Professional Documents
Culture Documents
www.seipub.org/aee
Introduction
Future networks will include widespread penetration
of Small-Scale Generators like PVs, wind turbines and
fuel cells in residential area. PV sources increasingly
contribute to the total renewable energy in LV network
[1]. There are two types of PV system in LV network,
standalone and grid-connected, in the first of which
used for remote area, the aim is to balance the load and
generation to prevent loss of load in each time step.
Therefore, the optimization algorithms are used to
minimize the cost and the loss of load.
However, for the grid-connected type, the main
problem is power quality issues. The high penetration
of grid-connected PVs may reverse the power flow in
the network and introduce new technical challenges
for the system. These issues include voltage tripping,
voltage imbalance, harmonic and reverse power flow.
To deal with technical challenges of grid-connected PV,
different strategies have been addressed in literatures.
The first approach is to curtail PVs output power in
critical condition. This approach is attractive, but
contradicts the maximum use of renewable energy.
53
www.seipub.org/aee
PV generation profile
load profile
2.5
Power (kW)
2
1.5
1
0.5
5
10
15
20
25
Time (hour)
(a) 1.5 kW PV
Power (kW)
2.5
load profile
PV generation profile
2
1.5
1
0.5
5
10
15
20
25
Time (hour)
(b) 3 kW PV
FIG. 1 LOAD AND PV GENERATION PROFILES; FOR (a) 1.5 kW, (b) 3 kW PVs
Power (kW)
2.5
PV generation profile
load profile
2
1.5
1
0.5
5
10
15
20
Time (hour)
FIG. 2 SHIFTED LOAD AND PV GENERATION PROFILES
54
25
www.seipub.org/aee
h 1, 2,..., 8760
exp ort
im p ort
55
www.seipub.org/aee
FIG. 4 TYPICAL TOPOLOGY OF FUTURE RENEWABLE ENERGY SYSTEM IN A GRID-CONNECTED RESIDENTIAL BUILDING
2)
exp ort
Pgrid ,h 0
import
Pgrid ,h 0
and
im p ort
exp ort
Pgrid ,h 0
export
exp ort
exp ort
Pgrid ,h Pmax
and
import
Pgrid ,h 0
56
) can be penalized
import
import
Pgrid ,h Pmax
and
exp ort
exp ort
Pgrid ,h Pmax
and
import
import
Pgrid ,h Pmax
for h 1, 2,...,8760
The goal for each case may give different
cost/benefit to customer and utility, as described
earlier. As a result, it can be said that the sizing of
both PV and storage need to be carefully
determined, considering these operational goals.
In the following section, the detail of combined PVenergy storage sizing approach for a Gridconnected residential building has been shown. The
study aims to determine this case in consideration
with different operational goals. Annual cash flow
is used to compare different sizing plan.
www.seipub.org/aee
between 6 pm 6 am,
Customer charectristics
Yearly load profile
Market Data
Operation goal
FIG. 5 FLOW CHART FOR COMBINED PV- ENERGY STORAGE SIZING ALGORITHM
} (4)
total CPinv CPmain CPelec CPCCL CR feed intariff
min{ C
Objective Function
The objective functions, considering the type of
operational goal of the building, can be written as
follow:
Self-consumption
min{ Ctotal CPinv CPmain CPelec CRself consumption }(1)
Zero power import
min{ Ctotal CPinv CPmain CR feed intarrif }
(2)
(3)
elec
feed intariff
} (5)
57
www.seipub.org/aee
(15)
8760
im port import
CPCCL rateCCL .( Pgrid ,h Pmax )
h1
(8)
CRself consumption
8760
rateself consumption .Pself consumption,h
h1
(9)
8760
export
CR feed intariff rate feed intariff .Pgrid ,h (10)
h1
where rateself-consumption is the self-consumption incentive
rate, ratefeed-in-tariff is the feed-in-tariff rate.
Equality and Inequality Constraints
The balance between supply and demand in each time
step can be achieved by equation (11):
import
PPV ,h Pstorage,h Pgrid ,h Pload ,h
(11)
58
max
PPV PPV
(12)
max
Estorage Estorage
(13)
exp ort
import
Pgrid ,h 0, Pgrid ,h 0
(14)
exp ort
import
Pgrid ,h 0, Pgrid ,h 0
Maximum power export
exp ort
exp ort import
Pgrid ,h Pmax , Pgrid ,h 0
(16)
exp ort
import
import
Pgrid ,h 0, Pgrid ,h Pmax
(17)
exp ort
exp ort import
import
Pgrid ,h Pmax , Pgrid ,h Pmax
(18)
Case Study
In this section, a grid-connected residential building
with annual hourly load profile of Fig. 6 is used as a
case study to find the optimal PV and storage sizing
for different operational goals. The type and details of
PV panel is shown in Table I. In addition, the annual
hourly generation profile of this panel is given in Fig. 7.
Homer software has been used to estimate the amount
of load and generation of the building for each hour
during a year. Due to installation space limitation, the
maximum allowable PV rating is considered to be 4.8
kW for the building. The direct search optimization
method has been used to establish an optimal plan for
each operational goal. Table II shows the component
cost and economic factors which are used in the
following case studies to determine the cash flow for
each plan.
