Professional Documents
Culture Documents
PART 1 GENERAL
BUILDING ENGINEERING
SERVICES
PART 1
DESIGN GUIDELINES
M&E Design,
Estates Office,
Coventry,
CV4 7AL
Issue No:
Revision:
Date:
Prepared by:
Checked by:
01
0
December 2007
A. Lawry
I.Williamson
Design Guidelines
PART 1 GENERAL
Issue/Revision Record
ISSUE
NO.
REVISION
DATE
PAGE(S)
AFFECTED
INSERTED
BY
This procedure will be updated when necessary by the issue of revised pages.
Each revision will be indicated by a black line on the right hand side of the
affected paragraph(s). As model on right.
The letter adjacent to the black line will indicate the revision letter registered.
On receipt of revised pages insert the new pages, remove and destroy redundant
pages and endorse the above record.
Design Guidelines
PART 1 GENERAL
Definitions
Client
Project Officer
University of Warwick
Member of Estates staff nominated by University of Warwick
to oversee the project
Design Guidelines
PART 1 GENERAL
Contents
1.
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
Introduction
Objectives
Exclusion of Warranty
Scope
Use and Limitation
Consultants design responsibility
Implementation
Updates
Documents
Reference Documents
Design documentation
2.
2.1
2.2
2.3
2.4
2.5
Environmental Criteria
Sustainability
BREEAM Assessment
Building Regulations Part L2A
Design Overview
Utilities efficiency
3.
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
4.
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
5.
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
Design Guidelines
PART 1 GENERAL
6.
6.1
6.2
7.
Lighting Protection
8.
Lift Systems
9.
External Services
10.
11.
11.1
11.2
11.3
11.4
Security
General
Exterior
Interior
Closed Circuit Television Cameras
12.
12.1
12.2
13.
13.1
13.2
13.3
13.4
13.5
14.
Card Access
15.
15.1
15.2
15.3
Plant Rooms
Location
Drawing/Information
Service Risers
16.
16.1
16.2
17.
Future Expansion
18.
18.1
18.2
Contractual Issues
Electrical
Building Management System
19.
Maintenance
20.
20.1
20.2
Design Guidelines
PART 1 GENERAL
Appendices
A.
B.
C.
D.
E.
F.
Reference Documents
Design Guidelines
PART 1 GENERAL
1. Introduction
1.1_Objectives
The purpose of these guidelines is to:-
1.2_Exclusion of Warranty
The University of Warwick (U of W) does not give any warranty, representation or
undertaking regarding U of W preliminaries, standard drawings and design guidelines.
1.3_Scope
These guidelines are:-
Design Guidelines
PART 1 GENERAL
1.5.2
Any proposed design work that falls outside the design guidelines must be approved by
the Universitys Project Officer.
The guidelines do not constitute a complete design manual and it is assumed that
professional knowledge and professional good practice will be applied by designers at
all times. They are intended as minimum standards/guidelines.
1.6_Implementation
The guidelines are not mandatory except to the extent compliance with Statutory
Regulations or recognised standards are required. The guidelines are based on
recommended good practice & sensible judgement being adopted when interpreting the
requirements. Where appropriate, account should be taken of whole life costs.
To ensure opportunity is identified to secure lowest life cycle cost, all submissions
should fully examine possible departures from the guidelines, with a range of optional
savings being highlighted.
Value Engineering & Management principles should be applied at the commencement
of a project to all elements of design to ensure optimum value for money.
Engineering systems design should cater as far as economically reasonable for the
flexibility of use of the internal areas of the buildings and especially those intended for
academic use.
1.7_Updates
From time to time amendments and additions to the guidelines will be necessary. These
will follow the procedure laid down at the beginning of this document. The complete
document will be reviewed and revised annually to take account of any minor revisions,
changes in legislation, regulation and standards.
1.8_Documents
Mechanical & Electrical engineering systems design should be developed in conjunction
with these design guidelines and the associated guidelines and specifications listed
below:Part 1: Design Guidelines
Part 2A: Standard Technical Specification Electrical Engineering service installation
Part 2B: Standard specification for Mechanical Services installations.
Part 3: Lift Installations
Part 4: District Heating
Part 5: Card Access Systems
Part 6: Automatic Doors
Part 7: Car Park Barriers
Part 8: External Services
Part 9: Fire & Security
Part 10: Control Strategy
Part 11: Project Manual/Handbook
Part 12: Fibre Network- External Works
Note: A number of the documents detailed above are under development.
8
Design Guidelines
PART 1 GENERAL
1.9_Reference Documents
1.9.1
All designs and installations should be carried out in accordance with the
recommendations of the current and appropriate Legislation, Regulations, Standards
and Codes of Practice including any specific requirements and guidelines appertaining
to the project.
1.9.2
A list of related documents and sources is detailed in Appendix E. This is an indicative
non-exhaustive list and intended as an initial source of reference only.
1.10_Design Documentation
The following standards should be utilised:
1.10.1 Drawings
All drawings should be produced in the latest version of AutoCAD and follow the
conventions laid down in the Universitys AutoCAD Procedures and Conventions
document.
1.10.2 Correspondence
All correspondence including specifications, letters, etc. should be produced in Microsoft
Word. Where possible, a PDF copy of any correspondence should be supplied.
1.10.3 Design
The University preferred design software is HEVACOMP and where possible
documents should be standardised to the Universitys format (e.g. Distribution board
schedules). Also where relevant, thermal analysis and modelling of the building should
be undertaken. Any additional costs must be identified and approved before any work
takes place.
