Professional Documents
Culture Documents
Network Growth
Company's transformation capacity stood at about 16,350 MVA as of March 2010.
Capacity at the 220 kV and 132 kV levels constituted a roughly similar share of 40
percent of the total. WBSETCL recorded the highest compound annual growth
rate (CAGR) of 13.5% in transformer capacity during 2006-07 to 2009-10 among all
state utilities.
At the end of 2009-10, its transmission line length stood at over 11,450 ckt. km, growing
at a CAGR of 6.5% from 2005-06. About 60% of its line network is at the 132 kV level.
Across all voltage levels, its 400 kV network(constituting 14% of its network) has grown
the fastest in the past five years, with a CAGR of about 20 percent
Future Plans
WBSETCL plans to add over 2,000MVA to its transformer capacity and 900 ckt. km to
its transmission line network in the current fiscal year (201011). A capex of over Rs 8
billion has been outlined in 2010-11 on various capacity augmentation projects. About
10 new substations would be commissioned by WBSETCL in the current fiscal(2010
21
11), which would add 2,180 MVA to its existing transformer capacity. These include a
400 kV substation at Kharagpur, two 220 kV substations at Singur and Dalkhola, and
five 132 kV substations at Chalsa, Kurseong, Khatra, Mohispota and Salt lake (this will
be GIS substation).
Besides the commissioning of new sub-stations, capacity augmentation would be
undertaken at 12 existing substations, of which five are at the 220 kV level. Over
912ckt. km of transmission line would also be added in the current fiscal through 19
ongoing transmission line projects. The estimated cost of these transmission line is Rs.
4.63 billion.
In order to reduce transmission losses further, the installation of 33 kV capacitors at
EHV substations and installation of EHV substations near the load centers are some of
the important strategies being deployed by WBSETCL
Growth Statistics[edit]
[2]
2008-09
Substations (no.)
93
102
9.68
3.90
2.74
21
ACKNOWLEDGEMENT
I being a student of electrical engineering from express
my sincere gratitude and heartfelt thankfulness to the
WEST BENGAL STATE ELECTRICITY TRANSMISSION
COMPANY LIMITED for granting us the opportunity to
receive training under this esteemed organisation, from 2
nd of January 2015 to 16th January 2015, in
BONGAON(Chalki power station).
We gained a lot of theoretical as well as a fabulous
practical experience in this short period of time. Our
special thanks extends to the Assistant Engineer of the
substation, Mr. Prosenjit Sarkar. and all the employees of
the substation, who were very helpful and co-operative to
help us learn and understand.
Overall it was an awesome experience as we got to learn
about the practical purposes of our trade.
21
TRANSMISSION
Electric power transmission is the bulk transfer of electrical energy from generating
power plant to electrical substation located near demand centers. This is distinct
from the local wiring between high-voltage substations and customers, which is
typically referred to as electric power distribution. Transmission lines, when
interconnected with each other, become transmission networks. These are typically
referred to as power grids or just the grid.
Transmission lines mostly use high-voltage three phase alternating current
(AC), although single phase. AC is sometimes used in railway electrification system.
High voltage direct current (HVDC) technology is for greater efficiency in very long
distances (typically greater than 400 miles, or 600 km) sub marine power cables
(typically greater than 30 miles, or 50 km). HVDC links are increasingly used as
isolating features to stabilize against control problems in large power distribution
networks where sudden new loads or blackouts in one part of a network can
otherwise result in synchronization problems that may bring the rest of the network
down. Electricity is transmitted at high voltages (110 kv or above) to reduce the
energy lost in long-distance transmission. Power is usually transmitted through
overhead power lines. Underground power transmission has a significantly higher
cost and greater operational limitations but is sometimes used in urban areas or
sensitive locations. A key limitation in the distribution of electricity is that, with
minor exceptions, electrical energy cannot be stored, and therefore must be
generated as needed. A sophisticated system of control is therefore required to
ensure electric generation very closely matches the demand. If supply and demand
are not in balance, generation plants and transmission equipment can shut down
which, in the worst cases, can lead to a major regional blackout. To reduce the risk
of such failures, electric transmission networks are interconnected into regional,
national or continental wide networks thereby providing multiple redundant.
Alternate routes for power to flow should (weather or equipment) failures occur.
Much analysis is done by transmission companies to determine the maximum
reliable capacity of each line ensure spare capacity is available should there be any
such failure in another part of the network.
METHODS OF TRANSMISSION
OVERHEAD TRANSMISSION
High-voltage overhead conductors are not covered by insulation. The
conductor material is nearly always an aluminum alloy, made into several strands
21
and possibly reinforced with steel strands. Copper was sometimes used for
overhead transmission but aluminum is lower in weight for only marginally reduced
performance and much lower in cost. Overhead conductors are a commodity
supplied by several companies worldwide. Improved conductor material and shapes
are regularly used to allow increased capacity and modernize transmission circuits.
Conductor sizes range from 12 mm2 (36 American wire gauge) to 750 mm2 (1,590,000
circular mils area), with varying resistance and current carrying capacity. Thicker
wires would lead to a relatively small increase in capacity due to the skin effect that
causes most of the current to flow close to the surface of the wire. Because of this
current limitation, multiple parallel cables (called bundle conductors) are used when
higher capacity is needed. Bundle conductors are also used at high voltages to
reduce corona discharge energy loss.
Today, transmission-level voltages are usually considered to be 110 kv and
above. Lower voltages such as 66 kv and 33 kv are usually considered sub
transmission voltages but are occasionally used on long lines with light loads.
Voltages less than 33 kv re usually used for distribution. Voltages above 230 kv are
considered high voltages are requiring different designs compared to equipment
used at lower voltages.
Science overhead transmission wires depend on air for insulation, design of
these lines require minimum clearances to be observed to maintain safety. Adverse
weather condition of high wind and low temperatures can lead to power outages:
wind speeds as low as 23 knots (43 km/h) can permit conductors to encroach
operating clearances, resulting in a flashover and loss of supply. Oscillatory motion
of the physical line can be termed gallop or flutter depending on the frequency and
amplitude of oscillation.
