You are on page 1of 10

BILL OF QUANTITIES

SUBSTRUCTURE

ITEM
REF.

ITEM DESCRIPTION

QTY

UNIT

SUBSTRUCTURE (ALL PROVISIONAL)

Piling
The following in 156 No. bored concrete piles all in
accordance with the specification to depths dictated
by the soil investigation report and the actual site
conditions
The contractor is required to price for designing the
piles based on the specification, drawings,
geotechnical investigation report and standards etc.

ii)

The contractor is required to price for installing


piles to the necessary depths to achieve required
working load capacity subject to appropriate tests
and the approval of the engineer, no additional
remuneration will be provided for piles installed to
greater depths than anticipated by the contractor at
tender stage, or for withdrawing and reboring piles.

iii)

Piling section is not remeasurable

iv)

Boring through rock under water or the like is


deemed included in the rates

Establish, mobilise all piling requirements and


provide access

Bored concrete piles; 600 mm diameter including


all necessary excavation, disposal, concrete,
reinforcement, linings and all other associated
works, overall 16,000 mm high

Ditto, 800 mm diameter; overall 20,000 mm high

Ditto, 1000 mm diameter; overall 24,000 mm high

3/1

BILL No. 3, 6 PERSON ROM BLOCK

i)

PAGE NO.

BILL NO.

Item

No
No

No

UNIT
RATE

TOTAL PRICE
RIALS OMANI

BILL OF QUANTITIES

SUBSTRUCTURE

ITEM
REF.

ITEM DESCRIPTION

Allow for testing piles

Cut off and scabble top of pile and prepare to


receive pile cap/ ring beams including starter bar
reinforcement

Demobilise, clean away piling requirement and


make good

QTY

UNIT

Item

No

Item

Note: Excavation/Earth work and concrete works


for basement envelope together with associated
ancillary works up to the ground floor level are
measured under substructure. All other works
within the basement envelop are measured under
appropriate trades in the Basement Bill.

Excavation
A

Excavate to reduce levels

m3

Extra Over excavate to reduce level for excavation


in rock

m3

Disposal
C

Remove surplus excavated material from site

m3

Filling
D

3/2

To Collection
A

PAGE NO.

BILL NO.

Selected excavated material in making up level


below beds

m3

Selected excavated material in backfilling around


foundations

m3

UNIT
RATE

TOTAL PRICE
RIALS OMANI

BILL OF QUANTITIES

PAGE NO.

BILL NO.

SUBSTRUCTURE

3/3

ITEM
REF.

ITEM DESCRIPTION

Imported material in making up levels below beds

m3

Imported material in backfilling around foundations

m3

QTY

UNIT

To Collection

Concrete work
Plain poured sulphate resistant cement concrete
grade C, 14 N/mm2
A

Blinding 75 mm thick

m3

Blinding 100 mm thick

m3

Ditto, to slope

m3

Reinforced poured sulphate resistant cement


concrete grade A, 45 N/mm2
D

Beds, 300 mm thick

m3

Ditto, shrinkage strip

m3

Ditto, 500 mm

m3

Ditto, shrinkage strip

m3

Ditto, 1100 mm

m3

Ditto, 1200 mm

m3

Ditto, 1250 mm

m3

Ditto, shrinkage strip

m3

UNIT
RATE

TOTAL PRICE
RIALS OMANI

BILL OF QUANTITIES

SUBSTRUCTURE

ITEM
REF.

ITEM DESCRIPTION

QTY

UNIT

Ditto, 1400 mm

m3

Column bases

m3

To Collection

Suspended slabs, 250 mm thick

m3

Ditto, 300 mm

m3

Ditto, Shrinkage Strip

m3

Ditto, 350 mm

m3

Ditto, 450 mm

m3

Ditto, 500 mm

m3

Ditto, 600 mm

m3

Upstands and parapets

m3

Walls, 400 mm thick

m3

Ditto, 800 mm thick

m3

Reinforcement, high yield steel deformed bars to


B.S. 4449, diameter
8 - 32 mm

kg

Shuttering, as struck finish to


P

Sides of column bases

3/4

PAGE NO.

BILL NO.

m2

UNIT
RATE

TOTAL PRICE
RIALS OMANI

BILL OF QUANTITIES

SUBSTRUCTURE

ITEM
REF.

