection ....................................................................................... 31
7.0
General .................................................................................................... 24
Accessibility ............................................................................................. 24
Chain Operators ...................................................................................... 24
Handwheel Access .................................................................................. 25
Valve Installation, Vertical Handwheel Orientation .................................. 26
Valve Installation, Horizontal Handwheel Orientation .............................. 26
Relative Valve Elevation .......................................................................... 27
Valves Below Grade ................................................................................ 27
Valve Body Cavity/Bonnet Pressure Relief ............................................. 27
Globe Type Control Valves ...................................................................... 28
Check Valves ........................................................................................... 28
Ball Valves ............................................................................................... 28
Safety Relief Valves................................................................................. 28
Thermal Relief Valves.............................................................................. 29
Valve Selection ........................................................................................ 29
General .................................................................................................... 31
Vent and Drain Piping (NPS 2 and smaller) ............................................ 31
Equipment Isolation and Drains............................................................... 31
Pipe Header Termination Drains ............................................................. 31
Vents on Buried Piping ............................................................................ 31
Drain Piping Slopes ................................................................................. 32
Open Drain Header Systems................................................................... 32
Closed Drain Header Systems ................................................................ 32
Expansion Chambers .............................................................................. 32
General .................................................................................................... 33
Revision 3
Page 5 of 44
Analysis ................................................................................................... 33
7.3
7.4
7.5
7.6
7.7
8.0
8.2
8.3
Backfill ..................................................................................................... 41
9.2
10.0
General .................................................................................................... 38
Road Crossings ....................................................................................... 38
8.4
General .................................................................................................... 37
Minimum Wall Thickness ......................................................................... 37
Road Crossings ....................................................................................... 38
9.0
General .................................................................................................... 41
Girth Weld Coatings ................................................................................ 41
INSULATION ...................................................................................................... 42
10.1
Revision 3
Page 6 of 44
11.0
10.2
10.3
10.4
10.5
Examinations ........................................................................................... 44
11.2
Testing ..................................................................................................... 44
APPENDICES
Appendix A:
Appendix B:
Appendix C:
Appendix D:
Appendix E:
Revision 3
Page 7 of 44
1.0 SCOPE
This standard is a guide to mandatory design practices for station piping. This
standard shall be limited to systems transporting liquid hydrocarbons including:
crude oil, condensate and liquid petroleum products. This standard shall be
further limited to the design of Low Vapour Pressure (LVP) systems intended for
Category I service.
The scope of this standard includes all pressure pipe, valves, fittings and auxiliary
components used in tank farms, pump stations and terminals. This standard does
not cover the design of Main Line piping systems. The designer is cautioned that
this standard is not a comprehensive design handbook; it does not do away with
the need for the designer or for competent engineering judgement.
The requirements of this standard shall not be applied retroactively to existing
installations, but shall apply to the extension, repair, maintenance, and upgrading
of such installations.
FIGURE 1.0.A -- SCOPE DIAGRAM
Note:
Facilities indicated by heavy lines are within the scope of this standard,
light lines indicate facilities not within the scope.
Revision 3
Page 8 of 44
MP1200
MP1300
MP2215
MP2217
MP2219
Full-Encirclement Saddles
MP3102
MP3110
MP3901
Joining Program
MP4111
GC3101
GC3102
GC3103
Revision 3
Page 9 of 44
3.0 DEFINITIONS
3.1
Isolation Valve
A valve used to isolate facilities such as pumping stations, tank farms,
refineries, terminals, drain lines, and vents from the main line.
3.2
Main Line
Those items through which oil industry fluids are conveyed, which includes
pipe, components, and any appurtenances attached thereto, up to and
including the isolating valves used at stations and other facilities.
3.3
NPS
NPS means Nominal Pipe Size, and the NPS system of nominal size
designation is contained in standards prepared by the American Society of
Mechanical Engineers.
3.4
PN
PN means Pressure Nominal and the PN system of nominal pressure class
designation is contained in standards prepared by the International
Organization for Standardization (ISO).
The numerical part of the
designation approximates the maximum cold working pressure rating in bars
(100 kPa).
3.5
Sectionalizing Valve
A valve for isolating a section of pipeline.
3.6
Station Piping
This includes all pipe, components, and any appurtenances at Pump
Stations, Tank Farms, and Terminals downstream from the first station
isolating valve or sectionalizing valve within the station.
3.7
SMYS
SMYS means Specified Minimum Yield Strength. This is the minimum
yield strength prescribed by the specification or standard under which the
material is produced.
Revision 3
Page 10 of 44
4.2
General
4.1.1
4.1.2
4.1.3
4.1.4
Materials
The material requirements for pipe, piping components and nonmetallic elements (ie. gaskets, elastomers) shall be in accordance
with the requirements of Appendix A.
Design Conditions
4.2.1
Design Pressure
The maximum operating pressure (MOP) shall equal the design
pressure for the pressure class specified in Table 4.2.1.A.
TABLE 4.2.1.A -- DESIGN PRESSURES
Pressure Class
PN 20
(ANSI 150)
PN 50
(ANSI 300)
PN 100
(ANSI 600)
1900
4960
9930
2375
6210
12415
2850
7450
14900
Revision 3
Page 11 of 44
Design Temperature
The pipeline operating (or fluid) temperature range is -5C to 25C.
The design temperature range of this standard is -29C to 50C.
Design temperatures outside of this range are beyond the scope of
this standard. Ambient temperature ranges must be considered when
specifying materials that are not at pipeline temperature.
4.2.3
Design Fluids
The table lists the nominal properties for various hydrocarbons that
flow in station piping systems:
TABLE 4.2.3.A -- PROPERTIES OF DESIGN FLUIDS
4.3
Fluid
Density
(kg/m3)
Viscosity
(mm2/sec
@ 10C)
Vapour
Pressure
(kPa)
Flash
Point(C)
825 - 860
6 - 15
25 - 60
<-40
920 - 930
220 - 300
40 - 50
<-40
Condensate
695 - 745
0.7 - 0.8
40 - 70
<-40
MTBE
740
0.35 @ 20C
53.5
-26
Gasoline
695 - 735
0.4 - 0.45
85 - 105
<-40
Diesel
830 - 865
1-5
0 - 10
40
Methanol
795
0.7
12.8
15
820
2.0
4.0
38
Pressure Design
4.3.1
4.3.2
Pipe Size
Rating
Nipple Size
Rating
NPS 1 to 2
XS (Sch 80)
NPS 1
Sch 160
NPS 3 to 10
NPS 1 to 2
XS (Sch 80)
NPS 12 to 30
Appendix A
Pressure Relief
Relief valves shall be used to prevent excessive pressure build up in
any piece of equipment or piping system segment that can be
Revision 3
Page 12 of 44
4.4
4.3.3
Pressure Class
The pressure class for any section of piping not protected by a relief
valve shall be equal to the maximum pressure which can be
developed as a result of pump shut-off, inadvertent valve closure, or
static head (note: thermal relief valves are inadequate for this type of
protection).
4.3.4
Pump Shut-off
For piping subject to pump shut-off pressure, the design pressure
shall exceed the maximum suction pressure plus the pump shut-off
head.
4.3.5
Hydraulic Design
4.4.1
Revision 3
Page 13 of 44
3500
Region 4
Avoid applications
in this region
3000
2500
Region 2
Discharge
Piping
2000
1500
1000
Region 1
Suction Piping
500
0
6
10
12
14
16
18
20
22
24
26
28
30
4.4.2
4.5
Valve Sizing
In order to minimize erosion damage, vibration, and noise, the
velocity of flow through valves should not exceed 7.6 m/s. Block
valve sizing shall be in accordance with Kinder Morgan Canada Inc.
Standard MP1300.
Branch Connections
4.5.1
Revision 3
Page 14 of 44
b)
ii)
H
E
A
D
E
R
S
I
Z
E
4.5.3
10
12
16
20
24
24
RT
RT
RT
20
RT
RT
RT
16
RT
RT
RT
12
RT
RT
RT
10
RT
RT
RT
RT
RT
RT
RT
RT
RT
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
T
RT
W
O
=
=
=
=
=
Revision 3
Page 15 of 44
B
R
A
N
C
H
S
I
Z
E
150
150
150
150
160
150
160
170
180
150
170
170
180
190
260
310
310
310
310
510
290
340
340
340
340
540
575
330
380
380
380
380
580
610
650
360
410
410
410
410
610
650
680
720
10
410
450
450
450
450
660
690
730
760
10
810
Revision 3
Page 16 of 44
5.2
Flanges
5.1.1
General
Raised face, weld neck flanges should be used for permanent
piping. Slip on flanges should be avoided. If slip on flanges are
used, they shall be double welded (welded on the inside and outside
diameter). Except as permitted by clause 5.1.2, the material grade
shall conform to the requirements of Appendix A.
5.1.2
Hub design
A flange with a SMYS less than that of the mating pipe may be used
provided that there is a corresponding increase in thickness of the
hub at the welding end of the flange. The hub thickness shall be
such that the product of its nominal thickness and its SMYS is equal
to or greater than the respective product for the mating pipe.
However, the ratio of the SMYS of the pipe to that of the flange shall
not exceed 1.5.
The end preparation shall conform to the
requirements of 5.3.5. When pipe of greater wall thickness than
required is used, match boring of the pipe ends to suit the flange
thickness is permitted.
Fittings
5.2.1
5.2.2
Increased Thickness
A fitting with a SMYS less than that of the mating pipe may be used
provided that there is a corresponding increase in the fitting wall
thickness. The fitting wall thickness shall be such that the product of
its nominal thickness and its SMYS shall be equal to or greater than
the respective product for the mating pipe. However, the ratio of the
SMYS of the pipe to that of the fitting shall not exceed 1.5. The end
preparation shall conform to the requirements of 5.3.5. When pipe of
greater wall thickness than required is used, match boring of the pipe
ends to suit the fitting thickness is permitted.
Revision 3
Page 17 of 44
5.3
5.2.3
Reducers
Concentric or eccentric reducers joining pipes of different thickness
should be specified for the thicker wall, with end preparation as per
subsection 5.3.5.
5.2.4
5.2.5
5.2.6
Piping Unions
Pipe unions shall be limited to drain piping and shall not be used in
pressure piping systems. Unions in drain systems shall be located
on the downstream or low pressure side of header drain valves.
Joint Design
5.3.1
General
Typical piping joints are welded, flanged or threaded. Piping systems
should be designed to minimize the number of joints, and should be
welded wherever possible. Joints on piping shall be in accordance
with the requirements of Table 5.3.1.A.
TABLE 5.3.1.A - JOINT SELECTION GUIDE
Joint Type
Application
Threaded
Socket
Welded
Butt
Welded
PN 20 NPS 1
PN 20 > NPS 1
Temporary only
Drain Systems
Buried Piping
Prohibited
PN 50 & PN 100
Prohibited
Prohibited
Revision 3
Page 18 of 44
End Preparations
Transition between ends of unequal thickness shall be accomplished
by the means illustrated in Figure 5.3.5.A.
FIGURE 5.3.5.A -- END PREPARATIONS
d) External Diameters
Unequal
SMYS 1
t2 = t1
and t2 1.5 t1
SMYS 2
e) External and Internal Diameters Unequal
t1 = design wall thickness of the mating pipe
t2 = design wall thickness of the fitting or thicker pipe
SMYS1 = SMYS of pipe
SMYS2 = SMYS of fitting or thicker pipe
1)
2)
3)
4)
Where the fitting is tapered within its design thickness (t2), the taper angle () shall be;
Wrought Fittings: 14 30, Flanges: 14 18
Where the taper is outside the design thickness, the minimum angle is 0 (wrought fittings only);
Undimensioned angles and lands shall be in accordance with either figure a or b.
In the case of match boring pipe of greater wall thickness than required, t1 is the thickness of the
fitting and t2 is the thickness of the pipe, with the corresponding reversal in SMYS1 and SMYS2.
Revision 3
Page 19 of 44
Elbows
Long radius elbows shall be used in permanent piping for sizes NPS
3 and larger. Because of their poor hydraulic characteristics, short
radius elbows are to be avoided, particularly in pump suction piping
and upstream of valves, flow measuring equipment, and
instrumentation connections. One exception is the use of short
radius elbows in safety relief valve discharge piping to minimize the
moment and forces on the valve. Elbows in piping systems designed
tp allow for internal inspection shall have a minimum radius of three
pipe diameters.
5.4.2
Reducing Elbows
Because of their high relative cost and quality assurance problems,
reducing elbows should be avoided.
If reducing elbows are
unavoidable, they must be carefully specified and inspected during
fabrication.
5.4.3
Miter Bends
Miter bends shall be avoided and their use is prohibited on PN 50
and PN 100 piping.
5.4.4
b)
General
The overall piping arrangement should be neat, orderly, and economical
based on the following guidelines:
6.1.1
Pipe Routing
Multiple adjacent piping runs should be routed parallel to one another
and at a common elevation. Branches off the main lines should be
Revision 3
Page 20 of 44
Consistency
Piping layouts at multiple identical pieces of equipment should be
alike for familiarity and ease of operation.
6.1.3
Maintainability
All piping and equipment requiring regular attention by operating and
maintenance personnel should be readily accessible. Adequate,
clear working spaces, of at least 1m, should be provided around
equipment such as pumps and valves. Piping should be self
supporting for ease of equipment removal.
6.1.4
Operability
Piping shall be designed such that operating personnel can perform
their functions in an efficient manner. Not every valve and instrument
can be ideally located, but priorities can be established by
consideration of the frequency of operation and degree of physical
effort required.
6.1.5
Safety
Stairs, ladders, and platforms shall be provided with adequate head
room and lateral clearance. Equipment, valves and other piping
components shall be located such that they do not create hazards.
Special care shall be taken in the placement of valve stems. Every
effort shall be made to keep such projections out of the area between
1400 to 1800 mm (face level) above grade.
6.1.6
Environment
At large integrated manifold systems, overhead cranes complete with
roof systems should be provided to shelter workers and equipment
from the elements and minimize the amount of rainwater runoff to be
processed. These manifolds shall also include liner systems and
sumps to collect and contain leakage.
6.1.7
Dead Legs
Industry experience has shown that dead legs (sections of pipe which
do not experience flow under normal conditions) are subject to
internal corrosion and thus should be avoided. These volumes also
present contamination problems and shall be minimized on any clean
product systems.
Revision 3
Page 21 of 44
6.2
6.1.8
6.1.9
aboveground piping is
maintenance and repair;
accessible
for
visual
inspection,
b)
c)
d)
e)
f)
Clearances
6.2.1
Revision 3
Page 22 of 44
Location
Above railroad tracks from base of rail
Above major roads open to unrestricted traffic
as periphery of manifold area limits)
6.8 m
(such
5.5 m
4.25 m
6.2.2
4.25 m
3.05 m
2.15 m
0.3 m
Piping Access
Piping shall be designed in order to maintain the minimum width of
accessway specified in Table 6.2.2.A.
TABLE 6.2.2.A -- MINIMUM WIDTH OF ACCESSWAY
Location
Manifold area
accessway
a)
b)
Width
Primary
Secondary
6.2.3
1.50 m
0.91 m
0.81 m
Revision 3
Page 23 of 44
135
135
365
Critical
service
applications
such as unit
and station
valves
155
155
380
160
160
180
180
210
210
255
255
285
285
1010
510
10
330
330
1040
555
12
355
355
1060
580
16
420
420
1100
645
20
480
480
1150
710
24
545
545
1200
770
30
640
640
1280
865
385
405
440
480
6.2.4
Revision 3
Page 24 of 44
6.3
Pipe
Size
10
12
16
20
24
30
30
475
475
500
550
575
625
650
700
750
775
825
875
950
24
450
450
450
475
525
550
575
625
650
700
750
800
20
400
400
425
425
450
475
525
550
575
625
675
16
325
350
350
375
400
425
475
500
525
575
12
275
300
300
325
350
375
400
450
475
10
250
275
275
300
325
350
375
400
225
250
250
275
300
325
350
275
200
225
225
250
250
175
175
200
200
225
150
150
175
175
125
125
150
125
125
125
Valves
6.3.1
General
Valves should be installed with their stems oriented between the
vertical upward (preferred) and 45 from vertical positions. Horizontal
valve installations should be avoided. Valves shall not be installed
upside down. The following safety hazards must be avoided when
determining stem orientation: head and knee interference, tripping
hazards, and valve stems at eye level in the horizontal plane. The
valve handwheel size shall not be reduced to accommodate the
piping arrangement.
6.3.2
Accessibility
In determining the location of valves in piping systems, accessibility
for operation and adequate space for maintenance shall be provided.
The use of extended stems should be considered in order to avoid
unnecessary loops or turns in the piping.
6.3.3
Chain Operators
The use of chain operators should be avoided. In general, only
infrequently used valves should be located with their handwheel
centerline higher than 1400 mm above grade. Platforms should be
provided for any valves required in piping above this elevation. An
exception to this requirement would be a high point vent.
Revision 3
Page 25 of 44
Handwheel Access
A minimum of 100 mm clearance shall be provided around the entire
circumference of all handwheels. For valve handwheels behind
obstructions, such as handrails, the following shall apply:
a)
b)
HORIZONTAL
VERTICAL
Revision 3
Page 26 of 44
6.3.5
6.3.6
Revision 3
Page 27 of 44
6.3.7
NEVER
AVOID
BETTER
BEST
6.3.8
6.3.9
Revision 3
Page 28 of 44
b)
b)
Revision 3
Page 29 of 44
d)
Where more than two safety valves are located in the same
header run, the spacing between valves should be varied such
that the distance between two adjacent valves differs by at least
an inlet nozzle diameter.
e)
The relief valve outlet piping shall consist of the mating flange
and a fitting to fitting short radius elbow in order to keep the
moment and forces imposed on the valve to a minimum.
MOP (kPa)
PN 20
1,900
2,000
PN 50
4,960
5,200
PN 100
9,930
10,400
Centrifugal Pumps
6.4.1
General
Piping systems at pump locations shall be designed to allow for
pump removal and maintenance. At locations with multiple pumps,
each pump should have isolation valves and a check valves. The
piping should be designed to minimize flanges loads on the pump
and flexible connections to pumps shall be avoided. Flexible
connections shall not be permitted for pumps with drivers greater
than 3 kw in size.
Revision 3
Page 30 of 44
Flange Loads
The suction and discharge piping must be supported independently
of the pump such that minimal load is transmitted to the pump
flanges. API Standard 610, Centrifugal Pumps for General
Refinery Service, should be consulted when designing suction and
discharge piping. Allowable pump flange loads are given in section
2.4 and in Appendix F -Criteria for Piping Design.
6.4.3
Piping Reducers
When a reduction in pipe size is required at the pump suction, an
eccentric reducer with the flat side up shall be used.
6.4.4
6.4.5
6.4.6
6.4.7
Temporary Strainers
Pump suction lines should be designed to accommodate a
temporary, in-line, conical type strainer used during pump
commissioning.
6.4.8
Revision 3
Page 31 of 44
6.5
Pump Selection
Pumps with cast iron pressure containing components shall not be
used for hydrocarbon service. Centrifugal pumps shall be in
accordance with API Standard 610, Centrifugal Pumps for
General Refinery Service.
General
High-point vent and low-point drain connections shall be provided
on all piping systems. These connections provide a means of
flooding and draining piping systems and equipment for hydrostatic
testing and during start-up and shutdown. The recommended design
of vents and drains shall be as shown in Appendix B.
6.5.2
6.5.3
6.5.4
6.5.5
Revision 3
Page 32 of 44
6.5.7
6.5.8
6.5.9
Expansion Chambers
Where it is impractical to route separate lines from closed and open
drain headers to a sump or slop tank, the headers can be connected
by use of an expansion chamber or blow-off box. The expansion
chamber should be vented to atmosphere and designed in
accordance with the requirements of Appendix B. For high volume
systems, installation of a high level alarm in the expansion chamber
should be considered.
Revision 3
Page 33 of 44
General
Piping systems shall have sufficient flexibility to prevent thermal expansion or
contraction or movements of piping supports from causing:
7.2
a)
b)
leakage at joints; or
c)
Analysis
Piping stress and flexibility analysis is required for NPS 4 and larger piping
when:
a)
it is connected to rotating equipment;
b)
c)
d)
e)
315
175
-25
2
P ip e S ize (N P S)
10
12
Revision 3
Page 34 of 44
Design Criteria
Section 4.6 of CSA Z662 provides concepts, data and methods for
determining the requirements for flexibility in a piping system. These
requirements include:
a)
b)
c)
7.4
207,000 MPa
12 x 10-6/C
0.30
20C
Routing
The following guidelines shall be used to obtain the required flexibility using
the minimum amount of pipe, fittings, and expansion loops:
a)
b)
c)
A piping system between two anchor points with the piping in two
planes should, as a minimum, consist of two L-shaped runs of pipe, one
in the horizontal plane and another in the vertical plane.
d)
When the expected thermal expansion in any given pipe run is high, the
use of an anchor at or near the center of the run will distribute the
expansion in two directions.
Revision 3
Page 35 of 44
7.5
Expansion Joints
Bellows or packed expansion joints shall not be permitted. Proper piping
design techniques, anchoring of piping and stress analysis shall be used to
eliminate the need for flexible connections.
7.6
Piping Supports
Pipe supports, anchors and guides shall be designed in accordance with
Appendix D of this standard. The design of piping supports shall be based
on all concurrently acting loads transmitted to such supports. These loads
shall include weight effects, loads induced by service pressures,
temperatures, vibration, wind, earthquake, shock and displacement strain.
Pipe supports shall also be designed to prevent wear and corrosion of the
pipe.
7.6.1
7.6.2
7.6.3
Anchor Blocks
Stresses and deflections occur in pipelines at the transition from the
below ground (fully restrained) to the above ground (unrestrained)
condition. Analysis of the stresses and deflections in the transition
areas, resulting form internal pressure and temperature change shall
be in accordance with Appendix C of this standard.
Revision 3
Page 36 of 44
7.7
Piping Class
20 - 30
8 - 30
Piping Spans
The maximum allowable distance between pipe supports shall be as given in
Table 7.7.A for each of the cases depicted in Figure 7.7.A.
Note: Spans listed in Table 7.7.A are designed to limit piping deflections to 6.35 mm. Do
not apply where concentrated weights such as heavy valves or heavy fittings exist.
FIGURE 7.7.A -- MAXIMUM SPAN BETWEEN SUPPORTS
Revision 3
Page 37 of 44
L1
L2
L3
L4
L5
L6
L7
1
2
3
4900
5500
6700
4000
4300
5200
4000
4600
5500
3700
4000
4600
3700
4000
4300
--4900
----
4
6
8
7600
8800
10100
5800
7000
7900
6100
7300
8200
4900
5500
6100
4900
5500
6400
5200
5800
6400
-7000
7600
10
12
14
11000
11900
12200
8500
9400
9800
9100
9800
10100
6400
6700
6700
7000
7300
7600
7700
7300
7600
7900
8200
8500
16
20
24
12800
14000
14900
10100
11100
11900
10700
11600
12200
7000
7300
7600
8200
8800
9400
8200
8800
9400
8800
9400
9800
General
The minimum design wall thickness for buried piping shall be
determined by the following design formula:
t = pipe design wall thickness (mm)
t=
PD
2SF
8.1.2
<6
6 - 14
16 - 30
per Appendix A
6.35
7.92
Revision 3
Page 38 of 44
Road Crossings
Notwithstanding 8.1.1 and 8.1.2, the minimum requirements for
buried, uncased road crossing piping shall be (based on 1.2 m of
cover):
TABLE 8.1.3.A -- MINIMUM REQUIREMENTS FOR ROAD CROSSINGS
Pressure Class
PN 50 (ANSI 300)
8.2
8.3
Size (NPS)
20
24
30
10
12
16
20
24 - 30
7.92
9.53
12.7
7.92
9.53
9.53
9.53
12.7
Min. Grade
241
241
241
290
359
359
General
Wherever possible, buried piping should be located in straight runs
on flat ground. Steep slopes should be avoided. In areas where
steep slopes cannot be avoided, piping should be located such that it
follows the fall line of the slope.
8.2.2
Road Crossings
Where buried piping crosses a road, the angle of intersection should
be as near to 90 degrees as possible. In no case should it be less
than 30 degrees. The crossing piping should be uncased.
Pipe Clearances
8.3.1
Minimum Cover
Piping should be buried at a constant depth below grade with a
minimum cover as given in Table 8.3.1.A (Measured from the top of
pipe to the top of the surface).
TABLE 8.3.1.A -- MINIMUM DEPTH OF COVER
Location
under bottom of ditches
non travelled surfaces
road crossings
Minimum Cover
0.9 m
1.0 m
1.2 m
Revision 3
Page 39 of 44
8.3.2
8.3.3
Clearance (mm)
600
1000
Revision 3
Page 40 of 44
Revision 3
Page 41 of 44
8.4
Backfill
With the exception of bored sections or piping installed in compressible soils
all buried piping should be backfilled in a manner consistent with the crosssection illustrated in Figure 8.3.3.A. The bedding material should be sand or
fine sand and gravel. If the native soils excavated for the trench are
unsuitable or cannot otherwise be screened, the sand bedding shall be
imported from an appropriate borrow site. Bedding should be placed around
the pipe in a manner to prevent damage to the coating and mechanically
compacted using vibratory equipment to 95% standard Proctor maximum
dry density.
Exposed Piping
All external surfaces of exposed, carbon steel piping shall be coated in
accordance with Kinder Morgan Canada Inc. Standard GC3101.
9.2
Buried Piping
9.2.1
General
All external surfaces of buried, carbon steel piping shall be coated in
accordance with Kinder Morgan Canada Inc. Standard GC3102.
Alternative coating systems are listed in Appendix A.
9.2.2
Revision 3
Page 42 of 44
10.0 INSULATION
10.1 Insulation Materials and Application
Insulation materials, including insulating cement and insulation covering,
shall not contain asbestos. Approved insulation materials are listed in
Appendix A.
10.1.1 Exterior Piping
Piping shall generally be insulated with preformed mineral wool or
spun glass fibre with the following exceptions:
a)
b)
Revision 3
Page 43 of 44
Revision 3
Page 44 of 44
Revision 1
Page 1 of 11
TABLE OF CONTENTS
1.0
SCOPE ................................................................................................................. 3
1.1
General ...................................................................................................... 3
1.2
2.0
3.0
DEFINITIONS ....................................................................................................... 4
3.1
3.2
3.3
Heat ........................................................................................................... 4
3.4
3.5
Supplier...................................................................................................... 4
3.6
NPS ........................................................................................................... 4
3.7
Pipe............................................................................................................ 5
3.8
3.9
SMYS......................................................................................................... 6
3.10
4.0
GENERAL REQUIREMENTS............................................................................... 6
5.0
5.1
5.2
6.0
Revision 1
Page 2 of 11
General ...................................................................................................... 7
6.2
7.0
8.0
8.1
8.2
Rejection .................................................................................................... 9
8.3
Defects....................................................................................................... 9
8.4
9.0
SHIPPING .......................................................................................................... 10
9.1
General .................................................................................................... 10
9.2
9.3
10.0
10.1
Marking .................................................................................................... 11
10.2
Revision 1
Page 3 of 11
1.0 SCOPE
1.1
General
This standard covers welded and seamless steel pipe primarily intended for
use in station piping systems. This standard does not cover line pipe for
main line applications. This pipe will comply with all the requirements of
Canadian Standards Association standard CSA Z245.1-95, Steel Line Pipe
and this standard. Pipe that conforms to all of the requirements of CSA
Z245.1-95 but does not comply with all of the requirements of this standard
may be acceptable subject to the discretion of Kinder Morgan Canada Inc.
