Professional Documents
Culture Documents
PAGE 1
EXECUTIVE SUMMARY
C. Summary of Impact Assessment and Environmental Management Plan
After assessing and managing the impacts discovered during the data gathering, the
IEE team was able to mitigigate the following environmental impacts; On, the preconstruction phase there are no significant impacts were found, Concurrently, On the Construction
Phase the team were able to mitigate,Land alteration and modification, Soil Physical Properties ,Increase TSP due to equipment /material movement, Generating of air pollutants , Surface /Groundwater contamination, Disturbance of local flora & faunaIncrease Employment
opportunities, Noise Generation and Traffic. On the Operational phase the team manage to
mitigate the following; Air pollutants from vehicles, Noise from vehicles ,Domestic waste water generated from operation,Solid waste generation, Increase employment
opportunities ,Increase traffic volume , Impact of environment to the project and Revenue
generation, Lastly, On the abandoment phase the team were able to provide enhance measures for Encroachment of the Park,Deterioration of aesthetic value and Proliferation of invasive species.
D. Summary of Environmental Monitoring Plan
The Environmental Monitoring plan includes environmental parameters that needs to
be monitored, location, time and frequency, cost for sampling and stage of subproject where
monitoring should be conducted.
PAGE 2
POSTAL ADDRESS:
PAGE 3
PAGE 5
Civil Engineer
Sanitary Engineer
Surveyor
Cost Engineer
Chemical Engineer
Pollution Specialist
( Water / Air)
Sociologist
Solid Waste
Management Engineer
Health Officer
ACTIVITY
WEEK 1
WEEK 2
WEEK 3
WEEK 4
PROJECT SCOPING
DATA GATHERING
NOVEMBER
ACTIVITY
WEEK 1
WEEK 2
WEEK 3
WEEK 4
IDENTIFICATION OF
POTENTIAL IMPACTS
ASSESSMENT OF
SIGNIFICANT
ENVIRONMENTAL ISSUES
DECEMBER
ACTIVITY
WEEK 1
PREPARATION OF
ENVIRONMENTAL
MANAGEMENT AND
MONITORING PLAN
SUBMISSION OF IEER
FOR ECC APPLICATION
PAGE 6
WEEK 2
WEEK 3
WEEK 4
PAGE 7
PAGE 8
3.PROJECT DESCRIPTION
3.1 PROJECT LOCATION, AREA,ECA CATEGORY
The project site is located in Barangay Antipuluan, Narra, Palawan. It is situated about
1.5 km northeast of the Narra town proper in the coastal plain, only about 200 m away from
the National Highway. Here the Katala Institute for Ecology and Biodiversity Conservation
(KIEBC) will be established. The site encompasses a total land area of 2.18 ha donated by
the municipal government of Narra. The area is surrounded by pastures and paddy fields,
with the Victoria Range as spectacular backdrop
The area will be landscaped through excavation of ephemeral ponds. These types of
wetlands once were typical for the coastal plain, before the onset of intensive rice cultivation.
Excavated materIal will be used to backfill built-up areas, also in order to avoid flooding during the rainy season. Landscaping will include reconstruction of vegetation formations typical for the area, like lowland rainforest, ultramafic forest, wetland vegetation, which will give
the area a park-like appearance .
About one third of the area will be occupied by parking lot, arboretum and a conservation education center with exhibit, which is openly accessible during day-time. Almost twothirds of the area will be open for the public through guided tours and eventually will accommodate enclosures for conservation breeding of selected species. About 2000m2 will not
be open to the public and will comprise a garden for growing feeds for the animals, offshow enclosures and quarantine, as well as the administration building (see red rectangular
in Fig. 1). The drafted plan with the location of the different project components (Fig. 1) is not
to scale but provides an overview of the relative proportions of the different areas. The following components are envisioned as part of the project. The sequence of listing is in line with
the legend of Figure 1.