ITEM DESCRIPTION

QTY

UNIT

Ditto, beds

m2

Soffits of suspended slabs

m2

Sides of upstands and parapets

m2

Ditto, walls

m2
To Collection

Shuttering, as fairfaced finish to


A

Soffits of suspended slabs

m2

Sides of walls

m2

Sundries
C

Anti-termite treatment (measured plinth area)

m2

Power floated finish to concrete slabs to receive


floor coating systems (measured separately)

m2

Cement and sand (1:3) protection screed, 50 mm


thick damp proof membrane

m2

Polythene damp proof membrane, 1200 gauge laid


horizontally to beds

m2

Ditto, to slope

m2

APP modified waterproofing membrane to


horizontal concrete surfaces

m2

Ditto, to vertical

m2

Protection boards to waterproof membrane, to


horizontal

m2

Ditto, to vertical

m2

3/5

PAGE NO.

BILL NO.

UNIT
RATE

TOTAL PRICE
RIALS OMANI

BILL OF QUANTITIES

SUBSTRUCTURE

ITEM
REF.

ITEM DESCRIPTION

QTY

UNIT

Prepare and apply two coats of bituminous paint

m2

Vapour barrier laid horizontally

m2

To Collection

Bitumen angle fillet, size 50 x 50 mm including 300


mm membrane reinforcing strip to internal angle

Cement and sand mortar angle fillet, size 50 x 50


mm including 300 mm membrane reinforcing strip
to internal angle

Bitumen reinforcing strip to external angle, 400 mm


wide

12 mm x 25 mm deep mastic sealant pointing to top


of protection system to walls

Expansion joint to floors, 250 mm high comprising


joint filler board, proprietary sealant joint to both
sides and the like including forming surfaces, all as
Drawing No.

3/6

PAGE NO.

BILL NO.

Ditto, 300 mm high

Ditto, 500 mm high

Ditto, 800 mm high

Ditto, 1100 mm high

Ditto, 1200 mm high

Ditto, 1250 mm high

Ditto, 1500 mm high

UNIT
RATE

TOTAL PRICE
RIALS OMANI

BILL OF QUANTITIES

SUBSTRUCTURE

ITEM
REF.

ITEM DESCRIPTION

Expansion joint to walls, 400 mm thick comprising


20 mm diameter dowels with cap, joint filler board,
proprietary sealant joint to both sides, PVC water
stop and the like including forming surfaces, all as
Drawing No.

Shrinkage strip to floors comprising 2500 mm long


x 16 mm diameter dowels, 240 mm long water
stops to both edges, and the like including forming
surfaces (concrete measured separately), all as
Drawing No.

To Collection

SUBSTRUCTURE
COLLECTION
3/1

3/7

QTY

UNIT

To Collection

PAGE NO.

BILL NO.

UNIT
RATE

TOTAL PRICE
RIALS OMANI

BILL OF QUANTITIES

SUBSTRUCTURE

ITEM
REF.

ITEM DESCRIPTION

3/2
3/3
3/4
3/5
3/6

Total of Substructure to Summary of


Bill No. 3

PAGE NO.

BILL NO.

3/8

QTY

UNIT

UNIT
RATE

TOTAL PRICE
RIALS OMANI

Project:

Client:
Contractor:

PROPOSED TENTATIVE CONSTRUCTION SCHEDULE

Work Breakdown Structure

A) Mobilization

Appr.
Duration
(Weeks)
2

B) Sub-Structure Works
1 Excavation for Foundation

Foundation Concrete & Blockwork upto Plinth


Beam

Foundation Waterproofing, Anti-Termite


Treatment & Backfilling

4 Slab-on-Grade Works

C) Super-Structure Works
1 Ground Floor Walls & RC Stairs

2 First Floor Slab

3 First Floor Walls

4 Roof Slab with Waterproofing & Insulation

5 Parapets

D) Finishes, Doors, Windows & MEP Works


1 Finishes & Installations for Ground Floor

2 Finishes & Installations for First Floor

E) External Works
1 Interlock Paving Works

2 Septic Tank

F) Project Closure
1 Commissioning of Works & Handing Over
TOTAL DURATION

2
6 months

Month 1

Month 2

Month 3

Month 4

Month 5

Month 6

Month 6