You are on page 1of 41

Perunding Atur Cekap Basic Preliminary Cost Data

A. PRELIMINARY COSTING DATA


DEVELOPMENT CHARGES / FEES
Note :

All cost data given hereunder are to be used for Preliminary Estimate and Cost Checking
only.

Conversion Fees

20% of Estimated Land Cost

Planning, Bldg & Earthwork Fees

RM 2,000.00 per Acre

DID Contribution Charges

RM 4,000.00 per Acre

LLN Contribution Charges

RM 3,500.00 per Acre

(* Connection & Main Cabling only)


5

Valuation Fees

RM 10,000.00 - RM 30,000.00 (SUM)

Subdivision Fees Including

RM 275.00 per unit (commercial unit)

Registration of Q.T

RM 225.00 per unit (low cost & link house)


RM 70.00 for registration of QT
RM 25.00 for pre-Computation

Quit Rent

average RM 350.00 per unit

1/41

Perunding Atur Cekap Basic Preliminary Cost Data


A.

PRELIMINARY COSTING DATA


INFRASTRUCTURE DEVELOPMENT COST

Note :

All cost data given hereunder are to be used


for Preliminary Estimate and Cost Checking Only.

1.0

2.0

Overall Infrastructure Costs

(low density)

(high density

110,000.00/acre

240,000.00/acre

Breakdown of Infrastructure Costs is generally as follow :


COST / ACRE

a.

CIVIL INFRASTRUCTURE
(Lower Range)

(Higher Range)

RM

RM

Site Clearance, Temporary Works comprising


Earth Drains, Silt Traps, Retaining Walls

1,500.00

4,500.00

b.

Earthworks

22,000.00

70,000.00

c.

Stormwater Drains, Culverts & Sumps

16,000.00

25,000.00

d.

Water Reticulation Mains & Hydrants

6,000.00

10,000.00

e.

Sewer Pipes & Manholes

6,000.00

10,500.00

f.

Roads & Paving

14,000.00

25,000.00

g.

Landscaping & Turfing

2,500.00

3,000.00

II

BULK SERVICES

h.

Water Retaining Structures, Reservoirs, etc

9,000.00

14,000.00

I.

Sewage Treatment Plants, Oxidation Ponds, etc

6,000.00

11,000.00

j.

Main Drains, Secondry Main Drains, Box Culverts, etc

8,000.00

12,500.00

22,000.00

25,000.00

3,000.00

6,500.00

III

M & E INFRASTRUCTURE

k.

LV / HV Electrical Installation, Substation

l.

Telephone Infrastructure - External Telecom Ducts,


Manholes, etc

m.

Streetlighting

(* Variable depending on ground conditions)

2/41

4,000.00

6,500.00

120,000.00

223,500.00

Perunding Atur Cekap Basic Preliminary Cost Data


A.

PRELIMINARY COSTING DATA


INFRASTRUCTURE WORKS

Civil, Mechanical & Electrical

Infrastructure Cost per House Unit

RM 10,000- RM 25,000 / No.

Oxidation Ponds

RM 650.00 RM 850.00 per Dwelling Unit

Main Sewers, Secondary Sewers & Manholes

RM 600.00 per Unit

Concrete Reservoir

RM 400.00 - RM 600.00 per


Dwelling Unit (RM1.50-RM 2.50 per Gallon)

Concrete Reservoir (Elevated)

RM 3.50 RM 5.50 per Gallon

Streetlighting

Allow 1 No. 8m High Street-light Post

RM 300.00 600.00/ unit at Rapat Jaya site

with 70W 'SON' Sodium Lamps at EV.132


of Road.
Each Approximately RM3,000.00 comp.
with Wiring
At Junctions, Crossings. Allow Additional
1 No.12M High Streetlight Post With 150W
SON' Sodium Lamps RM4,000.00 / No.

Road Pavements Comprising :-

7
8

(2' Sand Blinding)

(8' Crusher Run)

(2' Premixed Bit. Surf. Compound)

(Road Kerbs)

(Scupper Drains)

(Road Markings)

RM 9.00 / F.S

Substations Building (Single Chamber)

RM 110,000 / No.

Double Chamber

RM 145,000 / No.

LLN Substation Equipment


I)
ii)

9
I)

Single Chamber

RM80,000

RM140,000

Double Chamber

RM110,000

RM180,000

Bridges
Overhead Taxiway Bridge for Aircraft
49.90M x 61.0M (Source : Subang
Airport Project)

ii)

RM3,500 / M2

Pedestrian Bridge
58'6" x 10'0" (Source : Taman Melati Project)

iii)

iv)

RM1,400 / M2

Twin-Span Box Girder Vehicular Bridge


Crossing River (TTM)

RM2,000 / M2

Highway Flyover (costing given by Engineer)

RM3,000 / M2

3/41

Perunding Atur Cekap Basic Preliminary Cost Data

A.

PRELIMINARY COSTING DATA


SPORTS FACILITIES

RM
Football Field (including Rugby)

110,000

(Approx. 11,000 M2)


2

(RM 10 / M2)

Hockey Field

48,000

(Approx. 5,000 M2)


3

(RM 10 / M2)

Basketball Court

25,000

(Approx. 540 M2)

(RM 50 / M2)

Volleyball Court

15,000

(Approx 460 M2)

(RM 35 / M2)

Tennis Court

45,000

(Approx. 650 M2)


6

(RM 65 / M2)

Badminton / Sepak Takraw Open Court

9,000

(Approx. 240 M2)


7

(RM 35 / M2)

Netball Court

8,000

(Approx. 800 M2)


8

(RM 8 / M2)

Softball Field

110,000

(Approx. 12,000 M2)


9

(RM 10 / M2)

Handball Field

65,000

(Approx. 7,200 M2)


10

(RM 9 / M2)

Running Track

260,000

(Approx. 4,500 M2)


11

(RM 58 / M2)

Swimming Pool

95,000

Including Finishing Work - Pool Equipment


(110 M2 x AV. 1.50 M Deep)

4/41

Perunding Atur Cekap Basic Preliminary Cost Data

A.

PRELIMINARY COSTING DATA


GENERAL

Cinema Equipment

Mechanical Car Parks

RM1,500 per Seat

Manufacturer : KLAUS
1

G61 - 170

RM13,000.00 per car park space


(* Operated by car jockey)

TYP P200 (without pit)

RM45,000.00 per car park space

G62 - 170

RM15,000.00 per car park space

AIRPORTS

Passenger Conveyor Building (2 Storey)


(incl. M&E installations but excluding

special installation)

RM2,500 / M2

Avio-bridges

RM1,600,000 / No.

RM1,700,000 / No.

Travolators (1.0m width)

RM25,000 / M

Apron floodlights with High Sodium Lamps

RM40,000 / No.

Baggage Conveyor System

RM15,000 / M

Hangar

RM2,200 / M2

CONVENTION HALLS

Builders Work including M&E Services,


Acoustic Treatment Soft Seats

RM20,000

Specialist Theatre Equipment

RM15,000

Services Installation in Connection with


Theatre Equipment

RM1,500
RM36,500

5/41

Perunding Atur Cekap Basic Preliminary Cost Data

A.

PRELIMINARY COSTING DATA


BUILDING CONSTRUCTION COST
Notes :

(1)

Figures represent fixed price competitive tenders including all building works,
installation of services, and minimal external works, but excludes piling,
fitting out and professional fees.

(2)

The costs per square meter shown are those for areas measured overall (between
external wall faces) and should be used for preliminary estimates only. Average
conditions are assumed, cmitting any adjustments or variations in ground
conditions and the like. All buildings are assumed as having no basement.

Residential *

RM / M2

Double Storey Low Cost Terrace

400.00

470.00

Single Storey Terrace

470.00

650.00

Double Storey Terrace

490.00

700.00

Double storey Town Houses

590.00

720.00

Single Storey Semi Detached

640.00

780.00

Single Storey Bungalow

660.00

950.00

Double Storey Bungalow

690.00

920.00

Storey Low Cost Walk-up

380.00

620.00

Storey Medium Cost Walk-up

620.00

900.00

High-Rise Medium Cost Flats

890.00

1110.00

High Rise Medium Quality Condominiums

900.00

1400.00

High Rise Luxury Condominiums

1350.00

1600.00

High Rise Luxury Service Apartments

1,700.00

and

Above

* (excludes infrastructure works)


Office / Commercial
Double Storey Shop house (non air-conditioned)

480.00

590.00

Three Storey Shop house (non air-conditioned)

560.00

650.00

4 - 5 Storey Shop houses

640.00

690.00

High Rise Average Standard Office (air-conditioned)

1,450.00

1,800.00

High Rise Prestige Office (air-conditioned)

1,950.00

and

Three Storey to five Storey Shopping Complex

1,700.00

2,100.00

Light Duty Factory

460.00

520.00

Heavy Duty Factory

500.00

620.00

5 - Storey Flatted Factory

720.00

800.00

1 - 1 1/2 Storey Industrial Factories / Workshops cum Offices

440.00

560.00

Above

(air-conditioned)
Industrial * (Typically steel framed with industrial cladding)

* (with minimal services & excludes infrastructure works)

6/41

Perunding Atur Cekap Basic Preliminary Cost Data


A.

