You are on page 1of 39

LARSEN & TOUBRO LIMITED- ECCD

ELECTRICAL AND TELECOM UTILITIES FOR SUPPORT SERVICE AREA


PHASE I & II AND WEST END EXTENSION, RAS LAFFAN
Doc No:
2908-BG35-4033

Contract No:
GC 081117B0

Rev.
Date

Page 1 of 10

0
13-02-11

RASLAFFAN CITY
33/11KV SS1 SUBSTATION
SAT FOR LVAC ELECTRICAL EQUIPMENT TEST

Title of Document

Name of project

ELECTRICAL AND TELECOM UTILITIES FOR SUPPORT SERVICE AREA


PHASE I & II AND WEST END EXTENSION, RAS LAFFAN

Contract No

GC 081117B0

Name of client

Qatar Petroleum (QP)

Name of main contractor

LARSEN & TOUBRO LTD ECC DIVISION


Electrical

Discipline
Document No.

Rev.
No.

Date

2908-BG35-4033

Prepared by

Reviewed by

Reviewed by

Approved by
PM

Approved by
Customer Rep.

LARSEN & TOUBRO LIMITED- ECCD


ELECTRICAL AND TELECOM UTILITIES FOR SUPPORT SERVICE AREA
PHASE I & II AND WEST END EXTENSION, RAS LAFFAN
Doc No:
2908-BG35-4033

Contract No:
GC 081117B0

Page 2 of 10

CONTENTS

SL.NO

DESCRIPTION

Title & Approval sheet

Contents

Purpose

Introduction

Abbreviation used

Guidelines to organize the SAT for LVAC

Documentation required

List of LVAC Electrical Equipment test and Procedure

Test Report

Rev.
Date

0
13-02-11

LARSEN & TOUBRO LIMITED- ECCD


ELECTRICAL AND TELECOM UTILITIES FOR SUPPORT SERVICE AREA
PHASE I & II AND WEST END EXTENSION, RAS LAFFAN
Doc No:
2908-BG35-4033

3. PURPOSE:

Contract No:
GC 081117B0

Page 3 of 10

Rev
Date

0
13-02-11

This test document specifies the scope, the item to be tested and the test procedures for the

verification of LVAC switchboard. This test document provides systematic procedures in line with Contract
requirements and specifications to conduct the SAT Successfully
WHO SHOULD USE THIS DOCUMENT This document is for Site Acceptance Test and Testing engineer, Quality
Assurance personnel, L&T / QP representatives to test and evaluate the system.

4.

Introduction
The purpose of this document is to define the Site Acceptance Test procedure of 33/11kv SS1 LVAC
switchboard equipment for L&T contract with QP project GC 081117B0 Epic For Electrical And Telecom
Utilities For Support Services Area Phase I & II And West End Extension Of Raslaffan City.
The tests are performed by approved Testing engineers and witnessed by L&T / QP nominated representatives.
Each test, which will be signed off upon completion by Testing engineers and L&T / QP representatives.
This complete SAT document is in two parts. This part specify the Site Acceptance Procedure and the next part
specify the SAT Test Sheets of the equipment and functionalities
Comments are noted in separate Incident and Correction Reports (snag list) attached to the SAT Procedure.
The Site Acceptance Certificate will be signed off upon satisfactory completion of the test by both Testing
engineers and L&T / QP representatives.

5. Abbreviation Used
SAT -Site Acceptance Test
GA -General Arrangement
SLD -Single Line Diagram
QP -Qatar Petroleum
L&T -Larsen & Toubro
LVAC-Low Voltage Alternating Current

6.

GUIDELINES TO ORGANIZE SAT FOR LVAC ELECTRICAL EQUIPMENT.


Testing coordinator Responsibility:
Obtain Consolidated Permit to Work (CPW).
The Test panel is ready for pre-commissioning tests.
Availability of Qualified approved testing engineer.
Availability of tools and Test Kits and equipments with valid calibration certificate.
Stable Power Supply for testing.

LARSEN & TOUBRO LIMITED- ECCD


ELECTRICAL AND TELECOM UTILITIES FOR SUPPORT SERVICE AREA
PHASE I & II AND WEST END EXTENSION, RAS LAFFAN
Doc No:
2908-BG35-4033

Contract No:
GC 081117B0

Page 4 of 10

Rev
Date

0
13-02-11

QA/QC Engineer:
Ensure all AFC drawings are available and work procedures are as per QP standards.
Preparing request for inspections and getting clearances.
Complying, Inspecting as per the checklist and maintaining all quality records, standards.
Check all Testing instruments used are calibrated.

7. DOCUMENTATION REQUIREMENT:
Approved Drawing, Two sets of Drawings one for the witness engineer and one for the Testing engineer.
Catalogues, O&M Manuals, all relevant specifications and protection requirements.
Approved site test procedures and format.
Weekly Pre Commissioning & Testing Schedule.
Clearance from QA/QC to proceed with Testing

8.

LIST OF LVAC ELECTRICAL EQUIPMENT TEST


I.

Current Transformer test

II.

Voltage Transformer test

III.

MCCB test

IV.

Breaker with Micro logic Relay test

V.

Meter calibration

VI.

Auxiliary relay test

VII.

Busbar contact resistance test

VIII.

High voltage test

A.

