TECHNICAL
REQUIREMENTS
Part n 10
Roofing
CTI - 28/10/98
AR/SR
1/5
TECHNICAL SPECIFICATIONS
SECTION N 10
ROOFING
Page
REQUIREMENTS OF CURRENT REGULATIONS
1.
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
1.11
DESIGNATION OF PANELS
CHARACTERISTICS OF RIBBED PANELS
SUPPORTS
ROOF PITCHES
OVERLAP
PURLIN SPACING
INSTALLATION AND FASTENINGS
ROOF PARTS
CONDENSATION
ROOF SPACE VENTILATION
ROOF SPACE LIGHTING
CTI - 28/10/98
AR/SR
2/5
DESIGNATION OF PANELS
The panels will be in ribbed, galvanised prefabricated steel sheet. Profiles will be
selected by the Employer from suppliers' ranges.
1.2
For applications in an industrial environment, the ribbed plates will be given a zinc
coating of more than 300 g/m on both sides and possibly extending to 600 g/m on
both sides.
The corrosion resistance of accessories and fastenings will be the same as that of
the panels.
The hot galvanised fastenings will receive a zinc coating of 2 g/dm3.
The panels must not come into contact with copper or woods such as oak, chestnut
or cedar.
Panel lengths will be chosen by the Contractor who will submit a detailed drawing
corresponding with the overall style of the structure.
The mastic used will preferably be adapted for gun application.
1.3
SUPPORTS
Ribbed panels may be attached to purlins made of metal, wood or concrete. The
cross-sections of the purlins will be worked out according to the distance between
the main rafters, taking account of any overloads due to weather (Snow and Wind
Rules).
1.4
OVERLAPS
- Transverse: To be in accordance with roof pitches.
- Longitudinal: this affects the outer rib and should face away from the
prevailing rainbearing winds.
1.5
PURLIN SPACING
CTI - 28/10/98
AR/SR
3/5
The ribbed panels will be laid directly on the framework. The main ribs are arranged
on top and orientated down the line of greatest slope.
1.6.1
Attachments will always be at the top of the main ribs and at the ridgepole side
with respect to the purlins. The galvanised steel sheet roofing will be attached to
the framework by means of a secondary frame usually consisting of horizontal
metal sections (I, U, L) or wooden sections in certain cases.
The secondary framework will rest upon a metal or wood framework or, in certain
cases, a reinforced concrete structure.
1.6.2
DISPOSITION OF FASTENINGS
The hook bolts or draw bolts will be placed with at least 2 per panel and per
purlin on the lateral ribs.
1.7
ROOF PARTS
1.7.1
PROJECTIONS
RIDGE POLES
EDGES
PENETRATIONS
Light frames and pipe penetrations will consist of special panels. Duct
penetrations will be made using galvanised steel sheet panels with the same ribs
as the normal roofing elements.
1.7.6
STENCH PIPES
Sewer stench pipes will be made up using components similar to the roofing
elements and have a downward bend at one end.
Ridgepole vents will be of identical design with an upward bend at one end.
CTI - 28/10/98
AR/SR
4/5
1.7.7
GUTTERS
CHANNELS
FALLPIPES
Fallpipes will be made of galvanised steel sheet or PVC. Their section may be
circular, square or rectangular.
1.8
CONDENSATION
either at the gable ends, if these are not more than 12 m apart;
1.8.2
1.8.3
If the building is over 12 m long, and if there are openings in the gable ends,
intermediate openings will be arranged approximately every 12 m (cross-section of
openings 1/250 of the roofed area arranged half gutter, half ridge pole).
The second approach is to lay a vapour barrier on the ceiling, always under the
thermal insulation. This vapour barrier may consist of a sheet of polyethylene, kraft
paper, epoxy paint, rubber-based paint, etc.
1.9
This must always be provided. The section of the air openings will be at least 1/500
of the roofed area (1/250 of the roofed area in a moist atmosphere).
1.10 ROOF SPACE LIGHTING
Lighting will be obtained:
a) By framed roof lights.
b) By translucent panels in artificial resin with the same ribs as those on the
roofing elements and laid in the same way.
CTI - 28/10/98
AR/SR
5/5