UNDERGROUND TRANSMISSION :The design and construction of underground transmission line differ from
overhead linens because of two significant technical challenges that need to be
overcome. There are: 1) providing sufficient insulation so that cable can be within
inches of grounded material; and 2) dissipating the heat produced during the
operation of the electrical cables. Overhead lines are separated from each other and
surrounded by air. Open air circulating between around the conductors cools the
wires and dissipates heat very effectively. Air also provides insulation that can
recover if there is a flashover. In contrast, a number of different systems, materials,
and construction methods have been used during the last century in order to
achieve the necessary insulation and heat dissipation required for undergrounding
transmission lines. The first underground transmission line was a 132 kv line
constructed in 1927. The cable was fluid-filled and paper insulated. The fluid was
necessary to dissipate the heat. For decades, reliability problems continued to be
21
associated with constructing longer cables at higher voltages. The most significant
issue was maintenance difficulties. Not until the mid-1960s did the technology
advance sufficiently so that a high-voltage 345 kv line could be constructed
underground. The lines though were still fluid filled. This caused significant
maintenance, contamination, and infrastructure issues. In the 1990s the first solid
cable transmission line was constructed more than one mile in length and greater
than 230 Kv.
SUB-STATION
Introduction:
A substation is a part of an electrical generation, transmission, and distribution
system. Substations transform voltage from high to low, or the reverse, or perform
any of several other important functions. Electric power may flow through several
substations between generating plant and consumer, and its voltage may change in
several steps.
A substation may include step-up transformers (that increase the voltage while
decreasing the current) or step-down transformers (that decrease the voltage while
increasing the current) for domestic and commercial distribution. The
word substation comes from the days before the distribution system became a grid.
21
1.Primary power lines 2.Ground wire 3.Overhead lines 4.Transformer for
measurement of electric voltage 5.Disconnect switch 6.Circuit breaker 7.Current
transformer 8.Lightning arrester 9.Main transformer 10.Control building
11.Security fence 12.Secondary power lines
Where a substation has a metallic fence, it must be properly grounded to protect
people from high voltages that may occur during a fault in the network. Earth faults
at a substation can cause a ground potential rise.
SELECTION AND
SUBSTATION
LOCATION
OF
SITE
FOR
Area required
50 acres
25 acres
10 acres
Communication Facility:-
21
The site should be
such where staff can be provided essential amenities like school, hospital,
drinking water housing etc.
Drainage Facility:-
Classification OF SUB-STATIONS:
On the basis of Nature of Duties
1. Step-up or Primary Substation
2. Primary Grid Substation
3. Step-Down or Distribution Substation
21
21
The cinematograph sub-stations are also specific purpose sub-stations are
required to meet special requirements.
Depending on the constructional features the sub-station may be further subdivided into : 1. Outdoor type
2.Indoor type 3.Basement or Underground
type 4.Pole mounting-open or kiosk type.
For reason of cost and safety it is common to have Outdoor sub-stations for 33
kv and above.
Introduction:
Electrical power system has generally three steps, 1. Generation 2. Transmission
and 3.Distribution.The electric power is generate at the power plant. It is delivered
to the consumers through a large network of transmission and distribution. At many
places in the line of the power system, it may be desirable and necessary to change
some characteristics (e.g. voltage, a.c to d.c, frequency, power factor etc) of electric
supply. This is accomplished by suitable apparatus called sub-station.
Sub-Stations are important part of power system. The wrtinuity of supply depends
to a considerable extend upon to successful operation of sub- stations. It is
therefore, essential to exercise utmost care while designing and building a substation. The following are the important points which must be kept in view while
laying out a substation
1. It should be located at proper site. As far as possible, it should be located at
the centre of gravity of load.
2. It should be provide safe and reliable arrangement.
3. It should be easily operated and maintained.
BONGAON(132/33/11 KV) Sub- Station was built up under JBIC project(about 9 year
ago) having 2x31.5. 132/33 kv transformer capacity power to this sub-station is
feed from jeerat 400/200/132 kv sub-station through double circuit 132 kv line
namely JEERAT-BONGAON feeder I & II. A separate 132 kv double circuit has also
21
commissioned for feeding power to KRISHNAGAR 132 kv sub-station. These feeder
have been designed as BONGAON-KRISHNAGAR feeder I & II.
i)
ii)
iii)
Transformer
Circuit Breaker
Power Line Carrier Communication(PLCC)
Lightning Arresters
Battery Bank
Insulator
Isolators
Bus-bars
21
I.
J.
K.
L.
Capacitor bank
Metering and Indicating Instrument
Air Conditioner
Operating Computer
Details descriptions of the system are describe next. The layout designed of the
Sub-Station and other circuit designs are shown next
21
21
a.TRANSFORMER
Introduction:
A transformer is a static device which consists of two or more stationary
electrical circuits of transferring electrical energy between then. The transfer of
energy from one circuit to another takes place without a charge in frequency.
Here M is flux
POWER TRANSFORMER
21
POWER
21
CONSERVATOR TANK:-
Conservator is a small
auxiliary oil tank(an air tight cylindrical dram) that may be
mounted above the transformer and connected to the main
tank by a pipe. Its function is to keep the main tank of the
transformer completely filled with oil in all circumstances
despite expansion or contraction of oil with the change of
temperature-conservator is always partly filled with oil and
absorbs the expansion and contraction of oil and keeps the
main tank full oil. It also reduces the rate of oxidation of oil,
partly because less oil surface is exposed to air and partly
because of reduced temperature of the oil exposed to air.
Normally the capacity of conservator should be approximately
10-12% of the oil volume of the main tank.
BREATHER:-
21
transformers the tappings are to be changed after disconnecting them from the
supply mains.
RADIATOR-Radiators
21
Two 31.5 MVA power transformer (at rating 132/33 KV) for step down
from 132 KV primary voltage to 33 KV secondary voltage. The outgoing lines are
Gagnapur, Helencha, Bongaon-1, Bongaon-2, and Chandpara.
Two 6.3 MVA power transformer (33/11 KV) are use for step down from
33 KV primary to 11 KV secondary and the outgoing lines are Mamudpur,
Gopalnagar, Belta, and Nahata
MVA
NO LOAD
HV
NO LOAD
AMPERES
AMPERES
PHASE
FREQUENCY
31.5
132 KV
LV
HV
LV
TYPE OF COOLING
RATING OF MVA
CONNECTION
SYMBOL
NO LOAD LOSS
AUXILLARY LOSS
HEAVIEST PACKAGE
WITH OIL kg
ELECSPES
BH8002
MA1 08802A
33
137.78
551.10
3
50 HZ
ONAN/ONA
F
20.5/31.6
MAKERS WO NO.
MAKERES SERIAL NO
DIAGRAM DRG NO.
YEAR OF MFG.
UNTAKING MASS kg
BH8802
BH8802/13
MA3 08802C
2000-2001
31.150
13,300/15,200
TOATL MASS kg
59,500
YNd1
50
LOAD LOSS
102 KW MAX
55
19 KW
MAX
2 KW MAX
49,500
39,500
21
VECTOR GROUP
YNd1
ONAN
MVA RATING
MAKE
YEAR OF MFG.