Design Guidelines
PART 1 GENERAL
2. Environmental Criteria
2.1_Sustainability
The University is committed to developing a low carbon campus and believes that the
building engineering services will have a substantial impact on the sustainable
development of the campus. Therefore all design solutions should endeavour to
minimise the environmental impacts, challenge traditional methods/practices to offer
innovative and sustainable options.
In summary the key criteria to be adopted fell under the following generic headings:
Capital Cost
Build ability
Carbon Impact
Thermal Performance
Life Cycle Cost
All designs undertaken must reduce overall consumption and maximise energy
efficiency in compliance with the latest legislation including Energy Performance of
Building Directive and Part L of the Building Regulation.
Consideration of energy conservation and sustainable measures is a pre-requisite and
any opportunities should be drawn to the Universitys attention at the earliest
opportunity.
Sustainable Technologies/Systems
The incorporation of sustainable technologies and systems should be investigated as
part of all project designs. The list detailed in Appendix D is not exhaustive but intended
as a starting point. Each item should be reviewed as part of the initial feasibility study
and any decisions/conclusions recorded in Sustainability Checklist detailed (See
Appendix D).
Attention is also drawn to the Carbon Trust Energy Technology Product List which
details energy efficient products under 14 categories.
2.2_BREEAM Assessment
Designers must consider the above at the earliest opportunity, whereby it is the Estates
Offices aspiration that all NEW buildings over 1000m2 achieve a BREEAM (Building
Research Establishment Environmental Assessment Model) assessment rating of
EXCELLENT and all refurbishment projects achieve a VERY GOOD rating. The
University will conduct an outline, initial assessment with the aid of the design team.
The BREEAM Assessment should be implemented at the earliest opportunity in the
design process. Assessments must be carried out by a licensed BREEAM assessor. A
pre-assessment should be conducted by the design team at the commencement of the
project to ascertain the best cost effective design.
BREEAM makes an assessment of the buildings performance across a number of
different areas including:10
Design Guidelines
PART 1 GENERAL
Management
Energy use
Health & Well-being
Pollution
Transport
Land Use
Ecology
Materials
Water
For buildings below 1000m2 an In-house Pre-Assessment will be conducted with a view
of again achieving an EXCELLENT rating.
2.3_Building Regulations Part L
The regulations require the achievement of a target for the overall carbon emissions
produced by the services within the building. They also impose a minimum building
fabric performance, minimum plant efficiencies and avoidance of overheating, quality &
performance of the constructed building.
Any design solutions must aim to better the requirements and targets laid down in Part L
by a minimum of 20%.
Therefore in order to achieve carbon emission targets a holistic approach regarding
building fabric and engineering systems must be adopted. Areas to be considered
should include those detailed in the following sections:2.3.1_Whole Life Cost
Financial assessments of any project should consider the buildings Whole Life Costs
including design, construction, running and de-commissioning. The Whole Life costing
should be based on a pre-determined and agreed building life expectancy.
2.3.2_Integrated Passive Design (IPD)
Integrated passive design features should be evaluated to maximise the reduction in
environmental impact and running costs of the building including its services over the
projects life cycle. Options should be reported (See Appendix D) to provide an audit trail
for future use.
Main elements of IPD to be considered include:
Insulation
Building Orientation
Glazing and Shading measures
Thermal building mass
Building Air tightness/infiltration rates.
Natural Ventilation
Zoning
Plant efficiency & controls
Renewable technologies
Daylight analysis
11
Design Guidelines
PART 1 GENERAL
Design Guidelines
PART 1 GENERAL
position higher up to increase the access to daylight. Situating any potentially high heat
output operations (e.g. IT suites) in northerly spaces will reduce the internal heat gains
in areas more prone to overheating. Consider occupant requirements e.g. access to
views out of the building, level and type of sound experienced at the workstation, levels
of recycling to be employed.
Consider the use of direct extract of heat by duct work systems from equipment cabinets
in server and communications equipment rooms.
2.5 Utilities efficiency
2.5.1 Energy
Any enhancements that could reduce the operational energy use of the building should
be considered. The proposals should identify and cost out those enhancements that
could provide a simple payback on investment of 5 years or less.
Examples of possible measures that warrant investigation include:
The designer should demonstrate that the building during its operation will emit between
20 and 30% less carbon than an equivalent building constructed to meet current building
regulations. Savings are to be achieved through efficient design and controls and the
use of passive lighting, ventilation and cooling strategies.
Installation of the most appropriate renewable energy sources to meet at least 5% of the
total predicted energy demand of the site should be evaluated with non-installation
justified.
2.5.2 Water
All new projects and refurbishments should be designed to minimise potable water
consumption. Self closing taps should be specified. The feasibility of grey water
collection systems where the waste water from wash hand basins is collected from
80% of fittings and recycled to meet (in part) flushing demand within the buildings
should be evaluated.
The feasibility of installing rainwater collection and storage to collect at least 50% of the
total predicted rainfall (for the period of collection) should be evaluated. The stored
water being used on landscaped areas and/or for toilet flushing purposes.
Water consumption should at least meet the middle credit requirement stated in the
BREEAM for the relevant building.
Water meters should be installed at the intake position in an accessible location and be
complete with remote monitoring facility.
13
Design Guidelines
PART 1 GENERAL
Showers (including aerated shower heads) with a flow rate no greater than 15 litres per
minute at 1.5 bar pressure should be installed.
All WCs should consist of dual flush cisterns with a four litre flushing capacity and
reduced two litre flushing capacity.
