Professional Documents
Culture Documents
GARCIA
06 April 1995
Topic: Presumption of Regularity of Performance; Strong Evidence
SUMMARY :
Out of the groups interested in building the EDSA LRT III, only one (a corporation organized under HK
laws) satisfied the prequalification requirements. As such, DOTC awarded the contract to it by negotiation and
not by public bidding. The parties entered into agreements initially without congressional or presidential approval.
Petitioners questioned the validity of the proceedings conducted. SC dismissed the petition.
NATURE: Petition under Rule 65 to prohibit respondents (DOTC Sec. Garcia, Jr., and EDSA LRT Consortium) from
further implementing the agreement to build an LRT system in EDSA
N.B. Several DOTC Secretaries and Executive Secretaries were involved in this case. It's best not to focus on their names.
FACTS:
1989 - DOTC planned to construct an LRT line along EDSA (EDSA LRT III).
1990 - RA 6957, the "Build-Operate-Transfer (BOT) Law" was passed. It recognized 2 schemes for the
financing, construction, and operation of gov't projects: BOT and BT (Build-Transfer).
1991 - The Prequalification Bids and Awards Committee (PBAC) issued guidelines for the prequalification of
contractors. These were published in 3 newspapers of general circulation weekly for 3 consecutive weeks.
Of the 5 groups that submitted prequalification bids, only EDSA LRT Consortium, organized under HK laws,
met the requirement of 21 points per criterion (except Legal Aspects), garnering a total of 82/100.
DOTC Sec. Prado sent Pres. Cory 2 letters recommending the award of the project to the Consortium and
requesting authority to negotiate with it. Exec. Sec. Orbos directed DOTC to proceed.
Consortium submitted its bid proposal which DOTC found satisfactory. DOTC and EDSA LRT Corporation (in
substitution of Consortium; hereinafter "Corp") entered into an "Agreement to Build, Lease and Transfer a Light
Rail Transit System for EDSA".
1992 - DOTC Sec. Prado requested presidential approval of the contract, but Exec. Sec. Drilon said the
President could not grant the approval for the ff. reasons:
(1) DOTC failed to conduct actual public bidding in compliance with the BOT Law 5;
(2) The prequalification proceedings was not the public bidding contemplated under the law;
(3) Item 14 of the IRR of the BOT Law which authorized negotiated award of contract in addition to public
bidding was of doubtful legality;
(4) Congressional approval of the list of priority projects under the BOT/BT Scheme provided in the law had
not yet been granted at the time the contract was awarded
DOTC and Corp entered into a Revised Agreement, claiming that the DOTC has full authority to sign the
Agreement without need of approval by the President. They also entered into a Supplemental Agreement to
clarify their respective rights and responsibilities. DOTC Sec. Garcia submitted both to Pres. FVR for approval.
FVR approved them. Under the agreements, this is how the BOT scheme will work:
o Corp shall undertake and finance the project. Upon viability thereof, Corp shall deliver the use and
possession to DOTC which shall operate the same. DOTC shall pay monthly rentals. After 25 years and
DOTC has completed the payments, ownership shall be transferred for $1.
1994 - RA 7718 amending the BOT Law was passed. It expressly recognizes the Build-Lease-Transfer (BLT)
scheme and allows direct negotiation of BLT contracts.
PETITIONERS ARGUE: The Revised and Supplemental Agreements are unconstitutional/ invalid because:
(1) EDSA LRT III is a public utility, and the ownership and operation thereof is limited by the Constitution to Filipino
citizens and domestic corporations, not foreign corporations like private respondent;
(2) The BLT scheme provided in the agreements is not the BOT or BT scheme under the law;
(3) The contract was awarded to private respondent not through public bidding which is the only mode of
awarding infrastructure projects under the BOT law; and
(4) The agreements are grossly disadvantageous to the government.
VILLARAMA, BIANCA DANICA S.
PAGE 1
CASE # 14
PAGE 2
CASE # 14