CONCRETE

TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES


Ayala Blvd., Ermita, Manila
COLLEGE OF ENGINEERING
Civil Engineering Department

PROJECT TITLE: TROPICAL SEMI-ATTACHED RESIDENCE

OWNER/S: MR. & MRS DANILO REYES


LOCATION: SOUTHERN YEMEN ST. BETTER LIVING SUBDIVISION, PARANAQUE CITY
BILL OF MATERIALS

Item To Be
Estimated

Footings For
Rectangular
Column

Calculations

Materials And Estimated


Quantities Required
Cement
40kg.
(Bags)

Sand
(Cu.m.)

Gravel
(Cu.m.)

Central Footing-1 for Rectangular Column


Conc. vol./footing = 1.2 x 1.2 x 0.25 = 0.36m3
Conc. vol./footing for 4 footings =
1.44m3
Plus : 10 % allowance for wastage =
0.14m3
Total volume of footings =
1.58m3
Using the Formulas for Class AA concrete:
1.58 m3 x 12.0 = 18.96; say
1.58 m3 x 0.5 = 0.79; say
1.58 m3 x 1.0 = 1.58; say

19
1.0
2.0

Central Footing-2 for Rectangular Column


Conc. vol./footing = 1.3 x 1.3 x 0.25 = 0.42m3
Conc. vol./footing for 7 footings =
2.96 m3
Plus : 10 % allowance for wastage =
0.30 m3
Total volume of footings =
3.26 m3
Using the Formulas for Class AA concrete:
3.26 m3 x 12.0 = 39.12; say
3.26 m3 x 0.5 = 1.63; say
3.26 m3 x 1.0 = 3.26; say

40
2.0
3.5

Central Footing-3 for Rectangular Column


Conc. vol./footing = 1.4 x 1.4 x 0.25 = 0.49 m3
Conc. vol./footing for 2 footings =
0.98 m3
Plus : 10 % allowance for wastage =
0.10 m3
Total volume of footings =
1.08 m3
Using the Formulas for Class AA concrete:
1.08 m3 x 12.0 = 12.96; say
1.08 m3 x 0.5 = 0.54; say
1.08 m3 x 1.0 = 1.08; say

Central Footing-4 for Rectangular Column


Conc. vol./footing = 1.55 x 1.55 x 0.3 = 0.72 m3

13
1.0
1.5

Gravel
Fill
(Cu.m.)

Conc. vol./footing for 2 footings =


Plus : 10 % allowance for wastage =
Total volume of footings =

1.44 m3
0.14 m3
1.58 m3

Using the Formulas for Class AA concrete:


1.58 m3 x 12.0 = 18.96; say
1.58 m3 x 0.5 = 0.79; say
1.58 m3 x 1.0 = 1.58; say

19
1.0
2.0

Cen/Can Footing-5 for Rectangular Column


Conc. vol./footing = 0.6 x 0.6 x 0.2 = 0.07 m3
Conc. vol./footing for 16 footings =
1.15 m3
Plus : 10 % allowance for wastage =
0.12 m3
Total volume of footings =
1.27 m3
Using the Formulas for Class AA concrete:
1.27 m3 x 12.0 = 15.24; say
1.27 m3 x 0.5 = 0.635; say
1.27 m3 x 1.0 = 1.27; say

16
1.0
1.5

Cantilever Footing-6 for Rectangular Column


Conc. vol./footing = 1.05 x 1.05 x 0.25 = 0.28 m3
Conc. vol./footing for 4 footings =
1.10 m3
Plus : 10 % allowance for wastage =
0.11 m3
Total volume of footings =
1.21 m3
Using the Formulas for Class AA concrete:
1.21 m3 x 12.0 = 14.52; say
1.21 m3 x 0.5 = 0.605; say
1.21 m3 x 1.0 = 1.27; say

15
1.0
1.5

CantileverFooting-7 for Rectangular Column


Conc. vol./footing = 1.15 x 1.15 x 0.25 = 0.33 m3
Conc. vol./footing for 2 footings =
0.66 m3
Plus : 10 % allowance for wastage =
0.07 m3
Total volume of footings =
0.73 m3
Using the Formulas for Class AA concrete:
0.37 m3 x 12.0 = 4.44; say
0.37 m3 x 0.5 = 0.185; say
0.37 m3 x 1.0 = 0.37; say
Combined Footing-1 for Rectangular Column
Conc. vol./footing = 1.35 x 2.05 x 0.25 = 0.69 m3
Conc. vol./footing for 1 footings =
0.69 m3
Plus : 10 % allowance for wastage =
0.07 m3
Total volume of footings =
0.76 m3

5
0.5
0.5

Using the Formulas for Class AA concrete:


0.76 m3 x 12.0 = 9.12; say
0.76 m3 x 0.5 = 0.38; say
0.76 m3 x 1.0 = 0.76; say

Rectangular
Columns

10
0.5
1.0

Rectangular Column -1 with 250mm Footing


Conc. volume per column =

0.2 0.4 7.85=0.628 m

Conc. volume for 10 columns =

6.28 m

Conc. Volume per column =

0.2 0.4 6.85=0.548 m

Total Volume = 6.828 m3


3

Plus : 5 % allowance for wastage = 0.341 m


3
Total Volume for Columns = 7.17 m

65
4.0
7.5

Using Class A concrete mixture:

7.17 9.00=64.53 ; say


7.17 0.50=3.585 ; say

7.17 1.00=7.17 ; say


Rectangular Column -2& 3 with 250mm Footing
Conc. volume per column =

0.2 0.4 7.85=0.628 m

Conc. volume for 6 columns =

3.768 m

Conc. Volume per column =

0.2 0.4 4.85=0.388 m3


54

3
Conc. Volume for 2 columns =0.776 m

3.0
6.0

Conc. Volume per column =

0.2 0.4 6.85=0.548 m3


Conc. Volume for 2 columns =1.10 m
Total Volume = 5.644 m

Plus : 5 % allowance for wastage = 0.28 m


Total Volume for Columns =

5.93 m3
12
1.0

Using the formula for Class A concrete:

1.5

5.93 9.00=53.37 ; say


5.93 0.50=2.97 ; say
5.93 1.00=5.93 ; say
Rectangular Column -2 with 300mm Footing
Conc. volume per column =

0.2 0.4 7.8=0.624 m3


Conc. volume for 2 columns =

1.248 m3

12
1.0

3
Plus : 5 % allowance for wastage = 0.06 m

Total Volume for Columns =

1.5

1.31 m3

Using the formula for the Class A concrete:

1.31 9.00=11.79 ; say


1.31 0.50=0.655 ; say
16

1.31 1.00=1.31 ; say

1.0
2.0

Planted Column-1
Length of column = 0.2 x 0.4 x 3 = 0.24 m3
Conc. Vol./Column for 5 =
1.20 m3
Plus : 10 % allowance for wastage = 0.12 m3
Total Volume =
1.32 m3

Using the formula for Class A concrete:


1.32 m3 x 9 = 11.88; say
1.32 m3 x 0.5 = 0.66; say
1.32 m3 x 1.0 = 1.32; say
SC-1
Length of column = 0.15 x 0.3 x 2.125 =
Conc. Vol./Column for 16 =
Plus : 10 % allowance for wastage =
Total Volume =
Using the formula for Class A concrete:
1.68 m3 x 9 = 15.12; say
1.68m3 x 0.5 = 0.84; say
1.68m3 x 1.0 = 1.68; say

0.096 m3
1.53 m3
0.15 m3
1.68m3

Reinforced
Concrete
Beams

Ground Floor Beams


Length of Ground Floor Beam = 74.76 m
Conc. volume of beams = 0.2 x 0.4 x 74.76 = 5.98 m3
Plus : 10 % allowance for wastage =
0.60
Total Volume for Beam =
6.58 m3
Using the formula for Class A concrete:
6.58m3 x 9.0 = 59.22; say
6.58m3 x 0.5 = 3.29; say
6.58m3 x 1.0 = 6.58; say

60
3.5
7.0

Second Floor Concrete Beams


Length of Second Floor Beams = 122.624 m
Conc. volume of beams = 0.2 x 0.4 x 101.86 = 9.81
Plus : 5 % allowance for wastage =
0.49
Total Volume for Beam =
10.3 m3
Using the formula for Class A concrete:
10.3 m3 x 9.0 = 92.7; say
10.3m3 x 0.5 = 5.15; say
10.3m3 x 1.0 = 10.3; say

93
5.5
10.5

Roof Beams
Length of Roof Beams = 88.249 m
Conc. volume of beams = 0.2 x 0.4 x 94.97 = 7.05 m3
Plus : 5 % allowance for wastage =
0.35
Total Volume =
7.40 m3
Using Formula for Class A concrete:
7.4 m3 x 9.0 = 66.6; say
7.4 m3 x 0.5 = 3.7; say
7.4 m3 x 1.0 = 7.4; say

Concrete
Slab

67
4.0
7.5

Concrete Slab on Fill


Area of Conc. Slab = 164.25
Volume of Conc. Slab =164.25 x 0.125 = 20.53 m3
Plus : 10% allowance for wastage =2.05
Total volume of Concrete = 22.58 m3
Using Formula for Class B concrete:
22.58 m3 x 7.5 = 169.35; say
22.58 m3 x 0.5 = 11.29; say
22.58 m3 x 1.0 = 22.58; say

170
11.5
23.0

Second Floor Two-Way Slab ( S-1)


Area of Conc. Slab = 68.07
Volume of Conc. Slab = 68.07 x 0.10 = 6.81 m3
Plus : 5% allowance for wastage = 0.34
Total volume of Concrete = 7.15 m3
Using Formula for Class B concrete:
7.15 m3x 7.5 = 53.625; say
7.15 m3x 0.5 = 3.575; say
7.15 m3x 1.0 = 7.15; say

54
4.0
7.5

Second Floor Two-Way Slab ( S-2)