Current Transformer test:


Purpose: The following Tests shall be performed and Witnessed by the Clients to ensure the Current
Transformer operations and its Specific Functions following the Approved SLD.
Procedure: All tests shall be in accordance with IEC standards IEC 60044 1
a.)The Visual Inspection shall include
Check nameplate information for correctness
Check tightness of all CT secondary Terminal
Check that all grounding cables are securely connected
Check color codes(or)sleeves for secondary wiring and size of wires against specs
Check proper lugs has been used in termination
Check CTs location physically and secondary terminal labeling printed

LARSEN & TOUBRO LIMITED- ECCD


ELECTRICAL AND TELECOM UTILITIES FOR SUPPORT SERVICE AREA
PHASE I & II AND WEST END EXTENSION, RAS LAFFAN
Doc No:
2908-BG35-4033

Contract No:
GC 081117B0

Page 5 of 10

Rev
Date

0
13-02-11

b.)The Electrical Test shall include


Insulation Resistance Measurement
Polarity Tests
CT Winding Resistance
Knee Point Voltage Measurement
Ratio Test
c.)Insulation Resistance Measurement:
Purpose: To ensure that the CT is without any insulation failure.
Procedure: As per the standard IEC 60076, the calibrated Instrument was used to apply the +ve DC voltage to
Test point and the ve DC terminal for reference point (i.e. Earth) for various condition as per the attached format
the test to be perform, and note down the value
Method: Based on the leakage current measurement from test point to reference point the insulation resistance
value was calculated by the instrument automatically
d.)Polarity Tests:
Purpose: The test is to ensure that CT connected is optimized to the circuits and to ensure the direction of
connections.
Procedure: During the ratio test the angle displacement for primary and secondary are measured by the testing
kit automatically and confirmed the polarity.
Method: OK = phase Isec phase Iprim = -45< 0 < +45
NOT OK = all other cases
e.)CT Winding resistance Measurement:
Purpose: The Test to ensure that winding has got the acceptable resistance as per the FAT reports.
Procedure: Inject the test D.C Current and D.C voltage as per the recommendations into the winding at the
temperature and the similar resistance shall be converted for 75 Deg C.
Measure the Resistance from the kit and recorded in the Test reports.
Method: Based on voltage drop between the winding, the resistance was calculated
Note: Care should be taken for the Discharging the winding after the test.
f.)Knee Point Voltage:
Purpose: The test is to determine the saturation level of C.T. and to verify as per the Design requirement.
Procedure: The calibrated instrument was used to apply the AC voltage Gradually at CT secondary up to the level
of mention VK in name plate.
Method: According to IEC 60044-1, the knee point is defined as the point on the curve where a voltage increment
of 10%Increases the current by 50%.

LARSEN & TOUBRO LIMITED- ECCD


ELECTRICAL AND TELECOM UTILITIES FOR SUPPORT SERVICE AREA
PHASE I & II AND WEST END EXTENSION, RAS LAFFAN
Doc No:
2908-BG35-4033

Contract No:
GC 081117B0

Page 6 of 10

Rev
Date

0
13-02-11

Note: Demagnetize the core after the test.


g.)Ratio Test:
Purpose: The test is to ensure that the Current transformer shall be selected for the opt ratio with the rated
primary and the secondary current.
Procedure: The calibrated instrument was used to inject the recommended current to primary of the current
transformer and measure the CT secondary.
Method: The magnitude of the measured secondary current and injected primary current the ratio and error was
calculated by the instrument automatically.
Ratio: Measured pri (A) /Measured sec (A)
Error: (Kn x Isec - Iprim) / Iprim) x 100 Here: Kn-act pri/act sec
Test Documents:
Refer SAT for Current Transformer Test Sheet attached.
Note: Copy of the same test sheets will be used other Feeders CTs.
B. Voltage Transformer test:
Purpose: The following Tests shall be performed and Witnessed by the Clients to ensure the Voltage
Transformer operations and its Specific Functions are following the Approved SLD.
Procedure: All tests shall be in accordance with IEC standards IEC 60044-2
a.)The Visual Inspection shall include
Check nameplate information for correctness
Check tightness of all terminals
Check that all grounding cables are securely connected
Check color coded or sleeves for secondary wiring and size of wires against specs
Check proper lugs has been used in termination
Check VTs location physically and secondary terminal labeling printed
b.)The Electrical Test shall include
Insulation Resistance Measurement
Polarity Tests
VT Winding Resistance
Ratio Test
c.)Insulation Resistance Measurement
Purpose: To ensure that the VT is without any insulation failure.

