You are on page 1of 26

Sleipner Gas Condensate Field

Field development Case Study


History, on-going cases and lessons learned

1 - Classification: Internal

2011-05-25

The Sleipner Field

2 - Classification: Internal

2011-05-25

The Sleipner Field

3 - Classification: Internal

2011-05-25

Sleipner Vest Field


Phase 1 HP production
Phase 2 LP Production
Phase 3 - Pre-compressor modus
Phase 4 SLB compression

Phase 5 2008 -------

4 - Classification: Internal

2011-05-25

Sleipner Vest - Phase 1 HP production


(1996)
Process limitations
Inlet separator at 105bar (high back-pressure for wells) and declining well
pressures
2 export compressors

PUD Installation of a Compression platform at SLB in 2002


Further field development aim : Reduce back-pressure of wells and maximize
production at lowest possible investments

5 - Classification: Internal

2011-05-25

6 - Classification: Internal

2011-05-25

7 - Classification: Internal

2011-05-25

Sleipner Vest - Phase 2 LP production


(2002)
Inlet separator at 85bar
Modifications based on studies and testing at lower operational pressure
Effect on CO2 removal, maintain gas and condensate spec
2 export compressors, compressor rebundling (increased head)

Increased process cooling (new inlet cooler and new wet gas cooler)
Inlet separator modifications (New inlet cyclones, new double perforated
plate, new V-mesh, new mesh pad and outlet cyclones)

Scrubber modifications

8 - Classification: Internal

2011-05-25

9 - Classification: Internal

2011-05-25

Separator internals- Sleipner T inlet separator

Good performance and no reported separation problems


Liquid load/dump rate from down stream vessels constant as inlet pressure has
been reduced and volume flow increased

10 - Classification: Internal

2011-05-25

11 - Classification: Internal

2011-05-25

12 - Classification: Internal

2011-05-25

13 - Classification: Internal

2011-05-25

Sleipner Vest - Phase 3 Precompression


(2004)
Modified export compressor A Compress gas from inlet separator
Installed new precompressor scrubbers
Lay-out/area
Weight issues

Selected Gasune compact scrubbers


Tie-in of Alfa Nord sub-sea wells

14 - Classification: Internal

2011-05-25

15 - Classification: Internal

2011-05-25

SLT precompressor scrubber Gasunie design


2x50% design
20MSm3/d/60barg
High k-Faktor (0,9)
ID=932mm
Good performance
and no compressor
problems.
Mechanical damage
on scrubber
internals

16 - Classification: Internal

2011-05-25

Sleipner Vest - Phase 4 SLB compression


(2008)
New compression module on SLB (2008)
Inlet cooler, gas scrubber, compressor and condensate pumps.
El driven/VSD compressor ( approx 9 MW available el power)
Low k-value Compressor scrubber. Traditionally designed

Normally not manned operation

17 - Classification: Internal

2011-05-25

18 - Classification: Internal

2011-05-25

SLB Scrubber
K-value<0,1
Operational pressure, 6020barg
Max gas 18 MSm3/d

ID=3500mm
Good performance and no
compressor problems
Inspection in 2012 detected
some minor damage on
cladding (fabrication issues)

19 - Classification: Internal

2011-05-25

20 - Classification: Internal

2011-05-25

Sleipner Vest - Phase 5 2012 -- Gear revamp on SLB compressor (2012)


Revamp of SLT precompresssor to allow 20barg inlet pressure (2014)
Revamp of SLT recompressor and modification of 2nd stage separator (20132014)

Revamp of SLT export compressor (2014)


New tie-in candidates
Rerouting of Alfa Nord

21 - Classification: Internal

2011-05-25

Sleipner East Field Development phases


Similar pressure development as SLV reduce back pressure of wells
Utilise existing equipment, modify and reroute piping as reservoir pressure drops

22 - Classification: Internal

2011-05-25

23 - Classification: Internal

2011-05-25

Sleipner A Field Development phases


Phase 1
Both inlet separators operate at high pressure (approx 100barg)
Phase 2
Inlet separator A operate at high pressure (100barg)
Inlet separator B operate at low pressure (35barg), gas from inlet B is routed to
suction side of 2nd stage recompressor
Phase 3
Both inlet separators operated at low pressure (35barg). Gas from both separators
routed to suction side of 2nd stage recompressor
Phase 4 10 bar
Gas from inlet separator B routred to suction side of 1.st stage recompressor
- Inlet separator A at 35 bar, but wells on manifold A routed to B manifold via x-over

- Phase 5 Gudrun
- Gudrun on inletseparator A at 90 barg through processing train A
- Own production on inletseparator B at 10 barg

24 - Classification: Internal

2011-05-25

25 - Classification: Internal

2011-05-25

Thank you
Presentation title
Presenters name
Presenters title
E-mail address, tel: +00 00 00 00

www.statoil.com

26 - Classification: Internal

2011-05-25

You might also like