Automatic controls should be fitted to all flushing urinals to ensure a flush after each
use. These should have a minimal flushing when occupation has not been detected.
The use of waterless urinals should be investigated as an alternative.
WINTER (C)
Academic Offices
Staff Offices
Computer Rooms
I.T Teaching Rooms
Lecture Theatres
Seminar Rooms
Common Rooms
21 2
21 2
21 2
21 2
21 2
21 2
21 2
SUMMER
DESIGN (C)
Uncontrolled
Uncontrolled
28 max
28 max
28 max
28 max
Uncontrolled
CONTROLLED
(C)
n/a
n/a
24
24
24
24
n/a
14
Design Guidelines
PART 1 GENERAL
Library Areas
Communication/Data
Rooms
Toilets/shower/lockers
Corridors / Circulation
Spaces
Breakout Areas
Meeting Rooms
Presentation Suites
Plant rooms
Corridors with seating
Entrance/Lobby Areas
Workshop
Board Rooms
Gallery
Store Rooms
Store
Lift Motor Rooms
Laboratory
21 2
21 2
Uncontrolled
24 max
n/a
24
18 2
18 2
Uncontrolled
Uncontrolled
n/a
n/a
212
212
212
>=10
21 2
19 2
21 2
21 2
21 2
18 2
18
>=10
21 2
Uncontrolled
Uncontrolled
28 max
Uncontrolled
Uncontrolled
Uncontrolled
Uncontrolled
To be confirmed
Uncontrolled
Uncontrolled
Uncontrolled
35 max
24 2
n/a
n/a
24
n/a
n/a
n/a
n/a
n/a
35
24
3.3_Relative Humidity
Unless otherwise stated, i.e. scientific process applications, no provision for control of
humidity levels should be included. Subject to ambient conditions, relative humidity
within occupied spaces will range between 70% maximum.
3.4_Internal Heat Gains
Internal heat gains for thermal load calculations and plant sizing in areas where
mechanical air cooling may be required are given in the following table.
Table 3.2: Internal Heat Gains
AREA/ITEM
People (Sensible)
People (Latent)
Lighting
General Office Area
HEAT GAIN
80W/person
40W/person
10W/ m2
15W/ m2
4,000W
2200W
2,000 5,000W/m2
COMMENTS
Refer to CIBSE Guidance
Refer to CIBSE Guidance
25W/m2 Installed
provision
U of W measured
U of W measured
power
HLP assumed
U of W measured
High Powered Computing
facilities.
500W/ m2
15
Design Guidelines
PART 1 GENERAL
10W/400W
Paper Shredder
0W/350W
Large Centrifuge
Small Centrifuge
900W
400W
Standby/Operational
(U of W measured)
Standby/Operational
(U of W measured)
Standby/Operational
(U of W measured)
Areas not listed above are assumed to have no equipment heat gains.
3.5_Occupational density
The following details the suggested occupancy levels purely as a means to commence
design.
Table 3.3: Occupational density
AREA
Offices
Breakout Areas
Seminar Rooms
Meeting Rooms
Entrance/Reception
Research Area
Board Rooms
OCCUPATIONAL DENSITY
1 person per 10 m2
University to advise
University to advise
1 person per 2 m2
University to advise
1 person per 10 m2
University to advise
16
Design Guidelines
PART 1 GENERAL
The ratings are to taken at a distance of 1 metre when all devices are active.
Noise levels quoted will result in occupied furnished areas reflected after fit-out. Suitable
adjustments should be made to take into account lack of furnishings etc. Anti-vibration
mountings shall be installed as necessary to comply with the requirements of Table 3.4.
Noise breakout for ventilation systems components should be limited prior to silencing.
3.7_Air Permeability
Air permeability tests should be carried out on all new buildings in accordance with the
guidance provided by CIBSE TM 23 and current regulations. Air permeability of the
building should achieve 5m3/hr/m2 at 50Pa but must not exceed 10m3/hr/m2 at 50Pa as
laid down in the guidance.
3.8 Electro Magnetic Compatibility
All equipment and systems installed must provide electro magnetic compatibility within
the systems and with any systems installed in the same area. Also all equipment should
meet the requirements of the appropriate electromagnetic compatibility standard.
17
Design Guidelines
PART 1 GENERAL
4.
4.1 Ventilation
4.1.1 Natural Ventilation
It is the Universitys policy to achieve internal comfort conditions with the minimum use
of consumed energy. Therefore, wherever possible ventilation by natural means should
be adopted. However consideration must be given to external noise levels.
All areas of every building type must be adequately ventilated preferably by natural
means or otherwise mechanical methods if necessary. Where naturally ventilated,
internal space temperatures should not exceed 280C for more than 100 hours per year.
The CIBSE design summer year should be used for modelling purposes and a report
produced to predict and highlight the periods when the internal temperature is liable to
be above 250C. The report should also detail if the prescribed internal conditions cannot
be achieved utilising natural ventilation alone.
4.1.2 Ventilation Standards
Where ventilation is to be provided via a combination of natural and mechanical means.
The initial design criteria for each space will be as follows:Table 4.1: Ventilation Standards
LOCATION
Offices
Breakout areas
Presentation Suite
Seminar Rooms
Meeting Rooms
Board Room
Visualisation/Usability Lab
Entrance/Reception/Lounge
Server room
Demonstration/research areas
Sound booth
Gallery
Toilet/showers/lockers
Circulation space
Lecture Theatre
SUPPLY
Natural
Natural
Min 10l/s/person
Natural
Natural
Natural
Min 10/s/person
Natural
Transfer only
Natural
Min 10l/s/person (2 people)
Natural
8 ach transferred
Natural
TBC
EXTRACT
Natural
Natural
90% supply
Natural
Natural
Natural
90% supply
Natural
Transfer only
Natural
90%
Natural
6 Litres/Sec per WC
Natural
TBC
The minimum fresh air rate should not be less that 10 litres person per second.