LARSEN & TOUBRO LIMITED- ECCD


ELECTRICAL AND TELECOM UTILITIES FOR SUPPORT SERVICE AREA
PHASE I & II AND WEST END EXTENSION, RAS LAFFAN
Doc No:
2908-BG35-4033

Contract No:
GC 081117B0

Page 7 of 10

Rev
Date

0
13-02-11

Procedure: As per the standard IEC 60076, the calibrated Instrument was used to apply the +ve DC voltage to
Test point and the ve DC terminal for reference point (i.e. Earth) for various condition as per the attached format
the test to be perform, and note down the value
Method: Based on the leakage current measurement from test point to reference point the insulation resistance
value was calculated by the instrument automatically
d.)Polarity Tests:
Purpose: The test is to ensure that VT connected is optimized to the circuits and to ensure the direction of
connections.
Procedure: During the ratio test the angle displacement for primary and secondary are measured by the testing
kit automatically and confirmed the polarity.
Method: OK = phase Vsec phase Vprim = -45< 0 < +45
NOT OK = all other cases
e.)VT Winding resistance Measurement:
Purpose: The Test to ensure that winding has got the acceptable resistance as per the FAT reports.
Procedure: Inject the test D.C Current and D.C voltage as per the recommendations into the winding at the
temperature and the similar resistance shall be converted for 75 Deg C.
Measure the Resistance from the kit and recorded in the Test reports.
Method: Based on voltage drop between the winding, the resistance was calculated
Note: Care should be taken for the Discharging the winding after the test
f.)Ratio Test:
Purpose: The test is to ensure that the Voltage transformer shall be selected for the opt ratio with the rated
primary and the secondary voltage.
Procedure: The calibrated instrument was used to inject the recommended Voltage to primary of the Voltage
transformer and measure the VT secondary.
Method: The magnitude of the measured secondary voltage and applied primary voltage the ratio and error was
calculated by the instrument automatically.
Ratio: Measured pri (V) /Measured sec (V)
Error: (Kn x Vsec - Vprim) / Vprim) x 100 Here: Kn-act pri/act sec
Test Documents:
Refer SAT for voltage Transformer Test Sheet attached.
Note: Copy of the same test sheets will be used other Bays VTs.

LARSEN & TOUBRO LIMITED- ECCD


ELECTRICAL AND TELECOM UTILITIES FOR SUPPORT SERVICE AREA
PHASE I & II AND WEST END EXTENSION, RAS LAFFAN
Doc No:
2908-BG35-4033

Contract No:
GC 081117B0

Page 8 of 10

Rev
Date

0
13-02-11

C. MCCB test:
Purpose:
This test verifies the MCCB Tripping characteristics and rating are following the given name plate as per the
approved SLD data. In brief, the test verifies the MCCB trip test for each phase
Procedure:
1. Record the name and reference number of the panel to be tested in the test sheet
i.

Trip test: The calibrated instrument used to inject the 2 times of set current of MCCB in each pole to
pole, then the trip time was noted from the instrument and ensure that the time following the trip
characteristic as per the name plate.

2. Record if any comments in the Indication and Correction Report


Test Document:
Refer SAT Test Sheet
SAT for MCCB: Copy of the same test sheets will be used for the other MCCB.
D.Breaker with Micro logic Relay test:
Purpose:
This test verifies the Micro logic relay Tripping characteristics and rating are following the given name plate as
per the approved SLD data. In brief, the test verifies the Micro logic relay with Breaker trip test for each phase
Procedure:
1. Record the name and reference number of the panel to be tested in the test sheet
i.

Trip test: The calibrated instrument used to inject the recommended current in Breaker pole to pole of
each phase, then the trip time was noted from the instrument and ensure that the time following the
trip characteristic as per the name plate.

2. Record if any comments in the Indication and Correction Report


Test Document:
Refer SAT Test Sheet
SAT for Micro logic relay: Copy of the same test sheets will be used for other Breaker Micro logic relay
E. Ammeters/voltmeter calibration:
Purpose:
This test verifies the Meters operation and rating are following the name plate as per the approved schematic.
In brief, the test verifies the Meter error and operation of the particular meter.
Procedure:
1. Record the name and reference number of the panel to be tested in the test sheet
i.

Secondary injection test: The calibrated instrument used to inject from 0-1A of current in Meters
secondary terminal, Based on the secondary value the meter will display primary values ,the displayed

LARSEN & TOUBRO LIMITED- ECCD


ELECTRICAL AND TELECOM UTILITIES FOR SUPPORT SERVICE AREA
PHASE I & II AND WEST END EXTENSION, RAS LAFFAN
Doc No:
2908-BG35-4033

Contract No:
GC 081117B0

Page 9 of 10

Rev
Date

0
13-02-11

primary value are noted and error are calculated manually using the below mention formula.
Error = (Actual value - observed value)/ Actual value
2. Record if any comments in the Indication and Correction Report
Test Document:
Refer SAT Test Sheet
SAT for Ammeter/voltmeter: Copy of the same test sheets will be used for other Meters.
F. Auxiliary relay test:
i.

Trip circuit supervision relay-XR350

Purpose:
This test verifies the functionality and properties of Trip Circuit Supervision Relay under test
Procedure:
1. Select a Trip Circuit Supervision Relay from any one of the incomers
2. Record the Panel Reference in the test sheet
3. Perform the following routine tests which is applicable for this relay

Name Plate Rating Details

General Inspection

Resistance Check

Secondary Injection Test

Measurement of trip Circuit Current

Relay Operation Check

4. Record if any comments in the Indication and Correction Report attached.


Test Document:
Refer SAT Test Sheet
SAT for XR-350 relay: Copy of the same test sheets will be used for other XR-350.
G. Busbar contact test:
Purpose:
This test verifies the contact resistance of LVAC switchboard Busbar under test
Procedure:
1. Record the panel Reference in the test sheet
Contact resistance test: Test follows the standards IEC 62271-200,the calibrated testing instrument was used
to inject recommended current in LVAC Busbar of each verticals, Based on the voltage drop of one end to other
end of busbar the resistance was calculated by the instrument automatically. Ensure the value is following the
FAT value
The resistance is calculated R Contact = Applied-mV / I test