MAIN TANK OIL QUANTITY(KILOLITRES)
TOTAL WEIGHT(METTRIC TONES)
RATED VOLTAGR(KV)
RATED VOLTAGR(KV)
PHASE
MAXIMUM VOLTAGE(KV)
MINIMUM VOLTAGE(KV)
NO. OF TAPS
VECTOR GROUP
HV
LV
6.3
I.M.P.L
2001
3.315
12.65T
ON
33
11
3
34.05
29.7
7
Dyn11
21
INSTRUMENT TRANSFORMER
A transformer that transfers primary current, voltage, or phase values to the
secondary circuit with sufficient accuracy to permit connecting an instrument to the
secondary rather than the primary; used so only low currents or low voltages are
brought to the instrument.
An instrument transformers role is to provide accurate inputs to protection, control
and metering systems including revenue metering. It also measuring a large current
in a d.c. circuit.
The main tasks of instrument transformers are:
To transform currents or voltages from a usually high value to a value easy to
handle for relays and instruments.
To insulate the metering circuit from the primary high voltage system.
To provide possibilities of standardizing the instruments and relays to a few rated
currents and voltages.
CURRENT TRANSFORMER :
In electrical engineering, a current transformer (CT) is used for measurement of
electric currents. When current in a circuit is too high to directly apply to measuring
instruments, a current transformer produces a reduced current accurately
proportional to the current in the circuit, which can be conveniently connected to
measuring and recording instruments.
Circuit Diagram
CURRENT TRANSFORMER
21
SL
NO.
EQUIPMENT/FEEDER
C.T RATIO
SIDE OF
C.T
1
2
3
4
5
6
600-300/1A
600-300/1A
600-300/1A
600-300/1A
800-400/1A
300-150/1A
LINE
LINE
LINE
LINE
LINE
LINE
300-150/1A
LONE SIDE
8
9
10
11
12
13
LINE
LINE
LINE
LINE
LINE
LINE
14
15
16
17
18
19
20
11 KV GOPALNAGAR FEEDER
21
11 KV MAMUDPUR FEEDER
22
11 KV BELTA FEEDER
23
11 KV NAHATA FEEDER
400-200/1A
400-200/1A
400-200/1A
400-200/1A
400-200/1A
1000800/1A
1000800/1A
1000800/1A
200-100/1A
200-100/1A
400-200/5A
400-200/1A
400-200/5A
400-200/1A
200100/5+5A
200100/5+5A
200100/5+5A
200100/5+5A
SIDE
SIDE
SIDE
SIDE
SIDE
SIDE
SIDE
SIDE
SIDE
SIDE
SIDE
SIDE
LINE SIDE
LINE SIDE
LINE SIDE
LINE SIDE
LINE SIDE
LINE SIDE
LINE SIDE
LINE SIDE
LINE SIDE
LINE SIDE
21
STANDARD
IS.2705
145
INSULATION LEVELKV/KVP
275/650 KVP
31.5/3SEC
78.8 KAP
300
RATED FREQUENCY
50 Hz
ELEC SPEC
635716
ELEC SPEC
635716
21
YEAR OF MFG.
2001
POTENTIAL TRANSFORMER :
The instrument potential transformer (PT) steps down voltage of a circuit to a low
value that can be effectively and safely used for operation of instruments such as
ammeters, voltmeters, watt meters, and relays used for various protective
purposes.
Potential transformers (P.T.) are instrument transformers. They have a large
number of primary turns and a few numbers of secondary turns. It is used to control
the large value of voltage. The potential transformer works along the same principle
of other transformers. It converts voltages from high to low. It will take the
thousands of volts behind power transmission systems and step the voltage down
to something that meters can handle. These transformers work for single and three
phase systems, and are attached at a point where it is convenient to measure the
voltage.
The magnetic core of a potential transformer usually has a shell-type construction
for better accuracy. It orders to provide
adequate protection to the operator, one
end of the secondary winding is usually
grounded.
Circuit Diagram
POTENTIAL TRANSFORMER
21
CAPACITOR VOLTAGE TRANSFORMER :A capacitor voltage transformer (CVT), or capacitance coupled voltage transformer
(CCVT) is a transformer used in power systems to step down extra high voltage
signals and provide a low voltage signal, for measurement or to operate a
protective relay. In its most basic form the device consists of three parts: two
capacitors across which the transmission line signal is split, an inductive element to
tune the device to the line frequency, and a transformer to isolate and further step
down the voltage for the instrumentation or protective relay. The of the divider to
the line frequency makes the overall division ratio less sensitive to changes in the
burden of the connected metering or protection devices. The device has at least
four terminals: a terminal for connection to the high voltage signal, a ground
terminal, and two secondary terminals which connect to the instrumentation or
protective relay. CVTs are typically single-phase device used for measuring voltages
in excess of one hundred kilovolts where the use of wound primary voltage
transformers would be uneconomical. In practice, capacitor C1 is often constructed
as a stack of smaller capacitors connected in series. This provides a large voltage
drop across C1 and a relatively small voltage drop across C2.
21
The CVT is also useful in communication systems. CVTs in combination
with wave traps are used filtering high frequency communication signals from
power frequency. This forms a carrier communication network throughout the
transmission network.
A CAPACITOR VOLTAGE
TRANSFORMER
STATION-SERVICE TRANSFORMER
Station-service transformer or Earthing transformers are used to create a neutral
point in a three-phase system, which provides possibility for neutral earthing. The
earthing can be through an arc-suppression reactor, a neutral earthing reactor or
resistor or directly in these earth transformers. Earthing transformers are usually oil
immersed and may be installed outdoor. In cases where a separate reactor is
connected between the earth transformer neutral and earth, the reactor and the
transformer can be incorporated in the same tank. Neutral earthing transformers
are normally provided in 3-phase system, which is without neutral and earth fault
protection. Neutral earthing transformer is having zig-zag (interstar) winding to
achieve the required zero phase impedance. In addition an auxiliary winding can
also be provided to meet the requirement of auxiliary power supply in these
earthing transformers. ONAN /ONAF cooling with conventional pressed steel
radiators. The range includes up to 33 KV systems and as per the site requirements.
21
In this Bongaon132/33/11 kv Sub-Station two nos. of Earthing transformers or
station service transformer are used( 100 KVA). This transformer is simply a well
designed step down transformer. The stepped down voltage is measure with a low
range A.C. voltage. It orders to provide adequate protection to the operator one end
of the secondary winding is usually grounded.
KVA
100
VOLTAGE
H.V.
33000
V
AT
NO LOAD
L.V.
AMPERES
H.V.
0.415 V
1.75A
L.
