You are on page 1of 15

IPTC 14548

FLNG Development: Strategic Approaches to New Growth Challenges


Maneenapang Bunnag, Nunthachai Amarutanon, Saranee Nitayaphan, Manit Aimcharoenchaiyakul, PTT
Exploration and Production Plc.

Copyright 2011, International Petroleum Technology Conference


This paper was prepared for presentation at the International Petroleum Technology Conference held in Bangkok, Thailand, 1517 November 2011.
This paper was selected for presentation by an IPTC Programme Committee following review of information contained in an a bstract submitted by the author(s). Contents of the paper, as
presented, have not been reviewed by the International Petroleum Technology Conference and are subject to correction by the a uthor(s). The material, as presented, does not necessarily
reflect any position of the International Petroleum Technology Conference, its officers, or members. Papers presented at IPTC are subject to publication review by Sponsor Society
Committees of IPTC. Electronic reproduction, distribution, or storage of any part of this paper for commercial purposes without the written consent of the International Petroleum Technology
Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous
acknowledgment of where and by whom the paper was presented. Write Librarian, IPTC, P.O. Box 833836, Richardson, TX 75083 -3836, U.S.A., fax +1-972-952-9435

Abstract
Underneath the ground, the world still left a quarter of its natural gas reserve (approximately 2 billion TCF)
undeveloped or Stranded in offshore. Many gas fields were discovered in many decades ago, but reserve of
those fields could not commercially be justified for the development so they were classified as marginal fields. One
of the most promising solutions known as Floating Liquefied Natural Gas or FLNG is lately growing and foreseen
as potential technical to monetize this marginal gas. We are well aware of the potential in FLNG technology and
consider it as the one of the most important initiatives to lead our organization into target growth strategy.
Many challenges developing FLNG, however, have been found from major players in the past decade. Although
land-based LNG and offshore FPSOs are each successfully proven in operations, combining the two technologies
into a FLNG is complicated and face various technical challenges e.g. safety, ship motion, topside processing, hull
& containment, offloading, integration, and operation. Critical aspects of a FLNG are the space constraints, which
is very limited and required fully attention in order to deliver an inherently safe and a fit for purpose installation.
Altogether, FLNG concept shall fulfill a good balance between efficiency and simplicity to safeguard the reliability of
the facility.
Moreover, commercial aspect of FLNG is also highly challenging. With costly investment, FLNG project shall be
carefully ensured if it is economic viable in every step of the project. The sensitivity of market, LNG price, and
demand & supply shall be reviewed and taken into consideration prior to making the Final Investment Decision
(FID).
Certainly, FLNG initiative still has a lot of queries. However, after years of study and development in all aspects of
floating liquefaction, it finally lead into the key conclusion that today there are no technical issues show stoppers
for FLNG; whereas economic is also promisingly attractive. We believe that we have started off in the right track
and in the right sequence as well as adopting a risk management deciding a FLNG at the right size and the right
technology.

IPTC 14548

1. INTRODUCTION
Floating liquefaction solutions are receiving growing interest lately as they are seen as potential enablers to un-lock
and monetize offshore gas reserves that are currently considered stranded. More than 20 years development work
has been done on FLNG (Floating Liquefied Natural Gas) or also often referred to as LNG FPSO (Floating
Production, Storage and Offloading units for Liquefied Natural Gas) starting from Super Major Oil Companies to a
wide variety of companies i.e. E&P companies, FPSO operating companies, engineering companies, and LNG
shipping companies.
However, there are apparently challenges that have prevented the realization of such a project. Both the
organization of the project and the actual design of an FLNG are considerably more complicated than those of an
Oil FPSO. Although Onshore LNG liquefaction facilities and Offshore Oil&Gas FPSOs are each successfully
proven in operation, combining the two technologies into a FLNG poses new technical, organizational, execution
and economical challenges to the industry that have to be properly addressed to be able to successfully implement
a first of a kind concept. Important considerations in that perspective are listed below:

Safety Aspect on Space Constraints


o How to achieve high level of safety for complex operation with limit space on vessel.
o Cryogenic spilling and handling.
o Overall process integration.
o High potential of unforeseen weight growth and increasing space requirement during design.