PRELIMINARY COSTING DATA


BUILDING CONSTRUCTION COST (Cont'd)

Hotels *

RM / M2

Tourist Class Hotel

1,600.00

2,200.00

4 - Star Hotel

2,000.00

2,600.00

International Class Hotel (5 - Star)

2,500.00

and

above

600.00

* (inclusive of F, F & E)
(see also page BCC / 3)

Medical *
General Hospitals

1,650.00

* (excludes special installations and medical equipment)


( see also page BCC / 3)

Educational Establishments
Colleges - Administration Block

520.00

Colleges - Classroom / Laboratory Block

530.00

Colleges - Hostel Block (Fitted Out)

550.00

Colleges - Multi - purpose Hall

650.00

Colleges - Dining / Kitchen Block

500.00

Colleges - Headmaster's House

600.00

Colleges - Deputy Headmaster's House

560.00

Colleges - Catering Staff Quarters

620.00

Primary Schools

380.00

500.00

Secondary Schools

490.00

610.00

Above Ground (Less than 5-storey)

350.00

400.00

Above Ground (Part of High-rise)

450.00

550.00

Below Ground (Basement)

700.00

1,000.00

650.00

.
Car Park Buildings

General
Amphitheatre

and

above

Theatres (with Furnitures, M & E and excludes show equipment)

1,840.00

2,420.00

Sports Centre (inclusive of M & E)

1,500.00

1,850.00

Golf Course Club House

1,000.00

1,400.00

Mosques (exl. Piling & earthworks)

1,100.00

1,400.00

7/41

Perunding Atur Cekap Basic Preliminary Cost Data

PRELIMINARY COSTING DATA


HOTELS

Istana Hotel
a) Preliminaries

5% - 8%

b) 5 - Star Hotel

RM 350,000 per Room

c) F, F & E Costs (includes Public Areas)

RM 60,000 per Room

Sheraton Hotel, KL
a) 485 Modules
b) GFA - 501, 185 FS
c) Cost / Module (inclusive of F, F & E & Millwork)

RM350,000

d) F, F & E

RM 55,000 per Module *

e) Millwork

RM 30,000 per Module *

(* No. includes Public Areas)

GOLF COURSES

Horsedale Golf & Country Resort (36 - Hole)

RM 1,000,000 per Hole

Tuanku Ja'afar Golf & Country Resort (27 - Hole)

RM 700,000 per Hole

K.L. Golf & Country Resort (36 - Hole)

RM 1,700,000 per Hole

8/41

Perunding Atur Cekap Basic Preliminary Cost Data


PRELIMINARY COSTING DATA
HOSPITALS
Private Hospital : low rise with major operating theatre and food capacity : extensive specialist and service areas
1

GFA per bed

Building construction cost (includes external works, but

excluding services, special services and medical equipment

Air-conditioning Installation

(ii) Electrical (LT) Installation

(iii) Electrical (HT) Installation

(iv) Lift Installation

(v) Fire Protection Installation

(vi) Telephone Installation

(vii) Lightning Protection Installation

(viii) Internal Plumbing

RM 350 / m2

Special Installation including :(I)

RM 1,100 / m2

M & E Services including :(I)

65m2

Medical Gas Installation

(ii) Public Announcement System

(iii) Special Lights Installation

(iv) Automation System

(v) Nurse Call System

(vi) Piped LPG Supply System

(vii) Laundry Equipment

(viii) Kitchen Equipment

(ix) Boilers & Clarifiers

RM 450 / m2

Medical Equipment & Fittings including :(I)

Sterilizing Equipment

(ii) X-Ray Equipment

(iii) Hydrotherapy Equipment

(iv) Operating Room Equipment

(v) Observation Room Equipment

(vi) Patient Room Equipment

(vii) Accident/Emergency Room Equipment

(viii) Outpatient Room Equipment

(ix) Orthophaedic Equipment

(x) Obstetrics & Gynecology Department Equipment

(xi) Laboratory Equipment

(xii) Intensive Care Unit

(xiii) Mortuary Equipment

(xiv) Rehabilitation Equipment etc.

Total cost / m2 = RM 2,300

Cost / Bed = RM 150,000

Cost of Equipment / Bed = RM 25,000

9/41

RM 400 / m2

Perunding Atur Cekap Basic Preliminary Cost Data

B. MISCELLANEOUS INFORMATION
COST OF INTELLIGENT BUILDING IN MALAYSIA

Table 1 : Intelligent Building Cost vs Total Building Cost


Cost per Square Feet

Types

% IB Cost/Total Building Cost

Total Building Cost

IB Related Cost

1. IB with Trunking System

132.70

44.70

33.69%

2. IB with Local Raised Floor

145.40

57.40

39.48%

3. IB with Imported Raised


Floor

151.40

63.40

41.88%

4. Conventional Building

120.00

32.00

26.67%

Notes :

IB related components for Conventional building include lift, electrical system, fire alarm and CAV.
IB related components for Intelligent building include BAS, wiring system (trunking/raised floor), lift, security,
Electrical system, fire alarm, VAV and miscellaneous i.e subtle design changes which changes which need to be
made to make a building intelligent.

Table 2 : Major IB Component Additional Cost Contribution to total Building Cost

Major Cost Component

% IB Cost/Total Building Cost

a) Wiring Management :- #

10.00%

i) Infloor trunking System

2.00%

ii) Locally produced raised floor system

12.50%

iii) Imported raised floor system

17.50%

b) Contant Air Volume to Variable Air Volume

3.00%

c) Building Automation System (BAS)

1.70%

d) Electrical System

1.30%

e) Lift

1.30%

f) Security

0.60%

g) Analogue Addressable Fire Alarm

0.20%

h) Miscellaneous

0.80%
Average Total Cost (%) :

Notes :

# Average cost

10/41

18.90%

Perunding Atur Cekap Basic Preliminary Cost Data


Table 3 : Cost of Major IB Component
Component

Unit

Rate
(RM)

a) Wiring Management :i) Infloor trunking System


ii) Locally produced raised floor system
iii) Imported raised floor system

Cost per Gross Area (sq.ft) RM


Conventional

Intelligent Building

Sq.ft

3.50

2.30

Sq.ft

23.00

15.00

Sq.ft

32.00

b) Constant Air Volume (CAV)

c) Variable Air Volume (VAV)

21.00
13.00

16.50

2.00

500.00

10.50

e) Electrical System

9.00

10.50

f) Lift

9.00

0.70

g) Security

1.20

h) Analogue Addressable Fire Alarm

1.00

1.00

32.00

80.70

d) Building Automation System (BAS)

Point

i) Miscellaneous

Notes :

Total :

* Assuming 65% utilization of gross area


** An Intelligent Building should have about 6 point per square feet of conditioned space corresponds to about
4 points per 1000 gross square feet (65% utilization)

11/41

Perunding Atur Cekap Basic Preliminary Cost Data


B. MISCELLANEOUS INFORMATION (Contd)
PLANNING APPLICATION FEES
TYPES OF DEVELOPMENT

FEES

Residential

(i) RM 50/- per unit


(ii) In case of low cost housing by Government taken as
RM25/- per unit

Commercial, Industrial, Institutional,


Educational, Hotels

For the 1st 10,000 sq.ft. at the rate of RM40/- per 1,000
Partf thereof of floor area. For the next 5,000 sq.ft at the
RM20/- per 1,000 sq.ft or part thereof of floor area; and
At the frate of RM10/- per 1,000 sq.ft or part thereof of floor

Petrol Filling and Service station

RM1,000/- per station

Mixed Development

In accordance with rates charged for development


(a),(b),(c) above

Minor works to (a) and (c) above including partitioning,


Re-roofing changing of floor boards, small extensions,
(bathrooms, kitchen,etc.) changing of windows and
doors,covering of open area, aluminium awnings, open
car porch, garage, open shed, open verandah, wood
paneling, face lift, replacing wood beams with
reinforced concrete beams, reinforced concrete
cantilever projections, hooded windows, roof
extensions for covered way, balcony, window canopy,
corridor, lean-to sheds out-houses, room extension and
any other works that do not constitute erection or reerection.

RM 20/- per unit

Additional and alterations to development as in (b)


above

50% of the rate as in (b) above

Change of use of land

RM1,000.00

Increase of residential density

RM1,000.00

Renewal of Development Order

50% of the rate as in (a),(b),(c) and (d) above

Sales of Plans

RM20.00 per foots cape size or part thereof

Appeal Board Fees

RM500.00

Application for layout plan for conversation and


subdivision

RM250 per acre or part thereof

Application for amendment to approved layout plan

RM125.00 per acre

12/41

Perunding Atur Cekap Basic Preliminary Cost Data


DEVELOPMENT CHARGES/FEES
Note : All cost data given hereunder are to be used for Preliminary/First Line Estimate and cost checking only
1

Conversion Fees

20% of estimated Land Cost

Planning, Building & Earthwork Fees

* per Acre

DID Contribution charges

* per Acre

TNB Contribution charges


(Connection & Main cabling only)

RM250/Unit (Low Cost)


RM1700/unit (Kedai Desa /Sewerage Treatment Plant)

Lembaga Air

RM600/Unit
RM300/Unit
RM750/Unit
RM900/Unit

Valuation Fees

RM 30,000.00 (Sum)

Subdivision Fees including Registration of Q.T

*
*
*
*

Quit Rent

*RM4.00/m2/lettable area (commercial)

13/41

(Semi D Medium Cost)


(Low Cost)
(Shop House)
(Commercial Lot)

per unit (commercial unit)


per unit (low cost & link houses)
for registration of QT
for pre-computation

Perunding Atur Cekap Basic Preliminary Cost Data


IMPROVEMENT SERVICES FUND
CONTRIBUTION RATES FOR IMPROVEMENT SERVICES FUND (ISF)
a. RESIDENTIAL DEVELOPMENT
TYPES OF HOUSE

RATE PER UNIT

Low Cost
(Selling Price RM 50,000 and below)

RM150.00

Medium Cost
(Selling Price RM 50,001 to RM100,000)

RM500.00

High Medium Cost


(Selling Price RM100,001 to RM200,000)

RM1,000.00

High Cost
(Selling Price exceeding RM200,000)

RM2,000.00

Note : Residential development by individuals or private landowners up to a maximum of 4 units, the rate of ISF
contribution shall be 50% of the rates stated above.

b.