139.12
A
V.
PHASE
H.V.
L.
FREQUENCY -- 50 Hz
V.
DIAGRAM DRG NO.
Pt-242
Vector group
ZNYN 11
B. CIRCUIT
BREAKER
A circuit breaker is
defined as a mechanical
device capable of
making, carrying and
breaking currents under
normal circuit conditions
and also making, carrying for a specific time and breaking currents under specific
abnormal circuit conditions such as those of short circuit.
YEAR OF
MANUFACTURE
200
21
discontinue electrical flow. Unlike a fuse, which operates once and then has to be
replaced, a circuit breaker can be reset (either manually or automatically) to resume
normal operation. Circuit breakers are made in varying sizes, from small devices
that protect an individual household appliance up to large switchgear designed to
protect high voltage circuits feeding an entire city.
Miniature low-voltage circuit breakers use air alone to extinguish the arc.
Types Of Circuit Breaker :
In larger ratings, oil circuit breakers rely upon vaporization of some of the oil to blast
a jet of oil through the arc.
Gas (usually sulpher hexafluoride) circuit breakers sometimes stretch the arc using
a magnetic field, and then rely upon the strength of the sulpher hexafluoride (SF 6)
to quench the stretched arc.
Vacuum circuit breakers have minimal arcing (as there is nothing to ionize other
than the contact material), so the arc quenches when it is stretched a very small
amount (<23 mm). Vacuum circuit breakers are frequently used in modern
medium-voltage switchgear to 35,000 volts
Air circuit breakers may use compressed air to blow out the arc, or alternatively, the
contacts are rapidly swung into a small sealed chamber, the escaping of the
displaced air thus blowing out the arc.Circuit breakers are usually able to terminate
all current very quickly: typically the arc is extinguished between 30 ms and 150 ms
after the mechanism has been tripped, depending upon age and construction of the
device.
In this Bongaon 132/33/11 kv sub-station two types of circuit breaker are
used. SF6 circuit breaker and vacuum circuit breaker. SF6 breaker are use in 132 kv
sides and vacuum breaker are used in 33 kv sides and SF6 breakers.
21
CONSTRUCTION :
It consists of fixed and moving contacts
enclosed in a chamber (called arc interruption
chamber) containing SF6 gas. This chamber is
connected to SF6 gas reservoir. When the
contacts of breaker are opened, the value
mechanism permits a high pressure SF6 gas
from the reservoir to flow towards the arc
interruption chamber. The fixed contact is
hollow cylindrical current carrying contact
fitted with an arc horn. The moving contact is
also a hollow cylinder with rectangular holes
in the sides. To permit the SF6 gas to let out
through these holes after flowing along and
across the arc. The tips of fixed contact,
moving contact and arching horn are coated
with copper-tungsten are resistance material. Since SF 6 gas is costly, it is
reconditioned and reclaimed by suitable auxiliary system after each operation of the
breaker.
Advantages :
i) Due to the superior are quenching properties of SF 6. Such circuit breakers have
very short arching time. ii)Since the dielectric strength of SF 6 gas is 2 to 3 times
that the air, such breakers can interrupt much larger currents. The closed gas
enclosure keeps the interior dry so that there is no moisture problem and there is no
risk of fire in such breakers because SF 6 gas is non-inflammable. iii)There are no
carbon deposits so that tracking and insulation problems are eliminated.
Disadvantage :
i)SF6 breakers are costly due to high cost of SF 6.Since SF6 gas has to be
reconditioned after every operation of the breaker , additional equipment is required
for this purpose. ii)SF6 is to some extent suffocating. In case of leakage in the
breaker tank, this gas, being heavier than air settles in the surroundings and may
lead to suffocation of the operating personnel.
30 - SF6P - 25 A
RATED FREQUENCY
50 Hz
21
RATED VOLTAGE
33 KV
RATED NORMAL
CURRENT
1250 A
1.5
750 Kg
5 Kg / CM^2 - G (AT 20 * C)
4 Kg / CM^2 - G (AT 20 * C)
MOTOR VOLTAGE
170 KVp
TOTAL WT.
25 KV , 3
SEC
25KA
GAS WT.
62.5 Kap
230 VAC
AUX. CURRENT
80 KV (R.M.S.)
OPERATING MECHANISM
OPENIN
G
CLOSIN
G
HYDRAULIC PRESSURE
HYDRAULIC PRESSURE
21
2 COMMON FOR 3
POLES
220 VOLTS
PRESURE(QUINCHING)(KG/CM2)
PRESSURE(OPERATING)
(KG/CM2)
TESTING
TEMP.
20*C
NORMAL
NORMAL
ALARM
LOCK
OUT
7.5
bar
6.7ba
r
6.5ba
r
ALARM
LOCK
OUT
Advantages :
High breakdown strength for short gaps.
Half-cycle interruption of power currents.
Small
and
compact
size
of
the
interrupting unit and mechanism.
Disadvantage :
Seals ware not capable of withstanding
the stresses of high short-circuit currents.
340 bar
272 + 3 bar
>353&<273 bar
21
Electrode material gave out large amounts of gases at large and vacuum was
destroyed.
Current dropping resulted in severe surge voltage. At times the surfaces of
the contacts produced strong welds in vacuum with normal contact pressure
at normal current.
PVN 36
OPERATION SEQENCY
RATED NORMAL
1250 A
CURRENT
SYM BREAKING CAPACITY
SHORT TIME CURRIENT
DURATION
MAKING CAPACITY
P.F WITHSTAND
IMPULSE
SHUNT TRIP COIL
SPRING REL COIL
TOTAL WIGHT
SPEC
RATED FREQUENCY
50 Hz
21
Management information system of monitoring of project implementation, system
hazards, power station status, equipment failure and rectification report etc...
PLCC COMMUNICATION
Operating principle:
In power line carrier communication, the carrier signal is transmitted through
r and b phase. This Bongaon 132/33/11 kv sub-station the carrier transmitted to the
b phase. The carrier frequency used in this communication. Range from 50 kHz to
500 kHz. The carrier signal is modulated by speech signal and sent over power line.
In this communication system amplitude modulation is not use due to its broad
bandwidth requirements. The carrier signal used for the communication is not
entering in power equipment in the power station. For this purpose a line trap and
wave trap which is nothing but a inductance produce negligible impedance to RF
carrier power frequency coupling capacitor is also connected with parallel with line
trap, that it can be pass high frequency to flow through P.L.C.C.
VARIOUS COMPONENTS:
LINE TRAP OR WAVE TRAP :
As discussed earlier the function of a line trap is to
present high blocking impedance for the carrier
frequency, while introducing negligible impedance at the
21
power frequency. Web traps fall into two main categorise, Turned and
unturned. The tuned type of line trap is essentially a parallel l-c network with
variations in the tuning circuit.