LARSEN & TOUBRO LIMITED- ECCD


ELECTRICAL AND TELECOM UTILITIES FOR SUPPORT SERVICE AREA
PHASE I & II AND WEST END EXTENSION, RAS LAFFAN
Doc No:
2908-BG35-4033

Contract No:
GC 081117B0

Page 10 of 10

Rev
Date

0
13-02-11

2. Record if any comments in the Indication and Correction Report attached.


Test Document:
Refer SAT Test Sheet
SAT for Busbar contact resistance
H. High voltage test:
Purpose:
This test verifies the Insulation level of LVAC switchboard Busbar under test
Procedure:
1. Record the panel Reference in the test sheet
High voltage test: The calibrated testing instrument was used to apply recommended2000v AC (80% of FAT
test voltage) in LVAC Busbar for each phase separately as per the format.Based on the leakage current
measurement of busbar the Insulation level was ensured. Ensure the value is following the FAT value
2. Record if any comments in the Indication and Correction Report attached.
Test Document:
Refer SAT Test Sheet
SAT for LVAC High voltage test

9. Test Reports
All Site Test Report Formats is attached for the Individual tests.

ATTACHED TEST FORMATS

1. SAT FOR LVAC CT TEST


a) INCOMER CT TEST
b) OUTGOING CT TEST
2. SAT FOR LVAC VT TEST
3. SAT FOR LVAC MCCB TEST
4. SAT FOR LVAC BREAKER WITH MICROLOGIC RELAY TEST
5. SAT FOR LVAC AMMETER CALIBRATION
6. SAT FOR LVAC VOLTMETER CALIBRATION
7. SAT FOR LVAC TRIP CKT SUPR-RELAY TEST
8. SAT FOR LVAC BUSBAR RESISTANCE TEST
9. SAT FOR LVAC HIGH VOLTAGE TEST

1. SAT FOR LVAC CT TEST

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR CURRENT TRANSFORMER
33/11KV SS-1
Drawing No
2908-2-54-0206
LVAC
Equipment
CURRENT TRANSFORMER

Site location
Bay No

1.1 METERING CT: INCOMER-01 & 02


Make
Sl. No

SACI

R-

Y-

B-

1.2. Name Plate Details


CT
Desgn.

Core No.

Class

Ratio

Rct

KVP

Burden

Purpose

CT1

1200/1

10VA

KW-Metering

CT2

1200/1

10VA

KW-Metering

CT3

1200/1

10VA

KW-Metering

1.3. Insulation Resistance Measurement:


R-PHASE

Y-PHASE

B-PHASE

PRI TO EARTH
PRI TO SEC
SEC TO EARTH
Note: Primary Earth done with 1KV and rest with 500 V Megger for 1 Min
1.4. Polarity Test
CT
Designation

CORE NO

TERMINAL

CT1-3

S1-S2

R-PH

Y-PH

B-PH

1.5. CT Winding Resistance


MEASURED RESISTANCE (IN m )
CT Desgn.

CORE NO

TERMINAL
R-PH

CT1-3

Y-PH

B-PH

S1-S2

LARSEN & TOUBRO

QATAR PETROLEUM

Signature

Signature

Name
Date
Doc. No.

Name
Date
Page 1 of 2

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR CURRENT TRANSFORMER
33/11KV SS-1
Drawing No
2908-2-54-0206
LVAC
Equipment
CURRENT TRANSFORMER

Site location
Bay No

1.6. Knee Point Voltage measurement:

CT Desgn.

CORE NO

TERMINAL

CT1-3

CORE1

S1-S2

R PHASE
Vk
(in
Imag
Volts)
(in mA)

Y PHASE
Vk
(in
Imag
Volts)
(in mA)

B PHASE
Vk
(in
Imag
Volts)
(in mA)

1.7. Ratio Test


CT
Designation

Core

Terminal

Injected Primary
Current (Amps)

Expected
Sec.Current
(Amps)

CT1

R-Phase

S1-S2

600

0.500

CT2

Y-Phase

S1-S2

600

0.500

CT3

B-Phase

S1-S2

600

0.500

Measured
Sec.Current
(Amps)

% Error

1.8. Check List for Print out


1. CT ratio and polarity test ( for all cores and taps)
2. Knee point test ( for all cores and taps)
3. Winding resistance test (for all core & taps)

:
:
:

1.9. General Checks


1. Shorting of all unused cores
2. Check for tightness of all CT terminals

:
:

1.10 REMARK:

Sl.no

Equipment / Instrument

Make

Equipment Sl No.

1
2
3
4

LARSEN & TOUBRO

QATAR PETROLEUM

Signature

Signature

Name
Date
Doc. No.

Name
Date
Page 2 of 2

Calibration Due

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR CURRENT TRANSFORMER
33/11KV SS-1
Drawing No
2908-2-54-0206
LVAC
Equipment
CURRENT TRANSFORMER

Site location
Bay No

1. OUTGOING FEEDER CTS: Q2, Q5, Q23 & Q28


Make

SACI

Sl. No

R-

Y-

B-

2. Name Plate Details


CT
Desgn.