NON-RESIDENTIAL DEVELOPMENT
LOCATION

RATE

Within CPA

RM3,000.00 per 1,000 sq.ft

Outside the CPA but within 36 sq.miles limit

RM2,500.00 per 1,000 sq.ft

Outside 36 sq.miles limit

RM1,000.00 per 1,000 sq.ft

Note : Floor space for determining the ISF rate does not include floor space for car-parking.
* ISF calculations (for Non-Residential Development purpose) are calculated to the nearest RM500.00

14/41

Perunding Atur Cekap Basic Preliminary Cost Data


CARPARK REQUIREMENT
Part 1 : Parking Provision Uses Of Land/Building
1.1

1.2

RESIDENTIAL

CAR PARKING STANDARD

a) All residential uses other than flats


b) Flats
Type of Flats
RM25,000 & below
RM26,000 RM40,000
RM41,000 RM60,000
RM61,000 RM99,000
1 room
2 rooms
3 or more rooms
RM100,000 and above
1 room
2 rooms
3 or more rooms

1 cps per dwelling unit

1 cps per 4 units + 5% for visitors


1 cps per 2 units + 5% for visitors
1 cps per 2 units + 5% for visitors
1 cps per 2 units
1 cps per units
1 cps per units + 10% for visitors
1 cps per units
1 cps per units + 10%
1 cps per units + 20%

COMMERCIAL/LIMITED COMMERCIAL
a) Commercial & Office complexes (except cinema & bowling alleys)

1 cps per 50m2 of floor area + 1 cps


per 300m2 of floor area

b) Cinemas, Theatres & auditoriums

1 cps per 5 seats (allowing bumper to


bumper parking)
1mcps per 20 seats

c) Bowling alleys
2 cps per lane
1mcps per lane
d) Conventional shops
(not exceeding 2 lots)

i)Located within 36sq miles boundary


1 cps per 100m2 of floor area
ii) Located outside 36 sq miles
boundary
1cps per 100m2 of floor area no mcps
are required

1.3

INDUSTRIAL
All industrial

1.4

1 lorry bay per 1500m2 of floor area +


1 cps per 200m2 of floor area + 1
mcps per 50m2 of floor area

EDUCATIONAL
a) Creche, Kindergarden, Nursery

1 cps per 4 members of admin &


teaching staff

b) Secondary & Primary school

1 cps per 3 members of admin &


teaching staff

c) All institution of higher learning

1 cps per 2 members of admin &


teaching staff + 1 cps per 25 students
+ 1 mcps per 5 students

15/41

Perunding Atur Cekap Basic Preliminary Cost Data

CARPARK REQUIREMENT (Contd)


Part 1 : Parking Provision Uses Of Land/Building
1.5

1.6

1.7

RELIGIOUS

CAR PARKING STANDARD

a) All religious uses

1 cps per 75 m2

SPORTS
a) Public swimming pool

1 cps per 25m2 of swimming pool area


including bath, restaurant, bar etc. + 1
mcps per 100m2 of the same area
above

b) Stadium with club room etc.

1 cps per 8 seats + 1 mcps per 25 m2


of the games room + 1 mcps per 20
seats

c) Squash court/tennis court

2 cps per court + 1 mcps per court

INSTITUTION
a) Hostels & youth club

1 cps 100m2 of floor area + 1 mcps


per 100m2 of floor area

b) Hospital

1 cps 100m2 of floor area + 20% for


visitor+ 1 mcps per 100m2

c) Private Hospital/medical centre

1 cps 75m2 + 20% for visitors + 1


mcps per 100m2

d) Welfare Homes

1 mcps per 200m2

Part II : Static Requirement For Car


2.1

2.2

2.3

Dimension of Stall
Minimum stall width
Minimum stall length
Minimum stall length for lateral

2.4m (7 10)
4.8m (15 9)
6.0m (19 8)

Dimension of Accessway
Minimum Clear width

3.0m (19 10)

Aisle width
Parking Angle

One Direction Traffic Bays on one


side/both side

Two direction Traffic

90
60
45
30
Lateral

6.0m (19 8)
4.8m (15 9)
4.2m (13 9)
3.7m (12 2)
3.7m (12 2)

7.3m (23 11)


6.7m (22 0)
6.7m (22 0)
6.0m (19 8)
6.0m (19 8)

16/41

Perunding Atur Cekap Basic Preliminary Cost Data


TREATMENT WORKS AND DRAINAGE SUBMISSION FEES
TYPE OF DEVELOPMENT
1

Residential

5 persons/unit

Office -cum-shop and commercial

3.3 persons/1,000 sq.ft

Cinema

0.1 persons/seat

School

0.1 persons/pupil

Hotel

4.4 persons/room

Hospital

3 persons/bed

Industrial & Flatted Factory

2.5 persons/1,000 sq.ft

Shopping Complex

1.3 persons/1,000 sq ft

Fees for Consideration of Plans


1. For the Plan submitted in respect of any building
(a)

For each water closet, slope sink, urinal, budget, bath or shower

RM5.00

(b)

For each lavatory basin or sink or other sanitary appliances not


specified under these By-Laws

RM2.00

(c)

For every Septic Tank and Inhofe Tank the charge per cubic ft

RM0.40

(d)

Notwithstanding the provision of these By-Laws, the minimum


fee chargeable in respect of each application shall be

RM25.00

2. For each amendment plan to an approved plan where no addition is made to the total number of appliances shown in the
approved plan, one-fifth of the relevant fees specified in paragraph 1, subject to a maximum of RM25.00
3. For each amendment plan to an approved plan where no addition is made to the total number of appliances in the
amendment plan exceeds that in the original approved plan, fees specified in paragraph 1 in respect of the additional
appliances in additions to or one-fifth of the fees payable in respect of the approval of the original plan, whichever is less, shall
be payable.
4. For a series of identical sanitary installations in a number of the building of the same design when plans are submitted for
approval at the same time, a deduction of the fees specified in preceding paragraph shall be made on the following basis :a)

For the sanitary installation in the first building

Full fees

b)

In the 2nd to 5th building (inclusive)

90% of the fees

c)

In the 6th and every additional building

85% of the fees

*Provide that half of the fees set out above shall be charged in respect of plans for sanitary installations in buildings used
exclusively as places for religious worship, school or for charitable purposes
5. In all cases where work has been commenced before plans have been approved a fee equal to ten times that specified in
paragraph 1 shall be charged. The payment of which fee shall not except any person from being prosecuted by the Datuk
Bandar

17/41

Perunding Atur Cekap Basic Preliminary Cost Data


PLANNING GUIDELINES FOR CONDOMINIUM/HOUSING PROJECTS
THE TECHNICAL PLANNING GUIDELINES FOR CONDOMINIUM TYPE HOUSING ARE :STANDARD
Minimum site area (as in legal title)

SIZE OF DEVELOPMENT
2 acre

4 acre

6 acre and above

Maximum population density per acre

60

80

100

Minimum communal open space in


percentage of nett site area

30

35

40

Minimum communal facilities to be


provided

A swimming pool of not less


than 800 sq.ft surface area

As for column 1

A common games room of not


less than 500 sq.ft

2 badminton courts or
equivalent

A gymnasium, 2
squash courts

A gazebo area
A launderette and a
management office
Minimum carpark

1 carpark per residential unit


and 20% more for visitors

Note :
Nett site area means the area of the site excluding areas for public road, public road widening reserves, school,
drainage reserves, septic tank site, TNB substation site and any other portions that are to be surrounded to any
government authority.
Communal open space means the gardens and landscaped area within the development accessible to all
occupants of the condominium housing development and include pavilions, shelters, swimming pools, sand pits,
fountains and other open recreational facilities, but excludes taken areas taken up by private driveways, carparks,
electrical sub-stations, septic tanks and other services.