Technology Risk/Uncertainty
o New challenge for not only adopting onshore LNG process to fit with limited space on ship, but also
achieving effectiveness, efficiency and high safety level as per standard and design.

Ship Motions
o Mechanical fatigue on structures especially column and cold box.
o Dynamic impact on liquid motions in topside processing including sloshing effect in containment.
o How to design covering ship motion effect on equipment performance.

Offshore LNG Offloading


o LNG offloading in offshore environment with either conventional LNG loading arms or new technology
of cryogenic hoses.

Hull
o How to accommodate heavy load of topside processing which is higher degree that that of FPSO.
o Consideration of hull design for operation and maintenance on filed location, as unit will be on site for
20+ years.
o Redeployment for future re-location.
o Cargo Containment System selection to suit the Offshore Application as well as partial filling limitation
together with sloshing impact solution.

Commercial
o How to predict LNG demand, marketing, and negotiative price.

Because of these above issues, the FLNG concept does not being operational to date yet. Being technically quite
complex and capital intensive, it is essential to have a well-balanced, reputable, strong and experienced team to
develop and execute a project. Since there are many options to be made during selection, such a good team
should have a capability enough to explore and select the best choice for their FLNG. Table 1 below lists the main
system of a FLNG where options have to be made and carefully selected.

IPTC 14548

Table 1 - FLNG Main System

System
Inlet Facilities
Gas Treatment
NGL Separation
Liquefaction Process
Storage Tank Type
Offloading to Carriers
Power Generation
Fuel Gas System
Heating / Cooling Media
Turret and Mooring
system

Component
Slug Catcher, Hydrate Inhibitor, Water-, Condensate Treatment
CO2, H2S, H2O, Hg, Dust Removal
Separation of Natural Gas Liquids (NGLs: C3, C4, C5+): Produces LPG (if required)
LNG Liquefaction (may include N2-Removal)
Type of cryogenic storage tanks for LNG and LPG (if any), Condensate storage tank
Offloading method of products: LNG, LPG (if any), and Condensate
Power for liquefaction compressors and all other duties
Fuel for the power generation system
Compressor Discharge Cooling, Distillation Reboilers
External or internal turret configuration, permanent mooring under cyclonic condition

Anyhow, FLNG is not without any precedence, with the Department of Sustainability, Environment, Water,
Population and Communities (SEWPAC) of Australia recently approving the Shell Prelude FLNG facility (EPBC
reference: 2008/4146). Additionally, the concept of FLNG is somewhat similar to that of Floating Production,
Storage and Offloading (FPSO) facilities operating worldwide. So, it is strongly believe that the successful of FLNG
development is not that unachievable for any longer if we start off in the right track by doing this development in the
right sequence and being developed the vessel in the right size and with the right technology.
2. PROJECT STRUCTURE
PTT Exploration and Production Plc. (PTTEP), a subsidiary of PTT Plc. (PTT), has started developing the FLNG
concept since year 2009. The conceptual study phase was performed during late 2009 and completed in early
2010 in conjunction with Golar LNG. Preliminary Front End Engineering and Design (Pre-FEED) study was done
during Jul 2010-Mar 2011 with GL Noble Denton was engaged as an engineering consultant.
At April 2010, PTTEP and PTT International (PTTI) jointly established PTT FLNG Limited (PTT FLNG) to be
responsible for midstream FLNG development. SBM Offshore (SBM) and Linde Groups Engineering Division
(Linde) have been selected as the technical partners to jointly own and operate the FLNG vessel and a partnership
agreement has been signed in February 2011. Project structure is illustrated below (Figure 1):

Figure 1 - Project Structure

Detailed Pre-FEED study has started in March 2011. Lindes Engineering Division performed a design for the
topsides of the FLNG including gas processing and natural gas liquefaction based on Linde's proprietary natural
gas liquefaction technology. SBM Offshore, based in the Netherlands, is a market leader in the field of Floating
Production, Storage and Offloading units (FPSO) for the oil industry, so they will contribute their mooring system
technology, marine expertise and also be involved in the gas processing on FLNG topsides.

