Professional Documents
Culture Documents
STRUCTURES:
FOUNDATION :
1.
2.
3.
Disposition of foundation pedestals w.r.t. longitudinal axis of boiler and reference axis.
4.
5.
6.
Pitch distance of foundation pedestal bolts on both the axes and its diagonals.
(Tolerance : pitch distance : 3 mm, diagonal difference : 5 mm max.)
STRUCTURES :
1.
2.
3.
4.
5.
Orientation of columns. Check for match mark, elevation mark, column No., splice
size etc.
6.
7.
8.
Alignment of first piece of column with horizontal beams and vertical bracings
(Tolerance: Position w.r.t. reference axis: 5 mm ; elevation : 5 mm).
9.
10.
11.
12.
13.
14.
16.
Verticality of columns before and after ceiling girder erection, at every 5M and at
column erection joints. (Tolerance : 1mm / M; Max. 25mm).
17.
Centre line of ceiling girders marked w.r.t. longitudinal axis of boiler transferred from
ground level to top. (Tolerance : 12 mm max.)
18.
19.
Verticality of all main columns (wherever possible) immediately after drum lifting and
compare with previous values.
20.
ELECTROSTATIC PRECIPITATOR
FOUNDATION :
1.
2.
3.
4.
1.
2.
3.
4.
5.
Location & orientation of sliding supports w.r.t. fixed foot (Tolerance : 5mm).
6.
Top level of support (slide supports and fixed foot) (Tolerance : 5mm).
7.
8.
9.
10.
11.
Verticality of all columns of inlet, outlet and intermediate frames in both X & Y
directions (Tolerance : 1mm / M, 10mm Max).
12.
13.
Ensure the centre line matching of X81 columns, X01 bearings and X48 columns
before erection of casing assembly (maximum permissible deviation : 5 mm)
From the base plate, transfer the centre line to bearing bottom plate.
From the bearing bottom plate, transfer the centre line to X48 column centre.
CASING :
1.
2.
Verticality of walls.
3.
4.
5.
6.
7.
Locking of bearings.
8.
9.
10.
11.
Marking of gas path centre line (GPCL) on roof beams on top and bottom flange
(Tolerance : 2mm).
12.
1.
2.
3.
Straightness of frame.
4.
5.
6.
7.
Distance between centre of emitting system suspension point to first hook with
collecting electrodes frames (Tolerance : 3mm).
8.
9.
10.
2.
3.
4.
5.
6.
7.
8.
Holders are in one line for top, middle and bottom frame part.
9.
Verticality and diagonals of emitting frame work assembly for frame part middle and
bottom (Tolerance Verticality 5mm Max.; Diagonals : 10mm Max.).
10.
1.
2.
3.
Distance between collecting electrodes to vertical beam (on front & rear).
4.
5.
6.
Clearance between shock bar edge to shock bar guide (Min.40 mm).
7.
8.
Clearance between collecting electrodes and hopper (vertical) deflection plate in the
vertical plane (40 mm).
9.
1.
Record sweep / camber for vertical beam, vertical stay and supporting beam.
2.
3.
4.
Distance between emitting suspension screen tube edge and deflection plate (shield)
(Tolerance : 5mm).
5.
Distance between emitting rapping shaft screen tube edge and deflection plate
(Tolerance : 5mm).
6.
7.
8.
9.
10.
Clearance between the emitting frame and collecting electrode (Tolerance : 5mm).
COLLECTING RAPPING SYSTEM :
1.
Clearance between shaft axis to gable wall - front / rear (Tolerance : Min.350mm).
2.
Distance between centre line of rapping shaft to centre of shock bar (310 mm).
3.
Shock pad face and shaft axis to be in the same vertical plane (to be in the same line
for effective rapping).
4.
5.
Ensure phase angle of hammers and direction of rotation before welding of sleeves.
6.
7.
Alignment of plain bearing and proper seating of rapping shaft in the bearing with
lock plate.
8.
Ensure water level throughout the length of each shaft assembly (use shims if
required).
9.
Set ring position and completion of welding with pre-heating using recommended
welding electrode.
10.
11.
