Professional Documents
Culture Documents
Engineering
Technology (IJEET),
ISSN 0976 6545(Print),
INTERNATIONAL
JOURNAL
OFand
ELECTRICAL
ENGINEERING
&
ISSN 0976 6553(Online) Volume 6, Issue 1, January (2015), pp. 63-71 IAEME
TECHNOLOGY (IJEET)
ISSN 0976 6545(Print)
ISSN 0976 6553(Online)
Volume 6, Issue 1, January (2015), pp. 63-71
IAEME: www.iaeme.com/IJEET.asp
Journal Impact Factor (2014): 6.8310 (Calculated by GISI)
www.jifactor.com
IJEET
IAEME
ABSTRACT
In this paper, it was treated the dynamic stability of a photovoltaic production and its impact
on the level of protection, a number of simulations were performed to evaluate the system response
following the integration of a PV - production of 5 MW. The simulation results have explain
theunjustified operation of the protection system and the protection of the disconnection of the PVProduction hence the need for treatment of individual cases of PV integration in order to adjust the
level of protection at the rate of penetration of PV distributed generation (DG) on MV grid.
Keywords: PV-Production, 3-Phases Injector, Simulation, Fault.
1. INTRODUCTION
After promulgation the law N13-09 to renewable energies [1], relating to the clauses of
integration to the national electrical system the productions of energy from renewable sources, the
national electrical grid MV (Medium Voltage), know very soon a massive integration of productions
stemming of solar sources in the occurrence of them photovoltaic energy.
Gold, the MV grid conceived to insure the transit of energy of the uphill system to consumers
and to function on the basis of one direction of power flow, is not anticipated to welcome these DEP
(Decentralized Energy Production) to the large scale [2]. And consequently, circulation of power
flows are going to change and are going to be originally various problems disturbing the good
functioning of the electrical system.
Where, a behavior study is required so as to apprehend the reaction of the system MV in the
face of this integration, especially in terms of aspect controls the grid.
63
International Journal of Electrical Engineering and Technology (IJEET), ISSN 0976 6545(Print),
ISSN 0976 6553(Online) Volume 6, Issue 1, January (2015), pp. 63-71 IAEME
2
. + .
3 +
(1)
2
. .
3 +
Where;
P and Q are active and reactive powers of reference of the production PV
Vd and Vq are respectively the direct and squareness components of the voltage, measured to
the point of connection of the DEP.
Id and Iq are respectively the direct and squareness components of the current produced by the
point of connection to the DEP
A loop to bolting of phase PLL (Phase Locked Loop) is used to synchronize the
transformation of Park on the pulsation of the voltage measured on the system. Thus, when the
system is in established regime, the direct component Vd in exit of the transformation of Park is an
image of the amplitude of the measured voltage, and the squareness component Vq is null.
These current are then converted in the three phases referential, the amplitude and phasor of
the currents injected on the system go thus regulated powers to their value of order.
64
International Journal of Electrical Engineering and Technology (IJEET), ISSN 0976 6545(Print),
ISSN 0976 6553(Online) Volume 6, Issue 1, January (2015), pp. 63-71 IAEME
Gold, so as to keep the realistic and dynamic aspect of this model tells simplified, the DEP and
the converter insuring the interface with the system are going to be designed by a limitation and a
delay.
2.1.
A.
Simplification of dynamics
We consider that the dynamics of the converter is very rapid as compared to the dynamics of
the element of production. The dynamic deduction for the converter is in the order the tenth of
second. As for the dynamics of the unit of production PV is in the order some seconds.
In these conditions, the dynamics (constant of time) of the converter is retained for the regulation of
the reactive power and that the unit of production for the regulation of the active power.
B.
Consideration of limitations
The limit for the component Id is chosen according to the maximal current in exit of the
converter and the active power limit of the production PV, gold limits it the component Iq is chosen
consequently, manner to does not exceed the limit of the reactive power datum by a report Q/P=0,4.
The next table recapitulates dynamics and limitations considered for our model of the production
PV:
Table 1: characteristics of regulation loops P/Q
Loop of regulation
Parameter
Value retained
0,5
Active Power
Ki
2
Kp
1
0,1
Reactive Power
Ki
10
Kp
1
C.
x 10
4.5
4
P o w e r (W / V A R )
3.5
3
2.5
2
1.5
1
0.5
0
3
Time (s)
65
International Journal of Electrical Engineering and Technology (IJEET), ISSN 0976 6545(Print),
ISSN 0976 6553(Online) Volume 6, Issue 1, January (2015), pp. 63-71 IAEME
Current production PV
160
140
120
C u rre n t (A )
100
80
60
40
20
3
Time (s)
Transformer data
Line N1 data
Parameter
Psc
Nominal voltage
Nominal frequency
R/X
Power
Primary voltage
Secondary voltage
Usc
Wiring
Neutral resistance
Length
Section
Rd
Ro
Xd
Xo
Cd
Co
66
Value retained
277MVA
63kV
50Hz
0,05
20MVA
63kV
22kV
16%
YNyn
42,5m
36km
148mm
0,2236 m/km
0,368 m/km
0,35 m/km
1,588 m/km
11,13nF/km
5nF/km
International Journal of Electrical Engineering and Technology (IJEET), ISSN 0976 6545(Print),
ISSN 0976 6553(Online) Volume 6, Issue 1, January (2015), pp. 63-71 IAEME
The value of neutral resistance is 42,5m so as to limit the current to the earth to 300A.