Core No.

Class

Ratio

Rct

KVP

Burden

Purpose

CT1

250/1A

5VA

Metering

CT2

250/1A

5VA

Metering

CT3

250/1A

5VA

Metering

3. Insulation Resistance Measurement:


Ref

R-PHASE

Y-PHASE

B-PHASE

PRI TO EARTH
PRI TO SEC
SEC TO EARTH
Note: Primary Earth done with 1KV and rest with 500 V Megger for 1 Min
4. Polarity Test:
CT
Designation

CORE NO

TERMINAL

CT1-3

S1-S2

R-PH

Y-PH

B-PH

5. CT Winding Resistance
CT Desgn.

CORE NO

TERMINAL

CT1-3

S1-S2

MEASURED RESISTANCE (IN m )


R-PH
Y-PH
B-PH

LARSEN & TOUBRO

QATAR PETROLEUM

Signature

Signature

Name
Date
Doc. No.

Name
Date
Page 1 of 2

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR CURRENT TRANSFORMER
33/11KV SS-1
Drawing No
2908-2-54-0206
LVAC
Equipment
CURRENT TRANSFORMER

Site location
Bay No

6. Knee Point Voltage measurement

CT Desgn.

CORE NO

TERMINAL

CT1-3

CORE1

S1-S2

R PHASE
Vk
(in
Imag
Volts)
(in mA)

Y PHASE
Vk
(in
Imag
Volts)
(in mA)

B PHASE
Vk
(in
Imag
Volts)
(in mA)

7. Ratio Test
CT
Designation

PHASE

Terminal

Injected Primary
Current (Amps)

Expected
Sec.Current
(Amps)

CT1

R-Phase

S1-S2

125

0.5

CT2
CT3

Y-Phase
B-Phase

S1-S2
S1-S2

125
125

0.5
0.5

Measured
Sec.Current
(Amps)

% Error

8. Check List for Print out


1. CT ratio and polarity test ( for all cores and taps)
2. Knee point test ( for all cores and taps)
3. Winding resistance test (for all core & taps)

:
:
:

9. General Checks
1. Shorting of all unused cores
2. Check for tightness of all CT terminals
3. Neutral Earthing / Single point Earthing

:
:
:

10. Remarks

Sl.no

Equipment / Instrument

Make

Equipment Sl No.

1
2
3
4

LARSEN & TOUBRO

QATAR PETROLEUM

Signature

Signature

Name
Date
Doc. No.

Name
Date
Page 2 of 2

Calibration Due

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR CURRENT TRANSFORMER
33/11KV SS-1
Drawing No
2908-2-54-0206
LVAC
Equipment
CURRENT TRANSFORMER

Site location
Bay No

1. OUTGOING FEEDER CTS: Q3, Q6, Q9 & Q20


Make

SACI

Sl. No

R-

Y-

B-

2. Name Plate Details


CT
Desgn.

Core No.

Class

Ratio

Rct

KVP

Burden

Purpose

CT1

200/1A

5VA

Metering

CT2

200/1A

5VA

Metering

CT3

200/1A

5VA

Metering

3. Insulation Resistance Measurement:


Ref

R-PHASE

Y-PHASE

B-PHASE

PRI TO EARTH
PRI TO SEC
SEC TO EARTH
Note: Primary Earth done with 1KV and rest with 500 V Megger for 1 Min
4. Polarity Test:
CT
Designation

CORE NO

TERMINAL

CT1-3

S1-S2

R-PH

Y-PH

B-PH

5. CT Winding Resistance
CT Desgn.

CORE NO

TERMINAL

CT1-3

S1-S2

MEASURED RESISTANCE (IN m )


R-PH
Y-PH
B-PH

LARSEN & TOUBRO

QATAR PETROLEUM

Signature

Signature

Name
Date
Doc. No.

Name
Date
Page 1 of 2

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR CURRENT TRANSFORMER
33/11KV SS-1
Drawing No
2908-2-54-0206
LVAC
Equipment
CURRENT TRANSFORMER

Site location
Bay No

6. Knee Point Voltage measurement

CT Desgn.

CORE NO

TERMINAL

CT1-3

CORE1

S1-S2

R PHASE
Vk
(in
Imag
Volts)
(in mA)

Y PHASE
Vk
(in
Imag
Volts)
(in mA)

B PHASE
Vk
(in
Imag
Volts)
(in mA)

7. Ratio Test
CT
Designation

PHASE

Terminal

Injected Primary
Current (Amps)

Expected
Sec.Current
(Amps)

CT1

R-Phase

S1-S2

100

0.5

CT2
CT3

Y-Phase
B-Phase

S1-S2
S1-S2

100
100

0.5
0.5

Measured
Sec.Current
(Amps)

% Error

8. Check List for Print out


1. CT ratio and polarity test ( for all cores and taps)
2. Knee point test ( for all cores and taps)
3. Winding resistance test (for all core & taps)

:
:
:

9. General Checks
1. Shorting of all unused cores
2. Check for tightness of all CT terminals
3. Neutral Earthing / Single point Earthing

:
:
:

10. Remarks

Sl.no

Equipment / Instrument

Make

Equipment Sl No.