Where it is impractical to use natural ventilation alone use of mixed mode systems
should be developed. These will include heat recovery systems with all air handling
units (both supply and extract fans) being provided with variable speed drives to aid
commissioning and allow for minimum load/setback conditions to be achieved.
18
Design Guidelines
PART 1 GENERAL
19
Design Guidelines
PART 1 GENERAL
Consideration should be given to the following design criteria with regard to ductwork
installations:
Main Campus
90C
50C
Where heating systems are connected to the DH network they should be designed on
temperature differentials of 40C (delta T). Consideration should be given to the sizing
and impact thereof of emitters. Refer to Part 4 District Heating Guidelines for more
information.
20
Design Guidelines
PART 1 GENERAL
Maximum pipe work pressure drop shall be limited to 200-300 Pascals per metre
(300 Pa/m).
Boiler plant shall generate low-pressure hot water for distribution at a maximum
flow temperature of 70C and return temperature of 55C during wintertime
months. High limit cut-out to be approx 10C above the maximum temperature.
System pipe work heat losses shall be taken into account when pipe sizing.
All items of equipment, branches and mains shall have independent isolating
valves and regulating valves positioned as close as practical to their origin.
All boiler plant shall comply with Part L with primary heating sources being
selected to provide maximum energy efficiency with low NOx with Condensing
boilers being the preferred option where practical.
A minimum of two heating boilers should be provided each capable of 66% load
(excluding domestic, standalone installations). The boiler should be of a sectional
design manufactured from cast iron where appropriate.
All secondary space heating circuits will be arranged for weather compensated
operation, with flow temperatures being adjusted to suit the prevailing external
conditions.
Secondary pumped circuits should utilise inverter driven duty & stand by
pumping arrangements (VSD) complete with automatic changeover.
All items of mechanical plant will be provided with a local lockable isolator for
maintenance purposes.
21
Design Guidelines
PART 1 GENERAL
b)
c)
Bespoke Radan water heating units for direct connection to district heating
network complete with secondary return to reduce time lag on hot water delivery.
Design Guidelines
PART 1 GENERAL
4.
5.
4.7.2
No above ground drainage shall pass through lift shafts; lift motor rooms, electrical
switch rooms or computer server rooms.
4.7.3
All laboratory waste systems must be designed to withstand attack from chemicals and
acid e.g. polypropylene.
4.8 Cooling
All design options should be investigated in an attempt to negate the use of air cooling.
Methods of achieving internal temperature control should be prioritised as follows:
1.
2.
3.
4.
5.
6.
Natural ventilation
Mechanical ventilation with 100% fresh air intake and extract with recirculation
facilities incorporating full heat recovery. All motors to be inverter controlled.
As a last resort and only with Project Officers prior approval the use of
mechanical cooling.
Where mechanical cooling is utilised, all associated chillers above 100kW must
incorporate a soft start facility and integral power factor correction.
Night cooling of the building fabric.
Local interlocks with the heating systems/plant.
23
Design Guidelines
PART 1 GENERAL
TNS
30kA
50Hz
400/230 +10% - 6%
Connections to the Universitys wholly owned and operated 11kV network should where
possible be via oil filled externally sited transformers.
5.1.1 Electrical Loads
Estimated electrical loads should be based on the following allowances.
Table 5.2: Estimated Electrical Loads
Small Power Offices
Computer frame/patch room
Lighting
Offices/General
Communications & Safety
Lifts
Mechanical
Fans and pumps
Power Factor
25W/ m2
40W/ m2
10W/ m2
2.5W/ m2
5W/ m2
5kw per lift
80kW total cooling (tbc)
6W/ m2
Corrected to 0.97
24
Design Guidelines
PART 1 GENERAL
Every distribution board and switch panel should be provided with an engraved trafolyte
label easily visible affixed to the front of the cubicle and showing distribution board
designation, the measured valves of any prospective short circuit current and earth loop
impedance.
Each outgoing sub main/supply cable from cubicle switch panel should be fitted with an
engraved trafolyte label to indicate cable details, size type and purpose affixed by nylon
cable ties to the outside of the cable. This label should be attached within 1m of the
cables termination point.
Sub main distribution boards must have a minimum of 25% spare capacity and should
be located in secure purpose made cupboards or services duct/risers and not located in
cleaners cupboards or general areas including offices, standard rooms etc.
Both task and Emergency Lighting is to be installed in all locations where electrical main
switchboard distribution panels are located.
Installation of surge suppression should be considered for all distribution boards.
5.2
Cables
5.2.1 Sub-Mains
Sub-Main cabling shall be via multi-core CU/XLPE/SWA/LSF, installed on cable tray or
basket. The cable runs shall be in accessible ceilings on circulation routes. Where this
is not possible there shall be access hatches provided to minimise disruptions during
maintenance and rewiring.
5.2.2 Final Circuit
Final circuits shall be wired using LSF cables where possible contained in metal
trunking and conduits with bevelled edges, in voids and above the ceiling. Where Dado
trunking is to be utilised, this should have a minimum of two compartments, with the
ability to separate power from data by the required distance with the use of internal
partitioning.
