Professional Documents
Culture Documents
All cost data given hereunder are to be used for Preliminary Estimate and Cost Checking
only.
Conversion Fees
Valuation Fees
Registration of Q.T
Quit Rent
1/41
Note :
1.0
2.0
(low density)
(high density
110,000.00/acre
240,000.00/acre
a.
CIVIL INFRASTRUCTURE
(Lower Range)
(Higher Range)
RM
RM
1,500.00
4,500.00
b.
Earthworks
22,000.00
70,000.00
c.
16,000.00
25,000.00
d.
6,000.00
10,000.00
e.
6,000.00
10,500.00
f.
14,000.00
25,000.00
g.
2,500.00
3,000.00
II
BULK SERVICES
h.
9,000.00
14,000.00
I.
6,000.00
11,000.00
j.
8,000.00
12,500.00
22,000.00
25,000.00
3,000.00
6,500.00
III
M & E INFRASTRUCTURE
k.
l.
m.
Streetlighting
2/41
4,000.00
6,500.00
120,000.00
223,500.00
Oxidation Ponds
Concrete Reservoir
Streetlighting
7
8
(Road Kerbs)
(Scupper Drains)
(Road Markings)
RM 9.00 / F.S
RM 110,000 / No.
Double Chamber
RM 145,000 / No.
9
I)
Single Chamber
RM80,000
RM140,000
Double Chamber
RM110,000
RM180,000
Bridges
Overhead Taxiway Bridge for Aircraft
49.90M x 61.0M (Source : Subang
Airport Project)
ii)
RM3,500 / M2
Pedestrian Bridge
58'6" x 10'0" (Source : Taman Melati Project)
iii)
iv)
RM1,400 / M2
RM2,000 / M2
RM3,000 / M2
3/41
A.
RM
Football Field (including Rugby)
110,000
(RM 10 / M2)
Hockey Field
48,000
(RM 10 / M2)
Basketball Court
25,000
(RM 50 / M2)
Volleyball Court
15,000
(RM 35 / M2)
Tennis Court
45,000
(RM 65 / M2)
9,000
(RM 35 / M2)
Netball Court
8,000
(RM 8 / M2)
Softball Field
110,000
(RM 10 / M2)
Handball Field
65,000
(RM 9 / M2)
Running Track
260,000
(RM 58 / M2)
Swimming Pool
95,000
4/41
A.
Cinema Equipment
Manufacturer : KLAUS
1
G61 - 170
G62 - 170
AIRPORTS
special installation)
RM2,500 / M2
Avio-bridges
RM1,600,000 / No.
RM1,700,000 / No.
RM25,000 / M
RM40,000 / No.
RM15,000 / M
Hangar
RM2,200 / M2
CONVENTION HALLS
RM20,000
RM15,000
RM1,500
RM36,500
5/41
A.
(1)
Figures represent fixed price competitive tenders including all building works,
installation of services, and minimal external works, but excludes piling,
fitting out and professional fees.
(2)
The costs per square meter shown are those for areas measured overall (between
external wall faces) and should be used for preliminary estimates only. Average
conditions are assumed, cmitting any adjustments or variations in ground
conditions and the like. All buildings are assumed as having no basement.
Residential *
RM / M2
400.00
470.00
470.00
650.00
490.00
700.00
590.00
720.00
640.00
780.00
660.00
950.00
690.00
920.00
380.00
620.00
620.00
900.00
890.00
1110.00
900.00
1400.00
1350.00
1600.00
1,700.00
and
Above
480.00
590.00
560.00
650.00
640.00
690.00
1,450.00
1,800.00
1,950.00
and
1,700.00
2,100.00
460.00
520.00
500.00
620.00
720.00
800.00
440.00
560.00
Above
(air-conditioned)
Industrial * (Typically steel framed with industrial cladding)
6/41
Hotels *
RM / M2
1,600.00
2,200.00
4 - Star Hotel
2,000.00
2,600.00
2,500.00
and
above
600.00
* (inclusive of F, F & E)
(see also page BCC / 3)
Medical *
General Hospitals
1,650.00
Educational Establishments
Colleges - Administration Block
520.00
530.00
550.00
650.00
500.00
600.00
560.00
620.00
Primary Schools
380.00
500.00
Secondary Schools
490.00
610.00
350.00
400.00
450.00
550.00
700.00
1,000.00
650.00
.
Car Park Buildings
General
Amphitheatre
and
above
1,840.00
2,420.00
1,500.00
1,850.00
1,000.00
1,400.00
1,100.00
1,400.00
7/41
Istana Hotel
a) Preliminaries
5% - 8%
b) 5 - Star Hotel
Sheraton Hotel, KL
a) 485 Modules
b) GFA - 501, 185 FS
c) Cost / Module (inclusive of F, F & E & Millwork)
RM350,000
d) F, F & E
e) Millwork
GOLF COURSES
8/41
Air-conditioning Installation
RM 350 / m2
RM 1,100 / m2
65m2
RM 450 / m2
Sterilizing Equipment
9/41
RM 400 / m2
B. MISCELLANEOUS INFORMATION
COST OF INTELLIGENT BUILDING IN MALAYSIA
Types
IB Related Cost
132.70
44.70
33.69%
145.40
57.40
39.48%
151.40
63.40
41.88%
4. Conventional Building
120.00
32.00
26.67%
Notes :
IB related components for Conventional building include lift, electrical system, fire alarm and CAV.