1.2
1.2.2
Grade
This standard covers pipe from grade 207 to 359 inclusive.
1.2.3
Category
This standard covers Category I pipe, per CSA Z662.
API Spec 5L
API RP 5LI
ASTM A530
ASTM A53
ASTM A106
Revision 1
Page 4 of 11
CSA Z662
CSA Z245.1
3.0 DEFINITIONS
3.1
Analysis, Heat
The chemical analysis reported by the steel producer as being representative
of the heat of steel.
3.2
Analysis, Product
The chemical analysis made on a sample taken from the finished product or
material representative of the finished product. Also known as check
analysis.
3.3
Heat
Heat shall mean material produced from the same batch of steel tapped from
a melting furnace, rolled into plate or coil using the same rolling practice, and
made into pipe using the same forming, welding and expanding procedures.
3.4
Killed Steel
Steel treated with aluminum and silicon or other deoxidisers to minimize gas
evolution during cooling.
3.5
Supplier
The term Supplier as used in this specification shall mean those who have
contracted to provide pipe and shall include their facilities.
3.6
NPS
NPS means nominal pipe size, and the NPS system of nominal size
designation is contained in standards prepared by the American Society of
Mechanical Engineers.
Revision 1
Page 5 of 11
Pipe
A pressure-tight cylinder used to convey a fluid or to transmit a fluid
pressure. Types of pipe, defined according to the method of manufacture,
are defined as follows:
3.8
3.7.1
3.7.2
3.7.3
3.7.4
3.7.5
Seamless
Pipe produced by piercing a billet followed by rolling or drawing, or
both.
Skelp
The hot-rolled plate or coil that is used to form pipe.
Revision 1
Page 6 of 11
SMYS
SMYS means Specified Minimum Yield Strength. This is the minimum
yield strength prescribed by the specification or standard under which a
material is purchased.
Deoxidation Practice
All pipe manufactured to this specification shall be made from fully-killed
steel. Silicon is an acceptable deoxidizer, but aluminum shall also be used
for grain refinement.
5.2
Pipe Manufacture
5.2.1
Material Specification
This standard covers pipe made to the requirements of CSA
Standard Z245.1. Where such line pipe is not available, pipe that is
manufactured in accordance with API Standard 5L, ASTM A53,
ASTM A106, or ASTM A333 (grade 6 only) shall be permitted.
5.2.2
Process of Manufacture
Only pipe produced by the submerged arc welding (SAW), high
frequency electric resistance welding (HFERW) and seamless
manufacturing processes are acceptable. Pipe produced by furnace
butt-welding or continuous welding and electric fusion welding
processes are specifically prohibited. For submerged arc welded
pipe, the pipe shall contain a single straight seam using at least two
weld passes. At least one pass shall be made from the inside and at
least one pass shall be made from the outside.
Revision 1
Page 7 of 11
= % Expansion
General
Chemical composition based on both heat and product (check) analysis shall
fall within the limits established in Table 6.1.A.
TABLE 6.1.A -- CHEMICAL COMPOSITION REQUIREMENTS
COMPOSITION
Element
Carbon
Manganese
Phosphorus
Sulfur
Silicon
Niobium1
Vanadium
Aluminum
Copper
Chromium
Molybdenum
Nickel
Boron
C Equivalents
PIPE
Symbol
C
Mn
P
S
Si
Nb
V
Al
Cu
Cr
Mo
Ni
B
CECSA2
Grade 241
0.18
1.35
0.023
0.025
0.35
0.070
0.070
0.060
0.30
0.25
0.50
0.20
0.0005
0.36
Mn Si Cu Ni Cr + Mo +V + Nb
+ +
+ +
+ 5B
CE CSA = C + F
6
24
15
20
5
Revision 1
Page 8 of 11
C. Content
C. Content
C. Content
<0.06/0.06
0.07
0.08
0.09
0.53/0.54
0.56
0.58
0.62
0.10
0.11
0.12
0.13
0.66
0.70
0.75
0.80
0.14
0.15
0.16
0.17
0.85
0.88
0.92
0.94
0.18
0.19
0.20
0.21/>0.21
0.96
0.97
0.98
0.99/1.00
6.2
Intentional additions
No deliberate additions of boron are allowed. All elements listed in Table
6.1.A of and any other intentionally added elements shall be reported in the
mill test certificates and shall be to the same number of decimal points as
shown. The carbon equivalent shall be calculated using the formula above.
Ratio
Seamless
0.90
HFERW
0.93
DSAW
0.85
Plant Access
Kinder Morgan Canada Inc. representatives will conduct audit checks as
deemed necessary by themselves to ensure compliance with these
specifications. This shall be done without interfering unnecessarily with
operations.
Revision 1
Page 9 of 11
Rejection
Kinder Morgan Canada Inc. authorized inspection representatives have the
authority to reject any pipe that does not comply with these specifications.
Pipe will not be accepted for inspection by Kinder Morgan Canada Inc.
unless it is free inside and outside of all oil, grease, excessive rust, flux or
caustic substances. Pipe that is not free of rust, flux, etcetera shall be shot
blasted, sand blasted, or otherwise cleaned in a manner acceptable to Kinder
Morgan Canada Inc. enabling an adequate inspection. Heat and pipe
number identification shall be maintained.
8.3
Defects
In addition to the requirements of CSA Z245.1, finished pipe shall be free of
the following defects:
8.3.1
Plain Dents
All body dents of depth greater than 3.5 mm or weld dents of a depth
greater than 1.5 mm shall be cut out as a cylinder.
8.3.2
Laminations
Laminations extending into the bevel face of the pipe and having
either a transverse dimension exceeding 6 mm or an accumulated
length exceeding 6 mm in the same plane in any 50 mm sector of the
circumference, are considered defects. Pipe containing such defects
shall be cut back until all such lamination is removed.
8.3.3
Undercuts
The maximum length of an undercut to be repaired by grinding and
welding is 25 mm. The maximum depth of a repairable defect shall
not exceed 12.5% of the specified wall thickness.
8.3.4
Other Defects
Imperfections which have a depth less than 12.5% of the specified
wall thickness shall be given one of the following two dispositions:
a)
Revision 1
Page 10 of 11
8.4
Length Tolerance
Tolerances on length shall be as given in Table 8.4.A.
TABLE 8.4.A -- LENGTH TOLERANCES
Length
Nominal 12 m
Nominal 18 m
Nominal 24 m
Minimum Average
Maximum
8.10
15.10
15.10
10.70
16.00
21.40
13.70
19.80
25.30
Note: Unless otherwise specified, the minimum average length shall be 12.0m.
9.0
SHIPPING
9.1
General
Care shall be taken to ensure that pipe is stored, loaded, and transported in
such a manner as to avoid damage. The occurrence of critical stresses and,
possibly, of fatigue of the pipe while in transit shall be avoided.
9.2
Weld Seams
The weld seam of submerged arc welded pipe shall not contact any part of
the separator blocks. No weld seam shall contact any part of the railway car
or truck trailer. Particular attention shall be paid to the positioning of
circumferential welds.
9.3
Metal Contact
For submerged arc welded pipe there shall be no metal to metal contact
between adjacent pipe. Tie-down chains may be used provided that they do
not come into direct contact with the pipe. A minimum separation between
pipe and bulkhead shall be maintained at 300 mm.
Revision 1
Page 11 of 11
b)
c)
d)
e)
f)
g)
h)
i)
Heat number.
Heat and product analysis for elements given in Section 6.0, or other
intentionally added elements and those appearing in the carbon
equivalent formula;
b)
Pipe body tensile test results for yield strength, tensile strength and
percent elongation;
c)
d)
e)
f)
g)
SHEET
ITEM
SIZE
(NPS)
CATEGORY
THICKNESS
(mm)
PROCESS OF
MANUFACTURE
JOINT
LENGTH (m)
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
-29oC to 50oC
-5oC to 25oC
FLUIDS HANDLED
crude oil
methanol
diesel
M.T.B.E.
gasoline
condensate
heavy crude oil
DOCUMENTATION
Gr. 207,241
Gr. A,B
Gr. 6 (A333)
Carbon
Manganese
Phosphorus
Sulfur
Silicon
Niobium
Vanadium
Aluminum
Copper
Chromium
Molybdenum
Nickel
Boron
C
Mn
P
S
Si
Nb
V
Al
Cu
Cr
Mo
Ni
B
0.18
1.35
0.023
0.025
0.35
0.070
0.070
0.060
0.30
0.25
0.50
0.20
0.0005
0.15
1.35
0.023
0.025
0.35
0.070
0.070
0.060
0.30
0.25
0.50
0.20
0.0005
Carbon
Equivalents
CECSA
0.36
0.36
Element
b)
c)
d)
e)
f)
g)
Revision 0
April 2007
Page 1 of 9
TABLE OF CONTENTS
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
SCOPE ................................................................................................................. 2
1.1
General ...................................................................................................... 2
1.2
Size and Pressure Class............................................................................ 2
1.2.1 Size ............................................................................................................. 2
1.2.2 Pressure Class ............................................................................................ 2
1.3
Category .................................................................................................... 2
1.4
End Configuration ...................................................................................... 2
REFERENCE PUBLICATIONS ............................................................................ 2
DESIGN ................................................................................................................ 3
3.1
Gate Valves ............................................................................................... 3
3.2
Floating Ball Valves ................................................................................... 3
3.2.1 Required Features ...................................................................................... 4
3.2.2 Optional Features ....................................................................................... 4
3.3
Check Valves ............................................................................................. 5
3.3
Operating Conditions ................................................................................. 5
MATERIALS AND MANUFACTURE .................................................................... 4
4.1
Fluids Handled ........................................................................................... 4
4.2
Materials .................................................................................................... 6
4.3
Valve Coatings ........................................................................................... 7
CHEMICAL TEST REQUIREMENTS ................................................................... 8
MECHANICAL TEST REQUIREMENTS .............................................................. 9
HYDROSTATIC TESTING ................................................................................... 9
DOCUMENTATION AND REPORTING ............................................................... 9
Revision 0
April 2007
Page 2 of 9
1.0
SCOPE
1.1
General
This standard covers requirements for small steel gate, ball, and check
valves intended for use in liquid petroleum pipeline systems. Needle
valves or other valves associated with instrumentation are not included in
the scope of this standard. All valves shall comply with the requirements
of this standard as applicable.
1.2
2.0
1.3
Category
This standard covers valves built for ASME B31.4 or Category I service
per CSA Z662.
1.4
End Configuration
This standard covers valves with threaded end configurations. Valve end
connections shall be internally taper threaded as specified in ANSI/ASME
B1.20.1.
REFERENCE PUBLICATIONS
Where reference is made to other publications, such references shall be
considered to refer to the latest edition and any revisions thereto approved by the
organization issuing that publication.
Some reference publications are
supplemented or qualified, or both, by specific requirements in this standard;
therefore, reference publications should be applied only in the context of this
standard.
API 602
API 607
ASME B16.34
ANSI B31.4
ANSI/ASME B1.20.1
Revision 0
April 2007
Page 3 of 9
3.0
DESIGN
3.1
Gate Valves
The following features are required:
a)
meet the requirements of API 602;
3.2
b)
c)
d)
e)
Revision 0
April 2007
Page 4 of 9
Check Valves
The following features are required:
a)
regular swing or in-line (spring assisted) type;
b)
soft seat seal;
c)
permanent flow direction arrow on the valve body;
d)
cast or forged steel body.
3.4
Operating Conditions
The valve shall be designed to operate under the conditions listed in Table
3.4.A.
TABLE 3.4.A OPERATING CONDITIONS
Valve
Piping System
MOP
2000 WOG
9930 kPa
(1440 psi)
Design (Ambient)
Temperature
-29C to 38C
(-20F to 100F)
14,890 kPa
3000 WOG
PN150 (ANSI 900)
(2160 psi)
Notes: Normal Product Temperature Range -5C to 38C (23F to 100F).
Valves are in a CSA Z662 Cat. I and/or B31.4 service.
Valves may be subject to vacuum conditions up to -50 kPa (-7.25 psi)
gauge.
MOP (maximum operating pressure) is equivalent to maximum differential
pressure across the valve.
4.0
Fluids Handled
The valve materials shall be compatible with fluids listed in Table 4.1.A.
Revision 0
April 2007
Page 5 of 9
Viscosity
Sediment %*
H2S (ppm)
Specific Gravity
<1
0.69 0.74
0.5 0.7
<1
0.81 0.87
2-7
Synthetic Crude
0 0.01
<1
0.86 0.88
6 - 10
0.01 0.02
< 10
0.82 0.85
4 - 15
0.01 0.03
< 250
0.84 0.87
5 - 20
Heavy Crude
0.01 0.02
< 20
0.9 0.94
150 - 350
Light Sweet
Crude
(cSt)
4.2
Materials
The valve shall be designed to meet or exceed material specifications as
listed in Tables 4.2.A and 4.2.B. Equivalent or alternate materials may be
acceptable if approved by Kinder Morgan Canada Inc.
Revision 0
April 2007
Page 6 of 9
Stem/
Shaft
Seats/
Slips
Seat Inserts
Gaskets
Elastomers
Packing
Bolting
Springs/
Pins
Gate
ASTM A36
ASTM A105
ASTM A537
Valve Type
Ball
ASTM A148
ASTM A350 LF2
ASTM A105
Check
ASTM A36
ASTM A216 Gr.
WCC, WCB
ASTM A105
AISI 4130
AISI 4140
ASTM A276 Gr. T304, T310, T410, T416, T420
ASTM 582 Gr. T582
ASTM A36
ASTM A182 Gr. F6a, F304, 310, F316
ASTM A217 Gr. CA15
ASTM A351 Gr. CF8, CF8M, CN7M
ASTM A395
ASTM A537
ASTM A572
Nitrile, nylon, teflon, or viton or equivalent as recommended by the
manufacturer based on operating conditions.
Gaskets shall be non-asbestos type manufactured in accordance with
ANSI B16.21.
Nitrile or viton as per manufacturers recommendation based on
operating conditions.
Packing shall be non-asbestos type per manufacturers
recommendation based on operating conditions.
Studs ASTM A193 B7
Nuts ASTM A194 2H
AISI 302, 304, or 316 Stainless steel
Revision 0
April 2007
Page 7 of 9
4.3
5.0
Castings
ASTM A216 Gr. WCB, WCC
ASTM A217 Gr. WC1, CA15
ASTM A352 Gr. LCB, LCC,
LC1, LC2, LC2.1, LC3
ASTM A487 Gr. 1, Cl. A & B
ASTM A487 Gr. 2, Cl. A & B
ASTM A487 Gr. 4, Cl. A, B &
E
ASTM A487 Gr. CA6NM
ASTM A487 Gr. CA15M
ASTM A757 (all grades
except B3Q & B4N)
Forgings
ASTM A105
ASTM A181 Cl. 60, 70
ASTM A182 Gr. F1, F2, F11,
F12
ASTM A350 Gr. LF1, LF2,
LF3
ASTM A541 Cl. 1, 4
CSA Z245.11
CSA Z245.12
Valve Coatings
Unless otherwise specified, all valves shall be cleaned, primed, and top
coated in accordance with the Kinder Morgan Canada Inc. standard
specified on the data sheet.
Symbol
Element
Symbol
Carbon
C
Aluminum
Al
Manganese
Mn
Copper
Cu
Phosphorus
P
Chromium
Cr
Sulphur
S
Molybdenum
Mo
Silicon
Si
Nickel
Ni
Niobium
Nb
Boron
B
Vanadium
V
Carbon Equivalent
CE(1)
(1) The carbon equivalent (CE) shall be calculated using the CSA or Yurioka formula as
follows:
Revision 0
April 2007
Page 8 of 9
Mn Si Cu Ni Cr + Mo +V + Nb
+ +
+ +
+ 5B
CE CSA = C + F
24 15 20
5
6
6.0
7.0
F
0.53
0.54
0.56
0.58
0.62
0.66
Carbon Content
(%)
0.11
0.12
0.13
0.14
0.15
0.16
F
0.70
0.75
0.80
0.85
0.88
0.92
Carbon Content
(%)
0.17
0.18
0.19
0.20
0.21
Greater than 0.21
F
0.94
0.96
0.97
0.98
0.99
1.00
General
Test results shall be submitted for mechanical properties of all pressurecontaining components or from the same type of material, manufactured
using the same procedures and heat treatment, at a frequency of one set
of tests per heat. Where the Manufacturer is other than the Vendor name
appearing on the mill test certificate, the name of the Manufacturer and
date that the component was formed shall be included in the remarks.
6.2
Tensile Tests
The tensile properties of each pressure-containing part in the valve shall
be in accordance with the applicable material standard or specification.
HYDROSTATIC TESTING
Hydrostatic testing shall be in accordance with Kinder Morgan Canada Inc.
Standard MP4301, Valve Test Procedure. Prior to testing, a visual examination
shall be performed by the valve supplier of all castings of pressure containing
components to assure conformance with MSS-SP-55. Castings containing repair
welding that was made to correct hydrostatic test defects shall be stress relieved
or heat treated after welding.
Revision 0
April 2007
Page 9 of 9
8.0
(1)
Heat or product analysis for all elements given in Section 5.0 and
other intentionally added elements;
(1)
(1)
If information is unavailable two weeks after the order date, it shall be provided at the earliest
possible date.
SHEET
REV
VALVE
TAG #(s)
PROJECT
TITLE
End Configuration
2000
3000
Threaded
Additional Requirements
Yes
No
SHEET
REV
VALVE
TAG #(s)
PROJECT
TITLE
2000
3000
MP4301
Top Entry
End Entry
No
Additional Requirements
Yes
No
SHEET
REV
VALVE
TAG #(s)
PROJECT
TITLE
2000
3000
Threaded
Additional Requirements
Yes
No
Revision 0
Page 1 of 12
TABLE OF CONTENTS
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
SCOPE ................................................................................................................. 3
REFERENCED PUBLICATIONS.......................................................................... 3
DEFINITIONS ....................................................................................................... 4
3.1
Ambient Temperature ................................................................................ 4
3.2
Cold Bending ............................................................................................. 4
3.3
Hot Bending ............................................................................................... 4
3.4
Main Line Piping ........................................................................................ 4
3.5
NPS ........................................................................................................... 4
3.6
Pipeline ...................................................................................................... 4
3.7
Station Piping ............................................................................................. 4
WELDING ............................................................................................................. 5
4.1
Longitudinal Weld Seams .......................................................................... 5
4.2
Weld Spacing ............................................................................................. 5
4.3
Mitred Joints .............................................................................................. 5
4.4
Welded Valves ........................................................................................... 5
BRANCH CONNECTIONS ................................................................................... 6
5.1
General ...................................................................................................... 6
5.2
Branch Piping ............................................................................................ 6
5.3
Reinforcement Requirements .................................................................... 6
5.4
Inspection .................................................................................................. 6
FLANGES AND FITTINGS ................................................................................... 7
Slip-on Flanges .......................................................................................... 7
6.1
6.2
Flange Alignment ....................................................................................... 7
6.3
Threaded and Socket-Welding Fittings ...................................................... 7
BENDS MADE FROM PIPE ................................................................................. 8
7.1
Minimum Bend Radius ............................................................................... 8
7.2
Bend Tolerances ........................................................................................ 8
ALIGNMENT......................................................................................................... 9
8.1
Piping Distortion ......................................................................................... 9
8.2
Cold Springing ........................................................................................... 9
8.3
Flanges ...................................................................................................... 9
8.4
Equipment Connection............................................................................... 9
FLANGED JOINTS ............................................................................................. 10
9.1
Flange Facings ........................................................................................ 10
9.2
Stud Length ............................................................................................. 10
Revision 0
Page 2 of 12
10.0
9.3
Gaskets.................................................................................................... 10
9.4
Thread Compound ................................................................................... 10
9.5
Bolting ...................................................................................................... 11
PIPE SURFACE DEFECTS................................................................................ 12
10.1 Pipe Manufacturing Defects ..................................................................... 12
10.2 Dents ....................................................................................................... 12
10.3 Gouges and Grooves ............................................................................... 12
10.4 Arc Burns ................................................................................................. 12
10.5 Minimum Repair Section .......................................................................... 12
Revision 0
Page 3 of 12
SCOPE
This standard covers mandatory requirements governing the fabrication and
assembly of piping systems. This a supplementary standard, and unless
otherwise specified, all other aspects of piping fabrication not covered by this
standard shall be in accordance with Kinder Morgan Canada Inc. Standards
MP3110, Station Piping Fabrication or MP3120, Pipeline Construction. This
standard is limited to systems transporting liquid hydrocarbons including: crude oil,
condensate, and liquid petroleum products. This standard excludes the joining of
piping and components for Highly Volatile Liquids.
All fabrication shall be completed in accordance with Canadian Standards
Association CAN/CSA Z662 standard, Oil And Gas Pipeline Systems. This
standard contains requirements that are in addition to CSA Z662.
2.0
REFERENCED PUBLICATIONS
Some referenced publications are supplemented or qualified, or both, by specific
requirements in this standard; referenced publications should therefore be applied
only in the context of this standard.
Kinder Morgan Canada Inc. Standards
MP2217
Induction Bending
MP3110
MP3120
Pipeline Construction
MP3901
Joining Program
Revision 0
Page 4 of 12
DEFINITIONS
3.1
Ambient Temperature
The temperature of the surrounding medium, usually used to refer to the
temperature of the air in which a structure is situated or a device operates.
3.2
Cold Bending
Bending of ferritic steels at a temperature below the transformation range.
3.3
Hot Bending
Bending of ferritic steels above the transformation range, but within a
temperature range consistent with the material and the intended service.
3.4
3.5
NPS
NPS means nominal pipe size; the NPS system of size designation is
contained in Standards prepared by the American Society of Mechanical
Engineers.
3.6
Pipeline
A line for the transmission of natural gas including branches, extensions and
attached appurtenances shall jointly or singly be referred to as the pipeline.
3.7
Station Piping
Any piping after the first valve off the mainline and before the last valve into
the mainline at a station.
Revision 0
Page 5 of 12
WELDING
Welding shall be performed by qualified welders in accordance qualified welding
procedure specifications, CSA Z662 and Kinder Morgan Canada Inc. Standard
MP3901, Joining Program.
4.1
4.2
Weld Spacing
Unless otherwise required by the piping design, the minimum pipe length
used in pipeline construction shall be 2 m and in no case shall the distance
between any two adjacent welds be less than 1 m.
4.3
Mitred Joints
Mitred joints are not permitted. Deflections of up to 2.0N caused by
misalignment are not considered to be mitred joints.
4.4
Welded Valves
Any valve trim that may be damaged during welding operations shall be
removed. The valve will be properly reassembled after the valve body has
sufficiently cooled.
Revision 0
Page 6 of 12
BRANCH CONNECTIONS
5.1
General
For "stub-in" branch connections, the hole cut for the branch shall equal the
inside diameter of the branch pipe. The material removed to create the hole
(coupon) shall be removed from the pipe. Branch connections shall be
directly joined to the carrier pipe with full penetration welds.
5.2
Branch Piping
When reinforced branch connections are used, the branch piping shall be
made from XS pipe. As a minimum, the XS pipe stub shall extend from the
run pipe to 150 mm past the re-pad or saddle outlet before any reduction in
wall thickness. Pad-type reinforcement shall be in accordance with the
requirements of CSA Z662.
5.3
Reinforcement Requirements
A vent hole shall be provided at the side of any pad, and not the crotch, to
reveal leakage and allow venting during welding and heat treatment. The
vent hole shall be plugged with a non-pressure retaining plug.
5.4
Inspection
The pressure containing weld shall be visually and non-destructively
examined prior to the installation of the re-pad. All branch connections to
headers NPS 16 and larger shall be visually inspected both internally and
externally.
Revision 0
Page 7 of 12
Slip-on Flanges
Raised face, weld neck flanges should be used for permanent piping.
Unless otherwise specified, the use of slip-on flanges is prohibited. If slip-on
flanges are specified, they shall be double welded (welded on the inside and
outside diameter). The slip-on flange face shall be positioned 3 mm plus the
nominal wall thickness of the pipe, past the end of the pipe. The welds shall
be applied so the flange face is free of weld spatter and does not require
refacing.
6.2
Flange Alignment
Flanges shall be installed so that the bolt holes straddle the vertical
centerline of the pipe and the flange face is perpendicular to the longitudinal
pipe centre-line.
6.3
Revision 0
Page 8 of 12
7.2
6-8
10
20
10
Bend Tolerances
Bends shall be made in such a manner as to preserve the cross- sectional
shape of the pipe and be free from buckling, cracks, or other damage. At
any point along the bend the pipe outside diameter shall not be reduced by
more than 2.5%. Induction bends shall be in accordance with Kinder
Morgan Canada Inc.. Standard MP2217, Induction Bending.
Revision 0
Page 9 of 12
ALIGNMENT
8.1
Piping Distortion
Any heating or distortion of piping or equipment to bring it into alignment for
joint assembly is prohibited.
8.2
Cold Springing
"Cold Springing" of piping shall not be permitted. Heating shall not be used
to close the gap to eliminate cold spring. Piping shall be installed in a stressfree condition.
8.3
Flanges
Prior to bolt-up, flange faces shall have the following shall have the following
minimum alignment:
8.3.1
with raised faces touching at one edge, the largest gap between the
faces at any point shall not exceed that listed in Table 5.1.3.A; and
8.3.2
8.4
Pipe
Size
(NPS)
PN 20
PN 50
PN 100
2.0
2.0
2.0
2.0
2.5
2.5
Flange Rating
2.5
3.0
3.0
10
3.0
3.5
3.5
12
3.5
4.0
4.0
14
4.0
4.0
4.5
16
4.5
4.5
5.0
18
5.0
5.0
5.5
20
5.5
5.5
6.0
24
6.5
6.5
6.5
30
7.5
8.0
8.0
Equipment Connection
Where pipe is connected to rotating equipment, the equipment shall be
aligned prior to connection of the piping. After connection of the piping, the
coupling alignment shall remain within 0.05 mm (0.002") TIR.
Revision 0
Page 10 of 12
FLANGED JOINTS
9.1
Flange Facings
Any damage to the gasket seating surface which would prevent gasket
seating shall be repaired, or the flange shall be replaced.
9.2
Stud Length
Studs shall extend completely through their nuts by at least two (2) threads.
Washers or other packing shall not be employed to use up excessive length
of flange bolts.
9.3
Gaskets
For flanged piping, new gaskets shall be used for every assembly operation
unless such assembly is intended solely for fit-up. Gaskets shall be new,
clean and free from foreign matter. No more than one gasket shall be used
between faces when assembling a flanged joint and no sealing compounds
shall be used with the gasket.
