Professional Documents
Culture Documents
The electrical load list (load schedule) is an estimate of the instantaneous electrical loads operating in a
facility, in terms of active, reactive and apparent power (measured in kW, kVAR and kVA respectively).
The load list is usually categorized by switchboard or occasionally by sub-facility / area.
Calculation Methodology
There are no standards governing load lists and therefore this calculation is based on generally accepted
industry practice. The following methodology assumes that the load list is being created for the first
time and is also biased towards industrial plants. The basic steps for creating a load list are:
Process loads - are the loads that are directly relevant to the facility. In factories and
industrial plants, process loads are the motors, heaters, compressors, conveyors, etc. that
form the main business of the plant. Process loads can normally be found on either
Mechanical Equipment Lists or Process and Instrumentation Diagrams (P&ID's).
Non-process loads - are the auxiliary loads that are necessary to run the facility, e.g.
lighting, HVAC, utility systems (power and water), DCS/PLC control systems, fire safety
systems, etc. These loads are usually taken from a number of sources, for example HVAC
engineers, instruments, telecoms and control systems engineers, safety engineers, etc.
Some loads such as lighting, UPS, power generation auxiliaries, etc. need to be estimated
by the electrical engineer.
Rated power is the full load or nameplate rating of the load and represents the maximum
continuous power output of the load. For motor loads, the rated power corresponds to the
standard motor size (e.g. 11kW, 37kW, 75kW, etc.). For load items that contain sub-loads
(e.g. distribution boards, package equipment, etc.), the rated power is typically the
maximum power output of the item (i.e. with all its sub-loads in service).
Absorbed power is the expected power that will be drawn by the load. Most loads will
not operate at its rated capacity, but at a lower point. For example, absorbed motor loads
are based on the mechanical power input to the shaft of the driven equipment at its duty
point. The motor is typically sized so that the rated capacity of the motor exceeds the
expected absorbed load by some conservative design margin. Where information
regarding the absorbed loads is not available, then a load factor of between 0.8 and 0.9 is
normally applied.
Power factor of the load is necessary to determine the reactive components of the load
list. Normally the load power factor at full load is used, but the power factor at the duty
point can also be used for increased accuracy. Where power factors are not readily
available, then estimates can be used (typically 0.85 for motor loads > 7.5kW, 1.0 for
heater loads and 0.8 for all other loads).
Efficiency accounts for the losses incurred when converting electrical energy to
mechanical energy (or whatever type of energy the load outputs). Some of the electrical
power drawn by the load is lost, usually in the form of heat to the ambient environment.
Where information regarding efficiencies is not available, then estimates of between 0.8
and 1 can be used (typically 0.85 or 0.9 is used when efficiencies are unknown).
Voltage Level
What voltage level and which switchboard should the load be located? Large loads may need to be on
MV or HV switchboards depending on the size of the load and how many voltage levels are available.
Typically, loads <150kW tend to be on the LV system (400V - 690V), loads between 150kW and 10MW
tend to be on an intermediate MV system (3.3kV - 6.6kV) where available and loads >10MW are
usually on the HV distribution system (11kV - 33kV). Some consideration should also be made for
grouping the loads on a switchboard in terms of sub-facilities, areas or sub-systems (e.g. a switchboard
for the compression train sub-system or the drying area).
Load duty
Loads are classified according to their duty as either continuous, intermittent and standby loads:
1) Continuous loads are those that normally operate continuously over a 24 hour period, e.g.
process loads, control systems, lighting and small power distribution boards, UPS systems, etc.
2) Intermittent loads that only operate a fraction of a 24 hour period, e.g. intermittent pumps
and process loads, automatic doors and gates, etc.
3) Standby loads are those that are on standby or rarely operate under normal conditions, e.g.
standby loads, emergency systems, etc.
Note that for redundant loads (e.g. 2 100% duty / standby motors), one is usually classified as
continuous and the other classified as standby. This if purely for the purposes of the load list and does
not reflect the actual operating conditions of the loads, i.e. both redundant loads will be equally used
even though one is classified as a standby load.
Load criticality
Loads are typically classified as either normal, essential and critical:
1) Normal loads are those that run under normal operating conditions, e.g. main process loads,
normal lighting and small power, ordinary office and workshop loads, etc.
2) Essential loads are those necessary under emergency conditions, when the main power supply
is disconnected and the system is being supported by an emergency generator, e.g. emergency
lighting, key process loads that operate during emergency conditions, fire and safety systems,
etc.
3) Critical are those critical for the operation of safety systems and for facilitating or assisting
evacuation from the plant, and would normally be supplied from a UPS or battery system, e.g.
safety-critical shutdown systems, escape lighting, etc.
Where
Notice that the loads have been categorized into three columns depending on their load duty
(continuous, intermittent or standby). This is done in order to make it visually easier to see the load duty
and more importantly, to make it easier to sum the loads according to their duty (e.g. sum of all
continuous loads), which is necessary to calculate the operating, peak and design loads.