18/41

Perunding Atur Cekap Basic Preliminary Cost Data


C. PROJECT FACT FILE UNIT COSTS
1

Industrial Building

(a)

GBH Factory (Single Storey Factory With Office)


GFA 12,551 m2
1
Foundation Piling & Basement Works
2
Structural Frame
3
Internal & External Finishes
4
Services
5
External Works
6
Preliminaries
Total Construction Cost ( exc. Contingencies)

Residential

(a)

Village Genting (26-Storey high rise condominium)


(i) Carpark , ( GFA : 21,464 m2)
1
Foundation, piling & basement work
2
Structural frame
3
Internal & External Finishes
4
Services
5
Preliminaries
Total Construction Cost

Total Cost
RM

180.00
250.00
48.00
225.00
45.00
45.00
10,549,105.00

61.00
160.00
78.00
127.00
42.00
10,176,760.00

(ii) Podium ,( GFA : 8,595 m2)


1
Foundation, piling & basement work
2
Structural frame
3
Internal & External Finishes
4
Services
5
Preliminaries
Total Construction Cost

7.00
355.00
204.00
20.00
82.00

(iii) Tower
1
Foundation, piling & basement work
2
Structural frame
3
Internal & External Finishes
4
Services
5
Preliminaries
Total Construction Cost

65.00
223.00
210.00
158.00
79.00

(iv)
(b)

Cost/M2
RM

6,055,544.00

49,582,246.00
1,637,000.00

External Works (Allowance only)

Villa Bukit Tunku (Luxury Low Rise Apartment)


(GFA : 12,676 M2)
1
Foundation, piling & basement work
2
Structural frame
3
Internal & External Finishes
4
Services
5
External Works
6
Preliminaries
Total Construction Cost

164.00
129.00
51.00
219.00
91.00
218.00
14,170,663.00

19/41

Perunding Atur Cekap Basic Preliminary Cost Data


C. PROJECT FACT FILE UNIT COST (Contd)
2

Residential

(c)

Gasing Condominium Phase 2 (22- Storey)


(GFA : 29,450 m2)
1
Basement Works
2
Super Structure
3
Internal & External Finishes
4
Services
5
External Works
6
Preliminaries
Total Construction Cost ( exc. Contingencies)

(d)

Cost/M2
RM

Double Storey Link House at Taman Melawati


( GFA : 142 m2)
1
Substructure
2
Super Structure
3
Internal & External Finishes
4
Services
5
External Works
6
Preliminaries
Total Construction Cost

22,286,497.00

79,150.00

Offices/Commercial

(a)

Hicom Ladang Damansara (1 block of 2 storey shophouse)


1
Substructure
2
Super Structure
3
Internal & External Finishes
4
Services
5
External Works
6
Preliminaries
Total Construction Cost ( exc. Contingencies)

(c)

9.00
270.00
142.00
219.00
60.00
58.00

88.00
257.00
105.00
56.00
25.00
26.00

(b)

Total Cost
RM

Wisma Kelwaram ( 2- level basement, 5-level Podium & 30-level office)


(GFA : 100,631 M2)
1
Substructure
2
Super Structure
3
Internal & External Finishes
4
Services
5
External Works
6
Preliminaries
Total Construction Cost ( exc. Contingencies)
Wisma C & C ( 1- level basement, 9-level Podium & 18-level office)
(GFA : 100,631 M2)
1
Substructure
2
Super Structure
3
Internal & External Finishes
4
Services
5
External Works
6
Preliminaries
Total Construction Cost ( exc. Contingencies)

20/41

95.00
194.00
86.00
36.00
2.00
46.00

199.00
563.00
363.00
452.00
15.00
138.00
175,000,000.00

199.00
491.00
190.00
537.00
16.00
61.00
98,199,000.00

Perunding Atur Cekap Basic Preliminary Cost Data


C. PROJECT FACT FILE UNIT COST (Contd)
3

Offices/Commercial

(d)

Lion Tower ( 50-Storey Office)


(GFA : 138,563 M2)
1
Substructure
2
Super Structure
3
Internal & External Finishes
4
Services
5
External Works
6
Preliminaries
Total Construction Cost

(e)

Cost/M2
RM

Total Cost
RM

167.00
403.00
65.00
471.00
8.00
126.00
180,051,000.00

Telekom HQ ( 2-Level basement , 3-level Podium & 55-storey Tower Block)


Foundation Piling Works
Structural & Architectural Works to Basement
Carcase
Finishing
Mechanical Carpark
Preliminaries
Others
Total Group Cost
Structural & Architectural Works to Podium
Superstructure
Finishing
Fittings & Furniture
Preliminaries
Others
Total Group Cost
Structural & Architectural Works to Tower
Superstructure
Finishing
Fittings & Furniture
Preliminaries
Others
Total Group Cost
M & E Services
Site Preparation & Demolition Works (Sum)
Sky Gardens, Antenna Tower & Helipad (Sum)
Sky Garden
Antenna Tower
Helipad
Preliminaries
Total Group Cost

169.00
129.00
32.00
85.00
8.00
3.00
257.00
586.00
244.00
154.00
51.00
37.00
1,072.00
831.00
255.00
191.00
131.00
38.00
1,446.00
520.00
1,025,000.00
12,700,000.00
11,700,000.00
4,200,000.00
1,470,000.00
16,245,000.00
30,070,000.00
60,944,000.00
498.00

External Works & Services (sum)


Soft Cost (sum)
Intelligent Building Services
Mandatory Items
First Priority Items
Others

176.00
171.00
151.00
Total Group Cost

21/41

498.00

Perunding Atur Cekap Basic Preliminary Cost Data


C. PROJECT FACT FILE UNIT COST (Contd)
3

Retail

Cost/M2
RM

(a)

Klang Shopping Centre (7- Storey including 3-storey car parking)


(i) Shopping Complex GFA : 26,323 m2)
1
Substructure
2
Super Structure
3
External Walling & Finishes
4
Internal Walling
5
Internal Finishes
6
Services
7
Builders Work
Total Construction Cost
Car Parking
( GFA : 18,777 m2)
1
Substructure
2
Super Structure
3
External Walling & Finishes
4
Internal Walling
5
Internal Finishes
6
Services
7
Builders Work
Total Construction Cost

(b)

(c)

225.00
191.00
42.00
53.00
97.00
485.00
21.00
29,514,369.00

115.00
244.00
8.00
9.00
31.00
108.00
3.00
9,437,118.00

Taman Segar Shopping Centre


( GFA : 19,038 m2)
1
Substructure
2
Super Structure
3
External Walling & Finishes
4
Internal Walling
5
Internal Finishes
6
Services
7
Preliminaries
8
External Works & Services
9
Contingencies (P.C Sum)
Total Construction Cost

303.00
157.00
18.00
61.00
75.00
14.00
164.00
41.00
1,300,000.00
1,300,833.00

Renovation & Extension to Existing Jaya Supermarket


(GFA : 19,400 M2)
1
Total Construction Cost (Extension)
2
Total Construction Cost (Renovation & Upgrading)

Hotels

(a)

Radisson Hotel (4 Star)


310 Modules
1
GFA/Module in F.S (exclude Carpark)
2
FF & E / Module
3
HOE / Module
4
Total Construction Cost/Module
5
Carparking Cost/Module

Total Cost
RM

17,000,000.00
7,900,000.00

Unit Cost (RM)

822
25,419.00
9,484.00
127,308.00
16,171.00

22/41

Perunding Atur Cekap Basic Preliminary Cost Data


C. PROJECT FACT FILE UNIT COST (Contd)
4

Hotels

(b)

Swiss Garden (3 Star)


320 Modules
1 GFA/Module in F.S (exclude Carpark)
2 FF & E / Module
3 HOE / Module
4 Total Construction Cost/Module
5 Carparking Cost/Module

Unit Cost (RM)

(c)

(d)

(e)

(f)

(g)

(h)

822.00
25,419.00
9,484.00
127,308.00
16,171.00

Katari Hotel (Budget)


102 Modules
1 GFA/Module in F.S (exclude Carpark)
2 FF & E / Module
3 HOE / Module
4 Total Construction Cost/Module
5 Carparking Cost/Module

597.00
25,223.00
13,353.00
92,677.00
8,902.00

Istana Hotel (5 Star)


620 Modules
1 GFA/Module in F.S (exclude Carpark)
2 FF & E / Module
3 HOE / Module
4 Total Construction Cost/Module

318.00
6,000.00
2,941.00
49,167.00

Regent Hotel (5Star)


501 Modules
1 GFA/Module in F.S (exclude Carpark)
2 FF & E / Module
3 HOE / Module
4 Total Construction Cost/Module
5 Carparking Cost/Module

1,334.00
45,000.00
25,000.00
199,004.00
20,359.00

Shangri La Hotel (5-star)


774 Modules
1 GFA/Module in F.S (exclude Carpark)
2 FF & E / Module
3 HOE / Module
4 Total Construction Cost/Module
5 Carparking Cost/Module

1,070.00
40,000.00
24,000.00
174,548.00
8,398.00

New World (5-Star)


622 Modules
1 GFA/Module in F.S (exclude Carpark)
2 FF & E / Module
3 HOE / Module
4 Total Construction Cost/Module
5 Carparking Cost/Module

1,014.00
50,000.00
30,000.00
188,814.00
15,434.00

Ramada (5-Star)
515 Modules
1 GFA/Module in F.S (exclude Carpark)
2 FF & E / Module
3 HOE / Module
4 Total Construction Cost/Module
5 Carparking Cost/Module

1,416.00
60,000.00
40,000.00
236,835.00
21,359.00

23/41

Perunding Atur Cekap Basic Preliminary Cost Data


C. PROJECT FACT FILE UNIT COST (Contd)
4

Hotels

(i)

Sheraton Hotel, KL
485 Modules
1 GFA/Module in F.S (exclude Carpark)
2 FF & E / Module
3 HOE / Module
4 Total Construction Cost/Module

Cost / m2

55,000.00
39,000.00
350,000.00

General

(a)

Pusat Sains Negara Construction Floor Area : 22,179 m2


1 Total Construction Cost
2 Cost/m2

(b)

(c)

(d)

Unit Cost (RM)

Resort Kampung Cherating


(GFA : 3,844 m2)
1 Substructure
2 Super Structure
3 External Walling & Finishes
4 Services
5 Preliminaries
6 External Works & Services
7 Contingencies ( Allowance only)

47,800,000.00
2,155.00

90.00
304.00
123.00
152.00
180.00
2.00
776,000.00

Kinta Swimming Club,Ipoh


(GFA : 8,854 m2)
1 Substructure
2 Super Structure
3 External Walling & Finishes
4 Services
5 External Works & Services
6 Preliminaries (P.C Sum)

168.00
248.00
111.00
337.00
158.00
470,000.00

Twin Mini Cinemas, Sungei Wang Plaza


1 Demolition & Structural Works
2 Internal Wall
3 Internal Finishes
4 Joinery Fittings, etc
5 Services
6 Preliminaries
7 Builders Work
8 Contingencies