9.4
Thread Compound
All bolts and studs shall be coated with AJet Lube TF-15" thread sealing
compound (or approved equal) prior to being made up with nuts.
Revision 0
Page 11 of 12
Bolting
Flange faces and gaskets shall be cleaned immediately prior to bolt-up.
Flange studs shall be tightened evenly in an alternating pattern, to achieve a
uniform gasket seating pressure. Misalignment shall not be corrected by
force or uneven bolt tightening. Only new studs shall be used. All bolts and
studs shall be tightened to the torque shown in Table 9.5.A as a minimum.
TABLE 9.5.A -- RECOMMENDED TORQUES FOR B7 STUDS
Nominal Stud Size
Threads
per inch
Torque
(mm)
(inches)
(ft. lbs.)
12.7
13
50 - 70
15.87
11
100 - 145
19.05
10
170 - 240
22.22
260 - 375
25.4
400 - 570
28.57
590 - 840
31.75
875 - 1250
38.1
1290 - 1850
41.27
1750 - 2500
44.45
2310 - 3300
47.62
2870 - 4100
50.8
3430 - 4900
Revision 0
Page 12 of 12
b)
c)
Revision 0
Page 1 of 11
TABLE OF CONTENTS
1.0
2.0
3.0
4.0
5.0
6.0
7.0
SCOPE ................................................................................................................. 3
REFERENCED PUBLICATIONS.......................................................................... 3
DEFINITIONS ....................................................................................................... 4
3.1
Ambient Temperature ................................................................................ 4
3.2
Main Line Piping ........................................................................................ 4
3.3
NPS ........................................................................................................... 4
3.4
Station Piping ............................................................................................. 4
3.5
WHMIS ...................................................................................................... 4
MATERIALS ......................................................................................................... 5
4.1
General ...................................................................................................... 5
4.2
External Piping ........................................................................................... 5
4.3
Internal Piping ............................................................................................ 5
4.4
Buried Piping ............................................................................................. 5
4.5
Vessels and Tanks .................................................................................... 5
4.6
Valves and Equipment ............................................................................... 6
4.7
Insulation Cladding .................................................................................... 6
ACCESSORIES FOR INSULATION SYSTEMS................................................... 7
5.1
General ...................................................................................................... 7
5.2
Tie Wire ..................................................................................................... 7
5.3
Fasteners ................................................................................................... 7
5.4
Bands and Clips ......................................................................................... 7
INSULATION APPLICATION ............................................................................... 8
6.1
General ...................................................................................................... 8
6.2
Surfaces Not Insulated............................................................................... 8
6.3
Surface Preparation ................................................................................... 8
6.4
Weather Protection .................................................................................... 8
6.5
Heat Tracing .............................................................................................. 8
6.6
Installation.................................................................................................. 8
6.7
Banding...................................................................................................... 9
CLADDING APPLICATION ................................................................................ 10
7.1
Banding.................................................................................................... 10
7.2
Side Lap................................................................................................... 10
7.3
Joints ....................................................................................................... 10
7.4
Cladding Overlap ..................................................................................... 10
7.5
Flanges .................................................................................................... 10
Revision 0
Page 2 of 11
Tracing ..................................................................................................... 11
Revision 0
Page 3 of 11
1.0 SCOPE
This standard covers mandatory requirements governing the installation of
Insulation on piping, vessels and equipment. This a supplementary standard, and
unless otherwise specified, all other aspects of piping fabrication not covered by
this standard shall be in accordance with Kinder Morgan Canada Inc. Standard
MP3110, Station Piping Fabrication.
This standard is limited to systems
transporting liquid hydrocarbons including: crude oil, condensate and liquid
petroleum products.
All fabrication shall be completed in accordance with Canadian Standards
Association standard CAN/CSA Z662, Oil and Gas Pipeline Systems. This
standard contains requirements that are in addition to CSA Z662.
Revision 0
Page 4 of 11
3.0 DEFINITIONS
3.1
Ambient Temperature
The temperature of the surrounding medium, usually used to refer to the
temperature of the air in which a structure is situated or a device operates.
3.2
3.3
NPS
NPS means nominal pipe size; the NPS system of size designation is
contained in Standards prepared by the American Society of Mechanical
Engineers.
3.4
Station Piping
Any piping after the first valve off the mainline and before the last valve into
the mainline at a station.
3.5
WHMIS
WHMIS means workplace hazardous materials information system.
Revision 0
Page 5 of 11
4.0 MATERIALS
4.1
General
Insulation materials, including insulating cement and insulation covering,
shall not contain asbestos. All insulation application shall be carried out by
tradesmen skilled in the application of insulation. Approved insulation
materials are listed in Table 4.1.A.
TABLE 4.1.A -- INSULATION MATERIALS
Material
4.2
Material
Specification
Application
Mineral Wool
ASTM C547
ASTM C592
ASTM C547
Calcium Silicate
ASTM C533
Cellular Glass
ASTM C552
External Piping
Piping shall generally be insulated with preformed mineral wool or spun glass
fibre with the following exceptions:
4.3
a)
all piping below 2150 mm above grade shall be insulated with calcium
silicate (where the pipe goes underground, the calcium silicate shall stop
300 mm above grade per 10.2.3);
b)
Internal Piping
Piping located within enclosed buildings shall be insulated with preformed
mineral wool or spun glass fibre unless otherwise specified.
4.4
Buried Piping
Unless otherwise specified, buried piping shall be insulated with cellular
glass foam from 300 mm above grade to a depth of 1 m below grade. Piping
extending below this depth shall not require insulation.
4.5
Revision 0
Page 6 of 11
4.7
Insulation Cladding
Insulation cladding shall conform to requirements of Table 4.7.A.
TABLE 4.7.A -- INSULATION CLADDING
Material
Material Specification
Aluminum
Stainless Steel
Minimum Thickness
(mm)
(inch)
4.4
0.016
Revision 0
Page 7 of 11
General
Components of dissimilar metals subject to galvanic corrosion shall not be
brought into contact with each other. Unless otherwise specified, plated or
clad accessories shall not be used.
5.2
Tie Wire
Tie wire for the securing of insulation only shall be galvanized steel, stainless
steel or copper. The minimum diameter shall be 1.57 mm (0.062"). Copper
wire shall be soft drawn, galvanized and stainless steel wire shall be
annealed.
5.3
Fasteners
Sheet metal screws and rivets shall be stainless steel or aluminium. Screws
shall be self-tapping, #8 by 20 mm (") long.
5.4
Size
(mm)
(inch)
10 x 0.4
x 0.015
12.7 x 0.4
x 0.015
20 x 0.5
x 0.020
Revision 0
Page 8 of 11
General
Insulation shall not be applied until coating, heat tracing and pressure testing
has been completed. If it is necessary to insulate a system before it is
tested, all welds, connections and flanges shall be left un-insulated until the
completion of pressure testing.
6.2
6.3
equipment nozzles;
expansion joints;
nameplates (unless a duplicate is applied to the cladding);
pipe flanges, except on heat traced lines; and
safety valves.
Surface Preparation
Piping and equipment surfaces shall be prepared and primed in accordance
with Kinder Morgan Canada Inc. Standard GC3101, External Coating of
Piping, Components and Structural Steel. Insulated piping, with the
exception of any exposed surfaces such as flanges or nozzles, shall not be
top coated.
6.4
Weather Protection
All insulation shall be protected from moisture and weather before and during
application. If applied insulation should get wet before it is sealed, it shall be
thoroughly dried before it is sealed.
6.5
Heat Tracing
The insulation for heat traced lines shall be one pipe size larger to
accommodate the tracer.
6.6
Installation
Preformed insulation shall be installed as shown in Figure 6.6.A. All
insulation joints shall be butted together. Transverse joints shall be
staggered and all gaps in calcium silicate cellular glass foam insulations shall
be filled with insulating cement.
Revision 0
Page 9 of 11
Banding
Insulation shall be secured with bands or wire ties every 600 mm. No less
than two ties shall be used to secure a single piece of insulation on straight
runs of pipe.
FIGURE 6.6.A -- PIPE INSULATION
Revision 0
Page 10 of 11
Banding
Install cladding snugly and secure with the specified bands on 300 mm
centers. Lap all joints to the weather as shown in Figure 7.4.A. Tie wires
shall not be used in place or bands on external cladding.
7.2
Side Lap
The side lap shall be secured with screws at 100 mm centers.
7.3
Joints
Covers at the end of the run shall be banded. Screws shall not be used to
secure end covers. To allow for thermal expansion, screws shall not be used
at the ends of cladding sections.
7.4
Cladding Overlap
The laps in cladding shall be position to shed water as shown in Figure 7.4.A.
The extend of the overlap shall be as given in Table 7.4.A.
TABLE 7.4.A -- Cladding Lap
7.5
Piping Size
Minimum Lap
NPS 24
50 mm
> NPS 24
75 mm
Flanges
End bevels shall be lapped against the weather and secured with bands.
Sufficient clearance (A), as shown in Figure 7.5.A, shall be maintained
between the end of the flange and the end of the insulation to allow for the
removal of studs and nuts. Where specified, flanges shall be insulated with
removable boxes or insulated fabric covers.
Revision 0
Page 11 of 11
7.6
Tracing
The insulation shall be sealed with silicone caulking at the beginning and end
and at the entry to instrument housings.
Revision 1
Page 1 of 16
TABLE OF CONTENTS
1.0
2.0
3.0
4.0
SCOPE ................................................................................................................. 3
REFERENCED PUBLICATIONS.......................................................................... 3
DEFINITIONS ....................................................................................................... 4
3.1
Ambient Temperature ................................................................................ 4
3.2
Main Line Piping ........................................................................................ 4
3.3
MSDS ........................................................................................................ 4
3.4
NPS ........................................................................................................... 4
3.5
Station Piping ............................................................................................. 4
3.6
WHMIS ...................................................................................................... 4
3.7
Cold Bending ............................................................................................. 4
3.8
Hot Bending ............................................................................................... 4
PIPE FABRICATION ............................................................................................ 5
4.1
Dimensional Tolerances ............................................................................ 5
4.1.1
4.1.2
4.1.3
4.1.4
4.1.5
4.2
4.3
4.4
Welding ...................................................................................................... 7
Piping Fabrication and Assembly ............................................................... 7
Material Handling and Shipment ................................................................ 7
4.4.1
4.4.2
4.4.3
5.0
6.0
6.2
Bedding ..................................................................................................... 9
Ditch Design .............................................................................................. 9
De-Watering .............................................................................................. 9
Ditch Spoil ................................................................................................. 9
General ...................................................................................................... 9
Bending Equipment ................................................................................... 9
Revision 1
Page 2 of 16
6.3
6.4
8.0
Backfilling................................................................................................. 10
6.4.1
6.4.2
6.4.3
6.4.4
7.0
Tolerances ............................................................................................... 10
Circumferential Welds ............................................................................. 10
Longitudinal Weld Seams ........................................................................ 10
Coating Protection ................................................................................... 10
PIPE COATINGS................................................................................................ 13
7.1
Exposed Piping ........................................................................................ 13
7.2
Buried Piping ........................................................................................... 13
7.3
Girth Weld Coating (buried piping) ........................................................... 13
7.4
Piping Insulation ...................................................................................... 13
QUALITY CONTROL .......................................................................................... 14
8.1
Quality Control Program .......................................................................... 14
8.2
Project Quality Control Procedure ........................................................... 14
8.2.1
8.2.2
8.3
General .................................................................................................... 14
Procedure Elements ................................................................................ 14
General .................................................................................................... 15
Record Elements ..................................................................................... 15
Material and Weld Location Maps ........................................................... 16
Revision 1
Page 3 of 16
1.0 SCOPE
This standard covers mandatory requirements governing the fabrication of station
piping systems.
This standard is limited to systems transporting liquid
hydrocarbons including: crude oil, condensate and liquid petroleum products. This
standard is further limited to the joining of piping and components for Category I,
Low Vapour pressure piping systems.
All fabrication shall be completed in accordance with Canadian Standards
Association standard CAN/CSA Z662, Oil and Gas Pipeline Systems. This
standard contains requirements that are in addition to CSA Z662.
This standard does not cover the fabrication of Main Line piping systems. This
standard also excludes the design, layout and material selection of piping
systems.
Revision 1
Page 4 of 16
3.0 DEFINITIONS
3.1
Ambient Temperature
The temperature of the surrounding medium, usually used to refer to the
temperature of the air in which a structure is situated or a device operates.
3.2
3.3
MSDS
MSDS means material safety data sheet.
3.4
NPS
NPS means nominal pipe size; the NPS system of size designation is
contained in Standards prepared by the American Society of Mechanical
Engineers.
3.5
Station Piping
Any piping after the first valve off the mainline and before the last valve into
the mainline at a station.
3.6
WHMIS
WHMIS means workplace hazardous materials information system.
3.7
Cold Bending
Bending of ferritic steels at a temperature below the transformation range.
3.8
Hot Bending
Bending of ferritic steels above the transformation range, but within a
temperature range consistent with the material and the intended service.
Revision 1
Page 5 of 16
Dimensional Tolerances
4.1.1
Linear Tolerances
The tolerances on linear dimensions shall apply to the face to face,
face to end, and end to end measurements of fabricated straight pipe
and headers; center to end or center to face of nozzles and other
attachments; or center to face of bends; as illustrated by dimension A
in Figure 4.1.A. Linear tolerances shall be as indicated in Table
4.1.1.A.
TABLE 4.1.1.A -- LINEAR TOLERANCES
4.1.2
Pipe Size
(NPS)
Tolerance
(mm)
12
3.0
12 to 24
5.0
> 24
6.0
Angular Misalignment
As illustrated by dimension B in Figure 4.1.A, end preparations for
welding shall not deviate from true by more 3.0 mm across the land.
As illustrated by dimension C in Figure 4.1.A, the inclination of flange
faces shall not deviate from true across any diameter by more than
4.0 mm per meter or 1.0 mm whichever is greater.
4.1.3
Bend Radius
Bend Radii shall be within 1% of the specified value.
4.1.4
Bend Angle
The bend included angle shall be within 1.0 degrees of the
specified value.
4.1.5
Out of Plane
Out of plane measurements shall not exceed 6.0 mm as illustrated by
dimension D in Figure 4.1.A.
Revision 1
Page 6 of 16
Revision 1
Page 7 of 16
Welding
Welding shall be performed by qualified welders in accordance Kinder
Morgan Canada Inc. Standard MP3901, Joining Program.
4.3
4.4
Internal Cleaning
All pipe, fittings, valves and other components shall be clean, dry and
free of foreign matter prior to installation.
4.4.2
Material Handling
Pipe and fittings shall be handled using wide canvas, leather, nylon
or padded slings. Use of bare cables, chains, hooks, pipe clamps or
other similar equipment will not be allowed.
4.4.3
Revision 1
Page 8 of 16
Examinations
All nondestructive examinations (visual, radiographic, liquid penetrant and
magnetic particle) shall be in accordance with Kinder Morgan Canada Inc.
Standard MP3901, Joining Program.
5.2
Hydrostatic Testing
All pressure piping and atmospheric drain systems shall be hydrostatically
tested in accordance with Kinder Morgan Canada Inc. Standard MP4111,
Station Hydrostatic Test Procedure. Where pre-tested assemblies are
installed, the numbers of "tie-in" welds not subjected to a pressure test shall
be minimized to the extent possible.
Revision 1
Page 9 of 16
Excavation
6.1.1
Bedding
The bottom of the ditch shall be free from rocks, clods and debris at
the time the pipe is lowered in and so graded that the pipe will have a
uniform bearing on the bottom of the ditch. Jagged, sharp and strong
roots or other projections must be removed from the ditch to prevent
damage to the pipe or protective coating.
6.1.2
Ditch Design
The sides of the ditch shall be sloped to comply with Occupational
Health and Safety requirements and to prevent sloughing. Additional
depth of bury will be required adjacent to sharp changes in ground
profile in order to comply with minimum radius of curvature for the
pipe material specified.
6.1.3
De-Watering
Excavations shall be kept free of water as required. Ditch water shall
not be permitted to enter any piping. Discharge from dewatering
equipment shall be controlled to prevent damage.
6.1.4
Ditch Spoil
If space adjacent to the ditch is insufficient for the spoil, it shall be
removed, stockpiled and returned for backfill or alternatively, wasted
in a manner approved by Kinder Morgan Canada Inc. and replaced
by appropriate backfill material.
6.2
Field Bending
6.2.1
General
The Contractor shall make all field bends necessary for piping
construction. Sags and overbends shall conform to the profile of the
bottom of the ditch. Side bends shall fit the centerline of the ditch.
6.2.2
Bending Equipment
All field bends shall be made by the cold bending method using
Kinder Morgan Canada Inc. approved bending equipment. An
internal bending mandrel shall be used.
Revision 1
Page 10 of 16
Tolerances
Bends shall be free from buckling, cracks and other evidence of
mechanical damage. All bends shall meet the requirements of CSA
Z662.
6.2.4
Circumferential Welds
Circumferential welds shall not be stressed during bending. A
tangent length of at least 1.0 m shall be maintained between any
circumferential weld and the start of any cold bend.
6.2.5
6.2.6
Coating Protection
Padded shoes and padded slings shall be used when bending precoated pipe to prevent damage to the coating.
6.3
Lowering in Pipe
6.3.1
6.3.2
Pipe Bedding
When all rocks, skids, clods and debris have been removed, the
bottom of the ditch shall be graded to give support to the pipe
throughout its entire length. Where necessary Contractor shall install
bottom padding, the bottom layers of sack breakers, foam or
sandbag pillows.
6.4
Backfilling
6.4.1
Revision 1
Page 11 of 16
Padding Material
With the exception of bored sections or piping installed in
compressible soils all buried piping should be backfilled in a manner
consistent with the cross-section illustrated in Figure 6.4.2.A. The
bedding material should be sand or fine sand and gravel. If the
native soils excavated for the trench are unsuitable or cannot
otherwise be screened, sand bedding shall be imported from an
appropriate borrow site. Rock or large gravel shall not be backfilled
directly on the pipe.
FIGURE 6.4.2.A -- PLACEMENT OF PIPE BEDDING MATERIAL
6.4.3
6.4.4
Revision 1
Page 12 of 16
Revision 1
Page 13 of 16
Exposed Piping
Unless otherwise specified, all external surfaces of exposed, carbon steel
piping shall be coated in accordance with Kinder Morgan Canada Inc.
Standard GC3101, External Coating of Pipe, Components and Structural
Steel.
7.2
Buried Piping
Unless otherwise specified, all external surfaces of buried, carbon steel
piping shall be coated with one of the following systems in Table 7.2.A.
TABLE 7.2.A -- APPROVED COATING SYSTEMS FOR BURIED PIPING
7.3
TM System
Description
Standard
C1
C2
CSA Z245.20-M92
C3
7.4
Piping Insulation
Unless otherwise specified, carbon steel piping, shall be insulated in
accordance with Kinder Morgan Canada Inc. Standard MP3102, Piping
Insulation Requirements.
Revision 1
Page 14 of 16
8.2
General
The contractor shall create and submit to Kinder Morgan Canada Inc.
five (5) copies of a Project Quality Control Procedure specific to
the requirements of the work, two (2) weeks after award of the
contract.
8.2.2
Procedure Elements
The Project Quality Control Procedure shall include as a minimum:
a)
b)
c)
d)
e)
Revision 1
Page 15 of 16
8.3
General
The contractor shall create a Project Quality Control Record at the
beginning of construction. The Contractor shall continuously update
the Project Quality Control Record and make it readily available for
review by Kinder Morgan Canada Inc. The contractor shall submit
three (3) copies of the Project Quality Control Record not less than
two (2) weeks after the date of substantial performance.
8.3.2
Record Elements
The Project Quality Control Record shall include as a minimum:
a)
contractor and
certifications;
subcontractor
b)
contractor and
certifications;
c)
d)
e)
f)
g)
h)
i)
j)
k)
subcontractor
structural
piping
fabrication
fabrication
CWB
ASME
Revision 1
Page 16 of 16
b)
c)
d)
e)
f)
g)
Revision 0
Page 1 of 3
INTRODUCTION
MP3110 is a compilation of requirements that have been derived from different
sources. Where applicable, this appendix lists the reference from which the
clause was developed.
MP3110 REFERENCE INDEX
Clause
Title
CSA Z662
Other
Filler Metal
4.1.2
4.1.3
4.1.4
Backing Rings
7.2.4.2.1
7.2.4.2.2.2
Joint Design
7.2.7.6
4.2.2
Joint Preparation
7.2.7.1
4.2.3
Alignment
7.2.7.2
4.2.4
Grounding
7.2.7.3
4.2.5
Line-up Clamps
7.2.7.4
4.2.6
7.2.7.7
7.2.7.4
4.3.2
Cleaning
7.2.7.9
4.3.3
Preheat
7.2.7.15.2
4.3.4
Interrupted Welding
4.3.5
7.2.7.10.2.1
4.3.6
Weld Reinforcement
7.2.7.10.2.2
4.3.7
Controlled Cooling
7.2.7.15.4
4.4.1
Preparation
7.2.10.3.1
4.4.2
Preheat
7.2.10.3.2
4.4.3
Repair Welding
4.4.4
7.2.10.6
4.4.5
7.2.10.5
B31.3 330.2.4
7.2.9
Revision 0
Page 2 of 3
Title
CSA Z662
Other
General
4.6.2
7.2.1.4
B31.3 328.2.2
General
7.2.6.1.1
4.7.2
Butt Welds
7.2.6.1.3
.7.3
Fillet Welds
7.2.6.1.3
4.7.4
Pre-Qualification of Welders
B31.3 328.2.3
Examination
OPR 22
5.2
Hydrostatic Testing
5.3
OPR 21
5.4
OPR 21
5.5
OPR 22, 44
6.0 FABRICATION
6.1
Dimensional Tolerances
6.2
Welded Connections
6.3
Branch Connections
6.4
6.5
PFI ES-3
6.2.3
B31.3 328.5.4
6.2.3
7.0 ASSEMBLY
7.1
Alignment
B31.3 335.1
7.2
Flanged Joints
B31.3 335.2
7.3
7.4
7.5
6.3
6.2.2
Excavation
6.2.6
8.2
Field Bending
6.2.3
8.3
Lowering in Pipe
6.2.6
8.4
Backfilling
6.2.7
Revision 0
Page 3 of 3
Title
CSA Z662
9.1
Exposed Piping
6.2.5
9.2
Buried Piping
5.3.9
9.3
6.2.5
9.4
Repairs
Other
6.5
10.0 INSULATION
10.1
General
10.2
Insulation
10.3
Insulation Cladding
10.4
10.5
Insulation Application
10.6
Cladding Application
OPR 19
11.2
5.8
11.3
5.8
OPR
PFI
B31.3
Revision 2
February 4, 2010
Page 2 of 22
TABLE OF CONTENTS
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
SCOPE ................................................................................................................. 3
INTRODUCTION .................................................................................................. 3
ALTERNATE ALLOWABLE FLANGE ASSEMBLY METHOD .............................. 3
REFERENCED PUBLICATIONS.......................................................................... 4
DEFINITIONS ....................................................................................................... 4
DOCUMENTATION .............................................................................................. 5
BEST PRACTICES ............................................................................................... 6
FLANGE ALIGNMENT ......................................................................................... 7
FLANGE COMPONENTS .................................................................................... 8
BOLTING ............................................................................................................ 12
TORQUE INCREMENT ...................................................................................... 13
BOLT TIGHTENING SEQUENCE ...................................................................... 14
APPENDICE
Appendix A-FLANGE TRACKING SHEET.15
Appendix B-CONTRACTOR QUALIFICATION GUIDE................................19
Appendix C-SPIRAL WOUND GASKET SELECTION..................................22
Revision 2
February 4, 2010
Page 3 of 22
SCOPE
This standard covers mandatory requirements governing assembly of raised-face
flanges. This is a supplementary standard, and unless otherwise specified, all
other aspects of piping fabrication, fastener/gasket selection and assembly not
covered by this standard shall be in accordance with the following Kinder Morgan
Canada Inc. Standards;
INTRODUCTION
A bolted flange joint assembly (BFJA) is a complex mechanical device. Although
static by design, BFJAs that provide many years of leak-free service are the result
of correct assembly and torquing practices. The guidelines outlined in this
document address the correct assembly techniques, methods and practices
essential to achieving consistent leak-free performance of otherwise properly
designed and constructed BFJAs.
3.0
The Flange Tracking Record will contain in addition to all other required
information the following:
Revision 2
February 4, 2010
Page 4 of 22
4.0
REFERENCED PUBLICATIONS
ASME PCC-1---2000 Guidelines for Pressure Boundary Bolted Flange Joint
Assembly
ASME B16.5-------Pipe Flanges and Flanged Fittings
ASME B16.20-----Metallic gaskets for Pipe Flanges
ASME B16.21-----Non-metallic Flat Gaskets for Pipe Flanges
KMC MP1110A---Station and Terminal Piping and Design
5.0
DEFINITIONS
Bolted Flange Joint Assembly (BFJA): two pipe flanges of the same ANSI class
and size which when joined with fasteners and sharing a single common gasket
provide a leak-free jointed assembly.
Lubricant: a nickel-based anti-seize paste. Copper-based not permitted.
Gasket: flat, ring shaped, pliable component which when properly compressed
between the flange raised-face sealing surfaces creates the leak-free joint.
Torque: The turning/twisting motion of the fastener(s) and/or more usually the
nut(s).
Fastener: the combination of stud or bolt and nut(s) and at times a hardened
washer(s) utilized in joining a flanged assembly.
Target-torque: the final design torque applied to each fastener for a given stud
size
Flange Alignment: The orientation of the two flange faces to be joined in relation
to each other and the design plane.
Bolt Tightening Sequences: a predetermined and numbered cross-pattern
tightening sequence of the flange fasteners utilized to ensure even and consistent
gasket seating pressure.
Hardened Washer: A washer that is through-hardened rather than surfacehardened.
Revision 2
February 4, 2010
Page 5 of 22
Working Surface: The gasket contact surface of both joint flanges as well as the
nut bearing surface on the back side of each flange where the fasteners nut
contacts.
Nut bearing face: The smooth working side of the nut which has no identification
markings to hinder the torquing process.
Hydraulic Torque wrench: An electrically or pneumatically driven hydraulic pump
with a variable pressure output attached via high-pressure flexible hoses to one,
two or four small hydraulic piston-driven head(s) that convert hydraulic energy into
measurable rotating mechanical energy.
Torque Increment: Incrementally increasing the torque of each successive bolt
tightening sequence to a greater torque value with the final sequence at 100% of
Target-torque.
Flange tracking records: Documentation which records and identifies any and all
relevant information pertaining to the flange assembly to assist in tracking and
quality assurance.
Refer to Appendix A for Flange Tracking sheet.
Expedient Assembly practices: Requirements for completing flanged
connections from initial assembly to final torquing in a continuous uninterrupted
process in order to avoid contamination and degradation of gasket sealing
surfaces.
Flange Rating: the pressure rating within a specified temperature range a flange
is designed to safely withstand as defined by ASME B16.5.
6.0
DOCUMENTATION
.
6.1
Contractors will submit a flange bolting procedure and inspection test plan
for approval by the responsible KMC project manager prior to undertaking
any flange work.