This sub-station(Bongaon 132/22/11 kv) here four wave trap are used. Two
wave traps are connected to the incoming line KRISHNAGAR and others two
wave trap are connected another incoming line JEERAT.
Coupling capacitor:
The function of the coupling capacitors is to present a high blocking
impudence for the power frequency and low negligible impendence at the
carrier frequency.
PROTECTIVE DEVICES:
A three elements protective device is used as outdoor equipment to
protect the communication system from dangerous over voltages. It usually
consists ofI.
ORAINAGE COIL.
II.
LIGHTNING ARRESTER.
III.
EARTHING SWITCHES.
CO-AXIAL CABLE:
The H.F. cable shall have a dielectric strength about 2 KW against
ground. Cables are partly of single-centre-conductor type; the wire serving for
carrier energy transmission and the cable heat as return path.
CARRIER SET:
Its basic version the signal channel multipurpose set (ETBA) is fully equipped for
duplex transmission of a speech channel, with two and four wire inputs and outputs,
an AF hybrid and the input and the relay output for the associated calling and
dialing signals.
Current power line carrier communication devices use old
technologies and are slow and simple. It can be seen that for reliable performance
in a hostile communication environment, a PLCC system must use frequencyhopping communication technology to avoid superimposed charging noise, and
efficient error correction method to errors encountered. The method used for
coupling signal to the power line must be able to operate in a number of
21
unpredictable channel impedance. Lastly, the modulation technique of choice is
frequency shift being reliable in an environment of unpredictable phase shift.
CIRCUIT
DIAGRAM OF
BONGAON
SUB STATIONS. PLCC CONNECTION(CIRCUIT TO CIRCUIT)
D. LIGHTNING ARRESTERS
A lightning arrester is a device used on electrical power systems to protect
the insulation on the system from the damaging effect of lightning. The typical
lightning arrester also known as surge arrester has a high voltage terminal and a
ground terminal. When a lightning surge or switching surge travels down the power
system to the arrester, the current from the surge is diverted around the protected
insulation in most cases to earth.
Lightning arresters are protective devices for limiting surge voltages due to
lightning strikes or equipment faults or other events, to prevent damage to
equipment and disruption of service. Lightning arresters are installed on many
different pieces of equipments such as power poles and towers, power transformers,
circuit breakers, bus structures, and steel superstructures in substations.
21
LIGHTENING ARRESTER
ACTIONS OF A LIGHTNING ARRESTER: Under normal operation, the lightning arrester is off the line i.e. it conducts
no current to earth or the gap is non-conducting.
On the occurrence of overvoltage, the air insulation across the gap breaks
down and an arc is formed, providing a low resistance path for the surge to
the ground. In this way, the excess charge on the line due to the surge is
harmlessly conducted through the arrester to the ground instead of being
sent back over the line.
ZLAX2KC
YEAR OF MFG.
2000
SR .NO
10297
RATED VOLTAGE
120 KV
SYSTEM VOLTAGE
132 KV
MCOV
102
10 KAP
LD CLASS
21
PR.RELIF CURRENT
40 KA
APPR. WEIGHT
12O kg
ZLAX2KC
YEAR OF MFG.
2000
SR .NO
10446
RATED VOLTAGE
42KV
SYSTEM VOLTAGE
33 KV
MCOV
36 KV
10 KAP
LD CLASS
PR.RELIF CURRENT
40 KA
APPR. WEIGHT
40 kg
21
1. FLOAT CHARGING METHOD :
In this method all the cells are charged
together. The auto/manual selector switch is set to auto i.e.. the voltage and
current are selected automatically.
2.
Bongaon 132/33/11
Charger:-
KV
Sub-Stations
Battery
Bank
&
Battery
I visited BONGAON 132/33/11 kv sub-station and here a battery bank. Battery bank
is Heart of the sub-station. Here 15 nos. of cells each are 2v total 15*2=30v
battery are employed for the 11 kv control, protection and indication. The capacity
of this Battery Bank is 75 AH and this type is YKP-7.
Another side 24 nos. of cell each are 2 V total 24*2=48v Battery Bank are
used for Power Line Carrier Communication (P.L.C.C) equipments. This Battery Bank
capacity 100 AH and the type YKP-9.
Other side 110 nos. of cell each 2v having total 110*2=220 v. it is used for
132/33 kv system control, protection, indication and annunciation. Capacity of this
Battery Bank 200AH and type is YKP-17.All cells specific gravity are from 1200 to
1180.
220V DC supply has been effected through Battery. The caldyne
battery charger is provide with separate Float and Boost charger. Normally float
charger is parallel with battery will eater total D.C load of the system. If battery is
drained for a considerable time. It is advisable to change the battery on boost from
Battery charger. Incoming D.C has been brought to D.C distributer main D. C is
distributed to different locations. From D.C distributer main D.C has been
terminated at terminals of Bus- Coupler panel(control switch) from terminals
through fuse, bus wire has been formed to feed control and annunciation sets.
21
PbO2 + Pb + 2H2SO4
2PbSO4 + H2O
21
AC INPUT
SUPPLY
OUT PUT
FLOAT
BATTERY
BANK
242
VOLTS
25
AMPS.
D.C
CONTINOUS
480
mA
TRICKLE
CHARGING
CURRRENT
110 NOS. LEAD ACID CELL OF
200 AH. CAPACITY
OUTPUT
BOOST
MAX.OPERATI
NG TEMP.
TYPE
SL. NO
50*C
YEAR
2001
FCB
677/8
AC INPUT
SUPPLY
OUT PUT
FLOAT
BATTERY
BANK
OUTPUT
BOOST
36 VOLTS 10 AMPS
MAX.OPERATI
NG TEMP.
TYPE
SL. NO
50*C
YEAR
2001
FCB
677/8
21
Fuse FS 2, FS 3
Through TC 1 & TC 2
ii) C.B Remote close operation iii) Indication Circuit iv) D.C Emergency circuit v) Protection Relay Circuit -
Fuse FS4
Fuse FS 8, FS 9
Fuse FS 14, FS 15
Fuse FS 16, FS 17
21
F. CAPACITOR BANK
A capacitor bank is a grouping of several identical capacitors interconnected in
parallel or in series with one another. These groups of capacitors are typically used
to correct or counteract undesirable characteristics, such as power factor lag or
phase
shifts
inherent
in
alternating (AC) electrical power
supplies. Capacitor banks
may
also be used in direct current (DC)
power supplies to increase stored
energy and improve the ripple
current capacity of the power
supply. While the primary power
requirement of the industry and
community is that of reactive
Power.