IPTC 14548

Assumed that the gas resources being found meet expectations, the project will enter into front-end engineering
and design (FEED) studies by the end of 2011. The final investment decision (FID) is targeted for the end of 2012,
and first commercial operations for the end of 2016 to early 2017.
3. CASH/MAPLE FLNG DEVELOPMENT
Three gas resources from three groups of fields within three permit areas in the eastern region of the Territory of
Ashmore and Cartier Islands Offshore Australia have been considered as potential feedstock to the FLNG
production system;
1. Cash-Maple field (located within Petroleum Retention Lease AC/RL7);
2. Southern group of fields (located within Petroleum Production Licence AC/L7) comprising Padthaway,
Bilyara, Tahbilk and Montara fields; and
3. Oliver field (located within Petroleum Exploration Licence AC/P33).
The location of these fields is shown below (Figure 2).

Figure 2 - Targeted Gas Fields for FLNG Development

The facility will be located approximately 680 kilometers west of Darwin, Australia, and 200 kilometers southeast of
the Indonesian coastline. The plant will have the capacity to produce approximately 2.3 million tons of LNG per
annum.The water depth at Cash / Maple is approximately 130 metres, 305 metres for Oliver, and 80 metres for
Montara. The development concept has been compared between pipeline to land-based LNG vs. offshore FLNG.
Those three fields are well-suited to a stranded gas field concept i.e. they are not financially viable using traditional
production measures, such as an offshore platform, an export pipeline and onshore liquefaction plant. It is
therefore, according to feasibility study, the most attractive development option is FLNG.

IPTC 14548

4. KEY PARAMETER
For an offshore facility the interdependence of the options is much stronger than onshore because of the limited
plot area. Each key parameter has been investigated to address all risks carefully as per oil and gas business
approaching. On top of that, the integration of all systems to find out any showstoppers has been performed stepby-step. Key parameters that to be considered for offshore LNG are explained in the following sections:
4.1 Field Development
Two possible options were considered for development of those three fields. The illustrate of each option is shown
in Figure 3 and 4 respectively;
1. Relocation from each field from time to time. If this option is preferred, each field will be developed
independently and the FLNG facility will relocate to each group of fields as required at the end of field life.
2. Pipeline gas from the fields to a central location which allows more flexibility in terms of blending the gas
and daily operating flexibility. If this option is preferred, the FLNG facility will be located at a central point
(i.e., at the Cash-Maple field) with approximately 63 km of pipeline required to connect it to the Oliver field
and 88 km of pipeline to connect it to the Southern group of fields. During operations, regular pigging of the
lines or injection of chemical or Naphtha may be required if wax formation is predicted. Regular pigging
would require dual flowlines or a subsea pig launcher at the field location.

Figure 3 Field Development Option Relocation

IPTC 14548

Figure 4 Field Development Option - Pipeline

The relocation option results in simpler topsides facilities and lower overall CAPEX. However, relocation option has
lower economically recoverable reserves and the optimum point to move the vessel from one field to the next will
result in gas being left in the ground. This needs to be balanced against the higher pressure losses for the pipeline
options, which could result in lower recoveries for the remote fields.
The gas delivery profile gives short plateau periods for relocation option, followed by decline and then no
production when the vessel is moved from one field to the next. This profile is not ideal for long term LNG sales
agreements and may result in a lower LNG sales price.
4.2 Gas Field and Market
The required LNG specification dominates FLNG topside complexity. The Higher Heating Value (HHV)
specification for the LNG together with the hydrocarbon part of the feed gas composition determines the NGLSeparation (NGLs: C3, C4, C5+). A very rich gas (high C2, C3, C4s, and C5+ -content) with a market that
requires lean LNG will require a pre-treatment process that also produces LPG and condensate. The leaner the
LNG Spec, the more NGLs have to be separated. Therefore, when the feed gas composition is so lean that the
LPG (C3 + C4s) can remain in the LNG, or if the market accepts a rich LNG, this is strongly preferred, as without
LPG production and storage, the topsides are much simpler and safer.
The LNG markets require various LNG specifications depends on local facilities of that country. For UK, the lean
LNG specification is required while rich LNG specification is allowed for Japan market. LPG and Ethane
management are the key parameters for design consideration in order to meet LNG specification. For Cash/Maple
FLNG, the LNG specification has not reached the conclusion yet. It is subjected to continue discussion with PTT,
who is considered as a potential LNG offtaker.
4.3 Design Approach & Capacity
The design of the FLNG starts with Field Specific then extends to Generic. Redeployment is the major
attractiveness of FLNG. Hence, first to start, the design consideration is focused on prospect field specific (s), then
extend its gas envelops such as maximum CO2 & N2 content, rich gas, and lean gas well fluid to cover either
regional or worldwide stranded gas fields (s). With Generic design, however, higher investment is expected. The

