Professional Documents
Culture Documents
in use in
International
Projects
FIDIC Contracts
in use in
International
Projects
Red
Yellow
Silver
Green
Pink
Gold
Blue
White
FIDIC Contracts
in use in
International
Projects
The Current Suite:
A completely new set of contracts was
released by FIDIC in 1999:
Pink Book
The Multilateral Development Bank Construction Contract
(The Red Book For Development Bank financed projects)
Features provisions on:
- Corruption
- Social utility
- Loan facility
Blue Book
-
White Book
-
Consultancy Agreement
Gold Book
-
FIDIC Contracts
currently in use
by Kier in
Jamaica
FIDIC Contracts
in use in
International
Projects
In all FIDIC Forms the giving of Notices and
further updates by the Contractor is extremely
important
Time-bar issues
Claims should not be ignored financial and
/or time
Prescribed time in Contract for responding to
claims
Clause
Red
Yellow
Silver
Delayed Drawings or
Instructions
1.9
Y+
Errors in Employers
Requirements
1.9
Y+
Rights of Access
2.1
Y+
Y+
Y+
4.6 / 13.3
Y+
Y+
Y+
4.7
Y+
Y+
Unforseeable Physical
Conditions
4.12
Fossils
4.24
Testing
7.4
Y+
Y+
Y+
13.3
Y+
Y+
Co-operation
Setting-Out
Variations
Clause
Red
Yellow
Silver
8.4 (c )
Unforseeable
shortages in
personnel or
goods due to
the
Government
8.4 (d)
8.5
8.9
16.1
Y+
Y+
Y+
Delay,
prevention due
to Employer
Delay by
Authorities
Suspension
instructed by
CA
Suspension by
Contractor
Red
Yellow
Silver
Y+
Y+
Y+
Changes in Law
13.7
Employers Risks
17.4
Y/Y+
Y/Y+
Force Majeure
19.4
Limitations of Liability
Clause 17.6 of the Red, Yellow and Silver Books (similar
obligations):
Joint exclusion of:
- Loss of use of any Works, loss of profit, loss of any
contract or for any indirect or consequential loss or
damage (does not apply payments on termination and
does not apply to indemnities); and
Contract Sum Cap on Contractor liability (does not
apply to indemnities or other listed items, which include
intellectual property rights)
No limitation in case of:
Fraud
Deliberate default
Reckless misconduct
EOT Claims
Clause 20.1 EOT claims by Contractor
Notice to be given by the Contractor within 28 days of
the Contractor becoming aware or when it should have
become aware of the event
Condition precedent to entitlement to an extension of
time:
If the Contractor fails to give notice of a claim within
such period of 28 days, the Time for Completion shall
not be extended, and the Contractor shall not be
entitled to additional payment, and the Employer shall
be discharged from all liability in connection with the
claim.
Contractor bias amendment:
- Remove condition precedent
Clause
Red
Yellow
Silver
1.9
2.1
4.6/8.4(a)
Setting Out
Unforeseeable
Physical
Conditions
4.7
4.12
Fossils
4.24
Testing
7.4
Variations
8.4(a)
Adverse Weather
8.4(c )
Clause
Red
Yellow
Silver
8.4 (d)
8.5
8.9 / 16.1
9.2 / 10.2
Changes in Law
Consequences of
Employers Risks
13.7
17.4
Force Majeure
19.4
Liquidated Damages
Clause 8.7 Delay Damages
Amount stated in Contract Particulars / Appendix to
Tender
Delay Damages apply per day from the Time for
Completion (as may be extended) until the date stated
in the Taking Over Certificate
Possible for parties to cap the amount of Delay
Damages
Exclusive remedy for the Employer for Contractor
delay, except:
- in the event of termination, where the Employer may
be able to recover additional costs
- where the Contractor is required to accelerate the
Works under clause 8.6 for being too slow or having
failed to comply with the Programme
Claims
Red and Yellow Books have the same claims
provisions.
Silver Book is slightly different, with the only
real difference being the involvement or not of
the Engineer
For all claims, notices must follow the required
formalities at Clause 1.3:
In writing
Delivered by hand, sent by mail or courier or
any agreed systems of electronic transmission
Delivered to address set out in the Contract
(unless subsequently advised of a different
address)
Claims
Clause 2.5
Contractor bias amendment:
If the Employer fails to give notice of a claim within
such period of 15 Business Days after the Employer
became aware, or ought reasonably to suspect, or
ought reasonably to have become aware, or should
have become aware of the event or circumstance giving
rise to the claim, then the Employer shall not be entitled
to any amount, payment or extension whatsoever from
the Contractor in respect of such claim and the
Contractor shall be discharged from all liability in
connection with such claim
Golden Rules
- Beware enter in haste, repent at leisure
- Be sure you are in agreement before you
enter the Agreement
- The Contract requires the Contractor to issue
Notices or Time-bars him dont let emotions
cloud the need to issue or receive Notices.
END OF PRESENTATION