IB related components for Intelligent building include BAS, wiring system (trunking/raised floor), lift, security,
Electrical system, fire alarm, VAV and miscellaneous i.e subtle design changes which changes which need to be
made to make a building intelligent.
a) Wiring Management :- #
10.00%
2.00%
12.50%
17.50%
3.00%
1.70%
d) Electrical System
1.30%
e) Lift
1.30%
f) Security
0.60%
0.20%
h) Miscellaneous
0.80%
Average Total Cost (%) :
Notes :
# Average cost
10/41
18.90%
Unit
Rate
(RM)
Intelligent Building
Sq.ft
3.50
2.30
Sq.ft
23.00
15.00
Sq.ft
32.00
21.00
13.00
16.50
2.00
500.00
10.50
e) Electrical System
9.00
10.50
f) Lift
9.00
0.70
g) Security
1.20
1.00
1.00
32.00
80.70
Point
i) Miscellaneous
Notes :
Total :
11/41
FEES
Residential
For the 1st 10,000 sq.ft. at the rate of RM40/- per 1,000
Partf thereof of floor area. For the next 5,000 sq.ft at the
RM20/- per 1,000 sq.ft or part thereof of floor area; and
At the frate of RM10/- per 1,000 sq.ft or part thereof of floor
Mixed Development
RM1,000.00
RM1,000.00
Sales of Plans
RM500.00
12/41
Conversion Fees
* per Acre
* per Acre
Lembaga Air
RM600/Unit
RM300/Unit
RM750/Unit
RM900/Unit
Valuation Fees
RM 30,000.00 (Sum)
*
*
*
*
Quit Rent
13/41
Low Cost
(Selling Price RM 50,000 and below)
RM150.00
Medium Cost
(Selling Price RM 50,001 to RM100,000)
RM500.00
RM1,000.00
High Cost
(Selling Price exceeding RM200,000)
RM2,000.00
Note : Residential development by individuals or private landowners up to a maximum of 4 units, the rate of ISF
contribution shall be 50% of the rates stated above.
b.
NON-RESIDENTIAL DEVELOPMENT
LOCATION
RATE
Within CPA
Note : Floor space for determining the ISF rate does not include floor space for car-parking.
* ISF calculations (for Non-Residential Development purpose) are calculated to the nearest RM500.00
14/41
1.2
RESIDENTIAL
COMMERCIAL/LIMITED COMMERCIAL
a) Commercial & Office complexes (except cinema & bowling alleys)
c) Bowling alleys
2 cps per lane
1mcps per lane
d) Conventional shops
(not exceeding 2 lots)
1.3
INDUSTRIAL
All industrial
1.4
EDUCATIONAL
a) Creche, Kindergarden, Nursery
15/41
1.6
1.7
RELIGIOUS
1 cps per 75 m2
SPORTS
a) Public swimming pool
INSTITUTION
a) Hostels & youth club
b) Hospital
d) Welfare Homes
2.2
2.3
Dimension of Stall
Minimum stall width
Minimum stall length
Minimum stall length for lateral
2.4m (7 10)
4.8m (15 9)
6.0m (19 8)
Dimension of Accessway
Minimum Clear width
Aisle width
Parking Angle
90
60
45
30
Lateral
6.0m (19 8)
4.8m (15 9)
4.2m (13 9)
3.7m (12 2)
3.7m (12 2)
16/41
Residential
5 persons/unit
Cinema
0.1 persons/seat
School
0.1 persons/pupil
Hotel
4.4 persons/room
Hospital
3 persons/bed
Shopping Complex
1.3 persons/1,000 sq ft
For each water closet, slope sink, urinal, budget, bath or shower
RM5.00
(b)
RM2.00
(c)
For every Septic Tank and Inhofe Tank the charge per cubic ft
RM0.40
(d)
RM25.00
2. For each amendment plan to an approved plan where no addition is made to the total number of appliances shown in the
approved plan, one-fifth of the relevant fees specified in paragraph 1, subject to a maximum of RM25.00
3. For each amendment plan to an approved plan where no addition is made to the total number of appliances in the
amendment plan exceeds that in the original approved plan, fees specified in paragraph 1 in respect of the additional
appliances in additions to or one-fifth of the fees payable in respect of the approval of the original plan, whichever is less, shall
be payable.