341
127
80
31
221
38
6
103

24/41

Perunding Atur Cekap Basic Preliminary Cost Data


C. PROJECT FACT FILE UNIT COST (Contd)
5

General

(f)

Diagnostic Clinical Lab & Facilities Complex, University Hospital


1
Substructure
2
Super Structure
3
External Walling & Finishes
4
Internal Walling
5
Internal Finishes
6
M & E Services
7
Special Installation
8
Builders Works
9
Preliminaries
10 External Works & Services
11 Contingencies

Cost / m2

(g)

Seri Manjung Hospital


(268 bed district hospital including 3 operating theatres, wards, pathology,
X-ray and outpatient departments)
1
Cost per bed
2
Total Value
(*Information from external source not validated)

64.00
266.00
80.00
46.00
100.00
528.00
270.00
25.00
1,739,800.00
4,801,102.00
5,127,458.00

272,388 *
73,000,000.00

RM/m2 ; GFA
(Enclosed Area)
(h)

KL International Airport, Sepang


1
Main Terminal Building
2
Contact Pier & Transfer Lounge
3
1 No Satelite
4
Baggage Handling System Equipment (PC Sum)
5
Tunnels
a) racked transport system tunnel
b) Baggage handling Tunnel
6
Preliminary
7
Design Consultancy & Project Management Fees (P.C Sum)
8
Design Contingencies (P.C Sum)
9
Allowance for cost Escalation (Construction Period) (P.C Sum)

25/41

Unit Cost (RM)

RM/m2 ; GFA
(Gross Area)

3,938.00
5,199.00
4,935.00
75,000,000.00
23.00
17.00
156,194,000.00
171,813,000.00
94,497,000.00
396,888,000.00

Perunding Atur Cekap Basic Preliminary Cost Data


Job Title :

PROPOSED SINGLE STOREY FACTORY WITH OFFICE (GBH)

Location :

Kuala Lumpur

Building Analysis :

Single Storey Building With Office

GFA :

12,551 m2
ELEMENT

Total Element Cost


(RM)

Cost/m2 GFA
(RM)

% Cost/m2 GFA
(RM)
10.08%

SUBSTRUCTURE

Piling

1,063,718.00

84.75

Work Below Lowest Floor Finish

1,174,199.00

93.55

11.13%

2,237,917.00

178.31

21.21%

1,356,304.00

108.06

12.86%

0.00

0.00

0.00%

1,095,192.00

87.26

10.38%

Group Element Total


B

SUPERSTRUCTURE

Frame

Upper Floor

Roof

Staircase

4,975.25

0.40

0.05%

External Wall

94,878.00

7.56

0.90%

Window & Ext Doors

107,355.00

8.55

1.02%

Internal Wall & Partitions

439,650.00

35.03

4.17%

Internal Doors

31,005.00

2.47

0.29%

3,129,359.25

249.33

29.66%

Group Element Total


C

FINSHES

Internal Wall Finishes

182,491.00

14.54

1.73%

Internal Floor Finishes

329,478.00

26.25

3.12%

Internal Ceiling Finishes

68,641.00

5.47

0.65%

External Finishes

13,230.04

1.05

0.13%

593,840.04

47.31

5.63%

100,000.00

7.97

0.95%

Group Element Total


D

FITTINGS AND FURNISHINGS

SERVICES

Sanitary Appliances

3,453.05

0.28

0.03%

Plumbing Installation

58,880.00

4.90

0.56%

Air conditioning & Ventilation System

423,000.00

33.70

4.01%

Electrical Installation

1,697,200.00

135.22

16.09%

Fire Protection Installation

480,000.00

38.24

4.55%

Lift & Conveyor Installation

Communication Installation

Builders Profit & Attendance on Services

52,004.00

4.14

0.49%

Builders Work in Connection with Services

80,000.00

6.37

0.76%

Group Element Total

2,794,537.05

222.65

26.49%

Sub Total Excluding External Works,


Preliminaries & Contingencies

8,855,653.34

705.57

83.95%

EXTERNAL WORKS & SERVICES

Site work

803,793.79

64.04

7.62%

Drainage

246,237.26

19.62

2.33%

External Services

79,050.61

6.30

0.75%

Ancillary Buildings

5,000.00

0.40

0.05%

Recreational Facilities
Group Element Total

PRELIMINARIES
TOTAL (LESS CONTINGENCIES)

26/41

1,134,081.66

90.36

10.75%

559,370.00

44.57

5.30%

10,549,105.00

840.50

100.00%

Perunding Atur Cekap Basic Preliminary Cost Data


Job Title :

PROPOSED DOUBLE STOREY TERRACE HOUSE

Location :

Taman Melawati, Setapak

Building Analysis :

Double Storey Link Houses Type A

GFA :

142 m2
ELEMENT

Total Element Cost


(RM)

Cost/m2 GFA
(RM)

% Cost/m2 GFA
(RM)
10.87%

SUBSTRUCTURE

Piling & Foundation Works

8,200.00

57.73

Work Below Lowest Floor Finish

4,350.00

30.62

5.77%

12,550.00

88.35

16.63%

11,300.00

79.55

14.98%

7,100.00

49.98

9.41%

Group Element Total


B

SUPERSTRUCTURE

Frame

Upper Floor

Roof Structure

Roof Finish

190.00

1.34

0.25%

Staircase

1,800.00

12.67

2.39%

External Wall

5,100.00

35.90

6.76%

Window & Ext Doors

6,750.00

47.52

8.96%

Internal Wall & Partitions

2,400.00

16.90

3.18%

Internal Doors

1,900.00

13.38

2.52%

36,540.00

257.24

48.43%

FINSHES

Internal Wall Finishes

5,400.00

38.02

7.16%

Internal Floor Finishes

4,600.00

32.38

6.10%

Internal Ceiling Finishes

2,100.00

14.78

2.78%

External Finishes

Group Element Total

Group Element Total

2,800.00

19.71

3.71%

14,900.00

104.89

19.75%

SERVICES

Sanitary Appliances

1,900.00

13.38

2.52%

Plumbing Installation

4,000.00

28.16

5.30%

Refuse Disposal System

Air conditioning & Mechanical Ventilation

Electrical Installation

2,000.00

14.08

2.65%

Fire Protection Installation

Lift Installation

Communication Installation

Builders Profit & Attendance on Services

10

Builders Work in Connection with Services

7,900.00

55.61

10.47%

71,890.00

506.09

95.28%

Group Element Total

Sub Total Excluding External Works,


Preliminaries & Contingencies
EXTERNAL WORKS & SERVICES

Site work

3,400.00

23.94

4.51%

Drainage

160.00

1.13

0.21%

External Services

Ancillary Buildings

Recreational Facilities

3,560.00

25.08

0.05%

PRELIMINARIES

3,700.00

26.06

4.91%

79,150.00

531.16

100.00%

Group Element Total

TOTAL (LESS CONTINGENCIES)

27/41

Perunding Atur Cekap Basic Preliminary Cost Data


Job Title :

WISMA KEWALRAM, HIGH RISE OFFICE BUILDING

Location :

Jalan Ampang /Jalan Yap Kwan Seng Kuala Lumpur

Building Analysis :

2 level Basement, 5 level Podium & 30 level office

GFA :

100,631 m2
Total Element Cost
(RM)

ELEMENT
A

SUBSTRUCTURE

Foundation Piling & Basement Work


Group Element Total

Cost/m2 GFA
(RM)

% Cost/m2 GFA
(RM)

19,994,154.00

198.00

11.43%

19,994,154.00

198.00

11.43%

SUPERSTRUCTURE

Frame

38,845,346.00

386.02

22.20%

Upper Floor

1,408,057.00

13.99

0.80%

Roof

2,692,536.00

26.76

1.54%

Staircase

407,819.00

4.05

0.23%

External Wall

800,000.00

7.95

0.46%

Window & Ext Doors

9,600,000.00

95.40

5.49%

Internal Wall & Partitions

1,134,461.00

11.27

0.65%

Internal Doors

1,762,377.00

17.51

1.01%

56,650,596.00

562.95

32.37%

Group Element Total


C

FINSHES

Internal Wall Finishes

4,110333.00

40.85

2.35%

Internal Floor Finishes

5,882,391.00

58.46

3.36%

Internal Ceiling Finishes

4,540,907.00

45.12

2.59%

Internal Finishes to Floors, Walls & Ceiling

5,600.000.00

55.65

3.20%

External Finishes

16,400,000.00

162.97

9.37%

36,533,631.00

363.05

20.88%

936,223.00

9.30

0.53%

2,661,184.00

26.44

1.52%

30,000.00

0.60

0.02%

Group Element Total


D

FITTINGS AND FURNISHINGS

SERVICES

Plumbing & Sanitary Appliances

Refuse Disposal

Air conditioning & Ventilation System

14,000,000.00

139.12

8.00%

Electrical Installation

9,800,000.00

97.39

5.60%

Fire Protection Installation

3,700,000.00

36.77

2.11%

Lift & Conveyor Installation

10,000,000.00

99.37

5.71%

Communication Installation

1,000,000.00

9.94

0.57%

Special Installation

2,020,000.00

20.07

1.15%

Builders Profit & Attendance on Services

2,009,100.00

19.97

1.15%

10

Builders Work in Connection with Services

333,107.00

3.31

0.19%

45,553,391.00

452.68

26.03%

159,667,995.00

1,586.67

91.24%

Group Element Total


Sub Total Excluding External Works,
Preliminaries & Contingencies
F

EXTERNAL WORKS & SERVICES

1,476,412.00

14.67

0.84%

1,476,412.00

14.67

0.84%

13,855,593.00

137.69

7.92%

175,000,000.00

1,739.03

100.00%

Group Element Total


G

PRELIMINARIES
TOTAL (LESS CONTINGENCIES)