1
2
3
4

LARSEN & TOUBRO

QATAR PETROLEUM

Signature

Signature

Name
Date
Doc. No.

Name
Date
Page 2 of 2

Calibration Due

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR CURRENT TRANSFORMER
33/11KV SS-1
Drawing No
2908-2-54-0206
LVAC
Equipment
CURRENT TRANSFORMER

Site location
Bay No

1. OUTGOING FEEDER CTS: Q1 & Q19


Make

SACI

Sl. No

R-

Y-

B-

2. Name Plate Details


CT
Desgn.

Core No.

Class

Ratio

Rct

KVP

Burden

Purpose

CT1

400/1A

5VA

Metering

CT2

400/1A

5VA

Metering

CT3

400/1A

5VA

Metering

3. Insulation Resistance Measurement:


Ref

R-PHASE

Y-PHASE

B-PHASE

PRI TO EARTH
PRI TO SEC
SEC TO EARTH
Note: Primary Earth done with 1KV and rest with 500 V Megger for 1 Min
4. Polarity Test:
CT
Designation

CORE NO

TERMINAL

CT1-3

S1-S2

R-PH

Y-PH

B-PH

5. CT Winding Resistance
CT Desgn.

CORE NO

TERMINAL

CT1-3

S1-S2

MEASURED RESISTANCE (IN m )


R-PH
Y-PH
B-PH

LARSEN & TOUBRO

QATAR PETROLEUM

Signature

Signature

Name
Date
Doc. No.

Name
Date
Page 1 of 2

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR CURRENT TRANSFORMER
33/11KV SS-1
Drawing No
2908-2-54-0206
LVAC
Equipment
CURRENT TRANSFORMER

Site location
Bay No

6. Knee Point Voltage measurement

CT Desgn.

CORE NO

TERMINAL

CT1-3

CORE1

S1-S2

R PHASE
Vk
(in
Imag
Volts)
(in mA)

Y PHASE
Vk
(in
Imag
Volts)
(in mA)

B PHASE
Vk
(in
Imag
Volts)
(in mA)

7. Ratio Test
CT
Designation

PHASE

Terminal

Injected Primary
Current (Amps)

Expected
Sec.Current
(Amps)

CT1

R-Phase

S1-S2

200

0.5

CT2
CT3

Y-Phase
B-Phase

S1-S2
S1-S2

200
200

0.5
0.5

Measured
Sec.Current
(Amps)

% Error

8. Check List for Print out


1. CT ratio and polarity test ( for all cores and taps)
2. Knee point test ( for all cores and taps)
3. Winding resistance test (for all core & taps)

:
:
:

9. General Checks
1. Shorting of all unused cores
2. Check for tightness of all CT terminals
3. Neutral Earthing / Single point Earthing

:
:
:

10. Remarks

Sl.no

Equipment / Instrument

Make

Equipment Sl No.

1
2
3
4

LARSEN & TOUBRO

QATAR PETROLEUM

Signature

Signature

Name
Date
Doc. No.

Name
Date
Page 2 of 2

Calibration Due

2. SAT FOR LVAC VT TEST

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR VOLTAGE TRANSFORMER
33/11 KV S/S-1
Drawing No
2908-2-54-0206
LVAC
Equipment
VOLTAGE TRANSFORMER

Site location
Bay No

For 1CPT1, 2CPT1, 3CPT1, 4CPT1


1. Name Plate Details
:

Make

R-

Y-

Sl. No

Ratio

: 415V/3 / 110V/3

Burden

: 50VA

Purpose

: Protection/Metering

B-

2. Insulation Resistance Measurement:


Minimum Value: 1M /KV

Temperature
Applied Voltage
(VDC)
500 V

Description
Primary Earth
Primary- Secondary

500 V

Secondary -Earth

500 V

3. Polarity Test

R-PH(G)

Y-PH(G)

C
B-PH(G)

VT Designation

CORE NO

TERMINAL

XCPT1

CORE 1

1r - 1n

R-PH

Y-PH

B-PH

4. VT Winding Resistance:
Temperature:

VT Designation

CORE NO

TERMINAL

XCPT1

CORE 1

1r - 1n

MEASURED RESISTANCE ( IN OHMS)


R-PH
Y-PH
B-PH
At ambT
At ambT
At ambT
At 75 C
At 75 C
At 75 C

LARSEN & TOUBRO

QATAR PETROLEUM

Signature

Signature

Name
Date
Doc. No.

Name
Date
Page 1 of 2

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0

Site location
Bay No

SITE ACCEPTANCE TEST FOR VOLTAGE TRANSFORMER


33/11 KV S/S-1
Drawing No
2908-2-54-0206
LVAC
Equipment
VOLTAGE TRANSFORMER

5. Primary Injection Test / Ratio Test:


VT
Designation

PHASE

TERMINAL

XCPT1
XCPT1
XCPT1

R-PH
Y-PH
B-PH

1r - 1n

APPLIED PRIMARY
VOLTS

CALC
SEC.VOLTS

MEASURED
SEC.VOLTS

% ERROR

6. Check List for Print out


VT ratio and polarity test ( for all cores and taps)
VT secondary winding resistance ( for all cores and taps)

:
:

7. General Checks
General visual inspection
Name plate details
HV Terminal Marking
LV Terminal Marking
Check for tightness of all VT terminals

:
:
:
:
:

8. General Checks
:
MCB rating
Equipment Grounding System

:
:

9. Remarks

Sl.no

Equipment / Instrument

Make

Equipment Sl No.