1.
2.
Distance between centre line of rapping shaft to hitting point on shock beam
(Tolerance : 5mm).
3.
4.
Alignment of bearing & proper seating of rapping shaft in the bearing with lock plates.
5.
Ensure water level throughout the length of each shaft assembly (use shims if
required).
6.
Set ring position and completion of welding with pre-heating using recommended
welding electrode.
G D SCREEN RAPPING SYSTEM :
1.
2.
Distance between centre line of rapping shaft to hitting point at rapping bracket.
3.
4.
5.
Alignment of bearing and proper seating of rapping shaft in the bearing with lock
plate.
6.
Ensure circumferential groove on the coupling matches with the edge of clutch.
7.
8.
Set ring position and completion of welding with pre-heating using recommended
welding electrode.
INLET & OUTLET FUNNELS AND HOPPERS :
FUNNELS :
1.
Elevation.
2.
1.
Elevation.
2.
3.
Ensure correct orientation of hopper manhole door location w.r.t. gas flow direction
for each row of hoppers.
4.
Ensure welding of matching channel with ridges and casing assembly horizontal
channels.
ELECTRICAL PANELS :
1.
2.
3.
4.
5.
6.
Check for end covers, cooling fans, terminal boxes and oil plugs of rapping motors.
PRESSURE PARTS :
DRUM :
1.
2.
3.
4.
Drum suspension U rod dimensions and freeness of nuts. (Tolerance : arm length, arm
to arm distance : 25 mm; twist between limbs : 10 mm max.)
5.
Disposition of drum axis from centre line of furnace (Tolerance : 1 mm/ M, 5 mm max.)
6.
7.
Spacing of washer plate w.r.t. boiler and drum axis. (Tolerance 1 mm/ M, 5 mm max.)
8.
9.
10.
11.
Axial disposition of drum centre w.r.t. longitudinal axis of boiler. (Tolerance : 5 mm)
12.
12.
Minimum projection of threads above the nuts in the drum suspension rods.
13.
14.
1.
2.
3.
Cleanliness of headers.
4.
Bow in headers (Tolerance: 1mm / M, Max. 8mm for membrane panel headers and
Max. 10mm for other headers).
5.
Header scarffing line (Tolerance: 2mm Max. for membrane panels and 4mm Max. for
others).
6.
Completion of supports.
7.
Alignment of headers and elevation, horizontality and distance from reference axes.
(Tolerance : 3mm).
PANELS :
1.
Identification of panels.
2.
Width, diagonals & location of openings of the panels (Tolerance : Panel width : + 2mm
or 5mm. Diagonal difference (D1 ~ D2) : 10mm Max.).
3.
4.
Completion of supports.
5.
6.
7.
Alignment of water walls (Tolerance : Furnace Width & Depth : +10mm or 15mm;
Diagonal difference 20mm Max.).
8.
Ensure welding completion of baffle wall prior to the erection of SH / Eco coil assemblies.
9.
Ensure that furnace walls are studded and refractory lined upto 1200 mm from Distributor
Plate.
COILS AND TUBES :
1.
2.
3.
4.
5.
1.
2.
Clearance between end coil assembly and water wall side walls (Tolerance : 10mm).
3.
4.
Clearance between coil ends and front water wall / upper baffle wall
(Tolerance : 20mm).
5.
1.
2.
Clearance between end coil assembly and water wall side walls (Tolerance : 10mm).
3.
4.
Clearance between coil ends and upper baffle wall / rear water wall
(Tolerance : 20mm).
5.
1.
2.
3.
Orientation of DC pipes.
4.
5.
Alignment of supports.
6.
1.
2.
3.
Alignment of tubes.
4.
Completion of supports.
BUCKSTAYS :
1.
2.
3.
4.
5.
6.
1.
2.
3.
4.
5.
6.
Servicing of valves.
7.
8.
1.
Welding of insulation hooks / studs and attachments to pressure parts completion before
hydraulic test.
2.
3.
4.
Completion of air test of the system. (Max. Test Pressure : 2 Kg. / Cm2 g)
5.
6.
7.
1.
