You are on page 1of 11

Oracle

Exam 1Z0-485
Oracle Exadata Database Machine 2014 Implementation
Essentials

Oracle Exadata 1Z0-485

QUESTION NO: 1
You get a Host Unreachable error when you attempt to connect to a server through a
network terminal command line. What are two other ways in which you can connect?
A.
B.
C.
D.
E.

Use the ILOM Web GUI.


Use the dcli command at the root prompt on a database node.
Attach a terminal device to the back panel of the server with a serial cable.
Connect by using SQL *Plus.
Log in as root on the database node using the Net1 IP address.

Answer: A,C
Explanation Buy Full Product
QUESTION NO: 2
Identify three Exadata Storage Server software processes and their purpose?
A. CELLSRV: The Cell Server is responsible for servicing disk I/O and predicate processing
offload.
B. CELLSRV: The Cell Server is responsible for balancing workload to other storage servers.
C. MS: The Management Server is responsible for storage cell management and configuration.
D. MS: The Management Server is responsible for starting a local Enterprise Manager agent.
E. RS: The Restart Server is responsible for Automatic Storage Management (ASM) instance
restart.
F. RS: The Restart Server is responsible for CELLSRV and MS monitoring and restart.
Answer: A,C,F
Explanation Buy Full Product

QUESTION NO: 3
Your customer wants to increase the size of the DATA disk group on the Exadata systems.
The customer is currently using 600 GB disks. Which two are the best options that you
would recommend?
A. adding a High Capacity Storage expansion rack

www.exadata-certification.com

Oracle Exadata 1Z0-485

B.
C.
D.
E.

expanding the Exadata rack from a Half Rack to a Full Rack


moving underutilized grid disks from the RECO disk group to DATA
adding a ZFS storage appliance
adding a High Performance Storage expansion rack

Answer: B,E
Explanation Buy Full Product

QUESTION NO: 4
When would be the best time to run an Exadata health check (exachk)?
A. before patching, before upgrades, before backups, and on a regular basis
B. after patching, after upgrades, and after backups
C. only when advised by Oracle Support
D. before and after patching, when advised by Oracle Support, and on a regular basis
E. only after a hardware failure
F. monthly and after a hardware failure
Answer: D
Explanation Buy Full Product
QUESTION NO: 5
Which two statements describe correct network configuration for Exadata Database Machine?
A. The InfiniBand network subnet manager runs on all database servers to achieve
High Availability.
B. Oracle Clusterware communication is configured to use the management network.
C. The InfiniBand network interfaces on Linux servers are configured using activepassive bonding.
D. Database connections to the SCAN listener route through the Ethernet switch in the
Exadata rack.
E. Database servers are deployed with three logical network interfaces configured:
management, client access, and private.

www.exadata-certification.com

Oracle Exadata 1Z0-485

Answer: C,E
Explanation Buy Full Product

QUESTION NO: 6
Which Exadata feature eliminates unnecessary data transfers between database nodes
and storage?
A. database views
B. InfiniBand networking
C. Flash Cache
D. high performance SAS2 disk drives
E. cell offloading
Answer: E
Explanation Buy Full Product
QUESTION NO: 7
Identify the correct steps required to upgrade a 1/8th rack of Exadata to a 1/4th rack.
A.
Activate all cores by using a software command.
Activate all hard drives and flash drives.
Create the grid disks.
Expand the Oracle ASM diskgroups. Review the new configuration.

B.
Remove the doors of the 1/8th rack.
Add an additional Sun Datacenter InfiniBand Switch.
Add the new servers.
Cable the Database Servers in the rack.
Cable the Exadata Storage Servers in the rack.
Close the rack.
Configure the new hardware.

www.exadata-certification.com

Oracle Exadata 1Z0-485

C.
Activate all cores by using a software command.
Activate all hard drives and flash drives.
Answer: A
Explanation Buy Full Product

QUESTION NO: 8
You are asked to enable Write Back Flash Cache for one of your customers X3-2 Full Rack in a
rolling fashion. Put the following steps in the right order:

A) Set flash Cache mode to writeback.


B) Inactivate all grid disks and shut down cellsrv.
C) Drop the Flash Cache.
D) Verify that cell for flash cache mode is writeback.
E) Create the Flash Cache.
F) Startup cellsrv and activate all grid disks.
G) Check griddisk asmdeactivationoutcome and asmmodestatus for all grid disks to ensure that
all grid disks on all cells are set to Yes and online, respectively.
A.
B.
C.
D.

G. B, C, A, F, E, D, and G
G, A, B, C, F, E, D, and G
G, C, B, A, F, E, D, and G
G, E, C, B, F, A, D, and G

Answer: C
Explanation Buy Full Product

QUESTION NO: 9
Which statement is true about instance caging setup?
A. Instance caging is the right approach to make sure that database instances are not
stealing memory from each other.
B. The CPU Resource Manager and IORM need to be enabled to make instance caging to
work as expected.
www.exadata-certification.com

Oracle Exadata 1Z0-485

C. Database instances need to be restarted to make changes to cpu_count effective.


D. For a system with 16 threads, the sum of cpu_count for all databases should not be higher
than 32 to prevent oversubscribing
E. The init.org parameter resource_manager_plan should be set.
Answer: C
Explanation Buy Full Product

QUESTION NO: 10
Which two statements are true about Exadata memory capabilities?
A.
B.
C.
D.
E.

