You are on page 1of 3

Optimisation of Vessel Maintenance

Traditionally, vessel maintenance has always been carried out empirically, mainly based on
the recommendations of the manufacturers and the requirements of the classification
societies, but does this method optimise maintenance costs?
In general, most drilling equipment include systems and parts that are subject to scheduled
maintenance according to the prescriptions of the manufacturers. Such prescriptions, besides
being usually on the conservative side do not take into account the systems mission profile
and the actual environment in which they operate. Therefore, there is no evidence that they
are economically optimal.
To move from a prescriptive to an optimised and customised approach, it is necessary to
review the scheduled maintenance intervals established by manufacturers on the basis of the
actual reliability performance, safety and economic constraints. Such process falls within the
framework of the more general approach known as Reliability Centred Maintenance (RCM).
Computerised Maintenance Management System (CMMS) can thus be used to demonstrate
the application of preventative maintenance concepts in order to achieve better quality,
punctuality, speed and a higher service level for its fleet. Objectives are reached by planning
maintenance repairs at the most convenient time, without interfering with the equipments
availability, and thus reducing unexpected maintenance actions (i.e. breakdowns) while
maintaining (or even improving) the original safety levels.
Although not specifically aimed at reliability calculations, the presence of CMMS suggested
the application of RCM techniques in order to add the economical optimisation of
maintenance to the above objectives whilst improving the safety level.
The ultimate goal of the Reliability Centred Maintenance method, based on reliability,
availability and maintainability (i.e. RAM analysis), is the operating of the maintenance
process to take into account both the risk of accidents, which can occur if primary systems
fail, and the costs associated with their preventative and corrective maintenance.
The optimisation process is the result of balancing risk and cost on the basis of well-defined
RAM objectives of:
Safety
Economic
Commercial/quality
The RCM approach can thus be implemented by utilising risk analysis methods applied to
safety criteria defined by regulations and the cost minimisation criteria as defined by the
vessels owner. The basic methodology used in the implementation of the analysis included
the following nine stages:
1. Preliminary risk analysis to identify the critical items selected.
2. Identification of the items for which maintenance is more expensive and the quality
and quantity of data
3. Familiarisation with the type of maintenance strategy currently applied to the selected
items (see table)
4. Collection of historical data of the scheduled and unscheduled maintenance actions
on the items under analysis
5. Confirmation of the data received from the drilling vessels owner to evaluate their
consistency with those utilised in the preliminary analysis
6. Statistical analysis of the items for which a significant number of failures has been
collected
7. Definition of the costs associated with failure and maintenance of each selected item,
in terms of down times, off-hire, spare parts and resources
8. Upgrade of maintenance strategy and, if possible, definition of optimal maintenance
intervals
9. Update of statistical analysis and of the maintenance intervals on a regular basis

Following the data analyses of the main systems of drilling vessels, it was concluded that the
savings deriving from the customisation of the time intervals for the replacement of the
selected items were outstanding. E.g. The frequency of replacement was abated by a factor of more
than 2 (even 6 in one case).
Five broad classes of maintenance strategies can be distinguished
Maintenance Model

Preventive (scheduled)
maintenance

Corrective maintenance only

Corrective
(unscheduled)
maintenance
replace at failure

Age replacement policy (ARP)

replace at failure

Block replacement policy (BRP)

replace at failure

Minimal repair policy (MRP)

minimal repair by failure

Periodic testing (for standby


components)

none

replace after a time of


operation
replace after a fixed elapsed
time
replace after a fixed elapsed
time
replace after a fixed elapsed
time

none

Notes: For all strategies except MRP, the item is assumed to be restored as good as new after repair.
The term minimal repair means that the item is repaired to the state it had immediately before the
failure occurred.
The parts of the systems selected in the study were subject to the ARP policy only.
For these calculations, the definition of failure was crucial. Here, failure meant the actual
breakdown of an item, and for every reliable component, this can determine the significance
of the calculation.
In such cases, the failure mechanisms and the actual purpose of the prescribed maintenance
operations have to be thoroughly understood before applying the revised time intervals.
It should also be stressed that the adoption of the optimal replacement time of an item does
not necessarily minimise the number of failures.
In the extreme case of equal preventive and corrective maintenance costs, it would be
convenient to run the item to failure, thus tolerating the failures rather than carrying out the
preventive maintenance actions.
For this reason, this methodology is best applied to items where failure is expensive
compared to preventive operations, but not immediately critical for the drilling vessels safety,
so the risk of a failure can, in principle, be afforded.
It is theoretically possible to apply this methodology to very critical equipment, on condition
that the costs associated with its failure are correctly accounted for, which could be ve ry
difficult when safety issues are involved.
Another significant factor is the actual possibility of getting a statistic within a reasonable time
frame; obviously, this can be achieved when the samples are sufficiently wide, thus a
significant amount of data can be collected in a relatively short time.
When the samples are small, the trend tests can be ignored and the analysis can proceed as
illustrated. Care should be taken, however, when the economic risk associated with the items
analysed is high.
The uncertainties associated with optimal time intervals can be significant, and the decision to
adopt the mean, upper or lower value must be taken by making use of the experience of the
personnel in charge of maintenance activities.

A final consideration can be made for those items for which a statistical trend if detected and,
consequently the quantification of the optimal time intervals. Even in this case, the statistical
analysis can provide added value, in that it highlights the need for further investigation to
understand the causes of the trend (in particular, if it represents decreasing reliability).
The following checks should be made:
verify if the statistical results can be justified physically or are due to insufficient or
poorly elaborated data;
if they are justified, understand the reason for the trend; e.g. parts replaced with
inadequate spares, lack of skill of the operators performing the replacement, etc.
This process can highlight different maintenance performances among ships in the same
fleet.
A ship owner who has installed a CMMS onboard his ships obtained a real advantage by
employing the maintenance data for statistical analysis.
The cost of this is surely negligible with respect to the possible savings and the insights
provided, on condition that qualified resources are involved in the process; expertise is
particularly required in the phase of interpretation of the field data, which actually affects the
final results.

You might also like