4. For a series of identical sanitary installations in a number of the building of the same design when plans are submitted for
approval at the same time, a deduction of the fees specified in preceding paragraph shall be made on the following basis :a)
Full fees
b)
c)
*Provide that half of the fees set out above shall be charged in respect of plans for sanitary installations in buildings used
exclusively as places for religious worship, school or for charitable purposes
5. In all cases where work has been commenced before plans have been approved a fee equal to ten times that specified in
paragraph 1 shall be charged. The payment of which fee shall not except any person from being prosecuted by the Datuk
Bandar
17/41
SIZE OF DEVELOPMENT
2 acre
4 acre
60
80
100
30
35
40
As for column 1
2 badminton courts or
equivalent
A gymnasium, 2
squash courts
A gazebo area
A launderette and a
management office
Minimum carpark
Note :
Nett site area means the area of the site excluding areas for public road, public road widening reserves, school,
drainage reserves, septic tank site, TNB substation site and any other portions that are to be surrounded to any
government authority.
Communal open space means the gardens and landscaped area within the development accessible to all
occupants of the condominium housing development and include pavilions, shelters, swimming pools, sand pits,
fountains and other open recreational facilities, but excludes taken areas taken up by private driveways, carparks,
electrical sub-stations, septic tanks and other services.
18/41
Industrial Building
(a)
Residential
(a)
Total Cost
RM
180.00
250.00
48.00
225.00
45.00
45.00
10,549,105.00
61.00
160.00
78.00
127.00
42.00
10,176,760.00
7.00
355.00
204.00
20.00
82.00
(iii) Tower
1
Foundation, piling & basement work
2
Structural frame
3
Internal & External Finishes
4
Services
5
Preliminaries
Total Construction Cost
65.00
223.00
210.00
158.00
79.00
(iv)
(b)
Cost/M2
RM
6,055,544.00
49,582,246.00
1,637,000.00
164.00
129.00
51.00
219.00
91.00
218.00
14,170,663.00
19/41
Residential
(c)
(d)
Cost/M2
RM
22,286,497.00
79,150.00
Offices/Commercial
(a)
(c)
9.00
270.00
142.00
219.00
60.00
58.00
88.00
257.00
105.00
56.00
25.00
26.00
(b)
Total Cost
RM
20/41
95.00
194.00
86.00
36.00
2.00
46.00
199.00
563.00
363.00
452.00
15.00
138.00
175,000,000.00
199.00
491.00
190.00
537.00
16.00
61.00
98,199,000.00
Offices/Commercial
(d)
(e)
Cost/M2
RM
Total Cost
RM
167.00
403.00
65.00
471.00
8.00
126.00
180,051,000.00
169.00
129.00
32.00
85.00
8.00
3.00
257.00
586.00
244.00
154.00
51.00
37.00
1,072.00
831.00
255.00
191.00
131.00
38.00
1,446.00
520.00
1,025,000.00
12,700,000.00
11,700,000.00
4,200,000.00
1,470,000.00
16,245,000.00
30,070,000.00
60,944,000.00
498.00
176.00
171.00
151.00
Total Group Cost
21/41
498.00
Retail
Cost/M2
RM
(a)
(b)
(c)
225.00
191.00
42.00
53.00
97.00
485.00
21.00
29,514,369.00
115.00
244.00
8.00
9.00
31.00
108.00
3.00
9,437,118.00
303.00
157.00
18.00
61.00
75.00
14.00
164.00
41.00
1,300,000.00
1,300,833.00
Hotels
(a)
Total Cost
RM
17,000,000.00
7,900,000.00
822
25,419.00
9,484.00
127,308.00
16,171.00
22/41
Hotels
(b)
(c)
(d)
(e)
(f)
(g)
(h)
822.00
25,419.00
9,484.00
127,308.00
16,171.00
597.00
25,223.00
13,353.00
92,677.00
8,902.00
318.00
6,000.00
2,941.00
49,167.00
1,334.00
45,000.00
25,000.00
199,004.00
20,359.00
1,070.00