IPTC 14548

balancing between Generic design approach and investment shall be addressed based upon economic point of
view and business strategy of developer.
The FLNG production capacity follows from the field reserves size, normal field production period, and market
requirement. For Cash/Maple FLNG development, 2.3 Mtpa LNG product has been set as base case according to
potential recoverable resources and economic results with supporting from marketing point of view.
4.4 Topside Processing Design
FLNG shall be designed as a fully stand-alone system for offshore operation, making it independent from any
infrastructure and eliminating the need for new pipelines, platforms, etc. The topsides facilities have been designed
for the extreme cases of the design condition envelope, which implies that the overall dimensions of modules,
equipment, pipe sizes, weights, utilities, and power consumption are all based on these conservative conditions.
Hydrocarbon fluid from wells will be separated into 3 phases i.e. gas, liquid and water. Hydrocarbon gas is
processing further to condense into liquid phase at atmospheric pressure. Cryogenic process is applied with
operating temperature -161 C. With extremely low temperature, any of substances that become solid at low
temperature shall be removed in Gas Treatment system prior to cryogenic system.
A high level indicative block diagram highlighting the main process systems is provided in Figure 5. In summary,
FLNG topside processing will be comprised of:
A. Gas Treatment: To remove any of substances that become solid at liquefaction condition (i.e. CO2, Water,
and Hg). Because of the robust specification of inlet gas to liquefaction process, gas treatment has
stringent duty to remove any contaminants about 500-4600 times compare to pipeline specification.
B. Liquefaction: To liquefy hydrocarbon gas to be liquid at atmospheric pressure by means of cryogenic
processing.
C. Condensate Treatment: To treat condensate prior to sending to storage
D. Water Treatment: To treat water prior to overboard
E. CO2 Re-injection vs. Venting: If desired from an environmental point of view, the unit can sequestrate and
re-inject CO2 and water.

Figure 5 - FLNG Topside Processing System

IPTC 14548

A. Pre-Treatment
The inlet separation facilities are designed to separate the bulk liquids in the feed gas stream, such as hydrocarbon
condensate and any free water, including slugs, which are determined by water depth and temperature. Subsea
design and flow assurance calculations will give the size of the slug catcher and determine the requirement of a
continuous hydrate inhibitor injection. Provision should be made for a MEG injection & regeneration system, which
is required for possible pipeline tie-backs from remote fields and also for the feed gas compression will be installed
in late field life after pressure decline phase.
The non-hydrocarbon parts of the reservoir fluid composition determine the Gas Treatment part. Removal of CO2
and H2S is normally done by one of the well-known amine absorption processes (formulated MDEA). However,
appreciable concentrations of H2S will give safety and disposal problems. Gas downstream of gas sweetening will
be routed to a gas dehydration system consisting of two to three molecular sieve vessels in a duty/regeneration
type arrangement. Mercury removal is fixed bed adsorption; mercury guard bed. Inerts, like nitrogen, will carry to
liquefaction system and flash as End flash gas which to be further used as a fuel gas. This step is even increase
the energy consumption of liquefaction, but it is much simpler and cheaper than that of installing Nitrogen rejection
system upstream of liquefaction.
After some works on technology screening, there were two potential removal systems taking into consideration i.e.
1) Amine only and 2) Hybrid (Membrane then following by Amine system). Results from the study shown that the
Hybrid system requires more space and weight, and then Amine only option was selected as base case for design.
Anyhow, keep bearing in mind that the results with different design basis may resulted on different result.
B. Liquefaction Process
The most important independent choice for an FLNG is the selection of the liquefaction process which was driven
by the following criteria:

Safety
Track record in onshore LNG service
Relative simplicity and ease of start-up & operation
Offshore operability and maintainability
Balance between (economical reasons) and (technical-complexity reasons)
Adjustable to variations in gas composition
Reliability
Efficiency

The main choice is between two fundamentally different processes; liquid refrigerants and expander. Expander
processes (Figure 6 and 7) use gaseous nitrogen (Nitrogen expander) or feed gas (Niche Process) as refrigerant.
All large (baseload) plants use liquid refrigerants, either as single or dual mixed refrigerant (Figure 8 and 9). Most
developers for small scale FLNG (less than 2 Mtpa) prefer expander processes, however, liquid refrigerant is better
choice for bigger capacity. Many studies shown that the most suitable liquefaction process for the range capacity of
2-3 Mtpa is Single Mixed Refrigerant (SMR), while Dual Mixed Refrigerant (DMR) are selected for a large scale
FLNG (> 3Mtpa).
For a small scale FLNG (less than 2 Mtpa), the expander processes would be preferable in that:
Liquid refrigerant processes require higher hydrocarbon inventory, while expander processes using
nitrogen or feed gas as refrigerant, which is also only in the gas phase in the expander loop. This is highly
important in safety aspect especially offshore operation.
The liquid refrigerant processes have a higher equipment count since the refrigerant is required to
produced and stored separately onboard FLNG. Moreover, the nature of their two-phase process requires
liquid-gas separation in several stages.
Expander processes are not sensitive to motion and have no maldistribution problems as they are only in
the gas phase.
Expander processes can retain the refrigerants (gases) on shutdown in the process at settle-out condition
resulted in faster re-starting-up.

IPTC 14548

Figure 6 - Dual Nitrogen Expander Processes

Figure 8 - Single Mixed Refrigerant Processes

Figure 7 - Niche LNG Processes

Figure 9 - Dual Mixed Refrigerant Processes

Single Mixed Refrigerant (SMR), on the other hand, is considered to be a good selection for a medium scale FLNG
(2-3 Mtpa) by the reason of:
Higher efficiency than expander processes.
Lower overall equipment count for medium scale FLNG (2-3 Mtpa) than expander processes. This is due
to limitation of expander processes in capacity per train, so duplication of train is required for higher
capacity.
Lower rotating machinery (compressor-expander), so expected lower downtime for shutdown and
maintenance.

It seems that the grey area is around at 2 Mtpa in which both technologies, Expander (N2 or Niche) and SMR are
feasible. Comparison among candidate technologies for 2 Mtpa is shown in Table 3. Overall technical complexity
and safety studies have to be done along with life cycle economic analysis in order to judge the most suitable
liquefaction process in each case by case.

10

IPTC 14548

Table 2 - Main Liquefaction Processes for around 2 Mtpa

C. Condensate Treatment
The condensate is extracted from inlet facilities and is stabilized in a stabiliser column to achieve the specification;
RVP 10 psia (as Australias specification). Liquid condensate is subsequently sent to the storages. The overhead
product of the stabilization is re-compressed and route back to the inlet system.
D. Water Treatment
Produced water is being treated in conventional system to achieve specification (30 ppm of oil in water). The
system consists of hydrocyclone vessels and a degassing tank. Oil in water content is measured before being
routed overboard. If the water is off-spec, it can alternatively be routed to a slop tank, where it will settle and
further separate and eventually be pumped overboard when acceptable specification.
E. CO2 Re-Injection vs. Venting
From economical point of view, even venting case has to pay along with some amount of CO2 tax, the project
value is much better than CO2 sequestration via reinjection which require high CAPEX for CO2 compression and
pipeline system. It is therefore recommended that CO2 venting should be carried forward as the base case.
4.5 Utilities (Topside and Marine)
A. Power Generation and Driver Selection
The main power consumers of any LNG plant are the large compressors. The power plant will be an order of
magnitude greater than for oil FPSO. There are actually two choices: direct or indirect (electrical) drive and the
choice of the prime driver. Steam turbine and gas turbine drivers are screened options for further evaluation
of liquefaction compressor driver. While the potential options for power generation system are steam turbine
generator, gas turbine generator, and Dual Fuel Diesel Engines (DFDE). Pros and Cons of each type are
described herewith:
1. Steam Turbine driver and generator are a very robust system, high availability, reliability, safely, and can
handle high N2 content in fuel gas. Anyway, very large steam plant is required (large boilers, large stream
pipes) with high sea water demand and large condensers located at deck level.
2. Gas Turbines, especially modern aeroderivatives, have very good efficiencies but they have a limitation in
flame size and expected low availability. Moreover, the system is also sensitive to the fluctuations of fuel
gas quality / heating value.