Area of Conc. Slab = 28.82
Volume of Conc. Slab = 28.82 x 0.10 = 2.88 m3
Plus : 5% allowance for wastage = 0.144
Total volume of Concrete = 3.024 m3
Using Formula for Class B concrete:
3.024 m3 x 7.5= 22.68; say
3.024 m3x 0.5 = 1.512; say
3.024 m3x 1.0 = 3.024; say

23
1.5
3.0

Second Floor Two-Way Slab ( S-3)


Area of Conc. Slab = 8.03
Volume of Conc. Slab = 8.03 x 0.10 = 0.803
Plus : 5% allowance for wastage = 0.40
Total volume of Concrete = 1.20 m3
Using Formula for Class B concrete:
1.20 m3 x 7.5= 9; say
1.20 m3x 0.5 = 0.6; say
1.20 m3x 1.0 = 1.20; say

9
1.0
1.50

Second Floor Two-Way Slab ( S-4)


Area of Conc. Slab = 15.33
Volume of Conc. Slab =15.33 x 0.10 = 1.53
Plus : 5% allowance for wastage = 0.08
Total volume of Concrete = 1.61
Using Formula for Class B concrete:
1.61 m3 x 7.5=12.08; say
1.61m3x 0.5 = 0.81; say
1.61m3x 1.0 =1.61; say
Second Floor Two-Way Slab ( S-5)
Area of Conc. Slab = 14.81
Volume of Conc. Slab = 14.81 x 0.10 = 1.48m3

13
1.0
2.0

Plus : 5% allowance for wastage = 0.07


Total volume of Concrete = 1.55 m3
12

Using Formula for Class B concrete:


1.55m3 x 7.5=11.625; say
1.55m3x 0.5 =0.775; say
1.55 m3x 1.0 = 1.55; say

Gravel Fill
Stair

1.0
1.50

Volume of Gravel =164.25 x 0.1 = 16.425

16.5

Stair Details
19 Steps with Landing
Rise =

140 mm

Run =

250 mm

Width = 925 mm
Thickness of RC Slab = 0.125m.
Using Special Formulas and Calculations
Conc. volume of stairs =

1.31 m3

Plus : 5% allowance for wastage = 0.07 m

13

1.0

Total volume of Concrete = 1.38 m

1.5

Using the formula for Class A concrete:

1.38 9.00=12.42 ; say


1.38 0.50=0.69 ; say
1.38 1.00=1.38 ; say
TOTALS

810

52

97

16.5

Masonry

PROJECT TITLE: TROPICAL SEMI-ATTACHED RESIDENCE


OWNER/S: MR. & MRS DANILO REYES
LOCATION: SOUTHERN YEMEN ST. BETTER LIVING SUBDIVISION, PARANAQUE CITY
BILL OF MATERIALS

Item To Be
Estimated

CHB for
Exterior
Wall

Materials And Estimated Quantities


Required

Calculations

CHB
(200mm
)

Exterior Wall from Footing to Second


Floor
Area of Wall = 62.35 x 3.4 = 211.99m2
Less: Door: 2(2.1 x 0.9) = 3.78
2(2.3 x 1.8) = 8.28
4(2.1 x 0.8) = 6.72
Window: 1.2 x 1.6 =1.92
1.2 x 1.1=1.32
4(1.2 x 0.8)=3.84
4(1.8 x 0.35)=2.52
2(1.3 x 0.65) =1.69
2(2.1 x 0.6)=2.52
2(0.9 x 1.1)=1.98
6(0.55 x 0.5)=1.65
Net CHB Wall Area =

175.7 7

No. of CHB required:

175.77 12.50=2197.125 ; say

2198

Exterior Wall from Second Floor to Roof


Beam
Area of Wall =

67.34 2.7=181.818 m2

Less: Door: 2(2.3 x 2.3)=10.58


Window: 2(2.75 x 2.0)=11
6(1.3 x 1.9)=14.82
2(1.1 x 0.9)=1.98
4(0.55 x 0.5)=1.1
Net CHB Wall Area =

142.338
1780

No. of CHB required:

142.338 12.50=1779.225

; say

CHB
(150mm
)

Cement
(Bags)

Gravel
(Cu.m.)

Gravel Fill
(Cu.m.)

CHB for
Interior
Wall

Interior Wall on First Floor


Area of Wall =
Less: Door:

27.75 3.4=94.35 m

4 (2.1 x 0.6)=5.04

Net CHB Wall Area =

89.31 m

1117
No. of CHB required:

89.31 12.50=1116.375 ; say


Interior Wall on Second Floor
Area of Wall =
Less: Door:

46.46 2.7=125.442 m2

6(2.1 x 0.8)=10.08 m2

1380

4 (0.60 2.10)=5.04 m

Net CHB Wall Area =

110.322 m2

No. of CHB required:

110.322 12.50=1379.025

Materials
for CHB
wall
Footings

; say

Exterior Wall Footing


Total Length of Exterior Wall Footing =

62.35 m
Using the Volume Method of Concrete
Conc. volume of footing =

62.35 0.40 0.20=4.988 m

Plus : 10 % allowance for wastage =

0.50 m3
3

Total volume of footings = 5.49 m


Under Class A concrete mixture:

5.49 9.00=49.41 ; say


5.49 0.50=2.75 ; say

49
3.0
5.5

5.49 1.00=5.49 ; say


Interior Wall Footing
Total Length of Interior Wall Footing =

27.75 m
Using the Volume Method of Concrete
Conc. volume of footing =

22
1.5
2.5

27.75 0.40 0.20=2.22 m

Plus : 10 % allowance for wastage =

0.22 m3
Total volume of footings = 2.44 m

Under Class A concrete mixture:

2.44 9.00=21.96 ; say


2.44 0.50=1.22 ; say
2.44 1.00=2.44 ; say

Materials
for Cement
Mortar

Exterior Wall
Total Area =

175.77+142.338=318.11 m2
Under Class A mixture for a 200mm CHB:

719

318.11 2.26=718.93 ; say

39.0

318.11 0.125=38.76 ; say

Interior Wall
Total Area =

89.31+110.322=199.63 m2
Under Class B mixture for a 150 mm CHB:

199.63 1.526=304.64

; say

199.63 0.0844=16.85 ; say

305

17.0

Materials
for Cement
Mortar
Plastering

Exterior Wall
Total Area =

1175.77+ 142.338=318.11 m

Under 16 mm thick plaster Class A mixture:

92

318.11 .288=91.62 ; say

5.5

318.11 .016=5.09 ; say


Interior Wall
Total Area =

39

89.31+110.322=199.63 m2

3.5

Under 16 mm thick plaster Class B mixture:

199.63 0.192=38.33 ; say


199.63 0.016=3.19 ; say
TOTALS

3978

2497

1226

69.5

11.5

Metal
Reinforcement

PROJECT TITLE: TROPICAL SEMI-ATTACHED RESIDENCE


OWNER/S: MR. & MRS DANILO REYES
LOCATION: SOUTHERN YEMEN ST. BETTER LIVING SUBDIVISION, PARANAQUE CITY

BILL OF MATERIALS COMPUTATION


Item To Be
Estimated

Footings
Bars

Calculations

Materials And Estimated Quantities


Required
10MM
X 6.00M

12MM
X 6.00M

16MM
X 6.00M

Central Footing-1for Rectangular Column


Length of footing bar =

1.20 m

Plus:
Mild Steel Hook Allowance =

9 0.016=0.144 m
Allowance per footing bar =

2 0.144=0.288 m
Total Length of footing bar =

1.20+0.288=1.488 m
No. of Bar per Footing = 5 pieces
Total Length of bar per footing =

5 1.488=7.44 m
Total Length of bars for 4 footings =

4 7.44=29.76 m

Total Length of Side Footing Bars

29.76 x 2=59.52

10

20MM
X 6.00M

No. of Bars required:

59.52
=9.92 ; say
6
Central Footing-2 for Rectangular Column
Length of footing bar =

1.30 m

Plus:
Mild Steel Hook Allowance =

9 0.016=0.144 m
Allowance per footing bar =

2 0.144=0.288 m
Total Length of footing bar =

1.30+0.288=1.588 m
No. of Bar per Footing = 6 pieces
Total Length of bar per footing =

21

6 1.488=8.928 m
Total Length of bars for 7 footings =

7 8.928=62.496 m
Total Length of Side Footing Bars

62.496 x 2=124.992
No. of Bars required:

124.992
=20.832 ; say
6
Central Footing-3for Rectangular Column
Length of footing bar =

1.40 m

Plus:
Mild Steel Hook Allowance =

9 0.016=0.144 m
Allowance per footing bar =

2 0.144=0.288 m
Total Length of footing bar =

1.40+0.288=1.688 m
No. of Bar per Footing = 7 pieces
Total Length of bar per footing =

7 1.688=11.816 m
Total Length of bars for 2 footings =

2 11.816=23.632 m

Total Length of Side Footing Bars

23.632 x 2=47.264
No. of Bars required:

47.264
=7.88 ; say
6

10

Central Footing-4for Rectangular Column


Length of footing bar =

1.55 m

Plus:
Mild Steel Hook Allowance =

9 0.016=0.144 m
Allowance per footing bar =

2 0.144=0.288 m
Total Length of footing bar =

1.55+0.288=1.838 m
No. of Bar per Footing = 8 pieces
Total Length of bar per footing =

8 1.838=14.704 m
Total Length of bars for 2 footings =

2 14.704=29.408 m
Total Length of Side Footing Bars

29.408 x 2=58.816

15

No. of Bars required:

58.816
=9.80 ; say
6

Cen/Can Footing-5for Rectangular Column


Length of footing bar =

0.6 m

Plus:
Mild Steel Hook Allowance =

9 0.016=0.144 m
Allowance per footing bar =

2 0.144=0.288 m
Total Length of footing bar =

0.6+0.288=0.888 m
No. of Bar per Footing = 3 pieces
Total Length of bar per footing =

3 0.888=2.664 m

Total Length of bars for 16footings =

16 2.664=42.624 m

Total Length of Side Footing Bars

42.624 x 2=85.248
No. of Bars required:

85.248
=14.208 ; say
6
Cantilever Footing-6for Rectangular Column
Length of footing bar =

1.05 m

Plus:
Mild Steel Hook Allowance =

9 0.016=0.144 m
Allowance per footing bar =

2 0.144=0.288 m
Total Length of footing bar =

1.05+0.288=1.338 m

5
No. of Bar per Footing = 4 pieces
Total Length of bar per footing =

4 1.338=5.352 m
Total Length of bars for 4 footings =

4 5.352=21.408 m

Total Length of Side Footing Bars

21.408 x 2=42.816

No. of Bars required:

42.816
=7.136 ; say
6

CantileverFooting-7 for Rectangular Column


Length of footing bar =

1.15 m

Plus:
Mild Steel Hook Allowance =

9 0.016=0.144 m
Allowance per footing bar =

2 0.144=0.288 m
Total Length of footing bar =

1.15+0.288=1.438 m
6
No. of Bar per Footing = 5 pieces
Total Length of bar per footing =

5 1.438=7.19 m

Total Length of bars for 2 footings =

2 7.19=14.38 m

Total Length of Side Footing Bars

14.38 x 2=28.76
No. of Bars required:

28.76
=4.79 ; say
6
Combined Footing-1 for Rectangular Column
Length of footing bar S =

1.35 m

Plus:
Mild Steel Hook Allowance =

9 0.016=0.144 m
Allowance per footing bar S =

2 0.144=0.288 m
Total Length of footing bar S =

1.35+0.288=1.638 m
No. of Bar S per Footing = 6 pieces
Total Length of bar S per footing =

6 1.638=9.828 m

Length per footing bar L =

2.05 m

Plus:
Mild Steel Hook Allowance =

9 0.016=0.144 m
Allowance per footing bar L =

2 0.144=0.288 m
Total Length per footing bar L =

2.05+0.288=2.338 m
No. of bar L per footing = 10 pieces
Total Length of bar S per footing =

10 2.338=23.38 m

Total Length of Side Footing Bars

9.828 m+ 23.38 m=38.208


No. of Bars required:

38.208
=5.53
6

Rectangular Column Bars -1

Column
Bars

Length of vertical bar =

7.85 m

Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
Allowance per vertical bar =

0.08 m

Total Length of vertical bar =

7.85+0.08=7.93 m
No. of vertical bar per column = 5pieces
Total Length of vertical bar per column =

6 7.93=47.58 m
No. of Rectangular Column = 10 sets
Total Length of Vertical Bars =

10 47.58=475.8 m
No. of Bars required:

475.8
=79.3 ; say
6

Length of vertical bar =

6.85 m

Plus:
Mild Steel Bend Allowance =

80

5 0.016=0.08 m
Allowance per vertical bar =

0.08 m

Total Length of vertical bar =

6.85+0.08=6.93 m
No. of vertical bar per column = 6 pieces
Total Length of vertical bar per column =

6 6.93=41.58 m
No. of Bars required:

41.58
=6.93 ; say
6
Rectangular Column Bars -2
Length of vertical bar =

7.85 m

Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
Allowance per vertical bar =

0.08 m

53

Total Length of vertical bar =

7.85+0.08=7.93 m
No. of vertical bar per column = 8 pieces
Total Length of vertical bar per column =

8 7.93=63.44 m
No. of Rectangular Column = 5 sets
Total Length of Vertical Bars =

5 63.44=317.2 m
No. of Bars required:

317.2
=52.87 ; say
6

19

Length of vertical bar =

6.85 m

Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
Allowance per vertical bar =

0.08 m

Total Length of vertical bar =

6.85+0.08=6.93 m
No. of vertical bar per column = 8 pieces
Total Length of vertical bar per column =

8 6.93=55.44 m
No. of Rectangular Column = 2 sets
Total Length of Vertical Bars =

13

2 55.44=110.88 m
No. of Bars required:

110.88
=18.48 ; say
6

Length of vertical bar =

4.8 m

Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
Allowance per vertical bar =

0.08 m

Total Length of vertical bar =

4.8+ 0.08=4.88 m
No. of vertical bar per column = 8 pieces
Total Length of vertical bar per column =

8 4.88=39.04 m
No. of Rectangular Column = 2 sets
Total Length of Vertical Bars =

2 39.04=78.08 m
No. of Bars required:

14

78.08
=13.01 ; say
6

Rectangular Column Bars -3


Length of vertical bar =

7.85 m

Plus:
Mild Steel Bend Allowance =

21

5 0.016=0.08 m
Allowance per vertical bar =

0.08 m

Total Length of vertical bar =

7.85+0.08=7.93 m
No. of vertical bar per column = 10 pieces
Total Length of vertical bar per column =

10 7.93=79.3 m
No. of Bars required:

79.3
=13.22 ; say
6
Planted Column-1
Length of vertical bar =

3.00 m

24

Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
Allowance per vertical bar =

0.08 m

Total Length of vertical bar =

3.00+0.08=3.08 m
No. of vertical bar per column = 8 pieces
Total Length of vertical bar per column =

8 3.08=24.64 m

No. of Rectangular Column = 5 sets


Total Length of Vertical Bars =

5 24.64=123.2 m
No. of Bars required:

123.2
=20.53 ; say
6
SC-1
Length of vertical bar =

2.125 m

168

Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
Allowance per vertical bar =

0.08 m

Total Length of vertical bar =

2.125+0.08=2.205 m

No. of vertical bar per column = 4 pieces


Total Length of vertical bar per column =

4 2.205=8.82m

No. of Rectangular Column = 16 sets


Total Length of Vertical Bars =

16 8.82=141.12m

58
No. of Bars required:

141.12
=23.52 ; say
6
-------------------------------------------Column Ties / Lateral Ties
All Column Ties per set should be spaced, 1 @ 0.05
m; 10 @ 0.10 m; Rest @ 0.20 m O.C.
Length of column tie =

0.12+0.32+0.12+0.32=0.88 m

Plus:
Mild Steel Hook Allowance =

9 0.010=0.09 m
Allowance per column tie =

2 0.09=0.18 m

Total Length of column tie =

0.88+0.18=1.06 m
Rectangular Columnfrom Foundation to Second
Floor Beam
No. of column tie per column = 46 pieces
Total Length of column ties per column =

46 1.06=47.84 m
No. of Rectangular Column = 21 sets
Total Length of Column Ties =

21 47.84=1004.64 m
No. of Bars required:

1004.64
=167.44 ; say
6
Rectangular Columnfrom Second Floor to Roof
Slab
No. of column tie per column = 15 pieces
Total Length of column ties per column =

15 1.06=15.9m
No. of Rectangular Column = 16 sets
Length of column ties for 15 columns =

16 15.9=254.4 m
Plus:
11 pieces of column ties for 8 sets of column =

1.06 11 8=93.28 m
Total Length of Column Ties =

No. of Bars required:

347.68 m

347.68
=57.95 ; say
6

Beam Bars

GB-1
Ground Floor Beams
Length of Ground Floor Beam = 14.086 m
No. of horizontal top bar per beam = 2 pieces
No. of horizontal bottom bar per beam = 2 pieces
Length of horizontal bars =

2 x 14.086=28.172 m
Plus:
Mild Steel Bend Allowance =

5 0.012=0.06 m
No. of ground floor beam = 4 sets
Length of bend allowance =

4 2 4 0.06=1.92m
Total Length of Footing Tie Beam Bars =

309.6 m
No. of Bars required:

30.092
=5.02 ; say
6
No. of web bars per beam = 2 pieces
Length of web bars = 2 x 14.086= 28.172
Plus:
Mild Steel Bend Allowance =

5 0.012=0.06 m
No. of ground floor beam = 4 sets
Length of bend allowance =

4 2 2 0.06=0.96 m
Total Length of Web Beam Bars =

29.132 m
No. of Bars required:

29.132
=4.86 ; say
6

GB-2
Ground Floor Beams
Length of Ground Floor Beam = 27.138 m
No. of horizontal top bar per beam = 5 pieces
No. of horizontal bottom bar per beam = 5 pieces
Length of horizontal bars =

10 x 27.138=271.38m
47
Plus:
Mild Steel Bend Allowance =

5 0.012=0.06 m
No. of ground floor beam = 8 sets
Length of bend allowance =

8 2 10 0.06=9.6 m
Total Length of Footing Tie Beam Bars =

279.78 m
10

No. of Bars required:

280.98
=46.83 ; say
6
No. of web bars per beam = 2 pieces
Length of web bars = 2 x 27.138= 54.276
Plus:
Mild Steel Bend Allowance =

5 0.012=0.06 m
No. of ground floor beam = 8 sets
Length of bend allowance =

8 2 2 0.06=1.92 m

Total Length of Web Beam Bars =

No. of Bars required:

56.196
=9.37 ; say
6
GB-3
Ground Floor Beams
Length of Ground Floor Beam = 33.536 m

35

No. of horizontal top bar per beam = 3 pieces


No. of horizontal bottom bar per beam = 3 pieces
Length of horizontal bars =

6 x 33.536=201.216 m
Plus:
Mild Steel Bend Allowance =

5 0.012=0.06 m

12

No. of ground floor beam = 9 sets


Length of bend allowance =

9 2 6 0.06=6.48 m
Total Length of Footing Tie Beam Bars =

279.78 m
No. of Bars required:

207.696
=34.62; say
6
No. of web bars per beam = 2 pieces
Length of web bars = 2 x 33.536 = 67.072
Plus:
Mild Steel Bend Allowance =

29

5 0.012=0.06 m
No. of ground floor beam = 9 sets
Length of bend allowance =

9 2 2 0.06=2.16 m
Total Length of Web Beam Bars =

69.232 m
No. of Bars required:

69.232
=11.54 ; say
6
2B-1
Second Floor Concrete Beam
Total Length of 2B1 =

40.69 m

No. of horizontal top bar per beam = 2 pieces


No. of horizontal bottom bar per beam = 2 pieces

29

Length of horizontal bars =

4 40.69=162.76 m
Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
No. of 2B1 beam = 16 sets
Length of bend allowance =