40,000.00
24,000.00
174,548.00
8,398.00
1,014.00
50,000.00
30,000.00
188,814.00
15,434.00
Ramada (5-Star)
515 Modules
1 GFA/Module in F.S (exclude Carpark)
2 FF & E / Module
3 HOE / Module
4 Total Construction Cost/Module
5 Carparking Cost/Module
1,416.00
60,000.00
40,000.00
236,835.00
21,359.00
23/41
Hotels
(i)
Sheraton Hotel, KL
485 Modules
1 GFA/Module in F.S (exclude Carpark)
2 FF & E / Module
3 HOE / Module
4 Total Construction Cost/Module
Cost / m2
55,000.00
39,000.00
350,000.00
General
(a)
(b)
(c)
(d)
47,800,000.00
2,155.00
90.00
304.00
123.00
152.00
180.00
2.00
776,000.00
168.00
248.00
111.00
337.00
158.00
470,000.00
341
127
80
31
221
38
6
103
24/41
General
(f)
Cost / m2
(g)
64.00
266.00
80.00
46.00
100.00
528.00
270.00
25.00
1,739,800.00
4,801,102.00
5,127,458.00
272,388 *
73,000,000.00
RM/m2 ; GFA
(Enclosed Area)
(h)
25/41
RM/m2 ; GFA
(Gross Area)
3,938.00
5,199.00
4,935.00
75,000,000.00
23.00
17.00
156,194,000.00
171,813,000.00
94,497,000.00
396,888,000.00
Location :
Kuala Lumpur
Building Analysis :
GFA :
12,551 m2
ELEMENT
Cost/m2 GFA
(RM)
% Cost/m2 GFA
(RM)
10.08%
SUBSTRUCTURE
Piling
1,063,718.00
84.75
1,174,199.00
93.55
11.13%
2,237,917.00
178.31
21.21%
1,356,304.00
108.06
12.86%
0.00
0.00
0.00%
1,095,192.00
87.26
10.38%
SUPERSTRUCTURE
Frame
Upper Floor
Roof
Staircase
4,975.25
0.40
0.05%
External Wall
94,878.00
7.56
0.90%
107,355.00
8.55
1.02%
439,650.00
35.03
4.17%
Internal Doors
31,005.00
2.47
0.29%
3,129,359.25
249.33
29.66%
FINSHES
182,491.00
14.54
1.73%
329,478.00
26.25
3.12%
68,641.00
5.47
0.65%
External Finishes
13,230.04
1.05
0.13%
593,840.04
47.31
5.63%
100,000.00
7.97
0.95%
SERVICES
Sanitary Appliances
3,453.05
0.28
0.03%
Plumbing Installation
58,880.00
4.90
0.56%
423,000.00
33.70
4.01%
Electrical Installation
1,697,200.00
135.22
16.09%
480,000.00
38.24
4.55%
Communication Installation
52,004.00
4.14
0.49%
80,000.00
6.37
0.76%
2,794,537.05
222.65
26.49%
8,855,653.34
705.57
83.95%
Site work
803,793.79
64.04
7.62%
Drainage
246,237.26
19.62
2.33%
External Services
79,050.61
6.30
0.75%
Ancillary Buildings
5,000.00
0.40
0.05%
Recreational Facilities
Group Element Total
PRELIMINARIES
TOTAL (LESS CONTINGENCIES)
26/41
1,134,081.66
90.36
10.75%
559,370.00
44.57
5.30%
10,549,105.00
840.50
100.00%
Location :
Building Analysis :
GFA :
142 m2
ELEMENT
Cost/m2 GFA
(RM)
% Cost/m2 GFA
(RM)
10.87%
SUBSTRUCTURE
8,200.00
57.73
4,350.00
30.62
5.77%
12,550.00
88.35
16.63%
11,300.00
79.55
14.98%
7,100.00
49.98
9.41%
SUPERSTRUCTURE
Frame
Upper Floor
Roof Structure
Roof Finish
190.00
1.34
0.25%
Staircase
1,800.00
12.67
2.39%
External Wall
5,100.00
35.90
6.76%
6,750.00
47.52
8.96%
2,400.00
16.90
3.18%
Internal Doors
1,900.00
13.38
2.52%
36,540.00
257.24
48.43%
FINSHES
5,400.00
38.02
7.16%
4,600.00
32.38
6.10%
2,100.00
14.78
2.78%
External Finishes
2,800.00
19.71
3.71%
14,900.00
104.89
19.75%
SERVICES
Sanitary Appliances
1,900.00
13.38
2.52%
Plumbing Installation
4,000.00
28.16
5.30%
Electrical Installation
2,000.00
14.08
2.65%
Lift Installation
Communication Installation
10
7,900.00
55.61
10.47%
71,890.00
506.09
95.28%
Site work
3,400.00
23.94
4.51%
Drainage
160.00
1.13
0.21%
External Services
Ancillary Buildings
Recreational Facilities
3,560.00
25.08
0.05%
PRELIMINARIES
3,700.00
26.06
4.91%
79,150.00
531.16
100.00%
27/41
Location :
Building Analysis :
GFA :
100,631 m2
Total Element Cost