X3-8 can be purchased in a Half Rack configuration with 2 TB of memory.


X3-2 memory can be expanded to 512 GB per node from 256 GB.
X3-2 memory can be upgraded to use Flash in the compute nodes.
X3-8 memory is fixed at 4 TB per a Rack.
X3-2 can be purchased in a Half Rack configuration with 256 GB per node.

Answer: D,E
Explanation Buy Full Product
QUESTION NO: 11
Identify the relevant steps in the correct order for activating an Auto Service Request
(ASR) configuration.
1. Add SNMP traps manually or using OneCommand.
2. Install ASR Manager.
3. Activate a node on ASR Manager.
4. Validate the configuration.
5. Register ASR Manager with Oracle.
A. 2, 5, 1, 3, and 4
B. 2, 4, I, 3, and 5
C. 5, 2, 4, 1, and 3
www.exadata-certification.com

Oracle Exadata 1Z0-485

D. 5, 4, 2, 1, and 3
Answer: A
Explanation Buy Full Product

QUESTION NO: 12
You are going to set up grid disks for your customer. Which is the best practice to use when
defining grid disks for a Storage Server?
A. Create a grid disk for every table space.
B. Create two grid disks, one for data and one for recovery.
C. Create two grid disks, one for tables and one for Indexes.
D. Create a grid disk for each table.
Answer: B
Explanation Buy Full Product

QUESTION NO: 13
Striping data across disk is performed with what software?
A. CELLSRV
B. IORM
C. OEL
D. ASM
Answer: D
Explanation Buy Full Product

QUESTION NO: 14
Which three types of classification can you use to prioritize I/O requests with IORM?
A. Based on Database Manager consumer_group
B. Based on an Intradatabase Plan
C. Based on a Category Plan
www.exadata-certification.com

Oracle Exadata 1Z0-485

D. Based on the priority of the background process


Answer: A,B,C
Explanation Buy Full Product

QUESTION NO: 15
Which three statements are true with regard to I/O Resource plans?
A. You define inter-database resource plans with Database Resource Manager.
B. You define Intra-database resource plans with Database Resource Manager.
C. You define categories with Database Resource Manager.
D. You enable a category plan with CellCLI.
Answer: B,C,D
Explanation Buy Full Product

QUESTION NO: 16
Why is performing an incremental backup of data from an Exadata Storage Server likely faster
than backing up data from normal storage?
A. All data on the Exadata Storage Server is compressed.
B. All backups from the Exadata Storage Server are compressed.
C. Recovery Manager always uses more threads to perform backups from an Exadata Storage
Server.
D. Offload processing finds only the changed blocks.
Answer: D
Explanation Buy Full Product

QUESTION NO: 17
You are asked to install EM 12c agent. Put the following steps in right order.
1. Select operating system
2. Add host target

www.exadata-certification.com

Oracle Exadata 1Z0-485

3. Select add target from setup menu


4. Add target manually
5. Review Provided Information
6. Provide user credentials
7. Deploy Agent
A. 3,4,2,1,6,5,7
B. 1,3,2,4,6,5,7
C. 4,3,2,1,6,5,7
D. 3,2,4,1,6,5,7
E. 3,1,3,2,6,5,7
Answer: A
Explanation Buy Full Product

QUESTION NO: 18
You are asked to integrate Exadata with EM 12c. Put below steps in right order.
1. Discover Exadata component
2. Launch auto discovery
3. Specify component credentials
4. Deploy the management agents (OEM 12c Agent) on compute nodes
5. Review configurations and complete setup
A. 1,4,2,3,5
B. 2,4,2,3,5
C. 4,2,3,5,1
D. 1,3,4,2,5
Answer: C
Explanation Buy Full Product

www.exadata-certification.com

Oracle Exadata 1Z0-485

QUESTION NO: 19
What are three unique benefits of Exadata Storage Server compared to traditional storage
servers?
A. Larger disk sizes
B. Smart storage capabilities
C. Higher storage network bandwidth
D. Higher RAM capacity
E. Integrated database I/O resource management
Answer: B,C,E
Explanation Buy Full Product

QUESTION NO: 20
List three activities which will use exadata storage server features.
A. Tablespace Creation
B. SQL Predicate with where clause
C. Data mining scoring
D. Storage Index
Answer: B,C,D
Explanation Buy Full Product

QUESTION NO: 21
Put below steps in right order to create DBFS file system
1. Mount File System
2. Create Directory
3. Create DBFS file system
4. Grant privileges to user
5. Tablespace Creation
6. User creation
7. Connect to database with created user

www.exadata-certification.com

Oracle Exadata 1Z0-485

A. 5,6,4,7,3,2,1
B. 1,5,6,4,7,3,2
C. 2,5,4,6,3,7,1
D. 2,5,6,4,3,7,1
E. 2,5,6,4,7,3,1
Answer: E
Explanation Buy Full Product

www.exadata-certification.com