IPTC 14548

11

3. Dual Fuel Diesel Engines requires very lean fuel gas and can put in hull to safe deck space. But limitation
to only small size resulted in the utilization of several machines to achieve power requirement.
Evaluation and selection of the power generation system will include equipment, installation and life cycle cost,
footprint, possibility to install in the hull, heat available from exhaust WHRUs, etc. Optimization of the power
generation system must be done in parallel with evaluation and selection of the liquefaction compressor driver and
optimization of the heating medium system.
B. Other Utilities
For a gas turbine driven power plant, the choice of heating medium is between hot oil, steam or hot water. The
selection of heating medium is interdependent with power generation and liquefaction driver selection. The final
answer is differing from case by case.
For example, if gas turbine is selected, a closed hot water system might be a good solution for a FLNG comparing
to a steam system because it has less equipment, much simpler in operation, and does not require a continuous
supply of fresh water and treatment chemicals. Hot water might be competitive compared to hot oil as piping and
heat exchangers are smaller because of the higher heat capacity and lower viscosity of water. Also in view of
safety, water would be preferred over hot oil.
On the other hands, if steam turbine is selected, design heating medium by using steam is practical solution.
The main heat exchangers in LNG processes are coolers or condensers in the discharge of the compressors.
These high duty heat exchangers will, on a FLNG, not be air-coolers because of the required large plot area, high
weight (high design pressure), and impair the FLNG stability.
For cooling water, there is a difficult choice between direct seawater cooling and an indirect closed fresh water
loop. An indirect cooling water system gives the possibility to control the inlet and outlet temperatures of the heat
exchangers and so stabilize the processes that depend on cooling and reduce fouling problems. Further the
intercoolers can simply be spared for maintenance and cleaning.
End Flash Gas, Boil off Gas (BOG) and vapor return from the LNG carriers during offloading will be either
compressed to the fuel gas system or to the inlet of the cold box when the amount of gas exceeds the fuel gas
requirement. Boil off gas compressors used onshore are usually of the reciprocating type. Because of their large
size and weight, it is on an FLNG advantageous to use centrifugal compressors for BOG.
Fuel gas will be a mixture of Boil off gas, End flash gas (from flashing the LNG to storage pressure), possibly gas
from the NGL Separation and raw feed gas. Gas fields with high nitrogen content aggravate this problem as the
nitrogen is significantly enriched in the Boil off gas. The fuel gas system usually includes a mixing drum to dampen
the changes in fuel gas quality, and it might even require a nitrogen removal unit to avoid flaring of lean BOG gas.
All relief valves from hull and topsides have to be connected to central relief systems. For safety and environmental
reason they should be flared, not vented. The height of the flare is determined by the maximum allowable radiation
and gas dispersion in case of relief.
4.6 Hull, Storage and Offloading
A. Hull
Although the key benefits of the conversion are lower CAPEX and faster schedule, but it has been limited to 1.0
Mtpa capacity due to limited storage capacity and challenges regarding available deck space and limits of safety.
Moreover, at 1.0 Mtpa production capacity the conversion concept has lower value than the higher capacity new
build vessels across the range of reserves considered and cannot capture the significant value of reserves upside.
The OPEX for conversion i.e. maintenance & repair is high and more time than new build. Therefore, the new build
options should be carried forward as the base case.
The new-build FLNG is of the complete double hull. A range of topside weights and configurations have been
assessed obtain maximum motions and accelerations for hull, containment system and topsides. Design life of the