(RM)
ELEMENT
A
SUBSTRUCTURE
Cost/m2 GFA
(RM)
% Cost/m2 GFA
(RM)
19,994,154.00
198.00
11.43%
19,994,154.00
198.00
11.43%
SUPERSTRUCTURE
Frame
38,845,346.00
386.02
22.20%
Upper Floor
1,408,057.00
13.99
0.80%
Roof
2,692,536.00
26.76
1.54%
Staircase
407,819.00
4.05
0.23%
External Wall
800,000.00
7.95
0.46%
9,600,000.00
95.40
5.49%
1,134,461.00
11.27
0.65%
Internal Doors
1,762,377.00
17.51
1.01%
56,650,596.00
562.95
32.37%
FINSHES
4,110333.00
40.85
2.35%
5,882,391.00
58.46
3.36%
4,540,907.00
45.12
2.59%
5,600.000.00
55.65
3.20%
External Finishes
16,400,000.00
162.97
9.37%
36,533,631.00
363.05
20.88%
936,223.00
9.30
0.53%
2,661,184.00
26.44
1.52%
30,000.00
0.60
0.02%
SERVICES
Refuse Disposal
14,000,000.00
139.12
8.00%
Electrical Installation
9,800,000.00
97.39
5.60%
3,700,000.00
36.77
2.11%
10,000,000.00
99.37
5.71%
Communication Installation
1,000,000.00
9.94
0.57%
Special Installation
2,020,000.00
20.07
1.15%
2,009,100.00
19.97
1.15%
10
333,107.00
3.31
0.19%
45,553,391.00
452.68
26.03%
159,667,995.00
1,586.67
91.24%
1,476,412.00
14.67
0.84%
1,476,412.00
14.67
0.84%
13,855,593.00
137.69
7.92%
175,000,000.00
1,739.03
100.00%
PRELIMINARIES
TOTAL (LESS CONTINGENCIES)
28/41
Location :
Building Analysis :
GFA :
73,051 m2
Total Element Cost
(RM)
ELEMENT
A
SUBSTRUCTURE
Cost/m2 GFA
(RM)
% Cost/m2 GFA
(RM)
19,000,000.00
260.09
19.35%
700,000.00
9.58
0.71%
SUPERSTRUCTURE
Frame
Upper Floor
Roof
Staircase
540,000.00
7.39
0.55%
External Wall
12,850,000.00
175.90
13.09%
1,040,000.00
14.24
1.06%
0.61%
Internal Doors
Group Element Total
600,000.00
8.21
1,150,000.00
15.74
1.17%
35,880,000.00
491.16
36.54%
FINSHES
3,330,000.00
45.58
3.39%
3,330,000.00
45.58
3.39%
3,400,000.00
46.54
3.46%
External Finishes
3,800,000.00
52.02
3.87%
3,620,000.00
189.73
14.41%
3,620,000.00
49.55
3.69%
SERVICES
1,500,000.00
20.53
1.53%
14,720,000.00
201.50
14.99%
Electrical Installation
9,170,000.00
125.53
9.34%
3,750,000.00
51.33
3.82%
6,860,000.00
93.91
6.99%
Communication Installation
200,000.00
2.74
0.20%
Special Installation
860,000.00
11.77
0.88%
1,840,000.00
25.19
1.87%
300,000.00
4.11
0.31%
39,200,000.00
536.61
39.92%
92,560,000.00
1,267.06
94.26%
1,189,000.00
16.28
1.21%
1,189,000.00
16.28
1.21%
4,450,000.00
60.92
4.53%
98,199,000.00
1,344.25
100.00%
PRELIMINARIES
TOTAL (LESS CONTINGENCIES)
29/41
Location :
Building Analysis :
GFA :
138,563 m2
Total Element Cost
(RM)
ELEMENT
A
SUBSTRUCTURE
SUPERSTRUCTURE
Frame
Upper Floor
Roof
Staircase
External Wall
7
8
Cost/m2 GFA
(RM)
% Cost/m2 GFA
(RM)
23,077,000.00
166.55
12.82%
23,077,000.00
166.55
12.82%
33,019,000.00
238.30
18.34%
233,000.00
1.68
0.13%
185,000.00
1.34
0.10%
14,710,000.00
106.16
8.17%
308,000.00
2.22
0.17%
6,356,000.00
45.87
3.53%
Internal Doors
1,100,000.00
7.94
0.61%
55,911,000.00
403.51
31.05%
FINSHES
1,052,000.00
7.59
0.58%
2,686,000.00
19.38
1.49%
2,500,000.00
18.04
1.39%
External Finishes
2,776,000.00
20.03
1.54%
9,014,000.00
65.05
5.01%
682,000.00
4.92
0.38%
SERVICES
2,190,000.00
15.81
1.22%
17,200,000.00
124.13
9.55%
Electrical Installation
13,898,000.00
100.30
7.72%
5,260,000.00
37.96
2.92%
18,081,000.00
130.49
10.04%
Communication Installation
1,860,000.00
13.42
1.03%
Special Installation
4,975,000.00
35.90
2.76%
1,809,000.00
13.06
1.00%
65,273,000.00
471.07
36.25%
153,957,000.00
1,111.10
85.51%
1,069,000.00
7.71
0.59%
1,069,000.00
7.71
0.59%
