You are on page 1of 9

PREPARED

BY

29-Aug.-2007

UKHan

CHECKED BY

29-Aug.-2007

UKHan

APPROVED
BY

29-Aug.-2007

CSHong

CERTIFIED
BY
REV.

DATE

CHECKED

NEW PLANT 2 FURNACE PROJECT

APPROVED

DESCRIPTION

29-Aug-2007

UKHan

CSHong

Issued for Approval

26-Sep-2007

UKHan

CSHong

Issued for Construction

PTT Chemical Public Company Limited.


CONSTRUCTION EQUIPMENT PLAN

Doc No : G-11-C5-PN-002

REVIEW STAMP
WORK MAY PROCEED.
Submit Final Document
REVISE AND RESUBMIT
G: Work May Proceed subject
incorporation of Changes indicated
REVISE AND RESUBMIT
H:
Work May NOT Proceed
THIS REVIEW DOES NOT RELIEVE THE
CONTRACTOR OF HIS RESPONSIBILITY
FOR ERRORS IN DESIGN
E:

BY:
DATE:
PTT Chemical Public Company Limited.

CONTRACT NO.
04-018/2007

PTTCHEM JOB NO..

LINDE & SFPC JOB NO.

TWRE JOB NO.


06004D

APPENDIX C

CONSTRUCTION EQUIPMENT PLAN


( Doc No : G-11-C5-PN-002 )

Rev. 0
Date : 26 Sep 2007

GENERAL
TWRE will plan and provide, operate, utilize, service and maintain all the
construction equipment, tool, tackle, gear and auxiliary implements in quantity,
quality, characteristics and capacity required to carry out the individual work in
constructing the plant, including pre-fabrication and pre-assembly, in the most
efficient way and to a high technical standard.
The construction equipment, tools, etc., operated and/or used by the Contractor
shall be in excellent working condition and the most suitable for the purpose for
which they are intended.
Also TWRE stand by the mechanics full time at site and shall service, administer
and maintain the construction equipment, tools, etc., in such a way that losses,
breakdowns, repairs and replacements are kept to a minimum.
TWRE shall only bring construction equipment, tools, etc., to the site for use in the
work required and remove them from the site upon completion of the construction
work.
1. TOOL and Equipment List
TWRE already secured and will prepare enough Equipment/ Tools and equipment
to carry out the constructing the plant. (Attachment #1 : Tool and Equipment List
and Plan)

2. EQUIPMENT MOBILIZATION PLAN


TWRE will plan and control the equipment mobilization plan with preliminary bill of
materials and schedule. Development of Equipment Mobilization plan predicted and
adjusted with weekly monitoring of following items;
Construction Equipment Mobilization Plan by each discipline is

Material Delivery Schedule


Construction Progress and Schedule

Construction Equipment Mobilization plan is as per attachment #2 Equipment


Mobilization Plan

Attachment #1 : TWRES Tool and Equipment List and Plan


Attachment #2 : Equipment Mobilization Plan for PTTChem Furnace Project

Page 1of 1

Attachment #1 : TWREs Tool and Equipment List and Plan


Discpline
Common
Common
Common
Common
Common
Common
Common
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Mechanic
Common
Civil
Civil
Civil
Civil
Civil
Civil
Civil
Civil
Civil
Civil
Civil
Civil
Civil
E&I
E&I
E&I
E&I
E&I
E&I
E&I
E&I
E&I

Item

Spec

Hydro Crane
50 ton over
Hydro Crane
25 ton
Trailer
20 ton
Hiap Truck
5 ton
Truck
5 ton
Pick up
2 ton
Radio
Explosion Proof
Gantry Crane
10 ton
Electric Winch
5 ton
Electric Welding M/C
300 Amp
Engine Welding M/C
Holiday Detector
Plasma Cutting M/C
Chain Block
1.5ton
Chain Block
3 ton
Chain Block
5 ton
Chain Block
10 ton
Chain Block
15 ton
Air Compressor
for Valve Leak Test
Welding Tool Sets
Arc, Jig
Grinder
7"
Grinder
4"
Leveling Transit
Air Ejector
Blower
Electric
Leveling Transit
Theodolite
DT200
Laser Theodolite
GTS 600
Compactor
1 ton
Compactor
80 kg
Rebar Cutting M/C
Rebar Bending M/C
Dump Truck
Excavator
0.4m3
Water Pump
3 inch
Vibro Roller
10 ton
Excavator
1 m3
Vibrator
60 mm
Hydraulic Clamp
650m2
Chipping Machine
Thread Machine
up to 3 inch pipe
Pipe Bending M/C
~3" Hydraulic
Megger Tester
1000 Volts
Safety V/V Piping Tester
~30 inch
Digital Calibrator
Temperature Calibration Bath
HART Communicator
Speed Gun
Non Contact Temperature Gun

TWRE

Rental
1

1
1
2
15
4
0
49
9
1
1
78
17
4
2
2
2
92
36
160
3
2
18
2
3
3
1
1
3
3

Total
2
1
1
1

2
11

3
1
2
2
3
2
1
2
1
1
1

1
1
3

2
2
1
2
1
2
15
4
0
49
14
1
1
78
17
4
2
2
2
92
36
160
3
2
18
2
3
3
1
1
3
3
2
0
11
1
1
6
1
2
2
3
2
1
2
1
0
1
1

Unit
sets
set
sets
sets
set
sets
sets
sets
set
sets
sets
set
set
sets
sets
sets
sets
sets
sets
sets
sets
sets
sets
sets
sets
sets
sets
sets
sets
sets
sets
sets
sets
set
sets
set
set
sets
set
set
sets
sets
sets
set
set
set
sets
set
set

Remarks

Attachment #2 : Equipment Mobilization Plan for PTTChem Project

CONSTRUCTION EQUIPMENT MOBILIZATION PLAN


Unit : S/M
PROJECT : PTTChem Furnace Project
NO

EQUIPMENT NAME

Unit

2007
8

2008

10

11

12

10

Bored Pile M/C

Month

Hiap Truck (5 ton)

Month

3
4

JCB
Dump Truck

Month
Month

1
1

1
1

1
1

Hydraulic Crane (50 ton)

Month

Hydraulic Crane (25 ton)

Month

7
8

Hydraulic Crane (300 ton)


Hydraulic Crane (100 ton)

Day
Day

Welding Generator (200KVA)

Month
Month

21
3
3

10 Trailer (25 ton)

REMARKS

Tot

10
14
2

2
1

16

17
10