Operating load
The operating load is the expected load during normal operation. The operating load is calculated as
follows:
Where
Peak load
The peak load is the expected maximum load during normal operation. Peak loading is typically
infrequent and of short duration, occurring when standby loads are operated (e.g. for changeover of
redundant machines, testing of safety equipment, etc.). The peak load is calculated as the larger of
either:
or
Where
Design load
The design load is the load to be used for the design for equipment sizing, electrical studies, etc. The
design load is generically calculated as the larger of either:
or
Where
The design load includes a margin for any errors in load estimation, load growth or the addition of
unforeseen loads that may appear after the design phase. The load list is thus more conservative and
robust to errors. On the other hand however, equipment is often over-sized as a result. Sometimes the
design load is not calculated and the peak load is used for design purposes.
Worked Example
Step 1: Collect list of loads
Consider a small facility with the following loads (load redundancy) identified:
Abs.
Load
Rated
Load
PF
Eff.
Vapour compressor A
750kW
800kW
0.87
0.95
Vapour compressor B
750kW
800kW
0.87
0.95
Recirculation pump A
31kW
37kW
0.83
0.86
Recirculation pump B
31kW
37kW
0.83
0.86
Sump pump
9kW
11kW
0.81
0.83
Firewater pump A
65kW
75kW
0.88
0.88
Firewater pump B
65kW
75kW
0.88
0.88
HVAC unit
80kW
90kW
0.85
0.9
AC UPS System
9kW
12kW
0.85
0.9
7kW
10kW
0.8
0.9
4kW
5kW
0.8
0.9
Load Description
Rated
Load
Voltage
Duty
Criticality
800kW
6.6kV
Continuous
Normal
800kW
6.6kV
Standby
Normal
Recirculation pump A
37kW
415V
Continuous
Normal
Recirculation pump B
37kW
415V
Standby
Normal
Sump pump
11kW
415V
Intermittent
Normal
Firewater pump A
75kW
415V
Standby
Essential
Firewater pump B
75kW
415V
Standby
Essential
HVAC unit
90kW
415V
Continuous
Normal
AC UPS System
12kW
415V
Continuous
Critical
10kW
415V
Continuous
Normal
5kW
415V
Continuous
Essential
Intermittent
Standby
Load Description
Abs
Load
PF
Eff.
P
(kW)
Q
(kVAr)
P
(kW)
Q
(kVAr)
P
(kW)
Q
(kVAr)
Vap. compressor A
750kW
0.87
0.95
789.5
447.4
Vap. compressor B
750kW
0.87
0.95
789.5
447.4
Recircul. pump A
31kW
0.83
0.86
36.0
24.2
Recircul. pump B
31kW
0.83
0.86
36.0
24.2
Sump pump
9kW
0.81
0.83
10.8
7.9
Firewater pump A
65kW
0.88
0.88
73.9
39.9
Firewater pump B
65kW
0.88
0.88
73.9
39.9
HVAC unit
80kW
0.85
0.9
88.9
55.1
AC UPS System
9kW
0.85
0.9
10.0
6.2
Normal lighting
distribution board
7kW
0.8
0.9
7.8
5.8
Essential lighting
distribution board
4kW
0.8
0.9
4.4
3.3
SUM TOTAL
936.6
542.0
10.8
7.9
973.3
551.4
Q (kW)
936.6
542.0
5.4
4.0
97.3
55.1
789.5
447.4
Operating load
942
546.0
Peak load
1,731.5
993.4
Design load
1,825.7
1,047.9
Normally you would separate the loads by switchboard and calculate operating, peak and design loads
for each switchboard and one for the overall system. However for the sake of simplicity, the loads in this
example are all lumped together and only one set of operating, peak and design loads are calculated.
Operating Scenarios
It may be necessary to construct load lists for different operating scenarios. For example, in order to size
an emergency diesel generator, it would be necessary to construct a load list for emergency scenarios.
The classification of the loads by criticality will help in constructing alternative scenarios, especially
those that use alternative power sources.
What Next?
The electrical load list is the basis for the sizing of most major electrical equipment, from generators to
switchgear to transformers. Using the load list, major equipment sizing can be started, as well as the
power system studies. A preliminary load list will also indicate if there will be problems with available
power supply / generation, and whether alternative power sources or even process designs will need to
be investigated.
Load Redundancy
Load redundancy is the duplication of load equipment so that an alternative can be used in case one fails
or needs to be maintained. Redundancy is common in industrial plants where loads such as pumps, fans,
compressors, etc. need to operate continuously. In order for there to be minimal plant downtime, these
loads are replicated to ensure some redundancy.
Most commonly, the use of duty and standby equipment ("A" and "B" loads) is used. In a scenario
where the A/B loads are 100% redundant, the equipment can be referred to as "2 x 100%", meaning that
there are 2 equipment items capable of delivering 100% output each.
Other examples of redundant (and semi-redundant) configurations:
2 50% - 2 equipment items capable of delivering 50% output each. If one fails, then output is
reduced to 50%.
3 50% - 3 equipment items capable of delivering 50% output each. In this case, there is always
one equipment item out of service / on standby
3 33% - 3 equipment items capable of delivering 33% output each. If one fails, then output is
reduced to 66%.