PRELIMINARIES
17,414,000.00
125.68
9.67%
CONTINGENCIES
7,611,000.00
54.93
4.23%
180,051,000.00
1,299.42
100.00%
30/41
A
1
2
3
B
1
C
1
2
3
4
5
6
D
1
2
3
4
E
1
2
3
4
5
6
F
1
2
3
4
G
1
2
3
4
H
1
2
3
4
5
6
7
8
9
I
1
2
31/41
62.00
53.91
115.92
11.94%
10.38%
22.33%
4,155,096.00
4,155,096.00
228.59
228.59
44.03%
44.03%
11,404.80
97,642.92
26,414.50
15,302.17
150,764.39
0.63
5.37
1.45
0.84
8.29
0.12%
1.03%
0.28%
0.16%
1.16%
260,940.02
11,692.08
272,632.10
14.36
0.64
15.00
2.77%
0.12%
2.89%
55,025.46
119,024.37
174,049.83
3.03
6.55
9.58
0.58%
1.26%
1.84%
163,548.88
250,067.36
126623.24
17,335.84
557,575.32
9.00
13.76
6.97
0.95
30.67
1.73%
2.65%
1.34%
0.18%
5.91%
10,000.00
10,000.00
0.55
0.55
0.11%
0.11%
300,000.00
520,000.00
660,000.00
300,000.00
75,000.00
100,000.00
1,955,000.00
16.50
28.61
36.31
16.50
4.13
5.50
107.55
3.18%
5.51%
6.99%
3.18%
0.79%
1.06%
20.72%
17,000.00
38,000.00
55,000.00
0.94
2.09
3.03
0.18%
0.40%
0.58%
9,437,117.64
519.18
100.00%
Job Title :
Location :
Building Analysis :
GFA :
15,533 m2
ELEMENT
Cost/m2 GFA
(RM)
% Cost/m2 GFA
(RM)
SUBSTRUCTURE
WBLFF
0.00
0.00
0.00%
SUPERSTRUCTURE
Frame
467,000.00
30.07
37.63%
Upper Floor
Roof Structure
Roof Finish
Staircase
External Wall
1,000.00
0.06
0.08%
133,000.00
8.56
10.72%
Internal Doors
49,000.00
3.15
3.95%
650,000.00
41.85
52.38%
FINSHES
23,000.00
1.48
1.85%
53,000.00
3.41
4.27%
40,000.00
2.58
3.22%
External Finishes
116,000.00
7.47
9.35%
42,000.00
2.70
3.38%
SERVICES
8,000.00
0.52
0.64%
Air
160,000.00
10.30
12.89%
Electrical Installation
90,000.00
5.79
7.25%
65,000.00
4.18
5.24%
10,000.00
0.64
0.81%
333,000.00
21.44
26.83%
1,141,000.00
73.46
91.94%
25,000.00
1.61
2.01%
PRELIMINARIES
55,000.00
1.61
2.01%
CONTINGENCIES
150,000.00
3.22
4.03%
1,371,000.00
79.89
100.00%
TOTAL
32/41
Job Title :
Location :
Building Analysis :
GFA :
8,854 m2
ELEMENT
Cost/m2 GFA
(RM)
% Cost/m2 GFA
(RM)
7.44%
SUBSTRUCTURE
673,000.00
76.01
WBLFF
812,00.00
91.71
8.98%
1,485,000.00
167.72
16.42%
12.05%
SUPERSTRUCTURE
Frame
1,090,000.00
123.11
Upper Floor
Roof Finish
145,000.00
16.38
1.60%
Roof Structure
155,000.00
17.51
1.71%
Staircase
60,000.00
6.78
0.66%
External Wall
85,000.00
9.60
0.94%
360,000.00
40.66
3.98%
176,000.00
19.88
1.95%
Internal Doors
121,000.00
13.67
1.34%
2,192,000.00
247.57
24.24%
FINSHES
340,000.00
38.40
3.76%
299,000.00
33.77
3.31%
280,000.00
31.62
3.10%
External Finishes
60,000.00
6.78
0.66%
979,000.00
110.57
10.82%
230,000.00
25.98
2.54%
543,000.00
61.33
6.00%
SERVICES
Electrical Installation
4
5
620,000.00
70.02
6.86%
1,200,000.00
135.53
13.27%
245,000.00
27.67
2.87%
260,000.00
29.37
2.71%
60,000.00
6.78
0.66%
60,000.00
6.78
0.66%
2,988,000.00
337.47
33.04%
7,644,000.00
663.34
84.52%
Site Works
310,000.00
35.01
3.43%
Drainage
385,000.00
43.48
4.26%
External Services
20,000.00
2.26
0.22%
Ancillary Buildings
10,000.00
1.13
0.11%
Recreational Facilities
675,000.00
76.24
7.46%
1,400,000.00
158.12
15.48%
1,021.00
100.00%
PRELIMINARIES
470,000.00
9,514,000.00
33/41
Job Title :
Location :
Building Analysis :
GFA :
2,595 m2
ELEMENT
Cost/m2 GFA
(RM)
% Cost/m2 GFA
(RM)
SUBSTRUCTURE
187,700.00
72.33
17.43%
WBLFF
60,500.00
23.31
5.62%
248,200.00
95.65
23.05%
SUPERSTRUCTURE
Frame
251,400.00
96.88
23.34%
Upper Floor
Roof Finish
80,500.00
31.02
7.48%
Roof Structure
13,100.00
5.05
1.22%
Staircase
6,600.00
2.54
0.61%
External Wall
16,600.00
6.40