Refer to Appendix B for Contractor Qualification Guide.
6.2
Revision 2
February 4, 2010
Page 6 of 22
7.0
BEST PRACTICES
7.1
7.2
7.3
7.4
When utilizing an insulating flange kit with only one fibrous washer,
tightening of the fastener nut shall be performed opposite the side that
has the fibrous insulating washer. For kits with fibrous washer on both
sides, smaller incremental torque steps should be observed to reach the
recommended torque value as recommended by the kit manufacturer.
Isolation kits will be type F Linebacker style for raised face flanges with
Glass Reinforced Epoxy retainer material (G.R.E or NEMA G-10) and
Viton Sealing element. Glass Reinforced Epoxy Single Washers and
Sleeves.
Revision 2
February 4, 2010
Page 7 of 22
8.0
7.5
7.6
FLANGE ALIGNMENT
8.1
Prior to bolt-up, flange faces shall have the following maximum alignment
tolerances:
with raised faces separated by one gasket width at one edge, the
largest gap between the faces at any point shall not exceed that
listed in Table 8.3.A plus one gasket thickness if the faces are
separated by one gasket thickness at their closest point; and
Pipe
Size
(NPS)
PN 20
(150#)
PN 50
(300#)
PN 100
(600#)
2.0
2.0
2.0
2.0
2.5
2.5
2.5
3.0
3.0
10
3.0
3.5
3.5
12
3.5
4.0
4.0
14
4.0
4.0
4.5
16
4.5
4.5
5.0
18
5.0
5.0
5.5
20
5.5
5.5
6.0
24
6.5
6.5
6.5
30
7.5
8.0
8.0
Revision 2
February 4, 2010
Page 8 of 22
8.2
Piping Distortion
8.3
Flanges shall be installed so that the bolt holes straddle the vertical centerline
of the pipe and the flange face is perpendicular to the longitudinal pipe centreline.
8.4
Equipment Connection
9.0
FLANGE COMPONENTS
9.1
Flange Specifications
9.2
Flange Facings
Flange faces shall be inspected prior to assembly. Any damage to the gasket
sealing surface shall be repaired, or the flange shall be replaced.
Revision 2
February 4, 2010
Page 9 of 22
Flange working surface finish will be the same for both non-metallic
compressed graphite gaskets and semi-metallic spiral wound gaskets.
9.4
Stud Length
Studs shall extend completely through their nuts by at least two (2) threads.
Washers or other packing shall not be employed to use up excessive length
of flange bolts.
9.5
Nut Faces
Each nut shall be assembled onto the stud with the flat bearing face toward
the flange.
9.6
Gaskets
New gaskets shall be used for every assembly operation unless such
assembly is a temporary non-operational bolt-up intended solely for fitup. Gaskets shall be new, clean and free from foreign matter. One
gasket shall be used between faces when assembling a flanged joint
and no sealing compounds, lubricants, adhesives or any other
material shall be applied to the gasket.
Only one new gasket to be utilized per flange pair; stacking of multiple
gaskets to make-up excessive flange gap is not acceptable.
Warning:
Warning:
Newly constructed piping that has non-permanent start-upstrainers installed to protect pump internals should not be
operated more than a MAXIMUM OF TWO MINUTES at low-flow
conditions with cone-strainers installed, otherwise severe internal
damage may occur.
Revision 2
February 4, 2010
Page 10 of 22
Revision 2
February 4, 2010
Page 11 of 22
9.7
Thread Compound
All engaged external threads of the stud and internal threads of the nut to be
rotated shall be liberally coated with a nickel-based anti-seize paste prior to
assembly. Additionally, the flat nut bearing faces which bear against the
flange will be liberally coated with the same nickel anti-seize paste prior to
assembly. Approved lubricants include:
-
This anti-seize paste may be applied only to the nut and fastener on the side
of the flange which will be rotated or torqued. The nut on the opposite side
may be left un-lubricated in order that it may bite preventing additional
rotation, facilitating the speed of the torquing process.
Revision 2
February 4, 2010
Page 12 of 22
10.0 BOLTING
10.1 Bolt Numbering:
Number each bolt location 1 through N in a clockwise direction (where N
is the total number of bolts for the flange). Eg: 1,2,3,4,5,6N.
10.2 Torquing:
Flange studs shall be tightened evenly in an alternating pattern as detailed
in this Standard to achieve a uniform gasket seating pressure. Only new
studs and nuts shall be used. All bolts and studs shall be tightened to the
target torque shown in Table 9.5.A.
NOTE: THE TARGET-TORQUE VALUES EXPRESSED IN TABLE 9.5.A SHALL
APPLY TO FASTENERS UTILIZED IN BFJAS CONTAINING EITHER
COMPRESSED CARBON-FIBER GASKETS OR SPIRAL WOUND GASKETS.
Warning: Use only nickel based anti-seize paste for lubrication. Substituting other
lubricant will seriously alter target-torque value!
Threads
per inch
Torque
(mm)
(inches)
(ft. lbs.)
12.7
13
60
15.87
1/2
5/8
11
120
19.05
3/4
10
210
22.22
7/8
350
25.4
500
28.57
1-1/8
750
31.75
1-1/4
1050
34.92
1-3/8
1400
38.1
1-1/2
1800
41.27
1-5/8
2350
44.45
1-3/4
2950
47.62
1-7/8
3650
50.8
4500
63.5
2-1/2
9905
Revision 2
February 4, 2010
Page 13 of 22
Loading
Install
Align bolt holes with two non-tapered drift pins at 180 degree separation.
Hand-tighten fasteners and check flange gap around circumference for
uniformity. Document gap in the Flange Tracking sheet.
Round 1
Round 2
Round 3
Round 4
Round 5
CAUTION:
WARNING:
Round 6
Wait a minimum of 4 hours and repeat Round 5; this will restore the shortterm creep relaxation/embedment losses in the gasket and fasteners. If
the flange is subject to a subsequent test pressure higher than its rating,
round 6 should be repeated after the test is completed.
Revision 2
February 4, 2010
Page 14 of 22
# of
bolts
1-3-2-4
1-5-3-7 2-6-4-8
12
16
20
24
28
32
36
40
44
48
52
Revision 2
February 4, 2010
Page 15 of 22
# of
bolts
56
60
64
68
72
Revision 2
February 4, 2010
Page 16 of 22
APPENDIX A:
Bolted Flange Joint Assembly Tracking Sheet
Revision 2
February 4, 2010
Page 17 of 22
Studs:
Nuts:
Equip./Valve No.:
Class/Rating:
Pipe to Pump ___ Pipe to Blind ___
Other:
Used ___
Used ___
As specified on drawing or
specification?
New, clean and dry?
Yes ___
No ___
Yes ___
No ___
As specified on drawing or
specification?
Liberally coated with nickel anti-seize?
Extend 2-3 threads past full nut?
Yes ___
No ___
Yes ___
Yes ___
No ___
No ___
Yes ___
No ___
As specified on drawing or
specification?
Revision 2
February 4, 2010
Page 18 of 22
Yes ___
Yes ___
No ___
No ___
Offset ________
Gap ________
Flange Alignment:
Enter value in mm:
Angular _______
Yes ___
No ___
Yes___ No____
Reaction Head(s)
recently lubricated:
Yes___ No___
Torquing Record (Insert torque values for flange fastener size in ft-lbs):
Round 1
(30%)
Round 2
(60%)
Round 3
(80%)
Rounds 4, 5* & 6*
(100%)
Signature
Date
Revision 2
February 4, 2010
Signature
Date
Page 19 of 22
Revision 2
February 4, 2010
APPENDIX B:
Contractor Qualification Guide
Page 20 of 22
Revision 2
February 4, 2010
Page 21 of 22
Ensure that all their employees and sub-contractors hired by them are
competently trained in the assembly of Bolted Flange Joints and willing
to following the practices and procedures outlined by KMC.
Revision 2
February 4, 2010
APPENDIX C:
SPIRAL WOUND GASKET SELECTION
Page 22 of 22
Revision 2
February 4, 2010
Page 23 of 22
Inner ring, when required, is usually the same material as the winding
material. IE: 304 SS.
-The above gasket would be identified on the outer centering ring as yellow colored
(identifying the 304 SS winding material), with a grey stripe designating the graphite
filler material.
-The inner and outer centering ring material (if other than carbon steel) is identifiable by
stamped number identification.
-New construction for flanges incorporating spiral wound gaskets must be fabricated
with a gap between the flange working faces of between 3/16 to 1/4" to facilitate gasket
installation.
NOTE: For pigable piping, EXPRESS and PLATTE utilize a non-standard, special-order
spiral wound gasket with a large I.D. for than specified by ASME B16.20 and is
therefore not identified by the B16.20 marking.
Non pigable piping utilizes standard B16.20 spiral wound gaskets.
JOINING PROGRAM
MP3901, Revision 4, November 2003
Revision 4
Page 1 of 13
TABLE OF CONTENTS
1.0
2.0
3.0
4.0
SCOPE ........................................................................................................................ 3
1.1 General ............................................................................................................... 3
1.2 Format ................................................................................................................. 3
REFERENCED PUBLICATIONS ................................................................................. 4
DEFINITIONS .............................................................................................................. 5
3.1 Ambient Temperature ......................................................................................... 5
3.2 CE ....................................................................................................................... 5
3.3 Main Line Piping.................................................................................................. 5
3.4 NPS..................................................................................................................... 5
3.5 Station Piping ...................................................................................................... 5
3.6 WPS .................................................................................................................... 5
WELDING .................................................................................................................... 6
4.1 Welding Materials................................................................................................ 6
4.1.1 Filler Metal ............................................................................................... 6
4.1.2 Low-Hydrogen Electrodes ....................................................................... 6
4.1.3 Welds Thicker Than 13 mm ..................................................................... 6
4.1.4 Backing Rings.......................................................................................... 6
4.2 Welding Preparation............................................................................................ 6
4.2.1 Joint Design ............................................................................................. 6
4.2.2 Joint Preparation ..................................................................................... 6
4.2.3 Alignment................................................................................................. 6
4.2.4 Grounding ................................................................................................ 7
4.2.5 Line-up Clamps ....................................................................................... 7
4.2.6 Ambient Weather Conditions ................................................................... 7
4.3 Production Welding ............................................................................................. 7
4.3.1 Removal of Line-up Clamps .................................................................... 7
4.3.2 Cleaning .................................................................................................. 7
4.3.3 Preheat .................................................................................................... 7
4.3.4 Interrupted Welding ................................................................................. 8
4.3.5 Filler and Finish Beads ............................................................................ 8
4.3.6 Weld Reinforcement ................................................................................ 8
4.3.7 Controlled Cooling ................................................................................... 8
4.4 Weld Repair ........................................................................................................ 8
4.4.1 Preparation .............................................................................................. 8
4.4.2 Preheat .................................................................................................... 8
Revision 4
Page 2 of 13
5.0
APPENDICES
Appendix A:
Appendix B:
Appendix C:
Appendix D:
Appendix E:
Appendix G:
Appendix H:
Reference Index
Weld Procedure Specification TM-2
Weld Procedure Specification TM-4
Weld Procedure Specification TM-8
Weld Procedure Specification TM-9
Glossary of Terms
Supplemental Notes on In Service Welding Procedures
Revision 4
Page 3 of 13
1.0 SCOPE
1.1
General
This standard is Kinder Morgan Canada Inc.s joining program, as required by
section 16 of the Onshore Pipeline Regulations of the National Energy Board
Act. All welding shall be completed in accordance with Canadian Standards
Association standard CAN/CSA Z662, Oil and Gas Pipeline Systems. This
standard contains requirements that are in addition to that specification. This
standard is limited to the joining of piping and components for Category I, Low
Vapour pressure piping systems. This standard includes the following:
a)
b)
c)
d)
e)
f)
g)
Format
This standard includes all Kinder Morgan Canada Inc.s welding procedure
specifications (WPS) for butt-welding and fillet welding of pipe and fittings. The
welding procedures included with this standard are listed in Table 1.2.A.
TABLE 1.2.A
Appendix
WPS
Weld Type
Thickness (mm)
TM-2
Butt
12 - 30
1.5 - 12.7
TM-4
Butt
2 - 10
4.0 - 12.7
TM-8
TM-9
Pipe
12 - 30
6.35 - 12.7
Sleeve
12 - 30
6.35 - 12.7
Pipe
12 - 30
6.35 - 12.7
Branch
2 - 12
6.35 - 12.7
Revision 4
Page 4 of 13
Revision 4
Page 5 of 13
3.0 DEFINITIONS
3.1
Ambient Temperature
The temperature of the surrounding medium, usually used to refer to the
temperature of the air in which a structure is situated or a device operates.
3.2
CE
CE means Carbon Equivalent as contained in CSA standards and calculated
by the Yurioka Formula:
CE = C + F
Mn + Si + Cu + Ni + Cr + Mo + V + Nb
+ 5B
6
24
15
20
5
TABLE 3.2.A
C. Content
C. Content
C. Content
C. Content
<0.06/0.06
.07
0.08
0.09
0.53/0.54
0.56
0.58
0.62
0.10
0.11
0.12
0.13
0.66
0.70
0.75
0.80
0.14
0.15
0.16
0.17
0.85
0.88
0.92
0.94
0.18
0.19
0.20
0.21/>0.21
0.96
0.97
0.98
0.99/1.00
3.3
3.4
NPS
NPS means nominal pipe size; the NPS system of size designation is
contained in Standards prepared by the American Society of Mechanical
Engineers.
3.5
Station Piping
Any piping after the first valve off the mainline and before the last valve into the
mainline at a station.
3.6
WPS
WPS means weld procedure specification; the document which lists the
parameters to be used in the production of welds of a particular configuration in
accordance with applicable code requirements.
Revision 4
Page 6 of 13
4.0 WELDING
The following information shall supplement the welding procedure specifications
contained in the appendices of this standard. Welding shall be performed by qualified
welders in accordance with qualified welding procedure specifications, CSA standard
Z662 and the following requirements.
4.1
Welding Materials
4.1.1 Filler Metal
Filler metals shall be certified by the Canadian Welding Bureau as
Conforming to CSA Standard W48.1 or AWS Standard A5.1.
4.1.2 Low-Hydrogen Electrodes
Low-hydrogen electrodes are shipped in hermetically sealed containers,
which normally can be stored indefinitely without danger of moisture pickup. After removal from sealed containers, low-hydrogen electrodes shall
be stored in heated cabinets at temperatures from 120C to 150C.
4.1.3 Welds Thicker Than 13 mm
When the thickness of a butt weld exceeds 13 mm filler metals producing
low-hydrogen deposits shall be used. Cellulose coated electrodes may
be used for root passes.
4.1.4 Backing Rings
The use of backing rings is prohibited. Welding procedures requiring the
use of backing rings are unacceptable.
4.2
Welding Preparation
4.2.1 Joint Design
The ends of pipe and fittings shall be properly bevelled prior to welding.
Damaged ends will be re-cut and bevelled.
4.2.2 Joint Preparation
The surfaces to be welded shall be dry, smooth, uniform, free of fins,
laminations, tears, scale, slag, grease, paint and other foreign matter
which may adversely affect the welding.
4.2.3 Alignment
Alignment of abutting ends shall be such as to minimize the offset
between surfaces. For pipe of the same wall thickness, the maximum
allowable offset shall be 1.6 mm. Once welding of the root beads has
commenced, hammering at the joint shall not be permissible.
Revision 4
Page 7 of 13
Production Welding
4.3.1 Removal of Line-up Clamps
External line-up clamps, when used, shall not be removed until the
deposited root bead has been uniformly spaced around the pipe and shall
not have a cumulative length of not less than 50% of the pipe
circumference. Internal line-up clamps shall not be removed until the root
bead is complete.
4.3.2 Cleaning
Hand or power tools may be used. Oxides shall be thoroughly removed
from the edges to be welded for a distance of 13 mm on each side. Each
pass shall be thoroughly cleaned and free of slag, grease or dirt before
the commencement of the next pass. Inadequate cleaning can result in
inclusions, poor bead contour and lack of fusion. The completed weld
shall be free of slag and spatter.
4.3.3 Preheat
The wall thickness shall be heated uniformly for a minimum of 50 mm on
either side of the joint to the minimum temperature prescribed. The
preheat temperature shall be checked using temperature indicating
crayons, pyrometers or other suitable means. The preheat temperature
shall not exceed 200C, and shall be maintained until weld completion.
Revision 4
Page 8 of 13
Weld Repair
4.4.1 Preparation
Before weld repairs are made, injurious defects shall be removed by
power grinding to clean metal. The contour of the section to be repaired
shall be consistent with the joint design of the repair WPS.
4.4.2 Preheat
Preheating to a temperature of at least 150C shall be used when
effecting repairs. Preheating shall extend to a distance of at least 150
mm from any point of the area to be repaired. Care shall be taken to
prevent overheating, and no part of the area shall be heated to
temperatures in excess of 200C.
4.4.3 Repair Welding
After preparation and preheating of the repair site, the effected area shall
be re-welded in accordance with the WPS used to produce the original
weld or with a repair WPS approved by Kinder Morgan Canada Inc.
Revision 4
Page 9 of 13
4.6
b)
c)
Revision 4
Page 10 of 13
4.7
a)
b)
the Contractor has not made any change in the WPS; and
c)
d)
the WPS does not require the use of backing rings; and
e)
Qualification of Welders
4.7.1 General
Welders shall qualify by producing acceptable test welds in accordance
with specified procedures for the particular configuration involved. These
test welds shall be made in the presence of a Kinder Morgan Canada Inc.
representative. Welders shall be tested in accordance with the standard
with which the procedure was established.
4.7.2 Butt Welds
A welders shall be qualified to produce butt welds for a given procedure if
the test weld meets the following requirements of CSA Z662:
a)
b)
b)
Revision 4
Page 11 of 13
b)
the qualification test was performed by the Contractor and meets the
applicable requirements of 4.7.2 or 4.7.3; and
c)
the welder has used the specific WPS within the last three months.
WPS
Pipe Size
(NPS)
Thickness
(mm)
TM-2
12 S 24
6.35 t 12.7
TM-4
2 S 10
6.35 t 12.7
TM-8
TM-9
Carrier
24
12.7
Sleeve
24
9.5
Carrier
24
12.7
Branch
9.5
Configuration
Revision 4
Page 12 of 13
General
All welded joints, as a minimum, shall receive non-destructive examination
(NDE) prior to being placed in service. All joints should also be hydrostatically
tested, but some tie-in welds are permitted, providing the attached components
and piping have been hydro tested.
5.2
5.3
NDE Requirements
Completed production welds shall be visually examined to confirm code and
engineering requirements for materials, components, dimensions, joint
preparation, alignment, welding and assembly. These welds shall then be
nondestructively examined as indicated below:
5.3.1 Butt Welds
Butt welds shall be radiographically inspected for 100% of their
circumference.
5.3.2 Fillet Welds (empty piping)
Fillet welds shall be examined by liquid penetrant or magnetic particle
method for 100% of their circumference.
5.3.3 Fillet Welds (liquid filled piping)
Fillet welds on liquid filled piping shall be examined by liquid penetrant or
magnetic particle method for 100% of their circumference. Filled welds
on sleeves shall then be ultrasonically inspected for 100% of their
circumference. These examinations shall completed not less that 48
hours after completion of the weld.
5.4
Revision 4
Page 13 of 13
Revision 2
Page 1 of 2
INTRODUCTION
MP3901 is a compilation of requirements that have been derived from different
sources. Where applicable this appendix lists the reference from which each clause
was developed.
MP3901 REFERENCE INDEX
Clause
Title
CSA Z662
Other
Filler Metal
4.1.2
4.1.3
4.1.4
Backing Rings
7.2.4.2.1
7.2.4.2.2.2
Joint Design
7.2.7.6
4.2.2
Joint Preparation
7.2.7.1
4.2.3
Alignment
7.2.7.2
4.2.4
Grounding
7.2.7.3
4.2.5
Line-up Clamps
7.2.7.4
4.2.6
7.2.7.7
7.2.7.4
4.3.2
Cleaning
7.2.7.9
4.3.3
Preheat
7.2.7.15.2
4.3.4
Interrupted Welding
4.3.5
7.2.7.10.2.1
4.3.6
Weld Reinforcement
7.2.7.10.2.2*
4.3.7
Controlled Cooling
B31.3, 330.2.4
7.2.7.15.4
Preparation
7.2.10.3.1
4.4.2
Preheat
7.2.10.3.2
4.4.3
Repair Welding
4.4.4
7.2.10.6
4.4.5
7.2.10.5
7.2.1.5
OPR 16
Revision 2
Page 2 of 2
Title
CSA Z662
Other
General
4.6.2
Qualification of Welders
7.2.1.5
B31.3,328.2.2
General
7.2.6.1.1
4.7.2
Butt Welds
7.2.6.1.3
4.7.3
Fillets Welds
7.2.6.1.3
4.7.4
Pre-Qualification of Welders
4.7.5
Test Configuration
4.7.6
Qualification Intervals
OPR 16
B31.3,328.2.3
7.2.6.2
General
OPR 17
5.2
OPR 16
5.3
NDE Requirements
7.2.8.1.2
5.4
7.2.11.5.1
OPR 16
OPR
B31.3
Revision 4
Page 1of 1
(7.2.5.2.2.1)
TM-2B-1/2
SMAW
Manual
BASE MATERIALS
(7.2.5.2.2.2)
Standard or
Specification
(P No.: P1)
Grade
SMYS
CE
1.5 - 12.7
12 - 30
ELECTRICAL CHARACTERISTICS
Current Type
(7.2.5.2.2.4)
CSA W48.1
(7.2.5.2.2.3)
Polarity
(7.2.5.2.2.9)
DC
Reverse
3.2 - 4.0
AMPS
Min/Max
96 - 144
Volts
Min/Max
21 - 33
Travel Speed
(cm/min)
14 - 27
Heat Input
(KJ/cm)
6.6 - 13.9
E55010 (E8010)
3.2 - 4.0
108 - 204
22 - 34
20 - 33
6.5 - 14.2
Fill
E55010 (E8010)
4.0 - 5.0
132 - 204
22 - 33
16 - 32
7.9 - 16.9
Cap
E55010 (E8010)
4.0 - 5.0
108 - 186
21 - 32
11 - 18
12.7 - 19.1
Pass
Electrode
Root
E41010 (E6010)
Hot
(7.2.5.2.2.7)
TECHNIQUE
(7.2.5.2.2.10)
Number of Welders
Line-Up Clamps
2
Internal/External
Line-Up Clamp
Removal
Bead
No. Of Passes
Cleaning Methods
TEST DATE:
WELDER:
L. Verbeek, M. Verbeek
TESTED BY:
APPROVED BY:
G.A. Toth
Revision 2
Page 1of 1
SMAW
JOINT GEOMETRY
Method
BASE MATERIAL
(7.2.5.2.2.2)
Material Specifications
(7.2.5.2.2.4)
CSA W48.1
3
Rod Size (mm)
ELECTRICAL CHARACTERISTICS
Current Type
Polarity
AMPS Min/Max
Volts
Travel Speed
Min/Max
(cm/min)
80/110
24/28
20
E41010 (E6010)
3.2
E48010G (E7010)
3.2
110/140
26/30
24
E48010G (E7010)
4.0
120/150
26/30
16
E48010G (E7010)
4.8
120/150
24/30
16
E48010G (E7010)
4.8
115/145
24/30
14
E48010G (E7010)
4.8
115/145
24/30
12
POSITION
AND DIRECTION
Position
Direction
(7.2.5.2.2.5)
5G
Vertical Down
POSTWELD
(7.2.5.2.2.7)
HEAT TREATMENT
None
Number of Welders
Line-Up Clamps
TECHNIQUE
1
Internal/External
(7
TEST DATE:
WELDER:
D. Hoffman
TESTED BY:
APPROVED BY:
G.A. Toth
Revision 2
Page 1of 1
(7.2.5.2.2.1)
This procedure covers the fillet welding of full encirclement sleeves to liquid filled pipe. All supplemental requirements
Terasen Pipelines (Trans Mountain) Inc. Standard MP3901 and Appendix H shall apply to this procedure.
Process
SMAW
JOINT GEOMETRY
Method
BASE MATERIAL
(7.2.5.2.2.2)
(7.2.
Material Specifications
12 - 3
Grade
359 m
CE
0.48 m
ELECTRICAL CHARACTERISTICS
(7.2.5.2.2.4)
Material Specification
CSA W48.1
Current Type
Polarity
Pass
Electrode
AMPS Min/Max
Volts
Min/Max
Travel Speed
(cm/min)
E48018 (E7018)
3.2
140/150
28/30
17
E48018 (E7018)
3.2
140/150
28/30
7.5
E48018 (E7018)
2.4
100/105
25/27
7.5
E48018 (E7018)
3.2
125/135
26/28
10
POSITION
(7.2.5.2.2.5)
AND DIRECTION
Position
2G,5G
150
Direction
Vertical Up
55 - 150
POSTWELD
(7.2.5.2.2.7)
HEAT TREATMENT
None
TECHNIQUE
Number of Welders
Line-Up Clamps
Clamp or Tack
Cleaning
TEST DATE:
WELDER:
W. Edlund, K. Robertson
TESTED BY:
Coast Testing
APPROVED BY:
R.T. Ballantyne
Revision 2
Page 1of 1
(7.2.5.2.2.1)
This procedure covers the welding of branch connections to pipe filled with liquid. All supplemental requirements of
section 4.0 of Terasen Pipelines (Trans Mountain) Inc. Standard MP3901 and Appendix H shall apply to this
procedure.
Process
SMAW
JOINT GEOMETRY
Method
Manual
BASE MATERIAL
(7.2.5.2.2.2)
(7.2.5.2.
2.3)
Material Specifications
(P No.:
P1)
Attribute
Branch
Carrier
2 - 12
12 - 30
6.35 - 12.7
6.35 - 12.7
Grade
359 max.
CE
0.47 max.
ELECTRICAL CHARACTERISTICS
(7.2.5.2.2.4)
(7.2.5.2.
2.9)
Material Specification
Filler Metal F No.
Pass
Electrode
1
E48018 (E7018)
CSA W48.1
4
Rod Size
(mm)
2.4
E48018 (E7018)
2.4
90/110
26/28
10
30
E48018 (E7018)
3.2
120/140
28/30
10
30
E48018 (E7018)
2.4
95/120
28/30
30
E48018 (E7018)
2.4
95/110
28/30
30
E48018 (E7018)
2.4
95/110
28/30
30
AMPS
Min/Max
90/125
POSITION
(7.2.5.2.2.5)
AND DIRECTION
Current Type
Polarity
Volts
Travel Speed
Min/Max
(cm/min)
25/27
10
DC
Reverse
Burn Off Rate
cm/min)
30
2G,5G
Vertical Up or
Horizontal
Direction
POSTWELD
(7.2.5.2.2.7)
HEAT TREATMENT
None
150
50 - 150
Maximum
IntervalBetween
Passes
Cooling
TECHNIQUE
Revision 2
Page 2of 1
Line-Up Clamps
Tack Weld
TEST DATE:
May 6, 1991
TESTED BY:
Coast Testing
Line-up Clamp
Removal
Cleaning
WELDER:
APPROVED
BY:
Not applicable
Power brush and grind after each
pass
Revision 1
Page 1 of 9
INTRODUCTION
This appendix defines basics terms used in welding technology.