16 2 4 0.08=10.24 m
Total Length of Horizontal Bars =

91.62 m
No. of Bars required:

173
=28.83; say
6
No. of web bars per beam = 4 pieces
Length of web bars = 4 x 40.69 = 162.76
Plus:
Mild Steel Bend Allowance =

37

5 0.012=0.06 m
No. of second floor beam = 16 sets
Length of bend allowance =

16 2 4 0.08=10.24 m

Total Length of Web Beam Bars =

173 m

No. of Bars required:

173
=28.83; say
6
2B-2
Second Floor Concrete Beam
Length of 2B2 = 46.01 m
No. of horizontal top bar per beam = 2 pieces
No. of horizontal bottom bar per beam = 2 pieces
Length of Horizontal Bars =

4 46.01=184.04 m
Plus:
Mild Steel Bend Allowance =

17

5 0.016=0.08 m
No. of 2B2 beam = 14 sets
Length of bend allowance =

14 2 4 0.08=8.96 m

193 m

Total Length of Horizontal Bars =


Length of left and right support bar =

11.5025 m
No. of left and right support bar = 2 pieces
Length of left and right support bar =

2 11.50=23.0 m
Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
11

No. of 2B2 beam = 14 sets


Length of bend allowance =

14 2 2 0.08=4.48 m
Total Length of Left and Right Support Bar =

27.485 m

Total Length of 2B2 Bars =

220.485 m

No. of Bars required:

220.485
=36.7475; say
6
7

No. of web bars per beam = 2 pieces


Length of web bars = 2 x 46.01 = 92.02
Plus:
Mild Steel Bend Allowance =

5 0.012=0.06 m
No. of second floor beam = 14 sets
Length of bend allowance =

14 2 2 0.08=4.48 m

Total Length of Web Beam Bars =


No. of Bars required:

96.5 m

96.5
=16.08 ; say
6
2B-3
Second Floor Concrete Beam
Total Length of 2B3 =

8.998 m

No. of horizontal top bar per beam = 2 pieces


No. of horizontal bottom bar per beam = 3 pieces
Length of Horizontal Bars =

5 8.998=44.99 m
Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
No. of 2B3 beam = 2 sets
Length of bend allowance =

2 2 5 0.08=1.6 m
Total Length of Horizontal Bars =

46.59 m

Length of left and right support bar =

4.499 m

No. of left and right support bar =3 pieces


Length of left and right support bar =

3 4.499=13.497 m
Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
No. of 2B3 beam = 2 sets
Length of bend allowance =

2 2 3 0.08=0.96 m
Total Length of Left and Right Support Bar =

14.457 m

Total Length of 2B-3 Bars =


No. of Bars required:

61.047
=10.17 ; say
6

61.074 m

No. of web bars per beam = 4 pieces


Length of web bars = 4 x 8.998 = 35.992
Plus:
Mild Steel Bend Allowance =

5 0.012=0.06 m
No. of second floor beam = 14 sets
Length of bend allowance =

14 2 2 0.08=4.48 m
Total Length of Web Beam Bars =
10

40.472 m
No. of Bars required:

40.472
=6.75 ; s ay
6
2B-4
Second Floor Concrete Beam
Total Length of 2B4 =

4.434 m

No. of horizontal top bar per beam = 3 pieces


No. of horizontal bottom bar per beam = 3 pieces
Length of horizontal bars =
7

6 4.434=26.604 m
Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
No. of 2B1 beam = 1 set
Length of bend allowance =

1 2 6 0.08=0.96 m
Total Length of Horizontal Bars =

27.564 m

Length of left and right support bar =

2.2495 m

No. of left and right support bar =2 pieces


Length of left and right support bar =

2 2.2495=4.499 m
Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
No. of 2B4 beam = 1 set
Length of bend allowance =

1 2 2 0.08=0.32m
Total Length of Left and Right Support Bar =

4.819 m
Total Length of 2B-4 Bars = 32.383 m
7
No. of Bars required:

32.383
=5.397 ; say
6
No. of web bars per beam = 2 pieces
Length of web bars = 2 x 4.434 = 8.868
Plus:
Mild Steel Bend Allowance =

5 0.012=0.06 m
No. of second floor beam = 1 set
Length of bend allowance =

1 2 2 0.08=0.32m

Total Length of Web Beam Bars =

9.188 m

No. of Bars required:

56

9.188
=1.53 ; say
6

2B-5
Second Floor Concrete Beam
Total Length of 2B5 =

9.466 m

No. of horizontal top bar per beam = 3 pieces


No. of horizontal bottom bar per beam = 2 pieces
Length of horizontal bars =
Plus:
Mild Steel Bend Allowance =

5 9.466=47.33 m
27

5 0.016=0.08 m
No. of 2B1 beam = 3 sets
Length of bend allowance =

3 2 5 0.08=2.4 m
Total Length of Horizontal Bars =

49.73 m

Length of left and right support bar =

4.733 m

Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
No. of 2B5 beam = 1 set
Length of bend allowance =

14

1 2 1 0.08=0.16 m
Total Length of Left and Right Support Bar =

4.893 m
Total Length of 2B-4 Bars = 54.623 m
No. of Bars required:

54.623
=9.10; say
6
No. of web bars per beam = 4 pieces
Length of web bars = 4 x 9.466 = 37.864
Plus:
Mild Steel Bend Allowance =

5 0.012=0.06 m
No. of second floor beam = 1 set
Length of bend allowance =

1 2 2 0.08=0.32m
Total Length of Web Beam Bars =

38.184 m
No. of Bars required:

38.184
=6.364 ; say
6

2CB-1
Second Floor Concrete Beam
Total Length of 2B1 =

8.82 m

No. of horizontal top bar per beam = 3 pieces


No. of horizontal bottom bar per beam = 2 pieces
Length of horizontal bars =

5 8.82=44.1 m

Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
No. of 2B1 beam = 4 sets
Length of bend allowance =

4 2 5 0.08=3.2m
3
Total Length of Horizontal Bars =

47.3 m

No. of Bars required:

47.3
=7.88 ; say
6
No. of web bars per beam = 4 pieces
Length of web bars = 4 x 8.82 = 35.28
Plus:
Mild Steel Bend Allowance =

5 0.012=0.06 m
No. of second floor beam = 4 sets
Length of bend allowance =

4 2 4 0.08=2.56 m

Total Length of Web Beam Bars =

37.84 m

No. of Bars required:

37.84
=6.31 ; say
6
27
RB-1
Roof Beam
Total Length of RB-1 =

79.749 m

No. of horizontal top bar per beam = 2 pieces

No. of horizontal bottom bar per beam = 2 pieces


Length of Horizontal Bars =
53

4 79.749=318.996 m
Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
No. of UDB1 beam = 22 sets
Length of bend allowance =

22 2 4 0.08=14.08 m
Total Length of Horizontal Bars = 333.076 m

63

No. of Bars required:

333.076
=55.51; say
6
No. of web bars per beam = 2 pieces
Length of web bars = 2 x 79.749 = 159.498
Plus:
Mild Steel Bend Allowance =

5 0.012=0.06 m

90

No. of roof beam = 2 sets


Length of bend allowance =

2 2 2 0.08=0.64 m

Total Length of Web Beam Bars =

160.138 m

No. of Bars required:

160.138
=26.69 ; say
6

90

RCB
Roof Beam
Total Length of RCB =

8.5 m

No. of horizontal top bar per beam = 6 pieces


No. of horizontal bottom bar per beam = 3 pieces
Length of Horizontal Bars =

9 8.5=76.5 m

16

Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
No. of UDB2 beam = 4 sets
Length of bend allowance =

4 2 9 0.08=5.76 m
Total Length of Horizontal Bars =

82.26 m

No. of Bars required:

82.26
=13.71; say
6
No. of web bars per beam = 2 pieces
Length of web bars = 2 x 8.5 = 17
Plus:
Mild Steel Bend Allowance =

19

5 0.012=0.06 m
No. of roof beam = 4 sets
Length of bend allowance =

4 2 2 0.08=1.28m

Total Length of Web Beam Bars =

18.28 m

No. of Bars required:

21

18.28
=3.05; say
6
SB
Stair Beam
Total Length of Stair Beam =

4.0 m

No. of horizontal top bar per beam = 3 pieces


No. of horizontal bottom bar per beam = 3 pieces
Length of Horizontal Bars =
Plus:
Mild Steel Bend Allowance =

5 0.016=0.08 m
No. of UDB2 beam = 2 sets
Length of bend allowance =

6 4.0=24.0 m

2 2 6 0.08=1.92 m
Total Length of Horizontal Bars =
147

25.92 m
No. of Bars required:

25.92
=4.32; say
6
No. of web bars per beam = 4 pieces
Length of web bars = 4 x 4 = 16
Plus:
Mild Steel Bend Allowance =

21

5 0.012=0.06 m
No. of roof beam = 2 sets
Length of bend allowance =

2 2 4 0.08=1.28m

Total Length of Web Beam Bars =

17.28 m

No. of Bars required:

17.28
=2.88; say
6
-------------------------------------------Stirrups / Beam Ties
All Stirrups per set should be spaced, 1 @ 0.05 m;
10 @ 0.10 m; Rest @ 0.20 m O.C.
Length of stirrups =

0.20+0.40+ 0.20+0.40=1.20
Plus:
Mild Steel Hook Allowance =

9 0.010=0.09 m
Allowance per column tie =

2 0.09=0.18 m

Total Length of column tie =

1.20+0.18=1.38 m
For GB-1

Ground Floor Beam


No. of stirrups = 117 pieces
Total Length of Stirrups =

117 1.38=161.46 m
No. of Bars required:

161.46
=26.91; say
6
For GB-2
Ground Floor Beam
No. of stirrups = 228 pieces
Total Length of Stirrups =

228 1.38=314.64 m
No. of Bars required:

314.64
=52.44 ; say
6
For GB-3
Ground Floor Beam
No. of stirrups = 272 pieces
Total Length of Stirrups =