Elevation and location of lug plates for supporting Distributor Plate (DP) assembly
(Tolerance 3 mm).
2.
Soundness of welding of lug plates with W.W. Tubes (Random LPI 10 %).
3.
4.
5.
Soundness of welding of scalloped bar with W.W. Tube and DP (Random LPI 10 %).
6.
Elevation and routing of coal feed air line from header to DP connection
(Tolerance 5 mm).
7.
8.
9.
Soundness of welded joints in the pipe line to avoid fuel / air leaks.
10.
11.
12.
Centre line of bolt holes of matching faces of rectangular / circular flanges (applicable for
site drilled flanges) (Tolerance : 1.5 mm).
Minimum clearance between duct and adjacent member for insulation and thermal
expansion.
10
11
12
13
14
15
16
17
Welding completion for supports, suspensions, guides, internal stays, studs and tapping
points.
18
19
20
Clearance between blade tip to tip and between frame and blade tip.
Orientation of dampers.
Alignment of actuators.
10
Ensure the correct position of drive side shaft collar with the flap pulled towards drive
side.
GATES :
Orientation of gates.
Seal damages.
Alignment of actuators.
Ensure removal of flats, transport clamps between the bellows of the expansion joint.
Ensure cover plates direction of flow and welding completion of cover plate.
AIR & GAS TIGHTNESS TEST :
Air and gas tightness test for complete assembly of ducts, dampers, gates and expansion
joints.
INSULATION :
Completion of insulation for ducts, hot air / gas dampers, gates and expansion joints.
Ensure the following are erected / installed only after completion of hydraulic test and
steam blowing for oil lines.
- Orifices
- Flow meter
- Trip valves and 3 way valves (oil system)
Flow direction of control valves, traps, non-return valves and trip valves for oil lines.
The HEA ignitor flexible cable hanging / or U form without twist and strain.
Circuit length.
OIL COMPARTMENT :
1
Check the following after keeping the nozzle tips in 0 degree position.
a) Oil burner length and position.
b) HEA ignitor tip location.
c) Scanner viewing head position.
Tightening of cap-nut with spray plate upto the required torque value.
Disposition of diffuser shroud with respect to the wind box nozzle outlet plane after
mounting.
RADIAL FAN :
FOUNDATION :
1.
2.
Elevation.
3.
1.
Alignment of base plates and bearing pedestals (Horizontality of bearing pedestals within
0.04 mm / M with respect to the fan centre line).
2.
3.
4.
Pre-assembly of spiral casing and ensure completion of seal welding for gas tightness
and welding of distance bolts with casing.
5.
6.
7.
8.
Elevation and horizontality at the parting plane of bottom half of spiral casing at four
corners.
9.
10.
Ensure proper seating of the locating groove in the shaft flange with the impeller.
11.
Torque tightening of bolts for shaft, conical cover plate, flange and impeller.
12.
Gap between impeller & shaft flange and impeller mating face (0.05 mm feeler should
not go).
13.
14.
15.
Ensure 80% colour matching between bearing housing and the bearing pedestals.
16.
17.
18.
Radial
19.
20.
21.
Adjustment of duct supports of suction and discharge ducts to avoid loading / pulling of
fan.
22.
Alignment of coupling with motor & fan and ensure tightness of bolts fixing coupling with
shaft.
23.
Alignment of motor & fan after successful trial run and dowell all the areas as specified in
the drawing.
24.
AIR PREHEATER :
1
Supporting beam spacing w.r.t. boiler axis and air pre heater axis.
(Tolerance : 1 mm / M ; Max. 5 mm).
11
12
13
14
Ensure duct loads, thermal expansion loads etc. are not transmitted to air pre heater
blocks.
15
16
Ensure seal plates are welded with tube plate assembly after fixing the duct.
17
Ensure seal welding all around between bolt & nut and bolt, nut and split plate.
18
Completion of guide vanes and splitter vanes at the inlet and outlet of air ducts for
uniform distribution of the air across the air pre heater and to avoid flow stratification.
19
20
21
Completion of castable refractories at gas inlet of each block to a height of 150 mm.
PIPING :
1
Verticality of pipelines.