In terms of the sites ECA Category,the area of construction is not listed at the Environmentally Critical Area (ECA) Categories as declared by Proclamation No. 2146 (1981).
The figure below shows the Vicinity Map of the proposed project.
PAGE 9
Figure 1: Draft plan of the Katala Institute for Ecology and Biodiversity Conservation.
PAGE 10
3.PROJECT DESCRIPTION
3.2 PROJECT RATIONALE
The Palawan faunal region is of high species diversity, reminiscent of the close-by is
land of Borneo, but at the same time holds a high percentage of endemics, therefore resembling the Oceanic Philippines. Although still extensive areas of pristine forests, mangroves
and coral reefs exist on Palawan, the rate of destruction, deterioration and fragmentation of
these ecosystems is one of the highest in Southeast Asia.
Since 1998, KFI is implementing the Philippine Cockatoo Conservation Program
(PCCP) in Narra, Palawan. It is one of the first community-based species conservation programs in the Philippines, and was deemed as one of the most successful of its kind. Within
eight years, the population of the critically endangered Philippine cockatoo increased more
than fourfold in a protected area specifically established for this species. Rasa Island is now
the single-most important habitat for the Philippine cockatoo and is one of the most accessible wild places in the Philippines for a broader public to experience first-hand a rare and endemic species in its natural habitat.
In order to institutionalize this project and to broaden conservation efforts within
southern Palawan, the establishment of the KATALA Institute for Ecology and Biodiversity
Conservation (KIEBC) was envisioned by KFI and its local and international partners.
1. Design and Construction Phase Clearly specify the different list of parameters as follow:
1. Project objective
2. Site feasibility and proximity to population centroids
3. Marketing plan
4. Materials market and net revenue
5. Security
6. Master Planning
7. Risk Assessment Study
8. Data Collection and Assessment
9. Technical Specifications, Performance Standards and Scope of Works
PAGE 11
3.PROJECT DESCRIPTION
2. Facility Design Operations Specify limitations or ranges on certain parameters as follow:
1. Conceptual design
2. Site plan
3. Hours of operation
4. Limitation of the quantity processed material on site
5. Operational approaches to prevent materials from exiting the building
and becoming litter
6. Placement of exterior lights and other security features
3. Schedule It must include the contract development stages, construction, and com
mencement of commercial operations to conclude a successful procurement process and
then meet construction deadlines.
4. Marketing Plan Marketing requirements will specify the materials that are to be marketed. Financial analysis will be catered and provide a financial risk discussion on state market
developments.
5. Compensation It will provide a compensation structure and detailed cost data to execute
the marketing plan.
6. Reporting It includes reports on several operating parameters, including hours of operation and others, in addition to quantities processed and revenue.
7. Proper Waste Disposal It will provide landfill disposal capacity for MRF residue.
8. Capital Repair To ensure the long-term viability of the facility, process equipment and
vehicles will be adequately maintained.
9. Continuous Monitoring Monitor the performance of the facility on an ongoing basis, with
rights to come on site daily.
10. Additional Materials This will include the additional new materials needed to use on the
MRF project.
PAGE 12
3.PROJECT DESCRIPTION
3.4 BUILT-IN POLLUTION CONTROL MEASURES
3.4.1 Preconstruction Phase: August to November 2014
Proposals for funding of the different components/phases of the project.
Rehabilitation of access road.
Landscaping through excavation of ephemeral ponds.
Backfilling for built-up areas to avoid flooding during the rainy season.
Establishment of plant nursery.
Planting with mainly indigenous tree species.
3.4.2 Construction Phase
Activities during the operational phase are limited to the three main objectives of
KIEBC. The operational phase includes construction of the facilities. Constructions and operations are dIvided into three phases the division of which is in line with the working plan of
Katala Foundation Inc. and the possible acquisition of funding:
Phase I: December 2014 to December 2016
Phase II: January 2017 to December 2018
Phase III: January 2019 to December 2020
Phase I focuses on the establishment of facilities for the captive management of Philippine
freshwater turtles, and rescued Philippine cockatoos from Rasa Island.