272 1.38=375.36 m

No. of Bars required:

375.36
=62.56 ; say
6
For 2B-1
Second Floor Concrete Beam
No. of stirrups = 388 pieces
Total Length of Stirrups =

388 1.38=535.44 m
No. of Bars required:

535.44
=89.24 ; say
6

For 2B-2
Second Floor Concrete Beam
No. of stirrups = 391 pieces
Total Length of Stirrups =

391 1.38=539.58 m
No. of Bars required:

539.58
=89.93; say ..
6
For 2B-3
Second Floor Concrete Beam
No. of stirrups = 68 pieces
Total Length of Stirrups =

68 1.38=93.84 m
No. of Bars required:

93.84
=15.64 ; say ..
6
For 2B-4
Second Floor Concrete Beam
No. of stirrups = 34 pieces
Total Length of Stirrups =

34 1.38=46.92 m
No. of Bars required:

46.92
=7.82; say
6
For 2B-5
Second Floor Concrete Beam
No. of stirrups = 82 pieces
Total Length of Stirrups =

82 1.38=113.16 m
No. of Bars required:

113.16
=18.86 ; say ..
6

For 2CB-1
Second Floor Concrete Beam
No. of stirrups = 90 pieces
Total Length of Stirrups =

90 1.38=124.2m
No. of Bars required:

124.2
=20.7 ; say
6
For SB
Stair Beam
No. of stirrups = 33 pieces
Total Length of Stirrups =

33 1.38=45.54 m
No. of Bars required:

45.54
=7.59 ; say ..
6
For RB-1
Roof Beam
No. of stirrups = 652 pieces
Total Length of Stirrups =

652 1.38=899.76 m
No. of Bars required:

899.76
=146.96 ; say
6
For RCB
Roof Beam
No. of stirrups = 88 pieces
Total Length of Stirrups =

88 1.38=121.44 m

No. of Bars required:

121.44
=20.24 ; say
6

Reinforced
Bars on
CHB Wall
Footing

Exterior Wall Footing


Total Length of Exterior Wall Footing =

62.35 m
For longitudinal bars at 0.30 m on center:

62.35 3=187.05m long


32
No. of Bars required:

187.05
=31.175 ; say
6

For transverse bars at 0.30 m on center:


No. of transverse bars = 208 pieces
14

208 0.40=83.2 mlong


No. of Bars required:

83.2
=13.87 ; say
6
Interior Wall Footing
Total Length of Interior Wall Footing =

27.75 m
14

For longitudinal bars at 0.30 m on center:

27.75 3=83.25 mlong

No. of Bars required:

83.25
=13.875; say
6

For transverse bars at 0.30 m on center:


No. of transverse bars = 93 pieces

93 0.40=37.2 mlong
No. of Bars required:

37.2
=6.2
6
Reinforced
Bars on
CHB Wall

Exterior Wall from Footing to Second Floor


Area of Wall = 62.35 x 3.4 = 211.99m2
Less: Door: 2(2.1 x 0.9) = 3.78
2(2.3 x 1.8) = 8.28
4(2.1 x 0.8) = 6.72
Window: 1.2 x 1.6 =1.92
1.2 x 1.1=1.32
4(1.2 x 0.8)=3.84
4(1.8 x 0.35)=2.52
2(1.3 x 0.65) =1.69
2(2.1 x 0.6)=2.52
2(0.9 x 1.1)=1.98
6(0.55 x 0.5)=1.65
Net CHB Wall Area =

175.77

Under vertical reinforcement spaced at 0.60m:

175.77 2.13=374.39m long


Under horizontal reinforcement at every 3 layers:

175.77 2.15=377.91m long

No. of Bars required:

374.39+377.91
=125.38 ; say
6

Exterior Wall from Second Floor to Roof Beam


Area of Wall =

67.34 2.7=181.818 m2

Less: Door: 2(2.3 x 2.3)=10.58

126

Window: 2(2.75 x 2.0)=11


6(1.3 x 1.9)=14.82
2(1.1 x 0.9)=1.98
4(0.55 x 0.5)=1.1
Net CHB Wall Area =

142.338

Under vertical reinforcement spaced at 0.60m:

142.338 2.13=303.18 m long


Under horizontal reinforcement at every 3 layers:

142.338 2.15=306.03 m long


102
No. of Bars required:

303.18+ 306.03
=101.535; say
6
Interior Wall on First Floor
Area of Wall =
Less: Door:

27.75 3.4=94.35 m2

4 (2.1 x 0.6)=5.04

Net CHB Wall Area =

89.31 m

Under vertical reinforcement spaced at 0.60m:

89.31 2.13=190.23 m long

64

Under horizontal reinforcement at every 3 layers:

89.31 2.15=192.02 mlong


No. of Bars required:

190.23+192.02
=63.71 ; say
6
Interior Wall on Second Floor
Area of Wall =
Less: Door:

46.46 2.7=125.442 m

6(2.1 x 0.8)=10.08 m2

4 (0.60 2.10)=5.04 m2

79

Net CHB Wall Area =

110.322 m

Under vertical reinforcement spaced at 0.60m:

110.322 2.13=234.99 mlong


Under horizontal reinforcement at every 3 layers:

110.322 2.15=237.19 mlong


No. of Bars required:

234.99+ 237.19
=78.70; say
6
TOTAL

789

126

Lumber

1015

PROJECT TITLE: TROPICAL SEMI-ATTACHED RESIDENCE


OWNER/S: MR. & MRS DANILO REYES
LOCATION: SOUTHERN YEMEN ST. BETTER LIVING SUBDIVISION, PARANAQUE CITY

BILL OF MATERIALSCOMPUTATION SHEET


Item To Be
Estimated
Ceiling Joist

Materials And Estimated Quantities


Required

Calculations

6mm THK
Plywood

12mm THK
Plywood

2 by 2
Lumber

First Floor Ceiling


First Floor Area = 164.25 m2
Less: Stairwell Area =

6.555 x 2=13.11

Total First Floor Ceiling Area =

151.14 m2

Under 2 by 2 ceiling joist at 0.40 m by 0.40 m


spacing :

151.14 6.379=964.12 ; say


Second Floor Ceiling
Second Floor Area =

135.06 m

Less: Interior Wall Area =

965

2 by 3
Lumber

798

67.34 0.15=10.1 m

Total First Floor Ceiling Area =

124.96 m2

Under 2 by 2 ceiling joist at 0.40 m by 0.40 m


spacing :

124.96 6.379=797.12 ; say

Ceiling
Board

First Floor Ceiling


First Floor Area = 164.25 m2

6.555 x 2=13.11

Less: Stairwell Area =

Total First Floor Ceiling Area =

151.14 m

No. of Plywood required:


53

151.14
=52.48 ; say
2.88
Second Floor Ceiling
Second Floor Area =

135.06 m2

Less: Interior Wall Area =

67.34 0.15=10.1 m2
Total First Floor Ceiling Area =

44

124.96 m2

No. of Plywood required:

124.96
=43.39
2.88

Forms for
Rectangular
Column

Rectangular Column 1,2 & 3

P=2 ( a+b ) +0.20


P=2 ( 0.4+ 0.2 )+ 0.20
P=1.4 m
2

Area of the Forms 1.4 7.85=10.99 m

Total Area for 16 columns

10.99 16=175.84 m2

62

No. of Plywood required:

175.84
=61.06 ; say
2.88

1840

Under Column using 6 mm thick plywood on 2 by


2 wood frame:

62 29.67=1839.54 ; say
Rectangular Column 2

P=2 ( a+b ) +0.20


P=2 ( 0.4+ 0.2 )+ 0.20
P=1.4 m
8
Area of the Forms 1.4 7.8=10.92m

Total Area for 2 columns

10.92 2=21.84 m2
238
No. of Plywood required:

21.84
=7.58 ; say
2.88
Rectangular Column 1 & 2
Under Column using 6 mm thick plywood on 2 by
2 wood frame:

8 29.67=237.36 ; say
10

P=2 ( a+b ) +0.20


P=2 ( 0.4+ 0.2 )+ 0.20
P=1.4 m

297

Area of the Forms 1.4 6.85=9.59 m

Total Area for 3 columns

9.59 3=28.77 m2
No. of Plywood required:

28.77
=9.99 ; say
2.88

Under Column using 6 mm thick plywood on 2 by


2 wood frame:

10 29.67=296.7 ; say
Forms for
Beam and
Girder

P=

2 ( a+b ) +0.10

P=

2 ( 0.40+0.20 ) +0.10

P=

1.30

Total Length of Beams =

285.727 m

Total Area of the beams

1.30 285.727=371.445 m2
129
No. of Plywood required:

371.445
=128.97 ; say
2.88

3828

Under Beam using 6 mm thick plywood on 2 by 2


wood frame:

129 29.67=3827.43 ; say

Forms for
Concrete
Slab

Total Area of Concrete Slab =


No. of Plywood required:

299.31
=103.93
2.88

299.31 m2
104

Scaffolding
for Column

Length of Column =

7.85 m

Total Length for 11 columns

7.85 11=86.35 m

Length of Column =

7.8 m

Total Length for 2 columns

7.8 2=15.6 m

Length of Column =

6.85 m

Total Length for 3 columns

6.85 3=20.55 m
Length of Column = 4.85 m
Total Length for 2 columns

4.85 2=9.7 m
926
Net Length = 132.2
Under Column using 2 by 3 lumber for vertical
support:

132.2 7.00=925.4

; say

Under Column using 2 by 2 lumber for horizontal


support:

132.2 21.00=2776.2 ; say

Under Column using 2 by 2 lumber for diagonal


braces:

132.2 11.70=1546.74 ; say

Scaffolding
for Beam
and Girder

Total Length of Beams =

2777

371.445 m

1547

Under Beam using 2 by 3 lumber for vertical


support:

2229

371.445 6.00=2228.67 ; say


Under Beam using 2 by 2 lumber for horizontal
support:

1746

371.445 4.70=1745.79 ; say

Scaffolding
for Concrete
Slab

Total Area of Concrete Slab =

299.31 m2

Under Column using 2 by 3 lumber for vertical


support:
2724

299.31 9.10=2723.72 ; say


TOTALS

209

201

14036

5879

Tile works

PROJECT TITLE: TROPICAL SEMI-ATTACHED RESIDENCE


OWNER/S: MR. & MRS DANILO REYES
LOCATION: SOUTHERN YEMEN ST. BETTER LIVING SUBDIVISION, PARANAQUE CITY

BILL OF MATERIALS COMPUTATION


Item To Be
Estimated

Calculations

Materials And Estimated Quantities


Required

0.3 x 0.3
Unglazed
Floor tiles

Floor Tiles

0.3 x 0.3
Wall tiles

0.6 x 0.6
Unglazed
Floor Tiles

First Floor Tiles


First Floor Area =

41.3404 + 40.5320 = 80.87

Less: Kitchen Area = 17.05 + 16.9725 = 34.0225


Net First Floor Area =

48.85 m2

Under 60 by 60 cm floor tiles:

48.85 2.78=135.803
Plus : 10 % allowance for cutting and edging =

150

13.58
Total No. of Tiles = 149.38 ; say
Second Floor Tiles
Second Floor Area =

5.9294+6.325=12.25

38

Under 60 by 60 cm floor tiles:

12.25 2.78=34.055
Plus : 10 % allowance for cutting and edging =

3.41
Total No. of Tiles = 37.465 ; say

Bedroom
Floor Tiles

Bedroom 1 Floor Area =


27.75 m

14.0 .9+ 13.66=

Bedroom 2 Floor Area = 14.16 + 14.09 = 29.25

m2
Masters Bed Floor Area = 20.91 + 21.70 = 42.61

m2
333

2
Maids Room = 4.5 + 4.7 = 9.2 m

Net Bedroom Floor Area =


Under 60 by 60 cm floor tiles:

108.81 2.78=302.49

108.81m

Plus : 10 % allowance for cutting and edging =

30.25
Total No. of Tiles = 332.75 ; say

Stair Tiles

Stair Tread Area =

0.95 0.30=0.285 m2

No. of Steps = 19 Steps


Stair Tread Area for 19 steps =

19 0.258=4.902 m2
Stair Landing Area =

2.11 0.95=2.11 m2

Net Stair Tile Area =

Net Bedroom Floor Area =

8.71 m2
93.72 ft 2

Plus : 5 % allowance for cutting and edging =

4.68 ft 2
Total Stair Tile Area =

Unit AMasters
T&B

98.40 ft 2 ; say

Bathroom Wall Tiles


Wall Area= 2.524 x 2.6 = 6.31
2 x 2.4 = 4.8
2.5 x 2.6 = 6.25
1.5 x 2.4 = 3.6
Less: 0.55 x 0.5=0.275
2.1 x 0.6=1.26
Total Area = 19.425
Under 30 by 30 cm floor tiles:

19.425 11.11=215.81
Plus : 10 % allowance for cutting and edging =

21.58
Total No. of Tiles = 237.39 ; say

238

Bathroom Floor Tiles


Floor Area:4.6942 m2
Under 30 by 30 cm floor tiles:

4.70 11.11=52.217

58

Plus : 10 % allowance for cutting and edging =

5.22
Total No. of Tiles = 57.437 ; say

Unit BMasters
T&B

Bathroom Wall Tiles


Wall Area: 1.8 x 2.4 x 2 = 8.64
2.55 x 2.6 x 2 =12.75
Less: 2.1 x 0.6=1.26
0.55 x 0.5=0.275
Total Area = 19.855
Under 30 by 30 cm floor tiles:

19.855 11.11=220.59
Plus : 10 % allowance for cutting and edging =

243

22.06
Total No. of Tiles = 242.65 ; say...
Bathroom Floor Tiles
Floor Area: 2.55 x 1.8 = 4.59
Under 30 by 30 cm floor tiles:

4.59 11.11=50.9949
Plus : 10 % allowance for cutting and edging =

5.10
Total No. of Tiles = 56.09 ; say

Unit ACommon
T&B

Bathroom Wall Tiles


Wall Area: 1.52 x 2.4 = 3.648
2.7 x 2.6 = 7.02 -0.27 = 6.75
1.5 x 2.4 = 3.6
2.5 x 2.6 = 6.5 0.25 = 6.25
Less: 0.55 x 0.5=0.275
2.1 x 0.6=1.26
Total Area= 18.713

57

Under 30 by 30 cm floor tiles:

18.713 11.11=207.90
229

Plus : 10 % allowance for cutting and edging =

20.79
Total No. of Tiles =

228.69 ; say

Bathroom Floor Tiles


Floor Area: 2.5 x 1.5 = 3.75
0.2 x 1.5 / 2 = 0.15

48

Under 30 by 30 cm floor tiles:

3.9 11.11=43.329

Plus : 10 % allowance for cutting and edging =

4.33
Total No. of Tiles = 47.659 ; say

Unit BCommon
T&B

Bathroom Wall Tiles


Wall Area: 1.5 x 2.4 x 2 = 7.2
2.55 x 2.6 x 2 = 12.15
Less: 0.55 x 0.5=0.275
2.1 x 0.6=1.26
Total Area= 17.815
Under 30 by 30 cm floor tiles:

17.815 11.11=197.92

Plus : 10 % allowance for cutting and edging =

218

19.79
Total No. of Tiles = 217.71 ; say
Bathroom Floor Tiles
Floor Area: 2.55 x 1.5 = 3.825
Under 30 by 30 cm floor tiles:

3.825 11.11=42.50

Plus : 10 % allowance for cutting and edging =

4.25
Total No. of Tiles = 46.75 ; say

47

Bathroom Wall Tiles


Unit AGround Flr. Wall Area: 1.2 x 2.4 x 2 = 5.76
2.45 x 2. x 2 = 12.0975
T&B
Less: 0.55 x 0.5=0.275
2.1 x 0.6=1.26
Total Area = 16.3225
Under 30 by 30 cm floor tiles:

16.3225 11.11=181.34
Plus : 10 % allowance for cutting and edging =

200

18.13
Total No. of Tiles = 199.47 ; say
Bathroom Floor Tiles
Floor Area: 1.2 x 2.45 = 2.94
Under 30 by 30 cm floor tiles:

2.94 11.11=32.66

36

Plus : 10 % allowance for cutting and edging =

3.27
Total No. of Tiles = 35.93 ; say
Bathroom Wall Tiles
Unit BGround Flr. Wall Area: 1.2 x 2.4 x 2 = 5.76
2.45 x 2.6 x 2 = 12.22
T&B
Less: 0.55 x 0.5=0.275
2.1 x 0.6=1.26
Total Area = 16.445

Under 30 by 30 cm floor tiles:

16.445 11.11=182.70
Plus : 10 % allowance for cutting and edging =

18.27
Total No. of Tiles = 200.97 ; say
Bathroom Floor Tiles
Floor Area: 1.2 x 2.45 = 2.94

201

Under 30 by 30 cm floor tiles:

36

2.94 11.11=32.66
Plus : 10 % allowance for cutting and edging =

3.27
Total No. of Tiles = 35.93 ; say

Maids
T&B

Bathroom Wall Tiles


Wall Area: 1.35 x 2.5 x 4 = 13.5
Less: 0.55 x 0.5=0.275
2.1 x 0.6=1.26
Total Area =11.965

Under 30 by 30 cm floor tiles:

11.965 11.11=132.93
Plus : 10 % allowance for cutting and edging =

147

13.29
Total No. of Tiles = 146.22 ; say
Bathroom Floor Tiles
Floor Area: 1.35 x 1.35 = 1.8225
Under 30 by 30 cm floor tiles:

1.8225 11.11=20.25
Plus : 10 % allowance for cutting and edging =

2.025
Total No. of Tiles = 22.28 ; say

23

Unit AKitchen

Kitchen Tiles
Kitchen Area =

4.9 x 3.65=17.885

0.8395=17.05
Less: Island Counter Top = 4.681 m
Total Kitchen Tile Area =

12.37 m2

Under 60 by 60 cm floor tiles:

38

12.37 2.78=34.39
Plus : 10 % allowance for cutting and edging =

3.44
Total No. of Tiles =

Unit BKitchen

37.83 ; say

Kitchen Tiles
Kitchen Area = 4.65 x 3.65 = 16.9725
Less: Island Counter Top = 3.844 m
Total Kitchen Tile Area =

13.13 m2

Under 60 by 60 cm floor tiles:

13.13 2.78=36.50

41

Plus : 10 % allowance for cutting and edging =

3.65
Total No. of Tiles =

40.15 ; say
TOTAL:

305

1276

600

BILL OF MATERIALS COMPUTATION SHEET


Item to be
Estimated
Kitchen Tiles

Materials And Estimated Quantities


Required

Calculation

Kitchen Area of Unit A=

Cement
(bags)

White Cement
(kg)

Tile Adhesive
(bags)

4.9 x 3.65=17.885

0.8395=17.05
Less: Island Counter Top = 4.681 m
Total Kitchen Tile Area =

12.37 m2

Kitchen Area of Unit B= 4.65 x 3.65 = 16.9725


Less: Island Counter Top = 3.844 m
Total Kitchen Tile Area =

Total Area of Kitchen = 25.5

m2

13.13 m2

3
13.0

Under 60 by 60 cm floor tiles:

25.5 0.086=2.193 ; say


25.5 0.50=12.75 ; say
25.5 0.11=2.805 ; say

Bathroom
Tiles

Bathroom Wall Area

Unit A-Masters T&B= 19.425m2


Unit B-Masters T&B= 19.855m2
Unit A-Common T&B = 18.713m2
Unit B-Common T&B = 17.815m2
Unit A-Ground Flr. T&B= 16.3225m2
Unit B-Ground Flr. T&B= 16.445m2
Maids T&B=11.965 m2
2
Total Bathroom Tile Area = 120.54 m
Under 30 by 30 cm floor tiles:

120.54 0.086=10.37 ; say


120.54 0.50=60.27 ; say
120.54 0.11=13.26 ; say
Bathroom Floor Area

Unit A-Masters T&B=


Unit B-Masters T&B= 4.59 m2
Unit A-Common T&B = 3.9m2
Unit B-Common T&B = 3.825m2
Unit A-Ground Flr. T&B= 2.94m2
Unit B-Ground Flr. T&B= 2.94m2
Maids T&B=1.8225m2
2
Total Bathroom Tile Area = 120.54 m
Under 30 by 30 cm floor tiles:

120.54 0.086=10.37 ; say


120.54 0.50=60.27 ; say
120.54 0.11=13.26 ; say

11
60.5
14

Floor Tiles

First Floor Tiles


First Floor Area =

41.3404 + 40.5320 = 80.87

Less: Kitchen Area = 17.05 + 16.9725 = 34.0225


Net First Floor Area =

48.85 m

Under 60 by 60 cm floor tiles:

24.5

48.85 0.086=4.20 ; say

48.85 0.50=24.425 ; say


48.85 0.11=5.37

; say

Second Floor Tiles


Second Floor Area = 5.9294+6.325=12.25

1
6.5
2

Under 60 by 60 cm floor tiles:

12.25 0.086=1.05 ; say


12.25 0.50=6.125 ; say
12.25 0.11=1.35 ; say

Bedroom
Floor Tiles

Bedroom 1 Floor Area =


27.75 m

14.0 .9+ 13.66=

Bedroom 2 Floor Area = 14.16 + 14.09 = 29.25

m2
Masters Bed Floor Area = 20.91 + 21.70 = 42.61

Maids Room = 4.5 + 4.7 = 9.2

10
54.5

2
Net Bedroom Floor Area = 108.81m

12

Under 60 by 60 cm floor tiles:

108.81 0.086=9.36 ; say


108.81 0.50=54.41 ; say
108.81 0.11=11.97 ; say
TOTAL:

30

159.0

37

BILL OF MATERIALSCOMPUTATION SHEET


Item To Be
Estimated

Floor Tiles

Calculations

Materials And Estimated Quantities


Required
Wood Glue
(gallons)

Polymer
Liquid
(gallons)

Hardener
(quarts)

Calsomine
Powder
(kg)

First Floor Tiles


First Floor Area =

41.3404

+ 40.5320 = 80.87

Less: Kitchen Area = 17.05 + 16.9725 = 34.0225


Net First Floor Area =

48.85 m2

Under 60 by 60 cm floor tiles:

2
2

48.85 0.035=1.70 ; say

48.85 0.030=1.46 ; say


48.85 0.045=2.20 ; say
Second Floor Tiles
Second Floor Area = 5.9294+6.325=12.25

1
1
1

Under 60 by 60 cm floor tiles:

12.25 0.035=0.43 ; say


12.25 0.030=0.37 ; say
12.25 0.045=0.55 ; say

Bedroom
Floor Tiles

Bedroom 1 Floor Area =


27.75 m

14.0 .9+ 13.66=

Bedroom 2 Floor Area = 14.16 + 14.09 = 29.25

m2
Masters Bed Floor Area = 20.91 + 21.70 = 42.61

Maids Room = 4.5 + 4.7 = 9.2


Net Bedroom Floor Area =

18

108.81m2

No. of Wood Glue required:

108.81 0.165=17.95 ; say


Stair Tiles

Stair Tread Area =

0.925 0.30=0.30 m

No. of Steps =19 Steps


Stair Tread Area for 22 steps =
2

22 0.30=6.60 m

Stair Landing Area =

2.11 1.00=2.11 m2

Total Stair Tile Area =

8.71 m

No. of Wood Glue required:

8.71 0.165=1.44 ; say


TOTALS

20

Paint

PROJECT TITLE: TROPICAL SEMI-ATTACHED RESIDENCE


OWNER/S: MR. & MRS DANILO REYES
LOCATION: SOUTHERN YEMEN ST. BETTER LIVING SUBDIVISION, PARANAQUE CITY

BILL OF MATERIALSCOMPUTATION SHEET

Item to be
Estimated

Exterior
Paint

Calculations

Materials And Estimated Quantities


Required
Concrete
Primer Sealer
(gallons)

Acrylic Gloss
Latex Paint
(gallons)

Concrete
Neutralizer
(quarts)

First Floor Exterior Wall


Surface Perimeter =

62.35

Surface Area = 62.35 x 3.3 = 205.755m2


Less: Door: 2(2.1 x 0.9) = 3.78
2(2.3 x 1.8) = 8.28
4(2.1 x 0.8) = 6.72
Window: 1.2 x 1.6 =1.92
1.2 x 1.1=1.32
4(1.2 x 0.8)=3.84
4(1.8 x 0.35)=2.52
2(1.3 x 0.65) =1.69
2(2.1 x 0.6)=2.52
2(0.9 x 1.1)=1.98
6(0.55 x 0.5)=1.65
Net Wall Area =

169.535

Under area coverage of 40 sq. m. per gallon:


For Primer Paint:

169.535
=4.24 ; say
40
For Final Coating:

169.535
=4.24 ; say
40
For Concrete Neutralizer:

169.535
=4.24 ; say
40
2.0
* One quart of neutralizer is mixed with 2- gallons of
water

4.24
=1.70 ; say
2.5
Second Floor Exterior Wall

Surface Perimeter =

69.34 m

67.34 3.0=202.02 m2

Surface Area = =

Less: Door: 2(2.3 x 2.3)=10.58


Window: 2(2.75 x 2.0)=11
6(1.3 x 1.9)=14.82
2(1.1 x 0.9)=1.98
4(0.55 x 0.5)=1.1

162.54

Net Wall Area =

Under area coverage of 40 sq. m. per gallon:

For Primer Paint:

162.54
=4.06 ; say
40
For Final Coating:

162.54
=4.06 ; say
40
For Concrete Neutralizer:

162.54
=4.06 ; say
40
* One quart of neutralizer is mixed with 2- gallons of
water

4.06
=1.63 ; say
2.5

Interior
Paint

Interior Wall on First Floor


Total Surface Perimeter =
Surface Area =
Less: Door:

117.85 m

117.85 2.7=318.195 m2

4 (2.1 x 0.6)=5.04

2(2.1 x 0.9) = 3.78


2(2.3 x 1.8) = 8.28
4(2.1 x 0.8) = 6.72
Window: 1.2 x 1.6 =1.92
1.2 x 1.1=1.32

2.0

4(1.2 x 0.8)=3.84
4(1.8 x 0.35)=2.52
2(1.3 x 0.65) =1.69
2(2.1 x 0.6)=2.52
2(0.9 x 1.1)=1.98
6(0.55 x 0.5)=1.65
Net Wall Area =

276.935 m2

Under area coverage of 40 sq. m. per gallon:


7

For Primer Paint;

276.935
=6.92 ; say
40

For Final Coating;

276.935
=6.92 ; say
40
For Concrete Neutralizer;

276.935
=6.92 ; say
40
3
* One quart of neutralizer is mixed with 2- gallons of
water

6.92
=2.77
2.5

Interior Wall on Second Floor


Total Surface Perimeter =

162.26 m

Surface Area = 162.26 2.7=438.102 m


Less: Door:

6(2.1 x 0.8)=10.08 m2

4 (0.60 2.10)=5.04 m2
2(2.3 x 2.3)=10.58
Window: 2(2.75 x 2.0)=11
6(1.3 x 1.9)=14.82
2(1.1 x 0.9)=1.98

10

4(0.55 x 0.5)=1.1
Net Wall Area =

383.502m

10
Under area coverage of 40 sq. m. per gallon:
For Primer Paint;

383.502
=9.59 ; say
40
For Final Coating;

383.502
=9.59 ; say
40

4.0

For Concrete Neutralizer;

383.502
=9.59 ; say
40
* One quart of neutralizer is mixed with 2- gallons of
water

9.59
=3.836 ; say
2.5

TOTALS

26

26

11

ELECTRICAL

PROJECT TITLE: TROPICAL SEMI-ATTACHED RESIDENCE


OWNER/S: MR. & MRS DANILO REYES
LOCATION: SOUTHERN YEMEN ST. BETTER LIVING SUBDIVISION, PARANAQUE CITY

BILL OF MATERIALSCOMPUTATION SHEET


Item to be
Estimated

Materials Required

Estimated
Quantity

30.00mm2 THHN Copper Wire, 150m

4 boxes

8.0mm2 TW Copper Wire, 150m

2 box

32 mm RSC Pipe

4 boxes

Lighting Outlet

63 pieces

Duplex Convenience Outlet

16 pieces

Refrigerator Outlet

2 piece

Washing Machine Outlet

2 piece

Range Outlet

2 piece

Air Conditioning Unit Outlet

10 pieces

Weather-proof Outlet

4 pieces

Single Pole Switch

4 pieces

Duplex Pole Switch

14 pieces

Triplex Pole Switch

14 pieces

Three-way Switch

4 pieces

Fuse Box

2 piece

Circuit Breaker

30 pieces

Junction Box D.T. 4 x 4

108 pieces

Utility Box D.T. 2 x 4

150 pieces

Solvent Cement
Electrical Tape

50 rolls

PLUMBING

PROJECT TITLE: TROPICAL SEMI-ATTACHED RESIDENCE


OWNER/S: MR. & MRS DANILO REYES
LOCATION: SOUTHERN YEMEN ST. BETTER LIVING SUBDIVISION, PARANAQUE CITY

BILL OF MATERIALS

COMPUTATION SHEET
Item to be
Estimated

Materials Required

Estimated
Quantity

PVC Pipe 4 , 10 ft
Sanitary Line

Length of Pipe:

2.50+1.00+5.00+11.50 +10.50+1.50+1.50+21.00+3.00+2.50+ 2.00=62.00 x 2=124 m314.9


No. of Bars required:

341.96
=31.496
10
; say

32 pieces

Sanitary Tee

18 pieces

Elbow

28 pieces

1/8 in. Bend Elbow

28 pieces

1/8in. Bend Elbow and Wye Combo

4 pieces

Sanitary Wye

30 pieces

Coupling

40 pieces

Clean-out with Plug

20 pieces

Solvent Cement

30 liters

Pipe in. by 14.00 ft


Water Line

Length of Pipe:

1.50+13.00+18.00=32.50 x 2=65 m165.1 ft

No. of Bars required:

106.62
=7.62
14
; say

8 pieces

Pipe in. by 14.00 ft


Length of Pipe

0.25+0.80+ 0.60+ 1.80+4.00+10.50+ 3.00+ 1.00=21.95 m72.00 ft


No. of Bars required:

72.00
=5.14
14
; say

6 pieces

Elbow in.