1
2
3
4

LARSEN & TOUBRO

QATAR PETROLEUM

Signature

Signature

Name
Date
Doc. No.

Name
Date
Page 2 of 2

Calibration Due

3. SAT FOR LVAC MCCB TEST

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END
EXTENSION OF RAS LAFFAN CITY GC081117B0

Site location
Bay No

SITE ACCEPTANCE TEST FOR MCCB


Drawing No
2908-2-54-0206
Equipment
MCCB

33/11KV S/S-1
LVAC

MOULDED CASE CB
1. Name Plate Details:
Make

: MERLIN GERIN

Feeder

Type

Frequency

: 50 Hz

Aux. Volts

Nominal Current

Range

Feeder Ratings

2. TRIP TEST
LONG INVERSE OVER CURRENT:
Operating time measured at 2Is (sec)

Set
(Is) Amp

Phase

R Phase
Y-Phase
B-Phase

MCCB Found Healthy


3. REMARK

Sl.no

YES / NO
:

Equipment / Instrument

Make

Equipment Sl No.

1
2

LARSEN & TOUBRO

QATAT PETROLEUM

Signature

Signature

Name

Name

Date

Date

Doc.No.

Rev

Calibration Due

4. SAT FOR LVAC MICROLOGIC


RELAY TEST

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0

Site location
Bay No

33/11KV S/S-1
LVAC

SITE ACCEPTANCE TEST FOR MOULDED CASE C.B


Drawing No
2908-2-54-0206
Equipment
MCCB WITH MICROLOGIC

MOULDED CASE WITH MICROLOGIC TEST FOR QM1, QM2 & QB


1. NAME PLATE DETAILS:
MAKE

MERLIN GERLIN

TYPE

NW12H1

FREQUENCY

50HZ

NOMINAL CURRENT

1250 A

AUX VOLTS

110 V DC

SERIAL NO

SETTINGS :
SHORT CIRCUIT

INSTANETANEOUS

EARTH FAULT
2. BREAKER TESTS
2.1 SHORT CIRCUIT:
PHASE

SETTING OF CURRENT

INJECTED CURRENT

OPERATED TIME

SETTING OF CURRENT

INJECTED CURRENT

OPERATED TIME

SETTING OF CURRENT

INJECTED CURRENT

OPERATED TIME

R - PH
Y - PH
B - PH
2.2 INSTANETANEOUS
PHASE
R - PH
Y - PH
B - PH
2.3 EARTH FAULT
PHASE
NEUTRAL

LARSEN & TOUBRO

QATAR PETROLEUM

Signature

Signature

Name
Date
Doc. No.

Name
Date
Page 1 of 2

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0

Site location
Bay No

33/11KV S/S-1
LVAC

SITE ACCEPTANCE TEST FOR MOULDED CASE C.B


Drawing No
2908-2-54-0206
Equipment
MCCB WITH MICROLOGIC

3. Tripping of CB By simulating of Relay Operation


1. Relay found Healthy

: Yes / No

2. Ammeter and Selector switch Found Healthy

: Yes / No

3. Aux contacts

: ok / with comments

4. REMARK:

Sl.no

Equipment / Instrument

Make

Equipment Sl No.

1
2
3
4

LARSEN & TOUBRO

QATAR PETROLEUM

Signature

Signature

Name
Date
Doc. No.

Name
Date
Page 2 of 2

Calibration Due

5. SAT FOR LVAC AMMETER


CALIBRATION

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END
EXTENSION OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR AMMETER CALIBRATION
33/11KV S/S-01
Drawing No
2908-2-54-0206
LVAC
Equipment
AMMETER

Site location
Bay No

AMMETER CALIBRATION
1.

Name Plate Details:

Make

Feeder Ref

Type

Range

S.NO

2. MEASUREMENT TEST :

Secondary Injected Current in


Amps

3. Ammeter Found Healthy:

Expected Current in
(A)

Ammeter Reading in (A)

% Error

YES / NO

Instruments Used:
SL.NO

DESCRIPTION

MAKE

EQUIPMENT

CALIBRATION

CALIBRATION

SL.NO

ON DATE

DUE DATE

1
2
3.

LARSEN & TOUBRO

QATAT PETROLEUM

Signature

Signature

Name

Name

Date

Date

Doc.No.

Rev

6. SAT FOR LVAC VOLTMETER


CALIBRATION

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END
EXTENSION OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR VOLTMETER CALIBRATION
33/11KV S/S-01
Drawing No
2908-2-54-0206
LVAC
Equipment
VOLTMETER

Site location
Bay No

VOLTMETER CALIBRATION

1.

Name Plate Details:

Make

Feeder Ref

Type

Range

S.NO

2. MEASUREMENT TEST:

Injected Voltage in Volts

Expected Voltage in
(kv)

Voltmeter Reading in (kv)

% Error

3. Voltmeter Found Healthy: YES / NO


Instruments Used:
SL.NO

Description

MAKE

EQUIPMENT
SL.NO

CALIBRATION
ON DATE

CALIBRATION
DUE DATE

1
2

LARSEN & TOUBRO

QATAT PETROLEUM

Signature

Signature

Name

Name

Date

Date

Doc.No.