Ensure sufficient gap around the pipelines with structure / wall to accommodate the
insulation thickness and expansion provision during operation.
Ensure erection of boiler feed re-circulation NRVs after chemical cleaning of pipelines.
10
11
12
Cleanliness of piping.
13
14
Identification of weld joints and maintenance of records indicating number of joints, heat
treatment carried out and NDE results.
15
16
17
Completion of NDE.
Note : MPI / LPI on completed welds shall be carried out.
18
Completion of PWHT.
19
20
21
22
23
24
25
Ensure the waterwall, superheat and roof tubes regions, all tubes are in one plane before
application of castable refractories.
Ensure the availability of the asbestos packings and for proper closing and opening operation
for manholes, pee holes and elliptical doors before fixing.
Ensure the replacement of coir ropes by asbestos packing ropes in al the door assemblies
while erection.
Ensure the liner plates of manhole, peephole, observation doors and elliptical doors are filled
with castable refractories and proper curing of the same.
Ensure proper expansion provisions for castable refractories and pourable insulations.
Ensure the scalloped bars are cut at the top with opening for pouring of castable refractories
and then weld scalloped bars.
Ensure the openings on the top of scalloped bars in seal boxes are closed with patch plate
after curing of the castable refractories.
Ensure the provision of correct size openings in the refractories provided in the seal boxes.
10
Ensure the erection of gas distribution baffles in the second pass simultaneously along with
the pressure parts.
11
12
Ensure the slotted holes connections given for expansion shall not be welded (applicable for
enclosures).
13
Ensure no tampering / hammering of the skin casing after fixing in position so as to avoid any
damage / crack in already cast areas with pourable / castable refractories.
14
15
Ensure the gap between the two adjacent fins is not more than 4 mm before the application of
castable refractories.
16
17
Ensure completion of welding of all the items under fixing components and skin casing with
pressure parts before hydraulic test. Subsequently establish the quality of weld by hydraulic
test.
REFRACTORY & INSULATION MATERIALS :
ii)
iii)
iv)
v)
vi)
Hooks / studs welding on pressure parts using correct length of hooks / studs.
vii)
Ensure that the life of refractory materials is within the expiry date.
Ensure the coating of bituminous paint for tube surfaces and any other metal surfaces which
are embedded in or in contact with castable refractories / pourable insulation.
Ensure all aluminium sheets and M.S. Ribbed sheets are coated with two coats of black
bituminous paint or inner side.
6
7
Ensure proper iron parts and casing supports are fixed at required pitches and in straight
rows for sheeting works.
10
Ensure the outer casings are not in direct contact with any hot surface (like stiffeners, lifting
hooks etc.).
11
Ensure fixing of neoprene strips or aluminium paint coating wherever aluminium sheets are
envisaged over the retainers.
12
Ensure the provision of outer casing sheets immediately after erection of insulation to avoid
rain water entry.
13
Ensure segmental sheeting assembly for bends, elbows etc. following the same profile of
Ensure overlapping of sheeting edges are facing down against water flow direction for water
proof arrangements for vertical portion.
15
Ensure sheets and seams are overlapping on sides for effective water proofing in horizontal
portion.
16
17
Ensure proper pitch on either directions and maintaining of tightness for self tapping screws.
OUTER CASING / FIXING COMPONENTS :
Ensure all the fixing components are welded on pressure parts (water wall) issued under
PGMA 31-010 and 37-010 for fixing outer casing.
Clearance for boiler expansion between outer casing and structural members, floor etc.
Ensure all MS ribbed sheets are coated with two coats of black bituminous paint on inner
side, after application of red oxide primer.
Ensure the use of proper drill bit for making holes to fix self tapping screws.
4
5
Ensure all the openings around access doors, observation doors, instrument tappings etc. are
properly finished / terminated with plain sheets and fixed adequately with self tapping screws.
Ensure outer sheet casings are provided immediately after the insulations are fixed (this will
prevent rain water entry).
Ensure the gap between wall and ribbed casing is not more than as given in the drawing.
Ensure all fixing components are erected on buckstay beams before fixing the outer casing.