5.3 Sub Metering
Sub metering shall be provided for monitoring of all fuels in accordance with the current
Building Regulations for England and Wales Part L, 2006.
All sub secondary meters must incorporate a pulsed output facility, and should be
installed on large energy using equipment/installations including:
Lighting and small power loads
Computer Rooms
Server Rooms
Comms Room
Cooling & Boiler Plant
Humidification Plant
Motor Control centres and sub distribution panels
Major equipment or energy consuming items e.g. catering facilities
Tenancy areas
25
Design Guidelines
PART 1 GENERAL
26
Design Guidelines
PART 1 GENERAL
5.6.2 Maintenance
The following criteria (re: average maintained illuminance) should be used for lighting
calculations.
Table 5.4: Lighting Maintenance Factors
Reflectances
Environment
Ceiling
Floor
Solid/Partitioned
Windowed Walls/Partitions
Normal
0.7
0.2
0.5
0.0
27
Design Guidelines
PART 1 GENERAL
24 months
24 months
16,000 hours
Unless otherwise agreed by the University, luminaries having high frequency control
gear complete with the latest lamp technologies shall be used throughout. Ballasts
should be dimmable where this functionality is required. Special requirements for colour
rendering should be assessed as required. Use of daylight control and automatic
presence detection should be utilised wherever practical and possible. Otherwise
installations should be controlled in appropriate banks. Luminaries installed in
plantrooms should be to IP65 rating. All recessed luminaries shall be provided with plugin ceiling roses positioned directly above each luminance position to keep flexible cable
lengths to a minimum of one to two metres.
5.6.3 External Lighting
External lighting will be designed to CIBSE Exterior Lighting Guide and should
incorporate an external photocell and quartz time switch control, to enable them to be
switched on and off at pre-determined times, if required.
Amenity/Perimeter Lighting
10 - 20 LUX average
Walkways
10 - 20 LUX average
Entrances
Design Guidelines
PART 1 GENERAL
of providing for the connected load (plus an allowance of 25% for future growth) for a
period of not less than three hours.
The central battery system should use low maintenance sealed type cells. Both slave
luminaries and designated general lighting luminaries should be fitted with A.C. /D.C.
inverters. Facilities shall be provided for mains monitoring of designated lighting circuits
at each sub main distribution board position. Circuits shall include corridors, circulation
areas, stairwells and toilet facilities. Mains failure of any of the designated circuits shall
switch on the emergency power source to the luminaries affected.
An addressable relay shall be connected to analogue/addressable fire alarm systems
which should activate the emergency lighting system in the event of fire alarm
activation.
Emergency lighting from the central system or standalone self contained luminaries
complete with self test facility with LED indication for ease of maintenance in the
absence of a central system, should be installed within all plant rooms and above
electrical switch panels.
Local test switch facilities should be provided with the exact location being confirmed
with the University Fire & Safety Officer. Testing with a key switch will cause the normal
luminaries to extinguish and emergency lights to operate.
5.7 Damage
All accessories should be appropriately selected and positioned to avoid damage and
must be fit for purpose (e.g. external use and plant room use.)
5.8 Labels
Labels shall be provided on the front cover of all main and sub-main distribution boards.
(See Section 5.1.2 for details).
Each individual point/outlet on all final circuits shall be provided with a permanent
printed circuit reference label affixed to the front face of the accessory.
29
Design Guidelines
PART 1 GENERAL
6.
All fire alarm systems must be analogue addressable manufactured and installed in
accordance with BS 5839 2002, Local Authority Building Control Fire Officer and
University Insurers and Fire and Safety Officers recommendations/approval.
6.1 Fire Systems Categories
It should be assumed for initial design purposes that all fire systems are to be designed
to category L2 as described in the current British Standard. The finalised design
category will be subject to a fire risk assessment carried out by the Universitys Fire and
Safety Officer plus the relevant external approvals.
Fire alarm cabling shall use either red sheathed FP200 or FireTuff enhanced cabling.
This shall be independent cable basket along the major cable runs with spur off points
clipped directly installed on to the building to serve remote devices.
Evacuation alert shall be provided by a combination of sounders and flashing Xenon
beacons in laboratories, plant spaces, roof voids, W.Cs and circulation spaces inc.
corridors.
An As fitted drawing detailing zone / loop cables routes zoning, location etc shall be
provided. Also a zonal plan (A2 / A3 size) shall be located adjacent to the fire alarm
control panel with the relevant completion certification (as detailed in the B.S) being
provided.
6.2 Operation
Every fire alarm panel must have the facility to communicate with and be linked to the
existing site wide BMS network.
The following ancillary functions will operate in the event of fire alarm initiation.
All plant will automatically shut down
All lift cars will automatically return to ground level
All magnetically controlled doors will automatically unlock
7.
Lightning Protection
The inclusion of lightning protection shall be evaluated for all new buildings. Lighting
Protection Systems will be designed in accordance with BS 6651, 1990. The maximum
impedance of the earth termination network will be 10 ohms.
Ridge, roof and wall tapes should be installed as inconspicuously as possible using
PVC covered conductors to match and blend into the structure. At the base of each
down conductor, copper tape will connect to earth rods via bolted clamps and bimetallic
connectors where necessary.
30
Design Guidelines
PART 1 GENERAL
The lightning protection system will be bonded at a single point to the main building
earth. Surge diverters should be installed within the main switch panel to divert the
effects of lightning strikes, mains surge or switching transients to earth.
8.