3.4.3 Operational Phase
Phase II and III will focus on Conservation Education and Research.
With the Conservation Education building in place it is possible to cater for two groups of up
to 25 participants in weeklong courses (e.g. ecosystem exposures), which would give the center a capacity of 600 in-house students per year.
Until now 150 registered guests per year are visiting Rasa, with increasing tendency.
The visitor/education center will be open during daytime without entrance fee. The animal enclosures are only accessible through guided tours. Katala Foundation receives requests for
cooperation of about 20 students (BS and MS) yearly, of which roughly half are foreigners. So
far, most of these had to be turned down in the past, since they involved activities during the
breeding season, where access to Rasa is restricted. With mores species being involved and
an existing infrastructure, 10 to 15 students or researchers could be accommodated. Other
local or foreign visitors will arrive in a common visitors' parking area, and make their way to
the training and viewing areas by foot. Once inside, they will pay an entrance fee (except residents of Narra) that would allow them to use or interact with the training, conservation, and
Research facilities.
PAGE 13
3.PROJECT DESCRIPTION
3.4.4 Abandonment Phase
The KATALA Institute for Ecology and Biodiversity Conservation project will be ensured to last for many years especially if the community and government will continue to
support the project. Its lifespan will be dependent on the maintenance and if no accidents
will occur. It is advisable to do some checking and maintenance every month. Each structures has components that may be subjected to breakage, for that reason it should be
checked regularly. The following parameters must not be unaccounted during abandonment
phase:
Initial Environmental
1. Biological Environment There will be possible degradation on soil and water quality due
to contamination in the abandonment process. For cases of removal of storage tanks and
other equipment, and other liquid substances.
2. Physical Environment There will be a large volume of solid waste generation due to
stoppage of works and elimination of structures. The segregated usable materials will be
traded to qualified buyers. The contractor will be responsible for hauling the residuals.
3. Social Environment The possibility of loss of employment is high at abandonment phase.
Here, the affected personnel will have separation pay and other necessary compensation.
OPERATIONAL PHASE
PERSONNEL
NUMBER
PERSONNEL
NUMBER
PROJECT ENGINEER
SANITARY ENGINEER
SITE ENGINEER
HEALTH OFFICER
SAFETY ENGINEER
SKILLED WORKERS
11
FOREMAN
LABORERS
22
SKILLED WORKERS
12
CARETAKERS
LABORERS
22
PAGE 14
3.PROJECT DESCRIPTION
3.6 PROJECT COST
The project cost will be divided into two parts: Construction phase and Operational
phase. The construction cost consists of the construction materials to be used and budget for
manpower. It is estimated to be Php 3,500,000.00 as a result of surveys and tests analysis for the
project. For the operational phase, it is estimated to be 247,500 pesos. Below is a summary of
expenses per hog and piglet, operating and other expenses.
Monthly Feeding
Birds (P750/head) = 30heads x P750 = P22,500
Turtles (P500/head) = 20heads x P500 = P10,000
Exotic Species (P1,000/head) = 20heads x P1,000 = P20,000
Total = P52, 500/month
Medication
Birds (P1,000/head) = 30heads x P1,000 = P30,000
Turtles (P1,000/head) = 20heads x P2,000 = P20,000
Exotic Species (P2,000/head) = 20heads x P2,000 = P40,000
Total = P 90, 000/month
Operating Expenses
Salary (for all personnel) = P50, 000
Facilities Maintenance (all expenses on materials) = P30, 000
Electricity/Water = P15,0000
Initial Environmental Examination Report (IEER)
Total = P 95,000.00 /month
Other Expenses (raw materials etc;)
Total = P 10,000
Estimated Monthly Expenses = P247,500
PAGE 15
3.PROJECT DESCRIPTION
3.7 PROJECT DURATION AND SCHEDULE
The project development will start right after all permits and clearances are secured. It will
have duration of 12-14 months of construction. The IEER must be completed for the application
of ECC, the IEE team assessed the construction schedule. The environmental conditions such as
the weather can affect the planned schedule for the project.