TABLE I PV PANEL PARAMETERS
Maximum power
Efficiency
Capital cost
Life time
100 w
12 %
400 $
20 years
www.seipub.org/aee
800
700
600
500
400
300
200
100
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Hour in a day
25
20
15
10
5
0
0 1 2 3 4 5 6 7 8 9 10 11 1213 14 1516 17 1819 20 21 22 23 24 25
Storage
Average cost
Life cycle
Charge efficiency
Discharge efficiency
Initial state of charge
400 $/kWh
3 years
100%
80%
20%
PE converter
Average cost
Life cycle
500 $/kW
10 years
Economic parameters
Off-peak electricity price (1am-6am)
Semi-peak electricity price (7am-5pm)
Peak electricity price (6pm-12pm)
0.2 $/kWh
0.3 $/kWh
0.5 $/kWh
Feed-in-tariff rate
Self-consumption incentive rate
CCL rate
Installation Incentive rate for PV
Installation Incentive rate for storage
Interest rate
0.40 $/kWh
0.23 $/kWh
0.40 $/kWh
0.4
0.4
0.06
PPV (kW)
Estorage(kWh)
CPinv ($)
CPelec ($)
CRfeed-in-tariff ($)
CRself-consumption ($)
CPCCL($)
Ctotal ($)
2.3
6.7
1209.1
2885.5
0
849.54
0
3245.1
59
www.seipub.org/aee
5000
investment cost
electricity cost
self-consumption cost
4000
3000
2000
1000
0
-1000
-2000
0
PV capacity (kW)
FIG. 8 COST STRUCTURE FOR DIFFERENT PV CAPACITY
3000
2500
PV incestment cost
converter investment cost
Batteriy investment cost
2000
1500
1000
500
0
-1
PV capacity (kW)
FIG. 9 DIFFERENT PARTS OF THE INVESTMENT COST
60
www.seipub.org/aee
30
25
20
15
10
5
0
0
PV capacity (kW)
FIG. 10 ANNUAL RENEWABLE ENERGY LOSSES
6000
5500
5000
4500
0
0.1
0.2
0.3
0.4
0.5
4000
3500
3000
2500
0
PV capacity (kW)
FIG. 11 TOTAL ANNUAL COST FOR DIFFERENT INSTALLATION INCENTIVE RATES
4500
4000
3500
3000
2500
2000
1500
0
0.1
0.2
0.23
0.3
0.4
0.5
1
PV capacity (kW)
FIG. 12 TOTAL ANNUAL COST FOR DIFFERENT SELF-CONSUMPTION INCENTIVE RATES
61
www.seipub.org/aee
PPV (kW)
Estorage (kWh)
CPinv ($)
CPelec ($)
CRfeed-in-tariff ($)
CRself-consumption ($)
CPCCL($)
Ctotal ($)
2.9
0.5
775.6409
2966.1
437.8151
0
0
3245.1
PV capacity (kW)
FIG. 13 REQUIRED STORAGE SIZING AS A FUNCTION OF PV CAPACITY
5000
4500
4000
3500
3000
2500
0
0.5 kW
1.0 kW
1.5 kW
2.0 kW
2.5 kW
3.0 kW
1
PV capacity (kW)
FIG. 14 SENSITIVITY OF TOTAL ANNUAL COST TO THE MAXIMUM POWER EXPORT LIMIT
62
PPV (kW)
Estorage (kWh)
CPinv ($)
CPelec ($)
CRfeed-in-tariff ($)
CRself-consumption ($)
CPCCL($)
Ctotal ($)
www.seipub.org/aee
4.8
3.2
1552.2
805
696.9445
0
4.8563
1665.1
PPV (kW)
Estorage (kWh)
CPinv ($)
CPelec ($)
CRfeed-in-tariff ($)
CRself-consumption ($)
CPCCL($)
Ctotal ($)
20
15
3.6
3.2
1255.4
958.5301
367.6020
0
7.3679
1853.7
0.5 kw
1.0 kW
1.5 kW
2.0 kW
2.5 kW
3.0 kW
10
0
0
PV capacity (kW)
10
2
0
PV capacity (kW)
FIG. 16 STORAGE SIZING AS A FUNCTION OF PV CAPACITY
63
www.seipub.org/aee
Conclusions
REFERENCES
system,
Energy
Conversion,
IEEE
1-8.
Castillo-Cagigal, M., Caamao-Martn, E., Matallanas, E.,
Masa-Bote, D., Gutirrez, A., Monasterio-Huelin, F.,
PV/battery
system
via
SIMPLORER,
in:
Methodology
1-5.
photovoltaic/wind-generator
for
optimal
sizing
systems
of
stand-alone
using
genetic
64
1656.
Oudalov, A., Cherkaoui, R., Beguin, A., Sizing and Optimal
www.seipub.org/aee
Riffonneau, Y., Bacha, S., Barruel, F., Ploix, S., Optimal Power
65