The
reactive
power
invariably associated with the
active power consumption of
various system components and nature of loads to be controlled and compensated
to a level where the primary object of economic supply of good quality active power
is achieved without over burdening the sources. Depending upon specific effects of
reactive power at a given point in the system, different configurations are advised.
Mainly two types of compensations are involved inductive and capacitive. In the
country with power shortage, inductive compensation is restricted to trunk
transmission system. Mainly in case of minimize the heavy valve load the capacitor
bank is needed.
Capacitor banks control the level of voltage supplied by minimizing voltage
drops and absorbing energy from a line spike. The banks also provide Volt / VAR
Control by switching in capacitor banks to compensate for VAR losses when large
inductive loads occur, such as when air conditioners, furnaces, dryers, and/or
industrial equipment start.
33kv,10MVAR
Capacitor Bank
21
5. There are large amount of harmonics introduced in the system due to
pulsating loads and saturating system components which cause distortion in
wave forms detrimental to certain consumer equipments.
SERIAL NO.
SR-149
TYPE NO.
09NO V. 30
RATED OUTPUT
13260 KVAR
RATED VOLTAGE
38KV
CONNECTION
3-PHASE
R.FREQUENCY
50 Hz
U.TEMP.CAT
50*C
NO. OF PHASES
THREE
INS LEVEL
70/170 KV
DIELECTRIC
P.P.
IMPREGNANT
N.P.C.B
CAPACITOR BANK
OUT DOOR
DISCHARGE TIME
50V-600
SEC.
TOTAL WEIGHT
(APPROX)
3120 KGS.
CUSTOMER WBSETCL
21
g. BUS BARS.
Introduction:
An aluminum or copper conductor supported by insulators that interconnects the
loads and the sources of electric power in an electric power system. A typical
application is the interconnection of the incoming and outgoing transmission lines
and transformers at an electrical substation. Bus-bars also interconnect the
generator and the main transformers in a power plant. In an industrial plant such as
an aluminum smelter, large bus-bars supply several tens of thousands of amperes
to the electrolytic process. See also Electric power sub-station.
TYPES:
The major types are (1) rigid bus-bars, used at low, medium, and high voltage; (2)
strain bus-bars, used mainly for high voltage; (3) insulated-phase bus-bars, used at
medium voltage; and (4) sulphur hexafluoride (SF6)-insulated bus-bars, used in
medium- and high-voltage systems.
In sub-station there are use ~ 132 KV transfer bus, 132 KV main bus, 33 KV main
bus and 33 KV sub bus, 11 KV main bus and neutral bus.
21
h. INSULATOR.
An insulator, also called a dielectric, is a material that resists the flow of electric
charge. In insulating materials valence electrons are tightly bonded to their atoms.
These materials are used in electrical equipment as insulators or insulation. Their
function is to support or separate electrical conductors without allowing current
through themselves. The term also refers to insulating supports that attach electric
power transmission wires to utility poles or pylons.
Insulator
21
Some materials such as glass, paper or Teflon are very good electrical
insulators. Even though they may have lower bulk resistivity, a much larger class of
materials are still "good enough" to insulate electrical wiring and cables. Examples
include rubber-like polymers and most plastics. Such materials can serve as
practical and safe insulators for low to moderate voltages (hundreds, or even
thousands, of volts).
I. ISOLATER.
In electrical engineering, a dis connector or isolator switch is used to make sure that
an electrical circuit can be completely de-energised for service or maintenance.
Such switches are often found in electrical distribution and industrial applications
where machinery must have its source of driving power removed for adjustment or
repair. High-voltage isolation switches are used in electrical substations to allow
isolation of apparatus such as circuit breakers and transformers and transmission
lines, for maintenance. Often the isolation switch is not intended for normal control
of the circuit and is only used for isolation.
In some designs the isolator switch has the additional ability to earth the isolated
circuit thereby providing additional safety. Such an arrangement would apply to
circuits which inter-connect power distribution systems where both end of the circuit
need to be isolated. An isolator is an off-load device intended to be opened only
after current has been interrupted by some other control device. Safety regulations
of the utility must prevent any attempt to open the dis connector while it supplies a
circuit.
21
TYPE :
RATED VOLTAGE:
SYSTEM FREQUENCY:
50 HZ
RATED CURRENT:
PHASE
RATED S.T.C
WEIGHT OF ISOLATOR:
170 KVp
195 KVp
170 KVp
195 KVp
270.5 kg
(APPROX
)
21
K.AIR CONDITIONER
It is used in control room to protect the equipments from heat. It controls the
desirables air temperature of substation control room which leads to temperature
control of the equipment also.
L. OPERATING COMPUTER
There are two computers in that substation, one in control room other in office
room. They are used to store various data of sub-station like load voltage
fluctuations, monthly data, power consumption, load curve data etc.
21
PROTECTIVE RELAY
Introduction:
A protective relay is a device that detects the fault and initiates the operation
of the circuit breaker to isolate the defective element from the rest of the system.
21
increases more than the preselected value, then this relay provides an alarm.
Winding Temperature Trip :
21
Low Oil Alarm :
transformer decreases below a certain level then this relay provides an alarm.
Differential Relay :
This
relay s
functions
Design
and
theory of these protective devices is an important part of the education of an
electrical engineer who specializes in power systems. Today these devices are
nearly entirely replaced with microprocessor-based digital protective relays
(numerical relays) that emulate their electromechanical ancestors with great
precision and convenience in application. By combining several functions in one
case, numerical relays also save capital cost and maintenance cost over
electromechanical relays. However, due to their very long life span, tens of
thousands of these silent sentinels are still protecting transmission lines and
electrical apparatus all over the world.
There are many types of relay-
21
AUXIALIARY, NUMERICAL AND PROTECTIVE RELAYS
2
10.0
5
4.3
10
3.0
20
2.2
8.5
3.52
2.45
1.81
CTUM 15ZG001A
N0130213130132019
Vx 24-250V
USE Rext 2700 FOR 220-250 V ONLY
Features of REL relay:Basic protection functionally of this relay is line distance, which comprises:
a) Simultaneous measurement of phase to phase and phase to earth impedance for
ease type of fault and ease distance
zone.
b) Five Zone of operation- Z1,Z2 &Z3 are for three Zones protection.Z4 for operation
Soft Z5 is for reverse direction.
Scheme communication logic with current reversal and weak and in feed logic.
c) Power swing Detection.
Additional protection functionality such as:
i) Phase over current, residual current and voltage functions.
ii) Breaker failure protection.
iii) Fuse failure and current transformer circuit supervision.
iv) Single or multi pole tripping.