G.1
Arc Welding
A group of welding processes where fusion is produced by heating with an
electric arc or arcs, with or without the application of pressure and with or
without the use of filler metal. The filler metal is usually deposited in a
series of passes, or a single progression of the welding along a joint, weld
deposit or substrate. The result of the weld pass is a weld bead, layer or
spray deposit.
FIGURE G.1.A -- WELD PASS NOMENCLATURE
G.2
Backing Ring
Backing in the form of a ring that can be used in the welding of piping to
prevent weld spatter from entering a pipe and to assure full penetration of
the weld to the inside of the pipe wall.
G.3
Base Metal
The metal to be welded, brazed, soldered or cut. It is also referred to as the
parent metal.
G.4
Bevel Angle
A bevel is a type of edge or end preparation. The bevel angle is the angle
formed between the prepared edge of a member and a plane perpendicular
to the surface of the member.
G.5
Bond
The junction of the weld metal and the base metal or the junction of the
base metal parts when weld metal is not present. See Figure G.14.A.
Revision 1
Page 2 of 9
Butt-Joint
A joint between two members lying in the same plane. Other common joint
types are shown in Table G.6.A.
TABLE G.6.A -- TYPES OF JOINTS
Butt
Tee
Corner
Lap
Edge
G.7
Covered Electrode
A filler metal electrode, used in arc welding, consisting of a metal core wire
with a relatively thick covering which provides protection for the molten
metal from the atmosphere, improves the properties of the weld metal, and
stabilizes the arc.
G.8
Defect
A flaw or imperfection of such size, shape, orientation, location or properties
as to be rejectable. A flaw is an imperfection or unintentional discontinuity
which is detectable by a nondestructive examination.
G.9
Deposited Metal
Filler metal that has been added during a welding operation.
Revision 1
Page 3 of 9
G.15 Groove
Weld
A weld made in a groove between two members to be joined, such as a butt
weld. The groove angle is the included angle of the groove between the
parts to be joined. The groove face is the surface included in the groove.
Other common weld types are shown in Table G.15.A. Also see Figure
G.25.A.
TABLE G.15.A -- TYPES OF GROOVE WELDS
Type of Weld
Single
Double
Square
Bevel Groove
V-Groove
J-Groove
U-Groove
Revision 1
Page 4 of 9
Revision 1
Page 5 of 9
Revision 1
Page 6 of 9
Revision 1
Page 7 of 9
Revision 1
Page 8 of 9
G.37 Undercut
A groove melted into the base material adjacent the toe or root of a weld
and left unfilled by weld metal.
G.38 Weave Bead
A type of weld bead made with oscillation of the electrode transverse to the
axis of the weld as contrasted to a stringer bead.
G.39 Weld Metal
That portion of a weld which has been melted during welding. The portion
may be filler metal, base metal or both.
G.40 Welding Method
Common welding methods are defined as follows:
G.40.1 Manual Welding
Welding wherein the entire welding operation is performed and
controlled by hand.
G.40.2 Semi-Automatic Welding
Arc welding with equipment which controls only the filler metal feed.
The advance of the welding is manually controlled.
Revision 1
Page 9 of 9
Revision 2
Page 1 of 3
INTRODUCTION
This appendix supplements welding procedure specifications (WPS) TM-8 and
TM-9. These procedures have been specifically designed for welding attachments
to pipelines while in service (full of static liquid under reduced pressure).
H.1
General
The major objective of WPS TM-8 and TM-9 is to control the cooling rate of
the heat affected zone where the toe of the fillet weld meets the pipe. This
is accomplished through control of heat input and bead placement. The
pipe material in this case can have relatively high carbon equivalent. When
subjected to the severe thermal cycles created by the welding operation,this
region can be hardened to the extent of being crack sensitive. Because of
this, a great degree of care must be exercised regarding welding procedure
control.
H.2
Hydrogen Cracking
The area most prone to cracking is the coarse grained heat affected zone at
the toe of the weld in the carrier pipe. Cracks formed in this area are
hydrogen related. In order for hydrogen cracks to occur, the following
conditions must be present:
a)
a source of hydrogen;
b)
c)
Since the fillet weld does not lend itself to the control of restraint and stress
by procedure, control of cracking can be most effectively achieved by
addressing the first two points.
H.3
Hydrogen
Hydrogen may be present in the base metal, welding consumables, the
environment or any combination of the three.
H.3.1
Preheat
Although not totally effective because of the heat sink created by
the product filled line, it can be extremely useful in removing any
moisture from the surfaces to be welded.
Revision 2
Page 2 of 3
Consumables
Low hydrogen electrodes, by the nature of their coating, are very
sensitive to moisture pick-up. If exposed to atmospheric conditions
for more than 2 - 3 hours they can absorb enough moisture to make
them unsuitable for this application. Therefore portable electrode
stabilizing ovens are essential. These ovens should have good
door seals and be capable of holding a temperature of 120C to
150C. When dispensing electrodes from the ovens, welders
and/or helpers should take no more than enough electrodes to
complete 30 minutes of welding. The electrodes should be handled
with clean gloves as bare hands are a source of moisture,
particularly on warm humid days.
H.4
Control of Cooling
The critical area is in the heat affected zone of the pipe material at the weld
toe. It is therefore very important to cool this area down as slowly as
possible to minimize the formation of martensite (a brittle crack sensitive
microstructure). The procedure is designed to slow the cooling rate by
putting as much welding heat into the pipe as possible on the last weld pass
on the pipe.
FIGURE H.4.A -- WELD PASS CONFIGURATION
This pass must put as much heat as possible
into the pipe. The intent is to favour the pipe
surface rather than passes 1 & 2.
In order to accommodate more of the third pass on the pipe and still achieve
an acceptable profile, it may be desirable to place more of passes 1 & 2 on
the sleeve (or branch). This would leave more room on the pipe for pass 3.
2.4 mm (3/32") electrodes were chosen for the third pass so the welder can
go as slow as possible and place most of the bead on the pipe. Larger
diameter electrodes wound not give the same degree of weld pool control
and at the slow travel speeds would be prone to undercut and excessive
convexity.
Revision 2
Page 3 of 3
Note:
Summary
In order to reduce the risk of hydrogen cracking when welding on liquid
filled, line pipe, the following points must be exercised:
a)
b)
Put as much heat into the pipe as possible, particularly on the last pass
which touches the pipe. This can be done by placing most of that pass
on the pipe and travelling as slow as possible (not more than 7.5
cm/sec.).
c)
In spite of the fact that TM-9 is not a simple fillet weld (it is a combination bevel and fillet weld,
with the fillet weld providing reinforcement for the bevel weld) the principles behind the
development of the procedure are the same.
Revision 3
May 2009
Page 1 of 15
TABLE OF CONTENTS
1.0
2.0
3.0
4.0
SCOPE ................................................................................................................. 3
1.1
General ...................................................................................................... 3
1.2
Category .................................................................................................... 3
REFERENCE PUBLICATIONS ............................................................................ 3
DEFINITIONS ....................................................................................................... 3
3.1
ANSI .......................................................................................................... 3
3.2
Hydrostatic Testing .................................................................................... 4
3.3
Hydrostatic Testing .................................................................................... 4
3.4
Main Line Piping ........................................................................................ 4
3.5
MOP........................................................................................................... 4
3.6
NPS ........................................................................................................... 5
3.7
PN .............................................................................................................. 5
3.8
Station Piping ............................................................................................. 5
3.9
SMYS......................................................................................................... 5
TEST REQUIREMENTS ...................................................................................... 5
4.1
General ...................................................................................................... 5
4.1.1
4.1.2
4.2
4.3
4.4
5.0
General ...................................................................................................... 6
Additives .................................................................................................... 7
Other Test Media ....................................................................................... 7
4.5
Revision 3
May 2009
Page 2 of 15
6.0
7.0
8.0
5.3
Insulation ................................................................................................. 11
5.4
Temperature Recorders ........................................................................... 11
TEST PROCEDURES ........................................................................................ 11
6.1
General .................................................................................................... 11
6.2
Filling ....................................................................................................... 11
6.3
Temperature Stabilization ........................................................................ 12
6.4
Pressurization .......................................................................................... 12
6.5
Strength Test ........................................................................................... 12
6.6
Relief of Test Medium .............................................................................. 12
6.7
Visual Inspection ...................................................................................... 12
6.8
Depressurizing ......................................................................................... 13
6.9
Freezing Protection .................................................................................. 13
ACCEPTANCE CRITERIA ................................................................................. 13
7.1
Test Pressure .......................................................................................... 13
7.2
Reconciliations ......................................................................................... 13
RECORDING AND DOCUMENTATION ............................................................ 13
8.1
Test Data Logging ................................................................................... 13
8.2
Hydrostatic Test Record .......................................................................... 14
8.3
Hydrostatic Test File ................................................................................ 15
Revision 3
May 2009
Page 3 of 15
1.0 SCOPE
1.1
General
This standard covers the mandatory hydrostatic test requirements for
station piping systems.
This standard shall be limited to systems
transporting low vapour pressure (LVP) liquid hydrocarbons.
The scope of this standard includes all pressure pipe, fittings and fabricated
assemblies used in station piping systems. This standard excludes
pneumatic testing and hydrostatic testing of valves, main line piping
systems or buried station piping.
1.2
Category
This standard covers piping systems intended for ASME B31.4 or Category
1 service per CSA Z662.
ASME B31.4
API RP1110
3.0 DEFINITIONS
3.1
ANSI
ANSI means American National Standards Institute and for the purposes of
this standard refers to the ANSI system of nominal pressure class
designation as referenced in ANSI/ASME B16.5, Pipe Flanges and Flanged
Fittings.
Revision 3
May 2009
Page 4 of 15
3.2
Fabricated Assemblies
Fabricated assemblies shall include prefabricated components such as:
piping spools; scraper traps; and main line block valves with end extensions
and associated by-pass piping. The term excludes such manufactured
components as: valves; strainers; and pump casings.
3.3
Hydrostatic Testing
Hydrostatic testing is the application of internal pressure above the normal
or maximum operating pressure to a segment of piping or pressure
containing component. This pressure is applied under no flow conditions for
a fixed period of time, utilizing a liquid test medium.
3.4
1)
2)
3)
4)
5)
3.5
APPLICATIONS
Station Sectionalizing
Station Isolation
Unit or Main Line Pump Isolation
Main Line Sectionalizing
Main Line Sectionalizing By-Pass
MOP
MOP means Maximum Operating Pressure expressed in kPa or psi. The
MOP shall not be greater than 80% of the test pressure.
Revision 3
May 2009
Page 5 of 15
NPS
NPS means Nominal Pipe Size, and the NPS system of nominal size
designation is contained in standards prepared by the American Society of
Mechanical Engineers.
3.7
PN
PN means Pressure Nominal and the PN system of nominal pressure class
designation is contained in standards prepared by the International
Organization for Standardization (ISO).
The numerical part of the
designation approximates the maximum cold working pressure rating in bars
(100 kPa).
3.8
Station Piping
Station piping includes all pipe, components and any appurtenances at
Pump Stations, Tank Farms and Terminals between the station isolating
valves off the main line.
3.9
SMYS
SMYS means Specified Minimum Yield Strength. This is the minimum yield
strength prescribed by the specification or standard under which the
material is purchased.
General
4.1.1 Test Supervision
All testing shall be performed under general supervision of a Kinder
Morgan designated representative who shall witness the test, review
test records, and accept the results pursuant to Section 7.0 of this
standard. The designated representative shall be independent of
any contractor who carries out the pressure testing and any
contractor who constructed the piping or any component intended for
use in the piping. The designated representative shall be familiar
with the requirements of this standard.
4.1.2 Safety
Piping under hydrostatic test contains considerable stored energy
which can pose a safety hazard to employees, contractors, and the
public. Necessary precautions are provided in the Kinder Morgan
Safety Standards Manuals or the project specific safety plans as
applicable.
Revision 3
May 2009
Page 6 of 15
4.3
Pipe
Size
(NPS)
Press.
@
100%
SMYS
(kPa)
Press.
@
100%
SMYS
(kPa)
% SMYS @
Press.
% SMYS @
@
100%
Test
MOP SMYS Pressure MOP
(kPa)
% SMYS @
Test
Pressure
Test
Pressure
MOP
70,585
3.4
2.7
70,585
8.8
7.0
70,585
17.6
14.1
65,662
4.3
2.9
65,662
9.5
7.6
65,662
18.9
15.1
50,695
4.7
3.7
50,695
12.2
9.8
50,695
24.5
19.6
44,283
5.4
4.3
44,283
14.0
11.2
44,283
28.0
22.4
29,283
8.0
6.4
29,283
20.9
16.7
29,283
41.7
33.4
25,386
9.4
7.5
25,386
24.5
19.5
25,386
48.9
39.1
20,363
11.7
9.3
20,363
30.5
24.4
20,363
61.0
48.8
17,995
13.2
10.6
17,995
34.5
27.6
17,995
69.0
55.2
10
16,361
14.5
11.6
16,361
38.0
30.3
16,361
75.9
60.7
12
14,182
16.7
13.4
14,182
43.8
35.0
18,899
65.7
52.5
14
12,917
18.4
14.7
12,917
48.1
38.4
17,214
72.1
57.7
16
11,303
21.0
16.8
11,303
54.9
43.9
18,125
82.4
65.9
20
9,042
26.3
21.0
9,042
68.7
54.9
17,950
85.6
68.5
24
7,530
31.5
25.2
7,530
82.5
65.9
14,949
83.1
66.4
30
6,028
39.4
31.5
8,033
77.3
61.7
11,967
103.7
83.0
36
5,026
47.3
37.8
6,697
92.7
73.2
9,977
124.4
99.5
Test Medium
4.3.1 General
The preferred test medium is water without additives. All practical
steps shall be taken to use water as a test medium before
Revision 3
May 2009
Page 7 of 15
Revision 3
May 2009
Page 8 of 15
Test Configuration
Exposed
Piping
(1.25 x MOP)
Can
US
(kPa)
(psi)
2375
344
6210
900
12,415
1800
700
100
4.5
Test Pressure
Test Equipment
4.5.1 Equipment Required
The numbers of recorders, gauges, pumps, and other necessary
equipment are a function of the scope of a hydrostatic test. The
equipment listed in Table 4.5.1.A is the minimum required for a test
of prefabricated piping in a shop or yard.
TABLE 4.5.1.A -- MINIMUM EQUIPMENT REQUIREMENTS
Equipment
Quantity
Revision 3
May 2009
Page 9 of 15
Revision 3
May 2009
Page 10 of 15
TEST SECTION
LEGEND:
TR
PR
PI
DWT
*
Temperature Recorder
Pressure Recorder
Pressure Gauge
Dead Weight Tester
Locate in shade
Cleaning
Welding slag, sand and construction debris shall be removed from the test
section prior to commencement of the test.
5.2
Revision 3
May 2009
Page 11 of 15
Insulation
If ambient conditions (eg. wind, rain, sunlight) may have adverse effects on
the test results, the piping shall be insulated and/or covered and heated.
5.4
Temperature Recorders
All test equipment shall be installed prior to filling the section with water.
One recorder is installed with the temperature sensor attached to the pipe
and insulated. A second recorder shall be used to record the ambient air
temperature.
General
The test procedure covers five distinct phases. These phases include:
filling, temperature stabilization, pressurization, strength test and
depressurization. These phases are illustrated in Figure 6.1.A.
FIGURE 6.1.A -- HYDROSTATIC TEST PHASES
6.2
Filling
Long lines, such as tank lines, should be filled with water using a new
urethane pig ahead of the fill water. If filling with a pig, a back pressure
should be maintained ahead of the pig to prevent the pig from running away
from the water when it is travelling down hill. This can be achieved by
controlling the rate at which air leaves the opposite end of the test section.
Revision 3
May 2009
Page 12 of 15
Temperature Stabilization
After the majority of free air as has been removed using high point vents,
the test section shall be pressurized to 60% of the final test pressure and
held until the temperature stabilizes.
6.4
Pressurization
Upon completion of the temperature stabilization period, the pressure shall
be raised to the test pressure. Pressurizing shall be conducted in such a
manner to prevent surges and vibrations. All hydrostatic tests shall
commence on the hour or half hour. All personnel should be located in
accordance with the requirements of subsection 4.1.3 of this standard until
completion of the strength test.
6.5
Strength Test
Upon reaching the specified test pressure, the test section shall be isolated.
This may include disconnecting the pump. After transient pressure
conditions in the test section have dissipated, the strength test shall begin.
6.6
6.7
Visual Inspection
Upon completion of the strength test, the pressure shall be reduced to a
maximum of 115% of MOP and a visual inspection of the piping shall be
performed to confirm the absence of leaks. No visible leakage is permitted.
There shall be no visible evidence of drops or wetting of external surfaces.
Any evidence of leaks will require the test to be restarted. After completion
of the inspection, the test section can be depressurized. No visual
inspection shall be conducted within 15 metres (50 feet) of the pipe
while the test pressure exceeds 115% of MOP.
Revision 3
May 2009
Page 13 of 15
Depressurizing
After successful completion of the strength test the pressure shall be bled
down. Depressurizing should be carried out slowly to prevent hydraulic
surges and avoid excessive pipe vibration.
6.9
Freezing Protection
Dead legs, low points, and drain connections shall be emptied of water or
alternately displaced of water by methanol if freezing temperatures may
occur prior to placing the test section in service.
Test Pressure
The hydrostatic pressure in the test section does not fall below 100% of the
test pressure.
7.2
Reconciliations
The following circumstances shall be reconciled with the test data within the
accuracy limits of the instrumentation.
a)
b)
Revision 3
May 2009
Page 14 of 15
Revision 3
May 2009
Page 15 of 15
b)
c)
d)
e)
f)
g)
h)
DATE
MP4111
START OF
TEST
KINDER MORGAN
HYDROSTATIC TEST RECORD
END OF TEST
Station Piping
TEST NUMBER
TEST LOCATION
TEST MEDIUM
Design Factor
Wall Thickness
(mm)
OD (mm)
SMYS (MPa)
Design
Pressure (kPa)
km
Elevation
(m)
Minimum
kPa
%SMYS
Maximum
KPa
%SMYS
Test Point
High Point1
Low Point1
Type of Equipment
Serial Number
SIGNATURE
DATE
SIGNATURE
DATE
Comments:
1) This data is only required for long test sections, such as tank lines.
MP4111
HYDROSTATIC TEST DATA LOG
DATE
Station Piping
PAGE
kPa
TEST LOCATION
kPa
TEST MEDIUM
THERMOMETER
PIPE
TEMPERATURE
(C)
DEAD
WEIGHT
TESTER
(kPa)
PRESSURE
RECORDER
(kPa)
OF
REMARKS
SIGNATURE
DATE
SIGNATURE
DATE
REVISION INDEX
Rev
No.
A
Prepared by/
Date
F. Siwak & G. Hill/
2009-09-02
Reviewed by/
Date
Approved by/
Date
Pages
Revised
Remarks
Issued for Review
Revision A
September 2, 2009
Page 1 of 13
1.0
SCOPE ................................................................................................................. 3
2.0
3.0
DEFINITIONS ....................................................................................................... 3
4.0
5.0
3.1
3.2
3.3
3.4
Carrier ........................................................................................................ 3
Certifying Authority (CA) ............................................................................ 3
3.5
3.6
Contractor .................................................................................................. 3
Customer ................................................................................................... 3
3.7
3.8
Expediter.................................................................................................... 4
Purchase Order (PO) ................................................................................. 4
3.9
3.10
3.11
3.12
Receiver..................................................................................................... 4
Request for Quotation (RFQ) ..................................................................... 4
3.13
3.14
3.15
3.16
Traceability ................................................................................................ 4
Vendor ....................................................................................................... 4
4.3
5.2
Revision A
September 2, 2009
Page 2 of 13
5.4
6.0
7.0
5.5
Non-Conformance ..................................................................................... 9
5.6
6.2
6.3
6.4
6.5
REPORTING ...................................................................................................... 11
7.1
7.2
7.3
7.4
7.5
Completed Shipments.............................................................................. 13
APPENDICES
Revision A
September 2, 2009
Page 3 of 13
1.0
SCOPE
This standard is intended to establish quality assurance philosophies and
procedures for use by project managers and project engineers, procurement
specialists (including buyers, expediters, and receivers), quality control
specialists (including inspectors), and suppliers during the procurement of
materials (including fabricated assemblies) and equipment. While many of the
principles apply, this standard is not intended to be used during the purchase of
large diameter transmission pipe (also known as line-pipe), which requires its
own project-specific quality assurance program.
2.0
REFERENCE PUBLICATIONS
None
3.0
DEFINITIONS
3.1
Acceptance Criteria
Defined limits placed on the characteristics or attributes of materials or
equipment.
3.2
3.3
Carrier
A transportation firm engaged by the Vendor or the Customer to deliver
materials or equipment from the Vendors production or warehouse facility
to the Customer or Contractors marshalling facility or construction site.
3.4
3.5
Contractor
A construction firm engaged by the Customer to install materials or
equipment supplied by the Vendor.
3.6
Customer
KMC or its affiliated asset owning entities or an engineering and
procurement (EP) firm acting as an agent for KMC or its affiliated asset
owning entities.
Revision A
September 2, 2009
Page 4 of 13
Expediter
A person designated by the Customer to verify that materials or equipment
are being manufactured and shipped on schedule.
3.8
3.9
3.10
3.11
Receiver
A person designated by the Customer or the Contractor to receive,
account, and report on materials or equipment arriving at the Customer or
Contractors warehouse, marshalling facility, or construction site.
3.12
3.13
Resident Inspector
A person designated by the Customer to represent the Customers
interests at the construction site at which the materials or equipment
supplied by the Vendor are intended to be installed.
3.14
Sub-Vendor
A firm providing the Vendor with components or services associated with
the manufacture of materials or equipment.
3.15
Traceability
The ability to determine the history of a part by means of unique identifiers
and linked records.
3.16
Vendor
A manufacturer or provider of materials or equipment to the Customer.
Revision A
September 2, 2009
Page 5 of 13
4.0
4.2
4.3
Revision A
September 2, 2009
Page 6 of 13
5.0
Revision A
September 2, 2009
Page 7 of 13
Revision A
September 2, 2009
Page 8 of 13
Hold Point (H) the Vendor shall not proceed with the
production process or test activity without the presence of the
Certifying Authority (CA) or Authorized Inspector (AI), as
applicable. Note: a Hold Point should be used when it is
considered imperative that specified characteristics of the
materials or equipment be verified to ensure final quality
(incorrect or over use of hold points can cause schedule delays
or cost impacts).
Revision A
September 2, 2009
Page 9 of 13
5.5
Non-Conformance
The AI shall complete and issue a Non-Conformance Report (NCR) (see
Section 7.4) whenever discrepancies (that are not immediately
correctable by the Vendor) are identified during production, testing, or
documentation activities.
Revision A
September 2, 2009
Page 10 of 13
6.0
6.2
Missing MTR
Materials received without an MTR shall be quarantined and tagged
accordingly. Where an MTR cannot be located, the material in question
shall be identified as non-conforming and remain in quarantine until it is
disposed of.
6.3
Revision A
September 2, 2009
Page 11 of 13
7.0
6.4
6.5
Positive Recall
Undamaged materials or equipment that are not adequately identified or
are accompanied by incomplete documentation may be provisionally
accepted for installation on a positive recall basis. If a positive recall
option is deemed necessary for expediency, the Customer shall establish
a formal Positive Recall System with clear criteria under which positive
recall can be invoked. A key criterion shall be that the materials or
equipment in question can be easily removed from the work if subsequent
inspection shows that they do not comply with the PO specifications or
documentation requirements.
REPORTING
7.1
7.2
Revision A
September 2, 2009
Page 12 of 13
quantities are less than those on the PO, but the Vendor has indicated
that the delivery is to be considered complete
damage
In the case of damage, the Receiver shall take photographs showing the
extent of the damage, retain all packaging as evidence for inspection by
the Carriers representative, and attach copies of the following
documentation, as applicable, to the OSDR:
Bill of Lading
Waybill
Packing Slip
The Receiver shall retain the original OSDR, with copies sent to:
7.4
the Buyer
Revision A
September 2, 2009
Page 13 of 13
the Buyer
the Expediter
Completed Shipments
Once all items in the PO are received and deemed to be in conformance,
the PO shall be marked as complete and retained with the original MRR,
OS&D, and NCR reports, as applicable. At the end of the project, these
records shall be submitted to the Customer for inclusion in the project
records.
Revision A
September 2, 2009
Page 1 of 1
Size (NPS)
Application (check one)
Porting (check one)
Pattern (check one)
End Configuration (check
one)
Hydrostatic Test Standard
Mainline
Station
Regular Bore
Full Bore
Regular
Short
Flanged
Weld End
API 6D
TMPSEMP4301
CSA Z245.15
API 6D
Top Entry
End Entry
Manual
MOV
Right Hand
Left Hand
Locking Device
Trunnion Cavity Drain Port
Glycol Flush Prior to Shipping
Additional Requirements
Gaskets
Elastomers
Springs
Seat Inserts
Bolting
Packing
Yes
No
Integral
External
Dimensional Drawing
Included (check one)
Maximum Allowable Stem
Thrust or Torque
Number of Handwheel Turns
for Full Travel
Yes
No
Revision A
September 2, 2009
Page 1 of 1
(1)
(1)
(2)
(1)
If information is unavailable two weeks after the order date, it shall be provided at the earliest
possible date.
(2)
The Certified outline dimensional drawing shall be submitted within two weeks after the return
to Vendor of the approval drawings.
Revision A
September 2, 2009
Page 1 of 1
Page
Vendor or Sub-Vendor:
Project:
Customer:
PO No.:
of
ITP Approval
Vendor:
Customer:
Date:
Date:
Location:
Activity
No.
Process
Description
and Inspection
or Test Activity
Control Document
Specification,
Drawing or
Standard
Page or
Section
Reference
Acceptance
Criteria
Verifying
Document
To be
Included
in Data
Book
Certifying
Authority
Activity
Customer Activity
Activity
Frequency
Signature
E: Examine/Endorse Records
H: Hold Point
S: Submit Documents to
Customer for Approval
M: Monitor on a Random
Basis
V: Visual Inspection
W: Witness
Point
Revision A
September 2, 2009
Page 1 of 1
Frequency
HV
HD
Requirement
HE
HS
HVD
I, %
VD
Revision A
September 2, 2009
Page 1 of 1
MRR No.:
Project Name:
Project No.:
PO No.:
Date:
Vendor:
Storage Location:
Date Received:
Carrier:
Prepaid
Collect
OSDR No.:
Freight/Pro-Bill No.:
PO Item
Date:
Qty.
