PERHITUNGAN PRODUKTIFITAS TEORITIS

ALAT MUAT DAN ALAT ANGKUT


1. Produktifitas ke Rom Tempory
Lokasi
Alat muat
Kapasitas bucket (C)
Fill factor (f)
Kapasitas pengisian (Qm)
Waktu pengisian (Ctm)

: Pit 4700
: Excavator KOMATSU PC 300
: 1.83 m3
: 1,15
: C x f = 1.83x 1,15 = 2,10 m3
: 0,28 menit

Jumlah pengisian per jam

Jumlah alat muat (Nm)


Eff. Kerja
Alat angkut
Jumlah pengisian (n)
Total cycle time (Cta)

:1
: 51 %
: Scania P380
: 14
: 20,41 menit

Jumlah trip/jam

Eff. Kerja
Jumlah alat angkut (Na)
Jarak Angkut
Material
Bobot Isi (D)
Swell Factor (SF)

: 51 %
:5
: 2.410 meter
: Coal
: 1.3 t/m3
: 0,74

60
60
=
= 214
Ctm
0.28

60
60
=
= 2.93 3
Cta
20.41

a. Produktifitas Alat Muat


P = Qm jumlah pengisian per jam Eff. Kerja
= 2,1 214 51%
= 229,194 Lcm/jam
= 229,194 x SF = 229,194 x 0,74 = 170 Bcm/jam
170 x 1,3 = 220 ton / jam
b. Produktifitas Alat Angkut
P = n Qm jumlah trip per jam Eff. Kerja
= 14 2.10 3 51%
= 44.982 Lcm/jam
= 44.982 x SF = 44.982 x 0,74 = 33.28 Bcm/jam
33.28

33.28

= jumlah trip per jam =


= 11 Bcm/trip
3
= 11 x D = 11 x 1.3 = 14,42 Ton payload
= 3 x 14.42 = 43.26 ton / jam

c. Match Factor
4 (14 0,28)
Na (n Ctm)
MF
=
= 0,76
1 20,41
Nm Cta
d. Waktu Tunggu
MF < 1, waktu tunggu untuk alat angkut
(Nm Cta)
(1 20.41)
Wtm
(n Ctm) =
(4 0,28) = 4 menit
Na
4
2. Produktifitas Crushing
Lokasi
Alat muat
Kapasitas bucket (C)
Fill factor (f)
Kapasitas pengisian (Qm)
Waktu pengisian (Ctm)

: Pit 4700
: Excavator KOMATSU PC 300
: 1.83 m3
: 1,15
: C x f = 1.83x 1,15 = 2,10 m3
: 0,29 menit

Jumlah pengisian per jam

Jumlah alat muat (Nm)


Eff. Kerja
Alat angkut
Jumlah pengisian (n)
Total cycle time (Cta)

:1
: 51 %
: Scania P380
: 14
: 20,41 menit

Jumlah trip/jam

Eff. Kerja
Jumlah alat angkut (Na)
Jarak Angkut
Material
Bobot Isi (D)
Swell Factor (SF)

: 51 %
:5
: 20.1 km
: Coal
: 1.3 t/m3
: 0,74

60
60
=
= 214
Ctm
0.28

60
60
=
= 0.9 1
Cta
64.

e. Produktifitas Alat Muat


P = Qm jumlah pengisian per jam Eff. Kerja
= 16,1 214 51%
= 1.757,154 Lcm/jam
= 1.757,154 x SF = 1.292,17 x 0,74 = 1.300,29 Bcm/jam
f. Produktifitas Alat Angkut
P = n Qm jumlah trip per jam Eff. Kerja
= 14 2.10 1 51%
= 14.99 Lcm/jam
= 14.99 x SF = 44.982 x 0,74 = 11 Bcm/jam
11

11

= jumlah trip per jam =


= 11 Bcm/trip
1
= 11 x D = 11 x 1.3 = 14,3 Ton payload

= 14.3 x 1 = 14,3 Ton / jam


g. Match Factor
Na (n Ctm)
10 (14 0,28)
MF
=
= 0,61
Nm Cta
1 64
h. Waktu Tunggu
MF < 1, waktu tunggu untuk alat angkut
(Nm Cta)
(1 64)
Wtm
(n Ctm) =
(10 0,28) = 3.6 menit
Na
10

Estimasi Jumlah alat


NF

VP / WP
Kp

VP = Volume Pekerjaan
WP = Waktu penyelesaian
Kp = Kapasitas produksi alat
Target Produksi = 270.000
Kebutuhan Alat Muat
NF

270.000 ton / 720 jam


= 1,7 = 2 Excavator
220 ton

Kebutuhan Alat Angkut menuju Temporary


NF

270.000 / 720 jam


= 8.6 = 9 DT
43.26

NF

270.000 / 720 jam


=26 DT
14.3