1.54%
44,400.00
17.11
4.12%
81,700.00
31.48
7.59%
Internal Doors
11,500.00
4.43
1.07%
505,800.00
194.91
46.97%
FINSHES
104,900.00
40.42
9.74%
32,600.00
12.56
3.03%
64,400.00
24.82
5.98%
External Finishes
22,500.00
8.67
2.09%
224,400.00
86.47
20.84%
SERVICES
Sanitary Appliances
47,500.00
18.30
4.41%
Electrical Installation
45,400.00
17.50
4.22%
92,900.00
35.80
1.38%
1,071,300.00
412.83
92.23%
Site Works
Drainage
5,600.00
2.16
External Services
Ancillary Buildings
Recreational Facilities
Group Element Total
PRELIMINARIES
0.52%
5,600.00
2.16
0.52%
414.99
100.00%
119,900.00
1,196,800.00
34/41
APPENDIX 1
MATERIAL QUANTITIES FOR MORTAR
Table One : Mixers of (0.305 x 0.305 x 0.610) m gauge boxes capacity
Measure
Mortar Types
1
1
Cement
Lime
1
Cement
2
Lime
9
Sand
0.0126
0.0252
0.1132
0.0188
0.0188
Pounds
21
15
31
12
Litres
6.5
13.5
60
10
Kilograms
10
7.5
15
m3
6
Sand
1
Cement
Lime
3
Sand
0.0377
0.0094
0.1132
63
10
60
20
60
5.5
30
6
Sand
1
Cement
Lime
3
Sand
0.6660
0.1660
528.57
49.3
3724
0.1132
Measure
m3
1
Cement
0.2226
2
Lime
0.4452
9
Sand
Mortar Types
1
1
Cement
Lime
0.3321
0.3321
3724
263.57
98.77
Pounds
Litres
Kilograms
177.55
132.41
35/41
3724
material :Cement
Sand
Aggregate
Water
:
:
:
:
RM
RM
RM
RM
16.80
21.00
35.00
0.003
per
per
per
per
bag
m
m
litre
Cement
(kg)
Sand
(m3)
Aggregate (M3)
Water (litres)
Concrete Grade 15
- Mix 1:3:6
203
0.54
0.83
116
Concrete Grade 17
- Mix 1:2 :6
237
0.52
0.81
105
Concrete Grade 20
- Mix 1:2:4
291
0.55
0.79
119
Concrete Grade 25
- Mix 1:1 :3
361
0.48
0.74
150
Concrete Grade 30
- Mix 1:1:2
491
0.43
0.67
169
10
Mix
APPENDIX 3
Reinforcement Content Control Guide
Building Component
KG/M3
Pile Cap
77 89 kg/m3
Column Stump
Ground Beam
Ground Slab
89 107 kg/m3
Column
Upper Floor
Floor Beam
36/41
Nominal
Diameter
Cross-Section
Area
Mass Per
Unit Length
Mass Per
12m
mm,
kg/m
Kg
mm
mm
No. of Bars
Per Bundle*
Mass Per
Bundle*
Metric Ton
28.3
0.222
2.664
376'
1.002
10
78.5
0.616
7.392
137
1.013
13
132.7
1.042
12.504
81
1.013
54
1.023
16
201.1
1.579
18.948
20
314.2
2.466
29.592
35
1.036
22
380.1
2.984
35.808
28
1.003
25
490.9
3.854
46.248
23
1.064
28
615.8
4.834
58.008
18
1.044
14
1.061
32
804.2
6.313
75.756
35
962.1
7.553
90.636
12
1.088
38
1134.1
8.903
106.836
10
1.068
40
1256.6
9.864
118.368
20
25
30
35
Tension
anchorage length
(mm)
40.350
36.100
31.180
28.580
Compression
anchorage and lap
length (mm)
27.710
24.250
21.550
19.720
Mild Steel
fy = 250 N/mm'
Tension lap
length(mm)
50.440
45.130
38.980
35.730
Note:-
Compression
anchorage
and lap
length (mm)
45.300
38.800
36.200
32.000
Compression
anchorage and lap
(mm)
32.700
28.800
25.800
21.430
37/41
RECTANGULAR MESH
BRC
BS 4483
Main Wire
Cross Wire
Cross-Sectional Area
Mass Per
Ref.
or SS-32
Size
Spacing
Size
Spacing
Main
Cross
Unit Area
No.
Ref. No.
mm
mm
mm
mm
mm'/M
mm'/M
Kg/m'
B 12
B10
B9
B8
B7
B6
B5
B 1131
B 385
B 503
B 385
B 283
B 196
12
10
9
8
7
6
5
100
100
100
100
100
100
100
8
8
8
8
7
7
7
200
200
200
200
200
200
200
1131
785
636
503
385
283
196
252
252
252
252
193
193
193
10.90
8.14
6.97
5.93
4.53
3.73
3.05
C 10
C9
C8
C7
C6
C5
C 785
C 636
C 503
C 385
C 283
-
10
9
8
7
6
5
100
100
100
100
100
100
6
6
5
5
5
5
400
400
400
400
400
400
785
636
503
385
283
196
71
71
49
49
49
49
6.72
5.55
4.34
3.41
2.61
1.93
SQUARE MESH
BRC
BS
4483
Main Wire
Ref.
or SS32
Size
Spacing
Size
Spacing
Main
Cross
Unit Area
No.