Amount:
Description
COMPLETE
INCOMPLETE
Revision A
September 2, 2009
Page 1 of 1
Date:
Project Name:
Storage Location:
PO No.:
Vendor:
B/L No.:
Carrier:
Freight/Pro-Bill No.:
2. Shortage
3. Damage
Action to be Taken:
Additional Remarks:
Receivers Name:
Receivers Signature:
Comments
Revision A
September 2, 2009
Page 1 of 1
DATE:
JOB NO.:
EQUIP./DWG. NO.:
DESCRIPTION OF NON-CONFORMANCE:
AUTHORIZED INSPECTOR:
SECTION 2
PROPOSED DISPOSTION
REPAIR
REWORK
USE
AS IS
SCRAP
DISPOSITIONED BY:
DATE:
YY / MM / DD
QC INSPECTOR ACCEPTANCE:
DATE
YY / MM / DD
CUSTOMER ACCEPTANCE:
DATE
YY / MM / DD
DATE
YY / MM / DD
SECTION 3
COMPLETION OF DISPOSITION VERIFIED:
DATE:
AUTHORIZED INSPECTOR:
YY / MM / DD
DATE
QA MANAGER:
YY / MM / DD
DATE
PROJECT MANAGER:
YY / MM / DD
CAST-IN-PLACE CONCRETE
TMPSE-42EF0006, Revision 1, August 16, 2007
REVISION INDEX
Rev
No.
A
B
0
1
Prepared by/
Date
P. Aldridge/
24-Jan-06
P. Aldridge/
07-Apr-06
P. Aldridge/
19-May-06
S. Woodside/
16-Aug-07
Reviewed by/
Date
J. Buckle/
14-Mar-06
J. Buckle/
07-Apr-06
J. Buckle/
19-May-06
D. Blackadar/
13-Apr-06
D. Blackadar/
19-May-06
KMC Approved/
Date
F. Siwak/
30-Mar-06
T. Delong/
13-Apr-06
T. Delong/
19-May-06
Pages
Revised
Remarks
Issued for Review
Issued for Bid
Issued for Construction
Terasen References
removed
Revision 1
Page 2 of 34
TABLE OF CONTENTS
1.0
SCOPE ................................................................................................................. 5
2.0
3.0
2.1
2.2
2.3
2.4
2.5
2.6
2.7
General ...................................................................................................... 8
3.2
3.3
3.4
3.5
Tolerances ................................................................................................. 9
Submittals .................................................................................................. 9
3.5.1
3.5.2
3.5.3
3.5.4
3.5.5
3.5.6
3.5.7
3.5.8
4.0
General ................................................................................................... 9
Product Data ........................................................................................... 9
Formwork ...............................................................................................10
Reinforcement ........................................................................................10
Concrete.................................................................................................10
Certificates .............................................................................................11
Shop Drawings .......................................................................................11
Concrete Placement Maps .....................................................................11
3.6
3.7
3.8
Protection................................................................................................. 12
Sequencing and Scheduling .................................................................... 13
3.9
Grouting ................................................................................................... 13
MATERIALS ....................................................................................................... 13
4.1
General .................................................................................................... 13
4.2
Formwork ...............................................................................................13
Tubular Column Forms ...........................................................................14
Revision 1
Page 3 of 34
4.3
Reinforcement ......................................................................................... 14
4.4
4.5
4.6
4.7
Cement ..................................................................................................15
Water .....................................................................................................15
Aggregates .............................................................................................15
Admixtures .............................................................................................16
5.0
Falsework ...............................................................................................14
Form Ties ...............................................................................................14
Form Coating and Release Agents .........................................................14
EXECUTION....................................................................................................... 19
5.1
5.2
5.3
5.4
5.5
Settlement Observations.......................................................................... 23
5.6
General ..................................................................................................23
Revision 1
Page 4 of 34
5.7
5.8
Curing ...................................................................................................... 27
5.9
5.10
5.11
6.0
General ..................................................................................................30
Drilling Openings ....................................................................................31
Crack Repair ..........................................................................................31
Modifications to Concrete .......................................................................32
General .................................................................................................... 32
Testing ..................................................................................................... 32
6.2.1
6.2.2
6.2.3
6.3
7.0
Revision 1
Page 5 of 34
1.0
SCOPE
This specification provides the requirements for cast-in-place concrete
construction as shown on the drawings and specified herein. This scope shall
include, but not be limited to:
Batching, supply, placing, testing, and curing of all plain and reinforced
concrete work
2.0
REFERENCE PUBLICATIONS
Where reference is made to other publications, such references shall be
considered to refer to the latest edition and any revisions thereto approved by the
organization issuing that publication.
Some reference publications are
supplemented or qualified, or both, by specific requirements in this specification;
reference publications should therefore be applied only in the context of this
specification.
2.1
2.2
ACI 308R
Revision 1
Page 6 of 34
2.3
ACI 308.1
ACI 318M
ACI 350M
Environmental
Engineering
Structures and Commentary
ACI SP-66
Concrete
ASTM A167
Standard Specification for Stainless and HeatResisting Chromium-Nickel Steel Plate, Sheet,
and Strip
ASTM A185
ASTM A276
ASTM A307
ASTM A320
ASTM A496
ASTM A497
ASTM A575
ASTM A663
ASTM C171
ASTM C233
Wire,
Revision 1
Page 7 of 34
Standard Specification
Admixtures for Concrete
for
Air-Entraining
ASTM C309
ASTM C494
Standard
Specification
Admixtures for Concrete
ASTM C1077
ASTM D994
ASTM D1751
for
Chemical
2.4
2.5
2.6
CSA Standards
CSA A23.1
CSA A23.2
CSA A23.3
CSA A23.4
CSA A283
Qualification
Laboratories
CSA A3000
CSA G30.18
Code
for
Concrete
Testing
Revision 1
Page 8 of 34
2.7
CSA G40.21
CSA G164
CSA S16.1
CSA S269.1
CSA S269.2
CSA S269.3
Concrete Formwork
CSA W47.1
CSA W59
CSA W178.2
CSA W186
CSA/CAN3 A266.1M
CSA/CAN3 A266.4
3.0
Grouting
QUALITY ASSURANCE
3.1
General
All concrete material and work shall comply with the applicable
requirements of CSA A23.1, Concrete Materials and Methods of Concrete
Construction.
All embedded steel material and work shall comply with the applicable
requirements of CSA G40.21, General Requirements for Rolled or Welded
Structural Quality Steel; CSA S16.1, Limit States Design of Steel
Structures; and Trans Mountain Pipelines L.P. Specification TMPSE42EF0008, Structural Steel.
Revision 1
Page 9 of 34
Supplier Qualifications
Concrete shall be obtained from a Trans Mountain Pipelines L.P.approved ready-mix supplier.
3.3
3.4
Tolerances
Tolerances shall be according to CSA-A23.1, Concrete Materials and
Methods of Concrete Construction, Clauses 10, 12.8, 13.3, and 22.1.
3.5
Submittals
3.5.1 General
The Contractor shall submit two (2) copies of all submittals to the
Trans Mountain Pipelines L.P.s Designated Representative for
review and approval.
3.5.2 Product Data
The Contractor shall submit Manufacturers product data for
specified concrete-related materials and accessories including
Manufacturers installation instructions to Trans Mountain Pipelines
L.P.s Designated Representative for review prior to delivering
materials to site.
Revision 1
Page 10 of 34
Slump tests
Reports for the field testing shall be inclusive of but not limited to:
Revision 1
Page 11 of 34
3.5.6 Certificates
The following certificates shall be submitted to the Trans Mountain
Pipelines L.P.s Designated Representative:
Steel mill test reports for embedded metals and anchor bolts
prior to incorporating into the work
Environmental Conditions
Cold weather requirements shall apply when the air temperature is below
5C and shall comply with ACI 318M, Building Code Requirement for
Structural Concrete and Commentary and ACI 306R, Cold Weather
Revision 1
Page 12 of 34
Protection
Concrete materials, metal fabrications, and concrete reinforcement shall
be protected before, during, and after installation.
Reinforcing bar identification shall be maintained after bundles are broken.
Contamination of the reinforcing steel from dirt, oil and grease must be
prevented.
Shop painted or galvanized surfaces of metal fabrications must be
protected from damage. Contamination of painted surfaces or surfaces
specified to be painted must be prevented.
Metal fabrications to be embedded in concrete shall not be used as a
means of temporary support. Metal fabrications must be protected from
marking and distortion.
Mechanical disturbances of concrete immediately after placement and
during the specified curing period, as well as damage to finished concrete,
must be prevented by means of protection acceptable to Trans Mountain
Pipelines L.P.s Designated Representative.
The Contractor shall not place equipment or structures on concrete within
seven (7) days of pouring unless written approval has been received from
Trans Mountain Pipelines L.P.s Designated Representative.
Revision 1
Page 13 of 34
4.0
3.8
3.9
Grouting
Unless specified otherwise, epoxy grouting shall not commence until the
concrete has cured for a minimum 28 days, see Trans Mountain Pipelines
L.P. Specification TMPSE-CIV-135, Grouting.
MATERIALS
4.1
General
Concrete material and reinforcement shall conform to the requirements of
CSA A23.1, Concrete Materials and Methods of Concrete Construction.
Steel for embedded metal fabrications shall comply with CSA G40.21,
General Requirements for Rolled or Welded Structural Quality Steel,
Grade 300W unless otherwise specified.
Alternate products conforming to the applicable CSA / ASTM standards
may be submitted to Trans Mountain Pipelines L.P.s Designated
Representative for review and approval. Products that are not listed within
Section 4.0 of this specification shall not be used without written approval
from Trans Mountain Pipelines L.P.s Designated Representative.
Products shall meet applicable Volatile Organic Compound (VOC) and
environmental regulations.
4.2
Formwork Materials
4.2.1 Formwork
All formwork shall conform to the requirements of CSA A23.1,
Concrete Materials and Methods of Concrete Construction and
CSA S269.3, Concrete Formwork.
Forms shall be tight fit, well-braced or shored, and capable of
supporting the fluid pressure of concrete and other construction live
loads.
Formwork materials shall be suitable to impart concrete finishes
within the specified tolerances. Unless specified otherwise on the
drawings, forms for concrete above grade shall be of plywood,
metal, "Sonotube"-type, preformed cylinders, or similar approved
material.
Revision 1
Page 14 of 34
Reinforcement
All concrete reinforcement shall be deformed billet steel bars in
accordance with CSA G30.18, Billet-Steel Bars for Concrete
Reinforcement, or welded wire fabric in accordance with ASTM A496,
Standard Specification for Steel Wire, Deformed, for Concrete
Reinforcement.
Reinforcement shall be free of loose coating that would adversely affect its
bonding capacity. Yield strength of the reinforcing steel shall be 400 MPa
and of the welded wire fabric shall be 450 MPa or as specified on the
drawing.
Wire for tying reinforcement shall be 1.52 mm (16 gauge), black annealed
wire complying with ASTM A82, Steel Wire, Plain, for Concrete
Reinforcement.
Revision 1
Page 15 of 34
Concrete Materials
4.4.1 Cement
Type 50 (Sulphate Resistant) Portland cement in accordance with
CSA A3000, Cementitious Materials Compendium, shall be used
unless noted otherwise on the drawings. Any special cement (eg.
high alumina cement) shall not be used without prior approval.
4.4.2 Water
Water shall comply with CSA A23.1, Concrete Materials and
Methods of Concrete Construction, Clause 4. Water used for
concrete mixing shall be clear and free from oil, acid, alkali, or
organic matter. Use of untreated wash water shall not be
permitted.
4.4.3 Aggregates
All aggregates used in concrete work shall be in accordance with
CSA A23.1, Concrete Materials and Methods of Concrete
Construction, Clause 5. Normal density fine and coarse aggregates
shall be from a source capable of delivering the supplies of
consistent quality. Coarse aggregate shall be the maximum size,
but not larger than:
Revision 1
Page 16 of 34
Revision 1
Page 17 of 34
Concrete Accessories
4.6.1 Anchor Bolts
Anchor bolts shall be in accordance with the requirements of
ASTM A36, Standard Specification for Carbon Steel; ASTM A307,
Standard Specification for Carbon Steel Bolts and Studs, 60,000
PSI Tensile Strength; or ASTM A320, Standard Specification for
Alloy Steel and Stainless Steel Bolting Materials for Low
Temperature Service, Grade L7, as specified on the drawings.
Anchor bolts for pumps and equipment foundations shall be
supplied with Wilson sleeves or approved equal if shown on the
drawings.
4.6.2 Epoxy and Adhesive Anchors
Where specified on the drawings, epoxy anchors shall mean
anchor rods installed in existing concrete with epoxy grout. Anchor
rods shall be fully threaded bar conforming to ASTM A307,
Standard Specification for Carbon Steel Bolts and Studs, 60,000
PSI Tensile Strength, or ASTM A36, Standard Specification for
Carbon Steel, unless noted otherwise on the drawings.
Epoxy grout for the epoxy anchors shall be as specified on the
drawings. Length of anchor rod, drilled anchor hole diameter, and
depth shall be as per the Manufacturers recommendation or as
specified on the drawings.
Adhesive anchors shall be installed as per the Manufacturers
recommendations and only used if specified on the drawings.
4.6.3 Embedded Steel
All embedded steel parts shall conform to CSA G40.21, General
Requirements for Rolled or Welded Structural Quality Steel, Grade
300W, unless noted otherwise on the drawings.
Revision 1
Page 18 of 34
Revision 1
Page 19 of 34
5.0
EXECUTION
All concrete construction shall conform to CSA A23.1, Concrete Materials and
Methods of Concrete Construction.
5.1
In the oil containment areas, the concrete shall be impervious and the mix
design shall be based on ACI 350M, Environmental Engineering Concrete
Structures and Commentary.
Revision 1
Page 20 of 34
5.3
Fixing of Reinforcement
Reinforcing steel shall be cut, bent, and placed in accordance with
CSA A23.1, Concrete Materials and Methods of Concrete Construction;
ACI 315, ACI Detailing Manual; and CSA A23.3, Design of Concrete
Structures, and as shown on the drawings. The Contractor shall not field
bend reinforcement except where indicated on the drawings or authorized
by Trans Mountain Pipelines L.P.s Designated Representative.
Reinforcement steel must be clean of salt, oil, grease, dirt, and other
foreign matter that may reduce or destroy bond with concrete prior to
placing. Reinforcing steel shall be securely tied at intersections with tie
wire or clips and held in position by spacers, chairs, or other supports
approved by Trans Mountain Pipelines L.P.s Designated Representative.
For placement on grade, the reinforcement shall be supported on precast
Revision 1
Page 21 of 34
Welded wire fabric for paving slabs - surface in contact with ground:
40 mm
Concrete cover shall in all cases be no less than the diameter of the
bar.
Revision 1
Page 22 of 34
Concrete Accessories
5.4.1 Anchor Bolts and Inserts
Anchor bolts and inserts, including joint filler and water stop where
indicated on the drawing, shall be securely attached to prevent
displacement during placing and setting of concrete.
All anchor bolts shall be supplied and installed by the Contractor as
per the drawings. All anchor bolts must be set accurately and
secured with a template while concrete is being placed. In addition,
further securing shall be placed at or near the base of the anchor
bolts to prevent tilting during placing. Tolerances for anchor bolts
shall be +/- 3 mm horizontally and vertically. The waterstop shall be
tied at its upper and lower extremities to the rebar at 600 mm
intervals with tie wire. The waterstop shall be fitted accurately so as
to be continuous at all corners and intersections. All joints shall be
fuse welded. Rebar shall be depressed or bent locally to
accommodate waterstops.
Joint filler shall be securely held in place and bonded to the
previously placed concrete face using a bonding agent
recommended by the joint filler Manufacturer. Unless indicated
otherwise on the drawings, the Contractor shall use 13 mm thick
joint filler to separate slab-on-grade from vertical surfaces and shall
extend the joint filler from the bottom of slab to within 6 mm of the
finished slab surface.
Holes drilled for epoxy and adhesive anchors shall be to the
diameter and depth as shown on the drawings. Deeper holes shall
be required if fissures or poor quality rock is encountered; the depth
shall be as directed by Trans Mountain Pipelines L.P.s Designated
Representative. Drilled holes shall be cleaned from loose cuttings,
dust, soil, or moisture and air purged prior to Trans Mountain
Pipelines L.P.s Designated Representatives inspection. The grout
shall be in accordance with the drawings and Trans Mountain
Pipelines L.P. Specification TMPSE-CIV-135, Grouting and shall be
installed as specified by the Manufacturer.
5.4.2 Joint Sealants
Sealant shall be applied where shown on the drawings or as
specified herein in accordance with the Manufacturers instructions,
see Section 4.5.4 of this specification.
Revision 1
Page 23 of 34
Settlement Observations
When specified, reference pins for settlement observations shall consist of
10 mm diameter stainless steel bolts or threaded rods placed at locations
as shown on the drawing and shall project slightly above the top of the
concrete just enough to be located. Elevations of the pins shall be taken
as specified on the drawings.
5.6
Placing of Concrete
5.6.1 General
Placement of concrete shall be in accordance to CSA A23.1,
Concrete Materials and Methods of Concrete Construction. The
temperature of plastic concrete, as placed, shall not exceed 32C.
During cold weather, as placed, temperature shall not be less than
10C. For concreting in hot or cold weather conditions, see Section
3.6 of this specification.
Revision 1
Page 24 of 34
Revision 1
Page 25 of 34
Revision 1
Page 26 of 34
Spacing
metres
2.4
3.0
3.6
4.2
4.8
5.4
6.0
feet
8
10
12
14
16
18
20
Vibration of Concrete
Concrete, when placed, shall be compacted thoroughly and uniformly by
means of hand tamping tools, vibrators, or finishing machines to obtain a
dense, homogeneous structure, free of cold joints, fill planes, voids, and
honeycomb. Formed surfaces shall be smooth and free from large air and
water pockets. The concrete shall be well bonded to all reinforcing steel,
hardware anchors, waterstops, and other embedded parts.
Internal vibrators shall be used wherever practical for consolidating the
concrete, having regard to the size and spacing of reinforcement in the
form and may be supplemented by external form vibrators or vibrating
screeds.
Vibrators shall be applied systematically and at such spacing intervals that
the zones of influence overlap and the depth of penetration of the vibrator
enters the upper part of the previously placed lift of the concrete.
The vibrator shall be inserted into the concrete in as nearly a vertical plane
as possible and shall be withdrawn slowly in a vertical direction to facilitate
the removal of entrapped air bubbles.
The vibrator shall be applied, at any one (1) location, until the concrete is
consolidated, but not to the extent that segregation of the concrete will
occur.
Vibrators shall be used only for consolidation purposes and shall not be
used to move concrete more than a short distance.
Revision 1
Page 27 of 34
Curing
Concrete shall be cured in accordance with CSA A23.1, Concrete
Materials and Methods of Concrete Construction. Beginning immediately
after placement, concrete shall be protected from premature drying,
excessively hot or cold temperatures, and mechanical injury, and shall be
maintained with minimal moisture loss at a relatively constant temperature
during the period necessary for hydration of the cement and hardening of
the concrete. Materials and methods of curing shall be subject to the
approval of Trans Mountain Pipelines L.P.s Designated Representative.
The concrete shall be continuously moist-cured by one (1) of the following
methods:
Minimum cure time shall be the lesser of Column A (min. cure time) or
Column B (min. % specific strength) as shown in Table 5.8.A during which
the temperature of the air in contact with the concrete shall be kept above
10C. When necessary, arrangement for heating, covering, insulating, or
housing the concrete work shall be made by the Contractor in advance of
concrete placement and shall be adequate to maintain the required
temperature range between 10C and 21C without injury due to
concentration of heat.
The time during which concrete surfaces are in contact with wood or metal
forms may be considered as curing time. Wood forms shall be maintained
in a moist condition until removal. Should the wood forms be removed
before the end of the complete curing period, concrete surfaces no longer
in contact with the forms must continue to be cured by continuous
sprinkling or use of wet absorbent matting or fabric.
Revision 1
Page 28 of 34
7 days
Column B
Min. % Specified
Compressive Strength
70%
7 days
70%
Column A
Min. Cure Time
7 days
70%
See Note 4
7 days
70%
Notes:
1) The Contractor may determine the Minimum % Specified Strength by testing field cure cylinders or by
other non-destructive testing which is acceptable to Trans Mountain Pipelines L.P.s Designated
Representative.
2) Cure times shown are based on minimum ambient temperatures of 10C. For lower temperatures the
Contractor may need to extend the cure times to the satisfaction of Trans Mountain Pipelines L.P.s
Designated Representative.
3) For accelerated strength concrete mixes cure times shall correspond to the minimum specified
strength defined in the Table. 5.8.A.
4) Surfaces of slabs shall be wetted immediately after final finishing and covered with 6 mil polyethylene
membrane, clear or white, and secured in place with weights so as to prevent exposure of concrete
surfaces during curing period. Place the membrane flat, without wrinkles, to minimize mottled
discoloration. Provide traffic protection to protect the concrete surfaces and the curing membrane.
Leave the curing membrane undisturbed for minimum of 7 days and maintain a film of water under
the membrane and add water as required.
5.9
Concrete Finishes
The following finishes shall be used, as applicable, unless noted otherwise
on drawings:
Revision 1
Page 29 of 34
Removal of Formwork
Unless otherwise shown on the drawings or with written approval from the
Trans Mountain Pipelines L.P.s Designated Representative, falsework
and formwork shall not be removed prior to the lapsed time after concrete
placement (Minimum Stripping Time), in accordance with Table 5.10.A.
Immediately after removal of forms, bolts, ties, nails, and similar embedded
metals shall be removed or cut back 15 mm from the concrete surface and
the surface made good.
Revision 1
Page 30 of 34
Column A
Min. Stripping Time
(Curing Period
Above 10C)
4 days
Column B
Min. % Specified
Compressive
Strength
60%
7 days
70%
14 days
85%
21 days
90%
Notes:
1) The minimum stripping times defined in the Table 5.10.A above may have to be extended if retention of
formwork is chosen as a means of curing and protection.
2) Stripping times shown are based on minimum ambient temperatures of 10C (50F). For lower
temperatures the Contractor must extend the times to the satisfaction of Trans Mountain Pipelines
L.P.s Designated Representative.
3) Stripping times shown are based on no significant superimposed construction loads. The Contractor
shall ensure concrete is not loaded in excess of its design capacity after reaching its specified
compressive strength.
4) Stripping times shall be extended if more than 10% of supplementary cementitious material is
incorporated in the mix. The planned extended times must be submitted to Trans Mountain Pipelines
L.P.s Designated Representative who shall submit to the Trans Mountain Pipelines L.P.s Designated
Engineer for review and approval.
5.11
Revision 1
Page 31 of 34
Revision 1
Page 32 of 34
6.0
CONCRETE TESTING
6.1
General
The Contractor, at his expense, shall engage an independent CSACertified Laboratory approved by Trans Mountain Pipelines L.P.s
Designated Representative to sample and test delivered concrete in
accordance with CSA A23.2, Methods of Test and Standard Practices for
Concrete. Copies of test reports shall be submitted to Trans Mountain
Pipelines L.P.s Designated Representative immediately upon them
becoming available for review and approval.
6.2
Testing
6.2.1 Sampling Concrete
When concrete is conveyed from delivery equipment to point of
deposition, samples will be taken at point of deposition.
For a compressive strength test, three (3) standard 150 mm x
300 mm long test cylinders shall be made. One (1) cylinder shall
be tested at an age of seven (7) days and two (2) cylinders at an
age of 28 days. The seven (7) day result shall be used as an
indicator of the expected 28-day result. The test result shall be the
average of the strengths of the two (2) specimens tested at an age
of 28 days, except if any specimen shows definite evidence, other
than low strength, of improper sampling, moulding, handling,
curing, or testing, than it shall be discarded and the strength of the
remaining cylinder shall be considered the test result.
Slump shall be measured before addition of superplasticizers.
When concrete is to be placed by pump, slump and air properties
shall be measured at discharge from the hose. For pumping
purposes, the sand content of the pump mix, as a ratio by weight of
Revision 1
Page 33 of 34
Defective Concrete
Concrete failing to meet the strength requirements may be required to be
removed and replaced with concrete meeting the strength requirements.
Delivered loads of concrete not meeting either the slump or air
entrainment requirements shall be a cause of rejection at the discretion of
Trans Mountain Pipelines L.P.s Designated Representative.
Concrete with inadequate protection from extremes of temperature during
early stages of hardening or inadequate curing shall be subject to further
tests as specified by Trans Mountain Pipelines L.P.s Designated
Representative. In lieu of removing and replacing the defective concrete
structure or any member thereof, the Contractor may carry out drilled core
tests per CSA A23.2, Methods of Test for Concrete, or load testing of the
structure of the member in question if feasible and acceptable, as per
CSA A23.3, Design of Concrete Structures for Buildings, and
requirements of this specification.
Revision 1
Page 34 of 34
7.0
QUALITY RECORDS
Quality records shall be completed and maintained as objective evidence that
products were procured, manufactured, delivered, installed, and tested in
accordance to the project drawings, specifications, applicable codes, standards,
regulations, and contract document.
Quality records shall be legible, identifiable and traceable to materials, products,
services and persons involved.
Upon project completion, the Contractor shall index and submit their quality
documents to Trans Mountain Pipelines L.P.s Designated Representative. They
shall include, but not be limited to, the following:
As-built drawing records (inclusive of structural steel, rebar and anchor bolts,
concrete placement)
STRUCTURAL STEEL
TMPSE-42EF0008 Revision 3, August 16, 2007
REVISION INDEX
Rev
No.
A
B
0
1
2
Prepared by/
Date
J. Buckle/
08-Nov-05
J. Buckle/
11-Nov-05
J. Buckle/
18-Nov-05
J. Buckle/
27-Jan-06
J. Buckle/
07-Mar-06
S. Woodside/
16-Aug-07
Reviewed by/
Date
KMC Approved/
Date
Pages Revised
Remarks
Issued for Review
R. Pillai/
11-Nov-05
R. Pillai/
07-Mar-06
D. Blackadar/
18-Nov-05
D. Blackadar/
27-Jan-06
D. Blackadar/
07-Mar-06
F. Siwak/
16-Nov-05
T. Delong/
21-Nov-05
T. Delong/
27-Jan-06
T. Delong/
07-Mar-06
Revision 3
Page 2 of 15
TABLE OF CONTENTS
1.0
GENERAL ............................................................................................................ 4
2.0
RESPONSIBILITY ................................................................................................ 4
3.0
4.0
DESIGN ................................................................................................................ 5
5.0
MATERIALS ......................................................................................................... 5
6.0
7.0
8.0
5.1
5.2
General ...................................................................................................... 5
Structural Bolts and Nuts ........................................................................... 5
5.3
5.4
Grating ....................................................................................................... 6
Handrails and Toeplates ............................................................................ 6
CONNECTIONS ................................................................................................... 7
6.1
6.2
General ...................................................................................................... 7
Welding Connections ................................................................................. 8
6.3
FABRICATION ..................................................................................................... 9
7.1
General ...................................................................................................... 9
7.2
7.3
Grating ....................................................................................................... 9
Shop Welding ............................................................................................ 9
7.4
7.5
7.6
7.7
ERECTION ......................................................................................................... 10
8.1
8.2
General .................................................................................................... 10
Supply ...................................................................................................... 10
8.3
8.4
Field Repairs............................................................................................ 10
Surface Repairs ....................................................................................... 11
8.5
8.6
8.7
Revision 3
Page 3 of 15
8.10
9.0
10.0
INSPECTION...................................................................................................... 13
11.0
DRAWINGS ........................................................................................................ 14
11.1
General .................................................................................................... 14
11.1.1 Fabrication Drawings ..............................................................................14
11.1.2 Erection Drawings ..................................................................................14
12.0
Revision 3
Page 4 of 15
1.0
GENERAL
This specification covers the design, fabrication, and erection of structural steel
structures, herein referred to as structures.