Lift Systems
The lift engineering systems must conform to both EN 81 and Part M of the Building
Regulations and the Universitys standard specification (Part 3 Lift Instalations). Both
Passenger and Goods Lifts must incorporate a Windcrest Alarm System for
communication purposes. This will necessitate the installation of both Telephone and
Building Management System (B.M.S.) connections within the lift motor room.
9.
External Services
Prior to carrying out any external excavation works, a full sub-tronic site survey should
be completed to identify the presents of all underground services.
An excavation permit, which can only be issued by the Universitys Project Officer will be
required before any external works commence. All external services shall be laid no less
than 1m below the surface and surrounded with sand, Marker/ Tracer tape shall be laid
on the sand before back filling. All excavations shall be re-instated to the original (as
was) standard as agreed with the project officer.
Accurately marked (including dimensions from buildings, road/ kerb edges etc), Asinstalled drawings must be provided on completion of any external works with locations
of all underground services clearly dimensioned (utilising GPS co-ordinates) from
nearby buildings, road/kerb edges etc.
External aboveground pipe work should be fitted with a suitable trace heating system
where appropriate.
10.
Specific control strategies are detailed in Part 10 of the M&E Design guidelines All
Universitys facilities should be connected to the Honeywell Building Management
System. Control strategies should be developed to ensure the mechanical engineering
systems operate efficiently and effectively. Strategies to be considered include:
All new motor control centre panels (BMS) will incorporate two sections; one with mains
power units, the other with extra low voltage control units thus facilitating safe working
practices with regards to fault finding.
31
Design Guidelines
PART 1 GENERAL
Allowances should be made for connection of all new BMS Control panels to the
Universitys existing fibre optic network. Where motor speed controllers/inventors are
incorporated within the MCCP they must be easily accessible without defeating panel
safety systems and care should be taken to minimise electrical noise and interference.
Emergency backup in the form of a UPS should be provided for the network fibre drivers
within the BMS control panel.
All critical plant requiring Permits to Work must be located in a standalone section of the
MCCP. This section should have separate and dedicated control circuits.
11.
Security
The following details are intended to provide the general principles only to enable the
concept design for security systems within and around the building to commence. The
overall security requirements will differ for each individual building and location on
campus and all designs will require the approval of the Universitys Security Manager
and Insurers.
11.1
General
The design of the security system must comply with the latest NSI-NACOSS standards.
11.2
Exterior
The first consideration should be to secure the ground floor. This should be
implemented by providing access control measures at the buildings main entrance with
infrequently used doors being secured and alarmed as appropriate.
Where possible, security glass should be installed in all outer windows of the ground
floor. The windows should be lockable and incorporate limiting devices on the opening
mechanism.
If there are other methods of easy external access such as flat roofs, the accessible
windows need to be protected as above and the room/area alarmed internally.
The exterior of the building should be well illuminated, especially around the main
entrance areas.
External access and Fire doors should be controlled by a magnet locking device and if
forced must activate a security alarm. Green break glass units panels must also be
installed to disconnect the magnetic locks power supply in the event of an emergency.
All roofs and rainwater installations should be designed to discourage unauthorised
access to the roof. Only roof lights with a high degree of security should be specified.
Sun pipes should be considered as an alternative to provide natural daylight.
11.3 Interior
The internal level of security required will depend on occupancy level and usage of the
building. The corridors should be protected using P.I.R. sensors connected to an
addressable control system that is linked via the Universitys fibre network to the main
32
Design Guidelines
PART 1 GENERAL
12.
33
Design Guidelines
PART 1 GENERAL
14.
Card Access
All new buildings should incorporate Access control. The specific requirements for each
individual building should be development by and in conjunction with the Universitys
Card Access Control Manager and will utilise the existing University card.
The installation will be carried out by the Universitys nominated Access Control
contractor.
15.
Plant Rooms
The plant room must be accessible from outside the building with an appropriate
pathway to plant room door (to be agreed with the project officer) and access for
vehicles to off-load heavy items of equipment at appropriate locations. Suitable access
for plant area equipment removal must be provided.
All voids and walkways containing plant shall be illuminated using fluorescent fittings to
a minimum of IP56.
34
Design Guidelines
PART 1 GENERAL
Plant rooms must have painted water-tight floors, with a drain gully appropriately
located; the floor must be laid to fall towards the drain. Under no circumstances must
water be allowed to flow into occupied accommodation should flooding occur. All items
of plant to be located on suitable builders work plinths and should be mounted on
appropriate anti-vibration pads to isolate the equipment from the building structure.
All windows and external ventilation panels shall be fitted with grills to prevent bird entry
with access door controlled by stand alone electronic Onity locks.
Mechanical Engineering plant rooms, equipment storage or cleaners cupboards are not
acceptable locations for switchgear. Storage provision should be included for spares
including fuses, filters, etc.
15.1
Location
Consideration should be given to the location of the Plant Rooms so that any internal
noise and vibration does not impact on building users or adjacent areas.
15.2
Drawings/Information
All valves in Plant Rooms and main valves in the building should be clearly labelled.
Each plant room shall have a framed AO sized schematic drawing clearly showing the
system installation. In all service voids, valves shall be clearly labelled particularly
where services pass through floors or walls.
15.3 Access
A complete set of As fitted drawings shall be permanently positioned within the plant
room.
Access to plant rooms shall be readily available, where plant rooms have external
access then a permanent path shall be provided. The type and construction to be
agreed with the Project Officer.
15.4 Service Risers
Each service riser must be adequately lit including both task and emergency lighting.
16.