ACTIVITY FRAME
ACTIVITY
DURATION
PLAN/DESIGN
1 MONTH
PERMITS/CLEARANCE
3 MONTHS
LANDSCAPING
2 MONTHS
CIVIL WORKS
6 MONTHS
FINISHING
1 MONTH
1 MONTH
2 WEEKS
START-UP OPERATION
1 WEEK
PAGE 16
PAGE 17
4.1.2 Pedology
From the data gathered the KIEBC Project is located at Antipuluan,Narra, Palawan;
where It has an elevation of low land area and in a flat slope area which ranges from 0-2%.
The surrounding area is mostly pastures and paddy fields
4.1.3 Geomorphology
The soil structure of the project site in Narra, Palawan shows that the soil are generally
composed of wetland which is typical for the coastal plain, before the onset of intensive rice
cultivation.the plains and ridges developed, in part, as a result of the relatively flat continental shelf that is associated with the trailing edge of the philippine tectonic plate. The region
has been modified by repeated cycles of submersion and emersion by changes in sea-level.
As sea-level rose and fell in response to global changes in climate and movements of the
earths crust, coastal areas were periodically covered by the ocean. Long periods of submersion allowed deposition of marine sediments. Glaciation, and the associated drop in sealevel, results in a seaward shift in the shoreline, and erosion of marine sediments by rivers
and streams. The periodic landward and seaward movement of the shore across the coastal
plain can be seen in the landforms of the coastal plain and the ACE Basin such as relict
dune ridges and marsh plains.
4.2.1 Hydrology
From the local hydrology data, the proposed KIEBC Project is far enough from the any
rivers and the small ponds will be utilized as habitats.there the facilities will not adversely affect the quality of ground water. Below is the hydro geological map of the area surrounding
the project site.
Distance
50 meters
200 meters
PAGE 20
Affected Properties
Distance
50 meters
200 meters
The Clean Air Act outlines the governments measures to reduce air pollution and incorporate
environmental protection into its development plans. Under the Clean Air Act, EPA's Office of
Air Quality Planning and Standards (OAQPS) is responsible for setting standards, also
known as national ambient air quality standards (NAAQS), for pollutants which are considered harmful to people and the environment. The air quality should be based from this standard set by the government.
Based from environment of the area where the project will be constructed, the air
quality of the surrounding area is not polluted and fresh air can be observed. There are no
nearby factories or industrial buildings that will cause air pollution, and also there is a very
light traffic in the area.
4.3.1 Meteorology
Narra has favorable climate to agriculture. The rainy season starts on May and continue up to February. Dry season is experienced during the month of March and April. The
temperature varies, but not much, depending upon the terrain and vegetation.Also, based
on PAGASAs typhoon frequency classification, the project are lies on Type 1 shown in the
figure 3.
PAGE 21
PAGE 22
AURAL EFFECTS
SHOTGUN BLAST
140
UNCOMFORTABLY LOUD
120
EXTREMELY LOUD
100
MODERATELY LOUD
80
QUIET
60
VERY QUIET
60
VERY QUIET
10
JET PLANE
FIRECRACKER EXPLOSION
AMPLIFIED ROCK MUSIC
CROWD NOISE
THUNDER
JACKHAMMER
POWERED LAWN MOWER
TRACTOR
SUBWAY TRAIN
MOTORCYCLE
AIR CONDITIONER (WT)
TRUCK
SINGING BIRDS
NORMAL CONVERSATION
RUSTLE OF LEAVES
LIGHT RAINFALL
WHISPER
As we all know, a some animals causes noise that is sometimes very irritating to the
human ear. The most affected of this noise are the workers then the public. The noise produced by these animals can be because of some factors. One of this is the time of the day; it
is observed that the animals create noise especially during their feeding time.