Ref.
No.
mm
mm
mm
mm
mm'/M
mm'/M
Kg/m'
393
318
252
193
166
142
98
63
393
318
252
193
166
142
98
63
A 10
A9
A8
A7
A 6/5
A5
A4
A 393
A 252
A 193
A 142
A 98
-
10
9
8
7
6.5
6
5
4
Cross Wire
200
200
200
200
200
200
200
200
10
9
8
7
6.5
6
5
4
38/41
Cross-Sectional Area
200
200
2200
200
200
200
200
200
Mass Per
6.16
4.99
3.95
3.02
2.61
2.22
1.54
0.99
Mix
Sand m3
Coarse
Agg m3
Water
Litres
3 :6
0.14
0.21
1:21/2:5
0.11
0.17
1:2:4
0.09
0.14
22
1:11/2:3
0.07
0.11
20
1 :1:2
0.03
0.06
18
24
Use Recommended
Rough mass concrete,
footings, base courses etc.
Mass concrete of better
class, machinery bases etc.
Normal concreting,
lintols, general reinforced
concrete slabs etc.
High class reinforced
concrete water tight
basements, walls, tanks etc.
Thin section work, fence
posts, small precast items.
APPENDIX 3
Reinforcement Content Control Guide
Building Component
KG/M3
Pile Cap
Foundations
Column Base
Column Stump (Single Storey)
Column Stump (Multi Storey)
Encasement (Jacketing)
Ground Beam
Ground Slab
Column
Column (Multi Storey)
Beam
Slab
Upper Floor
Wall
Floor Beam
Staircase
Gutter
Retaining Wall
96 128 kg/m3
48 64 kg/m3
64 80 kg/m3
192 240 kg/m3
320 400 kg/m3
160 kg/m3
96 128 kg/m3
96 128 kg/m3
178 208 kg/m3
256 320 kg/m3
160 192 kg/m3
96 128 kg/m3
101 119 kg/m3
80 kg/m3
178 208 kg/m3
28 -160 kg/m3
28 160 kg/m3
28 160 kg/m3
39/41
Material
Sand
Bone dry
Average
Moist
Gravel
10 mm to Sand
20 mm to Sand
25 mm to Sand
38 mm to Sand
50 mm to Sand
75 mm to Sand
150 mm to Sand
38 to 20 mm
75 to 38 mm
150 to 75 mm
225 to 150 mm
Broken Stone
10 mm to Sand
20 mm to Sand
25 mm to Sand
38 mm to Sand
50 mm to Sand
Granite
6 mm to Sand
10 mm to Sand
20 mm to Sand
25 mm to Sand
38 mm to Sand
50 mm to Sand
'All-in" Ballast
Brick Hardcore
Brick ] Coarse
Aggte. ] Fine
Breeze ] Coarse
Clinker ] Fine
Foamed] Coarse
Slag ] Fine
Pumice
Vermiculite 66
Portland Cement
Chalk ] Lump
Plaster Light
Plaster of Paris
Loose Weight
Absorption by
Weight
Voids
Kg per m3
Per c. ft.
Per cu yd.
lb
cwt.
tons
1862
116
28
1.40
30
1595
100
24
1.20
39
1277
80
19
0.96
52
1408
88
21
1.06
47
1461
91
22
1.10
45
1488
93
1530
95
1556
97
1595
100
1635
22
23
%
0.4
1.0
1.0
I.0
~.
1.15
42
1.17
41
1.0
24
1.20
39
1.0
102
25
1.23
38
1.0
1635
102
25
1.23
38
1.0
1556
97
23
1.17
41
1.0
1461
91
22
1.10
45
1.0
1382
86
21
1.04
48
1.0
1250
78
19
0.94
53
2.0
1303
81
20
0.98
51
2.0
1330
83
20
1.00
50
2.0
1370
85
20
1.03
49
2.0
1382
86
21
1.04
48
2.0
1330
83
20
1.00
51
0.5
1370
85
20
1.08
50
0.5
1408
88
21
1.06
48
0.5
1435
90
22
1.08
47
0.5
1435
90
22
1.08
47
0.5
1461
91
22
1.10
46
0.5
1795
112
27
1.35
32
1 197
75
18
0.90
35
25
23
~0
0.6
878
55
13
0.66
52
25
1118
70
17
0.84
39
25
718
45
11
0.54
50
878
55
13
0.66
45
557
35
0.42
30
718
45
11
0.54
30
557
35
0.42
0.05
1436
90
22
1.08
54
718
54
11
0.45
73
798
50
12
0.60
65
918
56
14
0.69
66
TS 103
40/41
80
41/41