Appropriate handover to the Client at the various key stages of the project is Critical
16.1 Construction
Each stage of the building services (e.g. 1st fix, 2nd fix, commissioning etc.) installation
must be inspected by a representative of the Universitys Project team. Only upon
approval should the next phase of the installation commence.
A sample of the proposed installation standard of each stage should be completed for
the inspection and approval of the Project Officer or his representative before the full
installation continues.
The Design team should deliver a presentation to all
Maintenance to highlight the design intend of the proposed systems and their operation.
35
Design Guidelines
PART 1 GENERAL
16.2 Handover
A number of guided tours should organised at key periods throughout the construction
phase to help familarise the Maintenance staff with the buildings operation (suggested
milestones - first fix, second fix and pre-handover).
Before any services tour takes place a draft Operation and Maintenance manual or a
simple Building User Guide as described within BREEAM should be presented.
A dedicated handover meeting should be arranged at which the following information
and documentation should be supplied to the project officer.
17.
Future Expansion
An allowance in the order of an additional 25% should be made across all services for
future expansion and development.
18.
Contractual Issues
18.1 Electrical
All Electrical packages should include:
The installation of Category 6 data containment only. The cabling installation will
be carried out by the Universitys nominated Data installer.
19.
Maintenance
All engineering systems shall be designed in accordance with current Health and Safety
guidelines and good practice for access and maintenance of plant. Attention must be
given to the need for effective, safe and proper maintenance of all building systems. It
is a requirement that a full Preventative maintenance scheme and Legionella Risk
36
Design Guidelines
PART 1 GENERAL
Assessment for all building services be submitted in sufficient detail for operational
purposes from the date of practical completion for the employers approval.
20.
37
Appendix A
RIBA PROJECT WORK STAGES
STAGE 1
PRE-DESIGN
1.1 DEFINITION
1.2 Evaluation
1.3 Resource Planning
STAGE 2
DESIGN
1.4 Brief
STAGE 3
CONSTRUCTIO
N
3.1 PRE-PLANNING
3.2 Control
3.3 Construction
completion
3.4 Contractual
completion
APPRAISAL
Strategic Brief
Feasibility
OUTLINE
PROPOSALS
-Complete development of approved outline design into design solution (spec & drawing for costing purposes)
-Provide sketch drawings showing locations, sizes of plant rooms, items of plant & service runs
-Validates against brief
-Rational/develop specifications, calculations, schematic drawings & schedules
-Prepare revised cost estimates
-Prepare pre-tender document & drawings. Invite quotations for equipment report on & select equipment
-Prepare detailed drawings & specifications for tender
Scheme Design
E
F
G
Detail
Design
Production
Tender
Information
Tender Action
38
MOBILISATIO
N
Construction to
Practical
Completion
Completion
Design Guidelines
PART 1 GENERAL
Appendix B
SCHEDULE OF PREFERRED MECHANICAL & ELECTRICAL MANUFACTURES
AND SUPPLIERS
Mechanical Manufacturers
ITEM
SUPPLIER
Attenuators
Axia
Menerga
Barkwell
Birmingham Air
AAF
Moducell (External)
System Air
Flackt Woods
Dal Air
Nu-Aire
Vent Axia
Denco
IAC
Sound Attenuators
Industrial Acoustics
Allaway Acoustics
Isolated Systems
Tek
Spirax Sarco
BUYING AGENCY
/FRAMEWORK
Boso Flamco
Charles Winn
Boss
Ball Valves
Peglers
Worchester Bosch
Stokvis
Hoval Ultra Gas
Boilers Commercial
Stokvis
Hamworthy
Hoval
Chillers (Compression)
Airdale
York
Trane
Carrier
Dakiken
Chillers (Apsorption)
B.E.S Design Guidelines: General
Thermax
39
Design Guidelines
PART 1 GENERAL
Controls
Honeywell
Crane
Hattersley
Dampers, Fire
Actionair
Advanced Air
Trox
Actionair
Dampers, VCD
Differential Pressure Valves
(District Heating)
Open Book
Trox
Samson
Samson
Danfoss
SPV
Dosing Pots
Houseman Ltd
BOSS
DX Systems
Mitsubishi
Fans
Daikin
Woods
Vent Axia
Roof Units
Nu Aire
System Air
ACover
Flakt Woods
Crane
Hattersley
Flexible Connections
N Miniken
Engineering Appliances
Flexible Connections
for pumps
Star flex
Mercia
BSS
Flexible Ductwork
Hotchkiss
Hargreaves
Flues
A1 Bridge
Selkirk
Midtherm
Hamworthy
SFL Flues
Associated Plastics
Dynamic Plastics
40
Design Guidelines
PART 1 GENERAL
Central fans
Gas Fired Direct Water
Heaters
Hamworthy
Beamount
Andrews
Gauges