12

IPTC 14548

hull is 25-30 years and special attention is given to hull & tank design in terms of strength, fatigue, and coatings. A
sizeable width is advantageous, as this will reduce the roll and thus gives a greater operating window.
B. Storage (Containment)
Three main types are well-known and applicable for FLNG containment system (Figure 10). With the FLNG being
permanently moored at one location for possibly up to 20+ years without dry-docking, it is vital that the containment
system is robust, reliable and repairable, without having to cease production and leave the site.
Containment tanks for a FLNG will be either Self-Supporting Prismatic tanks (SPB) that are not sensitive to
sloshing during partial filling but are expensive and potential to structural fatigue, or strengthened Double-Rows
Membrane tanks that will withstand sloshing up to a certain sea state, while Spherical Moss-type that leaves less
deck-space for the topsides is only suitable for very small scale FLNG. The selection of FLNG containment will be
also limited by heavy weight of topside as the containment is required to support the load weight from topside.
With limitation of deck space, even extension in length or width, Moss spherical is considered not justify for
moderate size FLNG and has been ruled out from further study. Only flat deck SPB or Double-Membrane is
recommended to be further studied in Pre-FEED stage.
The total volume of the LNG storage capacity should be also carefully considered. It shall be a larger than the
volume of the designed LNG carrier with available space for continue production if delay or bad weather prevents
offloading.

Figure 10 - LNG Containment System

C. Offloading and LNG Carrier


The production capacity of the FLNG and the distance to the market (the regasification terminal) determines the
required number and size of LNG carriers. Metocean data of the location will determine the hull movements of both
FLNG and carrier. From these follows the choice of offloading method. Offloading can be done by marine side-byside loading arms up to a significant wave height of 2.5 m which is proven solution and has been used in industry
practice.
Although side-by-side LNG offloading is assumed the base case, provisions will nevertheless be made for a
tandem LNG offloading system. As such, the system can be tested and proven in operation, providing comfort that
such a system can successfully be applied on a FLNG in harsher environmental condition where tandem LNG
offloading would be the only means of offloading.

IPTC 14548

13

4.7 Turret and Mooring


The selection of the mooring system is very dependent on the local environmental conditions (either the water
depth or the extreme design conditions) and purpose of using. The internal turret will be considered as high safety
but less of hull space for turret compartment. The external turret will be given the optimum of hull space for cargo
containment. The permanent mooring is mainly selected in benign water, and the disconnectable mooring is
applicable for harsh water and relocation purpose.
The FLNG will be turret with weathervaning mooring system to enable freely moving around turret (by swivel) and
applicable for side by side or tandem offloading. Spread moored will only be possible in very sheltered waters but
limit the offloading operation. The choice between disconnectable and permanent turret depends on metocean
data in which areas where there is a possibility of hurricanes or icebergs occur, it might be required to select a
disconnectable turret. When disconnect, the FLNG will be freely sailed as ship powered by thrusters. Moreover,
thrusters are also used for heading control during offloading operation
4.8 FLNG Layout and 3D Schematic
As abovementioned, FLNG development has faced a challenging on design to adopt onshore LNG to offshore
operation within a very limited space. The major issue that FLNG development team has to be addressed and
solving is how to fit complex system on ship, but also maintain high level of safe operation.
To sort out the key showstoppers, the back-and-forth thinking is applied. At early of project development, topside
system requirement on space is estimated then put into ship space with preliminary layout. Next step,
brainstorming of interdiscipline was conducted to investigate the risks and record for requirement of design
changing. Several cycle of working were performed to establish robust deck space requirement with proper
mitigation of all risks.
The layout has been developed based on maximizing inherent safety without compromising concept. With
limitation of deck space, gray area for layout arrangement is still located in some cases. There is consequently
affect to increase risk of adjacent area which is unavoidable. If there is any risk remaining, the properly safety
device shall be put in place to mitigate all risk to an acceptable level.
Here below briefly explain the Basis of FLNG Layout (Figure 11):
-

Layout basis is started on internal turret, which is the weathervaning position of the vessel. The
accommodation shall be located at the bow in order to retain accommodation upwind of any gas leaks on
the topsides deck and riser for most of the time.