28/41

Perunding Atur Cekap Basic Preliminary Cost Data


Job Title :

PROPOSED HIGH RISE OFFICE BUILDING (C&C)

Location :

Jalan Raja Laut, Kuala Lumpur

Building Analysis :

1 level Basement, 9 level Podium & 18 level office

GFA :

73,051 m2
Total Element Cost
(RM)

ELEMENT
A

SUBSTRUCTURE

Foundation Piling & Basement Work


Group Element Total

Cost/m2 GFA
(RM)

% Cost/m2 GFA
(RM)

19,000,000.00

260.09

19.35%

700,000.00

9.58

0.71%

SUPERSTRUCTURE

Frame

Upper Floor

Roof

Staircase

540,000.00

7.39

0.55%

External Wall

12,850,000.00

175.90

13.09%

Window & Ext Doors

1,040,000.00

14.24

1.06%

Internal Wall & Partitions

0.61%

Internal Doors
Group Element Total

600,000.00

8.21

1,150,000.00

15.74

1.17%

35,880,000.00

491.16

36.54%

FINSHES

Internal Wall Finishes

3,330,000.00

45.58

3.39%

Internal Floor Finishes

3,330,000.00

45.58

3.39%

Internal Ceiling Finishes

3,400,000.00

46.54

3.46%

External Finishes

3,800,000.00

52.02

3.87%

3,620,000.00

189.73

14.41%

3,620,000.00

49.55

3.69%

Group Element Total


D

FITTINGS AND FURNISHINGS

SERVICES

Plumbing & Sanitary Appliances

1,500,000.00

20.53

1.53%

Air conditioning & Ventilation System

14,720,000.00

201.50

14.99%

Electrical Installation

9,170,000.00

125.53

9.34%

Fire Protection Installation

3,750,000.00

51.33

3.82%

Lift & Conveyor Installation

6,860,000.00

93.91

6.99%

Communication Installation

200,000.00

2.74

0.20%

Special Installation

860,000.00

11.77

0.88%

Builders Profit & Attendance on Services

1,840,000.00

25.19

1.87%

Builders Work in Connection with Services

300,000.00

4.11

0.31%

Group Element Total

39,200,000.00

536.61

39.92%

Sub Total Excluding External Works,


Preliminaries & Contingencies

92,560,000.00

1,267.06

94.26%

EXTERNAL WORKS & SERVICES

1,189,000.00

16.28

1.21%

1,189,000.00

16.28

1.21%

4,450,000.00

60.92

4.53%

98,199,000.00

1,344.25

100.00%

Group Element Total


G

PRELIMINARIES
TOTAL (LESS CONTINGENCIES)

29/41

Perunding Atur Cekap Basic Preliminary Cost Data


Job Title :

LION TOWER (Office Tower Only)

Location :

Jalan Ampang, Kuala Lumpur

Building Analysis :

50- Storey Office Tower

GFA :

138,563 m2
Total Element Cost
(RM)

ELEMENT
A

SUBSTRUCTURE

Foundation Piling & Basement Work


Group Element Total

SUPERSTRUCTURE

Frame

Upper Floor

Roof

Staircase

External Wall

Window & Ext Doors

7
8

Cost/m2 GFA
(RM)

% Cost/m2 GFA
(RM)

23,077,000.00

166.55

12.82%

23,077,000.00

166.55

12.82%

33,019,000.00

238.30

18.34%

233,000.00

1.68

0.13%

185,000.00

1.34

0.10%

14,710,000.00

106.16

8.17%

308,000.00

2.22

0.17%

Internal Wall & Partitions

6,356,000.00

45.87

3.53%

Internal Doors

1,100,000.00

7.94

0.61%

55,911,000.00

403.51

31.05%

Group Element Total


C

FINSHES

Internal Wall Finishes

1,052,000.00

7.59

0.58%

Internal Floor Finishes

2,686,000.00

19.38

1.49%

Internal Ceiling Finishes

2,500,000.00

18.04

1.39%

External Finishes

2,776,000.00

20.03

1.54%

9,014,000.00

65.05

5.01%

682,000.00

4.92

0.38%

Group Element Total


D

FITTINGS AND FURNISHINGS

SERVICES

Plumbing & Sanitary Appliances

2,190,000.00

15.81

1.22%

Air conditioning & Ventilation System

17,200,000.00

124.13

9.55%

Electrical Installation

13,898,000.00

100.30

7.72%

Fire Protection Installation

5,260,000.00

37.96

2.92%

Lift & Conveyor Installation

18,081,000.00

130.49

10.04%

Communication Installation

1,860,000.00

13.42

1.03%

Special Installation

4,975,000.00

35.90

2.76%

Builders Profit & Attendance on Services

Builders Work in Connection with Services


Group Element Total
Sub Total Excluding External Works,
Preliminaries & Contingencies

EXTERNAL WORKS & SERVICES


Group Element Total

1,809,000.00

13.06

1.00%

65,273,000.00

471.07

36.25%

153,957,000.00

1,111.10

85.51%

1,069,000.00

7.71

0.59%

1,069,000.00

7.71

0.59%

PRELIMINARIES

17,414,000.00

125.68

9.67%

CONTINGENCIES

7,611,000.00

54.93

4.23%

180,051,000.00

1,299.42

100.00%

TOTAL (LESS CONTINGENCIES)

30/41

Perunding Atur Cekap Basic Preliminary Cost Data


Job Title :
Location :
GFA :

A
1
2
3
B
1
C
1
2
3
4
5
6
D
1
2
3
4
E
1
2
3
4
5
6
F
1
2
3
4
G
1
2
3
4
H
1
2
3
4
5
6
7
8
9
I
1
2

Proposed Klang 7 Storey Shopping Centre (Including 3-Storey Car Parking


Klang ,Selangor
44,500 m2
SHOPPING COMPLEX
26,323 M2
ELEMENT DESCRIPTION
Budget
Cost Per M2 (GFA)
Allowance
RM
RM
%
SUBSTRUCTURE
Piling
1,632,400.00
62.01
5.53%
Foundation & Ground Slabs
1,400,000.00
53.19
4.74%
Basement Car case
2,886,851.90
109.67
9.78%
Group Total
5,919,251.90
224.87
20.05%
SUPERSTRUCTURE
Frame
4,502,834.62
171.06
15.26%
Group Total
4,502,834.62
171.06
15.26%
EXTERNAL WALL & FINISHES
Walls
118,114.00
4.49
0.40%
External Finishes
302,629.05
11.50
1.03%
Windows
25,127.60
0.95
0.09%
Ext Doors
34,518.15
1.31
0.12%
Ext Shopfronts
153,120.00
5.82
0.52%
Aluminium Grid Wall System
468,000.00
17.78
1.59%
Group Total
1,101,508.80
41.85
3.75%
ROOF COVERINGS,etc
Roofing
Rainwater Goods
23,628.00
0.90
0.08%
Space Frame/Canopy
360,000.00
13.68
1.22%
False Skylight
130,000.00
4.94
0.44%
Group Total
513,628.00
19.51
1.74%
INTERNAL WALL
Walls
289,015.95
10.98
0.98%
Toilet Cubicles
111,423.25
4.23
0.38%
Glazed Aluminium Shopfronts
94,857.30
3.60
0.32%
Aluminium Roller Shutter
17,692.00
0.67
0.06%
Internal Doors
207,134.59
7.87
0.70%
Fire Shutters
665,704.36
25.29
2.26%
Group Total
1,385,827.45
52.65
4.70%
INTERNAL FINISHES
Floors
1,166,599.52
44.32
3.95%
Walls
858,508.66
32.51
2.91%
Ceilings
442,279.02
16.80
1.50%
Staircases & Railings
75,209.69
2.86
0.25%
Group Total
2,542,596.89
96.59
8.61%
JOINERY FITTINGS, etc
Letter Boxes
9,973.82
0.38
0.03%
Built-In Fitmen
17,496.00
0.66
0.06%
Sign-Writing
70,000.00
2.66
0.24%
Food Court Fixtures & Counters
120,000.00
4.56
0.41%
Group Total
217,469.82
8.26
0.74%
SERVICES
Sanitary Fittings
90,842.80
3.45
0.31%
Plumbing/Sanitary Pipe
803,000.00
30.51
2.72%
Electrical/ Tel Installation
1,430,000.00
54.33
4.85%
Passenger Lift/Escalator
4,760,000.00
180.83
16.13%
Fire Fighting Installation
700,000.00
26.59
2.37%
Air-Conditioning /Ventilation
3,400,000.00
129.16
11.52%
Generator Set
675,000.00
25.64
2.29%
High Voltage Services
800,000.00
30.39
2.71%
LPG Gas Installation
120,000.00
4.56
0.41%
Group Total
12,778,842.80
485.46
43.30%
BUILDERS WORK
Builders Profit & Attendance
303,409.20
11.53
1.03%
Builders Work in Connection
249,000.00
9.46
0.84%
Group Total
552,409.20
20.99
1.87%
TOTAL CONSTRUCTION COST :
(Exc. Prelim, Contingencies & Ext work)
29,514,369.48
1,121.24
100%

31/41

CAR PARKING (3- STOREY)


18,177 M2
Budget
Cost Per M2 (GFA)
Allowance
RM
RM
%
1,127,000.00
980,000.00
2,107,000.00