Budenberg
BSS
BOSS
Grilles/Diffusers
Senior Colman
Trox
Gilberts
Tek
Schako
Kranz
SPC
Cental Coils
Pilkington
Rockwool
Phenolic
Kingspan
Lifts (New)
OTIS
Lift Engineering Services
Thyssens
Kone
Lifts (Refurbishment)
Metering
Elster/Jeavons
Gas
Schumbeger
Metering
Water
Switch2
ABB
Elster
Natural/Fan Convectors
Biddle
Myson
Shearflow
BSS
Perimeter Heating
radiator Section)
(See
Sill Line
Pipework / Fittings
Steel
Crane
George Fischer
Copper
Conex
Yorkshire
Plastic
George Fischer
Durapipe
41
Design Guidelines
PART 1 GENERAL
Stokvis
P.R.Vs
BSS
HSS
Honeywell Brockman
Pressurisation Units
Baileys
Pressmain
Grundfoss
BOSS
Hamworthy
Pillinger
Pumps- LPHW
Radiators
Radiant Heating
Stelrad
Hudevad
Sensotherm
Merriott
Ambirad
Safety Valves
Nabic
Showers
BOSS
Mira/Rada
Strainers
TRVs
Underfloor Heating
Spirax Sarco
Crane
Hattersley
Danfoss
Peglers
Drayton
Hertz
Wirsbo
Osman
Valves (LSV)
Crane
Hattersley
Reliant TM3
Water Boilers
Heatrae Sadia
Zip
Water Heaters
Heatrae Sadia
Santon
Radan
Braithwaites
Water Treatment
Dewey Waters
Balmoral
Scalewatcher Electronic
OGC
Enua
42
Design Guidelines
PART 1 GENERAL
Electrical Manufacturers
ITEM
SUPPLIER
Accessories
Novar MK
BUYING AGENCY
/FRAMEWORK
MEM
Crabtree
Busbar/Underfloor Trunking
MEM
Schneider
Novac MK
Legrand
Barduct
Cables
Specific LSF
XLPE 5
Enhanced Fire Tuff
Cable Containment
-Trays / Basket
Dal Air
Legrand
Marshal Turflex
Novar-MK
-Trunking
Walsall
Conduits
-Ladder Rack
Barton
Wiremold (Swifts)
-Steel Conduit
Mita
Legrand
Walsall Conduits
-Steel Trunking
Barton
Legrand
-PVC Conduit
Walsall
`
Marshall-Tufflex
-PVC Trunking
(Super high impact only)
Mita
Novar MK Electric
Marshall-Tufflex
Mita
Novar MK Electric
Legrand
Card Access
Group 4
Faac
OGC
43
Design Guidelines
PART 1 GENERAL
Heald
CCTV Cameras
Bosch
External Lighting
(Refer to
luminaire section for
additional information)
Holophane
Marlin
Design Plan
Kingfishers
Phillips
Emergency Lighting
(fittings)
Baravon
Cooper/Merivier
Emergency Lighting
(central battery system)
Ziton
Fire Sleeves
Gents
Dufaylite
Flexible Conduit
Adaptaflex
Kopex
Marshall Turflex
Fuses
Lawson
MEM
General Electric (GE)
DMS
Switch 2
ABB
Lamps
Lighting Controls
EX-Or
Lighting Dimming
Dynalite
OGC
I-light
Logging/Remote Monitoring
Energy
Luminaries
ICT
Sinergy
EMT
Concord/Marlin
Metering
Cooper/Crompton
Whitecroft
Phillips
Thorlux
Ridi
ABB
Electric
PRI Socomec
Elcomponent
44
Design Guidelines
PART 1 GENERAL
MEM Ltd
Dorman Smith
Merlin Gerin
GEC
H.V.
Schneider
ABB
Merlin Gerin
U.P.S. System
Chloride
MGE
APC
Honeywell
ABB
Grundfoss
Wiring Accessories
45
Design Guidelines
PART 1 GENERAL
Appendix C
DESIGNERS RISK REGISTER
ESTATES OFFICE
Project Title:
Specification Reference:
Project Manager :
CDM Co-ordinator:
DRA Ref.
Date
Entered
DRA Owner
Risk Considered
G1
001
1/1/07
A Pearson
Testing
Risk Assessment
L
1
1
1
1
1
2
2
2
2
3
3
3
4
4
5
S
1
2
3
4
5
2
3
4
5
3
4
5
4
5
5
A
1
2
3
4
5
4
6
8
10
9
12
15
16
20
25
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Testing
Testing
Risk Assesment.
Medium/High risks
must be identified on
rele vant dra wings
L
1
1
1
2
2
2
3
3
3
1
2
3
1
2
3
1
2
3
1
2
3
2
4
6
3
6
9
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Notes
Risk Matrix
46
Design Guidelines
PART 1 GENERAL
SUSTAINABLE TECHNOLOGIES/SYSTEMS
The Following provides an example of the report format and identifies a number of
technologies that would warrant investigation. The list is not exhaustive and should
be examined as necessary.
This is not an exhaustive list, add new technologies you feel necessary.
OPTIONS
FEASIBILE EST.
(Y/N)
COST
PAYBACK
(YEARS)
CO2
SAVINGS
COMMENTS
Biomass
Boilers / CHP
Solar Heating
Solar Power
(PV)
Absorption
Cooling
Rainwater
Harvesting
Green Roof
Wind Power
Ground Source
Heat Pumps
Enhanced
Building Fabric
and Envelope
Add Option
Add Option
Add Option
47
Design Guidelines
PART 1 GENERAL
Appendix E
M&E Design Document Register
The following document register provides reference details of the current Universitys
M&E design specifications and guidelines.
Ref
Document Name
Revision
States
Revision
Comments
Date
Issued
AL001
AL002
AL003
AL004
AL005
AL006
AL007
AL008
AL009
Nov 07
Nov 07
Nov 07
Nov 07
Nov 07
Nov 07
Nov 07
Nov 07
Nov 07
AL100
AL101
Nov 07
March 07
March 07
Dec 06
Nov 07
AL120
Aug 07
AL100
Document Register
General
Update
-
AL102
AL103
AL104
Nov 07
48
Design Guidelines
PART 1 GENERAL
Appendix F
REFERENCE DOCUMENTS
The following list is not intended to be exhaustive or complete but as a potential
source of reference.
49