PAGE 23
MITIGATION/ ENHANCEMENT
MEASURES
A. Pre-Construction Phase
INSTITUTIONAL
PLAN &
RESPONSIBILITIES
B. Construction Phase
1. Land alteration and
modification
KFI / LGU
DA-MAO, Contractor
Contractor, KFI
5. Surface /Groundwater
contamination
DENR
LGU, Contractor, KFI
LGU,KFI
_________
____________
7. Increase Employment
opportunities
8. Noise Generation
9. Traffic
PAGE 24
C. Operational Phase
1. Air pollutants from
vehicular
traffic
KFI, LGU
KFI, LGU
KFI, LGU
Waste segregation
KFI, LGU
5. Increase employment
opportunities
KFI, LGU,Contractor
Scheduling and limitation of visitation Provide separate entrance & exit routes. Allow only light vehicles to enter the site
KFI, LGU,Contractor
7. Impact of environment to
the project
KFI, LGU
8. Revenue generation
C. Abandoment Phase
1. Encroachment of the
Park
2. Deterioration of aesthetic
value
3. Proliferation of invasive
species a. fauna
b.flora
KFI, LGU
PAGE 25
PAGE 26
PARAMETER
MONITORING PLAN
FREQUENCY
RESPONSIBILITY
AIR
Methane Gases
and Hydrogen Sulfide
Annual
Sanitary Engineer
Monthly
Sanitary Engineer
Sanitary Engineer
Sanitary Engineer
NOSE
SOLID WAST
EFFLEUNT
STANDARDS
PAGE 27
PAGE 28
6. ANNEXES
6.1 ORIGINAL SWORN ACCOUNTABILITY STATEMENT OF THE PROPONENT
This is to certify that all information in the enclosed Initial Environmental Examination (IEE)/ Environmental Impact Statement (EIS) is true, accurate, and complete.
Should we learn of any information, which would make the enclosed EIS/IEE inaccurate, we shall bring said information to the attention of the Environmental Management
Bureau of the appropriate DENR Regional Office.
We hereby bind ourselves jointly and solidarity with the preparers for any penalty arising from any misrepresentations or failure to state materials information in the
IEE/EIS.
In witness whereof, we hereby set our hands this13th day of
December,2014 at the Mapua Institute of Technology
Proponent
SUBSCRIBED AND SWORN to before me this 13th day of December 2014,
affiant exhibiting her/his Community Tax Certificate No.1412 issued on June 2014 at
The Municipality of Paraaque
Notary Public
Doc. No. _______
Page NO._______
Book No. _______
PAGE 29
6. ANNEXES
6.2 ORIGINAL SWORN ACCOUNTABILITY STATEMENT OF THE IEE PREPARER
This is to certify that the data on information contained in the enclosed Initial
Environmental Examination (IEE)/Environmental Impact Statement (EIS) is true to the
best of my knowledge and information and that an undertaken in accordance with the
dictate of reasonable and sound judgment. Should I learn of any information, which
would make the enclosed IEE/EIS inaccurate, I shall bring said information to the attention of the Environmental Management Bureau of the appropriate DENR Regional
Office.
I hereby bind myself to answer for penalty that may be imposed for any
misrepresentations or failure to state materials information in the enclosed IEE/EIS
In witness whereof, we hereby set our hands this13th day of
December,2014 at the Mapua Institute of Technology
Accredited IEE/EIS
Preparer
SUBSCRIBED AND SWORN to before me this 13th day of December 2014,
affiant exhibiting her/his Community Tax Certificate No.1412 issued on June 2014 at
The Municipality of Paraaque
Notary Public
Doc. No. _______
Page NO._______
Book No. _______
PAGE 30
PAGE 31
PAGE 32