21
Through many functions can be used in the relay, have only Distance protection
function has been used with:
i) Fuse Failure supervision.
ii) Loss of voltage supervision.
iii) Power swing Detector.
iv) Switch auto fault protection (SOTF)
v) Broken conductor protection.
No other back up protection is used as separate O/C & E/F protection have been
provided.
Any disturbance will be recorded and maximum no. of recording is 10. New
disturbance will be recorded automatically
erasing the first one .Any disturbance record can be called from memory and
different information can be viewed.
21
SL
.N
O
RELAY
LOCATION OF RELAY
PROTECTION
2TJM10X3,IDMT
11 KV FEEDER PANELS
2TJM12,67A &
2TJM12,67C
OVER
CURRENT
2TJM12,67N
EARTH FAULT
REL 511
DISTANCE
2TJM1051A,51B,51
C
BACK UP
OVER
CURRENT
RADSB
RADHD,64REF
2TJMH104 50/51 A
DIFFERENTIAL
RESTRICTED
EARTH FAULT
CTUM15,50N
SENSITIVE E/F
10
RXIG22,50
SYSTEM
EARTH FAULT
11
RXFK2H
UNDER
FREQUENCY
OVER
CURRENT
21
REALY
FLAG
30A
LOCATION OF RELAY
30B
IN ALL PANELS
30C
IN ALL PANELS
30D
IN ALL PANELS
30E
IN ALL PANELS
30F
IN ALL PANELS
74B
86L
IN ALL PANELS
95/86L
IN ALL PANELS
10
80A
IN ALL PANELS
Supervise healthiness of 86
relay
Protection D.C failed
11
195
IN ALL PANELS
TC1 unhealthy
12
295
IN ALL PANELS
TC2 unhealthy
13
74A
TR.PANELS(132 KV)
14
74B
IN ALL PANELS
Buchhloz Alram
15
74C
IN ALL PANELS
16
74D
IN ALL PANELS
17
74E
IN ALL PANELS
18
74F
IN ALL PANELS
19
74G
IN ALL PANELS
20
74H
IN ALL PANELS
21
74J
IN ALL PANELS
MOG alarm
22
74L
IN ALL PANELS
23
74M
IN ALL PANELS
24
74A
25
74C
26
74D
27
74E
28
74F
29
74G
IN ALL PANELS
MEANING
Buchhloz trip
21
OPERATION GUIDE
Switching operation is a transmission sub-station is done is a very cautions way
as any mal-operation may cause power interruption of a very large area. Operation
is normally of two types. They are as following:
PRE-ARRANGED SHUTDOWN :
It means operation of various switching equipment for a pre-decided
maintenance, inspection or testing program for which a clearance from STATE
LOAD DISPATCH CENTER (SLDC) is required before taking the shut-down.
SLDC gives clearance of all pre-arranged and emergency shut down for
generating and transmission substation all over WEST BENGAL. Pre arranged
shut down may be of different types. In BONGAON 132 KV sub-station it may
be characterised into the following sections.
1. Shut down of a 33 KV line bay or equipment bay.
2. 33 KV Bus-section shut down.
3. Shut down of Power Transformer (132/33 ,31.5 MVA transformer 1 and
transformer 2)
4. Shut down of 132 KV line.
5. 132 KV bus section shut down.
EMERGENCY OPERATION :
In any emergency situation like - 1. Tripping of 132 KV /33 KV line, 2.
Tripping of 31.5 MVA transformers.
Switching operations are done in a fast but precise manner,
in order to ensure safe operation at the same time. In emergency situation all these
operations are carried out as per the adviser of SLDC.
A few special point need to be kept in mind
When two 132/33 KV Transformers are running in parallel, both the earthing
transformers should be kept connected to bus with Earthing Tr. Protection
selector switch in Both modes. If the transformers are required to be run
individually with bus section, then the switch should be kept in individual
mode.
In case of failure of feeder to trip on earth fault ,132 KV and 33KV Breakers of
both the transformers will trip. In such case , recording relay indication,
switch off all 33 KV feeders & open the faulty feeder isolator. And then
Energies the transformer one after another and then load the transformer
gradually. Inform SLDC and maintenance wing. In each, the transformer trips
on 64R-LV, both 132 KV and 33 KV side breaker will trip. Do not energies the
transformer and inform Testing wing.
Under frequency relay has been provided in 33 KV Bus-coupler panel for
tripping of all 33KV feeders. When it will be required to keep the total U/F
tripping out , switch off UFS at Bus-coupler panel. If any feeder requires to be
21
undisturbed in U/F tripping, individual switch situated inside each panel
should be kept off. Under frequency tipping will be controlled as per direction
of S.L.D.C.
In case of any tripping relays of transformer panel are to be accepted and the
33 KV feeder tripping as per load rejection scheme, may be charged or remain
unchanged depending on the load condition of the other transformers. The
incident has to be informed immediately to the engineer-in-charge , SLDC ,
control testing dept. and should not be charged without permission of engineerin-charge , SLDC and control testing department (if required).
7. In case of 132 KV line tripping the relays and facia of 132 KV line panel and the
33 KV feeder tripped in load rejection scheme are to be accepted and to be
informed in load rejection scheme may be switched on depending on the load
condition of the order line circuit. After taking permission from SLDC the line
may be charged by the sending end transmission sub-station and consequently
by BONGAON (receiving and sub-station) and the same to be informed
immediately to engineer-in-charge as advisor. If the line does not hold the same
also to be informed to the engineer-in-charge immediately.
21
21
PROTECTION
LOAD REJECTION SCHEME :
33 KV load rejection schemes at BONGAON are done in two
following ways :
Incoming Trip :
For BONGAON 132/33 KV sub-station there are two incoming lines.
They are a.
JEERAT, b. KRISHNAGAR. If any of the incoming line be tripped then
the whole load has to be carried out by the remaining incoming line. If the current
through that line exceeds 375 A then some selected feeders of 33 KV side will be
tripped. In incoming line CR panel there is an auxiliary relay. By this relay dc voltage
appears across the tripping circuit of the selected 33 KV feeders. As a result those
33 KV feeder gets tripped and total load of the sub-station is reduced to be less
than 375 A or at a lower value as far as possible.
Transformer Trip :
In case of transformer trip , if any of the transformer be tripped then
all the selected feeders of 33 KV side are tripped , this tripping does not depend
upon the amount of current carried by other transformers. By auxiliary contact of
trip relay of the faulty transformer tripping of the feeders of 33 KV side occurs.