Unless stated otherwise, structural elements shall be designed and fabricated using metric units. Any imperial dimensions shown are for reference only.
2.0
RESPONSIBILITY
The Contractor shall assume full responsibility for the fabrication, transportation,
and erection of all structural steel to the lines and levels shown on the drawings
and in accordance with the requirements of this specification.
ANSI B18.2.2
ASTM A53
ASTM A135
ASTM A139
ASTM A307
ASTM A325M
Revision 3
Page 5 of 15
4.0
CSA G40.21
CSA G164
CSA S16
CSA S136
CSA W47.1
CSA W48.1
CSA W59
CSA W178.1
CSA W178.2
TMPSE-45ES0012
TMPSE-45ES0012A
Field Touch-Up and Supplementary Schedule for External Coating of Aboveground Piping, Valves,
Equipment, and Structural Steel
TMPSE-CIV-135
Grouting
DESIGN
The design of all structures shall be in accordance with CSA S16 and the requirements of this specification
5.0
MATERIALS
5.1
General
Materials other than those listed in this specification may be considered;
but their use is contingent upon written approval of Trans Mountain Pipelines L.P.s Designated Engineer. All materials shall be of new stock.
All structural steel (rolled shapes, plates, and flats) shall conform to the
requirements of CSA G40.21. All steel, other than W, WWF, and Hollow
sections shall be grade 300W. Hollow structural sections shall conform to
CSA G40.21, Grade 350W, Class C. All W and WWF sections shall be
Grade 350W.
5.2
Revision 3
Page 6 of 15
Grating
Unless otherwise specified, all grating shall be "Standard Flow Forge Steel
Grating" - Type 19-4, or approved equal. All grating shall be clipped,
banded, and galvanized.
In exterior areas, open-type serrated grating shall be used.
Grating shall be a minimum of 25 mm (1") deep, with 5 mm (3/16") rectangular bearing bars spaced on 30 mm (1 3/16") centers and cross bars
spaced on 100 mm (4") centers. Other bearing bar sizes shall be 32 mm
(1 ) x 5 mm (3/16"), 38 mm (1 ) x 5 mm (3/16") and 76 mm (3) x 9.5
mm (3/8).
Grating size shall be shown on the drawings.
All grating shall be fastened to its supporting steel with saddle-type fasteners secured with 10 mm (3/8") self-tapping hexagon head stainless
steel bolts.
Steel stair treads shall be of the same make and type as the grating and
be supplied with checkered plate nosing.
5.4
Revision 3
Page 7 of 15
6.0
CONNECTIONS
6.1
General
Fabrication shall conform to the requirements of CSA S16, the CISC Code
for Standard Practice for Structural Steel, the drawings, and this specification.
The Contractor is responsible for the strength and adequacy of all connection details. Sketches and calculations shall be submitted for special
details at the request of Trans Mountain Pipelines L.P.s Designated Engineer. All design shall be performed by a Contractors registered structural
engineer. Relevant drawings and design notes shall be stamped by the
Contractors structural engineer performing the work, licensed to practice
in the province where the structure is located.
Member connections shall be designed to resist the loads shown on the
design drawings, unless they are governed by the minimum requirements
outlined below.
Moment connections shall be designed for the forces shown on the drawings. Where forces are not indicated, connection shall be designed to
develop the full bending capacity of the weakest member.
Shear connections shall be designed for the values given. Where reactions are not given, the connection shall be designed to resist not less
than the factored reaction of the uniform beam load, which would result in
a bending moment equal to the bending capacity of the section.
Unless otherwise noted on the drawings, bracing shall be connected for
the loads indicated or 50% of factored tension capacity on the net section,
whichever is greater. In all cases, the minimum number of bolts shall be
as follows:
Structural Tees
Angle Bracing
Revision 3
Page 8 of 15
Welding Connections
The Contractor's welding procedures shall be submitted to Trans Mountain
Pipelines L.P.s Designated Representative prior to commencing fabrication. Welding procedures that conform in all respects to CSA W59 shall be
deemed as pre-qualified and are exempt from tests for qualifications. Other procedures may be acceptable but shall be qualified by tests as
prescribed in CSA W59. The test records shall be submitted to Trans
Mountain Pipelines L.P.s Designated Representative.
Welding shall be performed only by welders who have been qualified in
accordance with CSA W59. Welder qualification test records shall be
made available upon request to Trans Mountain Pipelines L.P.s Designated Representative.
All butt welds shall be full penetration welds.
6.3
Bolting Connections
All bolted connections shall be bearing type, except at joints where slippage cannot be tolerated or where otherwise indicated on the design
drawings. Minimum bolt size shall be M20 (3/4" diameter) bolts, with
threads assumed in the shear plane, unless noted otherwise on the drawings or limited by the size of the connection.
Slip resistant (Friction-type) connections shall be designed using appropriate values corresponding to a 5% probability of slip.
Bolts for all members, except for secondary framing, shall conform to
ASTM A325M. Bolts for secondary framing shall conform to ASTM A307.
Revision 3
Page 9 of 15
7.0
FABRICATION
7.1
General
Only new steel shall be used.
Fabrication shall be in accordance with CSA S16, the requirements of this
specification and the CISC code of standard practice for structural steel.
Bolt holes shall be made by drilling only.
Base plates over 0.3 m2 (3 square feet) shall be provided with grout holes.
Shop splices of members will not be permitted without the prior written approval of Trans Mountain Pipelines L.P.s Designated Engineer. When
approval is given, shop splices must develop 100% of the capacity of the
member. Costs of splicing shall be borne by the Contractor. Nondestructive testing shall be done at the discretion of Trans Mountain Pipelines L.P.s Designated Representative.
All members shall be fabricated with natural camber up.
Unless otherwise specified by Trans Mountain Pipelines L.P.s Designated
Engineer, all shop connections shall be made by continuous welding.
The Contractor shall ensure all burrs and sharp edges on hand railings,
ladders, and safety cages have been removed.
7.2
Grating
The grating bearing bars will span in one (1) common direction. The grating bearing bars, banding bars, and twisted cross bars in adjacent panels,
shall be aligned in their respective directions.
7.3
Shop Welding
All welding processes, welders' qualifications, and process qualifications
shall be in accordance with CSA W47.1 and CSA W59.
Structures that are galvanized must be continuously seal welded.
All welding is to be completed prior to painting or galvanizing.
7.4
Surface Preparation
All surface preparation shall be as per Trans Mountain Pipelines L.P.
Specification TMPSE-45ES0012, External Coating of Aboveground Piping, Valves, Equipment, and Structural Steel.
Revision 3
Page 10 of 15
Galvanizing
Hot dip galvanizing: galvanize steel, where indicated, to CSA G164, minimum zinc coating 600 g/m2.
7.6
Surface Coating
The primer and the topcoat (finish paint) shall be applied within a shop environment. Coating application shall be as per Trans Mountain Pipelines
L.P. Specification TMPSE-45ES0012, External Coating of Aboveground
Piping, Valves, Equipment, and Structural Steel.
7.7
Delivery
Steelwork shall be properly protected during shipping so that parts will not
be bent, broken, deformed, strained, or otherwise damaged.
Damage to any part of the work due to lack of proper handling or shipping
by the Contractor shall be repaired or replaced at the Contractor's expense.
8.0
ERECTION
8.1
General
Erection shall be in accordance with CSA S16, the requirements of this
specification, and CISC code of standard practice for structural steel.
8.2
Supply
The Manufacturer shall supply all pre-fabricated structures, erection bolts,
nuts, washers, load indicator washers, shims, wedges, and leveling plates
required for proper fit-up.
The Erector shall furnish all other materials, tools, labour, equipment, and
supervision required to install the structure(s).
8.3
Field Repairs
All field repairs or alterations must be approved by Trans Mountain Pipelines L.P.s Designated Representative.
Bolt holes shall be made by drilling. Holes made by burning are not permitted.
Any cut member shall be dressed and have a smooth edge and shall be
regalvanized or repainted in accordance with original finish.
Revision 3
Page 11 of 15
Surface Repairs
Repairs to painted or galvanized areas may be accepted if repairs are
made by a method that will provide equal protection and is approved by
Trans Mountain Pipelines L.P.s Designated Representative.
8.5
Field Welding
Field welds shall be made by welders who have been qualified in accordance with CSA W47.1.
All field welding shall be in accordance with CSA W59.
Before field welding on galvanized or painted surfaces, remove the surface coating within 90mm (3 ") of welds 20 mm (3/4") or greater and
within 50 mm (2") of welds less than 20 mm (3/4").
8.6
Erection Tolerances
Fabrication tolerances for finished parts shall be as specified in Section
28.9 of CSA S16.
Rolling tolerances for profile dimensions permitted under CSA G40.20.
Individual members of structural steel frames shall be considered as being
plumb, level, and aligned when the deviation from the dimensions shown
does not exceed 1 in 500.
8.7
Revision 3
Page 12 of 15
8.9
8.10
9.0
Revision 3
Page 13 of 15
10.0 INSPECTION
The Fabricator shall establish a shop inspection procedure (Inspection Test Plan
ITP) to perform sufficient inspections and tests to assure conformance to contract requirements. The Fabricator's quality control program and ITP shall be
submitted in writing to Trans Mountain Pipelines L.P.s Designated Representative for review prior to proceeding with any scope of work. It shall include
sufficient detail to describe those items to be inspected, the manner of inspection, and shall adequately describe all fabrication quality control activities
contemplated, including provision for adequate documentation of the fabricator's
performance of such quality control and inspection. Records of inspections and
certified reports of tests performed shall be retained by the fabricator and submitted to Trans Mountain Pipelines L.P.s Designated Representative when
requested.
Random testing shall be performed on field bolted connections to ensure proper
tightening and installation techniques, as specified in CSA S16.
Trans Mountain Pipelines L.P.s Designated Representative reserves the right to
inspect any or all parts of the work during fabrication and erection. Such inspection shall in no way relieve the contractor of responsibility for the adequacy of the
work.
If errors in fabrication are discovered during erection or installation, the Contractor shall repair them at no cost to Trans Mountain Pipelines L.P.
Certified copies of all mill test reports covering the chemical analyses and physical properties of the steel, as described in the applicable ASTM and CSA
standards shall be submitted upon request to Trans Mountain Pipelines L.P.s
Designated Representative.
The Contractor shall provide Trans Mountain Pipelines L.P.s Designated Representative with suitable and safe access to all places of work for purposes of
inspection at all times. Materials and workmanship shall be subject to inspection at
any time.
All structural welds may be visually examined by Trans Mountain Pipelines L.P.s
Designated Representative. Where additional non-destructive testing is required,
such testing shall be carried out in accordance with requirements of CSA W59.
All faulty welding discovered during non-destructive tests shall be repaired to the
satisfaction of Trans Mountain Pipelines L.P.s Designated Representative at no
extra cost to Trans Mountain Pipelines L.P.
Revision 3
Page 14 of 15
11.0 DRAWINGS
11.1
General
The Manufacturer shall prepare and submit copies of all detail and erection drawings complete in every detail for the structures being furnished.
Detail and erection shop drawings shall be submitted to Trans Mountain
Pipelines L.P.s Designated Engineer for review prior to fabrication. If corrections are required, the Contractor shall make and clearly mark such
corrections and resubmit the drawings for final approval within seven (7)
calendar days.
Review of detail and erection drawings shall not relieve the Contractor of
responsibility for the completeness and accuracy of all dimensions and details.
After approval, the Manufacturer shall forward five (5) copies of "As Fabricated" drawings to Trans Mountain Pipelines L.P.s Designated Engineer.
11.1.1 Fabrication Drawings
Trans Mountain Pipelines L.P.s Designated Engineer (including the
Engineer for Design-Build packages) will furnish drawings that will
give all information required for the shop detailing of the steel.
The Contractor's erection drawings shall be referenced to Trans
Mountain Pipelines L.P.s Designated Engineers drawings. Shop
drawings shall be referenced to the related erection drawings.
11.1.2 Erection Drawings
Before the start of the work, drawings marked "Issued for Construction" will be supplied to the Contractor by Trans Mountain Pipelines
L.P.s Designated Engineer. The latest revisions of these drawings
shall be used.
The Contractor shall prepare erection diagrams and shop drawings
for structural steel and miscellaneous metal based on the design
drawings and specifications. Shop and erection drawings shall be
stamped by a professional engineer registered in the province
where the work is located. The Contractor shall furnish four (4)
prints of the following shop drawings to Trans Mountain Pipelines
L.P.s Designated Engineer, as well as electronic files.
Revision 3
Page 15 of 15
Material data, including catalogued Mill Test Reports (MTRs) and other product data sheets (coatings, etc.)
NDE data (if applicable), including third-party certifications and NDE Reports
REVISION INDEX
Rev
No.
A
B
0
1
2
Prepared by/
Date
P. Aldridge/
24-Jan-06
P. Aldridge/
28-Mar-06
P. Aldridge/
15-May-06
P. Aldridge/
12-Jun-06
S. Woodside/
16-Aug-07
Reviewed by/
Date
J. Buckle/
10-Mar-06
J. Buckle/
28-Mar-06
J. Buckle/
15-May-06
J. Buckle/
12-Jun-06
D. Blackadar/
30-Mar-06
D. Blackadar/
15-May-06
D. Blackadar/
12-Jun-06
KMC Approved/
Date
F. Siwak/
23-Mar-06
T. Delong/
30-Mar-06
T. Delong/
15-May-06
T. Delong/
12-Jun-06
Pages
Revised
Remarks
Issued for Review
Issued for Bid
Issued for Construction
Minor Revision to Section
3.1
Terasen References
removed
Revision 2
Page 2 of 11
TABLE OF CONTENTS
1.0
SCOPE ................................................................................................................. 3
2.0
3.0
General ...................................................................................................... 4
3.2
3.3
3.4
3.5
Submittals .................................................................................................. 5
3.5.1
3.5.2
4.0
PRODUCTS ......................................................................................................... 6
4.1
Materials .................................................................................................... 6
4.1.1
4.1.2
4.1.3
4.1.4
5.0
6.0
EXECUTION......................................................................................................... 7
5.1
5.2
5.3
General ...................................................................................................... 7
Survey Work .............................................................................................. 7
Pile Splicing ............................................................................................... 8
5.4
5.5
Pre-Drilling ................................................................................................. 8
Pile Driving................................................................................................. 8
5.6
5.7
Clean-Up.................................................................................................... 9
Inspection ................................................................................................ 10
5.8
Field Coating............................................................................................ 10
Revision 2
Page 3 of 11
1.0
SCOPE
This specification provides the requirements for the supply and installation of
driven steel pipe piles as shown on the drawings and specified herein.
2.0
REFERENCE PUBLICATIONS
Where reference is made to other publications, such references shall be
considered to refer to the latest edition and any revisions thereto approved by the
organization issuing that publication.
Some reference publications are
supplemented or qualified, or both, by specific requirements in this specification;
reference publications should therefore be applied only in the context of this
specification.
Alberta Building Code 1997
British Columbia Building Code 1998
National Building Code of Canada 2005 (Structural Commentaries (Part 4)
From the NBC 1995)
API 5A
API 5L
API 5LS
ASTM A36
ASTM A53
ASTM A252
ASTM D1143
CSA-G40.21-M
CSA W47.1
CSA W48.1
CSA W59-M
CSA-Z245.1
TMPSE-42EF0008
Structural Steel
TMPSE-45ES0012A
Revision 2
Page 4 of 11
3.0
TMPSE-ENV-150
Geotechnical Reports
QUALITY ASSURANCE
3.1
General
The Contractor shall supply the services of an approved third-party
geotechnical firm as required to ensure that soil conditions and piling
construction methods will produce suitable foundation systems. The field
engineer or technician shall monitor the piling installation and record the
results on an acceptable driving record, see Section 3.5.2 of this
specification.
Any difficulties encountered during the pile installation that deviates from
design requirements noted on the drawings or herein shall be reviewed
immediately with Trans Mountain Pipelines L.P.s Designated
Representative.
The Contractor shall be remove, repair, or replace any pile non-compliant
to the drawings or as specified herein at no cost to Trans Mountain
Pipelines L.P.
3.2
3.3
Tolerances
The Contractor shall install piles to the following tolerances:
Finished pile cut off elevation +/- 3 mm from elevation shown on the
drawings
Revision 2
Page 5 of 11
Welding
The Contractor shall complete all welding in accordance to the
requirements of Trans Mountain Pipelines L.P. Specification TMPSE42EF0008, Structural Steel. This is applicable for all shop fabrication, field
pile splicing, and pile cap installations.
3.5
Submittals
3.5.1 Prior to Installation
The Contractor shall, two (2) weeks prior to commencement of pile
installation, provide Trans Mountain Pipelines L.P.s Designated
Representative the following information for review and approval:
Steel producers certificate and copies of steel mill tests for steel
pile materials.
Revision 2
Page 6 of 11
4.0
PRODUCTS
4.1
Materials
4.1.1 Steel Piles
Steel pipe piles shall be new material in accordance with ASTM
A252, Grade 3, 350 Mpa, or approved equal with either straight
longitudinal or spiral seams and plain machine cut ends unless
indicated otherwise on the drawings.
Revision 2
Page 7 of 11
5.0
EXECUTION
5.1
General
The Contractor shall be familiar with soil descriptions and
recommendations provided in the project specific geotechnical report.
The choice of pile driving equipment shall be the responsibility of the
Contractor; the Contractor shall ensure that the pile wall thickness noted
on the drawings is sufficient for the pile driving equipment being utilized.
The Contractor shall ensure conditions at pile locations are adequate to
support piling equipment and shall make provisions for access and
support of piling equipment while driving piles.
The Contractor shall confirm location of existing underground pipelines or
utilities before starting pile driving operation and obtain an excavation /
ground disturbance permit from Trans Mountain Pipelines L.P.s
Designated Representative. If underground pipelines or utilities exist
within 5 m of a pile location, a hole of equal diameter to the piling shall be
hydro trenched to a minimum depth of 3 m or the pipeline or utility shall be
positively identified in its entirety by means of hydro trenching or hand
excavation prior to driving the pile. If an obstruction is encountered during
the hydro trench or hand excavation operation, the Contractor shall report
to Trans Mountain Pipelines L.P.s Designated Representative for further
instructions.
The Contractor shall ensure that he has proper clearance from
aboveground and overhead obstructions to install the piling at the required
locations and operate the equipment safely in respect to his own and other
personnel and equipment in the area.
5.2
Survey Work
The Contractor shall be responsible for establishing the lines, levels, and
locations of pile centers from the construction drawings and from base
lines and benchmarks established by the Contractor and Trans Mountain
Pipelines L.P.
Piles shall be finished to the alignment and elevations within the
tolerances specified on the drawing or herein, whichever is more stringent.
The Contractor shall be responsible for the protection of survey
monuments and shall repair any damage caused, during the course of the
work, to such monuments.
Revision 2
Page 8 of 11
5.4
Pile Splicing
Wherever possible, the Contractor shall supply or fabricate full-length piles
and provide equipment of sufficient capacity to handle full-length piles
without cutting and splicing. Should splicing be required, the Contractor
shall:
Pre-Drilling
Pre-drilling will be completed as shown on the drawings.
Where required, the Contractor shall pre-drill holes at any site where
frozen ground prevents driving piles to the lengths indicated on the
drawings. The diameter of predrilled holes shall not be greater than 90%
of the piles diameter, unless specified otherwise.
5.5
Pile Driving
The Contractor shall install piles to minimize interference with adjacent
piles and in accordance with the approved piling sequence schedule.
Driving of steel piles may be facilitated by the use of different kinds of
driving hammer. The rated energy of the driving hammer, however, shall
be limited to 630 J/cm2 (3000-ft. lb./in2) of pile cross sectional area and a
maximum energy as indicated on the drawings.
Elevation of the pile top shall be taken after each pile is driven to its
required depth. Heaving of the piles shall be checked periodically, and
piles that are heaved shall be re-driven.
Where piles are driven in-groups, they should be driven from the centers
outwards; and, in some cases, it may be necessary to leave some time
between the driving of piles in order to gain greater penetration as the soil
is intensified.
Revision 2
Page 9 of 11
Clean-Up
The Contractor shall dispose of excavated materials such as pre-drill
tailings off site or at a location designated acceptable by Trans Mountain
Pipelines L.P.s Designated Representative.
Upon completion of the work, the Contractor shall clean up and remove or
dispose of excess and waste materials off site.
Before leaving the jobsite, the Contractor shall ensure that the work site is
returned to a condition satisfactory to Trans Mountain Pipelines L.P.s
Designated Representative and at least equal to what existed before the
work commenced. The Contractor shall repair any adjacent work that has
been injured or marred by their operations.
Revision 2
Page 10 of 11
Inspection
The Contractor shall provide access to the work at all times to Trans
Mountain Pipelines L.P.s Designated Representative for checking
materials and pile installation procedures. Trans Mountain Pipelines L.P.s
Designated Representative reserves the right to check and confirm any
pile layout performed by the Contractor.
Trans Mountain Pipelines L.P.s Designated Representative shall have the
right to stop work and require repairs or alterations, if in his opinion, the
materials or workmanship do not meet the requirements of the drawings or
as specified herein. Any omissions or failure on the part of Trans Mountain
Pipelines L.P.s Designated Representative to disapprove or reject any
work or materials shall not be construed as an acceptance of any
defective work or materials.
All piles shall be inspected and approved by Trans Mountain Pipelines
L.P.s Designated Representative before demobilization of the pile driving
rig. Piles that are out of position, below final cut-off elevation, or otherwise
damaged will be rejected. Rejected piles, at the option of Trans Mountain
Pipelines L.P.s Designated Representative, shall be removed and
replaced with new ones or cut off as directed and replaced as necessary
to provide equivalent load carrying capability.
The Contractor shall bear the cost of repair and additional inspection
resulting from faulty materials or workmanship. If any pile is wrongly
located, the Contractor shall be responsible for correcting the pile
placement. Removal and replacement or other work made necessary
through rejection of a damaged or defective pile shall be at the
Contractors expense and at no additional cost to Trans Mountain
Pipelines L.P.
5.8
6.0
Field Coating
The Contractor shall coat the exposed portion of all pilings and pile caps in
accordance to Trans Mountain Pipelines L.P. Specification TMPSE45ES0012A, Field Touch-up and Supplementary Schedule for External
Coating of Aboveground Piping, Valves, Equipment, and Structural Steel.
QUALITY RECORDS
Quality records shall be compiled and maintained by the Contractor as objective
evidence that products were procured, manufactured, delivered, installed, and
tested in accordance to the project drawings, design specifications, applicable
codes and standards, regulations, and contract documents.
Quality records shall be legible, identifiable, and traceable to materials, products,
services, and persons involved.
Revision 2
Page 11 of 11
REVISION INDEX
Rev
No.
A
Prepared by/
Date
A. Hutchinson/
10-Nov-05
A. Hutchinson/
09-Jan-06
A. Hutchinson/
13-Jan-06
A. Hutchinson/
30-Jan-06
S. Woodside/
20-Aug-07
Reviewed by/
Date
D. Rauch/
09-Dec-05
D. Rauch/
30-Jan-06
KMC Approved/
Date
F. Siwak/
23-Dec-05
Pages
Revised
Remarks
Issued for Review
F. Siwak/
11-Jan-06
D. Blackadar/
13-Jan-06
T. Delong/
13-Jan-06
D. Blackadar/
30-Jan-06
T. Delong/
30-Jan-06
Revision 2
Page 2 of 7
TABLE OF CONTENTS
1.0
GENERAL ............................................................................................................ 3
2.0
3.0
4.0
5.0
6.0
7.0
8.0
3.1
Approved Manufacturers............................................................................ 3
3.2
3.3
4.3
4.4
5.2
5.3
APPLICATION ...................................................................................................... 6
6.1
6.2
6.3
6.4
6.5
6.6
INSPECTION........................................................................................................ 7
7.1
7.2
7.3
Revision 2
Page 3 of 7
1.0
GENERAL
This specification prescribes field touch up coatings of aboveground piping,
fittings, valves, equipment, and structural steel and is to be utilized as a
supplement to Trans Mountain Pipeline L.P. Specification TMPSE-45ES0012
External Coating of Aboveground Piping, Valves, Equipment, and Structural
Steel.
The purpose of this supplement is meant for field touch-up coatings of field welds
on piping and structural steel, handling damage to shop coated piping, structural
steel, tagged valves, and equipment, and is not meant for coatings of uncoated
raw materials, which could have been coated prior to shipping.
2.0
REFERENCE PUBLICATIONS
Where reference is made to other publications, such references shall be
considered to refer to the latest edition and any revisions thereto approved by the
organization issuing that publication.
Some reference publications are
supplemented or qualified, or both, by specific requirements in this specification;
reference publications should therefore be applied only in the context of this
specification.
ISO 8501-1
SSPC-PA-1
SSPC-SP-1
Solvent Cleaning
SSPC-SP-2
3.0
COATING SYSTEM
3.1
Approved Manufacturers
The specified coating systems are listed in Table 5.1.A within Trans
Mountain Pipeline L.P. Specification TMPSE-45ES0012 External
Coating of Aboveground Piping, Valves, Equipment, and Structural Steel.
Field touch-up coating shall be completed using the same Coating
Manufacturer that was selected to complete the original application at the
shop.
Revision 2
Page 4 of 7
4.0
3.2
Prime Coat
For the purpose of field touch-up only, it is acceptable to use a Trans
Mountain Pipeline L.P.-approved Surface Tolerant Epoxy in lieu of the
specified Coating System for the prime coat.
3.3
Topcoat Colour
The topcoat colour shall be as specified in Table 5.2.A within Trans
Mountain Pipeline L.P. Specification TMPSE-45ES0012 External
Coating of Aboveground Piping, Valves, Equipment, and Structural Steel.
COATING SCHEDULE
4.1
Structural Steel
Surface prep, prime, and topcoat all areas damaged during shipment,
handling, and field installation, this also includes areas affected by field
welding.
Any galvanized structure that has field damage shall be removed from site
for re-galvanizing, unless otherwise approved in writing by the Trans
Mountain Pipeline L.P. Designated Representative.
All bolts shall be galvanized, cadmium plated, and / or stainless steel;
therefore, additional field coating is not required.
4.2
4.3
Revision 2
Page 5 of 7
5.0
SURFACE PREPARATION
5.1
Solvent Cleaning
Solvent cleaning is a method for removing all visible oil, grease, soil,
drawing and cutting compounds, and other soluble contaminants from
steel surfaces. Solvent cleaning shall be used prior to the application of
coatings and in conjunction with surface preparation methods specified for
the removal of rust, mill scale, or paint.