6 pieces

Elbow in.

12 pieces

Street Ell

8 pieces

PE Adaptor

2 piece

Tapped Tee in.

2 piece

Tapped Tee in.

20 pieces

Reducer Ell

6 pieces

Septic Tank

Reducer Tee

10 pieces

Nipple

28 pieces

Union

4 pieces

Water Meter

2 piece

Gate Valve

6 pieces

Faucet (Kitchen)

2 piece

Faucet (Bathroom)

10 pieces

Hose Bibb

4 pieces

Concrete Hollow Blocks, 100

200 400 mm

200 pieces

Concrete Hollow Blocks, 150

200 400 mm

520 pieces

Steel Reinforcing Bars, Deformed10 mm

28 pieces

Cement

64 bags

Sand

6.4 cu.m.

Gravel

1.80cu.m.

PVC Pipe 6 in. , 10 ft


Catch Basin

Length of Pipe

36.00+14.00=50.00 m164.04 ft
No. of Bars required:

164.04
=16.40
10

Concrete Hollow Blocks, 100

Fixtures and
Accessories

; say

17 pieces

200 400 mm

240 pieces

Steel Reinforcing Bars, Deformed10 mm

6 pieces

Cement

30 bags

Sand

1.80 cu.m.

Gravel

2.40 cu.m

Water Closet

8 pieces

Bathtub

2 pieces

Lavatory

6 pieces

Kitchen Sink

2 piece

Laundry Tray

2 piece

Miscellaneous

Soap Holder

6 pieces

Toilet Paper Holder

6 pieces

Towel Holder

6 pieces

Shower Head

6 pieces

Floor Drain

8 pieces

Teflon Tape

40 rolls

PROJECT TITLE: TROPICAL SEMI-ATTACHED RESIDENCE


OWNER/S: MR. & MRS DANILO REYES
LOCATION: SOUTHERN YEMEN ST. BETTER LIVING SUBDIVISION, PARANAQUE CITY

BILL OF MATERIALS COMPUTATION SHEET


Item to be
Estimated
Excavation for
Rectangular

Computation
Central Footing-1 for Rectangular Column
Excavation vol./footing = 1.2 x 1.2 x 1.2 = 1.728 m3

Estimated
Quantity

Footing

No. of Side Footing = 4 sets


Total Excavation Volume =

4 1.728=6.912 m3

6.90 m3

Central Footing-2 for Rectangular Column


Excavation vol./footing = 1.3 x 1.3 x 1.2 = 2.028m3
No. of Side Footing = 7 sets
3

Total Excavation Volume = 7 2.028=14.196 m

14.20 m3

Central Footing-3 for Rectangular Column


Excavation vol./footing = 1.4 x 1.4 x 1.2 = 2.352 m3
No. of Side Footing = 2 sets
Total Excavation Volume = 2 2.352=4.704 m

4.80 m3

Central Footing-4 for Rectangular Column


Excavation vol./footing = 1.55 x 1.55 x 1.2 = 2.883m3
No. of Side Footing = 2 sets
Total Excavation Volume = 2 2.883=5.766 m

5.80 m3

Cen/Can Footing-5 for Rectangular Column


Excavation vol./footing = 0.6 x 0.6 x 1.2 = 0.432m3
No. of Side Footing = 16 sets
Total Excavation Volume = 16 0.432=6.912m

7.00 m3

Cantilever Footing-6 for Rectangular Column


Excavation vol./footing = 1.05 x 1.05 x 1.2 = 1.323m3
No. of Side Footing = 4 sets
Total Excavation Volume = 4 1.323=5.292 m

5.30 m3

Cantilever Footing-7 for Rectangular Column


Excavation vol./footing = 1.15 x 1.15 x 1.2 = 1.587m3
No. of Side Footing = 2 sets
3

Total Excavation Volume = 4 1.587=3.174 m

3.20 m

Combined Footing-1 for Rectangular Column


Excavation vol./footing = 1.35 x 2.05 x 1.2 = 3.321m3
No. of Side Footing = 1 sets
3

Total Excavation Volume = 1 3.321=3.321 m

Excavation for

Exterior Wall Footing

3.40 m

Wall Footing

Total Length of Exterior Wall Footing =


Total Excavation Volume =

62.35 m

62.35 0.60 0.80=29.928 m3

30.0 m

Interior Wall Footing


Total Length of Interior Wall Footing =
Total Excavation Volume =

27.75 m

27.75 0.60 0.80=13.32 m3

Excavation for
Septic Tank

ExcavationVolume of Septic Tank

Backfill and
Compaction for
Rectangular
Footing

F-1
Side Footing for Rectangular Column
Backfill and Compactionvolume per footing =

3.70 1.30 1.70 x 2=16.36 m3

0.93 0.80 0.90=0.67 m

13.40 m

16.40 m3

No. of Side Footing = 4 sets


Total Backfill and Compaction Volume =

2.70 m3

4 0.67=2.68 m

F-2
Center Footing for Rectangular Column
Backfill and Compaction volume per footing =
3

1.03 1.58 0.90=1.46 m

11.70 m3

No. of Side Footing = 8 sets


Total Backfill and Compaction Volume =
Backfill and
Compaction for
Wall Footing

8 1.46=11.72 m3

Exterior Wall Footing


Total Length of Exterior Wall Footing =
Total Excavation Volume =

62.35 m

62.35 0.45 0.60=16.8345 m3

16.90 m3

Interior Wall Footing


Total Length of Interior Wall Footing =

27.75 m

3
Total Excavation Volume = 27.75 0.50 0.60=8.325 m

8.40 m3

Gravel Fill

Volume of Gravel = 164.25 x 0.1 = 16.425

PROJECT TITLE: TROPICAL SEMI-ATTACHED RESIDENCE


OWNER/S: MR. & MRS DANILO REYES
LOCATION: SOUTHERN YEMEN ST. BETTER LIVING SUBDIVISION, PARANAQUE CITY

17.00 m3

BILL OF MATERIALS
Description of Materials

Quantity

Unit

Unit Cost

Total Cost

1
1
1
1

lot
lot
lot
lot

59
26.60
1
17.00

cu. m
cu. m
lot
cu. m

810
52
97

bags
cu. m.
cu. m.

220.00
825.00
950.00

178,200.00
42,900.00
92,150.00

729
126
1015
160

piece
piece
piece
kilogram

140.00
200.00
356.00
80.00

102,060.00
25,200.00
631,340.00
12,800.00

2497
3978
1226
69.5
11.5
30

piece
piece
bags
cu. m.
cu. m.
kilogram

33.53
40.00
220.00
825.00
950.00
80.00

83,724.41
159,120.00
269,720.00
57,337.50
10,925.00
2,400.00

14,036
5,879

board feet
board feet

45.00
50.00

631,620.00
293,950.00

209

sheet

341.25

71,321.25

1. MOBILIZATION
Mobilization
Layout and Staking
Site Clearing
Temporary Facility/Warehouse/Bunkhouse
2. EXCAVATION
Excavation
Backfill and Compaction
Soil Poisoning
Gravel Fill
3. CONCRETE WORKS
Republic Portland Cement, Lafarge
Vibro Washed Sand
Gravel or Crushed Stone
4. STEEL WORKS
Steel Reinforcing Bars, Deformed
10 mm by 6.00 meters
12 mm by 6.00 meters
16 mm by 6.00 meters
G.I. Tie Wire No. 16
5. MASONRY WORKS
Concrete Hollow Blocks
150

200

400 mm

200

200

400 mm

Republic Portland Cement, Lafarge


Vibro Washed Sand
Gravel or Crushed Stone
G.I. Tie Wire No. 16

6. FORMS AND SCAFFOLDING


Form and Scaffolding Lumber
2

2 12

3 12

Waterproof Plywood
1/4

4 8

1/2

4 8

PROJECT TITLE: TROPICAL SEMI-ATTACHED RESIDENCE


OWNER/S: MR. & MRS DANILO REYES
LOCATION: SOUTHERN YEMEN ST. BETTER LIVING SUBDIVISION, PARANAQUE CITY

SUMMARY COST ESTIMATES FOR MATERIALS, LABOR COST AND OTHER


CONSTRUCTION EXPENSES

A. ESTIMATED COST OF MATERIALS (From the Bill of Materials)


1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.

Mobilization
Excavation
Concrete Works
Steel Works
Masonry Works
Forms and Scaffolding
Plumbing Works
Electrical Works
Tileworks
Painting Works
Finishing
Miscellaneous Materials
Demobilization

B. ESTIMATED COST OF LABOR (Including Supervision Fees)


C. ESTIMATED COST OF EQUIPMENT
ESTIMATED TOTAL DIRECT COST

The above items comprise the estimated expenses for materials and labor applied directly in the
construction of the building. If the work would be undertaken by a contractor, the indirect costs shown below
should also be taken into account in projecting the total funding required for the completion of the project.

D. CONTRACTORS PROFIT (Including Overhead)


E. CONTRACTORS TAX
ESTIMATED TOTAL INDIRECT COST
TOTAL ESTIMATED PROJECT COST

Prepared By:

Approved:

MAGO, MONIQUE O.
BSCE-3C

ENGR. MARJUN B. MACASILHIG


INSTRUCTOR