Process utilities without gas (instrument air and nitrogen storage, cooling water, heating medium) and
power generation are placed between living quarters and turret to enhance as a safety gap from high
potential ignition source and the personnel living area.

From turret to the aft side, it started with inlet facilities, gas pre-treatment, NGL extraction, and then
liquefaction.

The emergency flare stack is located aft of the vessel and is of a sufficient height and incline to avoid
excessive radiation on the deck or at the LNG carrier bridge. For safety reasons, the flare stack has to be
as far as possible apart from the accommodation, and preferably downwind of it, to avoid gas emissions to
process area and accommodation.

14

IPTC 14548

Figure 11 - PTTEP FLNG Layout

CONCEPTUAL STUDY

A conceptual study phase was performed during late 2009 and completed in early 2010. This work was conducted
in conjunction with Golar LNG. The prime objective of this study was to carry out a preliminary assessment of the
overall economic viability of the project and to narrow down the number of options to be taken into the next stage
of development. The work has focused on making four key decisions regarding the configuration of the offshore
development and in particular:
1. To establish the optimum production capacity recognizing uncertainty in the gas resources volumes.
2. To evaluate the benefits of relocation of the FLNG vessel to each field in turn or pipelining the gas to a
single FLNG location.
3. To evaluate the merits of conversion of an existing LNG tanker or new built hull.
4. To determine the benefits of CO2 sequestration or venting to atmosphere.
The study options and results from the conceptual study are summarized in Table 3:
Table 3 - Study Options for FLNG Conceptual Study

FLNG Vessel
Design Capacity
Field Development
CO2 Disposal
CO2 Removal Process
LNG Containment Type

Study Option
New build vs. Conversion
1.0 / 1.5 / 2.0 Mtpa
Pipeline vs. Relocation to each field
Venting vs. Re-Injection
Amine only vs. Hybrid (Membrane + Amine)
Moss vs. SPB vs. 2row Membrane

Pre-FEED

Cash/Maple FLNG Pre-FEED stage has been started carrying out with main objectives to more refine the options
and identify the key design requirements to deliver an inherently safe and a fit for purpose installation. The
selected base case will be finally developed as completed design and sizing of all systems with 25% cost
estimation.
The topsides facilities will be designed to cover all worst cases of the design condition envelope. The key given
parameters have been carried out from conceptual study as described above. The main study options are
summarized below in Table 4:

IPTC 14548

15

Table 4 - Study Options for FLNG Pre-FEED

Liquefaction
LPG Removal
Driver Selection
Power Generation
Selection
LNG Storage
Turret
Mooring
Field Development
Condensate stabilisation
Mercury removal
Acid Gas Removal
Molecular Sieve (Gas
Dehydration)
Heating Medium

Study Option
Dual N2 Expander vs. SMR
Onboard FLNG vs. Onshore
Steam Turbine vs. Gas Turbine
Steam Generator vs. Gas Turbine Generator
SPB vs. DoubleRow Membrane
Internal turret vs. External turret
Disconnectable vs. Permanent
ReVisit Pipeline vs. FLNG Relocation
Flash column vs. Stabilizer
Upstream vs. Downstream of CO2 removal
Single vs. two stages configuration
Optimum number of Drier
Hot oil vs. Steam vs. Hot water

CONCLUSION

With a few years of studies from both brainstorming in-house and numerous learning and exchange idea with other
FLNG developers, Cash/Maple FLNG is now become more robust in both terms of technical and commercial
aspects. No more remaining technical issues show stoppers are foreseen to date. One of the most important from
now on is the sequence of execution in which such large development does not allow for any short cuts. It is
strongly believes that we have started off in the right track by doing this development in the right sequence and
being develop the vessel in the right size and with the right technology in order to get not only to successful of the
FLNG but also secure the energy demand to support Thailand country.

You might also like