Loads are simply modeled by a RL circuit in parallel; the next table recapitulates the different load
by line;
Table 3: Values of loads
Line
Active load (P
en kW)
Line N1
Line N2
Line N3
5103
4217
5808
Reactive
load (Q en
kVAR)
2016
1668
2295
The settings of the relays installed of the arrival MV and the line N1 are DGermined as follows:
Table 4: Setting of protection Bus MV and line N1
Protection
Fonction
Setting
Max I- Phase
610A
Bus MV
Max I -Homopolaire
17A
Max I-Phase
240A
Line N1
Max I-Homopolaire
14A
Concerning the production PV, its protection of DG Disconnection is that typical H3 according to [4]
& [5]:
Table 5: thresholds of setting protection PV Production
Protection
Relay
Setting
Action
Phase to Earth Faults
Max V0
10%Vn
0.650 s
Phase to Phase Faults
Min U
85%Um
0.650 s
Min U
85%Um
0.650 s
Max U 115%Um
instantaneous
Separate grid working
Min freq
49.5Hz
instantaneous
Max frq
50.5Hz
instantaneous
Strong off-peak voltage
Min U
25%Um
instantaneous
4. SCENARIOS OF STUDY
The line N1 having sheltered the PV production of 5MW is considered to equip a normal
ASR (Automatism of Service Resumption) of where the line faults are supposed cancelled in rapid
cycle temporized to 150ms.
Three types of fault will be analyzed:
Three-Phase symmetrical and frank fault;
Two-phase Frank fault;
Phase-earth fault, with resistances of earth are 30ohm and 450ohm.
These faults will be simulated on four points:
In end of line N1
To the MV bus
To the adjacent line N2
To the HTB bus
67
International Journal of Electrical Engineering and Technology (IJEET), ISSN 0976 6545(Print),
ISSN 0976 6553(Online) Volume 6, Issue 1, January (2015), pp. 63-71 IAEME
A comparison with the functioning of system without PV production has been made so as to
divulge the impact of the integration of the generator PV on the behavior of system protection. View
that 80% of the faults are fugitive defects [6]&[7]; the faults is supposed cancelled in rapid cycle
The different stemming curves of the simulation are represented to the next section.
4.1. Results of simulation the fault in end of line N1
A. 3-Phase symmetrical fault
The next table recapitulates the behavior of the different protections:
Table 6: Recapitulation of simulation results
Point of grid
Relay
Measure
Action
Grid with PV-P
Bus MV
Max I
590A
Not activated
Line N1
Max I
470A
Activated
Min U
9732V
Activated
3
Max U
19.10 V
Not Activated
Connection PV
Production
Min freq 49,8Hz
Not Activated
Max Frq 50,15Hz
Not Activated
Grid without PV-P
Bus MV
Max I
638A
Activated
Line N1
Max I
506A
Activated
For a three-phase fault, we observe the normal opening of the line N1 breaker, the PV
production is not disconnect seen the temporization of the relay Max Vo.
Nevertheless, we observe the blindness of the protection Max I bus MV in case of system with PV
production
B.
PH A-B
The next table recapitulates the behavior of the different protections:
Table 7: Recapitulation of simulation results
Point of grid
Relay
Measure
Action
Grid with PV-P
Bus MV
Max I
574A
Not activated
Line N1
Max I
427A
Activated
Min U
9700V
Activated
3
Max U
19.10 V
Not activated
Connection PV
Production
Min freq 49,9Hz
Not activated
Max Frq 50,0Hz
Not activated
Grid without PV-P
Bus MV
Max I
657A
Activated
Line N1
Max I
478A
Activated
For a two-phase fault, we observe the normal opening of the line N1 breaker, the PV
production is not disconnect seen the temporization of the relay Max Vo.
Nevertheless, we observe the blindness of the protection Max I bus MV in case of system
with PV production
68
International Journal of Electrical Engineering and Technology (IJEET), ISSN 0976 6545(Print),
ISSN 0976 6553(Online) Volume 6, Issue 1, January (2015), pp. 63-71 IAEME
C.
For a phase-earth fault, with an earth resistance is 30Ohm , we observe the normal opening of
the Bus MV breaker, the PV production is not disconnect seen the temporization of the relay Max
Vo.
D.
In this type of fault with a great resistance of earth, alone the PV production is disconnected
to the system.
In reality a research of the earth resistance undertakes to the level the source MV, this relay is
temporized to 15s.
69
International Journal of Electrical Engineering and Technology (IJEET), ISSN 0976 6545(Print),
ISSN 0976 6553(Online) Volume 6, Issue 1, January (2015), pp. 63-71 IAEME
For 1Km of distances the PV production will be disconnected instantaneously by the relay
Max freq, in the other cases it disconnection is make to the level of the line N2.
B.
70
International Journal of Electrical Engineering and Technology (IJEET), ISSN 0976 6545(Print),
ISSN 0976 6553(Online) Volume 6, Issue 1, January (2015), pp. 63-71 IAEME
Blindness of the protection Max I bus MV in case of failure protection Max I line N1, for
the 3 - Phase and 2 Phase faults;
Unjustified Disconnection of the PV production by Min VO, in case of research of the
resistance earth ;
Unjustified Disconnection of the PV production by Min U and Max Freq, in case fault on the
adjacent line ;
Unjustified Disconnection of the PV production by Min U and Max freq, in case of HV fault.
In this paper, it was demonstrated the need for simulation of the electrical network in case of
integration of PV products, to provide for the review of the thresholds of protection settings,
and therefore protect the network against faults that may occur.
6. REFERENCES
1.
2.
3.
4.
5.
6.
7.
8.
71