21
DC FAIL PROTECTION :
Almost all the tripping and closing circuits are energized by DC
voltage. So supervision of that DC system ensures healthiness of the tripping and
closing circuits. An AC voltage is used for the relay auxiliary contacts and the
system DC is used for the relay coil. When the DC supply fails, the relay coil gets
disenergized and the auxiliary contacts are closed to give supply to DC fail bell.
21
Annunciation
Distance
Protection
O/C
&
Protection
Action to be taken
Accept alarm. Normalize the discrepancy of control switch.
Observe the display window. Distance summary will be
automatically scrolled. Two latest disturbances (disturb
summary 1,which is the latest and Disturb summary 2,
Which is the second latest and disturb summary 3, which is
the third latest) are presented with
#Date and Time
# Selected indication
#Pre fault and post fault values,
#Nature of fault
Record all information and press C button to put the window
in idle mode. Rest 86 relay by pressing PB/86L. Yellow and
Red LED's of REL 511 will also reset. Reset all other relays, if
any. Reset annunciation. Contact SLDC. Getting their
clearance close the breaker. IF it trips again, repeat the
above and take action as per instruction of SLDC.
21
CB Loss of SF6
warning
CB Loss of N2 Accept alarm. Check whether 30D relays has operated. After
warning
some time reset the relay ,if the relay not reset check
hydraulic oil pressure .If oil pressure increase above 350
bar, divert the feeder through bus-coupler. Inform
Maintenance wing.
C.B
/motor Accept alarm. Check whether 30 E,F relay operated. An
O/L/MCB
attempt may be made to reset MCB/over load push and to
Trip
run the motor. If MCB again trip or O/L, operates, do not run
the motor again and inform maintenance wing.
Distance
protection
fuse fail
Back
Protection
MCB trip
10
Protection
supply
fail
11
Distance
protection
Relay trouble
12
TC1/TC2
unhealthy
13
14
TTS
wrong
15
Power
Block
21
16
17
operated
Distance
protection
Lose of voltage
annunciation.
Accept alarm. Check all the fuse in PT circuit FS 21, FS
22AND FS 23. Reset annunciation and display.
Broken
Conductor
protection
operated
Annunciatio
n
Action to be taken
Distance
protection
Operated
H.V
O/C Accept alarm. Note relay indications and annunciation. Check
Protection
up. Whether it has tripped on over load. It is so, energies and
operated
load the transformer .If tripping is due to fault, Inform Testing
wing & SLDC.
HV-CB
SF6
/OIL/N2 Pr.
Low
General
Lockout
4
CB /oil Presser
Low
warning
closing
lock
out
REF Protection
Trip
21
CB Loss of SF6 Accept alarm. Check whether SF6 pressure has fallen below 6.7
warning
bar. If it is so, divert the feeder through bus-coupler. Inform
Maintenance wing.
CB Loss of N2 Accept alarm. Check whether 30D relays has operated. After
warning
some time reset the relay, if the relay not reset check hydraulic
oil pressure .If oil pressure increase above 350 bar, divert the
feeder through bus-coupler. Inform Maintenance wing.
C.B
/motor Accept alarm. Check whether 30 E,F relay operated. An attempt
O/L/MCB Trip
may be made to reset MCB/over load push and to run the motor.
If MCB again trip or O/L, operates, do not run the motor again
and inform maintenance wing.
Transformer
Trouble Trip
10
Transformer
Trouble Alarm
11
Protection D.C Accept alarm. Check up Whether 80 A relay has reset. Check the
Supply fail
fuse FS 16 and FS17 and replace. Reset 80 A and annunciation.
12
TC1/TC2
unhealthy
13
14
TTS
position Accept alarm. Check whether i) Feeder is fed through normal
wrong
breaker and TTS is in Transformer position. ii) Feeder is fed
through Bus-Coupler breaker and TTS is in Normal Position.
Inform maintenance wing. iii) Feeder is fed through normal
21
breaker but transfer bus is closed. Change the position of TSS or
isolator and reset alarm.
15
Differential
Relay Loss of
Voltage
Annunciation
Distance
protection
Operated
Action to be taken
21
instruction of SLDC.
CB SF6/Oil Pr.
Low/N2
General Lock out
CB /oil Presser
Low warning
closing lock out
CB Loss of SF6
warning
CB Loss of N2
warning
C.B Motor
O/L/MCB Trip
Distance
protection fuse
fail
21
10
Back of Protection
MCB trip
11
Protection D.C
Supply fail
12
TC1/TC2
Unhealthy
13
Distance
protection Relay
trouble
14
15
PSS Position is
Wrong
16
Power Swing
Block Operated
17
Distance
protection Lose of
voltage
18
Broken Conductor
protection
operated
21
19
Earth fault
protection
Safety
Safety Precautions to be observed during Switching
Operations:Safety precautions are:-
21
with circuit
be opened
conversely
the circuit
CONCLUSION
The Industrial Training at WBSETCL has been a practical experience for all of us from
BONGAON Tr.(O&M) Sub-Division. We have been extremely fortunate to have got a
scope to learn the various intricate details of Power Transmission from the Engineers
and Officers of WBSETCL, Bongaon(132/33/11 kv sub-station). It was a firsthand
21
experience for all of us to see the various transmission methods that are employed
at a transmission sub-station. We got to understand how power from various
generating station is transmitted to a transmission sub-station and the several
processes that are undergone before transmitting the power to a distribution substation. While consuming a power we hardly cares about the fact that is the effort of
a million tireless people that we get to enjoy power at home.
We actually realize that power transmission is not an easy task and that it
comes after a lot of hard work and loss of innumerable energy. We also got to see
transformers and understand its functioning from very close quarters. We saw the
functioning of circuit breakers, isolators and capacitor banks all that we had been
only reading in textbooks. It was an enlightening experience to interact with the
engineers who had help us to enrich our knowledge.
During our visit I got a clear idea on how a sub-station works. I understood
the functions of different electrical equipments like C.B, C.T , C.V.T , P.T , BusBar ,
Lightning Arrester , Isolator , Insulator , Capacitor Bank and got some idea how a
Sub-Station tackles problem like various faults multi functioning of various
equipments , maintenance of different units and got a good exposure of the
SWITCHYARD and its layout which help me to understand Power System analysis ,
its transmission and distribution aspects.
We also learnt about PLCC and the various modes of communication that are
employed in power plants and other sub-stations. In all we had an overall
understanding and knowledge of the functions of a transmission sub-stations. We as
student fell proud to have been associated with the WBSETCL and hope to
strengthen our relationship in the near future.
We sincerely thank all the staff of WBSETCL, BONGAON (132/33/11 k v sub station)
for making our training a truly enriching and enjoyable.