62.00
53.91
115.92

11.94%
10.38%
22.33%

4,155,096.00
4,155,096.00

228.59
228.59

44.03%
44.03%

11,404.80
97,642.92
26,414.50
15,302.17
150,764.39

0.63
5.37
1.45
0.84
8.29

0.12%
1.03%
0.28%
0.16%
1.16%

260,940.02
11,692.08
272,632.10

14.36
0.64
15.00

2.77%
0.12%
2.89%

55,025.46
119,024.37
174,049.83

3.03
6.55
9.58

0.58%
1.26%
1.84%

163,548.88
250,067.36
126623.24
17,335.84
557,575.32

9.00
13.76
6.97
0.95
30.67

1.73%
2.65%
1.34%
0.18%
5.91%

10,000.00
10,000.00

0.55
0.55

0.11%
0.11%

300,000.00
520,000.00
660,000.00
300,000.00
75,000.00
100,000.00
1,955,000.00

16.50
28.61
36.31
16.50
4.13
5.50
107.55

3.18%
5.51%
6.99%
3.18%
0.79%
1.06%
20.72%

17,000.00
38,000.00
55,000.00

0.94
2.09
3.03

0.18%
0.40%
0.58%

9,437,117.64

519.18

100.00%

Perunding Atur Cekap Basic Preliminary Cost Data

Job Title :

Proposed Twin Mini Cinemas (Reyrofitting Works)

Location :

Sungai Wang Plaza, Kuala Lumpur

Building Analysis :

Twin Mini Cinemas

GFA :

15,533 m2
ELEMENT

Total Element Cost


(RM)

Cost/m2 GFA
(RM)

% Cost/m2 GFA
(RM)

SUBSTRUCTURE

Piling & Foundation Work

WBLFF

0.00

0.00

0.00%

SUPERSTRUCTURE

Frame

467,000.00

30.07

37.63%

Upper Floor

Roof Structure

Roof Finish

Staircase

External Wall

Window & Ext Doors

1,000.00

0.06

0.08%

Internal Wall & Partitions

133,000.00

8.56

10.72%

Internal Doors

Group Element Total

Group Element Total

49,000.00

3.15

3.95%

650,000.00

41.85

52.38%

FINSHES

Internal Wall Finishes

23,000.00

1.48

1.85%

Internal Floor Finishes

53,000.00

3.41

4.27%

Internal Ceiling Finishes

40,000.00

2.58

3.22%

External Finishes

116,000.00

7.47

9.35%

42,000.00

2.70

3.38%

Group Element Total

FITTINGS AND FURNISHINGS

SERVICES

Plumbing & Sanitary Appliances

8,000.00

0.52

0.64%

Air

160,000.00

10.30

12.89%

Electrical Installation

90,000.00

5.79

7.25%

Fire Protection Installation

65,000.00

4.18

5.24%

Builders Profit & Attendance on Services

10,000.00

0.64

0.81%

333,000.00

21.44

26.83%

1,141,000.00

73.46

91.94%

Group Element Total


Sub Total Excluding External Works,
Preliminaries & Contingencies
E

EXTERNAL WORKS & SERVICES

25,000.00

1.61

2.01%

PRELIMINARIES

55,000.00

1.61

2.01%

CONTINGENCIES

150,000.00

3.22

4.03%

1,371,000.00

79.89

100.00%

TOTAL

32/41

Perunding Atur Cekap Basic Preliminary Cost Data

Job Title :

Proposed Clubhouse, The Kinta Swimming Club

Location :

Jalan Silibin, Ipoh, Perak

Building Analysis :

1- Level Car Park & 4- Storey Buildings

GFA :

8,854 m2
ELEMENT

Total Element Cost


(RM)

Cost/m2 GFA
(RM)

% Cost/m2 GFA
(RM)
7.44%

SUBSTRUCTURE

Piling & Foundation Work

673,000.00

76.01

WBLFF

812,00.00

91.71

8.98%

1,485,000.00

167.72

16.42%
12.05%

Group Element Total


B

SUPERSTRUCTURE

Frame

1,090,000.00

123.11

Upper Floor

Roof Finish

145,000.00

16.38

1.60%

Roof Structure

155,000.00

17.51

1.71%

Staircase

60,000.00

6.78

0.66%

External Wall

85,000.00

9.60

0.94%

Window & Ext Doors

360,000.00

40.66

3.98%

Internal Wall & Partitions

176,000.00

19.88

1.95%

Internal Doors

121,000.00

13.67

1.34%

2,192,000.00

247.57

24.24%

Group Element Total


C

FINSHES

Internal Wall Finishes

340,000.00

38.40

3.76%

Internal Floor Finishes

299,000.00

33.77

3.31%

Internal Ceiling Finishes

280,000.00

31.62

3.10%

External Finishes

60,000.00

6.78

0.66%

979,000.00

110.57

10.82%

230,000.00

25.98

2.54%

543,000.00

61.33

6.00%

Group Element Total


D

FITTINGS AND FURNISHINGS

SERVICES

Plumbing & Sanitary Appliances

Air conditioning & Ventilation System

Electrical Installation

4
5

620,000.00

70.02

6.86%

1,200,000.00

135.53

13.27%

Fire Protection Installation

245,000.00

27.67

2.87%

Lift & Conveyor Installation

260,000.00

29.37

2.71%

Builders Profit & Attendance on Services

60,000.00

6.78

0.66%

Builders Work in Connection with Services


Group Element Total
Sub Total Excluding Ext Works,Prelim &
Contingencies

60,000.00

6.78

0.66%

2,988,000.00

337.47

33.04%

7,644,000.00

663.34

84.52%

EXTERNAL WORKS & SERVICES

Site Works

310,000.00

35.01

3.43%

Drainage

385,000.00

43.48

4.26%

External Services

20,000.00

2.26

0.22%

Ancillary Buildings

10,000.00

1.13

0.11%

Recreational Facilities

675,000.00

76.24

7.46%

1,400,000.00

158.12

15.48%

1,021.00

100.00%

Group Element Total


F

PRELIMINARIES

470,000.00

TOTAL (LESS CONTINGENCIES)

9,514,000.00

33/41

Perunding Atur Cekap Basic Preliminary Cost Data

Job Title :

Proposed 16 Units Double Storey Shophouses

Location :

Hicom Ladang Damansara, Shah Alam

Building Analysis :

1 Block Double Storey Shophouse

GFA :

2,595 m2
ELEMENT

Total Element Cost


(RM)

Cost/m2 GFA
(RM)

% Cost/m2 GFA
(RM)

SUBSTRUCTURE

Piling & Foundation Work

187,700.00

72.33

17.43%

WBLFF

60,500.00

23.31

5.62%

248,200.00

95.65

23.05%

SUPERSTRUCTURE

Frame

251,400.00

96.88

23.34%

Upper Floor

Roof Finish

80,500.00

31.02

7.48%

Roof Structure

13,100.00

5.05

1.22%

Staircase

6,600.00

2.54

0.61%

External Wall

16,600.00

6.40

1.54%

Window & Ext Doors

44,400.00

17.11

4.12%

Internal Wall & Partitions

81,700.00

31.48

7.59%

Internal Doors

11,500.00

4.43

1.07%

505,800.00

194.91

46.97%

FINSHES

Internal Wall Finishes

104,900.00

40.42

9.74%

Internal Floor Finishes

32,600.00

12.56

3.03%

Internal Ceiling Finishes

64,400.00

24.82

5.98%

External Finishes

Group Element Total

Group Element Total

Group Element Total

22,500.00

8.67

2.09%

224,400.00

86.47

20.84%

FITTINGS AND FURNISHINGS

SERVICES

Sanitary Appliances

47,500.00

18.30

4.41%

Electrical Installation

45,400.00

17.50

4.22%

92,900.00

35.80

1.38%

1,071,300.00

412.83

92.23%

Group Element Total


Sub Total Excluding Ext Works,Prelim &
Contingencies
E

EXTERNAL WORKS & SERVICES

Site Works

Drainage

5,600.00

2.16

External Services

Ancillary Buildings

Recreational Facilities
Group Element Total

PRELIMINARIES

0.52%

5,600.00

2.16

0.52%

414.99

100.00%

119,900.00

TOTAL (LESS CONTINGENCIES)

1,196,800.00

34/41

Perunding Atur Cekap Basic Preliminary Cost Data

APPENDIX 1
MATERIAL QUANTITIES FOR MORTAR
Table One : Mixers of (0.305 x 0.305 x 0.610) m gauge boxes capacity
Measure

Mortar Types
1
1
Cement
Lime

1
Cement

2
Lime

9
Sand

0.0126

0.0252

0.1132

0.0188

0.0188

Pounds

21

15

31

12

Litres

6.5

13.5

60

10

Kilograms

10

7.5

15

m3

6
Sand

1
Cement

Lime

3
Sand

0.0377

0.0094

0.1132

63

10

60

20

60

5.5

30

6
Sand

1
Cement

Lime

3
Sand

0.6660

0.1660

528.57

49.3

3724

0.1132

Note : *varies ; depends upon water content

Table Two : Mixers of 1m capacity

Measure

m3

1
Cement
0.2226

2
Lime
0.4452

9
Sand

Mortar Types
1
1
Cement
Lime

0.3321

0.3321

3724

263.57

98.77

Pounds
Litres
Kilograms

177.55

132.41

Note : *varies ; depends upon water content

35/41

3724

Perunding Atur Cekap Basic Preliminary Cost Data


APPENDIX 2
MATERIAL QUANTITIES FOR CONCRETE
Breakdown Rate for
1
2
3
4

material :Cement
Sand
Aggregate
Water

:
:
:
:

RM
RM
RM
RM

16.80
21.00
35.00
0.003

per
per
per
per

bag
m
m

litre

Cement
(kg)

Sand
(m3)

Aggregate (M3)

Water (litres)

50kg Cement bag per


Cubic meter

Concrete Grade 15
- Mix 1:3:6

203

0.54

0.83

116

Concrete Grade 17
- Mix 1:2 :6

237

0.52

0.81

105

Concrete Grade 20
- Mix 1:2:4

291

0.55

0.79

119

Concrete Grade 25
- Mix 1:1 :3

361

0.48

0.74

150

Concrete Grade 30
- Mix 1:1:2

491

0.43

0.67

169

10

Mix

APPENDIX 3
Reinforcement Content Control Guide
Building Component

KG/M3

Pile Cap

77 89 kg/m3

Column Stump

178 208 kg/m3

Ground Beam

149 208 kg/m3

Ground Slab

89 107 kg/m3

Column

178 208 kg/m3

Upper Floor

101 119 kg/m3

Floor Beam

178 208 kg/m3

36/41

Perunding Atur Cekap Basic Preliminary Cost Data

Weight Tables for


mild steel round bars & high tensile deformed bars
Weight

Nominal
Diameter

Cross-Section
Area

Mass Per
Unit Length

Mass Per
12m

mm,

kg/m

Kg

mm

mm

No. of Bars
Per Bundle*

Mass Per
Bundle*
Metric Ton

28.3

0.222

2.664

376'

1.002

10

78.5

0.616

7.392

137

1.013

13

132.7

1.042

12.504

81

1.013

54

1.023

16

201.1

1.579

18.948

20

314.2

2.466

29.592

35

1.036

22

380.1

2.984

35.808

28

1.003

25

490.9

3.854

46.248

23

1.064

28

615.8

4.834

58.008

18

1.044

14

1.061

32

804.2

6.313

75.756

35

962.1

7.553

90.636

12

1.088

38

1134.1

8.903

106.836

10

1.068

40

1256.6

9.864

118.368

High Yield Deformed Bar Type 2


Fy= 410 N/mrn~
Concrete
Grade

20
25
30
35

Tension
anchorage length
(mm)

40.350
36.100
31.180
28.580

Compression
anchorage and lap
length (mm)

27.710
24.250
21.550
19.720

Mild Steel
fy = 250 N/mm'

Tension lap
length(mm)

50.440
45.130
38.980
35.730

Note:-

Compression
anchorage
and lap
length (mm)

45.300
38.800
36.200
32.000

Compression
anchorage and lap
(mm)

32.700
28.800
25.800
21.430

1. Minimum lap length for bars in tension 250 + 150 mm


Minimum lap length for bars in compression 200 + 150 mm
Hooks and Passing In Reinforcement
The girth of a standard hook is 12d where d = the diameter of the bar.
The length of an overlap or passing for adequate bond in 1:2:4 concrete is 59d. The minimum overlap in longitudinal
steel in columns is 24d.
The necessary bond length (with or without a hook) depends upon the mix of concrete and the local stress on the steel.
Minimum end length is 14d straight, or a hook equivalent to 12d.
4466 "Bending dimensions and scheduling bars for reinforcement of concrete" illustrates some 35 different shapes
with full dimensions and suggests a form of bar schedule.

37/41

Perunding Atur Cekap Basic Preliminary Cost Data

RECTANGULAR MESH
BRC

BS 4483

Main Wire

Cross Wire

Cross-Sectional Area

Mass Per

Ref.

or SS-32

Size

Spacing

Size

Spacing

Main

Cross

Unit Area

No.

Ref. No.

mm

mm

mm

mm

mm'/M

mm'/M

Kg/m'

B 12
B10
B9
B8
B7
B6
B5

B 1131
B 385
B 503
B 385
B 283
B 196

12
10
9
8
7
6
5

100
100
100
100
100
100
100

8
8
8
8
7
7
7

200
200
200
200
200
200
200

1131
785
636
503
385
283
196

252
252
252
252
193
193
193

10.90
8.14
6.97
5.93
4.53
3.73
3.05

C 10
C9
C8
C7
C6
C5

C 785
C 636
C 503
C 385
C 283
-

10
9
8
7
6
5

100
100
100
100
100
100

6
6
5
5
5
5

400
400
400
400
400
400

785
636
503
385
283
196

71
71
49
49
49
49

6.72
5.55
4.34
3.41
2.61
1.93

SQUARE MESH
BRC

BS
4483

Main Wire

Ref.

or SS32

Size

Spacing

Size

Spacing

Main

Cross

Unit Area

No.

Ref.
No.

mm

mm

mm

mm

mm'/M

mm'/M

Kg/m'

393
318
252
193
166
142
98
63

393
318
252
193
166
142
98
63

A 10
A9
A8
A7
A 6/5
A5
A4

A 393
A 252
A 193
A 142
A 98
-

10
9
8
7
6.5
6
5
4

Cross Wire

200
200
200
200
200
200
200
200

10
9
8
7
6.5
6
5
4

38/41

Cross-Sectional Area

200
200
2200
200
200
200
200
200

Mass Per

6.16
4.99
3.95
3.02
2.61
2.22
1.54
0.99

Perunding Atur Cekap Basic Preliminary Cost Data

MIXED FOR VARIOUS USES


Based on 50 kg. cement

Mix

Sand m3

Coarse
Agg m3

Water
Litres

3 :6

0.14

0.21

1:21/2:5

0.11

0.17

1:2:4

0.09

0.14

22

1:11/2:3

0.07

0.11

20

1 :1:2

0.03

0.06

18

24

Use Recommended
Rough mass concrete,
footings, base courses etc.
Mass concrete of better
class, machinery bases etc.
Normal concreting,
lintols, general reinforced
concrete slabs etc.
High class reinforced
concrete water tight
basements, walls, tanks etc.
Thin section work, fence
posts, small precast items.

APPENDIX 3
Reinforcement Content Control Guide
Building Component

KG/M3

Pile Cap
Foundations
Column Base
Column Stump (Single Storey)
Column Stump (Multi Storey)
Encasement (Jacketing)
Ground Beam
Ground Slab
Column
Column (Multi Storey)
Beam
Slab
Upper Floor
Wall
Floor Beam
Staircase
Gutter
Retaining Wall

96 128 kg/m3
48 64 kg/m3
64 80 kg/m3
192 240 kg/m3
320 400 kg/m3
160 kg/m3
96 128 kg/m3
96 128 kg/m3
178 208 kg/m3
256 320 kg/m3
160 192 kg/m3
96 128 kg/m3
101 119 kg/m3
80 kg/m3
178 208 kg/m3
28 -160 kg/m3
28 160 kg/m3
28 160 kg/m3

39/41

Perunding Atur Cekap Basic Preliminary Cost Data

AGGREGATES, CEMENT, ETC


Approximate Average Properties

Material

Sand
Bone dry
Average
Moist
Gravel
10 mm to Sand
20 mm to Sand
25 mm to Sand
38 mm to Sand
50 mm to Sand
75 mm to Sand
150 mm to Sand
38 to 20 mm
75 to 38 mm
150 to 75 mm
225 to 150 mm
Broken Stone
10 mm to Sand
20 mm to Sand
25 mm to Sand
38 mm to Sand
50 mm to Sand
Granite
6 mm to Sand
10 mm to Sand
20 mm to Sand
25 mm to Sand
38 mm to Sand
50 mm to Sand
'All-in" Ballast
Brick Hardcore
Brick ] Coarse
Aggte. ] Fine
Breeze ] Coarse
Clinker ] Fine
Foamed] Coarse
Slag ] Fine
Pumice
Vermiculite 66
Portland Cement
Chalk ] Lump
Plaster Light
Plaster of Paris

Loose Weight

Absorption by
Weight

Voids

Kg per m3

Per c. ft.

Per cu yd.

lb

cwt.

tons

1862

116

28

1.40

30

1595

100

24

1.20

39

1277

80

19

0.96

52

1408

88

21

1.06

47

1461

91

22

1.10

45

1488

93

1530

95

1556

97

1595

100

1635

22

23

%
0.4

1.0
1.0
I.0

~.

1.15

42

1.17

41

1.0

24

1.20

39

1.0

102

25

1.23

38

1.0

1635

102

25

1.23

38

1.0

1556

97

23

1.17

41

1.0

1461

91

22

1.10

45

1.0

1382

86

21

1.04

48

1.0

1250

78

19

0.94

53

2.0

1303

81

20

0.98

51

2.0

1330

83

20

1.00

50

2.0

1370

85

20

1.03

49

2.0

1382

86

21

1.04

48

2.0

1330

83

20

1.00

51

0.5

1370

85

20

1.08

50

0.5

1408

88

21

1.06

48

0.5

1435

90

22

1.08

47

0.5

1435

90

22

1.08

47

0.5

1461

91

22

1.10

46

0.5

1795

112

27

1.35

32

1 197

75

18

0.90

35

25

23

~0

0.6

878

55

13

0.66

52

25

1118

70

17

0.84

39

25

718

45

11

0.54

50

878

55

13

0.66

45

557

35

0.42

30

718

45

11

0.54

30

557

35

0.42

0.05

1436

90

22

1.08

54

718

54

11

0.45

73

798

50

12

0.60

65

918

56

14

0.69

66

TS 103

40/41

80

Perunding Atur Cekap Basic Preliminary Cost Data


SPECIAL NOTES :.

41/41

You might also like