Rev

7. SAT FOR TRIP CKT SUPR


RELAY

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR TRIP CKT SUPRV RELAY
33/11KV S/S-01
Drawing No
2908-BG35-4004
LVAC
Equipment
XR-350

Site location
Bay No

1. Name Plate Rating Details of the Equipment


Relay Make

REYROLLE

Relay Model

XR350

MLFB Number

7PG1753-3CC10-4BE0

Serial Number
Rated Voltage

125 VDC

Rated Frequency

DC

Contacts Details

2NO; 2NC

2. General Inspection of Relay


S.No

Description

Installation and Correct Wiring as per drawing

Terminal Tightness

Relay Earth Connected to Local Earth Bar

Pass

3. Resistance Check
Measure the resistance of each coil and its external resistor; record the values in the following table
Element

Coil Resistance

External Resistance

A
B
C
4. Secondary Injection
Inject the relay including the external resistor, and record the values of pick-up voltage and current in
the following table.
Element

Pick-Up Volts

Pick-Up Current

A
B
C
LARSEN & TOUBRO

QATAT PETROLEUM

Signature

Signature

Name

Name

Date

Date

Doc.No.

Rev

Fail

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END EXTENSION
OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR TRIP CKT SUPRV RELAY
33/11KV S/S-01
Drawing No
2908-BG35-4004
LVAC
Equipment
XR-350

Site location
Bay No

5. Referring to the circuit diagram, replace the trip link with an ammeter and, with the trip circuit
operational, measure the trip circuit current with the breaker in the open and closed state.
Breaker Open

mA

Breaker Closed

mA

6. With CB closed short in turn coil A and check for no trip


7. Check for relay Operation by breaking the trip circuit continuity

Instruments Used:
Sl.no

Description

Make

Equipment

Calibration

Calibration

Sl.no

On date

Due date

1
2

LARSEN & TOUBRO

QATAT PETROLEUM

Signature

Signature

Name

Name

Date

Date

Doc.No.

Rev

8. SAT FOR MAIN CIRCUIT


RESISTANCE TEST

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END
EXTENSION OF RAS LAFFAN CITY GC081117B0

Site location
Bay No

SITE ACCEPTANCE TEST FOR LVAC MAIN CIRCIUT RESISTANCE


33/11KV S/S-01
Drawing No
2908-2-54-0206
LVAC
Equipment
BUSBAR

Make

: BIN GHALIB

Type

: 3PH 4 BUS

Serial No.

Rated current

: 1600A

Rated frequency

: 50HZ

Rated Voltage

: 415V

Short time rating

: 50KA/SEC

Control voltage

: 110V DC

Sl.No.

Contact Resistance Between


Cubicles

COL:1- COL:02

COL:1- COL:03

COL:1- COL:04

COL:1- COL:05

COL:1- COL:06

COL:1- COL:08

COL:1- COL:09

COL:1- COL:10

COL:1- COL:11

10

COL:1- COL:12

11

COL:1- COL:13

12

---

13

---

Bus bars Found Healthy :

R-phase in
micro-ohms

Y-phase in
micro-ohms

B-phase in
micro-ohms

NEUTRAL in
micro-ohms

YES / NO

REMARK:
Sl.no

Equipment / Instrument

Make

Equipment Sl No.

Calibration Due

1
2
LARSEN & TOUBRO LTD

QATAR PETROLEUM

Signature

Signature

Name

Name

Date
Doc. No.

Date
Page 1 of 1

9. SAT FOR BUSBAR HIGH


VOLTAGE TEST

CONTRACT: EPIC FOR ELECTRICAL AND TELECOM UTILITIES FOR


SUPPORT SERVICES AREA PHASE I & II AND WEST END
EXTENSION OF RAS LAFFAN CITY GC081117B0
SITE ACCEPTANCE TEST FOR LVAC HV TEST
33/11KV S/S-01
Drawing No
2908-2-54-0206
LVAC
Equipment
LVAC BUSBAR

Site location
Bay No

HIGH VOLTAGE TEST FOR 415V LVAC BOARD


Make

: BIN GHALIB

Type

: 3PH 4 BUS

Serial No.

Rated current

: 1600A

Rated frequency

: 50HZ

Rated Voltage

: 415V

Short time rating

: 50KA/SEC

1. INSULATION RESISTANCE TEST:

(1KV FOR 1 MINUTE)

MEGGER VALUE BEFORE


HV TEST

MAIN CIRCUIT

MEGGER VALUE AFTER


HV TEST

R (Y+B+N+PE)
Y (B+R+N+PE)
B (N+R+Y+PE)
N (PE+R+Y+B)
2. HV VOLTAGE : 2000V AC FOR 60SEC
REF

Leakage Current in mA

R (Y+B+N+PE)
Y (B+R+N+PE)
B (N+R+Y+PE)
N (PE+R+Y+B)
BUS BAR FOUND HEALTHY:

OK / NOT

3. REMARK:
Sl.no

Equipment / Instrument

Make

Equipment Sl No.

1
2

LARSEN & TOUBRO

QATAT PETROLEUM

Signature

Signature

Name

Name

Date

Date

Doc.No.

Rev

Calibration Due

You might also like