5.2
Revision 2
Page 6 of 7
6.0
APPLICATION
6.1
Prime Coat
Apply prime coat to recommended dry film thickness as per the
Manufacturers Data Sheet.
Allow sufficient drying time between primer and topcoat as per grade of
catalyst, ambient, and structure skin temperatures and in conjunction with
the Manufacturers Data Sheets.
6.2
Topcoat
Apply topcoat as per Manufacturers Data Sheets; care shall be taken to
ensure coating repair is feathered properly into previously coated areas.
6.3
Film Continuity
Coatings shall be uniformly applied and be free of runs, sags, holidays,
pinholes, voids, mud-cracking, and other anomalies.
6.4
Film Thickness
The Contractor shall provide the tradesmen applying coating materials
with wet film thickness gauges to ensure that the correct film thickness is
being applied.
6.5
Coating Contamination
If, in the judgment of Trans Mountain Pipeline L.P.s Designated
Representative, a coatings performance is jeopardized by contact with
rain, moisture condensation, dust, or other foreign elements, it shall be
removed and replaced.
Revision 2
Page 7 of 7
7.0
8.0
Overspray
Any surfaces contaminated by the Contractor with overspray or otherwise
displaced coating shall be cleaned or recoated to Trans Mountain Pipeline
L.P.s satisfaction.
INSPECTION
7.1
7.2
7.3
Pre-job review of Trans Mountain Pipeline L.P.s Specification TMPSE45ES0012, External Coating of Aboveground Piping, Valves,
Equipment, and Structural Steel, this supplement, and the
Manufacturers data sheets.
REVISION INDEX
Rev
No.
Prepared by/
Date
P. Aldridge/
24-Jan-06
P. Aldridge/
13-Mar-06
P. Aldridge/
07-Apr-06
1
2
S. Woodside/
20-Aug-07
Reviewed by/
Date
J. Buckle &
S. Gundry/
03-Mar-06
J. Buckle &
S. Gundry/
13-Mar-06
J. Buckle &
S. Gundry/
07-Apr-06
KMC Approved/
Date
Pages
Revised
Remarks
T. Delong/
13-Mar-06
D. Blackadar/
18-Apr-06
T. Delong/
18-Apr-06
S. Gundry/
05-Mar-07
D. Blackadar/
05-Mar-07
F. Siwak/
05-Mar-07
F. Siwak/
20-Aug-07
--
T. DeLong/
20-Aug-07
Revision 2
Page 2 of 6
TABLE OF CONTENTS
1.0
GENERAL ............................................................................................................ 3
1.1
Description ................................................................................................. 3
1.2
1.3
2.0
3.0
EXECUTION......................................................................................................... 4
3.1
Preparation ................................................................................................ 4
3.2
Surveying ................................................................................................... 5
Revision 2
Page 3 of 6
1.0 GENERAL
1.1
Description
This specification provides the requirements for facility construction
survey.
1.2
Quality Assurance
The Surveyor must hold a current, valid Land Surveyor registration in the
Province in which the work is being done.
The equipment, methods, and personnel employed to do the surveying
shall be suitable and qualified consistent with the industry standard for
specialists in this type of work.
All boundary surveys completed by the Surveyor shall be compliant with
the approving authorities Disposition Plan Requirements indicating when a
survey is required; when a sketch, without a survey, is allowed; and to an
accuracy suitable for registration as a legal plan.
Horizontal positions and elevations shall be staked or marked to within
3 mm (1/8).
Each survey point shall include elevation and UTM grid coordinates and
zone identification noting the NAD Map Datum.
All locations and elevations shall be confirmed by a second survey.
1.3
Quality Records
Quality records of survey data shall be compiled and maintained by the
Contractors Surveyor as objective evidence that services were completed
in accordance to the project drawings, specifications, applicable codes,
standards, regulations and contract documents.
Quality records shall be legible, identifiable, and traceable to the services
and persons involved.
Revision 2
Page 4 of 6
As-built Drawings
3.0 EXECUTION
3.1
Preparation
Before starting any construction work, the legal boundaries of the lease,
the mainline pipeline right-of-way, and any other overhead or underground
crossing dispositions within or adjacent to the lease must be established
and clearly staked and flagged by the Surveyor.
A survey plan of these boundaries shall be prepared suitable for legal
registration.
The basis for the above survey shall be legal registered plans, which shall
be obtained by the Surveyor from the land titles registry. Any plans
received from Trans Mountain Pipeline L.P.s Designated Representative
shall be verified for completeness using the most up to date registered
plans obtained. Where detailed registered plans do not exist, the
Surveyor shall consult with Trans Mountain Pipeline L.P.s Designated
Representative.
Prior to the start of the survey, the Surveyor shall submit for review to
Trans Mountain Pipeline L.P.s Designated Representative copies of the
Revision 2
Page 5 of 6
Surveying
The Surveyor shall scan the entire work area to identify and stake the
location of all undergrounds, pipelines, telecommunication lines, and
utilities. Coordinates and top-of pipe elevation of pipelines and utilities
exposed by the Contractor by means of hand excavation or hydro-vac
shall be recorded on the survey plans.
The Surveyor shall identify and stake cut-and-fill for rough grading; fill and
surfacing limits; limits-of-construction, sufficient to complete the work to
the required lines, and grades without unnecessary disturbance of lands
both inside and outside the legally established boundaries of the work.
Trans Mountain Pipeline L.P.'s Designated Representative shall be
notified if the limits of construction staked at any location extend beyond
the legal boundaries established for the work for confirmation of
permission to work in any such areas.
During construction, the Surveyor shall identify and stake the location of
all fencing, including lease boundary temporary fencing, facility permanent
fencing (excluding utility sub-station), piling, foundations, building
locations, steel support locations, underground tanks, piping, cables,
conduits, and culverts and other facilities as directed by Trans Mountain
Pipeline L.P.s Designated Representative.
Revision 2
Page 6 of 6
TOPSOIL
TMPSE-CIV-112, Revision 2, August 23, 2007
REVISION INDEX
Rev
No.
Prepared by/
Date
P. Aldridge/
24-Jan-06
P. Aldridge/
13-Mar-06
P. Aldridge/
07-Apr-06
1
2
S. Woodside/
23-Aug-07
Reviewed by/
Date
J. Buckle &
S. Gundry/
03-Mar-06
J. Buckle &
S. Gundry/
13-Mar-06
J. Buckle &
S. Gundry/
07-Apr-06
KMC Approved/
Date
Pages
Revised
Remarks
T. Delong/
13-Mar-06
D. Blackadar/
18-Apr-06
T. Delong/
18-Apr-06
S. Gundry/
05-Mar-07
D. Blackadar/
05-Mar-07
F. Siwak/
05-Mar-07
F. Siwak/
23-Aug-07
--
T. DeLong/
23-Aug-07
Revision 2
Page 2 of 5
Title: TOPSOIL
TABLE OF CONTENTS
1.0
2.0
3.0
MATERIALS ......................................................................................................... 3
4.0
CONSTRUCTION................................................................................................. 4
4.1
4.2
General ...................................................................................................... 4
Placing Topsoil .......................................................................................... 5
Revision 2
Page 3 of 5
Title: TOPSOIL
1.0
GENERAL DESCRIPTION
This specification shall consist of the stripping, loading, hauling, unloading,
placing, and finishing of topsoil material on slopes, ditches, or other areas, as
designated on the plans or as directed by Trans Mountain Pipeline L.P.s
Designated Representative, for the purpose of returning the area disturbed by
construction to an equivalent level of land capability and to create conditions
suitable for establishing a vegetation cover.
Those disturbed areas outside the final fenced perimeter of the pump station
yard that are not required for operations are to be graded as per the grading plan
and restored with topsoil so that vegetation can be established.
2.0
REFERENCE PUBLICATIONS
Where reference is made to other publications, such references shall be
considered to refer to the latest edition and any revisions thereto approved by the
organization issuing that publication.
Some reference publications are
supplemented or qualified, or both, by specific requirements in this specification;
reference publications should therefore be applied only in the context of this
specification.
Environmental Protection Plan, March 2007 (Rev 1) or most recent version
Kinder Morgan Health and Safety Execution Plan
3.0
TMPSE-CIV-100
TMPSE-CIV-100C
TMPSE-CIV-110
TMSPE-CIV-113
Seeding
TMPSE-ENV-150
MATERIALS
Topsoil is the uppermost layer (A-Horizon) of organic matter consisting of sand,
clay particles, and humus (peat and similar decomposed organic material) and is
suitable for supporting the growth of vegetation.
Topsoil shall be obtained from stripping operations performed under the contract,
unless otherwise directed by Trans Mountain Pipeline L.P.s Designated
Representative.
The stripping and stockpiling of topsoil from all sources shall be under the
direction of Trans Mountain Pipeline L.P.s Designated Representative.
Revision 2
Page 4 of 5
Title: TOPSOIL
4.0
CONSTRUCTION
4.1
General
Revision 2
Page 5 of 5
Title: TOPSOIL
Topsoil shall be free from objectionable quantities of sub-soil, roots,
stones, and other deleterious substances. Stripped material that, in the
opinion of Trans Mountain Pipeline L.P.s Designated Representative, is
not suitable shall be disposed of as directed by Trans Mountain Pipeline
L.P.s Designated Representative.
Before stockpiling the topsoil, the boundaries of the stockpile area shall be
staked, stripped, and graded for run-off control as shown on the drawings.
Stockpile sites shall be trimmed to present a neat and tidy appearance,
fenced, and debris resulting from the operation shall be removed and
disposed of, all in a manner satisfactory to Trans Mountain Pipeline L.P.s
Designated Representative.
At locations where a topsoil stockpile is to remain for future reclamation of
the facility, the stockpile shall be shaped to minimize erosion loss and
seeded as per Trans Mountain Pipeline L.P. Specification TMSPE-CIV113, Seeding.
Location and shape of the topsoil stockpile shall be as shown on the
drawings or as directed by Trans Mountain Pipeline L.P.s Designated
Representative.
If shown on the drawings, topsoil stockpiles shall be fenced with a four (4)strand barbed wire fence as per Trans Mountain Pipeline L.P.
Specification TMSPE-CIV-108, Barbed Wire Fencing.
4.2
Placing Topsoil
GROUTING
TMPSE-CIV-135, Revision 2, August 23, 2007
REVISION INDEX
Rev
No.
Prepared by/
Date
P. Aldridge/
07-Feb-06
P. Aldridge/
01-Mar-06
P. Aldridge/
07-Apr-06
Reviewed by/
Date
J. Buckle/
07-Feb-06
J. Buckle/
10-Mar-06
J. Buckle/
07-Apr-06
D. Blackadar/
07-Apr-06
KMC Approved/
Date
F. Siwak/
09-Feb-06
F. Siwak/
02-Apr-06
T. Delong/
07-Apr-06
P. Aldridge/
18-Apr-06
J. Buckle/
18-Apr-06
D. Blackadar/
18-Apr-06
T. Delong/
18-Apr-06
S. Woodside/
23-Aug-07
F. Siwak/
23-Aug-07
--
T. DeLong/
23-Aug-07
A
B
0
Pages
Revised
Remarks
Issued for Review
Issued for Approval
Issued for Construction
Changes to Formatting
and Sections 3.1.3, 3.3,
5.1, and 5.4.7
Terasen references
removed
Revision 2
Page 2 of 26
Title: GROUTING
TABLE OF CONTENTS
1.0
SCOPE ................................................................................................................. 5
2.0
3.0
GENERAL ............................................................................................................ 6
3.1
3.2
Submittals .................................................................................................. 8
3.2.1
3.2.2
3.3
3.4
Supply ....................................................................................................10
Storage and Handling.............................................................................10
3.5
3.6
3.7
3.8
3.9
4.0
Warranty .................................................................................................. 13
4.2
4.3
Revision 2
Page 3 of 26
Title: GROUTING
4.3.5
4.3.6
4.4
4.5
Vibrations ...............................................................................................15
Minimum and Maximum Grout Lift Placement ........................................16
Hot and Cold Weather ............................................................................16
Equipment................................................................................................ 16
4.5.1
4.5.2
4.5.3
4.6
4.7
4.8
Testing ..................................................................................................... 18
4.9
Clean-Up.................................................................................................. 19
4.9.1
5.0
Reports ..................................................................................................19
General .................................................................................................... 19
Non-shrink Epoxy Grout Materials ........................................................... 19
5.3
5.4
5.5
Vibrations ...............................................................................................22
Hot and Cold Temperatures ...................................................................22
Equipment Non-Shrink Epoxy Grout.......................................................23
Clean Mixing Equipment ........................................................................23
Revision 2
Page 4 of 26
Title: GROUTING
5.6
Mixing ...................................................................................................... 23
5.6.1
5.6.2
5.6.3
5.6.4
5.6.5
6.0
Placing ...................................................................................................23
Flowable Grouting ..................................................................................24
Equipment with elevated Interior Plate ...................................................24
Finishing.................................................................................................24
Curing ....................................................................................................25
5.7
Testing ..................................................................................................... 25
5.8
5.9
Clean-Up.................................................................................................. 25
Reports .................................................................................................... 25
6.2
Revision 2
Page 5 of 26
Title: GROUTING
1.0
SCOPE
This specification provides the requirements for the supply and installation of
structural grout as shown on the drawings, it shall include but not be limited to
the following:
Submittals
Training (supplier - installer qualifications)
Supply and storage of grouting materials
Preparation for grouting
Mixing and placement of grout
Finishing and curing of grout.
Testing and Quality Control
2.0
REFERENCE PUBLICATIONS
Where reference is made to other publications, such references shall be
considered to refer to the latest edition and any revisions thereto approved by the
organization issuing that publication.
Some reference publications are
supplemented or qualified, or both, by specific requirements in this specification;
reference publications should therefore be applied only in the context of this
specification.
ACI 304R
ACI 351.1R
ASTM C33
ASTM C109
ASTM C136
ASTM C150
ASTM C531
ASTM C579
Bases
for
Revision 2
Page 6 of 26
Title: GROUTING
3.0
ASTM C827
ASTM C939
ASTM C1019
ASTM C1107
CRD C621
CRD C611
CSA A23.1
Concrete Materials
Construction
CSA A23.2-1B
CSA A23.5
CSA A5
Portland Cement
TMPSE-42EF0006
Cast-in-Place Concrete
TMPSE-42EF0008
Structural Steel
TMPSE-MECH-420A
&
Methods
of
Concrete
GENERAL
All Non-Shrink Cementitious Grouts shall be handled, stored, mixed, placed, and
cured in conformance with this specification, CRD-C621, and the applicable
standards listed above.
All Non-Shrink Epoxy Grouts shall be handled, stored, mixed, placed, and cured
in strict conformance with the Manufacturers written instructions unless stricter
requirements have been specified herein or by the applicable standards.
3.1
Design Requirements
Foundation plates for equipment and structures shall be grouted to
provide full, uniform load transfer between bottom of plate and concrete.
Load transfer to foundation must be through grout, not through double nut
or other leveling devices.
Revision 2
Page 7 of 26
Title: GROUTING
3.1.1 Application Requirements
The grout selected shall be as specified on the design drawings or
as outlined, by application, in this specification. In the case of a
conflict between this specification and the design drawings, the
design drawings shall govern.
Non-shrink Cementitious Grout
Equipment with cast bases.
Column base plates.
Void filler for pump base framework.
Small equipment with flat plate bases.
Non-shrink Epoxy Grout
Generators, blowers, motors, pumps with bases wider than
600 mm (2), and other rotating equipment subject to vibration.
Heavy equipment with impact loading. Use only in areas
specified on the drawings.
Anchor Bolt/Dowel Grout.
Anchor bolt and dowel locations when called for on the drawings
All Other Applications
For all other grout applications not listed above or specified on
drawings, non-shrink cementitious grout shall be used unless
otherwise approved, in writing, by Trans Mountain Pipeline
L.P.s Designated Representative.
3.1.2 Grout Performance Requirements
The grout selected shall meet the following minimum requirements
or as specified on the drawings. In the case of a conflict between
this specification and the design drawings, the design drawings
shall govern:
Non-shrink Cementitious Grout
Grout shall not shrink and shall expand no more than 4.0%
when tested according to ASTM C827 (before set) and shall
expand no more than 0.4% when tested according to CRD
C621 (after set)
Compressive Strength for manufactured grouts Minimum
45 MPa at 28 days if tested according to ASTM C109
Revision 2
Page 8 of 26
Title: GROUTING
3.2
Submittals
3.2.1 Product Data
The Contractor shall submit the Manufacturers data including
limitations for handling, storage, and use of the proprietary grout
prior to delivery to the site. The Contractor shall also submit
imported sand and coarse aggregate sieve analysis to Trans
Mountain Pipeline L.P.s Designated Representative for approval
prior to use (minimum seven (7) working days).
Revision 2
Page 9 of 26
Title: GROUTING
3.2.2 Installation Procedures
The Contractor shall submit Non-Shrink Cementitious Grout, NonShrink Epoxy Grout, and Anchor Bolt / Dowel Grout installation
procedures to Trans Mountain Pipeline L.P.s Designated
Representative for approval. The procedures shall include but not
be limited to:
3.3
Materials
Handling and storage of materials
Sequencing and scheduling
Preparation of concrete and metal surfaces.
Formwork
Inspection
Temperature
Mixing and placing of grout
Curing and finishing
Testing
Reporting
Revision 2
Page 10 of 26
Title: GROUTING
3.4
3.5
3.6
Revision 2
Page 11 of 26
Title: GROUTING
3.7
Temperature
The ambient temperature and the temperature of both the grout and all
elements coming into contact with the grout shall not be less than 10C or
greater than 30C unless specified otherwise by the Manufacturer. All
grout shall be kept at 30C for at least 24 hours following placing unless
specified otherwise by the Manufacturer or this specification. Urethane
grout shall conform to the Manufacturers temperature and curing
requirements.
3.8
Surface preparation;
Materials and mixing procedures;
Installation procedure;
Curing methods;
Temperature requirements; and
Revision 2
Page 12 of 26
Title: GROUTING
Sampling
Non-Shrink Cementitious Grout compressive strength test
Non-shrink Epoxy Grout compressive strength test
The reports for the above testing shall include, but not be limited to:
Revision 2
Page 13 of 26
Title: GROUTING
Upon project completion, the Contractor shall index and submit
their quality documents to Trans Mountain Pipeline L.P.s
Designated Representative. They shall include, but not be limited to
the following:
3.9
4.0
Warranty
The Contractor shall be responsible for the satisfactory installation and
performance of all grout and grout installations. The Contractor shall
guarantee the grout supplied against defects material and workmanship or
design failure under normal usage, for a period of two (2) calendar years
from the date of the grout being placed in service The Contractor shall
repair or replace, without charge, any grouting found defective within the
guarantee period and reimburse Trans Mountain Pipeline L.P. for any
replacement costs involved in the removal and replacement of the
defective grout.
4.2
Masterflow 928
Sika Grout 212 HP
M-Bed Standard
M-Bed Superflow
Or approved equal
Revision 2
Page 14 of 26
Title: GROUTING
The Contractor shall submit imported sand and coarse aggregate sieve
analysis to Trans Mountain Pipeline L.P.s Designated Representative for
approval prior to use (minimum seven (7) working days).
4.3
Revision 2
Page 15 of 26
Title: GROUTING
Revision 2
Page 16 of 26
Title: GROUTING
4.4.2 Minimum and Maximum Grout Lift Placement
The Contractor shall place the grout in lifts, which allow shrinkage
or expansion from the setting of the grout to be minimized. The
minimum and maximum grout lifts placed at any one time shall be
25 mm and 100 mm, respectively, unless authorized in writing by
Trans Mountain Pipeline L.P.s Designated Engineer.
The
Contactor shall provide expansion joints and / or reinforcing bars for
grout pours deeper than 100 mm if shown on the drawings.
4.4.3 Hot and Cold Weather
When placing grout, the temperature of the foundation, base plate,
and grout material shall be within the temperature range
recommended by the Manufacturer and shall be measured with a
surface thermometer.
The Contractor shall refer to the Manufacturers procedures for
temperature limits on installation and curing of the grout.
4.5
Equipment
4.5.1 Grout Mixer
Mortar mixer with moving paddles inside a drum shall be used;
concrete mixer with fins attached to a rotating drum shall not be
used.
4.5.2 Grout Pump
Grout pump shall be a positive displacement type such as
diaphragm or piston pump; screw pump shall not be acceptable.
4.5.3 Clean Mixing Equipment
The Contractor shall clean all mixing equipment and tools to ensure
they are free from water, oil, dirt, grease, grout residue, or other
deleterious substances.
4.6
Revision 2
Page 17 of 26
Title: GROUTING
4.7
Mixing equipment must be free from oil, dirt, grease, leftover grout, and
other deleterious substances, discard leftover grout from previous
batch
Wash out mixer with clean water. Empty out water, leaving mixer wet
Mix only that quantity of grout that can be placed within the working
time of the grout
Do not add admixtures or ingredients other than those specified or
included with the manufactured grout
Add dry grout components to mixer and dry mix; add pre-measured
amount or potable water to mixer, mix grout for not less than three (3)
minutes nor more than five (5) minutes; place grout immediately.
Revision 2
Page 18 of 26
Title: GROUTING
4.7.2 Placing Pumped Non-Shrink Cementitious Grout
Use on large installations and multiple installations; for bases
with shear keys, stiffeners, or other obstructions; for grouting
over great distances; or if venting air is not possible.
Rinse pump, hose, and nozzle with water; wash cleansing plug
through line to ensure it is clear; pump grout slurry through
before starting.
Start grouting at far end of space to be grouted; slowly back out
nozzle so that it is always within the grout to prevent air
entrapment.
Continue placing grout until grout oozes out long entire
perimeter and up through every interior vent hole and grout
hole.
4.7.3 Equipment with Elevated Interior Plate
Grout under entire equipment base to top of exterior plate.
Stop grouting for a short time to allow grout to seal periphery of
exterior plate.
Continue placing grout until grout oozes up through every
interior vent hole and grout hole.
4.7.4 Finishing and Curing Non-Shrink Cementitious Grout
Remove shims (if specified on the drawings) as the grout
becomes capable of supporting the loads with out disturbance.
Just before grout has reached final set, cutback to lower edge of
plate.
A 45 angle cutback is preferred.
Top exposed surfaces shall be steel towelled.
The grout shall be moist cured for a period as per the
Manufacturers recommendations. If required, a suitable curing
and sealing compound shall be applied in accordance with the
Manufacturers recommendations.
Keep temperature of base plate, foundation, and grout between
10C and 32C or as per the Manufacturers recommendation,
for at least 72 hours after placing grout.
4.8
Testing
The Contractor shall field test Non-Shrink Cementitious Grouts. All fieldtesting shall be completed by the pre-approved third-party testing firm.
The field-testing and reports shall include but not be limited to the
following:
Revision 2
Page 19 of 26
Title: GROUTING
4.9
Clean-Up
The Contractor shall remove all formwork, containers, and other items
used in, but not incorporated into this work.
The Contractor shall clean up any spilled or leaked grout to the
satisfaction of Trans Mountain Pipeline L.P.s Designated Representative.
4.9.1 Reports
The Contractor shall submit written reports on each test as soon as
results are available.
5.0
General
The Contractor shall strictly adhere to the Manufacturers instructions,
details on drawings, and specifications for receiving, storing, placing,
curing, and testing of epoxy grout.
5.2
Ceilcote 648 CP
Sikadur 42
Talygrout 100
Revision 2
Page 20 of 26
Title: GROUTING
Or approved equal
5.3
5.4
Revision 2
Page 21 of 26
Title: GROUTING
5.4.4 Formwork
The Contractor shall design and install formwork as outlined:
Revision 2
Page 22 of 26
Title: GROUTING
Revision 2
Page 23 of 26
Title: GROUTING
The Contractor shall in hot weather:
Mixing
The Contractor shall carefully read the Manufacturers instructions as
supplied with grout before starting. Preparation shall be in accordance
with the Manufacturers instructions and approved installation procedures.
All epoxy grout components shall be conditioned to a temperature range
recommended by the Manufacturer prior to mixing.
The Contractor shall use only the pre-measured components supplied;
solvent shall not be added to change mix consistency.
During hot weather, the Contractor shall allow mixed resin and hardener to
remain without aggregate for more than five (5) minutes.
The Contractor shall mix only that quantity of grout that can be placed
within working time of the grout.
5.6.1 Placing
The grout mix must be of flowable consistency.
The Contractor shall place grout within the working time of the
grout; temperature shall affect working time of epoxy grout; grout
that is not placed within working time of the grout shall be
discarded.
The Contractor shall place grout from one (1) side of plate to the
other to avoid trapping air.
Revision 2
Page 24 of 26
Title: GROUTING
The Contractor shall place grout from one (1) long side or
equipment base to the other, in one (1) direction only.
If grout must be placed through grout holes, the Contractor shall
place from one (1) hole continuously until grout has passed second
hole; continue placing grout from next grout hole in similar fashion.
The Contractor shall check for leaks constantly and shall seal leaks
immediately to prevent voids.
The use of vibrators is not permitted. The use of steel straps is
permitted to move the grout into position.
Chaining is not permitted.
5.6.2 Flowable Grouting
Use moveable head box having an inclined plane to direct grout
beneath equipment base in a manner to minimize trapped air
and bubble formation.
For placing large volumes of grout continuously the Contractor
shall use head box with minimum 0.085 m3 (3 ft3) volume.
Fill head box to top and plunge grout down to top of base plate
and shall continue until grout rises above bottom of base plate
on far side.
Always keep surface of grout in head box above top of base
plate to prevent trapping air.
Pumping epoxy grout is permitted if so required.
5.6.3 Equipment with elevated Interior Plate
Grout under entire equipment base to top of exterior plate.
Stop grouting for a short time to allow grout to seal periphery of
exterior plate.
Continue placing grout until grout oozes up through every
interior vent hole and grout hole.
5.6.4 Finishing
Remove shims, designed to be removed, as the grout becomes
capable of supporting the loads with out disturbance.
Follow the Manufacturers recommendations for finishing grout
surfaces.
Epoxy grout cannot be trimmed after set, top surfaces may be
trowelled.
Revision 2
Page 25 of 26
Title: GROUTING
5.6.5 Curing
Cure grout according to the Manufacturers instructions.
Do not moist cure epoxy grout.
Keep forms in place overnight except for fast curing grouts.
Keep temperature of base plate, foundation, and grout between
10C and 32C for at least 24 hours after placing grout.
5.7
Testing
The Contractor shall field test Non-Shrink Epoxy Grouts. All field-testing
shall be completed by the pre-approved third-party testing firm. The fieldtesting and reports shall include but not be limited to the following:
5.8
Clean-Up
The Contractor shall remove all formwork, containers, and other items
used in, but not incorporated into this work.
The Contractor shall clean-up any spilled or leaked grout to the
satisfaction of Trans Mountain Pipeline L.P.s Designated Representative.
5.9
Reports
The Contractor shall submit written reports on each test as soon as results
are available.
Revision 2
Page 26 of 26
Title: GROUTING
6.0
6.2
Brutem MP
Talygrout 100
Sikadur 32 Hi-Mode
Anchor Fix 2
Or approved equal