Professional Documents
Culture Documents
S. #
Description
2
3
5
6
7
8
8
Page
No.
3
4
5
6-13
14-15
16
17
18
19-31
Hydro
Power
Pakhtunkhwa
Hydel Projects,
Completed
Projects
Pre-Feasibility
Khyber
32 - 50
Studies
Nil Da Katha,
Bhimbal Katha,
Saiful Maluk Katha,
Balkani,
Chowkel Khwar,
Kedam Khwar,
Gandigar,
Ayun Gol,
Barum Gol,
Mastuj River
11
Contact information
Board of Investment
Private Power Infrastructure Board (PPIB)
Thar Coal and Energy Board
Energy Department, Government of Punjab
Pakhtunkhwa
Hydel
Development
Organization
51-52
Private Sector
IPPs
8,630
37
KESC
2,381
10
Total
11,011
47
Salient Features
Transmission Line Policy 2014
List of Transmission System projects to be offered to
Private Sector will be prepared by GOP
BOOT Model
Policy to cover Transmission Line & Grid Station projects of
220 KV voltage level and above (EHVAC & HVDC)
Land & Legal Right of way to be provided by NTDC at no
cost
Project Term : 25-30 years
Equity : 18 %
Transmission utility (NTDC) to pay Transmission Service
Charge in Rs./km/month/circuit
Exemption from Corporate Income Tax and 5% flat Custom
Duties
Utility to provide Basic Design & Functional Performance
Specifications
Standardized Security Package (IA & TSA) One Window
facility by PPIB
Conceptual view
Transmission Line
Total
Note: These are very Preliminary and Rough Estimates and will
change considerably as design is finalized and costs are firmed up.
10
Business Model
GOB
11
Feasibility Study
NESPAK Completed Following Activities for Gaddani Power Park
Land Ownership Survey
Topographic Survey
Construction Material Study
On-shore
Geotechnical
Investigations
Already
Completed by NESPAK
Geophysical Survey on-shore
Seismic Study
Electric Resistivity Survey
Master plan for Pakistan Power Park completed in collaboration
with specialist foreign and local firms
Feasibility Study of Gaddani Power Park is in Progress
12
Investment Opportunities
8 x 660 MW Power Plants in IPP mode on Build, Own &
Operate basis
Construction of deep Sea Jetty and Marine Infrastructure
Development of infrastructure of Pakistan Power Park
Construction of Transmission Line
Construction of access Roads
13
10-20 m
Overburden
114-137 m
6.2:1
Fixed Carbon %
14.2 - 34.0
Volatile matter %
Moisture content %
23.1 - 36.6
29.6 - 55.5
Fixed Carbon %
Volatile matter %
Moisture content %
14.2-34.0
23.1-36.6
29.6-55.5
16
17
18
HYDROPOWER
PROJECTS
19
General:
Project Name
Location
: 58 MW
Gross Head
: 351 m
: 254 GWh
Project Type
: Run-of-River
Design Discharge
: 20.0 m3/sec
Plant Factor
: 50%
Estimated Cost
: 87 Mill US$
Current Status
Project is expected to be advertised approval from PPIB Board
PARTICIPATION REQUIRED
Project
Sponsors
through
International
Competitive
Bidding (ICB)
21
22
General
Project Name
River
Location
town
Distance
Technical
Capacity
: 80 MW
Energy
: 321 GWh
Project Type
: Run-of-River
Design Discharge
: 30 m3/s
Gross Head
: 341 m
Plant Factor
: 45.8 %
Estimated Cost
Current Status
Project Profile and Pre-Qualification Documents are being
prepared, EOI for development of the project will be solicited
through advertisement in the press shortly.
PARTICIAPTION REQUIRED:
Project
Sponsors
through
International
Competitive
Bidding (ICB)
23
24
General
Project Company
Project Sponsors
Project Cost
Project Consultant
: Scott Wilson
Technical
Capacity
: 640 MW
Energy
: 3075 GWh
Levelized Tariff
years)
Expected COD
: June 2020
Current Status
Tariff negotiated b/w Sponsors and NTDC
PARTICIAPTION REQUIRED:
Equity Partners
Debt Financing
EPC Contractor
Detailed Design Consultants
Equipment Suppliers
O & M Contractor
25
26
General
Project Sponsors : Suhail Jute Mills Ltd., Colony
Sarhad Textile Mills
Project Cost
Technical
Capacity
: 500 MW
Energy
: 2410 GWh
Levelized Tariff
Expected COD
: December 2020
Current Status
Feasibility Study has been approved by the Panel of
Experts
Feasibility Level Tariff has been finalized between
Sponsors and NTDC;
NTDC after approval from its Board will forward the case
to NEPRA for final approval
PARTICIAPTION REQUIRED:
Equity Partners, Debt Financing, EPC Contractor
Detailed Design Consultants, Equipment Suppliers
O & M Contractor
27
28
General
Project Name
Project Company
Project Sponsors
Project Consultant
Location
River
: Swat River
Project Cost
Technical
Capacity
: 157 MW
Gross Head
: 214.8 m
Tariff
: US 8.92/kWh
(Term 30 years at 2008 level cost)
Current Status
Feasibly Study has been completed, The Sponsors
have been advised by PPIB to approach NEPRA for
Tariff Determination.
PARTICIAPTION REQUIRED:
Equity Partners, Debt Financing, EPC Contractor
Detailed Design Consultants, Equipment Suppliers
O & M Contractor
29
30
General
Project Name
: Asrit-Kedam Hydropower
Project
Project Sponsors
Project Consultant
Location
River
: Swat River
Project Cost
Technical
Capacity
: 215 MW
Gross Head
: 214.8 m
Tariff
: US 7.83/kWh
32
Contacts
Board of Investment
Prime Ministers Office
Ataturk Avenue, Sector G-5/1, Islamabad, Pakistan.
Tel: 0092-51-9204339, 9207031
Fax: 0092-51-9218325, 9218323
Website: www.boi.gov.pk
Website: www.ppib.gov.pk
Energy Department,
Government of the Punjab,
Irrigation Secretariat,
Library Road, Old Anar Kali, Lahore, Pakistan.
Phone: 0092 42-99213974-5
33
34
35